Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
ii
EXECUTIVE SUMMARY
INTRODUCTION
The South African National Roads Agency SOC Limited (SANRAL) is proposing to improve 26.41 km of the
National Route 7 (N7), Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90) located within the
Swartland Local Municipality, Western Cape (see Figure 1).
OVERVIEW OF THE PROJECT
The proposed project mainly entails the provision of additional climbing / passing lanes and widening the road
and associated infrastructure in certain areas. The existing carriageway would be widened to the following
cross-sections:
• Where no climbing lanes are provided: two 3.7 m-wide lanes and two 3.5 m-wide shoulders;
• Where a climbing lane is provided on one side only: a 1.5 m-wide shoulder (1.0 m surfaced) with
3.5m-wide slow lane and 3.7 m-wide fast lane. The side without the climbing lane would have a 3.7
m-wide lane and a 3.5 m-wide shoulder (3.0 m surfaced); and
• In instances where climbing lanes are provided on both sides: each side would have a 1.5 m-wide
shoulder (1.0 m surfaced) with a 3.5 m-wide slow lane and a 3.7 m-wide fast lane.
Four bridge structures and six major culverts would need widening along the route, and accesses which do not
meet the SANRAL standards for sight distance will be further investigated during the final engineering design
stage in order to determine how the sight distance could be improved. Ancillary works mainly include the
following:
• Installation of concrete-lined side drains with subsoil drains;
• Replacement of minor culverts; and
• Resurfacing of intersections with provincial roads and major farm accesses.
JG Afrika (Pty) Ltd was appointed by SANRAL (under Contract No. NRA N.007-020-2020/1F) to provide
Consulting Engineering Services. SLR Consulting (South Africa) Pty Ltd (SLR) in turn, was appointed by JG Afrika
(Pty) Ltd to complete the Basic Assessment process as part of an Application for Environmental Authorisation in
terms of Chapter 5 of the National Environmental Management Act, 1998 (No. 107 of 1998) (NEMA), as
amended.
This final Basic Assessment Report (BAR) provides a description of the proposed project, the affected
environment and the BA process followed, and an assessment of the identified potential impacts on the
environment. The compilation of this report has, where applicable, been informed by comments received from
interested and affected parties (I&APs) and authorities during the pre-application notification period and on the
draft BAR. It should be noted that all significant changes to the draft report are underlined and in a different font
(Times New Roman) to the rest of the text.
This report is submitted to the Department of Environment, Forestry and Fisheries (DEFF) for consideration as
part of an application for Environmental Authorisation in terms NEMA.
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
iii
FIGURE 1: LOCATION OF THE N7, SECTION 2 BETWEEN ROOIDRAAI AND MOORREESBURG
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
iv
NEED AND DESIRABILITY
The road forms part of the national road network of South Africa and carries regional and national traffic. The
relevant section of road carries approximately 5 218 vehicles per day (both directions), of which 21% are heavy
vehicles. A Stage 1 (Feasibility/Preliminary Design Stage) Road Safety Audit highlighted some concerns related
to this section. As a result of the increased traffic and the findings of the Road Safety Audit, Section 2 of the N7
needs to be improved in order to conform to the Geometric Design (G2) Standards.
SUMMARY OF AUTHORISATION REQUIREMENTS
The proposed project triggers the need for a BA process to be undertaken in order for the DEFF to consider
granting or refusing Environmental Authorisation.
Registration of water uses in terms of the National Water Act, 1998 (No. 36 of 1998; NWA) is also required
where the proposed works cross drainage lines, and if water supply is required from a water resource (other
than a municipal supply).
Section 38 of the National Heritage Resources Act, 1999 (NHRA) requires a Notice of Intent to Develop (NID) to
be submitted to Heritage Western Cape (HWC).
AFFECTED ENVIRONMENT
Land Use and Character of the Surrounding Area
The terrain is relatively flat in relation to the hills and deeper valleys of the areas that lie to the west and east
of the road. Much of the area has been transformed for many decades by agricultural development and by the
N7 road itself. As a result, most of the natural vegetation cover and aquatic features have been significantly
modified. The nearest urban areas are the towns of Malmesbury, located close to the start point in the south,
and Moorreesburg, at the end point in the north.
Climate
Generally, the area has a Mediterranean climate with an average annual rainfall of approximately 305 mm and
an average temperature of 18.6°C. The summer months typically have lower rainfall, higher temperatures and
higher evaporation. During winter the area experiences high rainfall and lower temperatures with subsequent
lower evaporation.
Topography
The terrain along this section of road can be defined as flat and occasionally broken up by hills with grades
varying between 1.5% and 4%. The elevation of the study area varies between 123 m and 293 m above mean
sea level.
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
v
Geology and Geohydrology
The geology of the broader study area is dominated by granite of the Paardeberg Pluton, Cape Granite Suite,
greywacke and phyllite of the Moorreesburg Formation, Malmesbury Group and occasional diorite and gabbro
of the Yzerfontein Suite. Boreholes within the study area potentially yield between 0.6 – 0.8 litres/second with
a maximum volume of 15 000 – 25 000 m3/km
2/annum being abstracted while preserving sustained abstraction
within the aquifer system.
Freshwater Ecosystems
The study area is located within the G21D, G10J and G10L quaternary catchments, but primarily G10L. These
catchments are drained by the Diep River, as well as the Moorreesburgspruit and Sout River (tributaries of the
Berg River) respectively. A number of smaller seasonal to ephemeral tributaries of these rivers occur along the
road section. A number of valley bottom wetland areas are associated with the watercourses.
Vegetation
A single main vegetation type (Swartland Shale Renosterveld) occurs in the study area with a limited
occurrence of a second type (Swartland Granite Renosterveld) occurring along the southern parts of the route.
These vegetation types are classified as part of the Fynbos Biome. Swartland Shale Renosterveld has been
largely lost along the entire road section. This is ascribed to intense negative anthropogenic influences over a
long period. The affected vegetation is currently all secondary vegetation that has established since the last
road construction activities along the route.
Biodiversity and Terrestrial Ecosystem Status
There are various areas along the route which crosses Critical Biodiversity Area (CBA) 1 (terrestrial), CBA 2
(terrestrial), CBA 2 (river) and Ecological Support Area (ESA) 2 (Restore from other land use) areas. The entire
route falls within a Critically Endangered (CR) (A1 & D1) area. “A1” indicates irreversible loss of natural habitat,
where the remaining natural habitat is less than the biodiversity target for CR areas, while “D1” indicates
threatened plant species associations, with more than 80% constituting threatened Red Data List species for CR
areas. According to the botanical study no Species of Conservation Concern or IUCN Red List plant species were
found along the road section.
Socio-Economic Aspects
The population of the Swartland Local Municipality increased from 72 116 in 2001 to 133 762 in 2016.
Swartland’s population in 2016 was strongly concentrated in the younger age cohorts. The proportion of poor
people within the Swartland municipal area decreased slightly between 2011 and 2016. An increase in the
number of indigent households between was experienced between 2014 and 2016. The Swartland contributed
28 % in 2015 to the West Coast District’s gross domestic product per region (GDPR). The sectors that
contributed the most to Swartland’s GDPR in 2015 are manufacturing, agriculture, forestry, fishing,
wholesale/retail trade, catering and accommodation. Overall, between 2004 and 2015, every economic sector
in Swartland grew positively in terms of GDPR, except for the mining, electricity, gas and water sectors.
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
vi
Cultural Heritage
No heritage resources occur within close proximity to the proposed project. The Swartland is an important
cultural landscape with strong agricultural characteristics. Occasional large gum trees occur along the road and
are considered as being features of the Swartland cultural landscape. These occur in three places, i.e. km 20.50
northbound and km 29.67 – 32.80 southbound (in two locations).
IMPACT ASSESSMENT CONCLUSIONS
The majority of potential impacts are expected to occur during the construction phase of the proposed project.
All potential negative impacts related to the proposed project (during both construction and operations) are
rated as VERY LOW to LOW significance after mitigation. Socio-economic benefits related to employment
opportunities is rated as VERY LOW (POSITIVE) significance after enhancement, while the improvement in road
user safety and traffic accommodation is rated as HIGH (POSITIVE) significance after enhancement.
Implementation of the No-Go option would mean that the planned road improvement would not proceed.
Implementation of the No-Go alternative would not make provision for the anticipated increase in future traffic
along the road section and the related improvement of road user safety would not be realised.
A summary of the assessment of potential environmental impacts associated with the proposed project is
provided in the table below:
ISSUE / POTENTIAL Impact IMPACT SIGNIFICANCE
WITHOUT MITIGATION WITH MITIGATION
CONSTRUCTION PHASE
LAND USE
Impacts on the Land Use MEDIUM VERY LOW
GENERAL CONSTRUCTION RELATED IMPACTS
General construction related impacts VERY LOW VERY LOW
FRESHWATER ECOSYSTEMS
Impacts on Aquatic Habitats HIGH MEDIUM
Impacts on Surface Water Quality MEDIUM LOW
VEGETATION
Impact on Swartland Shale Renosterveld MEDIUM VERY LOW
Impact on Fynbos patch (N7PM54) HIGH LOW
BIODIVERSITY AND ECOSYSTEMS
Biodiversity and Terrestrial Ecosystems HIGH VERY LOW
SOCIO-ECONOMIC ASPECTS
Employment VERY LOW (POSITIVE) VERY LOW (POSITIVE)
Inconvenience to Road Users LOW VERY LOW
Land Acquisition MEDIUM VERY LOW
CULTURAL HERITAGE
Cultural Heritage Impacts LOW LOW
OPERATIONAL PHASE
FRESHWATER ECOSYSTEMS
Impacts on Aquatic Habitats and Surface Water Quality LOW VERY LOW
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
vii
ISSUE / POTENTIAL Impact IMPACT SIGNIFICANCE
WITHOUT MITIGATION WITH MITIGATION
VEGETATION
Impacts on Vegetation LOW VERY LOW
BIODIVERSITY AND ECOSYSTEMS
Biodiversity and Terrestrial Ecosystems LOW VERY LOW
SOCIO-ECONOMIC ASPECTS
Road User Safety and Traffic MEDIUM (POSITIVE) HIGH (POSITIVE)
RECOMMENDATIONS
In light of the above, this study recommends that the proposed Improvement of the N7, Section 2 between
Rooidraai (km 7.49) and Moorreesburg (km 33.90), if authorised, be implemented with due consideration of
the recommendations outlined in this report. These mitigation measures are all considered to be feasible and
have been included in the Environmental Management Programme for the proposed project.
The key recommendations are set out below:
Construction Phase:
Land Use
• Avoid as much land acquisition outside the road reserve as far possible during the design.
• Avoid acquiring prime agricultural land (i.e. land currently under cultivations) as far as possible.
General Construction Related Impacts
• Ensure that the generation of dust is minimised by implementing a dust control programme (with due
consideration to conserving water).
• Ensure vehicles and equipment are adequately maintained and in good working order.
• Ensure that the exposed soil and material stockpiles are adequately protected against the wind.
• Ensure that vegetation clearance is kept to a minimum.
• Ensure that the generation of dust is minimised and shall implement a dust control programme (with
due consideration to conserving water).
• Ensure that the exposed soil and material stockpiles are adequately protected against the wind.
• Limit activities resulting in high noise levels (e.g. pile driving, grinding, road material loading/unloading,
hammering, excavating, etc.) to the daytime.
Freshwater Ecosystems
• Ensure the identified location-specific mitigation measures are implemented during construction in
addition to the general mitigation measures as outlined below.
• Limit work within the watercourses and wetland areas as far as possible.
• Ensure disturbed areas are rehabilitated a soon as possible.
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
viii
• Ensure construction adjacent to the watercourses and wetlands are undertaken during the drier
months of the year as far as possible.
• Ensure construction within the watercourses takes place during the no flow period (November to
March) as far as possible.
• Remove excess spoil material and solid waste and ensure it is disposed of at approved disposal waste
sites.
• Once construction is complete, rehabilitate the area to resemble that of the surrounding natural
landscape (using suitable local indigenous plants as occur at that particular area).
• Ensure that culvert and bridge structures do not concentrate the flow or alter the current watercourse
channel shape and bed level from that upstream and downstream of the road.
• Ensure that stormwater runoff from the road, particularly where there are steeper gradients, do not
lead to erosion and sedimentation of the watercourses and wetland areas.
• Ensure invasive alien plants within the road reserve are monitored, removed and disposed on an on-
going basis according to appropriate methods.
• Prevent the direct discharge of potentially contaminated runoff into the watercourses and wetland
areas.
• Store and handle all hazardous materials and waste in a suitable manner, and at least 32 m outside of
the watercourses and wetlands.
• Do not place laydown areas or stockpiles within 32 m of the watercourses and wetlands.
Vegetation
• Fence off and restrict access to the area of the Fynbos patch located at waypoint N7PM54 (S 33° 21’
37.87”; E 18° 42’ 14.02”). The working zone in this area should not exceed a distance of 3 m from the
current road edge.
• Conserve shrubby vegetation (excluding alien invasive plant species) along the route where possible.
• Disturbed areas must be seeded with Hyparrhenia hirta.
Biodiversity and Terrestrial Ecosystems
• Ensure that the above mentioned operational phase mitigation measures for freshwater ecosystems
and vegetation as described above, as well as those listed below, are implemented effectively.
• Avoid construction work during the night-time where possible.
• Instruct staff not to disturb, injure, capture or hunt any fauna.
• Ensure that collection of wood (for fire) from areas with indigenous vegetation does not take place.
• Ensure that vegetation clearance is kept to a minimum
Socio-Economic Aspects
• Ensure that the “willing buyer willing seller” model is pursued for the proposed land acquisition as far
as possible.
• Provide fair and timely compensation to landowners affected by land acquisition.
• Ensure that safe and effective traffic control is implemented during construction.
• Provide sufficient signage to warn road users of the presence of construction works and of traffic
arrangements
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
ix
• Establish a Project Liaison Committee (PLC), comprising of representatives of SANRAL, the main
contractor and members of the local community (as elected by the community).
• Ensure that procurement specifications as stipulated in the SANRAL Procurement Policy is
implemented, with a focus on project area-specific local employment.
Cultural Heritage
• If possible, avoid removing or damaging the other mature Eucalyptus trees along the route.
• The Contractor should develop and implement a cultural heritage Chance Find Procedure (with
particular focus on excavations) prior to commencement of construction. This procedure shall contain
steps on who to notify, and what to do in the event of discovering archaeological or heritage resources
(including burial grounds/graves).
Operational Phase:
Freshwater Ecosystems
• Conduct maintenance works in accordance with an approved Routine Road Maintenance Programme.
• Implement the following as part of the Routine Road Maintenance Programme:
o Minimise the spatial extent of disturbance;
o Minimise the frequency of (or requirement for) maintenance activities;
o Do not impede the movement of aquatic and riparian biota;
o Minimise alterations to flow- and sediment-capacity;
o Rehabilitate and re-vegetate disturbed areas as soon as possible;
o Clear alien invasive plant species;
o Restrict maintenance activities to the dry season where possible;
o Prevent erosion and rehabilitate eroded areas;
o Use existing access routes as far as possible;
o Store and handle all hazardous materials and waste in a suitable manner, and at least 32 m
outside of the watercourses and wetlands;
o Remove excess spoil material and solid waste and ensure it is disposed of at approved waste
disposal sites;
o Ensure maintenance activities do not lead to channelization or canalisation of the
watercourses; and
o Remove cleared woody material from the areas adjacent to the watercourse and wetlands to
prevent it being washed into the watercourses or wetlands.
Vegetation
• The Routine Road Maintenance Programme should include specifications for alien vegetation control.
Specific measures for the effective control of Acacia saligna (Port Jackson Willow) Pennisetum
setaceum (fountain grass) must be included in the programme.
• Ensure that steps are implemented during routine road maintenance to avoid blanket vegetation
clearance at the Fynbos patch located at waypoint “N7PM54”.
South African National Roads Agency SOC Ltd Basic Assessment Report for the proposed improvement of the N7, Section 2 between Rooidraai (km 7.49) and Moorreesburg (km 33.90)
720.10018.00003
January 2020
x
Biodiversity and Terrestrial Ecosystems
• Ensure that the above mentioned operational phase mitigation measures for freshwater ecosystems
and vegetation as described above, as well as those listed below, are implemented effectively.
• Implement the following during the routine road maintenance periods:
o Avoid maintenance work during the night-time where possible.
o Instruct staff not to disturb, injure, capture or hunt any fauna.
o Ensure that collection of wood (for fire) from areas with indigenous vegetation does not take
place.
o Ensure that vegetation clearance is kept to a minimum.
o Limit work within the watercourses and wetland areas as far as possible.
o Ensure maintenance work within the watercourses takes place during the no flow period
(November to March) as far as possible.
o Ensure invasive alien plants within the road reserve are monitored, removed and disposed on
an on-going basis in accordance with appropriate methods.
o Once maintenance work is complete, rehabilitate the area to resemble that of the surrounding
natural landscape (using suitable local indigenous plants as occur at that particular area).
o Prevent the direct discharge of potentially contaminated runoff into the watercourses and
wetland areas.
o Conserve shrubby vegetation (excluding alien invasive plant species) along the route where
possible.
Socio-Economic Aspects
• Ensure that the above mentioned mitigation measures for the operational phase are included in the
Routine Road Maintenance Programme and implemented effectively.
• Other than the implementation of the safety and traffic accommodation measures as indicated in the
proposed project design, no other enhancement measures have been identified.