14 NOVEMBRE 2014 | PAGE 1
JULES HOROWITZ REACTOR
14 NOVEMBRE 2014 | PAGE 2
JULES HOROWITZ REACTOR: ORGANISATION FOR THE PREPARATION OF THE COMMISSIONING PHASE AND
NORMAL OPERATIONJ. ESTRADE - G. BIGNAN - JL. FABRE - O. MARCILLE – C. BLANDIN
CEA-DEN-DER-F-13108 Saint-Paul lez Durance
Corresponding author: [email protected]
JHR PROGRAM ORGANIZATION
Experimental Group:
Design and Operation process of experimental devices
JHR CONSORTIUM
JHR EXPERIMENTAL AND OPERATOR SECTION
support for safety analysis and licensing
processsupport for
calculations and physical analysis
JHR Program Leader
User Facility Interface Manager
Operator Group : - Reactor- Hot cells - integration of the experimental devices
Project in charge of JHR building
Prime contractorAREVA
Sub-contractorSub-contractor
Sub-contractor
Sub-contractor
Set-up the JHR section in 2010: efficiency passes by the existence of means shared between the operation and the experimental staffs to create a
unique culture around the JHR
14 NOVEMBRE 2014 | PAGE 4
Use the feed back of experience and the best practice
Code, guide, meeting…
French Research Reactor Group
NPP Tricastin
Opal reactor
2010 : SET-UP of JHR EXPERIMENTAL AND OPERATOR SECTION
4 Main functions :1] the operation of the reactor and the nuclear auxiliaries associated as well as the integration of the experimental devices2] the experiments via the design and the operation of the experimental devices3] a support for calculations and physical analysis4] a support for safety analysis and licensing process
JHR SECTION
The qualities and missions expected from this section are:
1] the human resources management to insure correctly the increase in importance of staff (by leaning in particular on the skills from the teams of othersexperimental reactors for example) and their associated trainings,
2] the implementation of a set of reference documents for ReactorOperation:Safety report, Main rules of Operation, Orders…)
� important task requiring significant means in anticipation of the starting up,
3] the management of the external interfaces with the User Facility Interface Manager,
4] the establishment of the main contracts linked to Reactor Operation: fuels, equipments, subcontractings…
JHR SECTION2010 : SET-UP of JHR EXPERIMENTAL AND OPERATOR SECTION
14 NOVEMBRE 2014 | PAGE 7
- Proposal of staffing and organizational structure,- Elaboration of staff training program,- Elaboration of the licensing documentation,- Elaboration of the operating documentation,- Elaboration of the maintenance, in-service and
periodic test programs,- Design and implementation of the experimental
device,- Elaboration of commissioning test programs.
JHR SECTION: main actionsto prepare the operation
REACTOR MANAGER
Experiment, NDE, hot cells, utilisation Laboratory
Hot cell groupCore and
experiment loadinggroup
Shift experimentoperator
Mechanical ElectricalLaboratory
Electrical group
Shift electricaloperator
Mechanical group
Shift mechanicaloperator
I andC Laboratory
I and C group
Shift reactoroperator
Logistic, maintenance and periodic test Laboratory
Shift manager group
Shift manager
Schedule, operationregistration group
LICENSING and SECURITY
ELABORATION OF A PROJECT OF ORGANISATION FOR THE OPERATOR SECTION
- Review of existing organisation in France and worldwide (OPAL,SAFARI…)
- List of operational phases- Assessment of maintenanceand periodic test program- Optimisation of number of personnal on shift- Training program- previous length of cycle
Neutronic,thermal hydraulic,system andequipment:
specific training sessions
Safety, security, environment, quality, radiation protection
General training session
The training program is adapted for each
staff member
Elaboration of staff training program
Elaboration of the licensing documentation
Proposal of SAR, SAFETY GENERAL RULES
Assessment by advisory group of the regulatory body
JHR in operation
ENTRANCE TOINSTRUCTIONS
DEVIATIONINCIDENTALSITUATION
ACCIDENTAL SITUATION
DBIE SITUATION
BDIE SITUATION
JHR CONTROL ROOM
A document of « entrance to instruction » will allow :- to confirm the expected automatic actions- to verify the parameters of the safety functions - to realize a diagnosis with the aim of anorientation towards the instruction adapted
List of Initiatingevents
Safetystudies
Design of I and C
Elaboration of procedures by
operators
Validation of procedures by using simulator
Training session for the operatorsfor qualification
Elaboration of the operating documentationStrategy of conduct :
ACCIDENTAL(DBIE AND
BDIE)
INCIDENTAL
NORMAL AND DEVIATION
SAFEGUARD SYSTEM
PREVENT AND NORMAL SYSTEM
NORMAL SYSTEM
14 NOVEMBRE 2014 | PAGE 12
NDE benches
MOLFI
pressu
eau
gaz
Vidange eau (retour eau pour trempe) + ligne pressu ? Injection gaz pour la vidange du dispositif Crayon combustible (Φ 9,6) Canal chaud (Φe 25) Zircone dense (Φe 29) Virole chauffante (Φe 33) Zircone poreuse (Φe 53) Canal froid (Φe 75 ) Ecran neutronique (Φe 55) Tube (s) dispo (1 ou 2 tubes) Creuset en zircone dense Niveau eau résiduelle Chaufferette
pressu
eau
gaz
pressu
eau
gaz
pressu
eau
gaz
Vidange eau (retour eau pour trempe) + ligne pressu ? Injection gaz pour la vidange du dispositif Crayon combustible (Φ 9,6) Canal chaud (Φe 25) Zircone dense (Φe 29) Virole chauffante (Φe 33) Zircone poreuse (Φe 53) Canal froid (Φe 75 ) Ecran neutronique (Φe 55) Tube (s) dispo (1 ou 2 tubes) Creuset en zircone dense Niveau eau résiduelle Chaufferette
CALIPSO&
MICALORELEI
ADELINE
MADISON
CARMEN
Commisionning
test device
Materials studies
Fuel studies
Fuel studies
Safety studies
Medical application
Design and implementation of the experimental device
Needs First
designInterface reactor analysis
Safety requierment Tempory safety analysis report
Primecontractor
Realization
Commisioning test program
14 NOVEMBRE 2014 | PAGE 13
Design and implementation of the experimental device
HOT CELLS LABORATORIES
EXPERIMENTAL DEVICE STORAGE
POOL
REACTOR POOLEXPERIMENTAL CUBICLE AREA
REACTOR CRANE
EXPERIMENTAL CUBICLE AREA
INTERFACE ANALYSIS EXPERIMENTAL DEVICE/REACTOR FACILITIES
Elaboration of commissioning test programs
Pre fuel loading
test
Fuel loadand
approachto
criticality
Low power test
Power ascension
and power test
Performance demonstration
tests
. < 300 kWth
2 MWth
50
100 MWth
70
.
First thermal balance
Thermal balance
Development ofspecific
instrumentationsPre qualification of
equipments and I and C
Commissionning test programm