Upload
doanthuan
View
216
Download
0
Embed Size (px)
Citation preview
LONG INTERNATIONAL
During Phase I, we first review any pleadings,statements of arbitration, contractor claims, andowner statements of defenses and counterclaims.We then perform a preliminary review of therelevant project documents prepared prior to andduring the execution of the project. Dependingon the scope of our assignment, the documentsthat we often review include, but are not limitedto, those that describe the scope of work andbasis for the contractual relationship that wasdeveloped, cost estimates, proposals, the drawingsand specifications that were used to develop thecontrol budget, pre-contract correspondence andmeeting minutes, the contract terms and conditions,execution phase correspondence, meeting minutes,monthly progress reports, native baseline scheduleand schedule update files, daily construction reports,job cost reports including control budgets andmonthly cost reports, photographs and videos ifavailable, pay requests and invoices, change orders,requests for information, submittals, materialdelivery records, subcontracts, and any otherrelevant documentation.
If many of the aforementioned documents are ina language other than English, we need to receiveeither 1) English translations of the documentsif they exist, or 2) electronic or clean hard copyversions of the documents for translation to English.Optical character recognition (OCR) software isused to convert the hard copies to electronic filesfor automatic translation followed by humantranslation clean-up.
In addition, we interview key project personneland discuss more completely the project problemsand issues. If possible, we also like to visit theproject site.
It normally takes two to six weeks to perform thisPhase I work. The Phase I duration, depends onthe complexity of the case, the volume and avail-ability of key documents, translation requirements,availability of client personnel, as well as any othertasks that our client requests to be performedduring Phase I.
After we have performed a preliminary review ofthe available documentation, we prepare preliminaryobservations and recommendations regarding theclaim and counterclaim issues, including our pre-liminary observations and opinions on the relevantissues. We also develop Phase II work plans, sched-ules, and budgets corresponding to the scope ofwork necessary to meet our client’s objectives. Wethen discuss our proposed tasks to ensure that ourapproach is consistent with our client’s needs.
OVERVIEW
Long International’s standard work plan for
providing engineering and construction claims
analysis and expert testimony services is to
use a “phased approach.” Our task
assignments are dependent on the work
already performed by our client, the
availability of project documentation, the
issues in dispute, and the timing of required
work products that are defined by the
arbitration/litigation schedule. Therefore, we
can make any necessary adjustments to our
typical work tasks described herein.
PHASE I:Project Orientation, Preliminary Document Review, andWork Plan Development
International Experts in Claims Analysis,
Dispute Resolution, and Project Management
for Process, Oil & Gas, Pipeline, Power, Industrial,
Infrastructure, and Building Construction Projects
LONG INTERNATIONAL
Evaluation of rework, nonconformance reports,inspectors’ logs, delays, absenteeism, supervisionratios, weld failures, correspondence, etc.
Def
ectiv
e &
Def
icie
nt C
ontra
ct D
ocs.
Diff
erin
g Si
te C
ondi
tions
Car
dina
l Cha
nge
Acce
lera
tion
Susp
ensi
on
Term
inat
ion
Dire
cted
Cha
nge
Con
stru
ctive
Cha
nge
Impl
ied
War
rant
y
Del
ays/
Dis
rupt
ion
Impo
ssib
ility
of P
erfo
rman
ce
Wea
ther
Strik
es
Mal
adm
inis
tratio
n
Supe
rior K
now
ledg
e
Ow
ner-F
urni
shed
Item
s
Unj
ust E
nric
hmen
t
Varia
tions
in Q
uant
ities
ClaimResolutionMethodology
Legal Entitlements / Liability*
Design & SpecificationRelated Problems
Directed andConstructive Change
Changed SiteConditions
Delay andSuspension
Lost Productivity /Impacts
Issues and Classification Causation Cost
$ $ $
Contractor-Caused Problems
Pending Change Orders
Approved Change Orders
Bid Estimate Analysis Bid Errors (NONCOMP)
Execution Errors (NONCOMP)
Pending ContractAdjustmentsChange Order
Documentation
IssueNo. 1
Original ContractScope
Contract Drawings andSpecifications and/or
Performance Requirements
CurrentContract
ValueCONTRACT TERMS AND CONDITIONS
AND CONSTRUCTION CASE LAW* Entitlements shown for each issue are presented as
an example only and do not limit other entitlementsfor potentially being appropriate. DOCUMENTATION ACTUAL COST RECORDS
POTE
NTIA
L CO
MPE
NSAB
LE D
AMAG
ES
IssueNo. 2
IssueNo. 3
IssueNo. 4
IssueNo. 5
Evaluation of RFIs, specifications, drawings,contract “order of precedence” clause, notices,correspondence, etc.
Evaluation of change orders, field work orders,contract “changes” clause, bid estimate,notices, etc.
Evaluation of core logs, soil reports, geologicalreports, photographs, notices, correspondence,drawings, etc.
Preparation of CPM schedule analyses such astime impact, as-built but-for, as-planned impacted,windows, or other analyses.
Evaluation of planned vs actual man-hours usingtechniques such as “measured mile”, impact factorsfrom Corp of Engineers, Business Roundtable, MCA,NECA reports, Leonard Study, etc.
$ $ $
$ $ $
$ $ $
$ $ $
SpecificationDelay
7/16 8/30
ProcurementDelay
3/1 3/30
UndergroundFoundation
Delay
7/1 7/20
Period ofPerformance of Defined
Work Change Orders5/1 8/31
Extended Durationof Inspection Work
11/1 2/28
ExtendedDuration of
RefurbishmentWork5/1 7/31
Period of Performance of AdditionalVariable Work Change Orders
11/16 4/15
Delay to CreateAccurate As-Built
P & IDs
7/1 8/9
ProcurementDelay
2/1 3/2
Period ofPerformance
of Defined WorkChange Orders
3/1 4/30
Gas PipelineStart Delay1/1 4/1
31 CDDELAY
92 CD DELAYTO MECHANICAL
COMPLETION
61 CDAWARDDELAY
92 CD DELAY TOCOMPLETION OFREFURBISHMENT
WORK
ENGINEERING7/1 9/30
PROCUREMENT2/1 11/30
CONSTRUCTION5/1 1/31
INSPECTION7/1
2/28
7/1
ENGINEERING FOR UPGRADE8/15
PROCUREMENTFOR UPGRADE
11/1 4/30
7/31
REFURBISHMENTWORK
10/1
CONSTRUCTION FOR UPGRADE2/1 1/31
DISTILLATE GAS PIPELINE1/31
1/1
DIG & BURYPIPELINE CO.ACTUALMECHANICALCOMPLETION
DRACONIAN’SACTUALMECHANICALCOMPLETION OFNEW ETHYLENEUNIT
ACTUALCONTRACTAWARD7/1
ACTUAL MECHANICALCOMPLETION OFREFURBISHMENT WORK7/31
DRACONIAN’SACTUALMECHANICALCOMPLETIONOF UPGRADETO DGS UNIT
10/31
F L O A T92 Cal DaysEF LF
11/1
10/1
ENGINEERING7/1 5/31
DRACONIANSUBMITS BID
PROPOSAL
3/3112/1
INVITATIONTO BID (ITB)ISSUED
PLANNEDCONTRACTAWARD
5/1
PROCUREMENT11/1 9/30
CONSTRUCTION5/1 10/31
INSPECTION7/1 10/31
PROCUREMENT FOR UPGRADE11/1 10/31
REFURBISHMENT WORK10/1 4/30
CONSTRUCTION FOR UPGRADE8/1 7/31
DISTILLATE GAS PIPELINE1/1 10/31
PLANNEDMECHANICALCOMPLETION10/31
PLANNEDMECHANICALCOMPLETION 4/30
12/31
CONTRACTMECHANICALCOMPLETION
10/31
DRACONIAN’SPLANNEDMECHANICALCOMPLETION
ENGINEERING FORUPGRADE
7/1 5/31
8/1
30 CD
20 CD
120 CD
92 CD151 CD
30 CD
61 CD
90 CD
45 CD
40 CD
123 CD
2008 2009 2010 2011 2012
A S - B U I L T
New EthyleneUnit
A S - B U I L T
Distillate GasSeparation Unit(DGSU)
A S - B U I L T
Distillate GasPipeline
A S - P L A N N E D
New EthyleneUnit
A S - P L A N N E D
Distillate GasSeparation Unit(DGSU)
A S - P L A N N E D
Distillate GasPipeline
OCT JUL AUG SEPNOV DEC JAN FEB MAR OCT NOV DECAPR MAY JUN JUL AUG SEPJAN FEB MAR OCT NOV DECAPR MAY JUNJUL AUG SEPJAN FEB MAR OCT NOV DECAPR MAY JUN JAN FEB MAR
031 - 01 4/28/00
LEGEND
Logic Tie
AS-PLANNED vs. AS-BUILTSCHEDULE COMPARISONCelestial Chemical Plant Project
Clean City, Utopia
11/1 1/31R A I N Y S E A S O NSTRIKEPERIOD6/1 - 6/1414 CDs
Activity Description
AS-BUILT
EF - Early FinishLF - Late FinishCD - Calenday Days
Activity Description
Start
AS-PLANNED
Start Finish
Finish
Critical Path
Delays
Additional Variable Work orDefined Work Change Order
Milestones
After performing a preliminary analysis of thedocumentation and technical, schedule, and costissues, Long International then performs a detailedanalyses that support opinions expressed in ourexpert reports. The task descriptions that are listedbelow are definitive analyses that substantiate thepreliminary findings, but they may be tailored tothe needs of our client, the actual scope of workand opinions required, and the deadlines of thearbitration/litigation.
1. Prepare Issue Packages for Contractor’sClaim Issues and Owner’s CounterclaimIssues
2. Prepare Issue Summaries/Proof Charts
3. Prepare Detailed Narratives withDocument References
4. Develop Cause-Effect Relationships
5. Prepare Detailed Schedule Analysis
a. Prepare List of Delays/FinalizeRelational Database of Key ScheduleDelay Information
b. Prepare Schedule Activity Start andDuration Variance Tables
c. Identify Responsibility for ActivityStart and Duration Delays
d. Prepare Detailed Schedule Analysesand Calculations Based on AgreedUpon Methodologies
e. Prepare Schedule AnalysisTabular Results
f. Prepare Schedule Analysis Graphics
6. Prepare Detailed Damages Analysis
The work products resulting from our detailedanalyses may take many forms, including butnot limited to claims/requests for equitablecontract adjustments, reports supporting thedefendant’s positions against claims, PowerPointpresentations, or expert reports. One or moreexpert reports may be required for arbitration orlitigation. Rebuttal reports may also be requiredto critique the reports of other experts. In addition,some arbitrations require that opposing expertsmeet to attempt to narrow the issues. Reportsmay be required to document this effort. Foreach claim document, presentation, or expertreport, our work plan is as follows:
1. Prepare Draft ClaimsDocuments/Presentations/Reports
2. Review with Client our Draft ClaimDocuments/Presentations/Reports
3. Prepare Final Claim Documents/Presentations/Reports
For each phase of arbitration or litigation, experttestimony may be required. Our work to performthis testimony includes the following:
1. Prepare for Testimony
2. Provide Expert Testimonyat Depositions
3. Provide Arbitration/LitigationExpert Testimony
Our Detailed Damages Analysis providesadequate detail and supporting spreadsheetsto fully explain the amount of the claim and/or counterclaim. Damages may arise froma variety of problems, and we endeavor tocalculate specific damages for each problemif possible from the data available. The cause-effect relationships linking the damages to theentitlement for each problem are demonstrated,if possible. We often develop a DamagesAnalysis Matrix for both man-hours and costs.This matrix delineates work activities and costtypes on one axis and variances betweenbudget/contract values and actual/projectedvalues along the other axis. These man-hourand cost variances are then allocated toproblems, if possible. Subtasks may include:
a. Evaluate Reasonableness of Bid andCalculation of Bid Error
b. Assess Owner’s Responsibility forDirect Cost Issues
c. Assess Responsibility forQuantity Overruns
d. Assess Contractor’s Responsibilityfor Performance Problems
e. Assess Responsibility for UnresolvedChange Order Requests
f. Allocate Contractor’s Delay Costs
g. Allocate Responsibility for Man-hour and Cost Overruns Associatedwith Welding Problems and otherRework Issues
h. Analyze and Allocate Loss ofProductivity Man-hours and Costs
i. Prepare Detailed Man-hour VarianceAnalysis Matrix
j. Prepare Detailed Cost VarianceAnalysis Matrix
k. Assess Liquidated/Actual Damages
l. Assess Costs Associated with Owner’sCounterclaims
m. Prepare Damages Tabular Results
n. Prepare Damages Analysis Graphics
PHASE II:Document DatabaseDevelopment andPreliminary Analysis
PHASE III:Detailed Analysis
PHASE IV:Report Preparation
PHASE V:Arbitration/LitigationTestimony
During Phase II, we perform tasks required byour client as part of the arbitration/litigationschedule. In addition, other potential Phase IItasks often include the following:
1. Develop Document Database
2. Analyze Contract
3. Review Invitation to Bid, Job Instructions,Procedures, and Contractor’s Proposal
4. Review Drawings and Specifications
5. Review and Prepare (as required) a Listof Problems and Issues for Claims andCounterclaims
6. Review Approved and Unapproved/Outstanding Change Orders
7. Prepare a Preliminary List of Alleged Delays
8. Identify, Organize, and Review ScheduleData
9. Identify any Schedule Software ConversionRequirements
10. Review Schedule Analysis Methodology inany Submitted Claims
11. Identify and Review Key ScheduleInformation
12. Identify, Organize, and Review Contractor’sMan-hour Data, including Control BudgetPlanned Man-hours and Actual Man-hours
13. Identify, Organize, and Review BulkMaterial Quantity Data
14. Identify, Organize, and Review Cost Data
15. Develop Summary Schedule VarianceComparisons
16. Develop Macro Man-hour Variance Analysis
17. Develop Macro Quantity Variance Analysis
18. Develop Macro Labor Productivity Analysis
19. Develop Macro Cost Variance Analysis
20. Evaluate and Select Schedule AnalysisMethodology Options
21. Develop Phases III and IV Work Plans,Budgets, and Schedules
22. Provide an Overall Assessment of theStrengths and Weaknesses of Issues
Experience Matters ...
SpecificationDelay
7/16 8/30
ProcurementDelay
3/1 3/30
UndergroundFoundation
Delay
7/1 7/20
Period ofPerformance of Defined
Work Change Orders5/1 8/31
Extended Durationof Inspection Work
11/1 2/28
ExtendedDuration of
RefurbishmentWork5/1 7/31
Period of Performance of AdditionalVariable Work Change Orders
11/16 4/15
Delay to CreateAccurate As-Built
P & IDs
7/1 8/9
ProcurementDelay
2/1 3/2
Period ofPerformance
of Defined WorkChange Orders
3/1 4/30
Gas PipelineStart Delay1/1 4/1
31 CDDELAY
92 CD DELAYTO MECHANICAL
COMPLETION
61 CDAWARDDELAY
92 CD DELAY TOCOMPLETION OFREFURBISHMENT
WORK
ENGINEERING7/1 9/30
PROCUREMENT2/1 11/30
CONSTRUCTION5/1 1/31
INSPECTION7/1
2/28
7/1
ENGINEERING FOR UPGRADE8/15
PROCUREMENTFOR UPGRADE
11/1 4/30
7/31
REFURBISHMENTWORK
10/1
CONSTRUCTION FOR UPGRADE2/1 1/31
DISTILLATE GAS PIPELINE1/31
1/1
DIG & BURYPIPELINE CO.ACTUALMECHANICALCOMPLETION
DRACONIAN’SACTUALMECHANICALCOMPLETION OFNEW ETHYLENEUNIT
ACTUALCONTRACTAWARD7/1
ACTUAL MECHANICALCOMPLETION OFREFURBISHMENT WORK7/31
DRACONIAN’SACTUALMECHANICALCOMPLETIONOF UPGRADETO DGS UNIT
10/31
F L O A T92 Cal DaysEF LF
11/1
10/1
ENGINEERING7/1 5/31
DRACONIANSUBMITS BID
PROPOSAL
3/3112/1
INVITATIONTO BID (ITB)ISSUED
PLANNEDCONTRACTAWARD
5/1
PROCUREMENT11/1 9/30
CONSTRUCTION5/1 10/31
INSPECTION7/1 10/31
PROCUREMENT FOR UPGRADE11/1 10/31
REFURBISHMENT WORK10/1 4/30
CONSTRUCTION FOR UPGRADE8/1 7/31
DISTILLATE GAS PIPELINE1/1 10/31
PLANNEDMECHANICALCOMPLETION10/31
PLANNEDMECHANICALCOMPLETION 4/30
12/31
CONTRACTMECHANICALCOMPLETION
10/31
DRACONIAN’SPLANNEDMECHANICALCOMPLETION
ENGINEERING FORUPGRADE
7/1 5/31
8/1
30 CD
20 CD
120 CD
92 CD151 CD
30 CD
61 CD
90 CD
45 CD
40 CD
123 CD
2008 2009 2010 2011 2012
A S - B U I L T
New EthyleneUnit
A S - B U I L T
Distillate GasSeparation Unit(DGSU)
A S - B U I L T
Distillate GasPipeline
A S - P L A N N E D
New EthyleneUnit
A S - P L A N N E D
Distillate GasSeparation Unit(DGSU)
A S - P L A N N E D
Distillate GasPipeline
OCT JUL AUG SEPNOV DEC JAN FEB MAR OCT NOV DECAPR MAY JUN JUL AUG SEPJAN FEB MAR OCT NOV DECAPR MAY JUNJUL AUG SEPJAN FEB MAR OCT NOV DECAPR MAY JUN JAN FEB MAR
031 - 01 4/28/00
LEGEND
Logic Tie
AS-PLANNED vs. AS-BUILTSCHEDULE COMPARISONCelestial Chemical Plant Project
Clean City, Utopia
11/1 1/31R A I N Y S E A S O NSTRIKEPERIOD6/1 - 6/1414 CDs
Activity Description
AS-BUILT
EF - Early FinishLF - Late FinishCD - Calenday Days
Activity Description
Start
AS-PLANNED
Start Finish
Finish
Critical Path
Delays
Additional Variable Work orDefined Work Change Order
Milestones
After performing a preliminary analysis of thedocumentation and technical, schedule, and costissues, Long International then performs a detailedanalyses that support opinions expressed in ourexpert reports. The task descriptions that are listedbelow are definitive analyses that substantiate thepreliminary findings, but they may be tailored tothe needs of our client, the actual scope of workand opinions required, and the deadlines of thearbitration/litigation.
1. Prepare Issue Packages for Contractor’sClaim Issues and Owner’s CounterclaimIssues
2. Prepare Issue Summaries/Proof Charts
3. Prepare Detailed Narratives withDocument References
4. Develop Cause-Effect Relationships
5. Prepare Detailed Schedule Analysis
a. Prepare List of Delays/FinalizeRelational Database of Key ScheduleDelay Information
b. Prepare Schedule Activity Start andDuration Variance Tables
c. Identify Responsibility for ActivityStart and Duration Delays
d. Prepare Detailed Schedule Analysesand Calculations Based on AgreedUpon Methodologies
e. Prepare Schedule AnalysisTabular Results
f. Prepare Schedule Analysis Graphics
6. Prepare Detailed Damages Analysis
The work products resulting from our detailedanalyses may take many forms, including butnot limited to claims/requests for equitablecontract adjustments, reports supporting thedefendant’s positions against claims, PowerPointpresentations, or expert reports. One or moreexpert reports may be required for arbitration orlitigation. Rebuttal reports may also be requiredto critique the reports of other experts. In addition,some arbitrations require that opposing expertsmeet to attempt to narrow the issues. Reportsmay be required to document this effort. Foreach claim document, presentation, or expertreport, our work plan is as follows:
1. Prepare Draft ClaimsDocuments/Presentations/Reports
2. Review with Client our Draft ClaimDocuments/Presentations/Reports
3. Prepare Final Claim Documents/Presentations/Reports
For each phase of arbitration or litigation, experttestimony may be required. Our work to performthis testimony includes the following:
1. Prepare for Testimony
2. Provide Expert Testimonyat Depositions
3. Provide Arbitration/LitigationExpert Testimony
Our Detailed Damages Analysis providesadequate detail and supporting spreadsheetsto fully explain the amount of the claim and/or counterclaim. Damages may arise froma variety of problems, and we endeavor tocalculate specific damages for each problemif possible from the data available. The cause-effect relationships linking the damages to theentitlement for each problem are demonstrated,if possible. We often develop a DamagesAnalysis Matrix for both man-hours and costs.This matrix delineates work activities and costtypes on one axis and variances betweenbudget/contract values and actual/projectedvalues along the other axis. These man-hourand cost variances are then allocated toproblems, if possible. Subtasks may include:
a. Evaluate Reasonableness of Bid andCalculation of Bid Error
b. Assess Owner’s Responsibility forDirect Cost Issues
c. Assess Responsibility forQuantity Overruns
d. Assess Contractor’s Responsibilityfor Performance Problems
e. Assess Responsibility for UnresolvedChange Order Requests
f. Allocate Contractor’s Delay Costs
g. Allocate Responsibility for Man-hour and Cost Overruns Associatedwith Welding Problems and otherRework Issues
h. Analyze and Allocate Loss ofProductivity Man-hours and Costs
i. Prepare Detailed Man-hour VarianceAnalysis Matrix
j. Prepare Detailed Cost VarianceAnalysis Matrix
k. Assess Liquidated/Actual Damages
l. Assess Costs Associated with Owner’sCounterclaims
m. Prepare Damages Tabular Results
n. Prepare Damages Analysis Graphics
PHASE II:Document DatabaseDevelopment andPreliminary Analysis
PHASE III:Detailed Analysis
PHASE IV:Report Preparation
PHASE V:Arbitration/LitigationTestimony
During Phase II, we perform tasks required byour client as part of the arbitration/litigationschedule. In addition, other potential Phase IItasks often include the following:
1. Develop Document Database
2. Analyze Contract
3. Review Invitation to Bid, Job Instructions,Procedures, and Contractor’s Proposal
4. Review Drawings and Specifications
5. Review and Prepare (as required) a Listof Problems and Issues for Claims andCounterclaims
6. Review Approved and Unapproved/Outstanding Change Orders
7. Prepare a Preliminary List of Alleged Delays
8. Identify, Organize, and Review ScheduleData
9. Identify any Schedule Software ConversionRequirements
10. Review Schedule Analysis Methodology inany Submitted Claims
11. Identify and Review Key ScheduleInformation
12. Identify, Organize, and Review Contractor’sMan-hour Data, including Control BudgetPlanned Man-hours and Actual Man-hours
13. Identify, Organize, and Review BulkMaterial Quantity Data
14. Identify, Organize, and Review Cost Data
15. Develop Summary Schedule VarianceComparisons
16. Develop Macro Man-hour Variance Analysis
17. Develop Macro Quantity Variance Analysis
18. Develop Macro Labor Productivity Analysis
19. Develop Macro Cost Variance Analysis
20. Evaluate and Select Schedule AnalysisMethodology Options
21. Develop Phases III and IV Work Plans,Budgets, and Schedules
22. Provide an Overall Assessment of theStrengths and Weaknesses of Issues
Experience Matters ...
LONG INTERNATIONAL
Other tasks that our clients may request LongInternational to perform during arbitrationor court proceedings include:
1. Develop Requests for Arbitration
2. Develop Detailed Memorials/Statementsof Claim for Arbitration
3. Develop Detailed Responsesand Counterclaims
4. Assist with Settlement Negotiations
5. Prepare Presentations for Useat Mediations
6. Assist with Developing DocumentRequests from Opposing Party
7. Assist with Developing DepositionQuestions for Opposing Witnesses
8. Assist with Developing Interrogatories
9. Assist with Preparing Witness Statements
10. Prepare Issue and Event Timelines
11. Prepare Graphics for Technical Issues
12. Prepare Multimedia GraphicsPresentations for Use at Trial or Hearing
13. Prepare Document Indices
14. Attend Depositions as Requestedby Counsel
15. Perform Other Tasks as Requestedby Our Clients
Arbitration/LitigationSupport ThroughoutProject As Required
Engineering and Construction Claims Analysis Experience
You Can Rely On...
LONG INTERNATIONAL
Project Work Activities
ApprovedChangeOrders
CurrentContract
Value
PendingChangeOrders
Bid Error(Noncompensable)
ContractorCaused
Problems(Noncompensable)
InaccurateP&IDs
IncreasedPiping
Quantities Delay
Disruption/Loss of
Productivity
TotalActualCosts
Cost / Damages Matrix
Potential Compensable Damages
OriginalContract
Value
C/D MATRIX GS 8/1/03
(All Costs Shown in $000)
ENGINEERING $2,500 $400 $2,900 – – $120 $250 $500 – $3,770
EARTHWORK $1,000 – $1,000 – – $200 – – – – $1,200
CONCRETE $500 $20 $520 – – $100 – – – – $620
STRUCTURAL STEEL $1,000 $100 $1,100 – – – – – – $1,100
INSTALLED EQUIPMENT $7,200 $900 $8,100 – – $50 – – – – $8,150
PIPING $2,000 $1,055 $3,055 $2,500 $500 $750 $1,250 $345 – $2,500 $10,900
Direct Labor $500 $250 $750 $600 $75 $112 $300 $75 – $600 $2,512
Labor Taxes & Burdens $215 $108 $323 $280 $35 $53 $145 $35 – $280 $1,151
Permanent Material & Equip $800 $400 $1,200 $950 $200 $300 $475 $100 – $950 $4,175
Consumable Materials $50 $25 $75 $50 $10 $15 $40 $5 – $50 $245
Owned Construction Equipment $25 $10 $35 $25 $10 $15 $30 $5 – $25 $145
Rental Equipment $10 $5 $15 $10 $50 $75 $10 $25 – $10 $195
Subcontracts $400 $257 $657 $585 $120 $180 $250 $100 – $585 $2,477
TANKAGE $500 $100 $600 – – – – – – – $600
INSTRUMENTATION $800 $200 $1,000 $700 – $600 $1,000 – – $700 $4,000
ELECTRICAL $1,500 $450 $1,950 $900 – $800 $1,800 – – $900 $6,350
PROJECT/CONST MANAGEMENT $2,000 $425 $2,425 $1,800 $400 $750 $2,200 – $600 $1,800 $9,975
OTHER FIELD INDIRECTS $1,500 $300 $1,800 $1,300 $300 $600 $1,000 $300 $450 $1,300 $7,050
HOME OFFICE OVERHEAD $2,000 $400 $2,400 $800 – $400 $400 $200 $600 $800 $5,600
FEES/PROFIT $2,500 $850 $3,350 $1,000 – – $800 $80 $750 $1,000 $6,980
TOTAL PROJECT $25,000 $5,200 $30,200 $9,000 $1,200 $4,370 $8,700 $925 $2,900 $9,000 $66,295
IssueNo. 1
IssueNo. 2
IssueNo. 3
IssueNo. 4
TOTAL COST OVERRUN = $36,095
POTENT IAL CLA IM VALUE = $21,525
www.long-intl.com5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180••• •Long International, Inc. •