Harrisburg Overpass Construction Update January 5, 2016
Utilities Completed 3,800 LF
% Completed Installed Total
80% 3,040 LF
All Utility Work East of Union Pacific Railroad
Utilities Remaining to be Relocated East of Union Pacific Railroad
Concrete Paving East of Union Pacific Railroad
Paving Progress East of Union Pacific Railroad
All Utility Work West of Union Pacific Railroad
Utilities Completed 4,150 LF
% Completed Installed Total
85% 3,530 LF
Utilities Remaining to be Relocated West of Union Pacific Railroad
Concrete Paving West of Union Pacific Railroad
Paving Progress West of Union Pacific Railroad
Progress and Planned Activities
• Final Pavement Operations in Southeast Quadrant to start late January
• McCarthy will maintain driveways by adding crushed stone as required
• METRO/McCarthy continue to look for opportunities to compress schedule o Select construction activities will be built concurrently with major bridge activities during
the third phase of construction
• McCarthy is working extended hours to expedite completion of Phase 1
o Earthwork, Paving and Utility crews have been working 12 hour days
• McCarthy starts on drill shafts at Abutment #1 west of UPRR in mid January
10
30 Day Look Ahead
11
West of UPRR
Install remaining curb and sidewalk
Install temporary asphalt transitions from existing roadway to new concrete pavement
Seal and stripe pavement
Switch traffic to new pavement
Start drilling shafts for bridge columns
Asphalt pave permanent side street transition to new pavement
Install Phase 2 utilities
East of UPRR
Complete remaining storm sewer lines
Complete remaining sanitary sewer lines
Wet connects for water services
Complete demolition of existing pavement for new sidewalk and frontage concrete pavement
Grading, lime stabilization and placing concrete for new roadway, intersections and driveways
Install curb and sidewalk