IVRINDI & LAPSEKI GOLD PROJECTS
Halil TATAYOGLU
Chief Geologist
www.tumad.com.tr
MINING INDUSTRY AND TRADE INC.
DISCLAIMER
This presentation has been prepared by Tumad Mining Industry and Trade Inc. (Tumad). The information contained in this presentation is a professionalopinion only and is given in good faith.
Certain information in this document has been derived from third parties and though Tumad has no reason to believe that it is not accurate, reliable orcomplete, it has not been independently audited or verified by Tumad. Any forward-looking statements included in this document involve subjectivejudgement and analysis and are subject to uncertainties, risks and contingencies, many of which are outside the control of, and maybe unknown to,Tumad. In particular, they speak only as of the date of this document, they assume the success of Tumad’s strategies, and they are subject tosignificant regulatory, business, competitive and economic uncertainties and risks. Actual future events may vary materially from the forward lookingstatements and the assumptions on which the forward looking statements are based. Recipients of this document ("Recipients") are cautioned to notplace undue reliance on such forward-looking statements.
Tumad makes no representation or warranty as to the accuracy, reliability or completeness of information in this document and does not takeresponsibility for updating any information or correcting any error or omission which may become apparent after this document has been issued. Tothe extent permitted by law, Tumad and its officers, employees, related bodies corporate and agents ("Agents") disclaim all liability, direct, indirect orconsequential (and whether or not arising out of the negligence, default or lack of care of Tumad and/or any of its Agents) for any loss or damagesuffered by a Recipient or other persons arising out of, or in connection with, any use or reliance on this presentation or information.
The exploration data and results, resource and reserve statements, feasibility data and financial statements contained in this presentation are based oninformation related to Mineral Resource and Feasibility Studies of Tumad reviewed by Halil Tatayoglu. He is Chief Geologist of the Company and hassufficient experience to analyse which is relevant to this type of data.
1
TUMAD AT A GLANCE
2
Ivrindi major license has been acquired from
government with an auction and drilling campaign has
started afterwards.
2013
TÜMAD is part of a large, %100 Turkish
conglomerate called NUROL Holding
2012
Lapseki Project (Kestanelik) has been acquired
from Chesser Resources (Australia).
2014
Mineral Resource Estimation and Definitive
Feasibility Studies Compliant with International
Standards (NI 43-101 and JORC) for Lapseki
and Ivrindi Projects have been completed.
2015-2016
Lapseki Project has been commissioned.
2017
Ivrindi investment studies are in progress.
2018-2019
FINANCE AGREEMENT
3
FINANCE
AGREEMENT
210,000,000 USD
ENVIRONMENTAL AND
SOCIAL IMPACT STUDIES
MANAGEMENT PLANS
AND PROCEDURES
UPDATING
RESERVE
REVIEW OF
TECHNICAL DATA
TUMAD’s Ivrindi and Lapseki Projects Receive from EMEA Finance and GFC Media
“Best Natural Resources Deal” Award
PROJECT LOCATIONS
4
LAPSEKI PROJECT
IVRINDI PROJECT
MAJOR PROSPECTS OF NW TURKEY
5
Lapseki
Ivrindi
Kirazli
TV
Tower
Karadag
Halilaga
Agi
Dagi
Egmir
Tepeoba
Kucukdere
Balya
Red Rabit
Akarca
Gediktepe
Operations
In DevelopmentOvacik
Cukuralan
CanakkaleBandirma
Balikesir
Province
Biga
IvrindiBigadic
Can
Gelibolu
> 10 million ounces gold potential
IVRINDI PROJECT SO FAR
6
2012 2013 2014 2015 2016 2017 2018
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Project
Startup
Permits and Drilling Studies
Environmental
and Social
Studies
Environmental and Social Studies
EIA Report
Resource and
Reserve
Studies
3 NI 43-101 Compliant Resource Report
NI 43-101 Pre Feasibility & Feasibility Studies
Investment
and Finance
Detail Engineering and
Construction
Finance Due Diligence and SIP
IVRINDI PROJECT EXPLORATION STAGE
7
SURFACE SAMPLING
• 450 rock chip
• 190 channel
• 450 soil
DRILLING
• 460 Drill Hole
• 100,000 meters
GEOPHYSICAL STUDIES
• 45.6 km MAG GAR
• 48.6 km IP/Res
SURFACE MAPPING
• 1/5,000 geology
• 1/1,000 vein and alteration
• 1/1,000 cartographic
IVRINDI PROJECT MAIN ZONES AND GEOLOGY
8
South
Ballik
Kabak
Kartel
Gok Tepe
InrusionMetamoprhics
Andesitic
Volcanics
Volcano
Sedimentary
IVRINDI PROJECTRESOURCE & RESERVE STATEMENT
9
CategoryMineralise
(mton)
Au
(g/t)
Ag
(g/t)
Recovered Metal
Gold (ons)
Recovered Metal
Silver (ons)
Proven 7,90 0.82 1.92 146,000 224,500
Probable 37,10 0.63 1.56 529,200 857,000
Grand Total 45,00 0.67 1.62 675,200 1,081,500
CategoryMineralise
(mton)
Au
(g/t)
Ag
(g/t)
Metal Content
Gold (ons)
Metal Content
Silver (ons)
Measured 11.1 0.82 2.25 292,200 804,300
Indicated 52.5 0.57 1.58 957,300 2,662,200
Mea & Ind 63.6 0.61 1.70 1,250,000 3,500,000
Inferred 51.0 0.55 1.27 904,000 2,082,000
Grand Total 114.6 0.59 1.52 2,154,000 5,582,000
IVRINDI PROJECTDESIGN CRITERIA
10
FINANCE
• Total CAPEX is 220 M $
• Operating cash cost 509 $ / ons
• Payable gold 675,000 ons
• Investment is going to be completed at
the end of 2019
PROCESS
• Heap leach
• 70% leach recovery (estimated)
• Daily process capacity 21,260 ton
MINING
• Open Pit
• 6 years of mine life
• Annual 7.7 Mt ore production
• Overall strip ratio is 2.3
* All information is based on TUMAD Feasibility Report at 2017
IVRINDI PROJECTPLANT LAYOUT
11
Crushing - Screening
Main
Switchyard
ADR
Heap Leach
Aglomeration Power Transmission Line
HPGR
Ponds
Ancillary Facilities
11/07/2018
LAPSEKI PROJECT SO FAR
12
2009-2013
2014 2015 2016 2017 2018
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Project
StartupPermits and Drilling Studies
Environmental
and Social
Studies
Environmental and Social Studies
EIA Report
Resource and
Reserve
Studies
2 JORC Compliant
Resource Report
NI 43-101 Feasibility Study
Investment
and Finance
Detail Engineering and
Construction
Finance Due Diligence and SIP
Infill and Exploration Drillings
Pre-Feasibility
Studies
3 JORC Compliant Resource
Report
LAPSEKI PROJECT EXPLORATION STAGE
13
SURFACE SAMPLING
• 601 rock chip
• 333 channel
• 5283 soil
DRILLING
• 850 Drill Hole
• 120,000 meters• TUPRAG:1,500m
• Chesser: 70,500m
• TÜMAD: 48,000m
GEOPHYSICAL STUDIES
• 35.6 km MAG GAR
• 38.6 km IP/Res
SURFACE MAPPING
• 1/5,000 geology
• 1/1,000 vein and alteration
• 1/1,000 cartographic
LAPSEKI PROJECTMAIN ZONES
14
LAPSEKI PROJECTSTRATIGRAPHY
15
FORMATION ROCK TYPE CONTACT REMARK
COLLUVIUM
BASALT, ANDESITE
RHYOLITE AND
BASALTIC
VOLCANOCLASTICS
AND PYROCLASTS
SANDSTONE WITH
NUMMULITES
ANDESITIC LAVA
AND PYROCLASTS
GRANITE AND
DIORITE PORPHYRY
CETMI OPHIOLITIC
MELANGESERPANTINITE
SAHINLI FORMATION
SOGUCAK FORMATION
BEYCAYIR FORMATION
EOCENE GRANITES
CAMLICA
METHAMORPHICS
MICA SCHIST,
QUARTZ SCHIST
AND CALC SCHIST
DISCONFORMITY
BILALLER UNIT
NONCONFORMITY
MAGMATIC CONTACT
TECTONIC CONTACT
LAPSEKI PROJECTCONCEPTUAL MODEL
16
KARAKOVAN & KARATEPEKESTANELIK
* Suggested model illustrating mode of formation and vertical zonation of
epitermal veins in the Lapseki deposit, Kuscu 2011
Syntethic faultsAntitethic faults Present level of erosionSouth
North
LAPSEKI PROJECTRESOURCE STATEMENT
17
CategoryMineralise
(mton)
Au
(g/t)
Ag
(g/t)
Metal Content
Gold (ons)
Metal Content
Silver (ons)
Measured 1.6 2.3 2.0 116,000 104,000
Indicated 7.4 1.8 2.1 446,000 500,000
Mea & Ind 9.0 2.0 2.1 562,000 604,000
Inferred 11.0 1.1 1.4 368,000 491,000
Grand Total 20.0 1.5 1.7 930,000 1,100,000
Open Pit
Topography
Ore Body
LAPSEKI PROJECTOPEN PIT RESERVE STATEMENT
18
CategoryMineralise
(mton)Au (g/t) Ag (g/t)
Metal Content
Gold (ons)
Metal Content
Silver (ons)
Proven 1.32 2.22 1.83 90,300 56,500
Probable 5.83 1.76 1.86 312,700 252,500
Total 7.15 1.85 1.86 403,000 309,000
Some portion of orebody belonging to open pit is
planned to be mined as underground because of
the lack of geotechnical conditions
LAPSEKI PROJECTPLANT LAYOUT
Dry Stack Tailings
Crushing - Screening
Filter Press
ADR
Grinding
Tank Leach
Fine Ore Bin
Open Pit
Core ShedHaul Road
19
29/06/2018
Stockpile
LAPSEKI PROJECTDESIGN CRITERIA
20
FINANCE
• Total Capex is 160 M $
• Operating cash cost 538 $/ons
• Payable gold is 403,000 ons
• First dore poured at December 2017
PROCESS
• Conventional process plant
3 staged crushing, screening, leach
and CIP
• %96 leach recovery
• All process within enclosed area
• Daily process capacity 2,055 ton
MINING
• Open Pit
• 10 years of mine life
• Annual 0.75 Mt ore production
• Overall strip ratio is 8.5
* All information is based on TUMAD Feasibility Report at 2017
LAPSEKI PROJECTBEST AVAILABLE ENVIRONMENTAL TECHNOLOGY
21
The unique gold mine in the world
having such high level of standards
Heavy metal stabilization
with Fe SO4
Filter Press Process
Chemical destruction of CN-
to <10 ppm by INCO SO2/AirZERO discharge to
the surface water
Dry Stacked Tailings Disposal
with rock-fill embankments and
lined with a composite liner
system
Lapseki Project Receive “Best Available Technology” Award
from Istanbul Minerals and Metals Exporters Association
LAPSEKI PROJECTTOTAL PRODUCTION
22
* All numbers are project to date and based on TUMAD Production Report at February 2019
Open Pit Production
1,150,000 t
Grinded Ore
580,000 t
Poured Gold
60,000 ons
Poured Silver
30,000 ons
Gold Grade
2.40 g/t
Gold Leach Recovery
96 %
Silver Grade
2.30 g/t
Silver Leach Recovery
68 %
THANKS…
The New Power in Turkey’s Gold Production
Best available
technologies
Local
Workflow
Contribution to
national economy