Upload
jhony-nailwal
View
220
Download
0
Embed Size (px)
Citation preview
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 23/92
23
Kanti Bijlee Utpadan Nigam Limited, (formerly known as Vaishali Power
Generating Company Limited): To take over Muzaffarpur Thermal Power Station
(2*110MW), a subsidiary company named ‘Vaishali Power Generating CompanyLimited (VPGCL)’ was incorporated on September 6, 2006 with NTPC contributing
51% of equity and balance equity was contributed by Bihar State Electricity Board.
This company was formed to renovate the existing unit and run the plant. The
second unit has been successfully re-synchronized on October 17, 2007 after 4 years
of being idle. The company was rechristened as ‘Kanti Bijlee Utpadan Nigam
Limited’ on April 10, 2008.
Bharatiya Rail Bijlee Company Limited (BRBCL): A subsidiary of NTPC under
the name of ‘Bharatiya Rail Bijlee Company Limited’ was incorporated on
November 22, 2007 with 74:26 equity contribution from NTPC and Ministry of
Railways, Govt. of India respectively for setting up of four units of 250 MW each of
coal based power plant at Nabinagar, Bihar. Investment approval of the project was
accorded in January, 2008.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 24/92
24
JOINT VENTURES
S.NoName of the JointVenture Company
Date of Incorporation
Promoter’s EquityHolding as on
31.3.2008Area(s) of Operation
1. PTC India Limited 16.04.99
NTPC 5.28%NHPC 5.28%PFC 5.28%Power GridCorp 5.28%
Trading of power,import/export of powerand purchase of powerfrom identified private
power projects andselling it to identified
SEBs/others.
2.Utility Powertech
Limited (UPL) 23.11.95
NTPC 50%RelianceInfrastructureLtd.
50%
To take up assignmentsof construction,
erection andsupervision in power
sector and other sectorsin India and abroad.
3. NTPC-SAIL Power
Company Pvt. Ltd.08.02.99
NTPC 50%
SAIL 50%
To own and operate acapacity of 564 MW as
captive power plantsfor SAIL’s steel
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 25/92
25
manufacturing facilitieslocated at Durgapur,Rourkela and Bhilai.Another unit of 250
MW is expected to be
commissioned shortly.
4.NTPC-AlstomPower ServicesPrivate Limited
20.09.99NTPC 50%Alstom PowerGeneration AG
50%
To take up Renovation& Modernization
assignments of powerplants both in India and
abroad.
5.NTPC Tamil NaduEnergy Company
Ltd.23.05.03
NTPC 50%Tamil NaduElectricity
Board
50%
To set up a coal-basedpower station of
1000MW capacity, atVallur , using Ennore
port infrastructurefacilities. The
construction work atsite is under progress.
6. Ratnagiri Gas andpower Pvt. Limited
08.07.05 NTPC 28.33%
To take over andoperate gas based
Dabhol Power Projectalongwith LNG
terminal. NTPC’sshareholding is to berevised to 32.88%.
7.Aravali Power
Company PrivateLtd.
21.12.06
NTPC 50%
IndraprasthaPowerGeneration Co.Ltd.
25%
HaryanaPowerGenerationCorp. Ltd.
25%
To set up coal basedpower Project of 1500MW (3x500 MW),inJhajjar District of
Haryana. NTPC wouldalso operate and
maintain the station onManagement Contract
basis for at least 25years.
8. NTPC-SCCL GlobalVenture Pvt. Ltd.
31.07.07
NTPC 50%SingareniCollieriesCompany Ltd.
50%
To jointly undertakethe development and
operation &maintenance of coal
Blocks and integratedcoal based power
projects in India andabroad.
9.Meja Urja Nigam
Private Limited02.04.08
NTPC 50%
Uttar PradeshRajya Vidyut 50%
To set-up a power plantof 1320 MW (2X660
MW) at Meja Tehsil orany other suitable site
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 26/92
26
UtpadanNigam Limited
in Allahabad district inthe state of UP.
10. NTPC BHEL PowerProjects Pvt Ltd. 28.04.08
NTPC 50%Bharat HeavyElectrical Ltd 50%
To carry outEngineering
Procurement andConstruction (EPC)
activities in the powersector and to engage in
manufacturing andsupply of equipment forpower plants and otherinfrastructure projectsin India and Abroad.
11. BF-NTPC EnergySystems Limited 19.06.08
NTPC 49%Bharat ForgeLimited 51%
To establish a facility totake up manufacturing
of castings, forgings,fittings and highpressure piping
required for powerprojects and other
industries, Balance of Plant (BOP) equipment
for the power sector
12.
Nabinagar Power
GeneratingCompany PrivateLimited
09.09.08
NTPC 50%NTPC BiharStateElectricityBoard
50%
To set-up a coal basedpower project havingcapacity of 1980 MW
(3X660 MW) andoperation &
maintenance thereof atNabinagar in district
Aurangabad of State of Bihar.
13. National PowerExchange Limited
11.12.08
NTPC 16.67%NHPC 16.67%PFC 16.66%TCS 50%
To operate a PowerExchange at National
level.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 27/92
27
FUTURE CAPACITY ADDITIONS
NTPC has formulated a long term Corporate Plan upto 2017. In line with the Corporate Plan,
the capacity addition under implementation stage is presented below:
S.No PROJECT STATE FUEL MW1. Kahalgaon-II (3X500) Bihar Coal 5002. Sipat I (3 x 660) Chhattisgarh Coal 19803. Barh I (3 x 660) Bihar Coal 19804. Korba III ( 1 x 500) Chhattisgarh Coal 5005. Farakka III ( 1 x 500) West Bengal Coal 5006. NCTPP II ( 2 x 490) Uttar Pradesh Coal 9807. Simhadri II ( 2 x 500) Andhra Pradesh Coal 1000
8.Indira Gandhi STPP- JV with IPGCL &
HPGCL ( 3 x 500)Haryana Coal 1500
9. Vallur I -JV with TNEB ( 2 x 500) Tamilnadu Coal 1000
10.Nabinagar TPP-JV with Railways (4 x
250) Bihar Coal 1000
11. Bongaigaon(3 x 250) Assam Coal 750
12. Koldam HEPP ( 4 x 200)HimachalPradesh
800
13. Loharinag Pala HEPP ( 4x 150) Uttarakhand 60014. Tapovan Vishnugad HEPP (4 x 130) Uttarakhand 52015. Mauda ( 2 x 500) Maharashta Coal 100016. Barh II (2 X 660) Bihar Coal 132017. Vindhyachal-IV (2X500) Madhya Pradesh Coal 100018. Rihand III(2X500) Uttar Pradesh Coal 1000
Total 17930
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 28/92
28
Business Model of NTPC
Business model of NTP C has been formed based on the strategiesof NTP C. This included:
1. Cost efficiency i.e. providing power at reasonable prices so that they could provide power toall in need.
2. Eco friendly system: Driven by its commitment for sustainable growth of power, NTPC hasevolved a well defined environment management policy and sound environment practices forminimizing environmental impact arising out of setting up of power plants and preserving thenatural ecology.
3. Efficiency improvement includes both improvements in the existing process and throughimprovement in the technology used to increase the productivity of the company. Research &Development Centre is ISO 17025 accredited and provides high end scientific services to allthe company’s stations as well as many outside stations resulting in improving availability andreliability of stations by providing condition assessment, failure analysis, solving andanalyzing specific problems, and helping our stations in increasing the availability and
reliability of their units.4. Technology enhancement i.e. to stay in competition they have to continuously enhancetheir technology.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 29/92
29
SWOT ANALYSIS OF NTPC
STRENGTHS OF NTPC:
The company has kept with itself sufficient liquid funds to meet any kind of
cash requirement.
Efficient working capacity of plants.
Efficient and timely completion of projects.
A minimum risk factor.
Best-integrated project management systems.
Company with an excellent record and high profits.
An early starter-more than 30 years experience in power sector.
Highly motivated and dedicated workers and officers- no industrial relations
problem.
Excellent growth prospects with significant additions, modifications and
replacements.
Employee-friendly personnel policies.
Low project cost of NTPC’s plants.
WEAKNESSES OF NTPC:
Depleting raw materials.
Some of the Plant have become old and need investment in Renovation &
Modernization .
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 30/92
30
OPPORTUNITIES:
Demand and supply gap.
Upcoming hydro and nuclear sector.
Huge opportunity in consultancy services.
THREATS TO NTPC:
Rising prices of raw materials
Huge competition from SEB’s, Reliance Energy, Tata power and other Private
Development. Coming up of other sources of power.
Huge Capital requirement for expansion, diversification, horizontal & vertical
integration and R & M.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 31/92
31
FINANCIAL ANALYSIS
INTRODUCTION
Financial analysis refers to an assessment of the viability, stability and profitability of a
business, sub-business or project. It is performed by professionals who prepare reports using
ratios that make use of information taken from financial statements and other reports. These
reports are usually presented to top management as one of their bases in making business
decisions. Based on these reports, management may:
Continue or discontinue its main operation or part of its business;
Make or purchase certain materials in the manufacture of its product;
Acquire or rent/lease certain machineries and equipments in the production of its
goods;
Issue stocks or negotiate for a bank loan to increase its working capital .
Other decisions that allow management to make an informed selection on various
alternatives in the conduct of its business.
GOAL
Financial analysts often assess the firm's:
1. Profitability - its ability to earn income and sustain growth in both short-term and long-
term. A company's degree of profitability is usually based on the income statement, which
reports on the company's results of operations.
2. Solvency - its ability to pay its obligation to creditors and other third parties in the longterm.
3. Liquidity - its ability to maintain positive cash flow, while satisfying immediate
obligations;
.4. Stability - the firm's ability to remain in business in the long run, without having to sustain
significant losses in the conduct of its business. Assessing a company's stability requires the
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 32/92
32
use of the income statement and the balance sheet, as well as other financial and non-
financial indicators.
Comparing financial ratios are merely one way of conducting financial analysis. Financial
ratios face several theoretical challenges :
They say little about the firm's prospects in an absolute sense. Their insights about
relative performance require a reference point from other time periods or similar firms.
One ratio holds little meaning. As indicators, ratios can be logically interpreted in at least
two ways. One can partially overcome this problem by combining several related ratios to
paint a more comprehensive picture of the firm's performance.
Seasonal factors may prevent year-end values from being representative. A ratio's values
may be distorted as account balances change from the beginning to the end of an
accounting period. Use average values for such accounts whenever possible.
Financial ratios are no more objective than the accounting methods employed. Changes in
accounting policies or choices can yield drastically different ratio values.
They fail to account for exogenous factors like investor behavior that are not based uponeconomic fundamentals of the firm or the general economy.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 33/92
33
FORMAT OF FINANCIAL ANALYSIS AT NTPC :
INR Million
S.No. Particulars YEAR YEAR YEAR
1 Turnover
2 Profit After Tax
3 EBIT
4 Share Capital
5 Reserves & Surplus
6 Net Worth
7 Capital Employed
8 Net Profit Ratio (%)
9
RONW (%) (EAT /
NW)
10
ROCE (%) (EBIT /
CE)
S.No. Particulars
1
Average Turnover for preceding 3 financial years
(million INR)
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 34/92
34
2
Net worth as a percentage of Share Capital as on
last day of preceding financial year (%)
TURNOVER INR Million
S.No. Particulars YEAR YEAR YEAR
1 Sales & Services
2 Total Turnover
SHARE
CAPITAL INR Million
S.No. Particulars YEAR YEAR YEAR
1 Share Capital
RESERVES
& SURPLUS INR Million
S.No. Particulars YEAR YEAR YEAR
1 General Reserve
2 Share Premium
3
P & L Account
Balance
4 Less Misc. Exp.
5
Total Reserves &
Surplus
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 35/92
35
CAPITAL
EMPLOYED INR Million
S.No. Particulars YEAR YEAR YEAR
1 Net Block
2 Net Current Assets
3
Total Capital
Employed
PAT & EBIT INR Million
S.No. Particulars YEAR YEAR YEAR
1 PAT
2
Provision for
Taxation
3 Interest
4 EBIT
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 36/92
36
FORMULA'S:
1) NET WORTH = SHARE CAPITAL + RESERVE & SURPLUS
2) CAPITAL EMPLOYED = NET BLOCK + NET CURRENT ASSET
3) NET PROFIT RATIO = PROFIT AFTER TAX * 100
TURN OVER
4) RONW % = PROFIT AFTER TAX * 100
NET WORTH
5) ROCE % = EARNING BEFORE TAX & INTEREST *100
CAPITAL EMPLOYED
Abbreviation:
RONW = RETURN ON NET WORTH
ROCE = RETURN ON CAPITAL EMPLOYED
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 37/92
37
A financial statement analysis consists of application of analytical tools and techniques to the
data in financial statement in order to derive from these measurement and relationships that
are significant and useful for decision making.
Financial analysis can be used as the preliminary screening tool in selection of stock in
secondary market .It can be used as a forecasting tool of future financial condition and
results. It may be used as a process of evaluation and diagnosis of managerial, operating, or
other problem areas.
The principal tool for the analysis of financial statement is RATIO ANALYSIS.
RATIO ANALYSIS
A ratio gives the mathematical relationship between one variable and another. Ratio analysismainly helps in valuing the firm in quantitative terms.
Financial tools that help in ratio analysis are as follow:
(1) Liquidity Ratio(2) Activity or Efficiency Ratio
(3) Profitability Ratio
(4) Capital Structure of leverage ratio
(5) Investment Analysis ratio
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 38/92
38
COMPARATIVE ANALYSIS BETWEEN NTPC LTD AND TATAPOWER
Financial Analysis of NTPC AND TATA POWER
Ratio Analysis
Liquidity Ratio:
These ratios are calculated to ascertain the short term liquidity of the organization.
(1)Current Ratio:
Current ratio is the ratio of total current assets compared to total current liabilities. Current
ratio of the firm measures its short-term solvency i.e. its ability to meets short term
obligation.
Ideally a company should have > 2:1 current ratio its shows that company has enough funds
to meet its short term obligations. Higher the ratio better it is for company as it enhances the
liquidity position of the company and builds creditors and investor’s trust.
For NTPC:
YEAR 2009 2008 2007
current ratio
(CA/CL)
3.22 3.16 2.56
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 39/92
39
Illustration
As we see from 2009 to 2007 the current ratio of the company is increasing from 2.56 to
3.22. The overall current assets of the company are always greater than current liabilities
which show that firm has always enough funds to meet its day to day obligations.
For TATA POWER:
YEAR 2009 2008 2007
current ratio(CA/CL) 2.19 2.30 2.25
Illustration
For TATA POWER also the ratio is increasing from 2007 to 2008 but it decreases in 2009.
Hence the company doesn’t perform well in 2009 but as the ratio is greater than 2:1 it can
still meet its day today obligations.
(2)Quick Ratio:
It measures the instant debt paying capability or company’s ability to pay unexpected demand
for working capital. This ratio establishes the relationship between quick or liquid current
assets and current liabilities. The higher the ratio, the better is the position of the company.
For NTPC:
YEAR 2009 2008 2007
quick ratio(QA/CL) 3.33 2.80 2.14
Illustration
As we see the increasing trend in the quick ratio from 2.14 to 3.33 in the observed years so
this shows that company keeps enough liquid funds to meet its unexpected cash requirements
or obligations. For NTPC it shows that it can meet need for funds easily.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 40/92
40
For TATA POWER:
YEAR 2009 2008 2007
quick ratio(QA/CL) 1.85 2.07 1.92
Illustration
The quick ratio is always greater than 1:1 in case of TATA POWER so it implies that the
company is trying to increase its liquid funds so that it can meet its need for funds easily.
However, its performance in 2008 is not good as compared to 2007 but as the ratio is greater
than 1:1, it can meet its need for funds.
Solvency Ratios
(1)Debt- equity ratio:
This ratio indicates the relative proportion of debt and equity in financing the assets of a firm.
It reveals the relationship between internal and external sources of funds of a company.
Total long term debts refer to the total outside liabilities i.e. short term and long term loans.
Net worth mean total paid up amount of equity and preference share capital plus the total or
accumulated amount of reserves and surplus.
This ratio plays important role in analyzing the long term solvency of a company. It indicates
the firm’s capacity to pay long term debts and procure additional loans and informs whether
the firm is following the policy of trading on equity.
For NTPC:YEAR 2009 2008 2007
debt equity
ratio(Debt/equity) 0.59 0.50 0.45
Illustration
Debt Equity Ratio is also consistent and there has been not much variation in this ratio over
the years it was 0.45 in year 2007, 0.50 times in year 2008 and 0.59in year 2009. But, it is
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 41/92
41
slowly and steadily rising each financial year. This ratio shows that the long term solvency of
the firm is sound enough it has good capacity to pay its long term debts which make it easy
for it to procure funds from the market easily due to its long term solvency ratio.
Special issues relating to NTPC: Recently Government of India has prescribed the debt
equity ratio for funding the power projects in the ratio of 70:30 excepting for special projects.
This will affect the debt equity structure of the company .
For TATA POWER:
YEAR 2009 2008 2007
debt-equity
ratio(Debt/equity) 0.40 0.67 0.55
Illustration
As observed by the values above we infer that the value of equity is larger than debt in the
year 2009 so the long term solvency of the company is good and has a larger safety of margin
for creditors since owner’s equity is treated as margin of safety by creditors and vice versa.
(2)Interest coverage ratio:
This ratio measures the debt servicing capacity of the firm and particularly when payment of
fixed interest on long term loans is concerned.
The higher the ratio the more is the interest paying capacity of the firm and safety margin
available to long term creditors. The low ratio indicates that the firm is using excessive debt.
The investors can forecast the financial risk by comparing interest coverage ratio withstandard ratio of the industry.
For NTPC:
YEAR 2009 2008 2007
interest coverage
ratio(PBIT/Interest) 6.70 5.79 4.75
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 42/92
42
Illustration
As I see interest coverage ratio has increased from 4.75 times in the year 2007 to 5.79 in the
year 2008. But in the year 2009 it has increased to 6.70. This shows that firm can meet its
long term interest obligations on time as and when they arise. This is utmost important for
interest bearing securities which improves the overall credit rating of the organization.
For TATA POWER:
YEAR 2009 2008 2007
interest coverage
ratio(PBIT/Interest) 6.60 3.82 5.05
Illustration
As I see the ratio in the year 2007 was 5.05 and in 2008 it decrease to 3.82 but in 2009 it again
increase to 6.60. This means its interest payment capacity decreased in 2008 but it increased in
2009.
(3)Proprietary ratio
The objective of computing this ratio is to find out how the proprietors have finance the
assets. This ratio indicated the extent to which the assets of the firm have been financed out
of proprietor’s fund.
For NTPC:
YEAR 2009 2008 2007
proprietary
ratio(shareholder's
fund/ total assets) 66.70% 66.65% 72.79%
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 43/92
43
Illustration
Proprietary ratio for the company indicates that on an average 68.71% of the assets are
purchased out of shareholder’s fund.
For TATA POWER :
YEAR 2009 2008 2007
proprietary
ratio(shareholder's
fund/ total assets) 72% 53.13% 55.97%
Illustration
The general financial position of the company is good as the ratio is above 50%. So the assets
can be within the shareholder’s fund i.e. larger safety of margin as discussed above.
Activity Ratio:
(1)Capital turnover ratio
Capital turnover ratio determines the efficiency with which the capital employed is utilized. It
indicated firm’s ability to generate sales per rupee of capital employed. In general higher the
ratio the more efficient the management and the utilization of capital employed. A too high
ratio may indicate the situation of overtrading. If capital turnover ratio is lower than that
required reasonably and vice a versa.
For NTPC:
YEAR 2009 2008 2007
capital turnover
ratio(net sales/ capital
employed) 0.62 0.58 0.51
Illustration
As power sector is capital intensive sector and returns start after a gap of time so the blocked
capital can’t be used for revenue generation for that particular time period. So here capital
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 44/92
44
turnover ratio is smaller. Here the ratio increases from 2007 to 2009 showing better
management and better utilization of capital employed from 2007 to 2009.
For TATA POWER:
YEAR 2009 2008 2007
capital turnover
ratio(net sales/ capital
employed) 0.88 0.77 0.93
Illustration
This ratio indicates the efficient utilization of capital and liquidity and profitability position
of the business in the year 2009 as compared to 2008.
(2)Fixed assets turnover ratio
This ratio expresses the relationship between fixed assets (less depreciation) and net sales or
cost of goods sold. This ratio measures the efficiency and profit earning capacity of the firm.
The higher the ratio the greater is the intensive utilization of fixed assets. Lower ratio means
under utilization of fixed assets and excessive investment in these assets.
For NTPC:
YEAR 2009 2008 2007
fixed assets turnover
ratio(net sales/ net FA) 1.42 1.27 1.16
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 45/92
45
Illustration
Fixed Assets Turnover indicates that NTPC in the year 2009, for every 1 rupee in fixed assets
generate 1.42 in sales. It shows intensive utilization of fixed assets. Indicates the profit
earning capacity of the company is very high.
For TATA POWER:
YEAR 2009 2008 2007
fixed assets turnover
ratio(net sales/ net
FA) 1.97 1.56 1.51
Illustration
The fixed asset ratio for TATA POWER is increasing in the observed years which show that
there is continuous improvement in the utilization of fixed assets.
(3)Working capital turnover ratio
This ratio establishes relationship between net working capital and net sales. This ratio is
used to assess the efficiency with which the working capital is being used in the business.
A high working capital ratio indicates efficient management of working capital or over
trading i.e. low investment in working capital and more profits. Low working capital turnover
ratio implies under trading i.e. funds are not being utilized efficiently.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 46/92
46
For NTPC:
YEAR 2009 2008 2007
working capital
turnover ratio(net
sales/ net WC) 2.10 2.15 2.79
Illustration
Working Capital Turnover Ratio indicates the proper management of the working capital in
the firm which is required for the day to day operations of the firm. As observed the Ratio
here is in decreasing trend so it is subject of worry for NTPC as the working capital is not
being utilized efficiently or there is minor deteriorations which partially due to recent
adoption of a number of JV companies by NTPC and also take over of smaller power plants.
For TATA POWER:
YEAR 2009 2008 2007
Working capital turnover ratio
(net sales/ net WC) 2.91 2.06 2.74
Illustration
In year 2007 the working capital ratio was 2.74 i.e. the working capital was utilized
efficiently but in 2008 there is decrease in the ratio to 2.06 and further in 2009 the ratio
increase to 2.91. This means in 2008 the company was not able to utilize its funds efficiently
but in 2009 due to proper management of working capital the funds are utilized properly.
Profitability ratios:
(1)Net profit ratio
This ratio measures the relationship between net profit and sales of a firm. Net Profit is the
excess of revenue over expenses during a particular accounting period. The net profit ratio isdetermined by dividing the net profit by sales and expressed as percentage.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 47/92
47
This ratio is the indication of overall profitability and efficiency of the business. A high net
profit ratio would only mean adequate returns to the owners. It also enables a firm to
withstand in cut throat competition when the selling price is declining or cost of production is
rising. A low net profit ratio on the other hand, would only indicate inadequate return to the
owners.
For NTPC:
YEAR 2009 2008 2007
net profit ratio(PAT/
net sales) 20.00% 21.06% 21.80%
Illustration
Net profit of NTPC Ltd is showing a decreasing trend from 2007 to 2009 that shows the
decreasing trend of returns of NTPC Ltd and also the decreasing trend of its ability to survive
in the cut throat competition.
For TATA POWER:
YEAR 2009 2008 2007
net profit ratio(NP/
net sales) 2.4% 6.3% 5.1%
Illustration
As the net profit ratio is decreasing from 2007 to 2009, the company needs to work upon its
operational efficiency.
(2)Operating Profit Ratio
This ratio establishes the relationship between operating profit and net sales. It is also defined
as the ratio of profit before depreciation, interest and tax to total turnover. Operating profit
means the net profit arising from the normal operations and activities of the business without
taking account of extraneous transactions and expenses purely financial nature.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 48/92
48
This ratio indicates the net profitability of the main business i.e. operating efficiency of a
firm. The higher the operating ratio the better would be the operational efficiency of the firm.
A higher operating profit ratio means that a firm has been able not only to increase its sales
but also been able to cut down its operating expenses
For NTPC:
YEAR 2009 2008 2007
operating profit
ratio(operating
profit/net sales) 32.53% 33.03% 31.35%
Illustration:
As the operating profit ratio is increasing from 2007 to 2009 it shows that not only the
operating efficiency of the company is improving but also its sales are also increasing with
the decrease in its operating expenses. But in the year 2009 this ratio is decreasing which
shows that the company needs to work on its operating efficiency so as to improve its sales
and to decrease its operating expenses.
For TATA POWER:
YEAR 2009 2008 2007
operating profit
ratio(operatingprofit/net sales) 15.83% 15.34% 18.42%
Illustration
As this ratio measures the rate of net operating profit to sales and there is decrease from 2007
to 2009 and then increase in 2008. For the profitability and soundness of the company we
have to further analyze the balance sheet and profit and loss account of the company.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 49/92
49
(3)EPS (Earning per Share)
The rate of dividend on shares depends upon the amount of profits earned by the firm.
Whatever profits remains, after meeting all expenses and paying preference share dividend,
belongs to equity shareholders.
This is a popular ratio as it measures the profitability of a firm from owners’ standpoint. The
higher the ratio the greater would be the market price of a company’s shares or vice versa.
For NTPC:
YEAR 2009 2008 2007
Earning per share(EPS) 8.99 8.33 7.06
Illustration
As it is inferred from the observed value above that there is increase in the equity
shareholder’s fund as a result of retained earnings without any change in numbers of
outstanding shares. So the dividend paying capacity of NTPC has increased. Also considering
the gradual improvement of the operation and turnover, the EPS is expected to improve
further.
For TATA POWER:
YEAR 2009 2008 2007
earning pershare(EPS) 38.64 34.02 29.03
Illustration
This ratio helps in evaluating the prevailing market price of share in the light of profit earning
capacity. The more the EPS better is the performance and prospects of the company. This
also implies that share price is higher for investors.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 50/92
50
COMPARISON OF NTPC WITH TATA POWER
Liquidity
The basic objective of working capital is to provide adequate support for the smooth
functioning of the normal business operations of the company. The quantum of investment in
current assets has to be made in such a manner that it not only meets the needs of the
forecasted sales but also provides a built in cushion in form of safety stocks to meet
unforeseen contingencies.
Working Capital at NTPC is always greater than 2 in all 3 years for which data has been
analyzed indicating that NTPC never really face a major problem in meeting its short-
term liabilities, but this is not in case of Tata powers .
Profitability
NTPC AND TATA POWERS follows the Aggressive Approach in which the firm goes for
fewer investments in current assets, thus leaving more amounts of funds for investment
in more profitable ventures. This approach imparts greater PROFITABILITY to the
company. An ideal policy would be the moderate policy, which strikes a balance
between the two approaches.
Solvency
The solvency ratio measures the size of a company's after-tax income, excluding non-cash
depreciation expenses, as compared to the firm's total debt obligations. It provides a
measurement of how likely a company will be to continue meeting its debt obligations.
Debt is low for TATA Power as compared to NTPC. Both the companies can meet the
interest payments obligations easily and more than 50% assets are from shareholder’s funds.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 51/92
51
Activity
Activity ratios are that ratios which measure a firm's ability to convert different accounts
within their balance sheets into cash or sales. Both the companies (NTPC and TATA Power)
are typically trying to turn their production into cash or sales as fast as possible because this
will lead to higher revenues.
Such ratios are frequently used when performing fundamental analysis on different
companies. I observed that the power sector as a whole is more capital intensive sector
therefore capital is blocked in projects whose returns came after a period of time.
(Approximately 5 years).
PROCUREMENT AT NTPC
rocurement is the acquisition of goods and services for the direct benefit or use
of the governments, corporations or individuals generally via, but not limited to,
a contract. A key question in procurement is what to buy, given a limited
budget. Procurement involves a bidding process to purchase a given product or
service. The project is aimed to study and understand the process of tendering used for
procuring different plant equipment packages, from various bidders. Procurement at NTPC is
initiated on the basis of approved indents/requisitions indicating budget and project estimate
provisions. The contract services/materials management services receive the
requisition/indent for the procurement of materials/equipment/services duly approved by the
competent authority and then plan and organize the procurement action. Normally an open
tendering system for procurement is adopted during construction stage of a project. However,
P
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 52/92
52
depending on the circumstances and the requirements, limited tendering or single tendering
system is also adopted in specific cases. Following are three types of tenders:
Types of tenders
Based on the materials classification and Delegation of Powers (DOP) handbook of
NTPC, following three types of tendering is adopted in NTPC:
Fig-6: Types of Tenders
(a) Open Tender:
Procurements of value Rs 15 lakh and above must be done through open tendering, as it
involves a lot of cost and time. Open tender is accessible to all known reliable and proven
sources of particular equipment/ material. For the above purpose, advertisement is given
in two or more newspapers of all India repute in addition to one or more local
TYPES
OF
TENDERS
OPEN
TENDER
LIMITED
TENDER
SINGLE
TENDER
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 53/92
53
newspapers, where the work is to be executed. However, in case of Empanelment, a pre-
qualification process of invitation for bids will take place, only once in every three years,
by advertising in newspapers as stated above. Empanelment is done in case of award of
contract for Environmental Impact Assessment (EIA), Flora-Fauna study etc. The criteria
for pre-qualification will inter-alia consist of past performance, financial soundness,
technical competence, organizational capability etc., but for the items valued less than 15
lakh, the pre-qualification can be done on the basis of data available in trade journals,
manufacturer’s directory or approved vendors list of state government and central
government. For new ventures, methodology of Expression of Interest (EOI) is adopted
and by means of advertisement, new bidders are invited to provide their credentials and
based on it, short listing of appropriate bidders is done.
(b) Limited Tender:
Limited tender is a tender, where instead of sending bid enquiry to all the possible
vendors through newspapers, a limited number of vendors are intimated through post or
fax. But, a limited tender may be invited only for the procurement worth less than Rs. 15
Lacs. In case of a limited tender, minimum of four bidders are invited to quote the prices
for the required equipment/materials/services and these four bidders must be from the
approved list of vendors mentioned in the open tender. However, a limited tender is a
special case and cannot be issued without proper explanation and requirement. In case of
urgency& exceptional cases, items worth more than Rs.15 Lacs may also be procured
though a Limited Tender Enquiry (LTE), with authorization of competent authority and
the reason must be recorded in the indent documents/note sheet. Further, as per the
circular No. 265/2007 the selection of vendors are to be done through a screening
committee before approval by the competent authority.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 54/92
54
(c) Single Tender:
Where procurement is made by contacting only a single source on grounds that the item
to be procured is of a proprietary nature or on account of standardization or on grounds of
urgency of requirement, it will be treated as a single tender. In case of proprietary items, a
certificate to that effect has to be issued by the indenter at appropriate laid down levels in
each case. Orders on basis of single tender will be issued with the approval of General
Manger or any competent authority to which powers are delegated. However, a Single
Tender Enquiry (STE) is to be done only on exceptional cases and is not encouraged by
NTPC.
IMPORTANCE OF PROCUREMENT
Materials constitute a very significant proportion of total cost of finished products in most of
the manufacturing industries. It estimated that near about from 40% to 70% of total
production cost is related to material only. So control over material is very essential for any
organization.
The importance of Procurement may be summarized as follows:-
Availability of materials: There should be a continuous availability of all types of
materials in the factory so that the production may not be held up for want of any
material. Minimum quantity of each material is fixed to permit production to move on
schedule.
No excessive investment in materials : There should be no excessive investment in
stocks. Investment in materials must not tie up funds that could be better used in other
activities. For this purpose, a maximum quantity is assigned to each item of material
above which stock should not be exceeded. So there should be no over stocking of
materials because that would result in loss of
Interest charges
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 55/92
55
Higher godown charges
Deterioration in quality
Losses due to obsolescence
Reasonable price: Materials should be purchased at the reasonable price. Quality is
not to be sacrificed at the cost of lower price. The material purchased should be of
that quality alone which is needed.
The price paid should be the minimum possible otherwise the higher cost of the
finished products would make the products would make the products uncompetitive in
the market.
Minimum wastage: There should be minimum possible wastage of material while
these are being stored in the godowns by storekeeper or used in the factory by the
workers. Wastage should be allowed up to the certain level known as normal level of
wastage and it should not exceed that level.
Risks of spoilage and obsolescence : Material must be avoided from it. For this
purpose a maximum quantity of each material is determined and a proper method of
issue of material is followed. The materials received earlier should be issued earlier.
Information about availability of materials: It should be made continuously
available to the management so that planning of production may be done. The
storekeeper can supply this information because he keeps an up to date record of
every item of stocks under a proper system of material control.
Supply of material at right time: Procurement assures the required need and to
demand or fulfill at the right time from the right place so as to utilize all the resources
and none of them are kept idle.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 56/92
56
Japanese concept : Another common procurement issue is the just in t ime delivery, a
JAPANESE CONCEPT.
Other important : -
1) To stoppage the wastage of materials.
2) To maintain the flow of production.
3) To stoppage the theft of material.
4) To reduce the cost of storage.
5) Wastage during the process of manufacture should be the minimum possible.
VARIOUS PACKAGES AT NTPC
NTPC develops power plants across India and each plant requires huge investments in form
of time and money. For this purpose NTPC divides its work into different packages for each
power plant. Tenders are floated for each package for the purpose of erection of power plant
instead of the whole project being given on turnkey basis to a single bidder. These packagesare distinguished on the following basis:
Corporate Packages
Regional Packages
Site Packages
Details of some of the above packages are given below:
CORPORATE PACKAGES
MECHANICAL PACKAGES
1 Steam Generator with Electrostatic Precipitator
2 Steam Turbine Generator Package
3 Station piping
4 Ventilation System
5 Air conditioning System6 Fire Detection and Protection System
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 57/92
57
7 Ash Handling System Package
8 Coal Handling Plant
9 Pre-Treatment Plant
10 DM Plant & CW Treatment System
11 Condensate Polishing Plant
12 CW System Equipment Package
13 Cooling Towers
14 Make up Water Pipes
ELECTRICAL PACKAGES
1 Power Transformers
2 Outdoor Transformers
3 Generator Busducts & Associated Equipment, MV Busducts
4 MV Switchgears
5 Lt Switchgears And Lt Bus Ducts
6 Electrical Equipment Supply & Erection Package
7 Switchyard Package
C&I PACKAGES
1 Station Control and Instrumentation
2 Instrumentation Cables
CIVIL PACKAGES
1 Site Leveling & Infrastructure Works Package
2 Main Plant & Off Site Civil Works Package
3 Chimney and Chimney Elevator
4 Ash Dyke Package
5 CW and Make Up Water System Civil Work Package
6 Railway Siding and S&T System
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 58/92
58
CONSULTANCY PACKAGE
REGIONAL PACKAGES
1 Ash Water Recirculation System
2 Ht Power Cables
3 1.1 KV Power Cables
4 Control Cables
SITE PACKAGES
SITE PACKAGES ASSOCIATED WITH PLANT
1. Survey
2. Geotechnical Investigation
3. Workshop & Lab Equipment
4. Drinking Water Pipeline To Township
SITE PACKAGES ASSOCIATED WITH TOWNSHIP
1. Township site leveling and land development
2. Construction of Residential Quarters and associated
3. Misc. works
Each package consists of works that has to be completed according to the schedule,
developed at the planning stage of the project. Tenders are floated for award of contracts for
each package through the sale of bidding documents. The last date of receipt of bids is also
mentioned in the advertisements, as well as at the time of sale of bidding documents. The
bidders duly fill the bidding documents according to the specifications laid by NTPC andsubmit their bids before the last date along with Bid Security and Certificate of Compliance
to Important Conditions in separate sealed envelopes.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 59/92
59
PROCESS OF PROCUREMENT
Process of Procurement
CONTRACT PACKAGING
PREPARING A COST ESTIMATE
NOTICE INVITING TENDER
BID OPENING
BID EVALUATION
APPROVAL & AWARD OF
CONTRACT
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 60/92
60
1) CONTRACT PACKAGING
Contract packaging is the first step of procurement for a project. The total project work is
broken into smaller well-defined packages. This is done with the view to optimize the
number of contracts to be handled for the better planning, co-ordination and implementation
of the whole project and at the same time to execute the project at an optimum cost to the
organization. The development of contract package list for a project is done jointly by
Engineering, Contracts, and Corporate Planning and Finance functions of the organization.
The contract package, being extremely vital for a successful project implementation, is
approved by the highest corporate level authority. A feasibility report is also prepared for a
project, which contains all the details of the various equipment systems and services
required.
2) PREPARING A COST ESTIMATE
Cost estimation is the most important financial activity in the process of budgeting and
procurement. Further, Cost Estimate is the basis of Award and correctness & accuracy of the
estimate is of utmost priority and in turn, ensures procurement at lowest possible prices.
Whenever NTPC procures some material, it also specifies how it intends to finance the
package through External Commercial Borrowings (ECB), internal and other sources. The
procurement of the first kind i.e. ECB requires financial clearance from the Finance
(Concurrence) department. For this purpose, cost estimation is done before forwarding the
indent document to the finance department. The methods of cost estimation, which are used
by NTPC, are:
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 61/92
61
(a) Historical cost method:
In this method, the Cost Engineering department at NTPC utilizes the latest cost incurred for
similar kind of project. For example, if the cost estimate has to be prepared for new thermal
power plant, the latest executed thermal power plant rates will be used for estimation. Hence,
the rates so obtained are very near to the actual rates that might be prevalent in the market at
that point of time. But, to smoothen the effect of inflation and various other financial
components in the prices at the time of the execution of that project, an escalation factor is
used. All the prices of the previous projects are multiplied by this factor and a very close
estimation of market rare is thus obtained.
(b) Market Rate Method:
Market rate method is used for the procurement of equipments that are not in very large
numbers and value. In this method, once an indent is prepared, some of the vendors registered
at NTPC or listed in trade journals are sent a request for quoting the prices of particular
equipment. This enquiry is not a tender and the rates provided by the vendors are not a part of
the bid. After the information is received, the rates quoted by various vendors are compared
and the lowest quoted price is taken as base rate for calculations. However, if the difference
in the price quoted by two vendors is reasonably high, an average of the two may be taken as
the base. However, 10% discount is considered in the budgetary offers.
3) NOTICE INVITING TENDER
The next step is to invite various bidders to bid for the required package. The Notice inviting
tender (NIT) is published in various leading national newspapers as per guidelines and
procedures. Copies of NIT are also sent to the bidders who have evinced interest in supplying
similar equipments or services in the past. In case of procurements funded by external
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 62/92
62
funding agencies following international competitive bidding procedures, the NIT is also
published in the Indian trade journal and a copy of NIT is sent to each of the embassies/ high
commissions of members countries of the funding agency. In the NIT, time, date and venue
of bid opening, amount of bid security etc. is mentioned and only a specific part of
Qualifying Requirements (QR) is published. However, the bidding documents stipulate the
complete and detailed QR specific requirements to a particular contract package. Such
qualification criteria include the financial status of a bidder (manufacturer or project
executing agency), technical requirements to be fulfilled etc. NTPC invites sealed bids in two
stages i.e. Stage- I: Techno Commercial Bid and Stage- II: Price Bid or both simultaneously.
For Hydel and wind power projects, bids are invited in separate stages, whereas in case of
thermal power projects, bids are invited simultaneously. All bids must be accompanied by
Bid Security of a particular amount in a separate sealed envelope. Any bid not accompanied
by an acceptable bid security in a separate sealed envelope shall be rejected by NTPC as
being non-responsive and returned to the bidders without being opened.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 63/92
63
4) BID OPENING
Bid opening is the next step in procurement process. Tenders are opened on the due date and
time mentioned in the NIT. If the date mentioned is declared holiday, the next working day
will be considered as the opening date, but the time will remain the same. These sealed bids
are opened by a committee nominated by the tender committee members from the respective
departments at the time indicated in the invitation to tender, in presence of representatives of
the tenderers, who wish to attend and a representative of Finance. When bids are opened, the
names of all present tenderers would be read out for the benefit of the bidders present and
where feasible, the various price schedules from the Grand Summary Price Schedule
(Schedule 5) are read out. Any omission or irregularity such as absence of signature of a
tenderer, absence of earnest money deposit, references etc. may be pointed out on the
document itself and is signed by the nominated bid opening committee.
5) BID EVALUATION
The process of evaluation of bids begins with an examination of the bids in order to
determine:
1. Acceptance of all Qualifying Requirements.
2. Acceptability of bid security furnished by the bidder.
3. Completeness of bid and correctness of signature.
4. Computation of arithmetical errors in the bid price schedules.
5. Stated deviations from the bidding conditions, which might reflect on the substantial
responsiveness of the bid and justify its rejection.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 64/92
64
The detailed evaluation is carried out only for bids, which are substantially responsive. Bid
evaluation considers price and other factors in a transparent manner and in accordance with
the stipulated evaluation criteria stated in bidding documents such as cost compensations for
the deviations from the bidding conditions taken by the bidders, differential price factors for
guaranteed parameters etc. In case of procurement under international competitive bidding
procedures, the bid price is converted into a single currency i.e. in the Indian National Rupees
(INR). If the bidder wishes to pay a combination of amounts in different currencies, it may
quote its price accordingly, but use not more than three foreign currencies. The foreign
currencies in which the bid prices are quoted should be converted into INR by applying SBI
bill selling rate on bid opening date.
Once the lowest evaluated bidder is selected as above the next step is to determine whether
the qualification requirement as stipulated in bidding documents are met and whether the
bidder in question is capable to successfully execute the contract. An affirmative
determination of the above is pre-requisite for award of contract to the bidder. In case the
lowest evaluated bidder does not meet the above requirement, the similar determination is
done for the next lowest bidder. If the bidder also fails, the process is continued, until the
lowest evaluated and qualified bidder is chosen.
6) APPROVAL & AWARD OF CONTRACT
A Tender Committee is formed to decide on the award of contract valuing 2 lacs and above.
The members of Tender Committee at appropriate level shall consist of representatives each
from Indenting, Procurement/Contracts and Finance department. NTPC determines to its
satisfaction whether the Bidder selected as having submitted the lowest evaluated responsive
bid is qualified to satisfactorily perform the contract in terms of the qualifying requirements
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 65/92
65
stipulated in Bid Data Sheet. The determination will take into account the Bidder’s financial,
technical and production capabilities, in particular to its contract, work in hand, future
commitments and current litigation. It will be based upon an examination of the documentary
evidence of the Bidder’s qualifications submitted by the Bidder in Attachment 3 to the bid, as
well as any other information, as NTPC deem necessary and appropriate. An affirmative
determination will be a prerequisite for award of the contract to the Bidder. A negative
determination will result in rejection of the Bidder’s bid, in which event; NTPC will proceed
to the next lowest evaluated bid to make a similar determination of that Bidder’s capabilities
to perform satisfactorily. “The bidder which satisfies all the qualifying requirements and
offers the least price is awarded the contract”.
PROCEDURE FOR INTENDING
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 66/92
66
For the purpose of indenting, material planning is required. It is nothing but classifying the
materials
into various categories to facilitate a speedy and efficient procurement. In this process all the
materials which may be required at any of the NTPC projects or offices are classified in to
five major categories and their procurement is to be done on the basis predefined for them.
1.Stock item (Automatic Recoupement items/AR)
2.Insurance Items (I)
3.Unit Replacement item (UR)
4.Capital Item (P)5.Other non-stock items (Not falling under any of the above category)
6.But since this classification is very vague and unspecific, a further classification is done to
exercise selective control over all Material Management activities. This classification is
known as the ABC analysis.
IDENTIFICATION OF RESPONSIBILITIES:
NTPC being a utility organization with projects located away from the corporate office, has
divided the responsibility of contracts management, both pre-award and post award, between
the corporate office and project site.
A contract management function as an independent specialized techno commercial function
to meet the overall corporate objective in the area of project procurement has been in place
since inception as a department named as “Corporate Contracts” within the organization
structure of NTPC. The ‘Corporate Contracts’ procures plants/ equipment and services for its
projects, which are characterized by adherence to the procurement of external funding
agencies, factoring of long process owner for award of all such contracts including high value
civil works, its monitoring and post award follow up till the delivery of equipment from the
suppliers works till the closure if the contracts. The Corporate Contracts division is the
receipt and installation of the plant and equipment and its execution is the responsibility of
the project site.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 67/92
67
There are a number of other small value contracts with lesser of engineering coordination,
whose pre-award and post-award contracts are handled by the project sites. The principles
and guidelines followed for these site contracts are similar to those applicable for the
Corporate Contracts.
In view of the complexity involved in the construction of thermal generation projects, the
Contracts Management Systems calls for further sharing of responsibilities for specialized
functions such as Engineering, Finance, Cost Engineering, Quality Assurance, and Inspection
at Corporate Center and Erection, Site Finance, Field Quality Assurance etc. as the Project
Site.
CONTENTS OF A BIDDING DOCUMENT
The facilities required, bidding procedures, contract terms and technical, requirements are
prescribed in the bidding documents. The bidding documents include the following sections:
Section I – Invitation for Bids (IFB)
Section II – Instructions to Bidders (ITB)
Section III – Bid Data Sheet (BDS)
Section IV – General Conditions of Contract (GCC)
Section V – Special Conditions of Contract (SCC)
Section VI – Technical Specifications and Drawings (TS)
Section VII – Forms and Procedures (FP)
Documents Comprising the Bid
The bid submitted by the Bidder shall comprise the following documents:
1. Bid Form duly completed and signed by the bidder, together with all Attachments
2. Price Schedules duly completed in all respect by the bidder.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 68/92
68
3. The bid shall also contain necessary details of the Equipment and Mandatory Spares to
be imported from Associate/Collaborator by manufacturer or bidder
Each Bidder shall submit with its bid the following attachments:
(a) Attachment 1: Bid Security
A bid security shall be furnished in a separate sealed envelope. Bids not accompanied by the
requisite bid security in a separate sealed envelope, or bids accompanied by bid security of
inadequate value, shall not be entertained and in such cases, bids shall be returned to the
bidders without being opened.
(b) Attachment 2: Power of Attorney
A power of attorney, duly authorized by a Notary Public, indicating that the person(s) signing
the bid has/have the authority to sign the bid and thus that the bid is binding upon the Bidder
during the full period of its validity.
(c) Attachment 3: Bidder’s Qualifications
The Bidder shall provide satisfactory evidence that he and/or, where applicable, his
collaborator/associate/partner(s) of Joint Venture:
Is a manufacturer, who regularly manufactures equipment of the type specified and/or
undertakes the type of work specified and has adequate technical knowledge and relevant
experience for the works covered in the bidding documents.
Does not anticipate a change in ownership during the proposed period of execution of
work (If such a change is anticipated, the scope and effect thereof shall be defined).
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 69/92
69
Has adequate financial stability and capability to meet the financial obligations pursuant
to the Works covered in the Bidding Documents. (The Bidders should submit five (5)
copies of their profit & loss account and balance sheet for the last five (5) years).
Have adequate design, manufacturing and/or fabrication capability and capacity available
to perform the work within the time period specified.
Has an established project management organization covering the areas related to
engineering of equipment/systems, interface engineering, procurement of equipments and
the necessary field services required for successful construction, testing and
commissioning of all the power plant equipments and systems covered in the scope of
work for the package.
Has established quality assurance systems and organization designed to achieve high
level of equipment/system reliability, during manufacturing and/or fabrication and field
installation activities.
A company formed by the merger of two or more companies or divisions of such
companies engaged in supply and installation of power generation equipments can also
participate provided the constituent companies or divisions before merger individually or
jointly meet the stipulated qualification requirements fully.
(d) Attachment 4: Eligibility and Conformity of the Facilities
Documentary evidence that the facilities offered by the Bidder in its bid or in any alternative
bid, (if permitted) are eligible and conform to the bidding documents. The documentary
evidence of the eligibility of the facilities shall consist of a statement on the country of origin
of the plant and equipment offered, which shall be confirmed by a certificate of origin issued
at the time of shipment.
Attachment 4A: Special Tools and Tackles
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 70/92
70
The bidder shall provide the details regarding Special Maintenance Tools and Tackles. The
cost of these Tools and Tackles shall be included in the Bid Price.
(e) Attachment 5: Subcontractors Proposed by the Bidder
The Bidder shall include in its bid details of all major items of supply or services that it
proposes to purchase or sublet, and shall give details of the name and nationality of the
proposed Subcontractor, including vendors, for each of those items. Bidders are free to list
more than one Subcontractor against each item of the facilities. Quoted rates and prices will
be deemed to apply to whichever Subcontractor is appointed, and no adjustment of the rates
and prices will be permitted.
(f) Attachment 6: Deviations
Deviations, if any, from the terms and conditions of Bidding Documents or Technical
Specifications shall be listed only in Attachment 6 to the bid. The Bidder shall also provide
the additional price, if any, for withdrawal of the deviations. Except for the deviations listed
in Attachment 6, the bid shall be deemed to comply with all the requirement in the bidding
documents and the bidders shall be required to comply with all such requirements of bidding
documents and technical specifications without any extra cost to NTPC irrespective of any
mention to the contrary, anywhere else in the bid, failing which the bid security of the Bidder
may be forfeited.
Attachment 6A: Certificate Regarding Acceptance of Important Conditions
Bidders are required to furnish a certificate indicating their compliance to the provisions, duly
signed and stamped by the bidder, in a separate sealed envelope. Any bid not accompanied by
such certificate in a separate sealed envelope shall be rejected by NTPC and returned to the
Bidder without being opened.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 71/92
71
(g) Attachment 7: Alternative Bids
Bidders wishing to offer technical alternatives to the requirements of the bidding documents
must first price the NTPC’s design of the facilities as described in the bidding documents,
and shall further provide all information necessary for a complete evaluation of the
alternatives by the NTPC, including drawings, design calculations, technical specifications,
breakdown of prices, proposed installation methodology and other relevant details. Only the
technical alternatives, if any, of the lowest evaluated bidder conforming to the basic technical
requirements shall be considered by the NTPC.
(h) Attachment 8: Local Representation
If a foreign bidder has engaged an Indian agent, it will be required to give the following
details in its bid as per the format enclosed in the Bidding documents:
The name and address of the local agent;
What Service the agent renders; and
The fixed amount of remuneration for the agent included in the offer.
(i) Attachment 9: Deemed Export Benefits
The CIF (Cost of Insurance & Freight) value of import content in the Ex-works (India) price
quoted in Schedule-2 of the bid, if any, shall be necessarily declared by the bidders in
Attachment-9 to the bid. The relevant certificate for claiming the deemed export / custom
duty benefits shall be issued on the aforesaid declaration basis only. In case, no such import
content is envisaged in the bid or the CIF value of import content to be declared is zero, the
bidder shall indicate "NIL" against the CIF value of import content. In case where no value is
indicated by the bidder against the CIF value of import content in Attachment -9 or statement
/ any declaration like 'later', 'to be furnished later', 'NA' etc. are indicated by the bidder, in
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 72/92
72
such cases the CIF value of import content in the bid shall be considered as "NIL" for the
purpose of evaluation of bids and issuance of relevant certificate for claiming the deemed
export / custom duty benefits
Attachment 9A: Customs Duty Benefits for Import of Construction
Equipment
Declaration regarding the Customs Duty Benefits, for Import of Construction Equipment
Considered in the bid.
(j) Attachment 10: Functional Guarantees
The declaration on the guaranteed parameters and declaration on demonstration parameters as
per NTPC's format.
(k) Attachment 11: Erection Tools and Tackles
List of Erection Tools and Equipments which the bidder proposes to bring to site in case the
contract is awarded to him.
(l) Attachment 12: Technical Data Sheets
Technical Data Sheets duly filled in as per the NTPC's format.
(m) Attachment 13: Bought Out Items
Details of bought out items to be directly dispatched by the sub-vendor(s) to site.
(n) Attachment 14: Quality Assurance Programme
Details regarding the overall quality management & procedures which the bidder proposes, to
follow during various phases of execution of the contract.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 73/92
73
(o) Attachment 15: Additional Information
Any additional Information which the bidder wishes to provide in his bid.
(p) Attachment 16: Milestone Schedule
Details regarding the timing & sequence of all key activities necessary for successful
completion of the facilities and giving the important milestone as per NTPC's format.
(q) Attachment 17: Price Adjustment Data
Details regarding Price Adjustment as per NTPC's format.
(r) Attachment 18: Equipment and Mandatory Spares to be imported
from Associate/Collaborator
Details of Equipment (including type test) and Mandatory Spares to be imported from
Associate/Collaborator by the Manufacturer or the bidder, as per NTPC's format.
(s) Attachment 19: Electronic Fund Transfer Authorization Form
Electronic Fund Transfer Form duly filled in as per NTPC's format.
(t) Attachment 20: Declaration on Fraud Policy
Form of Acceptance of Fraud Policy duly filled in as per NTPC's format.
The Bidder is expected to examine all instructions, forms, terms, specifications and other
information mentioned in all the sections as well as attachments stated above in the bidding
documents. Failure to furnish all information required by the bidding documents or
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 74/92
74
submission of a bid not substantially responsive to the bidding documents in any aspect will
be at the Bidder’s risk and may result in rejection of its bid. The Bidder is advised to visit and
examine the site where the facilities are to be installed and its surroundings and obtain for
itself on its own responsibility all information that may be necessary for preparing the bid and
entering into a contract for supply and installation of the facilities. The costs of visiting the
site shall be at the Bidder’s own expense. The Bidder and any of its personnel or agents will
be granted permission by NTPC to enter upon its premises and lands for the purpose of such
inspection, but only upon the express condition that the Bidder, its personnel and agents will
release and indemnify NTPC and its personnel and agents from and against all liability in
respect thereof and will be responsible for death or personal injury, loss of or damage to
property and any other loss, damage, costs and expenses incurred as a result of the inspection.
PRICE SCHEDULES
Bidders shall give a breakdown of the prices in the manner and detail called for in the Price
Schedules. Separate numbered Schedules shall be used for each of the following elements.
The total amount from each Schedule (1 to 4) shall be summarized in a Grand Summary
(Schedule 5) giving the total bid price(s) to be entered in the Bid Form. The Bidders shall
present their prices in the following manner:
Schedule No. 1 - Plant and Equipment including Type Tests charges and Mandatory
Spares Parts supplied from Abroad
Schedule No. 2 - Plant and Equipment including Type Tests charges and Mandatory
Spares Parts to be manufactured within Employer's (NTPC) Country.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 75/92
75
Schedule No. 3 - Local Transportation including port handling, port clearance, port
charges, Inland transit Insurance and other local cost incidental to delivery of Plant &
Equipment and Mandatory Spares.
Schedule No. 4 - Installation Services including Erection Works, insurance covers other
than inland transit insurance and other services.
Schedule No. 5 - Grand Summary (Schedules Nos. 1 to 4)
Schedule No. 6 -Recommended Spare Parts
Schedule No.7 -Taxes and Duties, applicable on Ex-Works (India) Price Component
(Schedule-2) in respect of direct transaction between the Bidder and Employer (NTPC),
not included in Bid Price.
Schedule No. 8A - Break up type test charges quoted in Schedule-1
Schedule No. 8B - Break up type test charges quoted in Schedule-2
Schedule No. 9 - Unit Adjustment rates.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 76/92
76
E- PROCUREMENT
E-PROCUREMENT is very important to achieve e-governance and for applicability of
uniform procurement process to all units. It has the ability to reduce procurement cost by
reduction in lead time, reduction in transaction cost and cycle times etc. E-procurement also
helps in building collaborative relationship with suppliers. It enables greater transparency;
implements best practices, and increases the vendor base. It also reduces the possibility of
cartel formation and generates reasonable competition. It helps to achieve savings in
administrative and process cost. E-procurement enhances the security and it is also a step
towards ERP systems for the organization.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 77/92
77
CONCEPT AND SCOPE
E-procurement is purchase and sale of supplies and services and management of procurement
process over Internet. Manual tender processes can be long and cumbersome, often taking
three months or longer, which is costly for both buyer and supplier organizations. E-
Tendering replaces these manual paper-based tender processes with electronically facilitated
processes based on best tendering practices to save time and money. Through E- Tendering,
NTPC is able to manage the tenders coming in, with all tenders stored in one place. It can cut
and paste data from the electronic tender documents for easy comparison in a spreadsheet.
Suppliers' costs in responding to Notice Inviting Tender (NIT) are also reduced as the tender
process cycle is significantly shortened. E-tendering offers an opportunity for automating
most of the tendering process: from help with preparing the tender specification; advertising,
to tender evaluation and placing of the contract.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 78/92
78
E-PROCESS WORKFLOW
Fig-8: Process of E-procurement
The process of e-procurement shall be taken up at Contracts & Materials (C&M) department
after receipt of the requisition or the indent. The indent duly approved by the competent
authority, as per Delegation of Powers (DOP) handbook of NTPC, is a pre-requisite to
initiate e-procurement action. Once the indent is approved, the C&M department then plan
and organize the procurement action.
In case of open tender contract valuing 2 lacs and above, a Tender Committee is formed for
preparation and approval of Qualifying Requirements (QR). Then, various bidders are
invited online to bid for various packages. A Notice Inviting Tender (NIT) is published
R R ee gg iiss tt rr aa tt iioo nn oo f f iinn dd ee nn tt
Check forvalue / type
PP rr oo pp oo ss aa ll f f oo rr f f lloo aa tt iinn gg oo nn -- lliinn ee tt ee nn dd ee rr tt hh rr oo uug hh
R R ee llee aa ss ee TTee nn dd ee rr tt hh rr oo uu gg hh ee --
TC nominationIndentor &
OOnn lliinn ee PP R R EE BBII DD tt ee cc hh nn iiccaa ll cc llaa rr iif f iiccaa tt iioo nn
Online BID
OOnn lliinn ee tt ee cc hh nn iicc aa ll BBII DD
Offline EMDsubmissions
NNoo mm iinn aa tt iioo nn oo f f QQR R cc oo mm mm iitt tt ee ee aa nn dd
A A pp pp rr oo vvaa ll oo f f QQR R
TTee cc hh nn iicc aa ll ee vvaa lluu aa tt iioo nn uu ss iinn gg oo nn lliinn ee OOnn lliinn ee qq uu ee rr iiee ss f f rr oo mm iinn dd ee nn tt oo rr ,, tt ee cc hh nn iicc aa ll
cc llaa rr iif f iicc aa tt iioo nn tt oo & & f f rr oo mm
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 79/92
79
online on NTPC’s E-procurement portal. The interested bidders can purchase the tender
document of the required package, by sending a demand draft or a cheque of the required
amount, as mentioned in NIT, in favour of NTPC. Once the payment is received, a login id
and password is given to the bidder to view and download the tender document.
Clarifications regarding QR or any other technical queries in the document are resolved
online through e-mails, message chart boards etc. Based on the clarifications to the bidders,
if required, the tender committee may issue the necessary amendments. These amendments
shall be automatically forwarded to all the vendors who have downloaded the documents.
The bidders shall prepare the bids online. Till the time they are submitting their bids, they
shall be saving the bids at the server under their Digital Certificate.
Bidders are then required to submit and upload their bid online prior to a pre-defined date
and time, as mentioned in the NIT, on the NTPC’s e-procurement website based on the
tender requirements defined in the tender documents, viz:
Qualifying Requirements documents,
EMD details
Technical data sheets and Commercial bid etc.
However, the Earnest Money Deposit (EMD) / Bid Security of a particular amount, have to
be submitted offline in a separate sealed envelope. Any bid not accompanied by an
acceptable bid security in a separate sealed envelope shall be rejected by NTPC as being
non-responsive and returned to the bidders without being opened.
Once the bids are uploaded by all the bidders, neither any bidder nor any employee of NTPC
can access the server prior to bid opening date and time. At the time of bid opening, using
individual digital certificates & passwords, the tender committee shall open the EMD
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 80/92
80
documents first, then the qualifying requirement details shall be opened, followed by the
Technical bid opening and the technical data sheets and the deviation statement – technical.
The commercial price bids of only those bidders who are meeting QR and are
TECHNICALLY acceptable, and have submitted the necessary EMD will be opened on later
date by the tender committee. On the date of price bid opening, a comparative statement of
bid price schedules is automatically generated online and only the members of tender
committee have access to both the quoted price and ranking of each bidder. However, each
bidder can only view the rankings and not the quoted price of other bidders.
e- procurement workflow chart for a tender……..annexure-II
S.No
Steps Proposed /suggested action
1. Defining work flow To be configured by the SERVICE PROVIDER and to be followed uniformly by thepurchase groups while following electronic tendering e-procurement.
2. Appointment of Service provider Service Provider by Corporate Centre
3. e-tendering as aEVENT
Is broadly defined in following segments
a. e-procurement pre-requisites … includes setting of software and buyercum supplier Training.
b. Pre-event … items identifications, specifications, etc
c. Event .. On-line tendering including Auctions & reports
d. Post-Event. .. Post auction Item rate and Archive reports,
4 Features of the process
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 81/92
81
4.1 Hoisting of Tender Documents
Hoisting of Tender Documents by TC using Digital Certificate On line
Allowing Downloads to Bidders. By providing pass words On line
Submission of EMD Off line
Verifying of EMD Details Off line
Submission of BIDs On line
4.2 Tender Opening
Bid opening by TC. Using Individual Digital Certificates & Pass Words On line
Opening of Technical Bids Online
Evaluation of tech Bids. Online
Technical Clarifications Online
Approval of Technical Bids & short listing of bidders Off line
4.3 Opening of Price Bids
Arriving at Technical Loading Off line
Incorporation of Loading Logic Online
Opening of Price Bids Using Individual Digital Certificates & Pass Words. Online
4.4 Conducting of REVERSE AUCTION with lowest bid price as the openingprice
Reverse Auction A process technique which allows prospective buyers tolist any item(s)5 they wish to buy, and the sellers bid to provide the bestprice , Suppliers Competing, can be from anywhere in the world…justneed to have Internet access. . ‘Reverse’ in nature…Because prospectivesellers bid the price DOWN as they compete for the work and the Prices Spiral Down, the process is More Consumer Oriented and is Mosteffective after Technical evaluation.
Online
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 82/92
82
1
Defining tendering
procedures
Procedures shall be similar at all the plants, process designed by CMM based
on various experiences gathered from Pilot e procurement projects carriedout at Corporate Centre and various plants.
2 Mode of tendering Short listing of vendors shall be based on mode of tendering, viz
Restricted tender or Limited Tender Open tender
In case of open tender case. Short listing will be done through qualifyingrequirements.
3 Nomination of TenderCommittee
Tender committee shall be nominated in advance and shall be associatedwith the tender from preparing of tender documents, auction rules, securityaspects and finalization of tender, as per the strategy agreed upon.
4 Defining tenderdocuments
The broadly following sections should be part of a tender document.
1. Qualifying requirements in case of open tender.2. Bill of materials3. Instructions to bidders.4. General purchase conditions5. Proforma of bank guarantee towards EMD6. Quality plan format7. Reverse Auction Rules.8. Technical Data Compliance Sheets.9. Bid Price Schedule10. Statement of deviation
Defining auction rules Auction rules shall be incorporated in the tender document and madeknown to vendors at the time of tender release.
However, the strategies shall be finalized before Price bid opening date isannounced.
5 Apply & issue of digital certificates
Apply and Receive the digital Certificate form the certifying authorities forthe tender committee members.
Certifying authorities are TCS, Safescrypt, MTNL, n-code solutions.
Service Provider may also render assistance through sub-CA.
6 Generating of Generated by SERVICE PROVIDER and re-fixed by the digital certificate
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 83/92
83
passwords. holders.
7 Defining of Servertiming of clock
The server time of e-procurement portal / site shall be ensured beforerelease of tender document.
8 Hosting of tenderdocuments
Tender documents to be electronically released by the Tender Committeefor hosting at the e-procurement portal.
Release andUploading of documents
The tender documents defined above shall be released and uploaded on e-procurement portal (in association with Service Provider) by the TenderCommittee under their Digital Certificate and Pass Words
9 Defining TenderSchedule
Tender Schedule is as below: -
S.No. NTPC Stage Contractor Stage SERVER date & time Envelopes
Start Expiry
1. Release Tender - Pre-Qualifying,
Technical sheets BidCommercialrequirements,
Bid price Scheduleetc.
2. - TenderDownload
3. - Bid Preparation
4. Close for Bidding -
5. - Bid Submission For details refer PARA – 22.0
6. Bid Opening -
7. Reverse Auction -
8. Item Rate form Item Rate form
9. View Item Rate Form - -Do-
10. Tender Award -
10 Allowing download of Tender Document
In case of Open Tender documents will be allowed to be downloaded by allthe vendors who are registered / enrolled at the portal.
In case of Restricted/ Limited Tender, only those authorized by NTPC at thetime of the Tender release.
In case of Open tender pay for tender documents either through online
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 84/92
84
payment or shall send this payment to NTPC or through DD directly to NTPCrespective plant. Or along with EMD before bid opening
11 Clarification on tenderdocument on line
If required, Vendors shall seek on line clarifications on released document,TC shall respond and issue the clarifications on-line to the queries, thesequeries shall be on ONE to MANY basis. The reply to the query shall beautomatically forwarded to all the vendors who have down loaded thedocuments.
12 Amendments Based on the clarifications to the Vendors, if required TC may issue thenecessary amendments, these shall be on ONE to MANY basis. Theamendment shall be automatically forwarded to all the vendors who havedown loaded the documents and shall be available for down load too.
13 Preparation of bids online
Vendors shall be preparing the bids on line. Till the time they are submittingtheir bids, they shall be saving the bids at the server under their DigitalCertificate also using PKI for encryption & decryption for ensuring theconfidentially and security of the bids.
14 Submission of bids online
Vendors shall have to submit bids online on the NTPC, e-procurementwebsite
15 UP – Loading of bids All the vendors shall upload their bids on the NTPC, e-procurement websitebased on the tender requirements defined in the tender documents, viz
Qualifying Requirements documents, EMD details Technical data sheets and Commercial bid etc.
16 Submission of EMD –off-line
All the vendors shall send the EMD in acceptable form to NTPC directly andshould reach to tendering authority on or before bid opening date.
Any Special treatment to be allowed foe EMD should be clearly brought outin the Tender documents.
17 Submission of EMD –on line
The copies of the EMD details shall be uploaded on the website. In case of vendors who are exempted from submitting EMD, the necessary documentsshall be uploaded on the website.
18 Opening of BIDS – online
Applying individualdigital certificates
& Pass words
By
At the time of bid opening, tender committee shall open the EMDdocuments first, Then the qualifying requirement details shall be opened,followed by the Technical bid opening and the technical data sheets and thedeviation statement – technical.
TC using individual digital certificates & pass words shall open theelectronic tender box consisting of
1. Envelope-1 …containing EMD details
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 85/92
85
Tender Committee 2. Envelope-2 …containing Qualifying requirements
3.Envelope-3…containing Technical details & data sheets.
4. Envelope-4 …containing Technical deviation details.
5. Envelope-5 …containing bid price schedule . The commercial bids of only those vendors who are meeting QR and areTECHNICALLY acceptable, and have either submitted necessary EMD orsubmitted necessary documents for EMD exemption will be opened on laterdate by the tender committee
19 Opening of
EMD
Envelope-1
Tender committee shall Open the EMD Details and compare and verify withthe physical details of EMD received.
Where ever EMD has been found OK, proceed further
20 Opening of
QR
Envelope-2
Tender committee shall Open the QR Details for those vendors whose EMDis OK.
QR
Verification
This is a on line activity and Tender Committee will verify QR using individualdigital certificates
QR
Clarification
This is a on line activity and If required TC will seek on-line clarifications forQR deficiencies
21 Opening of technicalBids envelope-3
Tender committee shall Open the Technical bids, using individual digitalcertificates
Opening of datasheets envelope-4
Tender committee shall Open the Technical deviation details, usingindividual digital certificates
On line evaluation of technical bids
TC will evaluate the bids on line based on the exception technicalcomparative sheets generated by the system.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 86/92
86
On line technicalclarifications
TC will seek on-line clarifications if required, from the individual vendor.These clarifications shall be on one to one basis and shall be sought on-lineonly.
22Arriving at technical
loading off line Based on the technical clarification furnished by the vendors, and thedeclared deviations (if any) arrive at the technical loading is required interms of money value.
Incorporation of loading logic
Incorporate the loading logics in consultation with Service Provider beforedeciding the price bid opening date.
Ensure the loading logic is incorporated towards the technical loading
23
Assessment of NEW Vendor
In the event of Open Tender, in case a new vendor is meeting the
QR and all technical requirements.
If required the tender committee shall carry out the assessment of thevendor as per laid down procedure and ensure the vendor’s capabilitybefore making final recommendations for opening of their price bid.
24 Short listing\ of Vendors after
technical evaluation
Based on technical evaluation cum QR qualification in case of Open Tender,obtain approval for short listing of Vendor for opening of Price Bid fortechnically qualified vendors.
Define Price Bid Opening Date,
25 Opening of Bid PriceSchedule envelope-5
Defining BOD for price bids opening
On line opening of price bids by TC using individual digital certificates &passwords with the help of Service Provider.
ComparativeStatement
Generate On-line Comparative statement, after completion of Price bidopening.
In case of Reverse Auction option, Decide the opening Price. For reverseauction or else process case for approvals & ordering.
26 Defining
Auction
Rules
Tender committee with the approval of approving authority shall fix OpeningPrice for reverse auction.
Opening price shall either be based on lowest technically acceptable pricereceived at the time of commercial bid opening of the price fixed bycommittee with the approval of approving authority based on estimate andlowest price received.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 87/92
87
Bid Price: - Reverse Auction shall be held on total bid price derived from theindividual item rates.
Alias Names:- During the reverse auction names of the parties will not be
displayed on the reverse auction portal. Only the rate of L1 bidder shall bedisplayed
To be defined by system Administrator / Service Provider
Rank Option : - The individual vendors shall know their rank only withrespect to the Lowest bid
Bid Decrement : - The minimum increment during reverse auction shall be(Rs. Xxxxx.xx) to be decided by TC depending upon the item beingprocured.
Auction Time :- The reverse auction shall be held for (xx hrs.) from ….. hrs to….. hrs to be decided by TC on case to case basis.
Extension time: - In case of last minute bidding the bidding time shall beextended for (.. minutes ) for infinite no. Of times. Or
Provisions for limited extensions can be also provided on case-to-case basisand to be decided by the TC.
ITEM RATE SUBMISSIONS: -After the successful completion of reverseauction the Lowest bidder shall be informed electronically to submit itemrate form.
27 Reverse Auction date& Time
Setting of reverse auction date in consultation with system administrator /Service Provider by the Tender Committee..
Inform the vendors the date and time of Reverse Auction, whose price bids,have been earlier opened.
28 Conducting reverse
auction
Shall be done in consultation with Service Provider.
29Providing of item wise
break up
by L1 bidder
After completion of reverse auction L1 bidder will submit the item rateswithin 48 hours (2 days) of completion of RA.
The % Reduction of prices achieved during the Auction can be uniformlydistributed over all the items. Or can be evenly distributed among all theitems.
In no case the individual item rate can be revised to higher value thanindicated in the original item rate schedule against which the RA has been
conducted.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 88/92
88
30 Finalrecommendations
And
Award
After receiving the item rate from the tender committee shall put uprecommendations to the competent authority off line.
After approval of competent authority the order shall be released to the L1bidder as per normal procedure.
31 Contract Agreement To be assigned by NTPC and the L1 bidder off line as per practices
32Training
Training of NTPC personnel
Training of vendors
The tender committee shall ensure that the proper training is imparted tothe participating Vendors.
Service Provider to ensure the same.
33 Archiving & Vaulting Data towards concluded tenders, which has been Logically Completed, shallbe transferred to NTPC Servers for the purpose of Long-term Auditrequirements.
34 Documents to beretained forVerifications
Case file should necessarily contain following document.
1. Purchase indent along with administrative approval.
2. Approved note sheet for resorting to e - tendering.3. Approved note sheet for nomination of Tender Committee.
4. Tender Documents.
5. Tender release schedule.
6. System generated technical data comparative statements.
7. Approved note sheet for technical evaluation / short-listing of vendors / Price Bid Opening.
8. System generated Price Bid comparative statements
9. Down loaded copy of item rate details as per BPS.10. Original Copy of item rate details as per BPS from L1 Bidder.
11. Snap Shots of Reverse Auction.
12. System generated audit trail report.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 89/92
89
EE--pprrooccuurree mmeenntt pprroommiisseess tthhee f f oollllooww iinngg ggaaiinnss::
NNoo ggeeooggrraapphhiiccaa ll bbaarrrr iieerrss :: ssaa lleess / / mmaarrk k eett iinngg tt iimmee rreedduucctt iioonn,, wwhhiicchh ootthheerrww iissee ssppeenntt oonn pprr iiccee nneeggoott iiaatt iioonnss,, f f oo llllooww uuppss eettcc..,, aass tthhiiss ww iillll lleeaadd ttoo qquuiicck k eerr oorrddeerr f f iinnaa lliizzaatt iioonn aatt oouurr eenndd
1
TTCC mm ee ee tt iinn gg ,, nn oo tt ee ,, pp rr oo pp oo ss aa ll f f oo rr
tt ee cc hh nn iicc aa ll aa pp pp rr oo vv aa ll,, ss hh oo rr tt lliiss tt iinn gg oo f f
A A uu tt oo -- oo pp ee nn iinn gg oo f f pp rr iicc ee BBII DD aa nn dd aa uu tt oo --eneration of CS re orts.
TTEER R oo f f f f lliinn ee
ReverseAuction
FFiinn aa ll TTCC rr ee cc oo mm mm ee nn dd aa tt iioo nn ..
A A pp pp rr oo vv aa ll oo f f TTCC rr ee cc oo mm mm ee nn dd aa tt iioo nn ..
R R ee gg iiss tt rr aa tt iioo nn oo f f PP OO
TToo rr ee llee aa ss ee EEMMDD f f oo rr uu nn ss uu cc cc ee ss ss f f uu ll BBiidd dd ee rr ss .. SSee cc uu rr iitt DDee oo ss iitt f f rr oo mm ss uu cc cc ee ss ss f f uu ll BBiidd dd ee rr ss ..
Release of
Preparation of draft PO /LOA and vetting of the
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 90/92
90
RReedduucctt iioonn iinn VV eennddoorr’’ss ccoossttss aass tthheeyy nneeeedd nnoott tt rraavveell ttoo oouurr oof f f f iicceess && tthheerree iiss nnoo nneeeedd ttoo mmaak k ee tthhoossee ccoommmmuunniiccaatt iioonn ccoossttss
CCoommpplleettee ttrraannssppaarreennccyy iinn tthhee pprroocceessss,, lleeaadd iinngg ttoo ssoouunndd ddeecc iissiioo nnss EEnnhhaanncceess sseeccuurr iittyy
SSaavviinngg iinn aaddmmiinn iisstt rraatt iivvee aanndd pprroocceessss ccoosstt
REVERSE AUCTION
The next step is called a REVERSE AUCTION. It is a type of auction in which the role of
the buyer and seller are reversed, with the primary objective to drive purchase prices
downward. In an ordinary auction (also known as a forward auction), buyers compete to
obtain goods or services. In a reverse auction, sellers compete to obtain business. During a
reverse auction, all the interested bidders log on to the auction site and inputs several quotes,
in multiples of a specified amount, over a 30-90 minute period. These quotes reflect the
prices at which they are willing to supply the requested package. As the bidder can only
view its relative position with respect to other bidders, he bids down the price until the price
quoted by him becomes the lowest of all.
After completion of reverse auction, the L1 bidder (the bidder which quotes the lowest price)
will submit the item rates within 48 hours (2 days) of completion of reverse auction. The
percentage reduction of prices achieved during the auction is uniformly distributed over all
the items. In no case, the individual item rate can be revised to higher value than indicated in
the original item rate schedule against which the reverse auction has been conducted. After
receiving the item rate, the tender committee shall put up recommendations to the competent
authority off line. After approval of competent authority the order shall be released to the L1
bidder as per normal procedure.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 91/92
91
BENEFITS TO NTPC
Reduced tender cycle-time.
Fast and accurate pre-qualification and evaluation, which enables the automatic rejection
of suppliers that fail to meet the tender specification.
Faster response to questions and points of clarification during the tender period.
Reduction in the labour intensive tasks of receipt, recording and distribution of tender
submissions.
Reduction of the paper trail on tendering exercises, reducing costs to both the
organization and the suppliers.
Improved audit trail increasing integrity and transparency of the tendering process.
Improved quality of tender specification and supplier response.
Provision of quality management information.
RECOMENDATIONS
Price bids should be filled online from various bidders, so that arithmetic accuracy can be
maintained.
Any technical and commercial details in the evaluation reports should be furnished with
proper reference along with the page numbers as mentioned in the bid documents.
Strict instructions should be given to all the bidders to furnish supporting schedules along
with the annual reports, without which complete Financial Analysis cannot be done.
Bidders should be given proper training sessions for filling of bid forms and schedules.
While preparing cost estimate many times, last awarded rates are taken which at times
are quite old. Hence in such cases parallel market rates collection should be insisted upon.
8/8/2019 Jitendra Report 2
http://slidepdf.com/reader/full/jitendra-report-2 92/92
Some times in the bid documents the treatment of taxes and duties in evaluations is not
clearly indicated. This leads to confusion. This aspects needs special care while reviewing
bid documents.
In the Q.R. certain financial parameter like return on net worth etc. are found to be
needing attention as the same has been kept very low and hence there are chances that are
very poorly performing company may enter as contractor.
In case of limited tender enquiry, the list of party needs to be constantly upgraded so that
good parties can find place.
While evaluating a bidder, some time the credentials of bidders are more than 7 year old.
The status of bidder might have changed by this t ime. Hence the status of recent year (last
3 years) is suggested to be considered for checking their credentials.
REFERENCES
Bidding documents
NTPC-Delegation of Powers (DOP)
Tender evaluation reports
NTPC Office Circulars