65
NAMA KEGIATAN : Peningkatan Jalan dan Pembangunan Jembatan Provinsi Jawa Timur PAKET KEGIATAN : Peningkatan Jalan Bts Kab Pamekasan - Bts Kota Sumenep ( Link 232 ) KONSULTAN SUPERVISI : PT. GUBAH ALAM LESTARI KONTRAKTOR PELAKSANA : PT. DUA PUTRI KEDATON KONTRAK NOMOR : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013 S P M K NOMOR : 602.1 / 0747 / SPMK / 110 / PNK. 10 / 2013 tanggal 12 April 2013 LOKASI : PAMEKASAN URAIAN PEKERJAAN Satuan JUMLAH HARGA BOBOT WAKTU PELAKSANAAN KETERANGAN (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 12-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 14-Apr 21-Apr 28-Apr 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 8-Nov 100 1.2 Mobilisasi Ls 1.00 38,925,000.00 38,925,000.00 0.56 Rencana 0.080 0.080 0.080 0.030 0.030 0.030 0.030 0.030 0.019 0.019 0.019 0.019 0.019 0.019 0.019 0.019 0.019 0.35 Realisasi 0.080 0.081 0.084 0.101 Galian Biasa (dibuang diluar lokasi pekerjaan) M3 1,500.00 33,320.00 49,980,000.00 0.72 Rencana 0.144 0.144 0.144 0.144 0.144 2.76 Realisasi 0.03 0.310 0.207 0.437 0.587 0.603 0.580 0.000 90 Galian Perkerasan Berasphal Tanpa Cold Milling Machine M3 10.000 109,172.15 1,091,721.50 0.02 Rencana 0.005 0.005 0.005 - Realisasi Urugan pilihan M3 186.00 97,961.94 18,220,920.84 0.26 Rencana 0.087 0.087 0.087 4.09 Realisasi 0.051 0.456 0.304 0.642 0.882 0.906 0.853 0.000 80 Lapis Pondasi Agregat Klas B M3 750.00 268,760.00 201,570,000.00 2.90 Rencana 0.483 0.483 0.483 0.483 0.483 0.483 - Realisasi CTB (Lapis Pondasi Campuran Semen) M3 5,785.00 466,807.98 ### 38.81 Rencana 3.881 3.881 3.881 3.881 3.881 3.881 3.881 3.881 3.881 3.881 20.59 Realisasi 0.242 2.174 1.449 3.059 4.023 4.136 5.511 0.000 70 Lapis resap pengikat (Prime Coat) Lt 17,532.00 8,107.46 142,139,988.72 2.04 Rencana 0.204 0.204 0.204 0.204 0.204 0.204 0.204 0.204 0.204 0.204 0.93 Realisasi 0.000 0.000 0.000 0.463 0.463 0.000 Lapis perekat (Tack Coat) Lt 2,625.00 8,000.00 21,000,000.00 0.30 Rencana 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 - Realisasi 60 Aggregat untuk ATB Ton 2,021.00 403,271.77 815,012,247.17 11.71 Rencana 1.464 1.464 1.464 1.464 1.464 1.464 1.464 1.464 - Realisasi Aspal untuk ATB Ton 122.00 9,159,000.00 ### 16.06 Rencana 2.007 2.007 2.007 2.007 2.007 2.007 2.007 2.007 - Realisasi 50 Bahan Pengisi (Filler) Semen untuk ATB Kg 43,824.00 1,331.25 58,340,700.00 0.84 Rencana 0.105 0.105 0.105 0.105 0.105 0.105 0.105 0.105 - Realisasi Aggregat untuk AC ( Laston ) Ton 1,643.00 419,266.53 688,854,908.79 9.90 Rencana 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 - Realisasi 40 Aspal untuk AC (Laston) Ton 103.00 9,159,000.00 943,377,000.00 13.56 Rencana 1.506 1.506 1.506 1.506 1.506 1.506 1.506 1.506 1.506 - Realisasi Bahan Pengisi (Filler) Semen untuk AC Kg 35,706.00 1,331.25 47,533,612.50 0.68 Rencana 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076 - Realisasi 30 Pasangan Batu (material batu hitam abrasi < 40 % ) M3 23.00 474,220.00 10,907,060.00 0.16 Rencana 0.052 0.052 0.052 - Realisasi Campuran aspal panas (untuk pekerjaan minor) M3 10.000 1,955,000.00 19,550,000.00 0.28 Rencana 0.094 0.094 0.094 - Realisasi 20 Marka Jalan M2 713.00 100,000.00 71,300,000.00 1.02 Rencana 0.342 0.342 0.342 - Realisasi Patok hektometer Bh 23.00 103,740.00 2,386,020.00 0.03 Rencana 0.017 0.017 - Realisasi 10 Penebangan pohon O/ 50 - 75 cm Bh 25.00 400,000.00 10,000,000.00 0.14 Rencana 0.144 0.49 Realisasi 0.224 0.092 0.167 0.000 0.006 ` Realisasi 0 JUMLAH 62,093,290.33 ### 100.00 PPN 10 % 695,807,134.38 JUMLAH + PPN (10%) ### DIBULATKAN ### RENCANA KEMAJUAN MINGGU INI 0.00 0.080 0.080 0.080 0.030 0.174 0.179 0.749 4.928 4.893 4.806 4.568 4.568 7.683 7.683 7.736 7.736 7.736 0.000 0.000 6.280 6.280 6.299 2.723 2.723 2.723 2.723 2.740 3.081 0.360 0.360 0.000 KUMULATIF RENCANA SAMPAI DENGAN MINGGU INI - 0.00 0.080 0.160 0.241 0.271 0.445 0.624 1.373 6.301 11.194 16.000 20.568 25.136 32.819 40.502 48.238 55.973 63.709 63.709 63.709 69.989 76.269 82.568 85.291 88.013 90.736 93.459 96.198 99.280 99.640 ### ### REALISASI PEKERJAAN MINGGU INI 0.00 0.080 0.081 0.084 0.101 0.327 2.940 1.960 4.362 5.585 6.275 7.407 0.006 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 KUMULATIF REALISASI PEKERJAAN SAMPAI DENGAN MINGGU INI - 0.00 0.080 0.161 0.245 0.346 0.672 3.613 5.573 9.935 15.519 21.794 29.202 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 DEVIASI PEKERJAAN SAMPAI DENGAN MINGGU INI 0.00 0.000 0.001 0.004 0.075 0.228 2.989 4.200 3.634 4.325 5.795 8.634 4.072 -3.612 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### 0.966 3.685 3.865 3.684 2.000 2.500 -1.365 No. Item Pembayaran VOLUME KE BUTUHAN HARGA SATUAN RENCANA REALISASI "3.2.(1)b "3.2.(6)b "3.3.(2) "5.1.(2) "5.8 "6.1.(1) "6.1.(2) "6.7.(1.1) "6.7.(1.2) "6.7.(1.3) "6.8.(1.1) "6.8.(1.2) "6.8.(1.3) "7.9 "8.1.(5) "8.4.(1) "8.4.(4) "8.11(3) JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULE) SESUAI KONTRAK Dibuat Oleh : KONTRAKTOR PELAKSANA PT. DUA PUTERI KEDATONJATI ONO FAISAL KUSUMA ARIF, ST General Superintendent Diperiksa Oleh : KONSULTAN SUPERVISI PT. GUBAH ALAM LESTARI Ir. W IHARKO Site Engineer Disetujui Oleh : PEJABAT PEMBUAT KOMITMEN PENINGKATAN JALAN PAMEKASAN HEROE SOEDARMADJI BE. t NIP. 19661218 199603 1 002 APRIL M E I AGUSTUS SEPTEMBER NOPEMBE R J U N I J U L Y OKTOBER RENCANA REALISA SI

Jadwal Pelaksanaan Paket 2 Addendum

Embed Size (px)

Citation preview

Page 1: Jadwal Pelaksanaan Paket 2 Addendum

NAMA KEGIATAN : Peningkatan Jalan dan Pembangunan Jembatan Provinsi Jawa Timur PAKET KEGIATAN : Peningkatan Jalan Bts Kab Pamekasan - Bts Kota Sumenep ( Link 232 ) KONSULTAN SUPERVISI : PT. GUBAH ALAM LESTARIKONTRAKTOR PELAKSANA : PT. DUA PUTRI KEDATONKONTRAK NOMOR : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013S P M K NOMOR : 602.1 / 0747 / SPMK / 110 / PNK. 10 / 2013 tanggal 12 April 2013LOKASI : PAMEKASAN

URAIAN PEKERJAAN Satuan HARGA SATUAN JUMLAH HARGA BOBOT

WAKTU PELAKSANAAN

KETERANGAN (%)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

12-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov

14-Apr 21-Apr 28-Apr 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 8-Nov

1001.2 Mobilisasi Ls 1.00 38,925,000.00 38,925,000.00 0.56 Rencana 0.080 0.080 0.080 0.030 0.030 0.030 0.030 0.030 0.019 0.019 0.019 0.019 0.019 0.019 0.019 0.019 0.019

0.35 Realisasi 0.080 0.081 0.084 0.101

Galian Biasa (dibuang diluar lokasi pekerjaan) M3 1,500.00 33,320.00 49,980,000.00 0.72 Rencana 0.144 0.144 0.144 0.144 0.144

2.76 Realisasi 0.03 0.310 0.207 0.437 0.587 0.603 0.580 0.000 90Galian Perkerasan Berasphal Tanpa Cold Milling Machine M3 10.000 109,172.15 1,091,721.50 0.02 Rencana 0.005 0.005 0.005

- Realisasi

Urugan pilihan M3 186.00 97,961.94 18,220,920.84 0.26 Rencana 0.087 0.087 0.087 4.09 Realisasi 0.051 0.456 0.304 0.642 0.882 0.906 0.853 0.000 80

Lapis Pondasi Agregat Klas B M3 750.00 268,760.00 201,570,000.00 2.90 Rencana 0.483 0.483 0.483 0.483 0.483 0.483

- Realisasi

CTB (Lapis Pondasi Campuran Semen) M3 5,785.00 466,807.98 2,700,484,164.30 38.81 Rencana 3.881 3.881 3.881 3.881 3.881 3.881 3.881 3.881 3.881 3.881

20.59 Realisasi 0.242 2.174 1.449 3.059 4.023 4.136 5.511 0.000 70Lapis resap pengikat (Prime Coat) Lt 17,532.00 8,107.46 142,139,988.72 2.04 Rencana 0.204 0.204 0.204 0.204 0.204 0.204 0.204 0.204 0.204 0.204

0.93 Realisasi 0.000 0.000 0.000 0.463 0.463 0.000

Lapis perekat (Tack Coat) Lt 2,625.00 8,000.00 21,000,000.00 0.30 Rencana 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022 0.022

- Realisasi 60Aggregat untuk ATB Ton 2,021.00 403,271.77 815,012,247.17 11.71 Rencana 1.464 1.464 1.464 1.464 1.464 1.464 1.464 1.464

- Realisasi

Aspal untuk ATB Ton 122.00 9,159,000.00 1,117,398,000.00 16.06 Rencana 2.007 2.007 2.007 2.007 2.007 2.007 2.007 2.007

- Realisasi 50Bahan Pengisi (Filler) Semen untuk ATB Kg 43,824.00 1,331.25 58,340,700.00 0.84 Rencana 0.105 0.105 0.105 0.105 0.105 0.105 0.105 0.105

- Realisasi

Aggregat untuk AC ( Laston ) Ton 1,643.00 419,266.53 688,854,908.79 9.90 Rencana 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100 1.100

- Realisasi 40Aspal untuk AC (Laston) Ton 103.00 9,159,000.00 943,377,000.00 13.56 Rencana 1.506 1.506 1.506 1.506 1.506 1.506 1.506 1.506 1.506

- Realisasi

Bahan Pengisi (Filler) Semen untuk AC Kg 35,706.00 1,331.25 47,533,612.50 0.68 Rencana 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076 0.076

- Realisasi 30Pasangan Batu (material batu hitam abrasi < 40 % ) M3 23.00 474,220.00 10,907,060.00 0.16 Rencana 0.052 0.052 0.052

- Realisasi

Campuran aspal panas (untuk pekerjaan minor) M3 10.000 1,955,000.00 19,550,000.00 0.28 Rencana 0.094 0.094 0.094

- Realisasi 20Marka Jalan M2 713.00 100,000.00 71,300,000.00 1.02 Rencana 0.342 0.342 0.342

- Realisasi

Patok hektometer Bh 23.00 103,740.00 2,386,020.00 0.03 Rencana 0.017 0.017

- Realisasi 10Penebangan pohon O/ 50 - 75 cm Bh 25.00 400,000.00 10,000,000.00 0.14 Rencana 0.144

0.49 Realisasi 0.224 0.092 0.167 0.000 0.006

`Realisasi

0JUMLAH 62,093,290.33 6,958,071,343.82 100.00PPN 10 % 695,807,134.38JUMLAH + PPN (10%) 7,653,878,478.20DIBULATKAN 7,653,878,000.00RENCANA KEMAJUAN MINGGU INI 0.00 0.080 0.080 0.080 0.030 0.174 0.179 0.749 4.928 4.893 4.806 4.568 4.568 7.683 7.683 7.736 7.736 7.736 0.000 0.000 6.280 6.280 6.299 2.723 2.723 2.723 2.723 2.740 3.081 0.360 0.360 0.000KUMULATIF RENCANA SAMPAI DENGAN MINGGU INI - 0.00 0.080 0.160 0.241 0.271 0.445 0.624 1.373 6.301 11.194 16.000 20.568 25.136 32.819 40.502 48.238 55.973 63.709 63.709 63.709 69.989 76.269 82.568 85.291 88.013 90.736 93.459 96.198 99.280 99.640 100.000 100.000REALISASI PEKERJAAN MINGGU INI 0.00 0.080 0.081 0.084 0.101 0.327 2.940 1.960 4.362 5.585 6.275 7.407 0.006 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000KUMULATIF REALISASI PEKERJAAN SAMPAI DENGAN MINGGU INI - 0.00 0.080 0.161 0.245 0.346 0.672 3.613 5.573 9.935 15.519 21.794 29.202 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207 29.207DEVIASI PEKERJAAN SAMPAI DENGAN MINGGU INI 0.00 0.000 0.001 0.004 0.075 0.228 2.989 4.200 3.634 4.325 5.795 8.634 4.072 -3.612 -11.295 -19.030 -26.766 -34.501 -34.501 -34.501 -40.782 -47.062 -53.361 -56.083 -58.806 -61.529 -64.251 -66.991 -70.072 -70.432 -70.793 -70.793

### 0.966 3.6853.865 3.6842.0002.500

-1.365

No. Item Pembayaran

VOLUME KE BUTUHAN

REN

CA

NA

REA

LISA

SI

"3.2.(1)b

"3.2.(6)b

"3.3.(2)

"5.1.(2)

"5.8

"6.1.(1)

"6.1.(2)

"6.7.(1.1)

"6.7.(1.2)

"6.7.(1.3)

"6.8.(1.1)

"6.8.(1.2)

"6.8.(1.3)

"7.9

"8.1.(5)

"8.4.(1)

"8.4.(4)

"8.11(3)

JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULE)SESUAI KONTRAK

Dibuat Oleh: KONTRAKTOR PELAKSANA

PT. DUA PUTERI KEDATONJATI ONO

FAISAL KUSUMA ARIF, STGeneral Superintendent

Diperiksa Oleh: KONSULTAN SUPERVISI

PT. GUBAH ALAM LESTARI

Ir. WIHARKOSite Engineer

Disetujui Oleh: PEJABAT PEMBUAT KOMITMEN

PENINGKATAN JALAN PAMEKASAN

HEROE SOEDARMADJI BE.tNIP. 19661218 199603 1 002

APRIL M E I AGUSTUS SEPTEMBER NOPEMBERJ U N I J U L Y OKTOBER

RENCANA

REALISASI

Page 2: Jadwal Pelaksanaan Paket 2 Addendum

NAMA KEGIATAN : Peningkatan Jalan dan Pembangunan Jembatan Provinsi Jawa Timur PAKET KEGIATAN : Peningkatan Jalan Bts Kab Pamekasan - Bts Kota Sumenep ( Link 232 ) KONSULTAN SUPERVISI : PT. GUBAH ALAM LESTARIKONTRAKTOR PELAKSANA : PT. DUA PUTRI KEDATONKONTRAK NOMOR : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013S P M K NOMOR : 602.1 / 0747 / SPMK / 110 / PNK. 10 / 2013 tanggal 12 April 2013LOKASI : PAMEKASAN

URAIAN PEKERJAAN Satuan JUMLAH HARGA BOBOT

WAKTU PELAKSANAAN

KETERANGAN (%)

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

12-Apr 15-Apr 22-Apr 29-Apr 6-May 13-May 20-May 27-May 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov

14-Apr 21-Apr 28-Apr 5-May 12-May 19-May 26-May 2-Jun 9-Jun 16-Jun 23-Jun 30-Jun 7-Jul 14-Jul 21-Jul 28-Jul 4-Aug 11-Aug 18-Aug 25-Aug 1-Sep 8-Sep 15-Sep 22-Sep 29-Sep 6-Oct 13-Oct 20-Oct 27-Oct 3-Nov 8-Nov

1001.2 Mobilisasi Ls 1.00 38,925,000.00 38,925,000.00 0.56 Rencana 0.080 0.080 0.080 0.030 0.030 0.030 0.030 0.030 0.019 0.019 0.019 0.019 0.019 0.019 0.019 0.019 0.019

0.35 Realisasi 0.080 0.081 0.084 0.101

Galian Biasa (dibuang diluar lokasi pekerjaan) M3 5,762.10 33,320.00 191,993,172.00 2.76 Rencana 0.552 0.552 0.552 0.552 0.552

2.76 Realisasi 0.03 0.310 0.207 0.437 0.587 0.603 0.580 0.000 90Galian Perkerasan Berasphal Tanpa Cold Milling Machine M3 25.000 109,172.15 2,729,303.75 0.04 Rencana 0.013 0.013 0.013

0.04 Realisasi 0.039

Urugan pilihan M3 2,952.90 97,961.94 289,271,812.63 4.16 Rencana 1.386 1.386 1.386 4.09 Realisasi 0.051 0.456 0.304 0.642 0.882 0.906 0.853 0.000 80

Lapis Pondasi Agregat Klas B M3 765.00 268,760.00 205,601,400.00 2.95 Rencana 0.492 0.492 0.492 0.492 0.492 0.492

- Realisasi

CTB (Lapis Pondasi Campuran Semen) M3 3,069.60 466,807.98 1,432,913,775.41 20.59 Rencana 2.059 2.059 2.059 2.059 2.059 2.059 2.059 2.059 2.059 2.059

20.59 Realisasi 0.242 2.174 1.449 3.059 4.023 4.136 5.511 0.000 70Lapis resap pengikat (Prime Coat) Lt 10,233.00 8,107.46 82,963,638.18 1.19 Rencana 0.119 0.119 0.119 0.119 0.119 0.119 0.119 0.119 0.119 0.119

0.93 Realisasi 0.463 0.463 0.000

Lapis perekat (Tack Coat) Lt 7,434.00 8,000.00 59,472,000.00 0.85 Rencana 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061

0.29 Realisasi 0.146 0.146 0.000 60Aggregat untuk ATB Ton 2,662.77 403,271.77 1,073,819,971.00 15.43 Rencana 1.929 1.929 1.929 1.929 1.929 1.929 1.929 1.929

11.01 Realisasi 5.504 5.504

Aspal untuk ATB Ton 176.56 9,159,000.00 1,617,113,040.00 23.24 Rencana 2.905 2.905 2.905 2.905 2.905 2.905 2.905 2.905

16.56 Realisasi 8.282 8.282 50Bahan Pengisi (Filler) Semen untuk ATB Kg 54,994.10 1,331.25 73,210,895.63 1.05 Rencana 0.132 0.132 0.132 0.132 0.132 0.132 0.132 0.132

0.75 Realisasi 0.375 0.375

Aggregat untuk AC ( Laston ) Ton 1,639.22 419,266.53 687,270,081.31 9.88 Rencana 1.097 1.097 1.097 1.097 1.097 1.097 1.097 1.097 1.097

- Realisasi 40Aspal untuk AC (Laston) Ton 104.83 9,159,000.00 960,137,970.00 13.80 Rencana 1.533 1.533 1.533 1.533 1.533 1.533 1.533 1.533 1.533

- Realisasi

Bahan Pengisi (Filler) Semen untuk AC Kg 33,781.88 1,331.25 44,972,127.75 0.65 Rencana 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072 0.072

- Realisasi 30Pasangan Batu (material batu hitam abrasi < 40 % ) M3 67.02 474,220.00 31,782,224.40 0.46 Rencana 0.152 0.152 0.152

- Realisasi

Campuran aspal panas (untuk pekerjaan minor) M3 25.000 1,955,000.00 48,875,000.00 0.70 Rencana 0.234 0.234 0.234

0.70 Realisasi 0.70 20Marka Jalan M2 809.82 100,000.00 80,982,000.00 1.16 Rencana 0.388 0.388 0.388

- Realisasi

Patok hektometer Bh 25.00 103,740.00 2,593,500.00 0.04 Rencana 0.019 0.019

- Realisasi 10Penebangan pohon O/ 50 - 75 cm Bh 84.00 400,000.00 33,600,000.00 0.48 Rencana 0.483

0.48 Realisasi 0.224 0.092 0.167 0.000 0.000

`Realisasi

0JUMLAH 62,093,290.33 6,958,226,912.05 100.00PPN 10 % 695,822,691.20JUMLAH + PPN (10%) 7,654,049,603.25DIBULATKAN 7,654,049,000.00RENCANA KEMAJUAN MINGGU INI 0.00 0.080 0.080 0.080 0.030 0.582 0.595 2.473 4.886 4.843 3.388 2.671 2.671 7.205 7.205 7.357 7.357 7.357 0.000 0.000 7.729 7.729 7.748 2.782 2.782 2.782 2.782 2.801 3.189 0.407 0.407 0.000KUMULATIF RENCANA SAMPAI DENGAN MINGGU INI - 0.00 0.080 0.160 0.241 0.271 0.853 1.448 3.921 8.807 13.650 17.038 19.709 22.380 29.585 36.790 44.148 51.505 58.863 58.863 58.863 66.592 74.321 82.069 84.851 87.633 90.415 93.197 95.998 99.187 99.593 100.000 100.000REALISASI PEKERJAAN MINGGU INI 0.00 0.080 0.081 0.084 0.101 0.327 2.940 1.960 4.362 6.325 20.583 21.715 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000KUMULATIF REALISASI PEKERJAAN SAMPAI DENGAN MINGGU INI - 0.00 0.080 0.161 0.245 0.346 0.672 3.613 5.573 9.935 16.260 36.843 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559 58.559DEVIASI PEKERJAAN SAMPAI DENGAN MINGGU INI 0.00 0.000 0.001 0.004 0.075 -0.180 2.165 1.651 1.127 2.610 19.805 38.850 36.179 28.973 21.768 14.411 7.053 -0.304 -0.304 -0.304 -8.033 -15.762 -23.510 -26.292 -29.074 -31.857 -34.639 -37.439 -40.628 -41.035 -41.441 -41.441

5,701,568,000.00 0.966 3.6853.865 3.6842.0002.500

-1.365

No. Item Pembayaran

VOLUME KE BUTUHAN

HARGA SATUAN

REN

CA

NA

REA

LISA

SI

"3.2.(1)b

"3.2.(6)b

"3.3.(2)

"5.1.(2)

"5.8

"6.1.(1)

"6.1.(2)

"6.7.(1.1)

"6.7.(1.2)

"6.7.(1.3)

"6.8.(1.1)

"6.8.(1.2)

"6.8.(1.3)

"7.9

"8.1.(5)

"8.4.(1)

"8.4.(4)

"8.11(3)

JADWAL PELAKSANAAN PEKERJAAN (TIME SCHEDULE)SESUAI ADDENDUM

Dibuat Oleh: KONTRAKTOR PELAKSANA

PT. DUA PUTERI KEDATONJATI ONO

FAISAL KUSUMA ARIF, STGeneral Superintendent

Diperiksa Oleh: KONSULTAN SUPERVISI

PT. GUBAH ALAM LESTARI

Ir. WIHARKOSite Engineer

Disetujui Oleh: PEJABAT PEMBUAT KOMITMEN

PENINGKATAN JALAN PAMEKASAN

HEROE SOEDARMADJI BE.tNIP. 19661218 199603 1 002

APRIL M E I AGUSTUS SEPTEMBER NOPEMBERJ U N I J U L Y OKTOBER

RENCANA

REALISASI

Page 3: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC1

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 1Tanggal : 12 s/d 14 April 2013

U R A I A N SAT HARGA SATUANKONTRAK

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.000 38,925,000.00 0.56 0.00 0.14 0.14 0.00 0.08 0.08

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 1,500.000 49,980,000.00 0.72 0.00 0.00 0.00 0.00 0.00 0.003.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 10.000 1,091,721.50 0.02 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 186.000 18,220,920.84 0.26 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 750.000 201,570,000.00 2.90 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 5,785.000 2,700,484,164.30 38.81 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 17,532.000 142,139,988.72 2.04 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 2,625.000 21,000,000.00 0.30 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,021.000 815,012,247.17 11.71 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 122.000 1,117,398,000.00 16.06 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 43,824.000 58,340,700.00 0.84 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,643.000 688,854,908.79 9.90 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 103.000 943,377,000.00 13.56 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 35,706.000 47,533,612.50 0.68 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 23.000 10,907,060.00 0.16 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 10.000 19,550,000.00 0.28 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 713.000 71,300,000.00 1.02 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 23.000 2,386,020.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 25.000 10,000,000.00 0.14 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 6,958,071,343.82 100.00 0.00 0.08 0.08 RENCANA KEMAJUAN TERHADAP MC 0.08 DEVIASI 0.00

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 4: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC1

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 2Tanggal : 15 s/d 21 April 2013

U R A I A N SAT HARGA SATUANKONTRAK

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.000 38,925,000.00 0.56 0.14 0.15 0.29 0.08 0.08 0.16

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 1,500.000 49,980,000.00 0.72 0.00 0.00 0.00 0.00 0.00 0.003.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 10.000 1,091,721.50 0.02 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 186.000 18,220,920.84 0.26 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 750.000 201,570,000.00 2.90 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 5,785.000 2,700,484,164.30 38.81 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 17,532.000 142,139,988.72 2.04 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 2,625.000 21,000,000.00 0.30 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,021.000 815,012,247.17 11.71 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 122.000 1,117,398,000.00 16.06 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 43,824.000 58,340,700.00 0.84 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,643.000 688,854,908.79 9.90 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 103.000 943,377,000.00 13.56 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 35,706.000 47,533,612.50 0.68 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 23.000 10,907,060.00 0.16 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 10.000 19,550,000.00 0.28 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 713.000 71,300,000.00 1.02 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 23.000 2,386,020.00 0.03 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 25.000 10,000,000.00 0.14 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 6,958,071,343.82 100.00 0.08 0.08 0.16 RENCANA KEMAJUAN TERHADAP MC 0.00 DEVIASI 0.16

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 5: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC2

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 3Tanggal : 22 s/d 28 April 2013

U R A I A N SAT HARGA SATUANCCO

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.29 0.150 0.44 0.16 0.08 0.25

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 0.00 0.00 0.00 0.00 0.00 0.003.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 6,958,071,340.88 100.00 0.16 0.08 0.25 RENCANA KEMAJUAN TERHADAP MC 0.00 DEVIASI 0.25

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 6: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-2

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 4Tanggal : 29 s/d 05 Mei 2013

U R A I A N SAT HARGA SATUANCCO

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.44 0.180 0.62 0.25 0.10 0.35

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 0.00 0.00 0.00 0.00 0.00 0.003.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 6,958,071,340.88 100.00 0.25 0.10 0.35 RENCANA KEMAJUAN TERHADAP MC 0.00 DEVIASI 0.35

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 7: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-2

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 5Tanggal : 06 s/d 12 Mei 2013

U R A I A N SAT HARGA SATUANCCO

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.62 0.00 0.62 0.35 0.00 0.35

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 0.00 72.00 72.00 0.00 0.03 0.033.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 0.00 36.00 36.00 0.00 0.05 0.05

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 0.00 36.00 36.00 0.00 0.24 0.24

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 6,958,071,340.88 100.00 0.35 0.33 0.67 RENCANA KEMAJUAN TERHADAP MC 0.44 DEVIASI 0.23

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 8: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-2

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 6Tanggal : 13 s/d 19 Mei 2013

U R A I A N SAT HARGA SATUANCCO

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.62 0.00 0.62 0.35 0.00 0.35

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 72.00 648.00 720.00 0.03 0.31 0.343.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 36.00 324.00 360.00 0.05 0.46 0.51

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 36.00 324.00 360.00 0.24 2.17 2.42

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 6,958,071,340.88 100.00 0.67 2.94 3.61 RENCANA KEMAJUAN TERHADAP MC 0.62 DEVIASI 2.99

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 9: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-2

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 7Tanggal : 20 Mei s/d 26 Mei 2013

U R A I A N SAT HARGA SATUANCCO

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.62 0.00 0.62 0.35 0.00 0.35

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 720.00 432.00 1,152.00 0.34 0.21 0.553.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 360.00 216.00 576.00 0.51 0.30 0.81

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 360.00 216.00 576.00 2.42 1.45 3.86

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 0 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH 6,958,071,340.88 100.00 3.61 1.96 5.57 RENCANA KEMAJUAN TERHADAP MC 1.37 DEVIASI 4.20

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 10: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-3

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 8Tanggal : 27 Mei s/d 02 Juni 2013

U R A I A N SAT HARGA SATUANADDENDUM

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.62 0.00 0.62 0.35 0.00 0.3457

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 1,152.00 912.00 2,064.00 0.55 0.44 0.993.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 0.00 0.00 0.00 0.00 0.00 0.003.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 576.00 456.00 1,032.00 0.81 0.64 1.45

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 576.00 456.00 1,032.00 3.86 3.06 6.92

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 0.00 0.00 0.00 0.008.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 0.00 39.00 39.00 0.00 0.22 0.22

JUMLAH 6,958,071,340.88 100.00 5.57 4.36 9.93 RENCANA KEMAJUAN TERHADAP MC 8.81 DEVIASI 1.13

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 11: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-3

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 9Tanggal : 03 s/d 09 Juni 2013

U R A I A N SAT HARGA SATUANADDENDUM

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.62 0.00 0.62 0.35 0.00 0.35

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 2,064.00 1,226.25 3,290.25 0.99 0.59 1.583.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 0.00 24.97 24.97 0.00 0.04 0.043.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 1,032.00 626.55 1,658.55 1.45 0.88 2.34

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 1,032.00 599.70 1,631.70 6.92 4.02 10.95

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 0.00 0.00 0.00 0.00 0.006.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 0.00 0.00 0.00 0.00 0.00

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 0.00 0.00 0.00 0.00 0.006.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 0.00 0.00 0.00 0.00 0.006.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 24.97 0.00 0.00 0.70 0.708.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 39.00 16.00 55.00 0.22 0.09 0.32

JUMLAH 6,958,071,340.88 100.00 9.93 6.33 16.26 RENCANA KEMAJUAN TERHADAP MC 13.65 DEVIASI 2.61

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 12: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-3

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 10Tanggal : 10 s/d 16 Juni 2013

U R A I A N SAT HARGA SATUANADDENDUM

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.62 0.00 0.62 0.35 0.00 0.35

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 3,290.25 1,259.85 4,550.10 1.58 0.60 2.183.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 24.97 0.00 24.97 0.04 0.00 0.043.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 1,658.55 643.35 2,301.90 2.34 0.91 3.24

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 1,631.70 616.50 2,248.20 10.95 4.14 15.08

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 0.00 3,974.61 3,974.61 0.00 0.46 0.466.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 0.00 1,270.97 1,270.97 0.00 0.15 0.15

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 0.00 949.74 949.74 0.00 5.50 5.506.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 0.00 62.92 62.92 0.00 8.28 8.286.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 0.00 19,614.36 19,614.36 0.00 0.38 0.386.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 0.00 0.70 0.00 0.708.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 55.00 29.00 84.00 0.32 0.17 0.48

JUMLAH 6,958,071,340.88 100.00 16.26 20.58 36.84 RENCANA KEMAJUAN TERHADAP MC 17.04 DEVIASI 19.81

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 13: Jadwal Pelaksanaan Paket 2 Addendum

REKAPITULASI LAPORAN MINGGUANREALISASI LAPANGAN SESUAI BACK UP MC-3

Pekerjaan : PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)Nomor Kontrak : 602.1 / 0721 / KTR / 110 / PNK. 10 / 2013 tanggal 5 April 2013Kontraktor : PT.DUA PUTRI KEDATONKonsultan : PT. GUBAH ALAM LESTARITahun Anggaran : 2013Nilai Kontrak Awal : Rp. 7,653,878,000.00 Minggu : 11Tanggal : 17 s/d 23 Juni 2013

U R A I A N SAT HARGA SATUANADDENDUM

KEMAJUAN PEKERJAANVOLUME PROGRES (%)

VOLUME JUMLAH HARGA (Rp) BOBOT (%) MINGGU LALU MINGGU INI MINGGU LALU MINGGU INI

DIVISI 1. UMUM1.2 Mobilisasi Ls 38,925,000.00 1.00 38,925,000.00 0.56 0.62 0.00 0.62 0.35 0.00 0.35

DIVISI 3. PEKERJAAN TANAH3.2(1)a Galian Biasa 33,320.00 5,762.10 191,993,172.00 2.76 4,550.10 1,212.00 5,762.10 2.18 0.58 2.763.2(7) Galian Perkerasan Aspal Tanpa Cold Milling Machine 109,172.15 24.97 2,726,028.59 0.04 24.97 0.00 24.97 0.04 0.00 0.043.3(2) Urugan Pilihan 97,961.94 2,952.90 289,271,812.63 4.16 2,301.90 606.00 2,907.90 3.24 0.85 4.09

DIVISI 5. PEKERJAAN BERBUTIR

5.1(2) Lapis pondasi agregat kelas B 268,760.00 765.00 205,601,400.00 2.95 0.00 0.00 0.00 0.00 0.00 0.005.8(1) Lapis Pondasi Agregat dengan Cement Treated Based (CTB) 466,807.98 3,069.60 1,432,913,775.41 20.59 2,248.20 821.40 3,069.60 15.08 5.51 20.59

DIVISI 6. PERKERASAN ASPAL6.1(1) Lapis Resap Pengikat Ltr 8,107.46 10,232.84 82,962,340.99 1.19 3,974.61 3,974.61 7,949.22 0.46 0.46 0.936.1(2) Lapis Perekat Ltr 8,000.00 7,434.00 59,472,000.00 0.85 1,270.97 1,270.97 2,541.94 0.15 0.15 0.29

6.7 (1.1) Agregat Untuk ATB (Laston Atas) Ton 403,271.77 2,662.77 1,073,819,971.00 15.43 949.74 949.74 1,899.48 5.50 5.50 11.016.7 (1.2) Aspal Untuk ATB (Laston Atas) Ton 9,159,000.00 176.55 1,617,021,450.00 23.24 62.92 62.92 125.84 8.28 8.28 16.566.7 (1.3) Bahan Pengisi Filler,semen Untuk ATB (Laston Atas) Kg 1,331.25 54,993.53 73,210,136.81 1.05 19,614.36 19,614.36 39,228.72 0.38 0.38 0.756.8(1.1) Agregat Untuk AC (Laston Atas) Ton 419,266.53 1,639.22 687,270,081.31 9.88 0.00 0.00 0.00 0.00 0.00 0.006.8(1.2) Aspal Untuk AC (Laston Atas) Ton 9,159,000.00 104.83 960,137,970.00 13.80 0.00 0.00 0.00 0.00 0.00 0.006.8(1.3) Bahan Pengisi Filler,semen Untuk AC (Laston Atas) Kg 1,331.25 33,781.88 44,972,127.75 0.65 0.00 0.00 0.00 0.00 0.00 0.00

DIVI 7. STRUKTUR7.10 Pasangan Batu (Material Batu Hitam Abrasi < 40%) 474,220.00 67.02 31,782,224.40 0.46 0.00 0.00 0.00 0.00 0.00 0.00

DIVISI 10. PENGEMBALIAN KONDISI DAN PEK. MINOR8.1(5) Campuran aspal panas (untuk pekerjaan minor) 1,955,000.00 24.97 48,816,350.00 0.70 0.00 0.00 24.97 0.70 0.00 0.708.4(1) Marka Jalan M2 100,000.00 809.82 80,982,000.00 1.16 0.00 0.00 0.00 0.00 0.00 0.008.4(4) Patok Hektometer Bh 103,740.00 25.00 2,593,500.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00

8.11(3) Penebangan Pohon Ø 50 - 75 Cm Bh 400,000.00 84.00 33,600,000.00 0.48 84.00 0.00 84.00 0.48 0.00 0.48

JUMLAH 6,958,071,340.88 100.00 36.84 21.72 58.56 RENCANA KEMAJUAN TERHADAP MC 19.71 DEVIASI 38.85

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :BINA MARGA Konsultan Supervisi PENYEDIA JASA

PROJECT OFFICER PT. DUA PUTRI KEDATON

ZAINAL FATAH HERLAMBANG SUSETYO, ST FAISAL KUSUMA ARIF, STNIP. 19660222 200801 1 005 Chief Inspector General Superintendent

MATA PEMBA- YARAN S/D MINGGU

INIS/D MINGGU

INI

M3

M3

M3

M3

M3

M3

M3

Page 14: Jadwal Pelaksanaan Paket 2 Addendum

ACTUAL CEK LAPANGAN

Kegiatan :PPK :Nama Paket:Lokasi Pake:

No.Item

Pembayaran

a

DIVISI 1. UMUM

1.2

JUMLAH HARGA BAB 1

DIVISI 3. PEKERJAAN TANAH

3.2(1)a 3.2(8) 3.3(2)

JUMLAH HARGA BAB 3

DIVISI 5. PERKERASAN BERBUTIR

5.1(2) 5.8(1)

JUMLAH HARGA BAB 5

DIVISI 6. PERKERASAN ASPAL

6.1(1) 6.1(2)

Page 15: Jadwal Pelaksanaan Paket 2 Addendum

6.7(1.1) 6.7(1.2) 6.7(1.3) 6.8(1.1) 6.8(1.2) 6.8(1.3)

JUMLAH HARGA BAB 6

DIVISI 7. STRUKTUR

7.10

JUMLAH HARGA BAB 7

8.1(5) 8.4(1) 8.4(4) 8.11(3)

JUMLAH HARGA BAB 8

JUMLAH

PPN 10 %

TOTAL KONTRAK

DIBULATKAN

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

Page 16: Jadwal Pelaksanaan Paket 2 Addendum
Page 17: Jadwal Pelaksanaan Paket 2 Addendum

ACTUAL CEK LAPANGAN

PENINGKATAN JALAN DAN PEMBANGUNAN JEMBATAN PROPINSI JAWA TIMURPENINGKATAN JALAN PAMEKASANPENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)KABUPATEN PAMEKASAN

URAIAN Satuan

b c

DIVISI 1. UMUM

Mobilisasi Ls

JUMLAH HARGA BAB 1

DIVISI 3. PEKERJAAN TANAH

Galian biasa (dibuang diluar lokasi pekerjaan) M3 Galian perkerasan beraspal tanpa cold milling machine M3 Urugan pilihan M3

JUMLAH HARGA BAB 3

DIVISI 5. PERKERASAN BERBUTIR

Lapis pondasi agregat kelas B M³Lapis pondasi agregat dengan cement treated base (CTB) M³

JUMLAH HARGA BAB 5

DIVISI 6. PERKERASAN ASPAL

Lapis resap pengikat (Prime Coat) Ltr Lapis perekat (Tack Coat) Ltr

Page 18: Jadwal Pelaksanaan Paket 2 Addendum

Agregat untuk ATB (Laston Atas) Ton Aspal untuk ATB (Laston Atas) Ton Bahan pengisi (filler), semen untuk ATB (Laston Atas) Kg Agregat untuk AC ( Laston ) Ton Aspal untuk AC ( Laston ) Ton Bahan pengisi (filler), semen untuk AC ( Laston ) Kg

JUMLAH HARGA BAB 6

DIVISI 7. STRUKTUR

Pasangan Batu ( Material Batu Hitam Abrasi <40%) M3

JUMLAH HARGA BAB 7

Campuran aspal panas (untuk pekerjaan minor) M3 Marka jalan M2 Patok hektometer Bh Penebangan pohon Ø 50 - 75 cm Bh Penanaman pohon kembali Bh

JUMLAH HARGA BAB 8

JUMLAH

PPN 10 %

TOTAL KONTRAK

DIBULATKAN

DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR

Page 19: Jadwal Pelaksanaan Paket 2 Addendum

Mengetahui :PEJABAT PEMBUAT KOMITMEN

PENINGKATAN JALAN PAMEKASAN

Heroe Soedarmadji, BENIP. 19661218 199603 1 002

Page 20: Jadwal Pelaksanaan Paket 2 Addendum

ACTUAL CEK LAPANGAN

PENINGKATAN JALAN DAN PEMBANGUNAN JEMBATAN PROPINSI JAWA TIMUR

PENINGKATAN JALAN BATAS KAB. PAMEKASAN - BATAS KOTA SUMENEP (LINK 232)

Harga KONTRAK ASAL REKAYASA LAPANGANSatuan

VolumeJumlah Harga Bobot

Volume(Rp) (Rp) (%)

d e f g

38,925,000.00 1.00 38,925,000.00 0.56

38,925,000.00

33,320.00 1,500.00 49,980,000.00 0.72 648.00 109,172.15 10.00 1,091,721.50 0.02 - 97,961.94 186.00 18,220,920.84 0.26 324.00

69,292,642.34

268,760.00 750.00 201,570,000.00 2.90 - 466,807.98 5,785.00 2,700,484,164.30 38.81 324.00

2,902,054,164.30

8,107.46 17,532.00 142,139,988.72 2.04 - 8,000.00 2,625.00 21,000,000.00 0.30

Page 21: Jadwal Pelaksanaan Paket 2 Addendum

403,271.77 2,021.00 815,012,247.17 11.71 9,159,000.00 122.00 1,117,398,000.00 16.06 1,331.25 43,824.00 58,340,700.00 0.84 419,266.53 1,643.00 688,854,908.79 9.90 9,159,000.00 103.00 943,377,000.00 13.56 1,331.25 35,706.00 47,533,612.50 0.68

3,833,656,457.18

474,220.00 23.00 10,907,060.00 0.16

10,907,060.00

1,955,000.00 10.00 19,550,000.00 0.28 100,000.00 713.00 71,300,000.00 1.02 103,740.00 23.00 2,386,020.00 0.03 400,000.00 25.00 10,000,000.00 0.14 200,000.00

103,236,020.00

6,958,071,343.82 100.00

695,807,134.38

7,653,878,478.20

7,653,878,000.00

Page 22: Jadwal Pelaksanaan Paket 2 Addendum

Diperiksa Oleh : Dibuat Oleh :KONSULTAN PENGAWAS PENYEDIA JASA

PT. GUBAH ALAM LESTARI PT. DUA PUTRI KEDATON

Ir. WIHARKO FAISAL KUSUMA ARIF, STSite Engineer General Superintendent

Page 23: Jadwal Pelaksanaan Paket 2 Addendum

ACTUAL CEK LAPANGAN

REKAYASA LAPANGANJumlah Harga Bobot

(Rp) (%)

- -

-

21,591,360.00 0.31 - - 31,739,668.56 0.46

53,331,028.56

- - 151,245,785.52 2.17

151,245,785.52

- - - -

Page 24: Jadwal Pelaksanaan Paket 2 Addendum

- - - - - - - - - - - -

-

- -

-

- - - - - - - - - -

-

204,576,814.08 2.94

20,457,681.41

225,034,495.49

225,034,000.00

Pamekasan, 2013

Page 25: Jadwal Pelaksanaan Paket 2 Addendum

Dibuat Oleh :Dibuat Oleh :PENYEDIA JASAPENYEDIA JASA

PT. DUA PUTRI KEDATONPT. DUA PUTRI KEDATON ###

###

FAISAL KUSUMA ARIF, STFAISAL KUSUMA ARIF, STGeneral SuperintendentGeneral Superintendent

Page 26: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

NO PEKERJAAN VOLUME

p L 1 Galian biasa pelebaran 75.00 x 1.60 x

Galian biasa raising - x 1.60 xGalian biasa (rekondisi) - x 1.00 x

2 Galian perker beraspal tanpa cold milling machine 100.00 x 2.00 x

3 Galian Batu - x 1.10 x

4 Urugan pilihan (Pelebaran) tanpa raising 75.00 x 1.60 xUrugan pilihan (Pelebaran) dengan raising - 1.60 xUrugan pilihan (bahu jalan) - x 1.00 xUrugan pilihan (Rising) - x 1.00 xUrugan Pilihan (Tiang Pancang) - x 3.00 x

Urugan pilihan (Pas. Batu) - x 1.25 x

- x 0.80 x

5 Lapis pondasi agregat dengan (CTB) Pelebaran 75.00 x 1.60 xLapis pondasi agregat dengan (CTB) Pelebaran - x 1.60 x

7 Prime Coat - x 1.60 x

Page 27: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = - mVOLUME

T K 0.600 x 1.00 = 72.00 m3 75.00

0.400 x 1.00 = - m3 0.600 x 1.00 = - m3 -

72.00 72.00

0.050 x 1.00 = - m3 -

0.200 x 2.00 = - m3

0.300 x 1.00 = 36.00 m3 0.200 x 2.00 = - 0.150 x 2.00 = - m3 - 0.300 x 1.00 = - m3 3.000 x 0.50 = - m3

1.000 x 2.00 = - m3

1.000 = - m3 36.00 m3

0.300 x 1.00 = 36.00 m3 0.200 x 2.00 -

36.00 m3

2.000 1.00 = - ltr -

Page 28: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = -

NO PEKERJAAN VOLUME

p L T K 1 Galian biasa pelebaran 675.00 x 1.60 x 0.600 x 1.00 = 648.00

Galian biasa raising - x 1.60 x 0.400 x 1.00 = - Galian biasa (rekondisi) - x 1.00 x 0.600 x 1.00 = -

648.00

2 100.00 x 2.00 x 0.050 x 1.00 = -

3 Galian Batu - x 1.10 x 0.200 x 2.00 = -

4 Urugan pilihan (Pelebaran) tanpa raising 675.00 x 1.60 x 0.300 x 1.00 = 324.00 Urugan pilihan (Pelebaran) dengan raising - 1.60 x 0.200 x 2.00 = - Urugan pilihan (bahu jalan) - x 1.00 x 0.150 x 2.00 = - Urugan pilihan (Rising) - x 1.00 x 0.300 x 1.00 = - Urugan Pilihan (Tiang Pancang) - x 3.00 x 3.000 x 0.50 = -

Urugan pilihan (Pas. Batu) - x 1.25 x 1.000 x 2.00 = -

- x 0.80 x 1.000 = - 324.00

5 Lapis pondasi agregat dengan (CTB) Pelebaran 675.00 x 1.60 x 0.300 x 1.00 = 324.00 Lapis pondasi agregat dengan (CTB) Pelebaran - x 1.60 x 0.200 x 2.00 -

324.00

7 Prime Coat - x 1.60 x 2.000 1.00 = - -

Galian perker beraspal tanpa cold milling machine

Page 29: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

overlaym

VOLUME

m3m3m3

m3###

m3

m3###

m3m3m3

m3

m3m3

m3###

m3

ltr

Page 30: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = - m

NO PEKERJAAN VOLUME

p L T K 1 450.00 x 1.60 x 0.600 x 1.00 = 432.00 m3

- x 1.60 x 0.400 x 1.00 = - m3Galian biasa (rekondisi) - x 1.00 x 0.600 x 1.00 = - m3Galian Pasangan batu - 0.60 x 0.620 x 1.00 = - Galian biasa (Rising) - x 2.00 x 0.300 x 1.00 = - m3Galian biasa (mortar) - x (0.6+0.5)/2 x 0.500 x = - m3

432.00

2 Galian perker beraspal tanpa cold milling machine 100.00 x 2.00 x 0.050 x 1.00 = - m3

3 Galian Batu - x 1.10 x 0.200 x 2.00 = - m3

4 Urugan pilihan (Pelebaran) tanpa raising 450.00 x 1.60 x 0.300 x 1.00 = 216.00 m3Urugan pilihan (Pelebaran) dengan raising - 1.60 x 0.200 x 2.00 = - Urugan pilihan (bahu jalan) - x 1.00 x 0.150 x 2.00 = - m3Urugan pilihan (Rising) - x 1.00 x 0.300 x 1.00 = - m3Urugan Pilihan (Tiang Pancang) - x 3.00 x 3.000 x 0.50 = - m3

Urugan pilihan (Pas. Batu) - x 1.25 x 1.000 x 2.00 = - m3

- x 0.80 x 1.000 = - m3 216.00 m3

5 Lapis pondasi agregat dengan (CTB) Pelebaran 450.00 x 1.60 x 0.300 x 1.00 = 216.00 m3Lapis pondasi agregat dengan (CTB) Pelebaran - x 1.60 x 0.200 x 2.00 - Lapis pondasi agregat dengan (CTB) Rekon - x 1.00 x 0.300 x 1.00 = - m3Lapis pondasi agregat dengan (CTB) Rising - x 7.20 x 0.200 x 1.00 = - m3

216.00 m3CTSB (Pelebaran) - x 1.60 x 0.300 x 2.00 = - m3

6 Lapis pondasi agregat kelas B - x 1.00 x 0.200 x 2.00 = - m3Lapis pondasi agregat kelas B - x 1.00 x 0.200 x 2.00 = - m3

-

7 Prime Coat - x 1.60 x 1.000 1.00 = - ltrPrime Coat (Tiang Pancang) - x 2.00 x 1.000 = - ltrPrime Coat (Rekon) - x 1.00 x 1.000 x 1.00 = - ltrPrime Coat (Rising) - x 7.20 x 1.000 x 1.00 = - ltr

-

8 Tack Coat (ATBL) - x 7.00 x 1.000 0.20 = - ltrTack Coat (ATBL) existing - x 4.00 x 1.000 0.35 = - ltrTack Coat Rising - x 6.00 x 1.000 0.15 = - ltrTack Coat (AC) - x 6.00 x 1.000 0.15 = - ltr

- x 1.50 x 1.000 0.35 = - ltr - ltr

9 ATB pelebaran - x 1.54 x 0.060 x 2.310 = - tonATB existing - x 4.00 x 0.068 x 1.000 = - m3ATB Rising - x 1.00 x 1.000 x 2.310 = - tonCampuran Aspal Panas - x 2.00 x 0.050 x 1.00 = - m3

- ton - ton

Galian biasa (dibuang diluar lokasi pekerjaan) pelebaranGalian biasa (dibuang diluar lokasi pekerjaan) pelebaran

Page 31: Jadwal Pelaksanaan Paket 2 Addendum

Aggregat - x 0.9200 = - tonAspal - x 0.0610 = - ton

Semen 0.920 - x 19.0000 = - kg

Page 32: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

NO PEKERJAAN VOLUME

p L 1 950.00 x 1.60 x

- x 1.60 xGalian biasa (rekondisi) - x 1.00 xGalian Pasangan batu - 0.60 xGalian biasa (Rising) - x 2.00 xGalian biasa (mortar) - x (0.6+0.5)/2 x

2 Galian perker beraspal tanpa cold milling machine 100.00 x 2.00 x

3 Galian Batu - x 1.10 x

4 Urugan pilihan (Pelebaran) tanpa raising 950.00 x 1.60 xUrugan pilihan (Pelebaran) dengan raising - 1.60 xUrugan pilihan (bahu jalan) - x 1.00 xUrugan pilihan (Recond) - x 1.00 xUrugan Pilihan (Tiang Pancang) - x 3.00 x

Urugan pilihan (Pas. Batu) - x 1.25 x

- x 0.80 x

5 Lapis pondasi agregat dengan (CTB) Pelebaran 950.00 x 1.60 xLapis pondasi agregat dengan (CTB) Pelebaran - x 1.60 xLapis pondasi agregat dengan (CTB) Rekon - x 1.00 xLapis pondasi agregat dengan (CTB) Rising - x 7.20 x

CTSB (Pelebaran) - x 1.60 x

6 Lapis pondasi agregat kelas B - x 1.00 xLapis pondasi agregat kelas B - x 1.00 x

7 Prime Coat - x 1.60 xPrime Coat (Tiang Pancang) - x 2.00 xPrime Coat (Rekon) - x 1.00 xPrime Coat (Rising) - x 7.20 x

8 Tack Coat (ATBL) - x 7.00 x

Galian biasa (dibuang diluar lokasi pekerjaan) pelebaranGalian biasa (dibuang diluar lokasi pekerjaan) pelebaran

Page 33: Jadwal Pelaksanaan Paket 2 Addendum

Tack Coat (ATBL) existing - x 4.00 xTack Coat Rising - x 6.00 xTack Coat (AC) - x 6.00 x

- x 1.50 x

9 ATB pelebaran - x 1.54 xATB existing - x 4.00 xATB Rising - x 1.00 xCampuran Aspal Panas - x 2.00 x

AggregatAspal

Semen 0.920

10 AC - x 6.00 xAC Rising - x 7.00 xAC Rising - x 1.00 x

AggregatAspal

Semen 0.922

11 Pas. Batu - x 0.45 x - x 0.60 x - x 0.45 x

12 Pas. Batu dg Mortar - x 0.30 x - x (0.5+0.4)/2 x

13 Pancang - : 0.25 x

14 Pemancangan - : 0.25 x

15 Beton K175 (Penutup Selokan) - x 0.15 x

16 Baja Tulangan - x 125.00

17 Patok Pengarah - : 3.00

18 Patok Hekto - : 1,000.00 x

Page 34: Jadwal Pelaksanaan Paket 2 Addendum

19 Marka JalanGaris Lurus Pinggir - x 0.12 xGaris Putus - x 0.12 xGaris Zebra Cross - x 2.00

20 Pembersihan dan Pembongkaran - x 0.80

Page 35: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = - mVOLUME

T K 0.600 x 1.00 = 912.00 m3 2,150.00

0.400 x 1.00 = - m3 0.600 x 1.00 = - m3 0.620 x 1.00 = - 0.300 x 1.00 = - m3 0.500 x = - m3

912.00 2,064.00

0.050 x 1.00 = - m3

0.200 x 2.00 = - m3

0.300 x 1.00 = 456.00 m3 0.200 x 2.00 = - 0.150 x 2.00 = - m3 0.300 x 1.00 = - m3 3.000 x 0.50 = - m3

1.000 x 2.00 = - m3

1.000 = - m3 456.00 m3

0.300 x 1.00 = 456.00 m3 0.200 x 2.00 - 0.300 x 1.00 = - m3 0.200 x 1.00 = - m3

456.00 m3 0.300 x 2.00 = - m3

0.200 x 2.00 = - m3 0.200 x 2.00 = - m3

-

2.000 1.00 = - ltr 1.000 = - ltr 1.000 x 1.00 = - ltr 1.000 x 1.00 = - ltr

-

1.000 0.20 = - ltr

Page 36: Jadwal Pelaksanaan Paket 2 Addendum

1.000 0.35 = - ltr 1.000 0.15 = - ltr 1.000 0.15 = - ltr 1.000 0.35 = - ltr

- ltr

0.060 x 2.310 = - ton 0.068 x 1.000 = - m3 1.000 x 2.310 = - ton 0.050 x 1.00 = - m3

- ton - ton

- x 0.9200 = - ton - x 0.0610 = - ton - x 19.0000 = - kg

1.000 1.00 = - m2 1.000 x 1.000 = - m2 0.040 x 2.327 = - ton

- ton - x 0.9220 = - - x 0.0590 = - - x 19.0000 = -

1.300 x 1.00 = - m3 0.500 x 2.00 = - m3 0.700 x 0.30 = - m3

23.00 m3

0.800 x 2.00 = - m3 0.300 = - m3

- m3 - m3

8.000 = - m'

4.000 = - m'

1.000 = - m3

= - Kg

= - Bh

9.000 = - Bh

Page 37: Jadwal Pelaksanaan Paket 2 Addendum

2.000 = - 0.375 = -

= - - m2

= - m2

Page 38: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = - m

NO PEKERJAAN VOLUME

p L T K 1 950.00 x 1.60 x 0.600 x 1.00 = 912.00 m3

150.00 x 1.79 x 0.500 x 1.00 = 134.25 m3Galian biasa (rekondisi) 200.00 x 1.50 x 0.600 x 1.00 = 180.00 m3Galian Pasangan batu - 0.60 x 0.620 x 1.00 = - Galian biasa (Rising) - x 2.00 x 0.300 x 1.00 = - m3Galian biasa (mortar) - x (0.6+0.5)/2 x 0.500 x = - m3

1,226.25 ###

2 Galian perker beraspal tanpa cold milling machine - x 1.50 x 0.050 x 1.00 = 24.97 m3

4 Urugan pilihan (Pelebaran) tanpa raising 950.00 x 1.60 x 0.300 x 1.00 = 456.00 m3Urugan pilihan (Pelebaran) dengan raising 150.00 1.79 x 0.300 x 1.00 = 80.55 Urugan pilihan (bahu jalan) - x 1.00 x 0.150 x 2.00 = - m3Urugan pilihan (Recond) 200.00 x 1.50 x 0.300 x 1.00 = 90.00 m3Urugan Pilihan (Tiang Pancang) - x 3.00 x 3.000 x 0.50 = - m3Urugan pilihan (Pas. Batu) - x 1.25 x 1.000 x 2.00 = - m3

- x 0.80 x 1.000 = - m3 626.55 m3

5 Lapis pondasi agregat dengan (CTB) Pelebaran 950.00 x 1.60 x 0.300 x 1.00 = 456.00 m3Lapis pondasi agregat dengan (CTB) Pelebaran 150.00 x 1.79 x 0.200 x 1.00 53.70 Lapis pondasi agregat dengan (CTB) Rekon 200.00 x 1.50 x 0.300 x 1.00 = 90.00 m3Lapis pondasi agregat dengan (CTB) Rising - x 7.20 x 0.200 x 1.00 = - m3

599.70 m3CTSB (Pelebaran) - x 1.60 x 0.300 x 2.00 = - m3

6 Lapis pondasi agregat kelas B - x 1.00 x 0.200 x 2.00 = - m3 -

7 Prime Coat 1,950.00 x 1.60 x 1.000 1.00 = 3,120.00 ltrPrime Coat (Tiang Pancang) - x 2.00 x 1.000 = - ltrPrime Coat (Rekon) - x 1.50 x 1.000 x 1.00 = - ltrPrime Coat (Rising) - x 7.20 x 1.000 x 1.00 = - ltr

3,120.00

8 Tack Coat (ATBL) - x 7.00 x 1.000 0.20 = - ltrTack Coat (ATBL) existing (150.00) x 4.00 x 1.000 0.35 = (210.00) ltrTack Coat Rising - x 6.00 x 1.000 0.15 = - ltrTack Coat (AC) - x 6.00 x 1.000 0.15 = - ltr

- x 1.50 x 1.000 0.35 = - ltr (210.00) ltr

9 ATB (Pelebaran) - x 1.04 x 0.060 x 2.00 = - m3ATB (Gal tanpa) - x 1.50 x 0.060 x 1.00 = - m3

- ton

9 ATB pelebaran - x 1.54 x 0.060 x 2.310 = - tonATB existing - x 4.00 x 0.068 x 1.000 = - m3ATB Rising - x 1.00 x 1.000 x 2.310 = - tonCampuran Aspal Panas - x 2.00 x 0.050 x 1.00 = 24.97 m3

24.97 tonATBL rekondisi - x 1.50 x 0.050 x 1.000 = - ton

Galian biasa (dibuang diluar lokasi pekerjaan) pelebaranGalian biasa (dibuang diluar lokasi pekerjaan) pelebaran

Page 39: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

NO PEKERJAAN VOLUME

p L 1 985.00 x 1.60 x

150.00 x 1.79 xGalian biasa (rekondisi) 200.00 x 1.50 xGalian Pasangan batu - 0.60 xGalian biasa (Rising) - x 2.00 xGalian biasa (mortar) - x (0.6+0.5)/2 x

2 Galian perker beraspal tanpa cold milling machine - x 1.50 x

4 Urugan pilihan (Pelebaran) tanpa raising 985.00 x 1.60 xUrugan pilihan (Pelebaran) dengan raising 150.00 1.79 xUrugan pilihan (bahu jalan) - x 1.00 xUrugan pilihan (Recond) 200.00 x 1.50 xUrugan Pilihan (Tiang Pancang) - x 3.00 xUrugan pilihan (Pas. Batu) - x 1.25 x

- x 0.80 x

5 Lapis pondasi agregat dengan (CTB) Pelebaran 985.00 x 1.60 xLapis pondasi agregat dengan (CTB) Pelebaran 150.00 x 1.79 xLapis pondasi agregat dengan (CTB) Rekon 200.00 x 1.50 xLapis pondasi agregat dengan (CTB) Rising - x 7.20 x

CTSB (Pelebaran) - x 1.60 x

6 Lapis pondasi agregat kelas B - x 1.00 x

7 Prime Coat - x 1.60 xPrime Coat (Tiang Pancang) - x 2.00 xPrime Coat (Rekon) - x 1.50 xPrime Coat (Rising) - x 7.20 x

Galian biasa (dibuang diluar lokasi pekerjaan) pelebaranGalian biasa (dibuang diluar lokasi pekerjaan) pelebaran

Page 40: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = - mVOLUME

T K 2730 5460

0.600 x 1.00 = 945.60 m3 4,085.00 1,075.00

0.500 x 1.00 = 134.25 m3 300.00

0.600 x 1.00 = 180.00 m3 4,385.00

0.620 x 1.00 = - 0.300 x 1.00 = - m3 0.500 x = - m3

1,259.85 4,550.10

0.050 x 1.00 = - m3

0.300 x 1.00 = 472.80 m3 0.300 x 1.00 = 80.55 0.150 x 2.00 = - m3 0.300 x 1.00 = 90.00 m3 3.000 x 0.50 = - m3 1.000 x 2.00 = - m3 1.000 = - m3

643.35 m3

0.300 x 1.00 = 472.80 m3 0.200 x 1.00 53.70 0.300 x 1.00 = 90.00 m3 0.200 x 1.00 = - m3

616.50 m3 0.300 x 2.00 = - m3

0.200 x 2.00 = - m3 -

1.000 1.00 = - ltr 1.000 = - ltr 1.000 x 1.00 = - ltr 1.000 x 1.00 = - ltr

3,974.61

Page 41: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

NO PEKERJAAN VOLUME

p L 1 1,075.00 x 1.60 x

- x 1.60 xGalian biasa (rekondisi) 200.00 x 1.50 xGalian Pasangan batu - 0.60 xGalian biasa (Rising) - x 2.00 xGalian biasa (mortar) - x (0.6+0.5)/2 x

4 Urugan pilihan (Pelebaran) tanpa raising 1,075.00 x 1.60 xUrugan pilihan (Pelebaran) dengan raising - 1.60 xUrugan pilihan (bahu jalan) - x 1.00 xUrugan pilihan (Recond) 200.00 x 1.50 xUrugan Pilihan (Tiang Pancang) - x 3.00 xUrugan pilihan (Pas. Batu) - x 1.25 x

- x 0.80 x

5 Lapis pondasi agregat dengan (CTB) Pelebaran 1,075.00 x 1.60 xLapis pondasi agregat dengan (CTB) Pelebaran - x 1.60 xLapis pondasi agregat dengan (CTB) Rekon 200.00 x 1.50 xLapis pondasi agregat dengan (CTB) Rising - x 7.20 x

CTSB (Pelebaran) - x 1.60 x

6 Lapis pondasi agregat kelas B - x 1.00 xLapis pondasi agregat kelas B - x 1.00 x

7 Prime Coat 1,150.00 x 1.60 xPrime Coat (Tiang Pancang) - x 2.00 xPrime Coat (Rekon) - x 1.50 xPrime Coat (Rising) - x 7.20 x

8 Tack Coat (ATBL) - x 7.00 xTack Coat (ATBL) existing - x 4.00 xTack Coat Rising - x 6.00 xTack Coat (AC) - x 6.00 x

- x 1.50 x

Galian biasa (dibuang diluar lokasi pekerjaan) pelebaranGalian biasa (dibuang diluar lokasi pekerjaan) pelebaran

Page 42: Jadwal Pelaksanaan Paket 2 Addendum

9 ATB (Pelebaran) - x 1.04 xATB (Gal tanpa) - x 1.50 x

9 ATB pelebaran - x 1.54 xATB existing - x 4.00 xATB Rising - x 1.00 xCampuran Aspal Panas - x 2.00 x

ATBL rekondisi - x 1.50 x

AggregatAspal

Semen 0.920

10 AC - x 6.00 xAC Rising - x 7.00 xAC Rising - x 1.00 x

AggregatAspal

Semen 0.922

11 Pas. Batu - x 0.45 x - x 0.60 x - x 0.45 x

12 Pas. Batu dg Mortar - x 0.30 x - x (0.5+0.4)/2 x

13 Pancang - : 0.25 x

14 Pemancangan - : 0.25 x

15 Beton K175 (Penutup Selokan) - x 0.15 x

16 Baja Tulangan - x 125.00

17 Patok Pengarah - : 3.00

18 Patok Hekto - : 1,000.00 x

Page 43: Jadwal Pelaksanaan Paket 2 Addendum

19 Marka JalanGaris Lurus Pinggir - x 0.12 xGaris Putus - x 0.12 xGaris Zebra Cross - x 2.00

20 Pembersihan dan Pembongkaran - x 0.80

Page 44: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = - mVOLUME

T K 0.600 x 1.00 = 1,032.00 m3 5,160.00 2730 5460

0.400 x 1.00 = - m3 300.00 -

0.600 x 1.00 = 180.00 m3 5,460.00 540.00

0.620 x 1.00 = - 0.300 x 1.00 = - m3 0.500 x = - m3

1,212.00 5,762.10

0.300 x 1.00 = 516.00 m3 0.200 x 2.00 = - 0.150 x 2.00 = - m3 0.300 x 1.00 = 90.00 m3 3.000 x 0.50 = - m3 1.000 x 2.00 = - m3 1.000 = - m3

606.00 m3

0.300 x 1.00 = 516.00 m3 0.200 x 2.00 - 0.300 x 1.00 = 90.00 m3 0.200 x 1.00 = - m3

606.00 m3 0.300 x 2.00 = - m3

0.200 x 2.00 = - m3 0.200 x 2.00 = - m3

-

1.000 1.00 = 1,840.00 ltr 1.000 = - ltr 1.000 x 1.00 = - ltr 1.000 x 1.00 = - ltr

1,840.00

1.000 0.20 = - ltr 1.000 0.35 = - ltr 1.000 0.15 = - ltr 1.000 0.15 = - ltr 1.000 0.35 = - ltr

- ltr

Page 45: Jadwal Pelaksanaan Paket 2 Addendum

0.060 x 2.00 = - m3 0.060 x 1.00 = - m3

- ton

0.060 x 2.310 = - ton 0.068 x 1.000 = - m3 1.000 x 2.310 = - ton 0.050 x 1.00 = - m3

- ton 0.050 x 1.000 = - ton

- ton

- x 0.9200 = - ton - x 0.0610 = - ton - x 19.0000 = - kg

1.000 1.00 = - m2 1.000 x 1.000 = - m2 0.040 x 2.327 = - ton

- ton - x 0.9220 = - - x 0.0590 = - - x 19.0000 = -

1.300 x 1.00 = - m3 0.500 x 2.00 = - m3 0.700 x 0.30 = - m3

23.00 m3

0.800 x 2.00 = - m3 0.300 = - m3

- m3 - m3

8.000 = - m'

4.000 = - m'

1.000 = - m3

= - Kg

= - Bh

9.000 = - Bh

Page 46: Jadwal Pelaksanaan Paket 2 Addendum

2.000 = - 0.375 = -

= - - m2

= - m2

Page 47: Jadwal Pelaksanaan Paket 2 Addendum

PERHITUNGAN VOLUME PEKERJAAN PENINGKATAN JALAN BTS.KAB. PAMEKASAN - BTS. KOTA SUMENEP (LINK 232)

22,020.000 - 25+000 = - m

NO PEKERJAAN VOLUME

p L T K 1 x 1.60 x 0.600 x 1.00 = - m3

x 1.79 x 0.500 x 1.00 = - m3Galian biasa (rekondisi) - x 1.00 x 0.600 x 1.00 = - m3Galian Pasangan batu - 0.60 x 0.620 x 1.00 = - Galian biasa (Rising) - x 2.00 x 0.300 x 1.00 = - m3Galian biasa (mortar) - x (0.6+0.5)/2 x 0.500 x = - m3

-

4 Urugan pilihan (Pelebaran) tanpa raising - x 1.60 x 0.300 x 1.00 = - m3Urugan pilihan (Pelebaran) dengan raising - 1.79 x 0.300 x 1.00 = - Urugan pilihan (bahu jalan) - x 1.00 x 0.150 x 2.00 = - m3Urugan pilihan (Rising) - x 1.00 x 0.300 x 1.00 = - m3Urugan Pilihan (Tiang Pancang) - x 3.00 x 3.000 x 0.50 = - m3Urugan pilihan (Pas. Batu) - x 1.25 x 1.000 x 2.00 = - m3

- x 0.80 x 1.000 = - m3 - m3

5 Lapis pondasi agregat dengan (CTB) Pelebaran - x 1.60 x 0.300 x 1.00 = - m3Lapis pondasi agregat dengan (CTB) Pelebaran - x 1.79 x 0.200 x 1.00 - Lapis pondasi agregat dengan (CTB) Rekon - x 1.00 x 0.300 x 1.00 = - m3Lapis pondasi agregat dengan (CTB) Rising - x 7.20 x 0.200 x 1.00 = - m3

- m3CTSB (Pelebaran) - x 1.60 x 0.300 x 2.00 = - m3

6 Lapis pondasi agregat kelas B - x 1.00 x 0.200 x 2.00 = - m3Lapis pondasi agregat kelas B - x 1.00 x 0.200 x 2.00 = - m3

-

7 Prime Coat - x 1.60 x 1.000 1.00 = - ltrPrime Coat (Tiang Pancang) - x 2.00 x 1.000 = - ltrPrime Coat (Rekon) - x 1.00 x 1.000 x 1.00 = - ltrPrime Coat (Rising) - x 7.20 x 1.000 x 1.00 = - ltr

-

8 Tack Coat (ATBL) - x 7.00 x 1.000 0.20 = - ltrTack Coat (ATBL) existing - x 4.00 x 1.000 0.35 = - ltrTack Coat Rising - x 6.00 x 1.000 0.15 = - ltrTack Coat (AC) - x 6.00 x 1.000 0.15 = - ltr

- x 1.50 x 1.000 0.35 = - ltr - ltr

9 ATB (Pelebaran) - x 1.04 x 0.060 x 2.00 = - m3ATB (Gal tanpa) - x 1.00 x 0.060 x 1.00 = - m3

- ton

9 ATB pelebaran - x 1.54 x 0.060 x 2.310 = - tonATB existing - x 4.00 x 0.068 x 1.000 = - m3ATB Rising - x 1.00 x 1.000 x 2.310 = - tonCampuran Aspal Panas - x 2.00 x 0.050 x 1.00 = - m3

- tonATBL rekondisi - x 1.50 x 0.050 x 1.000 = - ton

- ton

Aggregat - x 0.9200 = - tonAspal - x 0.0610 = - ton

Semen 0.920 - x 19.0000 = - kg

10 AC - x 6.00 x 1.000 1.00 = - m2AC Rising - x 7.00 x 1.000 x 1.000 = - m2AC Rising - x 1.00 x 0.040 x 2.327 = - ton

- ton

Galian biasa (dibuang diluar lokasi pekerjaan) pelebaranGalian biasa (dibuang diluar lokasi pekerjaan) pelebaran

Page 48: Jadwal Pelaksanaan Paket 2 Addendum

Aggregat - x 0.9220 = - Aspal - x 0.0590 = -

Semen 0.922 - x 19.0000 = -

11 Pas. Batu - x 0.45 x 1.300 x 1.00 = - m3 - x 0.60 x 0.500 x 2.00 = - m3 - x 0.45 x 0.700 x 0.30 = - m3

23.00 m3

12 Pas. Batu dg Mortar - x 0.30 x 0.800 x 2.00 = - m3 - x (0.5+0.4)/2 x 0.300 = - m3

- m3 - m3

13 Pancang - : 0.25 x 8.000 = - m'

14 Pemancangan - : 0.25 x 4.000 = - m'

15 Beton K175 (Penutup Selokan) - x 0.15 x 1.000 = - m3

16 Baja Tulangan - x 125.00 = - Kg

17 Patok Pengarah - : 3.00 = - Bh

18 Patok Hekto - : 1,000.00 x 9.000 = - Bh

19 Marka JalanGaris Lurus Pinggir - x 0.12 x 2.000 = - Garis Putus - x 0.12 x 0.375 = - Garis Zebra Cross - x 2.00 = -

- m2

20 Pembersihan dan Pembongkaran - x 0.80 = - m2