Ishika fertilisers limited Granulated Single Super Phosphate Project
1
Additional Information (Sought after EAC meeting dated 21.04.2015)
1. Layout map and green belt plan
1.1 Plant layout
Layout plan of the plants, associated facilities, green belt and rain water harvesting system is
presented at Annexure-I. The project proponent has acquired 8.41 hectares of land in Mantageria,
Chakturia & Sanmaninathpur villages in Kharagpur Tehsil, adjacent to the national Highway (NH-
60). The factory gate and boundary wall will be located at a distance of approx 200 metres from the
National Highway. Break-up of proposed land use for the acquired land is given in Table 1. Areas
provided for different plant facilities are given in Table 2.
Table-1: Proposed land use for plant & facilities
Sl. No Description of Plants / Facilities Area, Ha.
1. Sulphuric acid plant 0.45
2. GSSP plant, including acidulation, curing & granulation 0.73
3. Administration & amenities 0.53
4. Truck parking area 0.33
5. Rain water harvesting 0.33
6. Internal and approach roads 1.10
7. Green belt (34.7% of total area) 2.92
8. Future expansion 1.42
9. Un-utilized land 0.60
Total 8.41
Table-2: Areas under different plant sections/facilities
Sl. No Description Size in meters
1. Security, W.B. & Time Office 7.5 X 3.50 X 3.00 (H)
2. Weigh-Bridge Plate Form 8.00 X 3.00
3. Administration &laboratory 14 X 11.00 X 6.50(H)2 FLR.
4. Store Room 5.00 X 4.00 X (3.5 H )
5. Rock Phosphate Shed 48.00X 22.00X14.00
6. Gssp Shed 72.00X 24.00 X14.00>8.50
7. G.S.S.P. Plant 48.00 X 24.00X14.00>8.50
8. Green S.S.P. Shed 72.00X 22.00X14.00
9. Acid Storage Tanks Yard 27.00 X 16.00
10. Pollution Control (Scrubber) Unit 27.00 X 16.00
11. S.S.P. Plant & Machinery Shed 24.00 X 16.00 X10.00 (H)
12. Rock Storage Yard 42.00X 16.00X10.00
13. Elect. Yard & P.C.C. Room 12.00 X 5.00X4.00
14. Canteen 5.00 X 4.00X3.00
Ishika fertilisers limited Granulated Single Super Phosphate Project
2
Sl. No Description Size in meters
15. Toilet Block 5.00 X 3.00X2.50
16. MCC & VFD Panel Room 18.00 X 6.50X4.00
1.2 Green Belt Plan
The area identified for plantation and green belt development has been shown on the lay out plan
at Annexure-I. Out of the total plot area of 8.41 hectares, approx. 2.92 ha (more than 34% of total
land area) has been identified for plantation and green belt development. The project area is
agricultural land covered with fertile soil, and is suitable for the growth of tree species. However, at
present, it is devoid of any trees or plants. The following species, which are reported to prosper in the
area and known to be effective in air pollution mitigation and noise attenuation, shall be developed
under the proposed greenbelt and plantation program
1. Aegle marmelos 2. Azadirachta indica 3. Bauhinia acuminata 4. Bauhinia variegata 5. Bougainvillia sp. 6. Cassia fistula 7. Cassia siamea 8. Dalbergia sissoo 9. Delonix regia 10. Mangifera indica 11. Nerium indicum 12. Polyalthis longifolia 13. Psidium guayava 14. Syzygium cumini 15. Tamarindus indica 16. Terminalia arjuna 17. Terminalia bellerica
Dy. Manager (Horticulture), under control of Manager (EHS), will be responsible for development
and maintenance of green belt. The greenbelt development program shall be started with the start
of construction activities, i.e., immediately after the project is accorded environmental and other
statutory clearances, and will be completed within 3 years.
Plantation Program
The activities at the initial stage will consist of the following.
1. Appointment of expert/consultant for preparing a detailed plan in consultation with
local Forest Department authorities
2. Survey of the area for plantation of trees and preparation of detailed map
3. Identification of locations for plantation of saplings of different species
4. Digging of trenches and soil conditioning
5. Planting of saplings (during monsoon season)
Ishika fertilisers limited Granulated Single Super Phosphate Project
3
6. Surveillance, maintenance and irrigation of the saplings to achieve a targeted survival
rate of more than 80%.
The work plan for the second year is as follows:
1. Maintenance and irrigation of species planted earlier
2. Survey of the area to identify the locations for re-plantation of saplings
3. Plantation of saplings at the identified locations
4. Development of lawns and gardens in vacant areas around the administrative building
5. Maintenance and irrigation to achieve a targeted survival rate of 90%.
The work plan for the third year is as follows:
1. Maintenance and irrigation of species planted earlier
2. Survey of the area to identify the locations for re-plantation of saplings
3. Plantation of saplings at the identified locations
4. Identification of any remaining area within premises for afforestation and plantation of
saplings at identified locations
5. Development of lawns and gardens in vacant areas within the premises
6. Maintenance and irrigation to achieve the targeted survival rate of 100%.
The work plan for the subsequent years comprises
1. Irrigation and maintenance of saplings/trees on routine basis
2. Cleaning of afforested areas to remove undesirable species
3. Replacement of dead species with new ones.
Financial Provisions
Capital expenditure, excluding cost of land : Rs. 11.80 lakh
Revenue expenditure (annual) : Rs. 10.28 lakh
2. Enterprise Social Commitment
During appraisal of the project for grant of environmental clearance, the project proponent was
asked to earmark 5% of the project cost towards the Enterprise Social Commitment based on Public
Hearing issues and to provide item-wise details along with time bound action plan Accordingly, a
socio-economic study of the 3 nearby villages was performed to determine the socio-economic
development activities in consultation with local population and the Gram Panchyat. The study
report is attached as Annexure-II.
An amount of Rs. 3 Crore, being 5% of the total project cost (60 crore), has been earmarked
towards the various socio-economic development activities identified during Public Hearing and
the recent socio-economic study. The amount will be spent during the next 5 financial years @ Rs.
60 lakh per year.
The following issues identified during Public Hearing:
Vocational training program for the local youth for skill development
Provision of solar cookers
Ishika fertilisers limited Granulated Single Super Phosphate Project
4
Infrastructure in schools
Health camps
Farmers’ training
Women empowerment awareness programs
Environmental awareness
The additional issues identified through consultation with local population and Gram Panchayats
are as follows:
Drinking water sources
Scarcity of firewood for cooking
Domestic lighting facilities
Sanitation facilities in villages
Infrastructure and sanitation facilities in schools
Financial grants to poor students
Nutrition camps
Legal awareness program
The item wise details of proposed expenditure on CSR activities are presented in Table-3.
Table-3: Break-up of expenditure on CSR activities
Sl.
No.
CSR Activity/ Scheme Item Investment in 5
Years
1. Drinking Water Hand Pumps 1,80,000
2. Sanitation Community Toilets 6,75,000
3. Health & Medical Mobile Van 9,00,000
Health Camp 90,00,000
Free Dietary Supplements 90,00,000
4. Education Educational aids 1,50,000
Toilets 1,50,000
Scholarship 90,000
5. Skill Development Vocational training 18,00,000
6. Local Area Development Village roads upgrade 3,00,000
Plantation along roads 9,00,000
7. Energy conservation Solar cookers 13,50,000
Solar lanterns 60,000
8. Awareness programs Legal awareness 9,00,000
Environmental awareness 4,50,000
Women empowerment 18,00,000
Agricultural 3,00,000
9. Implementation & monitoring 20,00,000
Total 3,00,05,000
Ishika fertilisers limited Granulated Single Super Phosphate Project
5
3. Feasibility of utilization of Treated Effluent from nearby Industrial Area
3.1 Requirement of make-up Water
Under normal operation of the plants under the proposed project, the make-up water requirement
has been estimated at 200 KLD. Break-up of quantity and type of make-up water required for
different uses is given in Table-4.
Table-3: Quantity and type of make-up water Required for the project
Sl. Water use Qty., KLD Type of water
1. Make-up to cooling water system 32 Fresh water with low suspended solids, dissolved solids, and silica
2. Water to demineralization system for acid dilution in Sulphuric acid plant and power system make-up
48 Fresh water with low suspended solids, dissolved solids, and silica
3. Make-up water to SSP plant (acid dilution and granulation)
45 Fresh water or treated effluent (complying to specified standard)
4. Make-up water to scrubbing system 40 Fresh water or treated effluent (complying to specified standard)
5. Potable water 10 Fresh water meeting the drinking water standards.
6. Dust suppression and green belt development
10 Fresh water or treated effluent (complying to specified standard)
Thus, the proposed project can utilize 95 to 100 KLD of treated effluent, provided an assured and
regular source of the same is identified in the nearby area.
3.2 Vidyasagar Industrial Park at Kharagpur
Vidyasagar Industrial park is located at a minimum distance of 7 km to the nirth of the proposed
site for the SSP Project. West Bengal Industrial Development Corporation (WBIDC), the nodal
agency of the State Government, responsible for promoting industrialization in the State, is setting
up the Industrial Park near Kharagpur. The Industrial Park is spread over approx 1150 acres of
land, the ownership of which rests with WBIDC The Park is situated in the north – east end of
Kharagpur in West Midnapore district of West Bengal. The industrial park site is bound by NH 6
connecting Mumbai, Kolkata in the North, NH 60 towards Balasore in the East and Orissa Trunk
Road leading to the core city of Kharagpur. Kharagpur is an important railway junction, which is
bound by the Kharagpur - Howrah line of South Eastern Railway. The park is being developed
mainly for industrial manufacturing units, including their vendor parks etc.
The park is being developed mainly for industrial manufacturing units, including their vendor
parks, etc. M/s. Tata Hitachi Construction Machinery Company Limited (Formerly known as M/s
Telcon) has set up their unit in the park on 250 acres of land. They have achieved their commercial
production. A substantial area has also been earmarked for housing facilities for the employees of
the companies interested in providing the same.
Ishika fertilisers limited Granulated Single Super Phosphate Project
6
List of major units, which have already been allotted land in the Industrial Park are as follows:
M/s. Integrated Equipment & Infraservices Pvt. Ltd M/s. United Engineering Services M/s. Rabirun Vinimay (P) Ltd. M/s. Hard Rock Fabrication Pvt. Ltd. M/s. Imperial Auto Industries Ltd. M/s. Tatanagar Metal Industries Ltd. M/s. Apex Auto Limited M/s. Tractors India Limited M/s. Godrej Agrovet Limited M/s. Nutricraft India Private Limited M/s. Megatherm Transmission & Distribution (P) Ltd. M/s. Toro Processor Pvt. Ltd. M/s. Acropoly Ninomiya Pvt. Ltd. M/s. BASF Limited M/s. Ganapati Flour & Food Pvt. Ltd
It can be seen that almost all the industrial units in the park are engineering and equipment
manufacturing industries. Therefore, it is not possible to depend on the individual units for un-
interrupted supply of adequately treated effluents. However, as and when West Bengal Industrial
Development Corporation initiates work for combined effluent treatment plant, and adequate
quantity is available, the project proponent will initiate action for utilizing the same to part of its
requirements.
3.3 Other Industrial Units
Bengal Energy Limited is located at a distance of approximately 2 km to the south of the project site.
The site manufactures metallurgical grade coke. It was found that the unit does not have effluent for
disposal. Another industrial unit, Tractors India Limited, is located to the north of the project site.
TIL is engaged in manufacture of construction equipment and earthmovers, and does not have
regular source of effluent.
Associated Cement Company and Tata Hitachi have acquired significant land in the area and area in
the initial construction stage. These units are also unlikely to generate adequate effluent to facilitate
regular supply of treated effluent.
3.4 Conclusion
It is therefore, concluded that at present there is no source of uninterrupted supply of treated
effluent in the area.
4. Location of Piezometer for Monitoring of fluoride, etc
The project proponent will construct 2 piezometer wells - one near the rain water harvesting
System (which receives the run off from areas falling within the road surrounding the plants) and
the other in the south-eastern corner of the plot (which is at the lowest elevation within the plot of
land) for monitoring of ground water for fluoride and other important parameters specified under
Ishika fertilisers limited Granulated Single Super Phosphate Project
7
IS: 10500. The monitoring will be performed with a frequency of once in a month. Location of the
wells is shown in Annexure-III.
5. Soil monitoring report
Soil samples from the 6 locations were collected in the month of April and were analyzed for the
parameters analyzed earlier. Results of analysis are presented in Annexure-IV.
AANNNNEEXXUURREE II
MAIN ENTRANCE
3
21
14
1516
4
CHIMNEY
GREEN SSP SHEDROCK PHOSPHATE SHED
SSP PLANT & MACHINARY SHED
AREA RESERVED FOR
POLUTION CONTROL UNIT
BA
LL MILL
GR
P B
IN
RP
-BE
MIX
ER
AN
D D
EN
A. S. TANK 9 M. DIA.
A. S. TANK 9 M. DIA.
GSSP SHED GSSP PLANT
ROCK STORAGE YARD42 x 16 M.
48 x 22 M.
72 x 24 M.48 x 24 M.
72 x 22 M.
27 x 16 M.
APT TANK 2 x 8 x 1.5 M.
5
67
8
10
9
11
12
13
RO
AD
10.
00 M
.WID
E
Ht. 7 M Ht. 7 M
SULPHER YARD
ROAD 7.00 M.WIDE
ROAD 7.0 M.WIDE
TURBINE HOUSE
SULPHURIC ACID PLANTPLOT SIZE-100 x 70 M.
ROAD 15.00 M.WIDE ROAD 15.00 M.WIDE
ROAD 10.00 M.WIDE
RO
AD
10.
00 M
.WID
ER
OA
D 1
0.00
M.W
IDE
KEY PLAN
14 X 11.00 X 6.50(H)2 FLR.
7.5 X 3.50 X 3.00 (H)8.00 X 3.00
48.00 X 24.00X14.00>8.50
5.00 X 4.00 X (3.5 H )
8
G.S.S.P. PLANT
G.S.S.P. CHIMNEY9
SR. NO.
ADMN. OFFICE & LABORATORY
STORE ROOM
7
6
3
5
4
SECURITY,W.B. & TIME OFFICE
DESCRIPTION
WEIGH-BRIDGE PLATE FORM
1
2
SIZE IN MTRS.
GREEN S.S.P. SHED 72.00X 22.00X14.00 30.00 (H)
10
11
ACID STORAGE TANKS YARD
12
27.00 X 16.00POLUTION CONTROL UNIT
13
27.00 X 16.00
14
15
16
CANTEEN
TOILET BLOCK
5.00 X 4.00X3.00 5.00 X 3.00X2.50
ROCK PHOSPHATE SHED 48.00X 22.00X14.00 GSSP SHED 72.00X 24.00 X14.00>8.50
24.00 X 16.00 X10.00 (H)S.S.P. PLANT & MACHINERY SHED
ROCK STORAGE YARD 42.00X 16.00X10.00 ELECT. YARD & P.C.C. ROOM 12.00 X 5.00X4.00
17 MCC & VFD PANNEL ROOM 18.00 X 6.50X4.00
ISHIKA FERTILIZER PROPOSED GSSP PLANT
RAIN WATER
HARVESTING
TANK
GREEN BELT
'
NH
-60
FU
TU
RE
EX
PA
NS
ION
(B)
GR
EE
N B
EL
T
GREEN BELT
TR
UC
K P
AR
KIN
G A
RE
A
VACANT LAND(A)
FUTURE EXPANSION(A)
VACANT LAND(B)
ADMIN & AMENITIES
GSSP PLANT
8
9
S. NO.
7
6
3
5
4
SECTION NAME
1
2
AREA IN HECTARE
10
11
SULPHURIC ACID PLANT
GSSP PLANT
FUTURE EXPANSION(A)
FUTURE EXPANSION(B)
VACANT LAND(A)
VACANT LAND(B)
TRUCK PARKING AREA
RAIN WATER HARVESTING TANK
GREEN BELT
ADMIN & AMENITIES
0.45
0.73
0.53
1.01
0.41
0.19
0.40
0.33
0.33
2.92
1.1ROADS
TOTAL AREA 8.4
Annexure-I
AANNNNEEXXUURREE IIII
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd 1
M/S ISHIKA FERTILIZERS LTD
Socio‐economic Study for Enterprise Social Commitment
by Ishika Fertilizers Limited For the proposed Granulated SSP Project at Mantageria, Chakturia and Sanmaninathpur Villages, Tehsil Kharagpur, District West
Medinipur, West Bengal
M A N T E C C O N S U L T A N T S P V T L I M I T E D
Submitted By: M/S Ishika Fertilizers Ltd
Poddar Point, 1st Floor, Block A, 113, Park Street, Calcutta- 700016
West Bengal
Prepared By:
M/S Mantec Consultants Pvt Ltd
D-36, Sector-06, Noida-201301 Gautam Buddha Nagar Uttar Pradesh
Table of Contents
CHAPTER-1 : INTRODUCTION ............................................................................................................................... 1
1.1 INTRODUCTION ................................................................................................................................................ 1 1.2 NEED OF THE CSR POLICY ............................................................................................................................. 1 1.3 CONCEPT ............................................................................................................................................................. 1 1.4 OBJECTIVE .......................................................................................................................................................... 2 1.5 VISION .................................................................................................................................................................. 2 1.6 UTILIZATION ..................................................................................................................................................... 2
CHAPTER-2 : STUDY AREA ..................................................................................................................................... 3
2.1 DEMOGRAPHY OF THE STUDY AREA ......................................................................................................... 3 2.2 POPULATION OF THE STUDY AREA ........................................................................................................... 3 2.3 LITERACY LEVELS ............................................................................................................................................. 4 2.4 OCCUPATIONAL STRUCTURE ....................................................................................................................... 4 2.5 AREA IDENTIFICATION .................................................................................................................................. 5 2.6 PROJECT IDENTIFICATION ........................................................................................................................... 5 2.7 PARTNERING FOR EXECUTION .................................................................................................................... 5
CHAPTER-3 : SURVEY & OBSERVATIONS .......................................................................................................... 6
3.1 OBSERVATIONS ................................................................................................................................................ 7
CHAPTER-4 : PLANNING & IMPLEMENTATION ............................................................................................... 9
4.1 ACTIVITIES ......................................................................................................................................................... 9 4.2 BUDGET ............................................................................................................................................................ 10 4.3 COMMITTEE .................................................................................................................................................... 12 4.3.1 AUTHORITY & APPROVAL .............................................................................................................................................. 12
Table of Figures
FIGURE 1 : SURVEY CONDUCTED IN MANTAGARIYA ................................................................................................. 6
FIGURE 2 : SURVEY CONDUCTED IN CHAKTURIYA ..................................................................................................... 6
FIGURE 3 : SURVEY CONDUCTED IN SANMANINATHPUR ........................................................................................ 7
List of Tables
TABLE 1: VILLAGES FROM WHICH LAND TO BE AQUIRED ...................................................................................... 3
TABLE 2: DEMOGRAPHIC PROFILE OF THE STUDY AREA ........................................................................................ 4
TABLE 3: DISTRIBUTION OF LITERATES IN STUDY AREA ....................................................................................... 4
TABLE 4 : OCCUPATIONAL STRUCTURE ........................................................................................................................... 4
TABLE 5: CSR BUDGET ............................................................................................................................................................ 11
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 1
CHAPTER-1 : INTRODUCTION 1.1 INTRODUCTION
Ishika Fertilizers Limited, a Public Limited Company, promoted by Sanei group of
companies, propose to establish and operate facilities for manufacturing granulated single
super phosphate (SSP) in a plot of land located at Mantageria, Chakturia and
Sanmaninathpur Villages in Paschim Medinipur District of W. Bengal near NH-60, at a
distance of approximately 9 kms from Kharagpur. The plants will have in-built pollution
control devices and will be operated on zero discharge of effluent. Other facilities required
for operation of the project, viz., storage facilities, work shop, administrative building,
canteen, community centre, first-aid post, green belt, electric sub-station, truck parking,
boundary walls, internal roads, weigh bridge, etc. are also included in the project proposal.
The main raw materials for manufacture of SSP are Sulphuric acid and rock phosphate. The
project will utilize imported/indigenous rock phosphate and sulphuric acid from captive
production. Approximately 40,000 TPA of the acid will be consumed for manufacture of
SSP, and the balance will be sold out in market.
1.2 NEED OF THE CSR COMMITMENT
Based on the socio-economic studies conducted during the EIA studies and the public
hearing proceedings, the company had drawn schemes under Corporate Social
Responsibility Schemes, with a budgetary allocation of rs 4 lakh. However, during
appraisal of the project for grant of environmental clearance, the expert appraisal
committee desired that “5 % of the project cost shall be earmarked towards the Enterprise
Social Commitment based on Public Hearing issues and item-wise details along with time
bound action plan shall be included. Socio-economic development activities need to be
elaborated for 3 nearby villages in consultation of Gram Panchyat.” The socio-economic
study for Enterprise Social Commitment has been performed to fulfil this requirement.
1.3 CONCEPT
This Corporate Social Responsibility Policy (“CSR Policy”) of ISHIKA Fertilizer Ltd.
encompasses the company’s philosophy to discharge its Social Responsibility in the
upliftment/development of the communities in its operating territory and mechanism for
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 2
undertaking CSR activities/projects/programs with reference to provisions and Schedule
VII of the Companies Act, 2013 and the Companies (Corporate Social Responsibility
Policy) Rules 2014.
This policy shall apply to all CSR activities/programs/projects undertaken at Works at
ISHIKA Fertilizer Ltd. Area Offices and such other ISHIKA Fertilizer Ltd. locations for
the welfare and sustainable development of the community at large.
1.4 OBJECTIVE
To ensure an increased commitment at all levels in the organization, to operate its business
in an economically, socially & environmentally sustainable manner, while recognizing the
interests of all its stakeholders
1.5 VISION
ISHIKA Fertilizer Ltd. will continue to enhance value creation in the society in which it
operates, through its services, conduct & initiatives, so as to promote sustained growth for
the society and community, in fulfillment of its role as a Socially Responsible Corporate
Citizen with utmost environmental concern. The Ultimate Objective of CSR activities at
ISHIKA Single Super Phosphate are to improve the “Human Development Index.”
1.6 UTILIZATION Any unspent/unutilized CSR allocation of a particular year, will be dealt with in due
compliance of law for the time being in force. Any surplus arising out of CSR activities
may not form part of the business profits of a company.
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 3
CHAPTER-2 : STUDY AREA
As per EIA notification 2006 and its subsequent amendments, the study area of any project
activity is defined as the area falls in the periphery of 10 KM. A detailed socio economic
report has already been prepared and submitted to the relevant approval authority.
To prepare CSR policy and ensure its efficient delivery to the beneficiary, three
villages are chosen as study area for CSR implementation. These villages can be said the
project affected villages as the land for the proposed project has been acquired from these
villages. These three villages/ part of villages are located in the 3 Km radius around the
project area periphery. In the present case, the study area is spread over three villages
Mantageria, Chakturia, and Sanmaninathpur all located within Kharagpur sub-district of
Paschim Mednipur district.
Table 1: Villages surrounding the proposed project area
S.No. Village Name Sub District District 1. Mantageria Kharagpur Paschim Mednipur 2. Chakturia Kharagpur Paschim Mednipur 3. Sanmaninathpur Kharagpur Paschim Mednipur
2.1 DEMOGRAPHY OF THE STUDY AREA
Socio-economic status of the population is an indicator of development of the region. Any
developmental project of any magnitude will have a bearing on the living condition and the
economic bearing of the population in particular and the region as a whole. The section
delineates the overall appraisal of the socially relevant attributes. The data on socio-
economic aspects in the study area has been carried out through the analysis of the
secondary data available for the study area.
2.2 POPULATION OF THE STUDY AREA
The study area comprises of 3 villages. A comparative assessment has been made for the
respective demographic aspects, based on the year 2011 data, which has been discussed in
the following sections.
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 4
The total population of study area is 2068 the percentages of male & female population are
51.06% & 48.94% respectively. Breakup of the population for male and female is given in
following Table: 1
Table 2: Demographic profile of the study area
Village House Hold Total Population
Male Female SC ST
Mantageria 73 300 161 139 0 253 Chakturia 244 1030 524 506 59 41 Sanmaninathpur 168 738 371 367 28 383 Total 485 2068 1056 1012 87 677
2.3 LITERACY LEVELS
The literacy rate was 49.03% of the total population in 2011. The male literacy rate was
56.51% (of total male population), whereas corresponding figures for the female literacy
rate was 43.49% (of total female) in 2001 .The details are presented in Table 2
Table 3: Distribution of Literates in Study Area
Particulars Number Total Literates 1014 Male Literates 573 Female Literates 441
2.4 OCCUPATIONAL STRUCTURE
The occupational structure of the population in the study area has been studied with
reference to the total workers and non-workers. Further total workers grouped into two
categories main workers and marginal workers. Main workers have been grouped into four
categories namely: Cultivators, agricultural laborers, household workers and other workers.
The details of these groups are discussed givenbelow in Table
Table 4 : Occupational Structure S. No. Particulars Number of Workers in the study area Proportion
(%) 1. Total Male Female 2. Total Workers 534 435 99 22.76 3. Main Workers 273 226 47 20.80 4. Marginal Worker 261 209 52 24.88 5. Cultivators 41 40 1 2.50
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 5
6. Agricultural Labour 132 94 38 40.43 7. Household Worker 4 4 0 0.00 8. Other Worker 96 88 8 9.09 9. Non-workers 1209 398 811 203.77
2.5 AREA IDENTIFICATION To start with, the CSR activities will focus towards all its stake-holders, in the area
adjoining the Units of ISHIKA Fertilizer Ltd.this will include nearby villages Mantageria,
Chakturia and Sanmaninathpur that normally fall within a reasonable radius from its
operational Units. The area coverage will be gradually expanded in a manner that it
benefits the community at large. The amount earmarked for CSR shall be spent by the
Company by itself, or in collaboration with similar industry, or in partnership with NGOs,
or with the agencies of State or Central government.
2.6 PROJECT IDENTIFICATION
The following sequence will be followed:-
a. Need identification Studies by professional institutions/agencies.
b. Internal need assessment by cross‐functional team at the local level;
c. Receipt of proposals/requests from District Administration/local Govt. etc.;
d. Discussions and request with local representatives/Civic bodies/Citizen’s
forums/VOs;
e. Such other means/sources as may be deemed fit.
2.7 PARTNERING FOR EXECUTION
CSR activities will be executed either independently or through partnership with one or
other of the following agencies:-
a. Community based organizations whether formal or informal.
b. Elected local bodies such as Panchayats.
c. Voluntary Agencies (NGOs)
d. Trusts, Missions, Self‐help Groups.
e. Government, Semi‐Government and autonomous Organizations.
f. Professional Consultancy Organizations
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 6
CHAPTER-3 : SURVEY & OBSERVATIONS
A separate survey for CSR policy was conducted during April-May 2015. Three villages were
visited and activities on priority basis were selected for CSR policy.
The survey was conducted keeping in mind that the need of the people is addressed properly and
company`s expenditure will be made in line to meet the requirement of people.
Figure 1 : Survey Conducted in Mantagariya
Figure 2 : Survey Conducted In Chakturiya
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 7
Figure 3 : Survey Conducted in Sanmaninathpur
3.1 OBSERVATIONS
As per the survey conducted during month of May 2015, the observation made as follows:
1. Land was acquired from the three villages named Mantageriya, Chakturiya and
Sanmaninathpur, which fall within the periphery of three kilometers from the
project site.
2. The population in these three villages is dominated by Scheduled Tribe people
followed general which are more or less equal to the scheduled caste.
3. People live in mud houses which are covered by red mud clay roof tiles. The
drinking water and sanitation facilities are found not only inadequate but also in
very poor condition.
4. Rice is found to be the most widely consumed staple food in the area. In the
absence of other varieties of grains and poor options of vegetables, malnutrition
among the population is very common.
5. No medical facility is seen in these villages.
6. Though primary school facility is available in the villages but the facilities i.e.
seating, electricity, sanitation is not found.
7. Gender inequality is found very common in the area. Women are dependent on
male member of the family for livelihood. Any decision in the family is taken by
male member and women are there to follow the instructions.
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 8
8. No basic facility for pregnant women i.e. vaccination, nutrition, health checkup,
availability of female nurses/Asha workers etc are found. Neither any facility are
observed for mother & new born.
9. Literacy (till class V) in the area is very poor and women are no exception to it.
10. However, there are number of government plans & schemes in place, but people are
found to be almost unaware of these schemes.
11. In the non availability of education, the people are mostly dependent on agricultural
activity. Some are employed in the nearby industries/local houses for menial jobs
i.e. cleaning, washing, cooking etc.
Keeping the above points in view, this can be concluded that most of the population falls in
the range of lower income group to below poverty line.
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 9
CHAPTER-4 : PLANNING & IMPLEMENTATION 4.1 ACTIVITIES
1. Drinking Water Facilities :
Provision of five hand pumps per village is made to meet the demand of drinking water.
Total number of hand pumps to be installed in all the three villages comes out to be 15.
This is one time investment and once installed, only small amount of money will be needed
for maintenance purpose.
2. Sanitation Facilities
In the absence of any sanitation facility, the company will get community toilets
constructed in each village. The company will also contribute to Swachchh Bharat Abhiyan
set-up by the Central Government for promotion of sanitation and any other schemes
promoted by State/Central Government
3. Health & Medical
Provision of mobile health van for regular checkup preferably twice a month will be made
which will cover examination and general OPD.
A health camp shall also be put in place which includes check-up by specialist not qualified
below MD/MS, distribution of free medicines, dietary supplements etc to avoid & reduce
malnutrition in the population.
4. Education
M/S Ishika Fertilizers will provide infrastructure i.e. furniture, black boards etc to the local
school authority for smooth functioning of school. Besides providing financial aid to the
school authority, the company will also distribute free uniforms, books, pencil box, bags
etc to the students. Provision of scholarship is also kept in mind to support child eduction
as most of the population lives below poverty line.
5. Skill Development
Most of the population either busy in agricultural activities or employed in the menial jobs.
Company will arrange time to time vocation training to skill youth so that they can work in
the nearby industries or start their own set-up.
6. Local Area Development
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 10
CSR budget have provision for local area development which will cover construction of
wells, construction of ponds for rain water harvesting, construction of community halls,
and green initiatives tree plantation along the road etc.
7. Women Empowerment
To empower each and every woman in the community and to achieve her fullest potential,
women will be taught to take care of their family and legal awareness program regarding
education not only to the male child but also to female child, medical awareness i.e. illness
and injury-whether physical or emotional etc shall be done. The company will help in
formation of Self- Help group to take care of financial need of single women/widow.
Nutrition camp will also be organized to teach women about preparation of nutritional diet.
8. General Program
Legal awareness program shall be organized time to time which will cover various Pradhan
Mantry Yojana, government schemes, aadhar card registration etc.
The scope will not be only limited to legal awareness but also social issues i.e. dowry,
education, respect to women and elder etc shall be covered. Awareness about various
diseases and illness (HIV, TB etc.) along with sporadic diseases i.e. Swine Flu etc. will also
be spread among the people.
4.2 BUDGET
M/S ISHIKA Fertilizer Ltd. will allocate statutorily permissible at least 2% of average net
profits of the company made during the three immediately preceding financial years and
this would be the minimum overall Annual budget for CSR activities.
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 11
Table 5: CSR Budget
S.No. Activities Item Numbers/ Units Unit Cost Total Cost Investment in 5 Years
1. Drinking Water
Hand Pumps 3x5 Nos. 12,000 3x5x12,000 1,80,000
2. Sanitation Community Toilets 3 x 5 Nos. 45,000 3x5x45,000 6,75,000 3. Health &
Medical Mobile Van 1 No. 900,000 1x900,000 9,00,000 Health Camp Once/village/month 50,000 3x12x5x50,000 90,00,000 Free Dietary Supplements
Once/village/month 50,000 3x12x5x50,000 90,00,000
4. Education
Educational aids Once/village/year 10,000 3x5x10,000 1,50,000 Toilets 2x3 Nos. 25,000 2x3x25,000 1,50,000 Scholarship 2/village/year 3,000 2x3x5x3,000 90,000
5. Skill Development
Vocational training 2x3 persons/year 60,000 2x3x5x60,000 18,00,000
6. Local Area Development
Improvement of village roads
3 villages 100,000 3x100,000 3,00,000
Plantation along roads
3 km x 200 Nos. 1,500 3x200x1,500 9,00,000
7. Energy conservation
Solar cookers 150 9,000 150x9,000 13,50,000 Solar lanterns 150 4,000 150x4,000 60,000
8. Awareness programs
Legal 1/village/month 5,000 3x12x5x5,000 9,00,000 Environmental 1/village/year 30,000 3x5x30,000 4,50,000 Women empowerment
1/village/month 10,000 3x12x5x10,000 18,00,000
Agricultural 1/village/year 20,000 3x5x20,000 3,00,000 9. Implementation & monitoring Year 4,00,000 5x4,00,000 20,00,000
Total 3,00,05,000
Socio‐economic Study for Enterprise Social Commitment by Ishika Fertilizers Limited
Mantec Consultants Pvt Ltd Page 12
4.3 COMMITTEE
4.3.1 Authority & Approval
CSR activity budget shall be placed before the Board of Directors as a part of Company’s
annual budget. Having approval it from the Board of Directors, the Board level CSR
Committee, will examine the proposals for CSR activities and authorize the Managing
Director, to execute the same. The hierarchy flow of the CSR activities shall be as follows:
Board of Directors
Board Level CSR Committee
Managing Director
Dept of CSR & In-house CSR Committee under Chairman
An annual report on CSR shall be prepared as per the Annexure-I and the same shall be
displayed on the company`s website.
The proposed CSR policy which has budget of approx. 3.00 crore will definitely enhance
the living condition of these villages. The policy has been prepared keeping in mind
sharing of 2% on annual basis of its profit to the locality; moreover M/S Ishika will
always try to increase its budget for CSR policy implementation as and when based on the
need of the society and financial stability of the company.
AANNNNEEXXUURREE IIIIII
MAIN ENTRANCE
3
21
14
1516
4
CHIMNEY
GREEN SSP SHED ROCK PHOSPHATE SHED
SSP PLANT & MACHINARY SHED
AREA RESERVED FOR
POLUTION CONTROL UNIT
BA
LL MILL
GR
P B
IN
RP
-BE
MIX
ER
AN
D D
EN
A. S. TANK 9 M. DIA.
A. S. TANK 9 M. DIA.
GSSP SHED GSSP PLANT
ROCK STORAGE YARD42 x 16 M.
48 x 22 M.
72 x 24 M.48 x 24 M.
72 x 22 M.
27 x 16 M.
APT TANK 2 x 8 x 1.5 M.
5
67
8
10
9
11
12
13
RO
AD
10.
00 M
.WID
E
Ht. 7 M Ht. 7 M
SULPHER YARD
ROAD 7.00 M.WIDE
ROAD 7.0 M.WIDE
TURBINE HOUSE
SULPHURIC ACID PLANTPLOT SIZE-100 x 70 M.
ROAD 15.00 M.WIDE ROAD 15.00 M.WIDE
ROAD 10.00 M.WIDE
RO
AD
10.
00 M
.WID
ER
OA
D 1
0.00
M.W
IDE
KEY PLAN
14 X 11.00 X 6.50(H)2 FLR.
7.5 X 3.50 X 3.00 (H)8.00 X 3.00
48.00 X 24.00X14.00>8.50
5.00 X 4.00 X (3.5 H )
8
G.S.S.P. PLANT
G.S.S.P. CHIMNEY9
SR. NO.
ADMN. OFFICE & LABORATORY
STORE ROOM
7
6
3
5
4
SECURITY,W.B. & TIME OFFICE
DESCRIPTION
WEIGH-BRIDGE PLATE FORM
1
2
SIZE IN MTRS.
GREEN S.S.P. SHED 72.00X 22.00X14.00 30.00 (H)
10
11
ACID STORAGE TANKS YARD
12
27.00 X 16.00POLUTION CONTROL UNIT
13
27.00 X 16.00
14
15
16
CANTEEN
TOILET BLOCK
5.00 X 4.00X3.00 5.00 X 3.00X2.50
ROCK PHOSPHATE SHED 48.00X 22.00X14.00 GSSP SHED 72.00X 24.00 X14.00>8.50
24.00 X 16.00 X10.00 (H)S.S.P. PLANT & MACHINERY SHED
ROCK STORAGE YARD 42.00X 16.00X10.00 ELECT. YARD & P.C.C. ROOM 12.00 X 5.00X4.00
17 MCC & VFD PANNEL ROOM 18.00 X 6.50X4.00
RAIN WATER
HARVESTING
TANK
GREEN BELT
'
NH
-60
FU
TU
RE
EX
PA
NS
ION
(B)
GR
EE
N B
EL
T
GREEN BELT
TR
UC
K P
AR
KIN
G A
RE
A
VACANT LAND(A)
FUTURE EXPANSION(A)
VACANT LAND(B)
ADMIN & AMENITIES
GSSP PLANT
8
9
S. NO.
7
6
3
5
4
SECTION NAME
1
2
AREA IN HECTARE
10
11
SULPHURIC ACID PLANT
GSSP PLANT
FUTURE EXPANSION(A)
FUTURE EXPANSION(B)
VACANT LAND(A)
VACANT LAND(B)
TRUCK PARKING AREA
RAIN WATER HARVESTING TANK
GREEN BELT
ADMIN & AMENITIES
0.45
0.73
0.53
1.01
0.41
0.19
0.40
0.33
0.33
2.92
1.1ROADS
TOTAL AREA 8.4
ISHIKA FERTILIZER PROPOSED GSSP PLANT
Annexure - III
Location of piezometer well shown as
AANNNNEEXXUURREE IIVV
MANTEC ENVIRONMENTAL LABORATORY An ISO 9001:2008 Certified & NABL Accredited Laboratory
(Recognized by MoEF-Govt.of India) D-36, Sector-6, NOIDA, District- Gautam Budh Nagar, U.P.
Ph.0120-4215000,4215804,Fax,0120-4215809,Email:[email protected]
Soil analysis results of the study area
Name of the Project: Granulated SSP project
Name of the client: Ishika fertilizer Ltd.
Date of sample collection: 29.04.2015
Date of analysis: 02.05.2015
Sl. No
Parameter Soil Monitoring Location
S1 S2 S3 S4 S5 S6 Project Site Benapur Chakturia Amsarpur Kharigeria Dharimol
1. pH 7.6 7.55 7.68 7.72 7.48 7.78 2. Bulk Density, gm/cm3 1.52 1.54 1.55 1.52 1.55 1.56 3. Conductivity, µmhos/cm 385 435 420 365 400 410 4. Moisture, % 13.4 14.7 14.9 13.8 15.0 12.8 5. WHC 36.5 34.2 32.9 33.8 32.4 32.1 6. Texture Sandy
Loam Sandy Loam
Sandy Loam
Sandy Loam
Sandy Loam
Sandy Loam
7. Sand, % 72 76 78 75 79 80 8. Clay, % 13 12 12 13 11 11 9. Silt, % 15 12 10 12 10 9 10. Sodium, mg/100gm 42 36 44 38 45 40 11. Potassium, mg/100gm 4 3 2 2.5 4 2 12. CEC, meq/100gm 3.2 2.5 3.4 3.5 2.8 2.7 13. Nitrogen, mg/100gm 14.2 11 12.5 13 14.6 10 14. Organic Matter, % 1.95 1.46 1.5 2 2.2 1.3 15. Phosphorous, mg/100gm 74 72 76 70 80 78 16. Calcium, meq /100gm 8.4 9 10 10 12 9.5 17. SAR 1.98 2.1 2.3 2.4 2.5 1.8 18. Magnesium, meq /100gm 2.8 3.2 3 3.5 4 2.5
Analyzed by: Seal of Lab: Authorized Signatory: Notes:
The results relate only to the sample tested. This Test Report shall not be reproduced wholly or in part without prior written consent of the laboratory. The samples received shall be destroyed after two weeks from the date of issue of the Test Report unless specified
otherwise. This Test Report shall not be used in any advertising media or as evidence in the court of Law without prior written
consent of the laboratory.