Jim Huggins and the Case for CBT:A Play in Four Acts
The Scene
Hill Industries: Producer of manufacturing plant machinery
New competitors have been able to develop high-quality products more quickly and for less cost
Hill Industries has streamlined the PD process– Flatter organization– Fewer approval steps– Fewer prototypes– Early involvement of manufacturing/marketing– More reliance on design and engineering
The Players
Jim Huggins: Instructional Design Consultant
Bob Werner: Steering Committee Chair
John Eggleston: Committee Member/Training Supervisor
Committee Members
The Plot
Jim has been asked to develop a training program
Jim’s recommendation: Hypermedia CBT
CBT has been implemented at Hill Industries, but less than 15% of the 15,000 employees have used it
Let’s go back…
ACT I:Meeting #1 with the
Steering Committee at Hill Industries
Flag
Red Flag #1
Committee members do not understand what a CBT is, based on Jim’s description
Familiar with classroom training
Cannot visualize what Jim is talking about
Red Flag #1
Come with an example
Discuss how other companies like Hill Industries have used CBT (Review literature, etc.)
What could Jim do better?
Let’s Continue…
Flag
Red Flag #2
Hill Industries has traditionally used classroom training
Committee members know there are problems with classroom training, but they would rather have problems they understand than ones they don’t (CBT is too much of a mystery)
Committee members don’t know whether CBT can be used to teach PD processes
Red Flag #2
Come with an example of how CBT has been used to teach processes (“Straw” – Rossett, 1999)
Be prepared to discuss potential pitfalls of CBT – and how they can be avoided
Apply change management techniques (Dormant, 1999)– Demonstrate advantages of change– Identify key peers that can influence others– Identify sponsors who can promote the change
What could Jim do better?
Let’s Continue…
ACT II:Meeting #2 with the Steering Committee
Flag
Red Flag #3
Committee needs more data on how CBT has been used in their particular industry in order to be comfortable with the idea
CBT supporters are making decisions based on opinions of others and a desire to embrace the latest technology
Red Flag #3
Select better examples – companies similar to Hill Industries
Help the committee make a decision for CBT based on whether or not it is the best delivery option – not just because it is the “latest thing”
Consider drivers & barriers (Rossett, 1999)
What could Jim do better?
Let’s Continue…
Flag
Red Flag #4
Committee does not understand how cost of CBT is typically high at the front end (design & development), but the recurring costs are reduced.
Red Flag #4
Show that while initial CBT development costs are high, the overall cost may be less than that for classroom training (travel, materials, etc.)
What could Jim do better?
Let’s Continue…
ACT III:Yet another meeting with the Steering Committee…
Flag
Red Flag #5
Committee appears to have made a decision based on lower cost and popularity of “new” technology, not real understanding of what the solution will be
Red Flag #5
A small, less complicated prototype could have been used to help visualize the CBT program
Committee could make a decision based on what would be actually be delivered, not just on the basis of the dollar amount and the latest trends.
What could Jim do better?
ACT IV:Implementation…the Final Act!!!
Flag
Red Flag #6
CBT is being implemented because of a top-down mandate from management; stakeholders are not involved early in the process.
No one is made responsible for making sure that employees complete the CBT – only that they have access!
Red Flag #6
Press for earlier involvement with the training coordinators so that they understand the importance of the CBT (as part of a blended approach) and embrace the solution.
Make someone accountable for ensuring that employees complete the CBT
Change Management
What could Jim have done better?
What Can Be Done at this Stage?
Find out what the 15% who are using the program like about it
Use their successes as examples, reward them Establish incentives for using the program or
disincentives for not using it Consider a hybrid approach where trainers and
those who have successfully used the program become mentors
Lessons Learned
When making a change, make sure that benefits are clearly understood
In any change effort, there must be buy-in from management and other stakeholders
Be aware of drivers and barriers in the environment; they can make or break any type of new program
Questions?
Thank You!
References
Dormant, D. (1999). Implementing human performance technology in organizations. In H. D. Stolovitch & E. J. Keeps (Eds.), Handbook of human performance technology (2nd ed., pp. 237-59). San Francisco, CA: Jossey-Bass/Pfeiffer.
Mager, R.F. and Pipe, P. (1997) Analyzing Performance Problems. (3rd Ed. P. 75-77)Atlanta, GA. The Center for Effective Performance.