Issue 2007-I075
Non-CSA CR sends MVO with bypass CSA Flag
Issue Non-CSA CR submits a MVO with the bypass
CSA Flag, resulting in CSA CR never knowing the ESIID is not active. CSA premise management company is left with a Unit with no power and may incur charges for permits in the hundreds of Dollars.
Data for Comparison
1/29/08 – 1/31/0802/13/08 – 03/22/08
04/01/08 – 04/20/08
Count Percentage Count Percentage Count Percentage
Total MVOs Accepted
16,762 143,217 70,651
MVOs without flag
15,208 90.73% 128,353 89.62% 63,300 89.60%
MVOs with flag from CSA CR
608 3.63% 6,621 4.37% 2,787 3.94%
MVOs with flag and no CSA CR
872 5.20% 8,007 5.59% 4,185 5.92%
MVOs with flag from another CR
74 .44% 596 .42% 379 0.54%
Data for Comparison
01/29/08 – 01/31/08 02/13/08 – 03/23/08 04/01/08 – 04/20/08
Count Percentage Count Percentage Count Percentage
Total MVOs submitted with bypass flag
1,554 14,864 7,351
MVOs with flag from CSA CR
608 39.12% 6,261 42.12% 2,787 37.91%
MVOs with flag and no CSA CR
872 56.11% 8,007 53.87% 4,185 56.93%
MVOs with flag from another CR
74 4.76% 596 4.01% 379 5.16%
Market RequirementUpon receipt of an 814_24 containing the REF~2W,
ERCOT shall validate that the CR submitting the 814_24 is also the CR with an active CSA relationship.
1. If the CSA CR is different than the CR submitting the 814_24 MVO, ERCOT will ignore the REF~2W segment and will process as a MVO to CSA.
2. ERCOT will validate CSA CR based upon DUNS Validation of DUNS on exact DUNS or (Option A) Validation of DUNS based upon umbrella DUNS (Option B)
ERCOT will not validate on the 814_24 Move Out (MVO) that includes a REF~1P~B44
ERCOT Analysis
Option A (Validation of DUNS on exact DUNS ) Initial Estimate of 180 hours for Development and Testing
With the number of hours from the high level estimate, it was determined once the PRR or SCR would go through for approval, it would be worked in a project, and can not be worked as a SIR.
Option B (Validation of DUNS based upon umbrella DUNS) Initial Estimate of 640 hours for Development and Testing In addition, in order to allow for one log-in to access information across
multiple DUNS, the parent / child relationship was not implemented in the current architecture and would require significant architecture changes (across multiple systems).
With the number of hours from the high level estimate, it was determined once the PRR or SCR would go through for approval, it would be worked in a project, and can not be worked as a SIR.
Next steps
Where do we go from here?