Upload
baldwin-stephens
View
215
Download
2
Tags:
Embed Size (px)
Citation preview
January 23rd, 2008 CNGS & OPERA status Yves Déclais 1
I) CNGS status
• radiation damage on electronics• strip line repair
II) OPERA issues
Based on the work done by the CNGS/SBWG and the report given to RPC08 by I. Efthymopoulos
• proton intensity for the 2008 run• OPERA experiment status
January 23rd, 2008 CNGS & OPERA status Yves Déclais 3
CNGS Electronics - underground
Designated “radiation safe” areas for electronics
January 23rd, 2008 CNGS & OPERA status Yves Déclais 4
Ventilation Electronics - Layout
Temperature Probes
Ventilation Units
Target Chamber
Service Gallery
Proton Beam Line
…electronics equipment
Ventilation Chamber Junction gallery
January 23rd, 2008 CNGS & OPERA status Yves Déclais 5
Electronics Racks inside the Service GalleryVentilation ducts (to be moved)
January 23rd, 2008 CNGS & OPERA status Yves Déclais 6
Installed ventilation equipments
Unit 231
Ventilation duct
Service Gallery TSG4
Unit 232
TSG44
Balcony TCV4
Location of broken PLC
January 23rd, 2008 CNGS & OPERA status Yves Déclais 8
Radiation field – FLUKA simulation
Energetic (>20 MeV) hadron fluence (/cm2/yr1) for a nominal CNGS year of 4.5E19 pot
~ 107 – 109 h/yr
A.Ferrari, et. al., 2007
Location of observed failures
Can create Single Event Effects on electronics (bit flip, single event upsets...)
A fluence of ~109 h/yr would correspond to ~19 failures/yr per device
January 23rd, 2008 CNGS & OPERA status Yves Déclais 9
Radiation field – FLUKA simulation
Total dose in Gy/y for a nominal CNGS year with 4.5E19 pot
~ 0.1 – 10 Gy/y
A.Ferrari, et. al., 2007
Commercial electronics typically do not fail below 1 kRad (10 Gy)
January 23rd, 2008 CNGS & OPERA status Yves Déclais 10
Radiation field – FLUKA simulation
~ 109 – 1011 n/cm²
A.Ferrari, et. al., 2007
Commercial electronics typically do not fail below 1010 n/cm2
1 MeV eq. neutron fluence (cm-2 yr-1) for a nominal CNGS year of 4.5 E19 pot
January 23rd, 2008 CNGS & OPERA status Yves Déclais 11
Radiation effects on electronics
The ventilation electronics that failed were installed along the TSG4 gallery next to the ventilation ducts and in the TCV4 balcony
In both areas the radiation levels as predicted by the simulations are far too high for COTS componentsthe electronics should have failed and they did !
No failures to electronics in the TSG4 “safe” area were observedShould not have happened according to simulations
for the beam intensities we had, however would have happened if we were running longer...
During the 2007/2008 shutdown, work is organized to remedy the problem and assure nominal running of the facility for 2008 and beyond.
January 23rd, 2008 CNGS & OPERA status Yves Déclais 12
Actions for 2008 shutdown
General guideline:General guideline:
Move whatever is possible of the electronics out of the CNGS tunnels
For the equipment, which needs/must stay in the area: Create a “radiation-safe” area by adding adequate shielding and move all the electronics in there Address the sensitivity to radiation of the installed electronics and investigate upgrade possibilities to rad-tol components Assure a MTBF – of at least 1 year redundancy and preventive maintenance actions Install radiation monitoring system for electronics as in LHC
January 23rd, 2008 CNGS & OPERA status Yves Déclais 13
Ventilation duct layout
TCV4
TCC4
TSG4
old
TCV4
TCC4
TSG4
new
Shielding plugs
January 23rd, 2008 CNGS & OPERA status Yves Déclais 15
Status
The layout modifications will have no impact on operation and design principles of CNGS
However, access rules, procedures and dose estimates for maintenance operations need to be updated
Simulation studies are ongoing to estimate the radiation field for the electronics Preliminary results with “ideal” shielding (minimal penetrations) show a reduction of at least 104 in the high energetic hadrons, reality could be x10 lower Work is ongoing to implement the final shielding geometry as to be built.
Basically no work will be executed close to the “hot” areas in TCC4. In the rest of the areas the radiation levels are rather low.
Nevertheless, for the planning and execution of the works in-situ the same procedures as with the horn repairs will be followed
Optimization of design and execution taking into account RP and safety constraints Detailed planning of activities in parallel to dose planning Supervision of the works/workers in-situ ; use of appropriate materials for RP and waste handling
January 23rd, 2008 CNGS & OPERA status Yves Déclais 19
Tentative Schedule of the work
Very tight schedule: no contingency, 1-2 weeks to be added for beam commissioning
January 23rd, 2008 CNGS & OPERA status Yves Déclais 20
Gy/yr for a nominal CNGS year of 4.5 1019 pot
No shielding0.1 - 10
With shielding
(caveat: the option simulated in TSG41 does not include the ventilation ducts)
January 23rd, 2008 CNGS & OPERA status Yves Déclais 21
1 MeV eq. neutron fluence (cm-2 yr-1) for a nominal CNGS year of 4.5 1019 pot
No shielding 109 - 1011
With shielding
(caveat: the option simulated in TSG41 does not include the ventilation ducts)
January 23rd, 2008 CNGS & OPERA status Yves Déclais 22
Energetic (> 20 MeV) hadron fluence (cm-2 yr-1) for a nominal CNGS year of 4.5 1019 pot
No shielding108
106
With shielding
(caveat: the option simulated in TSG41 does not include the ventilation ducts)
January 23rd, 2008 CNGS & OPERA status Yves Déclais 24
TSG41 shielding : preliminary results
Fluence of high energy hadrons
Absorbed dose [Gy per particle]
simu
simu
January 23rd, 2008 CNGS & OPERA status Yves Déclais 26
Reflector flexible cable : Strip line
Failure observed only in the outer plate of the reflector The break is due to material fatigue from the mechanical & thermal effects during pulsing, most likely enhanced by the treatment during construction (brazing, etc..)
Last minute discovery before the 2007 startup Flexibles are needed to compensate for mis-alignment errors in the striplines and absorb the thermal dilation during operation
January 23rd, 2008 CNGS & OPERA status Yves Déclais 27
Reflector flexible cable : strip line
Temporary measures taken in 2007 to continue with the run:
Insulating sheets installed on the flexible section
Protects against short-circuits Installed on horn and reflector
Put an electrical by-pass in place Ensure that current still flows in case last cable breaks Installed on most outer reflector plate
In shutdown 2008: Design new flexible strip lines Replace existing ones for both horn & reflector
January 23rd, 2008 CNGS & OPERA status Yves Déclais 29
2008 run : SPS schedule
147 days max for the CNGSSpread over 23 weeks
(Nominal CNGS year : 200days)
May 29th
November 10th
January 23rd, 2008 CNGS & OPERA status Yves Déclais 30
2008 run : Super-Cycle
SPS super cycle as in the proposal
Proposed super cycle in 2008:
Extended to 39.6 sec in 2007:• 3 CNGS : 18 sec• fix target cycle 16.8 sec
(flat top 4.8 9.6 sec) • MD cycle added (4.8 sec)
Adding LHC pilot cycle: 8.4 sec super cycle = 48 sec ! tuning parameters:
o replace the LHC pilot cycle (and MD cycle ?) by CNGS cycles when LHC R&D is offo reduce the flat top for fixed target experiments to 4.8 sec
January 23rd, 2008 CNGS & OPERA status Yves Déclais 31
2008 run : expected statistics
Expected 2008 run Nominal CNGS
Number of days 147 200
Super Cycle (sec.)
48 27.6
Circulating proton
3.8 1013 4.5 1013 4.8 1013
efficiency 70% 80% 55%
Integrated pot 2.1 1019 2.9 1019 4.5 1019
Total number of interactions 2770
CC events 2070
NC events 455
Electron events 16
Charm decay 83
Tau candidate (@2.5 10-3 eV2) 1.1
Minimal granted by CERNIf no delay in the CNGS repair
~120 evts/week
January 23rd, 2008 CNGS & OPERA status Yves Déclais 32
Possible gain for the number of CNGS cycles
(A) Nominal 2008 Super Cycle 3 CNGS / 48 sec
1800 CNGS/shift 1.
(B) Reducing flat top to ~4.8 sec 3 CNGS / 43.2 sec
2000 CNGS/shift 1.11
(C) B + adding 1 CNGS cycle 4 CNGS / 49.2 sec
2341 CNGS/shift 1.30
(D) C + replacing LHC & MD by CNGS 6 CNGS / 48 sec
3600 CNGS/shift 2.00
(E) CNGS dedicated mode 1 CNGS / 6 sec
4800 CNGS/shift 2.7
Only way to increase the nb of pot and (or) compensate CNGS delay
Example of an optimized week (for OPERA):• scenario C during day shifts (working days)• scenario D during night shift and WE
Gain : ~1.7
This would imply up to ~200 evts /weekCan OPERA handle this rate ?
January 23rd, 2008 CNGS & OPERA status Yves Déclais 33
OPERA issues:
Status of the preparation of the OPERA experiment :
• Detector filling• Electronic detectors• Brick handling, processing, scanning
In 2008, our main goal is to get a full year of data taking:
First OPERA year
First candidates
January 23rd, 2008 CNGS & OPERA status Yves Déclais 34
Detector filling
Remember what was the situation one year ago !Warmest congratulations to the teams involved:
Brick components (Lead & CSd), BAM & BMSCoordinated in a Kaisen way by Salvatore
brick production/filling
020000400006000080000
100000120000140000160000180000
1 8 15 22 29 36 43 50 57 64 71 78 85 92
weeks
bri
ck
s
2 drums/day
2.5 drums/day
3 drums/day
real
154000
June 10th
July 28th
October 25th
Achieved !
Including 15% contingency (~3 weeks)
January 23rd, 2008 CNGS & OPERA status Yves Déclais 35
Electronic Detectors
SM1
VetoBMS
Target tracker
SM2
Spectrometer:XPC, HPT, RPC, magnet
all installed & commissioned DAQ validated, data transfer onto the DB implemented data analysis tools being tuned on real data !
o HPT reconstruction still to be validatedo Event reconstruction & Brick Finding:
more data needed for a complete tuning
January 23rd, 2008 CNGS & OPERA status Yves Déclais 36
Brick Handling, Processing & Scanning
This subject was the purpose of this Workshop
it was a very fruitful meeting, organized in a smart waythanks to Nakamura san, Hoshino san, Sato san & Kodama san
better to look at the summary reports from the Working groups
Recommendation:
1) Do not underestimate the amount of work for a nominal OPERA year with 5200 events this year 320 shifts to be fulfilled for the film development improving the track finding efficiency in the CSd is an issue
2) Quality control is essential during the brick processing
January 23rd, 2008 CNGS & OPERA status Yves Déclais 37
CONCLUSION
Looking forward to discuss the first Tau candidates next year in Nagoya
Keep your fingers crossed …in your mind, you need your hands for working !