31
25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 1

Introduction to Phase 1B HC PV Power

supply system

July 22, 2011

ECO, Addis Ababa

Page 2: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 2Page 2

Outline

Training objective

Overview

Main components introduction

PV array

Technical room

Health Electrical appliances

Health Center community

Load management

Routine maintenance

Follow-up and reporting

Page 3: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 3Page 3

Training objective

At the end of this training the trainees will:

Identify main parts of Health Center PV power

supply system

Perform routine service for the installed PV

system

Practice safe operation and appropriate

utilization of the system

Page 4: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 4Page 4

Overview

Background

Installed 50 PV 1.43KWp systems (Phase 1A) and

are operational since 2008

Installed 50 PV 1.7KWp systems(Phase 1B)

The systems are distributed in nine regional states

based on the Federal resource distribution method

8 local companies have installed the PV systems

Installation is supervised by GIZ-ECO

All installations are performed as per the preset

minimum standard

Page 5: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 5Page 5

First level end-user training conducted-by each

Installing company- for all employees of Health

center at site

This training is a continuation of the first one

Target Group:

Health center representatives and

Woreda health desk representative

Page 6: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 6Page 6

Main components of the system

Phase 1B HC PV power supply system is an AC coupled system

1. PV Power Generator

A. PV Array

B. Sunny Boy

2. Technical RoomA. Sunny Island including Sunny Remote Controller

B. Battery Fuse

C. Battery Bank

D. PV main distribution board

3. Health center electrical appliance

4. Health center community

Page 7: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 7Page 7

PV Power Generator

PV modules Converts

solar energy to

electrical energy

Types of PV modules

1. Crystalline

• Mono crystalline

• Poly Crystalline

2. Tin film

• Amorphous

Page 8: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 8Page 8

Health Center PV Module

Mono Crystalline

Module 1 x 170W=170 Wp

String 5 x 170W= 850 Wp

Array 2 x 850W=1700 Wp

Page 9: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 9Page 9

Sunny Boy

Is also called string inverter

Converts DC to AC

SB 1700

Input :

Power: 1850 Watt (max)

Voltage: 139- 400V DC

Output :

Power : 1700Watt (Max)

Voltage : 220-240V @50Hz

Page 10: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 10Page 10

Sunny Boy

Invert DC to AC

Create an

opportunity for AC

coupling

Function on wide

range of in put

voltage (139-400V

DC)

Page 11: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 11Page 11

Technical room

Is Power control house of the PV power supply

system

Is a room for Sunny Island, Battery Fuse ,

Battery Bank, Sunny Remote Controller, PV-

MDB

Requires Scheduled Cleaning

Do not store any material in TR

Put all forms and manuals properly in box file

provided

Page 12: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 12Page 12

Technical Room

Page 13: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 13Page 13

Sunny Island (SI)

SI is system manager, also called battery

inverter

Converts AC to DC when charging the battery

Converts DC to AC when supplying to the

system

Battery state Manager

Page 14: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 14Page 14

Sunny Island - SI2224

Inputs

Input AC:

Voltage:172.5-250V

@50Hz

Power: 5.75KW

max

Battery

Voltage :24V DC

Charging Current:

90A Max

Battery Capacity:

100-10000AH

Output

Voltage: 202- 250V

AC @ 45-65Hz

Power: 2200 W

Page 15: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 15Page 15AMES-E 15

Battery Management

Efficient battery charge and discharge

Load management

disconnect load at deep discharge and

connect load when recharged

System Management

Regulation of energy source

Regulation of load/ consumption

Over load protection

Main Tasks

Page 16: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 16Page 16

Sunny Remote Controller

The Sunny Island is controlled via the external

display (Sunny Remote Control) (SRC)

SRC is Sunny island and system controller

Monitoring and displaying device

Page 17: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 17Page 17

Bat Fuse

Protects battery from

short circuit

Isolate battery bank

form Sunny Island

Page 18: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 18Page 18

Battery Bank

Store electrical energy in a form chemical

energy

Supply the load in the evening and fogy days

Battery cell : 200AH @ 2V

Battery Bank: 12 cells 200AH @2V, connected in

series= 200AH @24V

Battery Bank: 2 of the above battery banks

connected in parallel = 400AH @ 24V

Page 19: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 19Page 19

Battery Bank:

Store the generated

electrical energy

Supplies the load during

night and foggy season

Page 20: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 20Page 20

PV Main Distribution board

Is the protection center of the PV system

Is main controller of the PV system

Interconnect and protect SB, SI and loads

Integrate the PV system with the building

electrical system

Register the Energy consumed via the Kilo- watt

hour meter (KWh-meter)

Page 21: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 21Page 21

Main Distribution Board (PV)

Page 22: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 22Page 22

Health Center Electrical appliances

Medical

Energy saving lamps , 220V AC 11W, and 8W

Vaccine refrigerators: Sibir:

Domatics: 3000/2000

Vaccine deep Freezers

Centrifugal machines:

Microscopes:

Suction pumps:

Starilizers:

Non Medical

Energy saving lamps ,

220V AC 11W, and 8W

Audio-Visual appliances:

Radio, TV, VCD/DVD

players

Mobile, telephone:

Computers:

Printers:

Page 23: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 23Page 23

Load management

Fridge

Operation hour:

Power:

Veranda Lighting

Operation Hour:

Watt: Operation Hour:

Watt:

• Energy

Consumption:

• Energy

Consumption:• Energy

Consumption:

• Daily generated Energy:

• Daily Consumed Energy:

Sterilizer

Page 24: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 24Page 24

Sterilizer/ fridge/verandah lighting/ tape

Page 25: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 25Page 25

Page 26: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 26Page 26

Page 27: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 27Page 27

Page 28: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 28Page 28

HC Community

HC employees

Medical staff

Support staff

Woreda Health Bureau

Page 29: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 29Page 29

Routine maintenance

Daily

Weekly

Monthly

Annual service (twice every sixth month)

Page 30: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 30Page 30

Follow up and reporting

Compile report

Submit every xxxxx to

Page 31: Introduction to Phase 1B HC PV Power supply system · 25.01.2012 Seite 1 Introduction to Phase 1B HC PV Power supply system July 22, 2011 ECO, Addis Ababa

25.01.2012 Seite 31Page 31

Thank You