Intro to TR15.306 and Task Based Risk Assessment R. Todd Dickey Engineering Coordinator Honda Engineering North America, Inc.

Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

  • Upload
    others

  • View
    9

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Intro to TR15.306 and Task Based Risk Assessment

R. Todd DickeyEngineering Coordinator

Honda Engineering North America, Inc.

Page 2: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

ANSI-Registered TR R15.306-2016

Task-based risk assessment– Updates the 2014 version of the

TR 306, which…• Updates the guidance given in

ANSI/RIA R15.06-1999, Clause 9

• Published in May 2016

– Key updates:• Table 2 – Risk level decision matrix

• Table 3 – Hierarchy of risk reduction measures

• Table 5 – Minimum functional safety performance

Page 3: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Representations of Risk

Risk can be conceptualized in a number of ways:

RISK

related

to the

considered

hazard

SEVERITY

OF HARM

that can result

from the

considered

hazard

is a

function

of

and

PROBABILITY OF

OCCURRENCE

of that harm

exposure to a

hazardous situation

the occurrence of a

hazardous event

the possibility to avoid

or limit the harm

Hazard

Risk

Exposure

Vulnerability

ISO/IEC Guide 51:2014(E)

Table 1

WHO Model used to describe natural

disasters

Page 4: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Risk Assessment (Part 2, 4.3)

• A systematic analysis of the tasks, hazards, and risksassociated with the robot system over its life cycle– Task (ISO 12100:2010, 3.25): specific activity performed by one or

more persons on, or in the vicinity of, the machine during its life cycle

– Hazard (ISO 12100:2010, 3.6): potential source of (physical injury or damage to health)

• ANSI/RIA R15.06-1999: Risk assessment was optional and a methodology was included in the standard

• ANSI/RIA R15.06-2012: Risk assessment is required but a methodology was not included in the standard

• RIA TR R15.306-2016: Risk assessment methodology that meets the requirements of R15.06-2012

Page 5: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Risk Assessment Process Flow

• Has been widely adopted for industrial automation since first appearence in ANSI/RIA R15.06-1999

• Any task-based risk assessment methodology is acceptable

ISO 12100:2010 Fig.1

Page 6: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Analysis of Initial Risk• New: 3x3x3 matrix• Initial risk is

assessed under the assumption no risk reduction measures have been implemented

• Requirements for risk reduction are a function of the severity, exposure and avoidance analysis

Page 7: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Risk Reduction and Safeguarding

• The hierarchy of risk reduction measures describes the preferred order for implementing risk reduction measures

Summary of Table 3 – Hierarchy of Risk Reduction Measures

Risk

Elimination

Substitution

Limit Interaction

Safeguards & SRP/CS

Complementary Protective

Measures

Warnings & Awareness

Means

Administrative Controls

Personal Protective

Equipment (PPE)

RIA TR R15.306-2016 Table 3

Page 8: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Risk Reduction and Safeguarding

The appropriate risk reduction measure is directly tied to the risk level

Page 9: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Functional Safety (SRP/CS)

Analysis of the hazard will establish the required performance level as described in ISO 13849-1

Page 10: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

Summary• General guidance for task based risk assessment

process methodology can be found in ANSI B11.0 and ISO 12100

• TR R15.306 provides a methodology for industrial robot system applications

• Effective safeguarding utilizes several conjunctive risk reduction measures

• Risk reduction should adhere to the hierarchy for the most effective safeguarding

• Functional safety ensures that safety functions relying on a control system will be effective for the associated risk(s)

Page 11: Intro to TR15.306 and Task Based Risk Assessment to T… · •General guidance for task based risk assessment process methodology can be found in ANSI B11.0 and ISO 12100 •TR R15.306

R. Todd Dickey

Engineering Coordinator

Honda Engineering North America, Inc.Marysville, Ohio USA

Telephone: +1 (937) 642-5000 Ext.61186

[email protected]

Contact Information