Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
25.01.2012 Seite 1
Introduction to Phase 1B HC PV Power
supply system
July 22, 2011
ECO, Addis Ababa
25.01.2012 Seite 2Page 2
Outline
Training objective
Overview
Main components introduction
PV array
Technical room
Health Electrical appliances
Health Center community
Load management
Routine maintenance
Follow-up and reporting
25.01.2012 Seite 3Page 3
Training objective
At the end of this training the trainees will:
Identify main parts of Health Center PV power
supply system
Perform routine service for the installed PV
system
Practice safe operation and appropriate
utilization of the system
25.01.2012 Seite 4Page 4
Overview
Background
Installed 50 PV 1.43KWp systems (Phase 1A) and
are operational since 2008
Installed 50 PV 1.7KWp systems(Phase 1B)
The systems are distributed in nine regional states
based on the Federal resource distribution method
8 local companies have installed the PV systems
Installation is supervised by GIZ-ECO
All installations are performed as per the preset
minimum standard
25.01.2012 Seite 5Page 5
…
First level end-user training conducted-by each
Installing company- for all employees of Health
center at site
This training is a continuation of the first one
Target Group:
Health center representatives and
Woreda health desk representative
25.01.2012 Seite 6Page 6
Main components of the system
Phase 1B HC PV power supply system is an AC coupled system
1. PV Power Generator
A. PV Array
B. Sunny Boy
2. Technical RoomA. Sunny Island including Sunny Remote Controller
B. Battery Fuse
C. Battery Bank
D. PV main distribution board
3. Health center electrical appliance
4. Health center community
25.01.2012 Seite 7Page 7
PV Power Generator
PV modules Converts
solar energy to
electrical energy
Types of PV modules
1. Crystalline
• Mono crystalline
• Poly Crystalline
2. Tin film
• Amorphous
25.01.2012 Seite 8Page 8
Health Center PV Module
Mono Crystalline
Module 1 x 170W=170 Wp
String 5 x 170W= 850 Wp
Array 2 x 850W=1700 Wp
25.01.2012 Seite 9Page 9
Sunny Boy
Is also called string inverter
Converts DC to AC
SB 1700
Input :
Power: 1850 Watt (max)
Voltage: 139- 400V DC
Output :
Power : 1700Watt (Max)
Voltage : 220-240V @50Hz
25.01.2012 Seite 10Page 10
Sunny Boy
Invert DC to AC
Create an
opportunity for AC
coupling
Function on wide
range of in put
voltage (139-400V
DC)
25.01.2012 Seite 11Page 11
Technical room
Is Power control house of the PV power supply
system
Is a room for Sunny Island, Battery Fuse ,
Battery Bank, Sunny Remote Controller, PV-
MDB
Requires Scheduled Cleaning
Do not store any material in TR
Put all forms and manuals properly in box file
provided
25.01.2012 Seite 12Page 12
Technical Room
25.01.2012 Seite 13Page 13
Sunny Island (SI)
SI is system manager, also called battery
inverter
Converts AC to DC when charging the battery
Converts DC to AC when supplying to the
system
Battery state Manager
25.01.2012 Seite 14Page 14
Sunny Island - SI2224
Inputs
Input AC:
Voltage:172.5-250V
@50Hz
Power: 5.75KW
max
Battery
Voltage :24V DC
Charging Current:
90A Max
Battery Capacity:
100-10000AH
Output
Voltage: 202- 250V
AC @ 45-65Hz
Power: 2200 W
25.01.2012 Seite 15Page 15AMES-E 15
Battery Management
Efficient battery charge and discharge
Load management
disconnect load at deep discharge and
connect load when recharged
System Management
Regulation of energy source
Regulation of load/ consumption
Over load protection
Main Tasks
25.01.2012 Seite 16Page 16
Sunny Remote Controller
The Sunny Island is controlled via the external
display (Sunny Remote Control) (SRC)
SRC is Sunny island and system controller
Monitoring and displaying device
25.01.2012 Seite 17Page 17
Bat Fuse
Protects battery from
short circuit
Isolate battery bank
form Sunny Island
25.01.2012 Seite 18Page 18
Battery Bank
Store electrical energy in a form chemical
energy
Supply the load in the evening and fogy days
Battery cell : 200AH @ 2V
Battery Bank: 12 cells 200AH @2V, connected in
series= 200AH @24V
Battery Bank: 2 of the above battery banks
connected in parallel = 400AH @ 24V
25.01.2012 Seite 19Page 19
Battery Bank:
Store the generated
electrical energy
Supplies the load during
night and foggy season
25.01.2012 Seite 20Page 20
PV Main Distribution board
Is the protection center of the PV system
Is main controller of the PV system
Interconnect and protect SB, SI and loads
Integrate the PV system with the building
electrical system
Register the Energy consumed via the Kilo- watt
hour meter (KWh-meter)
25.01.2012 Seite 21Page 21
Main Distribution Board (PV)
25.01.2012 Seite 22Page 22
Health Center Electrical appliances
Medical
Energy saving lamps , 220V AC 11W, and 8W
Vaccine refrigerators: Sibir:
Domatics: 3000/2000
Vaccine deep Freezers
Centrifugal machines:
Microscopes:
Suction pumps:
Starilizers:
Non Medical
Energy saving lamps ,
220V AC 11W, and 8W
Audio-Visual appliances:
Radio, TV, VCD/DVD
players
Mobile, telephone:
Computers:
Printers:
25.01.2012 Seite 23Page 23
Load management
Fridge
Operation hour:
Power:
Veranda Lighting
Operation Hour:
Watt: Operation Hour:
Watt:
• Energy
Consumption:
• Energy
Consumption:• Energy
Consumption:
• Daily generated Energy:
• Daily Consumed Energy:
Sterilizer
25.01.2012 Seite 24Page 24
Sterilizer/ fridge/verandah lighting/ tape
25.01.2012 Seite 25Page 25
25.01.2012 Seite 26Page 26
25.01.2012 Seite 27Page 27
25.01.2012 Seite 28Page 28
HC Community
HC employees
Medical staff
Support staff
Woreda Health Bureau
25.01.2012 Seite 29Page 29
Routine maintenance
Daily
Weekly
Monthly
Annual service (twice every sixth month)
25.01.2012 Seite 30Page 30
Follow up and reporting
Compile report
Submit every xxxxx to
25.01.2012 Seite 31Page 31
Thank You