Upload
dinhhanh
View
214
Download
0
Embed Size (px)
Citation preview
ISSUES AND CHALLENGES IN CONSTRUCTION OF ROLLER COMPACTED CONCRETE DAM IN MALAYSIA
ASSRUL REEDZA BIN ZULKIFLI
A project report submitted in partial fulfilment of the
requirements for the award of the degree of
Master of Science (Construction Management)
Faculty of Civil Engineering
Universiti Teknologi Malaysia
JUNE 2013
iv
ACKNOWLEDGEMENTS
Alhamdulillah, thank you Allah (Sub‟hanahuWata‟alah) Who create us, give
us life, wisdom, strength, protection, guidance, and made it possible for successful
completion of my program. I would first and foremost render my appreciation to my
parents, En. Zulkifli bin Md. Naim and Pn. Maznah binti Darus who were the
strength of my life.
I would also like to acknowledge the effort and assistance of my supervisor
Mr. Abdul Rahim bin Abdul Hamid for the encouragement, advice and guidance
which helped me in understanding my research and gave me the opportunity to
expand my views to pursue this research up to this stage.
Unforgotten to all the respondent who are willing to be the participate in this
study. Your cooperation is really appreciated. I will not forget all your kindness and
thank you very much.
v
ABSTRACT
Rapid and economical construction are among numerous advantages of the
construction of roller compacted concrete (RCC) dam compared to conventional
dam. However, the complex process of RCC dam construction is facing difficulties
due to lack of understanding and involvement from the local construction player
since this type of construction in Malaysia is still new. Therefore, the objectives of
this study is to examine the process of RCC dam construction and the issues and
challenges during construction stage of RCC dam project in Malaysia. The study on
the literature of RCC dam construction was performed to get the real view on the
construction process of such project. The expert panel interview was conducted to
get the view on RCC dam construction. Panel interview result was analysed and
relate it to the literature to gather the process of RCC dam construction, and to
further capture the issue and challenges of RCC dam construction. The results show
that the main construction processes consists of determination of mix design, RCC
production and RCC placement. Major issues and challenges in RCC dam
construction was to place a high volume of RCC and to ensure the quality of RCC
placement. Those issue and challenges during construction stage was overcome by
controlling the temperature during RCC placement.
vi
ABSTRAK
Tempoh pembinaan yang singkat dan pantas dan kos pembinaan yang rendah
adalah antara kelebihan pembinaan empangan konkrit termampat (empangan RCC)
berbanding empangan konvensional. Walau bagaimanapun, proses pembinaan
empangan RCC yang kompleks, menyebabkan kesukaran dalam pembinaan projek
seumpama ini di Malaysia. Ini kerana kurangnya pemahaman dan penglibatan dari
pemain industri pembinaan tempatan dalam projek empangan RCC disebabkan jenis
pembinaan ini masih baru di Malaysia. Objektif kajian ini adalah untuk mengkaji
proses pembinaan empangan RCC dan mengenal pasti isu-isu dan cabaran semasa
peringkat pembinaan projek empangan RCC di Malaysia. Kajian literatur mengenai
pembinaan empangan RCC di buat untuk mendapatkan gambaran sebenar mengenai
proses pembinaan projek itu. Temubual dengan pakar dalam pembinaan empangan
RCC telah dijalankan untuk mendapatkan data utama dalam kajian ini. Keputusan
temu bual pakar dianalisis dan dikaitkan dengan literatur untuk mendapatkan
keputusan proses pembinaan empangan RCC, dan untuk mengenalpasti isu-isu dan
cabaran dalam pembinaan empangan RCC. Keputusan menunjukkan, proses utama
pembinaan empangan RCC adalah terdiri daripada penentuan campuran konkrit
(RCC), pengeluaran campuran RCC dan penempatan campuran RCC. Isu dan
cabaran utama dalam pembinaan empangan RCC ialah jumlah campuran RCC yang
tinggi diperlukan untuk membentuk empangan dan untuk memastikan kualiti semasa
kerja-kerja penempatan RCC dijalankan. Pengawalan suhu semasa proses
penempatan RCC adalah salah satu cara mengatasi isu dan cabaran tersebut.
vii
TABLE OF CONTENTS
CHAPTER TITLE
PAGE
DECLAIRATION
DEDICATION
ACKNOWLEDGEMENTS
ABSTRACT
ABSTRAK
TABLE OF CONTENTS
LIST OF TABLES
LIST OF FIGURES
LIST OF ABBREVIATIONS
ii
iii
iv
v
vi
vii
x
xi
xiii
1 INTRODUCTION
1.1 Study Background
1.2 Problem Statement
1.3 Aim and Objectives
1.4 Scope and Limitation of Study
1.5 Significant of Study
1.6 Arrangement of the Report
1
1
2
4
4
5
5
2 LITERATURE REVIEW
2.1 Introduction
2.2 Advantage of Roller Compacted Concrete dam
2.3 Definition of Roller Compacted Concrete Dam
2.4 RCC Mixture
7
7
8
9
11
viii
2.5 Design and Construction Consideration
2.6 Properties of RCC Dam
2.7 Construction Method and Equipment
2.7.1 RCC Production
2.7.2 RCC transportation
2.7.3 RCC Placement at Dam Site
2.7.4 Lift Surface
2.7.5 Grout Enriched Roller Compacted concrete
2.7.6 Foundation Preparation
2.8 Issue and Challenges
2.8.1 Site Condition
2.8.2 During Construction Stage
2.8.3 Requirement of Temperature Control
13
14
14
15
16
18
21
21
22
23
23
24
25
3
4
RESEARCH METHODOLOGY
3.1 Introduction
3.2 Data Collection
3.3 Interview Design
3.4 Data Analysis
3.5 Respondent for Interview
RESULTS AND DISCUSSION
4.1 Introduction
4.2 Background of Respondent and Answer
4.3 Interview Data Analysis
4.4 Background of RCC dam in Malaysia
4.5 Construction Process of RCC dam
4.5.1 Determination of RCC mix
4.5.2 Aggregates Production
4.5.3 Foundation Preparation
4.5.4 Diversion Culvert and River Diversion
4.5.5 RCC mix production
4.5.5.1 Trial Embankment
27
27
28
29
31
33
34
34
35
36
44
44
47
48
48
51
52
53
ix
5
4.5.6 RCC Placement Works
4.5.6.1 Placement Preparation
4.5.6.2 Surface Preparation
4.5.6.3 Transport, Spread and Compact
4.5.6.4 GERCC Application
4.5.6.5 Transverse joint, Drain hole and Water
Stop
4.5.6.6 RCC Curing
4.5.7 Laboratory Testing and Quality Control
4.5.8 Instrumentation Works
4.6 Issues and Challenges of RCC dam construction
4.6.1 General Issues and Challenges
4.6.2 Technical Issues and Challenges-Refer to
construction process
4.6.2.1 Determination of RCC mix
4.6.2.2 Aggregates production
4.6.2.3 Foundation preparation
4.6.2.4 RCC placement
4.6.2.5 High volume of RCC placement
CONCLUSIONS AND RECOMMENDATION
5.1 Introduction
5.2 Conclusions
5.3 Limitation of Study
5.4 Recommendation for Further Research
53
54
56
56
59
61
63
63
67
68
71
72
72
73
73
74
75
76
76
76
78
78
79
82 - 84
REFERENCES
APPENDIX A
x
LIST OF TABLES
TABLE NO. TITLE PAGE
4.1
4.2
4.3
4.4
4.5
4.6
Respondent interview session
Interview question and answer
Laboratory testing and quality control for the RCC dam
Instrument installed at Batu Hampar dam
General issue and challenges and solution at Batu
Hampar dam
Technical issues and challenges and solution at Batu
Hampar dam
36
38 - 43
65 - 66
67
69
70
xi
LIST OF FIGURES
FIGURE NO. TITLE PAGE
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
3.1
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
Comparison RCC dam and other type of dam
RCC dam at Kinta dam
RCC production plant- continuous pugmill type
Conveyor System with mobile side discharge belt
Typical work layout for the RCC placement operation
Equipment used for spreading and compaction of RCC
dam
GERCC application using pocker vibrator at Kinta dam
Typical RCC dam construction process
Research methodology flow chart
View of RCC dam taken from as-built drawing of Batu
Hampar dam
Section view of Batu Hampar dam
Work Breakdown Structure of RCC dam construction
RCC foundation preparation at Batu Hampar dam
Portable drilling machine for foundation grouting
works
Remove overburden and rock scaling works at the river
portion
RCC Production Plant- Continuous Pugmill
Routine of RCC placement
Carpenter are fixing the formworks at upstream of the
dam
9
11
16
18
20
20
22
26
32
45
45
46
49
50
51
52
54
55
xii
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
Concrete block are arrange across the dam to form
downstream step
Dump truck was used to transport RCC mix direct to
dam site
Conveyor system used to Transport RCC Mix direct to
dam site
RCC placement routine works
Applying GERCC at upstream face of RCC
Smooth finishing at upstream of the dam
Water stop, drain hole and transverse joint location
Transverse joint installation
Vebe test equipment
Installation of instrumentation at Batu Hampar dam
55
57
58
59
60
61
62
63
66
68
xiii
LIST OF ABBREVIATIONS
ACI - America Concrete Institute
ASTM - American Standard Testing Material
GERCC - Grout Enriched Roller Compacted Concrete
RCC - Roller Compacted Concrete
USACE - United State Army Corps of Engineer
CHAPTER 1
INTRODUCTION
1.1 Study Background
Roller Compacted Concrete (RCC) has been rapidly developed over the past
40 years and commonly used for gravity dam application. Willow Creek Dam at
Willow Creek was the first Roller Compacted Concrete Dam in history which was
constructed by the Army Corps of Engineers between November 1981 and February
1983. There are numerous advantages of roller compacted concrete dam compared to
conventional dam has lead to the acceptance of this type of dam technology is and
are being used extensively in China, Japan, Spain, Brazil and elsewhere in Asia and
Southeast Asia.
In Malaysia, the first dam project which adopted RCC technology is Kinta
Dam was completed in March 2006. RCC dam is new to Malaysia construction
industry and the understanding on the construction of this type of dam is still at the
beginning stage. The local construction player such as a local consultant and
contractor has limited knowledge about RCC dam construction which leads to the
RCC dam construction in Malaysia facing many difficulties.
2
The process of construction of RCC dam is complex should be taken as a
positive challenge to the construction industries in Malaysia. Rapid and cheaper
construction are among the numerous advantage of constructing this type of dam.
The construction industry stakeholder such as the government need to benefit from
the numerous advantages which can give a significant impact to economy,
environment and social.
1.2 Problem Statement
RCC dam has numerous advantages over a conventional dam such as rapid
construction period and cheaper construction. The history of RCC technology began
in 1970 and from there on many of RCC dam projects were constructed in China,
Japan, Spain, Brazil and elsewhere including Southeast Asia.
For the large gravity dams, the projects can easily attract the big and well
known heavy and civil engineering contractors who were successful in applying their
overall construction knowledge in working with RCC dam. Today many of the
gravity dam projects require some degree of prequalification for contractors (Bass,
2004). Allen (1992) has state that in his article title RCC dam construction. A
contractor's view, construction team must be more than technically skilled and
experience to manage RCC dam project.
The first RCC dam project in Malaysia was Kinta dam situated in Ipoh and it
was constructed by Japanese contractor (Hazama Corporation) which was completed
in 2007. In 2008, Batu Hampar dam project then becomes the second RCC dam
project in Malaysia. “Dekon Sendirian Berhad” (Dekon), the local contractor who
had no previous experience of RCC dams was selected to construct the dam. The
government intention to develop local knowledge or expertise of RCC instead of
3
recourse to international contractor was the main reason why Dekon was selected to
undertake that project (Wagner, 2011).
Based on the above fact, RCC dam was considered new to the Malaysian
construction industry. Hence, the understanding and involvement from the local
construction players were still at the beginning stage. The construction personnel
such as engineer, supervisor, technician and even the general workers have very
limited knowledge, skills and experiences on the RCC dam project that lead to the
construction of RCC dam in Malaysia facing many issues and challenges both in the
technical and management aspects during construction. According to Bass (2004),
during the early years of RCC projects, even contractors had little to no experience
working with RCC.
By referring to real situation on construction of RCC in Malaysia, therefore
there is need to develop knowledge on construction of RCC dams among the local
construction industries player in order to benefit from the numerous advantage of
RCC dam construction. Refereed journals that discuss about the design aspect of
RCC dam are there, but not many report about the issues and challenges faced by the
construction team during construction period. Hence, there is a need to capture the
knowledge of RCC dam construction in term of process, issue and challenges during
construction stage.
This study will serve as an avenue for further understanding on construction
of RCC dam among the local construction industry players.
4
1.3 Aim and Objectives
The aim of this master project is to explore the construction process of the
Roller Compacted Concrete dam project in Malaysia. To achieve this aim, the
objectives of the study are as follows:
1. To examine the process of the construction of RCC dam
2. To identify the issue and challenges in construction of RCC dam
3. To investigate how certain issues and challenges were overcome during
construction stage
1.4 Scope and Limitation of Study
Scope of this study will focus on the perspective on construction of RCC dam
project during construction stage. The study only covers the physical construction
works in RCC dam construction project. The construction of RCC dam in Malaysia
is chosen as suitable case study due to the fact that only recently Malaysia has
adopted the RCC dam technology in the construction of the dam project.
Batu Hampar dam project will be used as a main case study to fulfil the aim
and objectives of this study. The respondents are chosen from the construction
personnel who were involved in the Batu Hampar and Kinta dam project which
consist of the professional and semi professional individuals.
The literatures search indicated a few study about the specific design aspect
of RCC dam construction project in term of the behaviour, characteristics and
5
performance of the RCC dam. However, the study on RCC dam construction in
Malaysia is not commonly covered by the refereed journals.
1.5 Significant of Study
The understanding and involvement from the local construction player on
construction of RCC dam is still at the beginning stage. To benefit from the
numerous advantage of RCC dam construction, there is need to develop knowledge
on construction of RCC dams among the local construction industries player. The
study will serve as an avenue for further understanding on construction of RCC dam
among the construction industries player. Throughout this study, the knowledge of
RCC dam construction in term of process, issue and challenges during construction
stage will be exposing to the public and the construction industries player can benefit
from it.
1.6 Arrangement of the Report
This master project report consists of five (5) chapters which are the
introduction, literature review, methodology, result and discussion, and conclusion.
Introduction chapter describes the background and the need to study the RCC dam
construction in Malaysia.
The literature review chapter describes the definition, characteristic and
process of RCC dam construction which was gathered from various sources such as
books, conference journal, engineering manual, journal paper and from the author
6
personal document. Most of refereed journals on this study matters come from the
various author who are experienced in RCC dam construction in others country
including Malaysia.
Research methodology chapter explains the methods used to conduct this
study which is taken from the author’s experience in RCC dam construction, expert
panel interview and supported with the refereed literature.
The interview data (primary data) and the literature review (secondary data)
was analysed and the results are discussed in Result and Discussion chapter. Then,
the conclusions are made based on each of the objectives of this study as described in
conclusion chapter.
79
REFERENCES
Allen, J. C. (1992). RCC dam construction. A contractor's view. Proceedings of the
3rd ASCE Specialty Conference on Roller Compacted Concrete. February 2-
5, 1992 San Diego, CA, USA: ASCE, 214-226
Bass, R. P. (1991). Alternative Dam Construction Techniques. Proceedings of the
1991 Georgia Water Resources Conference. March 19-20, 1991, Athens,
Georgia: Georgia Institute of Technology
Bass, R. P. (2003a). Improving the Safety of Our Dam Infrastructure - RCC Makes
the Grade. Proceedings of the World Water & Environmental
Resources Congress 2003: ASCE, 1-12
Bass, R. P. (2003b). Rehabilitating Dams with Roller Compacted Concrete. Bridging
the Gap: 1-9.
Bass, R. P. (2004). Hydraulic structures - Designing with RCC and soil-cement.
Proceedings of the Joint Conference on Water Resource Engineering and
Water Resources Planning and Management 2000, July 30 - August 2,
2000. Minneapolis, MN, United states: ASCE
Choi, Y., and Groom, J. (2001). RCC Mix Design—Soils Approach. Journal of
Materials in Civil Engineering, 13(1): 71-76.
Dunstan, M. R. H. (1999). Recent developments in RCC dams. International Journal
on Hydropower and Dams, 6(1): 40-45.
Forbes, B. A (2008), RCC – New Developments and Innovations, State of art of
RCD dams in Japan. Paper presented at the 50º Congresso brasileiro do
concreto, Salvador (1st Brazilian RCC Symposium September 2008)
Forbes, B. A, Hansen, Kenneth, D., Kitzgerald, Thomas, J. (2008) State of the
Practice – Grout Enriched RCC in Dams. Proceedings of the United States
Society on Dams Annual Conference. April/May 2008. Portland Oregon: 1-17
80
Forbes, B. A (2003), Using Sloped Layers to Improve RCC Dam Construction. Civil
structures, Hydro ReviewWorldwide (HRW). 11(3): 1-11
Forbes, B. A, Iskander, M.M. and Malkawi, A.I.H. (2001) High RCC Standard
Achieved at Jordan’s Tannur Dam. International Jounal on Hydropower and
Dams, Volume 7, Issue 3, June 2000.
Giang, P. H., Ngoc, N. H., and Khanh, M. H. T. (2007). The Dinh Binh RCC dam in
Vietnam. Paper presented at the New Progress on Roller Compacted Concrete
Dams Proceedings of the Fifth International Symposium on Roller
Compacted Concrete (RCC) Dams.
Hansen, K. (2008). Design considerations for small RCC dams. The international
journal on hydropower & dams, 15(3): 80.
Malkawi, A. I. H., Mutasher, S. A., and Qiu, T. J. (2003). Thermal-structural
modeling and temperature control of roller compacted concrete gravity dam.
Journal of performance of constructed facilities, 17(4): 177-187.
Nagataki, S., Fujisawa, T., and Kawasaki, H. (2008). State of art of RCD dams in
Japan. Paperpresented at the 50º Congresso brasileiro do concreto, Salvado
(1st Brazilian RCC Symposium september 2008)
Nagayama, I., and Jikan, S. (2003). 30 Years’ History of Roller-compacted Concrete
Dams in Japan. Paper presented at the Proceeding Fourth International
Symposium on Roller Compacted Concrete Dams: 27-38
Nawy, E. G. (2008). Concrete construction engineering handbook Second Edition:
Chapter 20 Roller Compacted Concrete, Salem USA: CRC LLC. Chapter 20
page 1-72
Parmar, B. J., & Shelke, V. C. (2011). ABC of RCC dam construction: Ghatghar
dam - a case study. Water and Energy International, 68(4): 25-31.
Roca, M., Sprenger, F.-D., Gross, C., Tejerina, H., and Ortega, F. (2002). La Canada
dam: Bolivia's first RCCexperience. International Journal on Hydropower &
Dams, 9(3): 82-86.
Sembenelli, P. and Shengpei, W. (1998). Chinese experience in the design and
construction of RCC arch dams. International Journal on Hydropower &
Dams, 5(5): 95-100.
Shaw, Q. H. W. (2011). Chapter 2 : RCC Construction, RCC Mixes, RCC
Instrumentation & RCC Dams Study. University of Pretoria: Ph.D. Thesis.
81
Tom Karlsson And Jonas Tallberg (2011). Concrete Face Rock-fill dam compared
to Roller Compacted Concrete dam: A case study of dam constructions in
Panama. Chalmers University Of Technology: Master Thesis.
United State Army Corps of Engineer (USACE). (2000). Engineer Manual-
Engineering and Design Roller-Compacted Concrete. EM 1110-2-2006.
Washington, D.C. : Department of the Army
Uribe, L., and Bosshart, D. (2002). Challenging RCC dam construction for the Ralco
project in Chile. International Journal on Hydropower and Dams, 9(4): 95-
99.
Wagner, C. (2011). Batu Hampar dam - design and construction of an RCC dam.
Dams and Reservoirs, 21(2): 77-90.
Warren, T., Denoyer, A., and Ulas, A. (2011). Taking advantage of RCC: Ted
Warren discusses the history of roller compacted concrete (RCC) dam
construction and its various applications and advantages to gravity dam
design and construction. International Water Power and Dam Construction,
63(7): 20-23.
Xia, Y. C., and Lin, D. F. (2012). Study on Temperature Control Method of Yeywa
Hydropower Station RCC Dam Construction. Applied Mechanics and
Materials, 170: 2110-2114.
Zhou, H., Shi, Q., and Li, Y. (2004). Study on rapid construction scheme for Longtan
high RCC dam. Proceedings of the 4th International Conference on Dam
Engineering - New Developments in Dam Engineering. Nanjing. 1139-1143
Zhu, Z. Y., Qiang, S., Liu, M. Z., and Wang, H. B. (2011). Cracking Mechanism of
RCC Dam Surface and Prevention Method. Advanced Materials Research,
295: 2092-2096.