ISSUES WITH RETROFIT REQUIREMENTS FOR HVRT
1
CURRENT SITUATION
• WGRs HAVE HAD A CLEAR LIMIT OF 1.1 pu SPECIFIED FOR HVRT IN THE GUIDES
• WGRs ARE NOW BEING DEVELOPED THROUGHOUT ERCOT IN MANY STAGES OF COMPLETION BASED UPON CURRENT STANDARDS
• ERCOT PANHANDLE STUDIES INDICATE CERTAIN CONTINGENCIES CAN RESULT IN VOLTAGE SWINGS EXCEEDING 1.1 pu
2
CURRENT SITUATION
• CURRENTLY DEVELOPERS ARE CONTACTING VENDORS AND PERFORMING STUDIES TO DETERMINE THE ABILITY TO COMPLY WITH HIGHER HVRT REQUIREMENTS
• A NERC HVRT STANDARD (PRC-024) IS BEFORE FERC FOR FINAL APPROVAL; IF APPROVED, PRC-024 ALLOWS FOR A 5 YEAR PHASE IN
3
KEY ISSUES/QUESTIONS
• IT IS NOT CLEAR WHY THE CURRENT HVRT STANDARDS ARE NOT WORKABLE
• DEVELOPERS MAKE SIGNIFICANT COMMITMENTS WELL BEFORE THEY SIGN THE SGIA MAKING UNTIMELY CHANGES COSTLY
• THE COMPLETED TSP FISs IN THE PANHANDLE DO NOT INDICATE ANY VOLTAGE SWING PROBLEMS
4
KEY ISSUES/QUESTIONS
• UNDER WHAT CONDITIONS DO THE STUDIES INDICATE POSSIBLE PROBLEMS
• ARE THE MODELS CORRECT• CHANGES TO STANDARDS MUST BE MADE
WITH ENOUGH LEAD TIME TO ALLOW THE INDUSTRY TO RESPOND EFFICIENTLY
• NEW HVRT STANDARDS APPLIED TO THE POI ARE FAR MORE DEMANDING THAN HVRT STANDARDS APPLIED TO THE TURBINES
5
KEY ISSUES/QUESTIONS
• ANY CHANGES THAT ARE SHOWN TO BE NECESSARY AND EFFICIENT MUST BE PHASED IN (PRC-024 ALLOWS FOR 5 YEARS FOR FULL IMPLEMENTATION)
• IF NEED IS DEMONSTRATED ONLY IN THE PANHANDLE, THEN OTHER AREAS SHOULD NOT BE INCLUDED IN NEW STANDARDS
• IF NEED IS DEMONSTRATED THEN ALL TECHNOLOGIES IN THE PANHANDLE SHOULD BE INCLUDED, NOT JUST WGRs
6
KEY ISSUES/QUESTIONS
• COMPLIANCE EVALUATION CRITERIA NEED TO BE ESTABLISHED WHICH PROVIDE MODELING REQUIREMENTS AND ASSUMPTIONS TO BE USED BY DEVELOPERS/TSPs
• THRESHOLDS OF PANHANDLE DEVELOPMENT NEED TO BE ESTABLISHED WHERE THE HIGH VOLTAGE PROBLEMS FIRST APPEAR
7
WGR PROJECT DEVELOPMENT