15
Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodside’s deepwater drilling operations in the turbulent waters offshore Kenya. At short notice, a decision was made by Woodside to contract a second ROV onboard support vessel Lady Grete to assist drillship Chikyu during the exploration drilling campaign. As their preferred supplier of ROVs, Woodside came directly to i-Tech for a solution. Due to the immediate requirement in a remote location, i- Tech mobilised a new Centurion QX work-class system directly after completing factory acceptance tests in the UK. An engineering team was dispatched from Australia to meet the system in Mombassa and began work onboard Lady Grete to design and install the ROV interface structures.

Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Embed Size (px)

Citation preview

Page 1: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Lady Grete

In 2006 i-Tech was awarded a contract to support Woodside’s deepwater drilling operations in the turbulent waters offshore Kenya. At short notice, a decision was

made by Woodside to contract a second ROV onboard support vessel Lady Grete to assist drillship Chikyu during the exploration drilling campaign. As their

preferred supplier of ROVs, Woodside came directly to i-Tech for a solution.

Due to the immediate requirement in a remote location, i-Tech mobilised a new Centurion QX work-class system directly after completing factory acceptance

tests in the UK. An engineering team was dispatched from Australia to meet the system in Mombassa and began work onboard Lady Grete to design and install

the ROV interface structures.

Page 2: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Lady Grete

After an initial design and engineering period lasting 12 days, fabrication of the massive mezzanine deck structure began. The majority of the steel came from South Africa and the fibre-reinforced walkway grating was flown in from Dubai. Twenty-four inch I-beams had to be manufactured from 20mm and 30mm plate as none were available locally at short notice, requiring an enormous welding effort. All beams were tested using non-destructive techniques to ensure they

complied with both Australian and DNV quality standards.

From a completely bare deck, more than 80 tonnes of equipment was fully installed and operational in 5 days through round-the-clock working, a

phenomenal achievement considering the complexity of such a job in an unfamiliar location. The photo diary illustrates just how complex this installation

was in such a short space of time and is a typical example of the skill and commitment of i-Tech’s ROV technicians and engineers.

Page 3: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Toolbox Talk gets things kicked off in

Mombasa

Page 4: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

The giant mezzanine deck is lifted onboard

Lady Grete

Page 5: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

From a bare deck, the mezzanine begins to

slot into place

Page 6: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Beams spread the load to the main deck

structure

Page 7: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Once the main mezzanine structure is in place, work can begin on the rest of

the installation

Page 8: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

The mezzanine structure is painted to

provide corrosion protection

Page 9: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Having loaded the ROV control van

onboard, the winch is craned into place

Page 10: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

At 30te, care is taken to position the winch

on the mezzanine structure

Page 11: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

ROV workshop van is hoisted into place

Page 12: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

After 5 days of round-the-clock construction

work, the ROV installation is

complete

Page 13: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Test dives ensure all systems are fully

operational

Page 14: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Key Facts – Equipment Installed

• A-frame 14.0Te

• Umbilical Winch 30.0Te

• Power Pack 2.8Te

• Control Van 12.0Te

• Workshop Van 8.0Te

• Centurion QX ROV 2.5Te

• TMS 2.5Te

• A-frame Mounting Skid 4.0Te

• Motor Alternator Set 0.5Te

TOTAL WEIGHT 76.3Te

Page 15: Intervention Technology Lady Grete In 2006 i-Tech was awarded a contract to support Woodsides deepwater drilling operations in the turbulent waters offshore

Intervention Technology

Project Summary

• i-Tech single-sourced by Woodside

• rapid mobilisation of Centurion QX ROV system to remote location – i-Tech’s first foray into Kenya

• from bare deck, full installation of pre-fabricated mezzanine structure and ROV spread onboard Lady Grete in 5 days

• i-Tech’s experience of installing ROVs onboard support vessels a key factor in the success of this mobilisation

• the global approach of i-Tech spanned three continents to ensure Woodside had a fully operational ROV in record time

• having completed the Kenya contract, the Centurion QX is now on long-term contract in Australia