ITS NCID Next Generation (NG)

Project Overview February 24, 2010

Page 2: ITS NCID Next Generation (NG) Project Overview February 24, 2010

Agenda Welcome & Introductions NCID Next Generation Overview   Proposed Migration Schedule Administrative Business Process Changes Agency Involvement & Level of Effort Migration Overview Q&A

Page 3: ITS NCID Next Generation (NG) Project Overview February 24, 2010

NCID Next Generation Overview Purpose & Objectives of NCID NG

Better Reliability Better Scalability & Performance Updated User Interface

Where are we today? 153,000 Active NCID users 55 Integrated Applications Approximately 3,500 Password Changes on Mondays DEV environment set to be released end of Q1 Pre-Prod & Production environments being provisioned

What are the remaining project milestones? Pre-Prod available for Agency Use end of Q2 Production available for Agency Use end of Q3 Agency Applications Finish Migration by 12/31/2010

Page 4: ITS NCID Next Generation (NG) Project Overview February 24, 2010

Proposed Migration Schedule Application Migration Proposed Schedule will be

sent to current NCID customers this week Agency Response needed by 3/1/10 for each

application’s migration dates in Dev, Pre-Prod & Production

Confirm agency contact per application User and Delegated Administrator Migration

Proposed Schedule will be sent shortly

Page 5: ITS NCID Next Generation (NG) Project Overview February 24, 2010

NG New Business Processes All accounts will require an email address Business & Individual accounts will continue to self-register, but

must respond to email link to complete registration New State & Local Gov’t employees will no longer self-register.

Delegated Admins will create their accounts. Accounts will auto-unlock after 1 hour. Any combination of 3 wrong

passwords or challenge question responses will lock an account Account transfer (Agency-to-Agency) will be enabled for State

employees Lost User ID recovery enabled via email

Page 6: ITS NCID Next Generation (NG) Project Overview February 24, 2010

What is Your Role in NG? Actively Participate in Scheduling &

Migrating Your Applications Have Your Delegated Administrators &

Application Admins Participate in Training That Will be Provided

Page 7: ITS NCID Next Generation (NG) Project Overview February 24, 2010

Migration Process NCID & NG Co-Existence

Synch of Identities between NCID NG & current NCID Administrate from current system (until Agency users migrate,

whereupon Administration occurs from NG) Single Sign-On from NCID NG to NCID

Transition to NG Phased Training & Migration of Delegated Admin Functions Phased Migrations of Users to NCID NG self-service functions Phased Migrations of Applications to NCID NG Users will have to select & answer New Challenge Questions

Page 8: ITS NCID Next Generation (NG) Project Overview February 24, 2010

Migration Impact Model-2 Applications

Minimal Impact Point to new NG infrastructure

Web Services Applications Minimal Impact Web Service Calls remain the same Point to new NG infrastructure

User GUID’s remain the same, but RDN’s will change Model-1 Applications

Reverse Proxy Architecture Replaces WebGates DNS traffic re-routed to Reverse Proxy SSL Certs Installed on Reverse Proxy User GUID’s remain the same, but RDN’s will change

Page 9: ITS NCID Next Generation (NG) Project Overview February 24, 2010

Model-1 Migration Impact

Reverse Proxy

SSL 1 SSL 1 SSL 3

Load Balancer Web Application

Novell IDP Server

Public DNS Entry

Public SSL Cert Private (Self-Signed) SSL Cert& DNS Entry

User AuthenticationRedirect

SSL 2

SSL 2

Oracle Access Service

Public SSL Cert& DNS Entry

User AuthenticationRedirect

SSL 1

WebGateOracle API

Web Application

NCID Current Model-1

NCID NG Model-1

Page 10: ITS NCID Next Generation (NG) Project Overview February 24, 2010

User Relative DN Changes GUIDs Remain the Same

Relative DN pretext changes Current RDN:

Examples: (State) cn=User-guid,ou=Internal,ou=People,dc=NC(External) cn=User-guid,ou=Local Government,ou=External,ou=People,dc=NC

cn=User-guid,ou=Business Users,ou=External,ou=People,dc=NCcn=User-guid,ou=Individuals,ou=External,ou=People,dc=NC

NG RDN:

Examples: (Internal) cn=User-guid,ou=State,ou=Internal,ou=People,o=NCcn=User-guid,ou=Local,ou=Internal,ou=People,o=NC

(External) cn=User-guid,ou=Business,ou=External,ou=People,o=NC cn=User-guid,ou=Individual,ou=External,ou=People,o=NC

Page 11: ITS NCID Next Generation (NG) Project Overview February 24, 2010

What can you expect from ITS? Ongoing communication:

FAQ Website - https://www.ncid.its.state.nc.us/NCID_FAQ2.asp

Communications Hub –https://communications.its.state.nc.us/

Monthly Updates NCID Integrator collaboration with Agency

Application contacts Coordination of Applications Moving to Dev

Starting 3/31/2010

Page 12: ITS NCID Next Generation (NG) Project Overview February 24, 2010

Questions and Answers

Chat Questions- noted during presentation Open Question period