ITS specification Duct Supply and Installation (ITS-02-01)

© NZ Transport Agency

First edition, Amendment number 6

Effective from February 2015

Page 2: ITS specification Duct Supply and Installation (ITS-02-01)

Copyright information

This publication is copyright © NZ Transport Agency

(NZTA). Material in it may be reproduced for personal or

in-house use without formal permission or charge,

provided suitable acknowledgement is made to this

publication and the NZTA as the source. Requests and

enquiries about the reproduction of material in this

publication for any other purpose should be made to:

NZ Transport Agency

Private Bag 6995

Wellington 6141

The permission to reproduce material in this publication

does not extend to any material for which the copyright is

identified as being held by a third party. Authorisation to

reproduce material belonging to a third party must be

obtained from the copyright holder(s) concerned.

Disclaimer

The NZTA has endeavoured to ensure material in this

document is technically accurate and reflects legal

requirements. However, the document does not override

governing legislation. The NZTA does not accept liability

for any consequences arising from the use of this

document. If the user of this document is unsure whether

the material is correct, they should refer directly to the

relevant legislation and contact the NZTA.

More information …

Published February 2015

If you have further queries, call our contact centre on

09 928 8718 or write to us:

NZ Transport Agency

Private Bag 6995

Wellington 6141

Page 3: ITS specification Duct Supply and Installation (ITS-02-01)

Page i

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Document management plan

1) Purpose

The purpose of this document is to specify the requirements for ITS power and communications

ducting design, supply and installation.

2) Document information

Document name ITS specification: Duct supply and installation

Document number ITS-02-01

Document status Provisional

Document availability This document is available upon request

Document author Jamie French (09) 300 9000

Tom Harris [email protected]

(09) 355 9542

Bruce Walton [email protected]

(09) 336 9465

Paul Addy [email protected]

(09) 308 0833

James Shi [email protected]

Document owner Kevan Fleckney

3) Key words

ITS Duct Supply and Installation Requirements

Page 4: ITS specification Duct Supply and Installation (ITS-02-01)

Page ii

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Record of amendments

Amendme

nt number

Section

amended

Description of change Updated by Effective

date

0 All ITS Draft Specifications Issue TLH 20/9/2010

Draft R1 All AMA Specifications Review JF & TLH 25/1/2011

Final R2 2.2.1

2.3.1

2.4.1

3.2.1

Removal of NZTA imprint on Ducting, Addition of

TDM section, change of dimension for protruding

ducts. Trench Depth Detail

JF 26/06/11

Final R3 All Updated following consultation comments PTA 09/01/2012

Final R4 All Final BW & JS 14/02/2012

Final R5

All Addition of DAS median duct, air-blown fibre and

clarification of previously identified issues.

KF & TLH

2/12/2014

Final R6 All Provisional KF & TLH 11/02/2015

Page 5: ITS specification Duct Supply and Installation (ITS-02-01)

Page iii

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Contents

Document management plan i

Record of amendments ii

General 1 1.0

1.1 Scope 1

1.2 Drawings 1

Cable Duct Requirements 2 2.0

2.1 General 2

2.2 ITS Backbone Ducts 2

Ducts 2 2.2.1

Sub-ducts 3 2.2.2

Air-blown Fibre Multi-ducting 3 2.2.3

Air-blown Fibre Micro-ducting 4 2.2.4

2.3 ITS Roadside Cabinet Connection Ducts 4

Jointing Chamber Connection Ducts 4 2.3.1

2.4 Local Equipment Connection Ducts 5

ITS Equipment Connection Ducts 5 2.4.1

Cable Pits and Jointing (Toby) Boxes 5 2.4.2

Distributed Acoustic Sensing Ducts 5 2.4.3

2.5 Draw-wires 6

2.6 Trace Wire 6

2.7 Plugging Ducts 6

2.8 Above Ground Ducts 7

Concrete Encased Ducts 7 2.8.1

Galvanised Steel Conduit 7 2.8.2

Duct installation 8

2.9 Handling 8

2.10 Trenching 8

Excavation 8 2.10.1

Surface Cutting 8 2.10.2

Dewatering Trenches 8 2.10.3

Support of Trenches 9 2.10.4

Page 6: ITS specification Duct Supply and Installation (ITS-02-01)

Page iv

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Duct Installation in Trenches 9 2.10.5

Jointing Ducts 9 2.10.6

Backfilling of Trenches 10 2.10.7

2.11 Directional Drilling or Thrusting Ducts 11

2.12 Jointing Chambers and Pull Pits 11

2.13 Proving Ducts 11

Appendix A: Drawings 12 3.0

Page 7: ITS specification Duct Supply and Installation (ITS-02-01)

Page 1

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

General 1.0

1.1 Scope

This specification sets out the requirements for the design and construction of the ITS Communications

Infrastructure main ducts and the local power, fibre optic and control cable and feeder cable ducts.

1.2 Drawings

The attached standard drawings are provided for information to provide a basis for design:

000-0000-0-7104-01-R2 Jointing Chamber and Pulling Pit

000-0000-0-7104-02-R2 Detail of Duct Installation Highways and Motorways

Site specific detailed design drawings for all duct routes and details shall be provided for review prior to

commencement of installation.

Page 8: ITS specification Duct Supply and Installation (ITS-02-01)

Page 2

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Cable Duct Requirements 2.0

2.1 General

Duct routes shall be kept as straight as possible.

Where curves are required, the natural flexibility of the duct shall be used to form the curve. The radii of

the curves for 100mm diameter ducts shall not be less than 35 metres.

Where bends are required in the duct, a pull-pit or chamber shall be installed.

Ducts shall be extra high impact uPVC or flexible High Density Polyethylene (HDPE) duct complying with

AS/NZS 2053.

In general, all duct installation shall be in open cut trench. Where crossings of existing roads or the like is

required, directional drilling or thrusting of duct shall be used as the preferred means to install ducts.

Cover to ducts shall be as required for the duct situation as detailed on drawing 000-0000-0-7104-02-R2.

Marker tape shall be laid within the trench excavation not more than 300mm above the ducts.

2.2 ITS Backbone Ducts

Ducts 2.2.1

In general, the ITS Backbone ducts shall be in the highway berm parallel to the edge of the carriageway

and ramp shoulders and outside any side protection barriers.

2.2.1.1 Urban Ducting

ITS backbone ducts shall be installed along the highway connecting to existing jointing chambers at each

end. The ITS Backbone shall have:

a. Two 100mm nominal bore (NB) ducts coloured Salmon

b. One 100mm N.B. duct coloured Orange.

c. Chamber locations shall be as specified in NZTA ITS specification ITS-02-02: Jointing Chambers

and Pull Pits section 2.1.1 Chamber Locations.

2.2.1.2 Rural Ducting

When ducts are installed for regional rural highways, depending on future need, the ITS backbone duct shall reflect the asset density required, proposed or projected along the highway.

If power for roadside assets is sourced locally and there is a low density of loop detectors the backbone ducting may consist of two ducts, or one duct.

A one-duct backbone shall comprise one 100mm N.B. orange duct containing four (4) 32mm internal diameter HDPE sub-ducts arranged as follows:

a. Three sub-ducts coloured salmon for fibre optic cable; and

b. One sub-duct coloured orange for low-voltage power cable.

c. Chamber locations shall be as specified in NZTA ITS specification ITS-02-02: Jointing Chambers

and Pull Pits section 2.1.1 Chamber Locations.

Page 9: ITS specification Duct Supply and Installation (ITS-02-01)

Page 3

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Sub-ducts 2.2.2

Four 32mm N.B. sub-ducts shall be installed in one of the backbone fibre optic cable ducts.

Sub-ducts shall be PE duct, installed in one continuous length from jointing chamber to jointing chamber

or from jointing chamber to pull-pit.

Sub-ducts shall protrude into Jointing Chambers and pull-pits by 400-600mm to allow for connection of

hauling equipment.

Air-blown Fibre Multi-ducting 2.2.3

If air-blown fibre ducting is specified a suitable multi-duct shall be used. The multi-duct installation shall

be appropriate to the requirements of the ducting network.

Where the ducting is installed either as part of a motorway or expressway backbone duct network, or

alongside a rural Highway, it may either:

a. Replace one or more of the 32mm sub-ducts in the fibre duct. It shall run from joint-to-joint and

the backbone micro-duct shall not be broken-out in pull-pits.

b. Be provided alongside the ATMS 100mm ducting.

Where only fibre is required and there is no foreseeable future requirement for non-fibre ducting, a

suitably designed direct-buried multi-duct may be provided on non-motorway/expressway roads.

HDPE direct-buried multi-ducting shall be installed along the highway connecting to existing joint chambers at each end, for the backbone cable.

The main features of multi-ducting shall be:

• Four 12mm OD/10mm ID + five 5mm OD/3.5mm ID HDPE micro-ducts with ribbed surface inside tubes to reduce friction

• Low friction internal coating for maximum fibre blowing distance • Ripcord • Tracer wire or sheath • Anti-rodent protective layer • Nylon Layer • Polymer Filler • HDPE Outer Jacket (UV resistant) coloured “Salmon” • 2km continuous lengths – minimise connectivity

Figure 1. Example of a typical backbone multi-duct.

Chamber locations shall be as specified in the NZTA ITS specification ITS-02-02: Joining Chambers and Pull Pits section 2.1.1 Chamber Locations. Pull pits are not required for this type of ducting.

Page 10: ITS specification Duct Supply and Installation (ITS-02-01)

Page 4

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

If the micro-ducting of one manufacturer is joined to the micro-ducting of a different manufacturer, the connector must be compatible to both ducting types. The installer must satisfy himself that the adjacent ducting types can be connected to manufacturer’s tolerances for water tightness and continuity.

Blowing a fibre of one manufacturer through the micro-duct of another manufacturer may limit the distance the fibre can be blown due to differences in texture and coating compatibility between the outer surface of the fibre and the inner surface of the micro-duct. In this situation, the installer must first satisfy himself that the fibre can be blown the required distance.

Air-blown Fibre Micro-ducting 2.2.4

If the system in use for the ITS backbone is air-blown fibre, one of the 5mm OD/3.5 mm ID micro-ducts may be used where a spur cable runs on the backbone route. If the backbone route is not followed by the spur cable, the spur cable shall be in its own separate duct of equal ID.

A spur duct separate from the backbone duct shall be a one way direct-buried 5mm OD/3.5 mm ID micro-duct

Construction of the micro-duct shall be as shown below. Note: a trace wire is shown, but a sheath may also be used:

Figure 2. Example of a 96f micro-fibre in a single direct-bury micro-duct. The blue inner duct can be jointed using the appropriate connectors to a compatible micro-duct. The orange protective outer covering can be seen on the right.

2.3 ITS Roadside Cabinet Connection Ducts

Jointing Chamber Connection Ducts 2.3.1

Local duct connections from the ITS Backbone jointing chambers to roadside control cabinets shall have:

a. One 100mm N.B, duct coloured Salmon.

b. One 100mm N.B. duct coloured Orange.

c. Separate ducts for local power and control cable ducts as required for connections to the ITS

systems equipment.

d. Any telephone cable ducts shall be 50mm N.B. duct coloured Green.

Duct connections into jointing chambers shall be made with straight ducts aligned directly to the roadside

control cabinet.

Page 11: ITS specification Duct Supply and Installation (ITS-02-01)

Page 5

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

2.4 Local Equipment Connection Ducts

ITS Equipment Connection Ducts 2.4.1

Local duct connections from the roadside control cabinets shall have separate ducts for power and

data/control cables.

Duct connections into the roadside control cabinets and into ITS equipment supports or foundations shall

be made with long radius bends, a minimum bending radius of 600mm is required for one 100mm duct (a

factor of 6).

Local equipment connection ducting shall be installed along on-ramps and the urban roads for connection of assets associated with Ramp Signals to the ramp signal controller cabinet. The TDM ducts shall have:

a. One 100mm N.B, duct coloured “Salmon” running the entire length of the On-Ramp for local fibre and inductive loop feeder cable.

b. One 100mm N.B. duct coloured “Orange” running the entire length of the On-Ramp for power cable.

Chamber locations shall be as specified in ITS 02-02 Section 2.1.3 Chamber Locations and ITS 05-01 Ramp Meter Site Layout.

Cable Pits and Jointing (Toby) Boxes 2.4.2

The supply and installation of cable pits and the connection of ducts into the pits shall comply with NZTA

ITS specification ITS-02-02: Jointing Chambers and Pull Pits.

Distributed Acoustic Sensing Ducts 2.4.3

The purpose of providing a fibre specifically for a distributed acoustic sensing role is to

a. Locate the fibre in a position where it will receive the best possible signal from passing traffic and,

b. Provide close coupling between the ground and the fibre in order that the fibre can detect as

much traffic noise as possible.

There are two locations where the duct can be laid

a. Alongside the carriageway and as close to it as possible to the edge of the carriageway. This

method is best used where there is a backbone fibre close to the opposite carriageway.

b. Along the central median. This method is best used where the backbone fibre is not close to the

side of the carriageway and provides equal signatures from both carriageways.

For motorways and expressways with two lanes in each direction, a fibre located in the median provides

the best signature frim both carriageways. The quality of this signature deteriorates as the road gets

wider and busier, so for larger motorways, a fibre placed alongside each side would be the better

solution.

The duct can be installed by any means, including thrusting, trenching, micro-trenching, chain-digging,

mole ploughing or casting within the foundation of a concrete barrier. Slot-cutting may be used if an air-

blown fibre micro-duct is used.

For loose tube fibre, the duct shall be a 25mm diameter duct containing a fibre of minimum 6 cores.

Where air-blown fibre is used, a 6mm internal bore will be optimal for a 2-core fibre to be blown for a

distance of 3-4km. The duct shall be laid at a depth of 100mm to 130mm

A suitably robust duct shall be used that will not become damaged by the passage of maintenance

vehicles if it not laid into a barrier foundation.

Page 12: ITS specification Duct Supply and Installation (ITS-02-01)

Page 6

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

If a duct is laid in the foundation of a concrete barrier, chambers shall be provided adjacent to the barrier

and connected to the duct under the barrier by using the natural curve of the duct itself.

The median duct shall be connected to the roadside backbone fibre with the use of cross-road structures

(under or over) or by thrusting a duct beneath the carriageway.

Chambers may be provided at intervals up to 2km.

2.5 Draw-wires

Draw tape shall be installed in all ducts and within one sub-duct to facilitate the hauling-in of cable after

the completion of the ducting.

Alternatively, each duct may be fitted with a pigmented, stranded polypropylene or equivalent rot-proof

material draw cord of 5kN breaking load and having a design life of not less than 20 years, the ends of

which shall be made fast within the chambers to which the duct is terminated. Draw cords shall be

secured to the duct plugs. Draw cords shall not be knotted within ducts; where a joint is required it shall

be a spliced joint.

All ducts and conduits used or unused shall be left with a draw-wire in place.

Draw-wires are not required for air-blown fibre systems

2.6 Trace Wire

A trace wire shall be installed either separately or integrated into one of the backbone fibre optic cable

ducts in the space between the sub-ducts and the main duct

A trace wire shall be installed in all local fibre optic cable ducts.

The trace wire shall be a copper-based wire with at least two conductors of 1.5mm2, individually

insulated, overall insulated. This is not applicable to pre-installed co-extruded trace wire.

If an air-blown micro-duct contains a built-in trace wire or sheath, a separate trace wire will not be

required.

2.7 Plugging Ducts

Cable ducts entering chambers shall be trimmed such that they protrude no more than 40mm from the

chamber wall and sealed with Telecrete or similar to avoid water seepage.

After installation of cables, all duct (but not sub-duct or micro-duct) entrances shall be filled with a

watertight, non-hardening sealant that can be removed as necessary in future to install more cabling.

All unused ducts, sub-ducts and micro-ducts shall be plugged with removable plugs or tight-fitting caps to

prevent ingress of water and soil.

Page 13: ITS specification Duct Supply and Installation (ITS-02-01)

Page 7

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

2.8 Above Ground Ducts

Concrete Encased Ducts 2.8.1

Where it is impractical to install ducts in trenches with the minimum cover requirements the ducts shall be

encased in concrete.

Where the duct is above ground the concrete cover to the ducts shall be a minimum of 50mm of concrete

below and on each side of the ducts and a minimum of 100mm on top of the ducts.

Concrete for encasing the ducts shall be minimum 17.5 MPa compressive strength concrete.

Mark all such lengths of encased duct at intervals of approximately 25m with the legend “ITS Cables”

clearly imprinted a depth of 5mm in the concrete during finishing.

The concrete surface shall be trowel or float finished to provide a smooth surface.

Galvanised Steel Conduit 2.8.2

Where ducts are exposed above ground and not encased in concrete. Galvanised steel pipe conduit

securely fixed in place with non-corroding, vibration resistant and UV stable fixings shall be used. The

design of above ground ducting shall consider the ability to pull cables around bends and deviations in

the duct (for example, at bridges). Access plates for cable pulling or jointing boxes shall be provided

where necessary.

The size and numbers of galvanised steel conduits shall be sufficient to match the size and numbers of

ducts provided for underground ducting connected.

All bends in the galvanised steel conduit shall be sweep bends with a minimum radius, which will be a

function of the diameter of the tube and elongation required.

Bending radius = 0.5x diameter of tube / % elongation required. The % elongation =

42% for AKDQ steel

60% for annealed 304 stainless steel

33% for annealed 409 stainless steel

Screw joints shall be fitted at 90 degree bends so the bend section can be removed for cable installation.

The galvanised steel conduit shall be fixed with galvanised steel saddles at regular intervals of not more

than 2.0m to the adjacent supporting structure.

All galvanised steel conduit shall be proved and have trace wire and draw tape installed.

Figure 3. Typical galvanised steel ducting on the side of a bridge.

Galvanised steel conduit shall not be attached to safety rails or rail posts or interfere with their

performance in the event of a crash.

Page 14: ITS specification Duct Supply and Installation (ITS-02-01)

Page 8

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Duct installation

2.9 Handling

Duct shall be given adequate support at all times when being handled. Care shall be taken at all times

when transporting it, loading and unloading to avoid sharp shocks, damage to ends of duct, or damage

from sharp objects to the walls of the duct. Any duct damaged must be rejected.

When stacking uPVC duct, the duct socket ends shall to be placed alternately with the sockets protruding

to avoid distortion of the duct. For long term stacking, each layer shall be separated with wooden packers,

each at least 50mm wide, at 1000mm centres. No more than six layers shall be stacked.

2.10 Trenching

Excavation 2.10.1

All excavations for trenches shall be to the lines shown on the drawings and to such directions as may be

given by the Engineer.

The excavations shall be open trenches unless the written permission of the Engineer is obtained for

other construction methodology.

Not more than 100 metres of trench shall remain open at one time unless otherwise approved by the

Engineer.

In excavating trenches any surfacing materials shall be salvaged and stockpiled as far as possible so as

to be replaced after the trench has been backfilled. Any surfacing materials lost shall be reinstated by the

Contractor at his own expense.

All spoil from the trench shall be kept away from the edge of the trench at the top to avoid overloading the

trench sides and to comply with the HSE Regulations.

Surface Cutting 2.10.2

The edge boundaries of trenches and excavations shall be marked on the surface in a line type or

coloured that is different from markings for existing services.

In sealed areas the sealed surface shall be neatly saw cut set back from the edge of the excavation. The

setback shall be 150mm for a trench width of 30mm or less, and 300mm elsewhere. In unsealed areas

the edge of the surface opening shall be kept as neat as possible.

Where the surface consists of cobblestones or pavers, these shall be carefully removed and stored for

reinstatement. Any damaged paver units shall be replaced by the Contractor.

Should the sides of the excavation slump, or the surface surrounding the edge of the excavation become

depressed, then the cut shall be opened wider until a stable sub-surface is found. This additional

excavation shall be at the Contractor’s cost.

Dewatering Trenches 2.10.3

The Contractor shall maintain all trench bottoms free from flowing or accumulated water, so that all ducts

can be bedded, laid and jointed in dry working conditions.

The Contractor shall provide sufficient labour and plant, and maintain all drains, pipes, pumps and sumps

to keep the works clear of water to the satisfaction of the Engineer.

Page 15: ITS specification Duct Supply and Installation (ITS-02-01)

Page 9

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

All water shall be disposed of to the approval of the Engineer and any damage caused shall be made

good by the Contractor at its own expense.

Support of Trenches 2.10.4

All work involving excavations must comply with the requirements in the HSE Act and the HSE

Regulations and OSH Best Practices.

Excavations shallower than 1.5 metres

Excavations shallower than 1.5m shall not necessarily be regarded as safe from the risk of collapse. The

Contractor shall consider such excavations on a case by case basis and determine if special precautions

or work methods are necessary.

Excavations 1.5 metres or deeper

Excavations greater than or equal to 1.5 m deep are particularly hazardous and must be supported or

benched back to a safe slope, as determined by the Contractor, in accordance with the HSE Regulations.

Duct Installation in Trenches 2.10.5

The floor of the trench shall be clear of any obstacles and shall be as flat as possible. It shall be de-

watered prior to installation of bedding material. If the bottom of the trench is naturally occurring rock, or

has stones, gravel or other sharp material in occurrence, a 50mm granular layer shall be laid and

compacted before the bedding layer is laid.

Bedding material shall be laid to 50mm minimum thickness (compacted) over the bottom of the trench.

Bedding material shall be clean imported sand free of larger sharp particles conforming to GAP 7.

Ducts shall be jointed before laying at the side of the trench or immediately above it on timber supports.

Prior to making the joint the duct checked for any internal damage or defects in the duct. Any damaged or

defective duct shall be discarded.

The duct shall be carefully lowered, not dropped, onto the bedding material. Open ends of ducts shall be

kept plugged to ensure material cannot enter ducts.

Ducts shall be laid with at least 50mm clearance to the trench walls, and shall be held in place with

packers as required. The packers shall be removed progressively as the bedding material is laid over the

ducts. Bedding material shall be laid over the ducts to a compacted thickness of 100mm.

Where more than two ducts are laid, they shall be laid with purpose made spacers and strapping which

shall bind the ducts tightly in the formation during installation, backfilling and for the whole life of the duct.

The spacing of the strapping shall be such that the ducts shall not separate by more than 50mm. This

spacing would typically be 1m. Spacers shall not cause damage to the ducts during installation or in

service. The spacer shall ensure that there is sufficient room for jointing collars.

Jointing Ducts 2.10.6

uPVC ducts shall be jointed with solvent cement of a type recommended by the duct manufacturer so as

to form a “solvent weld” joint. HDPE ducts shall be joined using the best method recommended by the

duct manufacturer to give a watertight seal. Prior to making the joint the duct shall be prepared by cutting

the spigot end square and de-burring the inside and outside edges and the joint surfaces and

components cleaned. Measures shall be taken to prevent soil or other material from entering ducts.

The ducts to be jointed shall then be dry fitted to ensure the inserted duct fits in at least two-thirds of the

way into the socket. Each duct shall be anchored to prevent movement before the work is completed.

Ducts shall not be jointed in adverse weather that may affect the quality of the joint.

The duct surfaces to be jointed together shall then be cleaned and degreased immediately before laying

with a fluid recommended by the manufacturer. The solvent cement shall then be uniformly applied over

Page 16: ITS specification Duct Supply and Installation (ITS-02-01)

Page 10

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

the surfaces to be jointed. The ducts shall then be connected and fully inserted without twisting the ducts,

and any surplus cement wiped off. The joint shall be left for at least 10 minutes undisturbed to allow the

joint to cure.

Solvent cements shall be kept in sealed containers at all times when not in use. Should the cement

become contaminated with foreign material (dirt etc.), then it shall be discarded. Solvent cement is a

volatile compound and shall be treated with care. Keep naked flames well clear of the cement, and

ensure adequate ventilation at all times when applying it.

Ducts will expand and contract with temperature changes. To minimise the chance of joints pulling apart,

when laying ducts in ground, the backing-filling shall be kept as close to the work face as possible. By

doing this, the ducts will have normalised to ground temperature.

Where air-blown ducting is directly buried, direct-buried connectors sourced

from the supplier of the ducting shall be used.

For 1-way direct buried 5mm OD/3.5mm ID micro-duct, remove adequate amount of

outer sheath to ensure that the inner micro-duct is pushed past the O-ring in

the connector, when joining or connecting to the air-blown fibre backbone

duct.

Figure 4. Example of a direct-buried ducting connector being installed. These connectors allow a spur to

be broken out of the duct line. The spur itself is broken out from the backbone fibre at an upstream joint.

The spur fibre is thus blown from joint to asset through this connector. This enclosure is direct-buried into

the trench (visible on the right). These are green ultra-fast broadband ducts.

Backfilling of Trenches 2.10.7

Ducts in trench shall be backfilled over as soon as is practicable after they have been laid, bedded and

jointed as specified.

Excavated materials shall only be used for backfilling where the excavation to be backfilled is in a

grassed or planted berm.

Page 17: ITS specification Duct Supply and Installation (ITS-02-01)

Page 11

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

In sealed or unsealed roadways, driveways or footpaths hardfill shall be used and the surplus excavated

material disposed of off the site.

Hardfill shall be GAP 65 laid in layers not exceeding 200mm and each layer compacted to a density of

90% of the optimum dry density as defined by test 4.1 in NZS 4402.

Full use shall be made of hand operated compaction tools on each side of the ducts and within a height of

0.6m above the crown of the ducts. Heavy construction equipment and heavy compaction plant shall not

be operated over or near the ducts until backfilling is completed.

Compaction requirements for fill material and the specification for the types of allowable fill material shall

be as per NZS/AS 3725.

2.11 Directional Drilling or Thrusting Ducts

Ducts for cables under trafficked carriageways shall be installed by directional drilling or thrust boring.

The directional drilling or thrust shall be made to provide a minimum cover of 2.0m at any point under a

carriageway along the length of the duct installed.

Before the design is complete, the designer must satisfy himself that sufficient space is available to set-up

the drilling rig in order to reach the required depth before the drill passes beneath the carriageway.

Additional permission may be required from adjacent landowners outside the highway designation for

temporary access.

The duct routes installed by directional drilling or thrusting shall be kept as straight as possible.

All pits required for directional drilling or thrusting shall comply with the requirements for excavation and

shall be kept as small as possible.

The ground surface at these pits shall be reinstated to the same condition as the adjacent surface.

Open ends of thrust ducts shall be kept plugged to ensure that material cannot enter the ducts.

Spoil from the drilling machinery and excavations shall be contained within the site, and shall not be

permitted to enter storm-water drains, natural drains, streams etc. The Contractor shall remove all spoil

from site at completion of drilling/thrusting at that site.

The minimum duct size for cross-carriageway thrusts is 100mm.

2.12 Jointing Chambers and Pull Pits

The supply and installation of jointing chambers and pull pits and the connection of ducts into the

chambers and pits shall comply with NZTA ITS specification ITS-02-02: Jointing Chambers and Pull Pits.

2.13 Proving Ducts

All ducts installed shall be proven as intact and free of obstacles by drawing a suitably sized mandrill

through the length of the duct, once installation of the duct is complete. Any damaged areas shall be

excavated, removed or repaired and re-tested until a satisfactory test is achieved.

Air-blown fibre ducting shall be tested for continuity using an approved

method (such as the ball chain test method) and pressure tested as per

manufacturer’s recommendation.

Page 18: ITS specification Duct Supply and Installation (ITS-02-01)

Page 12

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Appendix A: Drawings 3.0

Jointing Chamber and Pulling Pit 000-0000-0-7104-01-R2

Detail of Duct Installation Highways and Motorways 000-0000-0-7104-02-R2

Page 19: ITS specification Duct Supply and Installation (ITS-02-01)

Page 13

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Jointing Chamber and Pulling Pit

Page 20: ITS specification Duct Supply and Installation (ITS-02-01)

Page 14

NZ Transport Agency’s ITS specification: Duct supply and installation (ITS-02-01)

Revision 5

Detail of Duct Installation in Highways and Motorways