Jerry Elliott. Lead operations analyst iso new england. System Restoration. ISO New England Operating Procedure 6. Agenda. Introduction Major Changes Questions. Introduction. Operating Procedure No.6 (OP-6 ) is being revised to: - PowerPoint PPT Presentation
Citation preview
Jerry ElliottL E A D O P E R A T I O N S A N A L Y S T I S O N E W E N G L A N D
System Restoration
ISO New England Operating Procedure 6
2
Agenda
• Introduction
• Major Changes
• Questions
3
Introduction
• Operating Procedure No.6 (OP-6) is being revised to:– Establish a separation of System Restoration concepts and
responsibilities (OP-6 revision 11) from the System Restoration Plan and technical data (new Master/Local Control Center document suite M/LCC 18)
– Reflect changes in the application of present and future resources to prioritize and support regional restoration
• NERC Reliability Standard EOP-005-2 and EOP-006-2, effective 1 July, 2013, establish new Requirements that need articulation in the stated objectives
• Document changes are intended to consolidate information, instructions and forms
4
Major Changes – Main Body
• Technical data is relocated from OP-6 and populated in a newly created M/LCC 18– Consolidation of technical data sources for ease of System Operator use/access
when required – OP-6 document suite public information remains public in transition to M/LCC 18
document suite
• Identify the restoration objectives from the Reliability Coordinator (RC) perspective to NERC Reliability Standards requirements
• Add language that articulates completion of RC restoration objectives and ongoing ISO responsibility to coordinate LCC recovery actions
• Update and enhance responsibilities for ISO, LCC and Market Participants
5
Major Changes - Appendices
• OP-6A – System Restoration Guidelines becomes:– M/LCC 18 System Restoration Plan
• OP-6B – Restoration Sequence for Establishing a 345kV Backbone after a Total System Blackout (Confidential) becomes:– M/LCC 18 Attachment A – System Restoration Flowchart (text)– M/LCC 18 Attachment B – System Restoration One-Line Diagram (graphic)
• Both M/LCC Attachments A & B Confidential and represent the Primary restoration plan
• OP-6C through F become:– M/LCC 18 Attachments C through F
• Direct transfer of the same content with same document accessibility• 345kV Line charging, Inter-LCC and Inter-Area Ties, Control Center phone
6
Major Changes - Appendices
• OP-6G – 345kV Restoration Event Log becomes:– M/LCC 18 Attachment G – Restoration Strategies
• Retains all current content and add a “Rules of Thumb” checklist for ease of use• Document classification is no longer Confidential
• Additional information not previously captured in OP-6 Appendices:– M/LCC 18 Attachments H through M
• LCC Alternatives, documents Alternate restoration plans to achieve restoration objectives if Primary plan compromised, all Confidential
– M/LCC 18 Attachment N – Synchronizing Checklist• Provides guidance on content retired from NPCC Directory 8, Appendix B
– M/LCC 18 Attachment O – Additional Designated Blackstart Resources that Support Restoration Strategies (Confidential)
– M/LCC 18 Attachment P – Restoration Voltage Limits
7