JOB ORDER MV. SWERTIA

Embed Size (px)

Citation preview

  • 8/9/2019 JOB ORDER MV. SWERTIA

    1/15

    JOB ORDER

    TO MASTER OF MV SWERTIA

    Details of workDate of

    completion

    To be done good maintenance as soon as possible as follows

    1. To be removed rusty parts and paint at all rusty parts

    - H/C, Handrail, Oxy & Acetylene pipe lineat outside, on deck and mooring equipments.

    - If you find out rusty parts, please remove & paint there to maintain good condition.

    2. Liferaft & Rescue boat davit

    - To be painted S.W.L. on liferaft & rescue boat davit by distinctive color(red or yellow color)

    - To be removed rusty parts and paint.

    - To be supplied grease at moving parts.

    - To be replaced damaged & corroded pulley device.

    3. To be repaired & connected between wire and damper for fire damper on funnel and then

    tested damper.

    4. To be repaired all bilge valve for void space to smoothly operate them.

    5. To be repaired ram cylinder because of leakage oil (2 sets).

    6. To be connected between self ignited lighting and lifebuoy by rope at B-deck (P & S side)

    7. To be fitted plug at drain hole of air-vent coaming.

    8. To be used proper garbage can in accordance with garbage management plan.

    9. To be made newly container of new waste rag by making steel or removed using container.

    10. To be cleaned & renewed dirty & poor conditions IMO symbols.

    11. To be greased up gear and grease point of mooring equipments and made & repaired cover

    for gear.

    12. To be welded & repaired locking part of F.W.T.(P) filling line.

    13. To be kept properly fire mens outfit in accurate box in SOPEP store. Now it is keeping in

    another box in SOPEP store.

    14. To be installed quick closing spring for sounding cock of F.W.T.

    15. To be securely lashing Lub. Oil and container in steering gear room.

    16. To be remade & replaced poster of speed table at M/E local side.

    17. To be cleaned & painted dirty parts in E/R.

    18. To be replaced abnormal gauge for M/E & G/E.

    19. To be proper maintained S.W. SERV. PUMP.

    20. To be taped up high pressure fuel & L.O. connection part by using FN tape after cleaning

    connection part.21. To be greased up wire for accommodation ladder/gangway and grease points.

    22. To be repaired air vent for no.4 void (P).

    23. To be repaired or renewed seriously corroded air-vent pipe.

    24. To be covered connecting charger with vinyl to prevent damage by water.

  • 8/9/2019 JOB ORDER MV. SWERTIA

    2/15

    25. To be welded & repaired stair.

    26. To be repaired hanger for nozzle for fore hoe and locker for fire hose box.

    27. Rescue boat.

    - To be made cover for rescue boat engine to prevent water ingress to engine.

    - To be replaced wire.

    - To be securely fixed fire extinguisher for rescue boat.

    28. To be replaced plastic poster on door.

    29. To be removed Lub. Oil drums on deck.

    30. To be attached card for liferaft on case of liferaft.

    Remark: If you need store & spare in order to accomplish Job Orders items, please include

    item in periodical supply order with remark.

    [For internal audit of SMS/ISPS]

    1. To be remade out rest hour record.

    - Please make out it according to your contract and STCW regulation.

    - Satand Sunday are crews holiday on your contract and then not exceed 103hours/month

    of overtime hours.

    2. Please accurately file PSC deficiency report.

    3. Please properly file SMS documentation when you receive them

    - 2013 & 2014 SMS control committee.

    - Revision repeal record / after 2012/ 04/ 01.

    - SMS document revision record / after 2007/03/01.

    - Garbage management plan.

    - Cargo gear rope maintenance record & replacement plan.

    - Essential instruction

    4. Please correctly write down and use documentation

    - FFA : record five year service.

    - Recreational facilities and equipment check-list.

    - Food & catering facilities and equipment.

    - Form of TO DOCTOR

    - Maintenance plan(2014 ~2016)

    DATE:20thMAR2014

    ORDERED BY: SEUNG-BOK, PARKAll above work were completed by crew.

    Confirmed by Master /

  • 8/9/2019 JOB ORDER MV. SWERTIA

    3/15

    NO.1

  • 8/9/2019 JOB ORDER MV. SWERTIA

    4/15

    NO.2

  • 8/9/2019 JOB ORDER MV. SWERTIA

    5/15

    NO.3

  • 8/9/2019 JOB ORDER MV. SWERTIA

    6/15

    NO.4

    NO.5

    NO.6

  • 8/9/2019 JOB ORDER MV. SWERTIA

    7/15

    NO.7

    NO. 8

  • 8/9/2019 JOB ORDER MV. SWERTIA

    8/15

    NO.9

    NO.10

  • 8/9/2019 JOB ORDER MV. SWERTIA

    9/15

    NO.11

  • 8/9/2019 JOB ORDER MV. SWERTIA

    10/15

    NO.12 &13

    No.14 &15

    No.16

  • 8/9/2019 JOB ORDER MV. SWERTIA

    11/15

    No.17

  • 8/9/2019 JOB ORDER MV. SWERTIA

    12/15

    No. 18

    No.19

    No.20

  • 8/9/2019 JOB ORDER MV. SWERTIA

    13/15

    No.21

    No. 22

    No.23 & 24

  • 8/9/2019 JOB ORDER MV. SWERTIA

    14/15

    No.25

    No.26

    No.27

  • 8/9/2019 JOB ORDER MV. SWERTIA

    15/15

    No.28 & 29

    No.30