Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/071

2007 Downtime PMOG ReviewJose Chan

Page 2: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/072

Staff

2007 downtime installation staffKathleen Ratcliffe – BC2 Installation ManagerGreg Diaz (with Kathleen’s support)- L3 Installation ManagerMFD Staff – Installation (2 supervisors & 25 techs)Ponciano Rodriguez – Cable Installation ManagerPhil Cutino – Water Integration ManagerPatrick Smith/Tom Graul – Area ManagersJodi Collins/Brian Harris/Liberty Electric - Davis Bacon Contractors

Supporting StaffPaul Emma – LCLS Linac PhysicistRichard F. Boyce – L2 & BC2 Integration EngineerPhil Cutino – L3 & Water Integration EngineerCarl Rago/Tom Borden – Magnet EngineersTim Montagne – Diagnostic EngineerLeif Erikson – Vacuum Engineer

Page 3: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/073

IRR Review Summary

March 16th 2007Committee members

Richard M. BoyceDarren MarshMark ReichanadterStan EcklundScott DeBargerTom Himel

Comments/concerns“low priority” not implemented may reduce maximum achievable energyHardware needs to be tracked to ensure availability (i.e. kicker magnetPre-testing should be high priority to reduce in-field interference (i.e.BC2)Better scope definition the work required for the water system and BSY not clearIntegrated schedule is required to determined if scope of work can meet the downtime constraint

Page 4: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/074

Objective

Linac system for 2007 downtime installations Starts in September 4, 2007 thru December 3, 2007.12 weeks minus 2 weeks for PPS checkoutScheduled power outages

Work planned in three areasL2 – sector 21 to sector 24

Modifying girders 24-3,4,5 & 6

BC2 – last 3 girders of sector 24Modifying girders 24-7, 8 & 9

L3- sectors 25 to 30Modifying girders 25-1,2,3 & 9; 27-6 & 9; 28-5 & 7; 29-4

Page 5: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/075

Objective

L2Sector 24-3: removing a DLWG and installing a new wire scannerSector 24-4: removing a DLWG and installing a new wire scannerSector 24-5: removing a DLWG and installing a new wire scannerSector 24-6: installing correctors from sector 24-7

BC2Sector 24-7, 8 & 9: removing all components and DLWG from sectors 24-7, 8 & 9 to make room for BC2

L3Sector 25-1: removing all NPI components from exit of 25-1b DLWG to upstream of Q25701 and install two DLWG from sector 24; reconfigure waveguides to feed all 4 acceleratorsSector 25-2: removing 25-2d DLWG and installing a toroid and T-Cav. (from sector 29-4d)Connect waveguide from penetration 24-16 penetration (KLY 24-8) to sector 25-2 transverse cavity

Page 6: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/076

Objective

L3 (cont.)Sector 25-3: removing 25-3d DLWG: installing a X-Kicker Magnet and OTR 22 (do not omit this work unless desperate - P.Emma)Sector 25-9: removing all components and install OTR TCAVSector 27-6: removing 27-6d DLWG and install wire scanner from sector 27-9 (do not omit this work unless desperate - P.Emma)Sector 27-9: installing drift tubeSector 28-5: removing 25-5d drift and wire scanner; install DLWG from 28-7d and reconfigure waveguides (installing a drift tube)Sector 28-7: removing 28-7d DLWG and install wire scanner from 28-5d (do not omit this work unless desperate - P.Emma)Sector 29-4: removing 29-4d DLWG and install drift section and movable collimatorWater work: redistribute water to accelerators, magnet water and transverse cavity water

Page 7: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/077

Procurement

MFD (VISUAL)

P3(Primavera)

Design

Mech. Install(Microsoft Project)

AD Planning(Excel)

CF

Integrated(Microsoft Project)

Control

MPS/PPS

Cable Install(Microsoft Project)

Management

Schedules Flow Diagram

Page 8: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/078

Schedule

P3 downtime schedule P3 Installation ScheduleUsing Microsoft Project to track status, we’ll be tracking design and fabrications and kit assemblies for installation Design to Installation ScheduleLCLS 2007 downtime planning schedule Ponciano’s cable installation plan Cable Installation ScheduleMeetings

Weekly meeting: MFD installation manager, area supervisor and integration engineer Wednesdays –detail discussion and planning on specific installation

Weekly meeting: MFD & to discuss parts statusThursdays – MFD & LCLS to go over material list status for installation

Weekly meeting: engineers and designers to discuss design schedule and issuesThursdays – engineers and designers to go over design issues and schedule

Bi-weekly meeting: MFD, engineers and LCLS managementMondays – update status with E-beam system manager

Weekly meeting: integration team (R.M. Boyce)Tuesdays – update status to integration team

Bi-weekly meeting 2007 downtime schedule with AD

Page 9: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/079

    STATUS

  DESCRIPTION DESIGN COMPONENT

BC2 QE DONE RFI

BC2 QM21 DONE RFI

BC2 IMBC 21 DONE RFI

BC2 BX2 DONE FAB in EVERSON TESLA 6/8/07

BC2 CQ DONE RFI

BC2 BPMS21 DONE RFI

BC2 CE DONE RFI

BC2 OTR21 DONE RFI

BC2 CERAMIC GAP DONE RFI

BC2 BL21 (same as BL11) DONE (few optics modifications) Ready to submit to MFD 5/15/07

BC2 QE BPM DONE IN FINAL ASSY

L3 TOROID (IMBC20) DONE RFI

L3 T-CAV DONE (needs update support) RFI-LINAC

L3 WAVEGUIDE DONE MFD

L3 BXKIK Complete by 5/31/07  Submit to MFD by 6/4/07

L3 OTR T-CAV Complete by 6/30/07  Submit to MFD by 7/9/07

L3 WIRE SCANNER DONE RFI-LINAC

L3 MOVABLE COLLIMATOR DONE MFD vacuum Process 5/31/07

L3 DLWG DONE RFI-LINAC

Page 10: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0710

Challenges & Mitigations

2007 downtime installations2007 downtime 10 weeks vs. 2006 downtime 17 weeks

Plan to work two shifts

Reconfiguring 11 Linac girders vs 3 in 2006Schedule work on priority basis (i.e. Install BC2 first)

Longer distance from equipment lowered down to installation areasRefurbishing an electric cart for hardware transport in LINAC

Davis Bacon Linac installations maybe competing with LTU or other installations within SLAC

Manage and schedule Davis Bacon work prior to P.O. let out

Hardware and cable installations concurrent in same areaDaily tailgate meetings to discuss tasks from integrated schedule

Page 11: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0711

Challenges & Mitigations

BC2 designNew articulation and support designs

Performed several iterations and reviews Not enough time or space to test completed installation assembly in the lab.

Plan to test sub-assembly in building 26Bend magnets are substantial larger than BC1 bend magnets

Davis Bacon installation

L3 designDesigns for BXKIK and OTR-TCav in design stage

BXKIK design is near completeHave an agreement with Accelerator department to remove all components from girder 25-9, except scraper (collimator 25985) and QE4 (25901) which we can make use of existing OTR design with few modifications

Page 12: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0712

BC2 Documentation Status

Integration engineer – Richard F. BoyceDesign inputs from: Gordon Bowden, Paul Emma, Joe Frisch, Carl Rago and Jose ChanTwo designers (Steve Score and Ted Osier) currently assigned to this areaDesign more than 90% completeDesign Reviews

FDR Supports 5/3/07 Vacuum 5/10/07

Vacuum Supports 5/24/07System 6/7/07

Page 13: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0713

BC2 Documentation Status

Parts statusRFI

Magnets: LINAC QEs, QMs and CQsDiagnostics: Toroid, SLA BPM and ceramic gap

MFD fabricationVacuum chambersSupportsDiagnostics

ProcurementBX2 magnets from Everson Tesla scheduled to deliver first article on June 8 th

Ion pumps Beam line pneumatic valves

Outstanding QE strip line BPM (MFD fabrication issues with welding the bellows)

Page 14: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0714

BC2 Documentation Status

Page 15: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0715

L3 Documentation Status

Integration Engineers – Phil Cutino and Richard F. BoyceOne designer is currently working on L3Completed PDR on 12/19/2006Preliminary installation drawings being finalizedFDR scheduled for June 28th

Page 16: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0716

L3 Documentation Status

Parts statusRFI

Tranverse cavityPhase cavityMovable collimator (being vacuum processed)Wire scanners

MFD FabricationS-Band WaveguideSupports

ProcurementIon PumpsCeramic chambers

DesignBXKIKOTR T-CavityFinalize installation drawings

Page 17: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0717

Product Assurance & Safety

May require lead shielding around BC2 collimatorUsing existing shielding in sector 29-4 for the movable collimatorHoisting & Rigging bend magnets (3600-4300 lbs) in BC2Hoisting and rigging for other components (>40 lbs) are similar to 2006 installationCompleted seismic calculations for BC2 supports, also a peer reviewedMagnets will be reviewed by electrical safety officer

Page 18: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0718

Product Assurance & Safety

Following safety documents are required prior to installation or operation (Jim Turner will collect and manage all safety approvals and requirements)

Safety Overview ApprovalPenetration permitsWork authorization approval from LCLS and ADEarthquake approvalsBuilding inspection approvalsElectric safety approvalsRP approvalsNon-ionizing approvals

Page 19: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0719

Risks and Recommendations

Risks2007 installation schedule very tight

Design and MFD working with integrated scheduleControl group maybe left with little time for checkout

Scheduled BC2 installation first to give sufficient time for controls to install cables and check out BC2 systemMFD will staff up two shifts, four crews for 2007 LCLS installation

BC2- articulation design is unprovenTest center table and arms before installation

Components may not available on timeSetting critical items based on installation priorities

Design issuesAll designs are checkedAssemblies will be QC’d by mechanical engineers, controls and physicist prior to installation

Page 20: Jose Chan 2007 Downtime PMOG Reviewjqchan@slac.stanford.edu 5/16/07 1 2007 Downtime PMOG Review Jose Chan

Jose Chan

2007 Downtime PMOG Review [email protected]

5/16/0720

Open Items

Waiting for shielding requirement around BC2 collimator from RP, if required then we’ll plan to used existing BC1, TD11, shielding design