Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
BEFORE THE ADDITIONAL FACILITY OF THE
INTERNATIONAL CENTRE FOR SETTLEMENT OF INVESTMENT DISPUTE (ICSID)
BETWEEN:
MERCER INTERNATIONAL INC.
Claimant / Investor
AND:
GOVERNMENT OF CANADA
Respondent / Party
ICSID CASE NO. ARB(AF)/12/(3)
GOVERNMENT OF CANADA
REJOINDER MEMORIAL
31 March 2015
Departments of Justice and of Foreign Affairs, Trade and Development Trade Law Bureau Lester B. Pearson Building 125 Sussex Drive Ottawa, Ontario K1A 0G2 CANADA
PUBLIC VERSIONCONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
i
TABLE OF CONTENTS
I. INTRODUCTION ................................................................................................. 1
A. Executive Summary ................................................................................................ 1
B. Measures at Issue .................................................................................................. 11
C. Materials Submitted by Canada ............................................................................ 17
II. FACTUAL BACKGROUND ............................................................................. 21
A. The Claimant Has An Obligation to Supply its Mill Energy Needs ..................... 21
1. The Claimant is Required to Displace its Load with the Self-Generation fromits Original Turbine under the Terms of the Ministers’ Order ......................... 21
2. Celgar Pulp Applies for an Energy Project Certificate .................................... 26
3. The Evidence Concerning the Ministers’ Order .............................................. 28
4. The Claimant’s Numerous Allegations Concerning the Ministers’ Order....... 31
B. British Columbia’s Policy Developments with Respect to Self-Generators of Electricity .............................................................................................................. 42
1. The BCUC Directs BC Hydro to Establish a Short-Term Program to EnableSales of Self-Generation for Export from British Columbia in Order G-38-01 42
2. BC Hydro Attempts to Procure Electricity from Self-Generators and Developsthe Concept of a GBL in the 2002 Customer Based Generation Call for Power 46
3. BC Hydro Procures Electricity from Self-Generators in the Bioenergy Call forPower Phase I and the Integrated Power Offer ................................................ 48
a) The 2007 Energy Plan ......................................................................... 48b) Bioenergy Call for Power ................................................................... 50
C. The Claimant’s Treatment in the Bioenergy Call for Power ................................ 55
1. The Claimant’s False Assertions that BC Hydro Did Not Consider all of theData and that Celgar Did Not Understand that the GBL would be Set to Reflectan Annual Period .............................................................................................. 55
2. Mr. Merwin’s Baseless Claim that He Could Not Describe Normal Operationsat the Celgar Pulp Mill ..................................................................................... 60
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
ii
3. Celgar’s Negotiations with BC Hydro Concerning the Exclusivity Clause andthe Side Letter Agreement ............................................................................... 62
D. The Claimant’s Treatment at the BCUC ............................................................... 65
1. BCUC Order G-48-09 ...................................................................................... 65
2. Subsequent Proceedings Relating to a FortisBC-Celgar GBL ......................... 66
3. Subsequent Proceedings Relating to the Claimant’s “Access” to FortisBC’sEmbedded Cost Power ..................................................................................... 73
4. The Claimant’s Allegation of “Regulatory Indeterminacy” is a Product of itsOwn Making .................................................................................................... 77
E. BC Hydro’s Treatment of Skookumchuck ........................................................... 78
1. BC Hydro’s Treatment of Skookumchuck in the 1997 EPA Prior to theExisting Regulatory Framework ...................................................................... 78
2. BC Hydro’s Consideration of Skookumchuck in the 2009 EPA ..................... 82
F. BC Hydro’s Treatment of Howe Sound Pulp and Paper ...................................... 86
1. BC Hydro’s Negotiation of a Generation Threshold with Howe Sound Pulpand Paper in 2001 ............................................................................................. 86
2. BC Hydro’s Treatment of Howe Sound in the Integrated Power Offer ........... 88
G. The BCUC’s Approval of a Baseline Negotiated with FortisBC, the City of Kelowna and Tolko (Riverside) ............................................................................ 91
III. THE TRIBUNAL SHOULD NOT CONSIDER CLAIMS THAT AREINADMISSIBLE OR THAT DO NOT FALL WITHIN ITS JURISDICTION ............................................................................................................................... 93
A. Concise Statement of Canada’s Position .............................................................. 93
B. NAFTA Articles 1102 and 1103 Do Not Apply to BC Hydro’s Negotiation of Celgar’s GBL and Section 7.4 by Virtue of the Procurement Exception in Article 1108(7)(a) ............................................................................................................. 94
C. BC Hydro’s Negotiation of the GBL and Section 7.4(b) Was Not An Exercise of Delegated Governmental Authority and Cannot be the Subject of a Claim Under NAFTA Chapter Eleven ....................................................................................... 97
1. A State Enterprise Does Not Engage Article 1503(2) Merely Because It Has“Wide Discretion” or Because Its Acts Are Not “Purely Commercial” .......... 98
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
iii
2. BC Hydro’s Negotiation of the GBL and Section 7.4(b) In Its Procurement ofElectricity From Celgar Did Not Engage Article 1503(2) ............................. 100
D. The Claimant’s Claim Related to Section 7.4 and BC Hydro’s Setting of Celgar’s GBL are Time-Barred under Articles 1116(2) and 1117(2) ............................... 104
IV. THE CLAIMANT HAS FAILED TO PROVE THAT CANADA HASBREACHED ARTICLE 1102 OR 1103 .......................................................... 107
A. Concise Statement of Canada’s Position ............................................................ 107
B. The Claimant Misunderstands the Law under NAFTA Articles 1102 and 1103 108
1. The Claimant Misapplies the Three-Part Test under NAFTA Articles 1102 and1103 ................................................................................................................ 108
2. Nationality is a Critical Factor under NAFTA Articles 1102 and 1103 ........ 110
3. An Allegedly Illegitimate Governmental Objective is Not an IndependentGround for Liability under Article 1102 or 1103 .......................................... 113
C. The GBL Setting Methodology Applied by BC Hydro To The Claimant Under The 2007 Energy Plan Was Consistent With NAFTA Articles 1102 and 1103 . 116
1. BC Hydro Applied a GBL Methodology that the Claimant Understood ....... 118
2. BC Hydro’s GBL Methodology is Reasonably Related to Legitimate PolicyObjectives ....................................................................................................... 125
3. The Claimant Has Failed to Show Less Favourable Treatment ..................... 129
a) The “Below-Load Access Percentage” is an Inappropriate Measure ofLess Favourable Treatment ............................................................... 129
b) The Claimant Has Not Demonstrated the Absence of a UniformMethodology ..................................................................................... 130
c) BC Hydro Consistently Applied its GBL Methodology ................... 133
4. The Different Results of BC Hydro’s Consistent Application of its GBLMethodology Are Explained by the Unique Circumstances of Each Mill..... 139
a) Howe Sound (Port Mellon)’s 2010 EPA .......................................... 139b) Tembec (Skookumchuck)’s 2009 EPA ............................................. 144
D. The Claimant has Failed to Show that the Other Instances of GBL-Related Treatment it Identifies are Inconsistent with NAFTA Articles 1102 and 1103 .. 149
1. Tembec (Skookumchuck)’s 1997 EPA .......................................................... 150
2. Howe Sound’s 2001 Consent Agreement ...................................................... 153
3. Tolko Kelowna’s 2001 Exemption Order ...................................................... 155
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
iv
E. The Claimant Has Failed to Prove that the Restriction on Third-Party Sales in Section 7.4(b) of its EPA with BC Hydro is Inconsistent with NAFTA Articles 1102 or 1103 ....................................................................................................... 157
F. The Claimant Has Failed to Prove that BCUC Order G-48-09 is Inconsistent with NAFTA Articles 1102 or 1103 ........................................................................... 159
V. THE CLAIMANT HAS FAILED TO DEMONSTRATE A VIOLATION OF ARTICLE 1105 – THE CUSTOMARY INTERNATIONAL LAW MINIMUM STANDARD OF TREATMENT ................................................ 162
A. Concise Statement of Canada’s Position ............................................................ 162
B. Principles Governing a Claim under NAFTA Article 1105(1) ........................... 163
1. The Claimant Bears the Burden of Proving the Rules of the CustomaryInternational Law Minimum Standard of Treatment It Alleges Have BeenBreached ......................................................................................................... 163
2. Arbitral Case Law Does Not Create Custom ................................................. 165
3. The Threshold for Establishing a Breach of Article 1105(1) is High ............ 166
C. The Claimant Has not Established That Any of the Complained of Measures Rise to the Level Required to Breach Article 1105(1) ................................................ 168
1. The Acts of BC Hydro Did not Breach Article 1105(1) ................................ 169
a) The Claimant Fails to Establish that BC Hydro “Discriminated”Against the Celgar Mill Contrary to the Customary International LawMinimum Standard of Treatment ...................................................... 169
b) The Claimant Fails to Establish that BC Hydro Violated theCustomary International Law Minimum Standard of Treatment forFailing to Act “Transparently”.......................................................... 171
c) The Claimant Fails to Establish that BC Hydro Violated theCustomary International Law Minimum Standard of Treatment forActing in an “Arbitrary” Manner ...................................................... 174
d) The Claimant Fails to Establish that BC Hydro Violated theCustomary International Law Minimum Standard of Treatment forActing in a “Grossly Unfair, Unjust or Idiosyncratic” Manner ........ 175
2. The Claimant Fails to Establish a Breach of Article 1105(1) due to the Failureto Provide a “Stable Regulatory Environment” ............................................. 177
3. The Claimant Fails to Establish that the Acts and Omissions of the BCMinistry of Energy and the BCUC Violated Article 1105(1) ........................ 178
D. Conclusions ......................................................................................................... 182
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
v
VI. DAMAGES ........................................................................................................ 182
E. The Claimant’s Damages Related to Celgar’s Below-GBL Self-Generation are Unfounded........................................................................................................... 184
1. Celgar had No Financially Viable Market for its Below-GBL Energy ......... 185
a) Celgar Cannot Make Profitable Sales at Mid-C ............................... 187b) Celgar Does Not Have the Required Transmission Rights in Order to
Sustain Profitable Sales in the US in the Long-Run ......................... 190 c) Celgar’s Energy Does Not Qualify as a Renewable Energy Resource in
the NorthWest United States. ............................................................ 192
2. BC Hydro would not have purchased Celgar’s below-GBL electricity ......... 196
3. The Ministers’ Order Required Celgar to Use the Turbine Installed in 1993Expansion to Serve its Own Load .................................................................. 198
F. The Claimant’s Damages Related to its Alternative GBL Scenarios are Unfounded........................................................................................................... 199
1. The Claimant’s Proposed GBLs are Arbitrary and Have no Basis in ProvincialProcurement Policy ........................................................................................ 201
2. The Claimant wrongly assumes that the EPA would be renewed ................. 201
3. The Claimant Overstates the Damages Relating to its GBL .......................... 204
4. Like its First Report, Navigant’s Second Damages Report is Fatally Flawed 205
5. The Claimant ignores the effect of the 1991 Ministers’ Order ...................... 208
G. The Claimant Fails to Independently Quantify its Article 1105 Damages Claim............................................................................................................................. 208
VII. COSTS ................................................................................................................ 208
VIII. CONCLUSION AND REQUEST FOR RELIEF .......................................... 209
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
1
I. INTRODUCTION
A. Executive Summary
Proponents responding to a competitive call for the procurement of energy1.
sometimes disagree with the contractual terms and conditions proposed, which define the
parameters of the procurement. In these circumstances, the proponent has a choice: it
can accept these terms and conditions; it can attempt to negotiate new terms and
conditions; or it can walk away from the process. It is not reasonable, however, for a
proponent to expect the procuring entity to offer terms and conditions that differ
fundamentally from the mandate of the call and that would effectively reduce the amount
of the energy procured.
This is precisely what the Claimant alleges should have happened when it claims2.
that BC Hydro should not have “imposed” a “restriction” on Celgar through the
exclusivity clause in its Electricity Purchase Agreement (“EPA”). It also complains that
the B.C. Utilities Commission (“BCUC”) effectively continued this “restriction” on its
ability to sell electricity in Order G-48-09. Much of the Claimant’s case now appears to
rest on these supposed “restrictions.” The Claimant, however, also continues to complain
about the amount of electricity BC Hydro procured when it set a Generator Baseline
(“GBL”) for Celgar.
The Claimant in complaining about these “restrictions” expects this Tribunal to3.
assume the role of BC Hydro, a state enterprise, in the context of a competitive
procurement so that it can assess the commercial reasonableness of the exclusivity clause,
which applied to all proponents. It also requests this Tribunal to substitute its judgement
for that of BC Hydro when it made complex and highly technical decisions concerning
the amount of electricity it would procure when it set GBLs. The Tribunal is then
expected to vault into the role of the BCUC to interpret its previous regulatory decisions
and replace the BCUC’s weighing and balancing of what is in the “public interest” with
decisions that would only be in the Claimant’s interest. It is not the role of a NAFTA
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
2
Chapter 11 tribunal to act in the stead of state enterprises and administrative tribunals in
this manner.
Perhaps more importantly, the Claimant’s alleged “restrictions” are not really4.
restrictions at all. The Claimant asserts that BC Hydro used the exclusivity clause to
“force”1 Celgar to use its self-generated electricity for its own load and to prevent it from
selling its electricity in the U.S. market. Mr. Merwin tries to paint BC Hydro in an
unfavourable light alleging that it foisted the clause on Celgar in the context of the EPA
negotiations at the “11th hour,” leaving the Claimant with no choice but to accept it.2
Nothing could be further from the truth. The exclusivity clause is a standard5.
provision of every EPA (including the Tembec and Howe Sound EPAs) and formed part
of the terms and conditions when the Claimant made its bid into the competitive call for
power. As Mr. Scouras explains in his second witness statement, it was Mr. Merwin who
requested the removal of the clause relatively late in the negotiations.3
The exclusivity clause ensures that BC Hydro will have security of supply under6.
the EPA, and thus its removal was a concern. BC Hydro nonetheless “wanted to be
responsive to the interests of Celgar”4 and proposed a compromise—a Side Letter
Agreement that would require the parties to amend the exclusivity clause if the BCUC
decided that Celgar could sell below-GBL electricity in “any pending or future regulatory
1 Claimant’s Reply, ¶ 1. 2 Brian Merwin Statement II, ¶ 13. (“Just before the presentation to its Board, however, BC Hydro insisted on changing the text of Section 7.4, in a new Version 8 of the draft EPA, to preclude Celgar from selling its below-GBL energy to a third party. I remember this change well, as I was on vacation with my family at the time, and this 11th hour highly significant change disrupted that vacation”.) 3 Jim Scouras Statement II, ¶ 18. 4 Jim Scouras Statement II, ¶ 25.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
3
proceeding.5 No other pulp mill in British Columbia has received an accommodation
similar to the Side Letter Agreement.6
Mr. Merwin’s testimony leaves the impression that BC Hydro strong-armed7.
Celgar into accepting the exclusivity clause in the EPA.7 This misleading version of
events, however, is contradicted by Mr. Merwin’s own contemporaneous report to his
CEO on this issue, which indicates that:
[O]n Friday Hydro added one major wrinkle to our negotiations. This wrinkle was not unexpected and approximately 4 weeks ago we had reached agreement on how this issue would be addressed. The issue at hand is our current activities to allow us to sell all of Celgar’s existing generation (the Arbitrage Project). …A number of weeks ago we reached agreement with Hydro that we would leave this issue for the BC Utilities Commission to decide and withdrew the term from the EPA and agreed to set up a side letter acknowledging this withdrawal and that neither party could use this omission to further their argument. BC Hydro came back to us on Friday with the position the wording should be left in the contract to prevent us from selling our mill load and we would have a side letter acknowledging that subject to certain conditions this term would be removed. … They however indicated they are prepared to live by the principles we established several weeks ago which [sic] was to leave this to the BCUC to decide.8
This email stands in stark contrast to how the Claimant and Mr. Merwin now8.
attempt to characterize the discussions concerning the exclusivity clause in the context of
the EPA negotiations.9
BC Hydro and the Claimant subsequently negotiated the Side Letter Agreement9.
and executed it alongside the EPA on January 27, 2009.10 The parties effectively agreed
5 Jim Scouras Statement II, ¶ 25. [Emphasis added.] 6 Jim Scouras Statement II, ¶ 33. 7 Brian Merwin Statement II, ¶¶ 12-13. 8 Email from Brian Merwin to David Gandossi and Jimmy Lee, RE: Celgar EPA negotiations with BC Hydro, 8 November 2008, MER00071253, R-528. [Emphasis Added] 9 See Brian Merwin Statement I, ¶¶ 102-105; Brian Merwin II, ¶¶ 11-13. 10 Side Letter Agreement between BC Hydro and Zellstoff Celgar Limited Partnership, RE: Electricity
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
4
in the Side Letter Agreement that they would to leave it to the BCUC to decide the issue
of Celgar’s sales of below-load electricity.
BC Hydro had separately applied to the BCUC to determine whether FortisBC10.
was permitted under the terms of its 1993 Power Purchase Agreement (“1993 PPA”) with
BC Hydro to supply electricity to customers such as the City of Nelson and Celgar who
intended to engage in arbitrage. The Claimant intervened in this proceeding to push its
buy all, sell all scheme. Mr. Merwin, contrary to his most recent testimony,11 was fully
aware that there was a risk that the BCUC could reject his “Arbitrage Project.” Mr.
Debienne, Vice President of Power Supply and Strategic Planning for FortisBC, had
discussed with Mr. Merwin the relevant BCUC regulatory precedents and informed him
that there was a 50 percent chance that the BCUC could reject the project.12 The Claimant
had also advised its Board of Directors of this regulatory risk.13
FortisBC’s reservations turned out to be right. The BCUC in Order G-48-0911.
amended the 1993 PPA to prevent FortisBC from selling electricity supplied under this
agreement to a customer that was selling electricity below their load (i.e., engaging in
arbitrage). The Claimant characterizes Order G-48-09 as the second “restriction” on its
ability to sell below-GBL electricity because it allegedly “prevents” FortisBC from
supplying any embedded cost energy to facilitate arbitrage. This, however,
mischaracterises Order G-48-09, which places no restrictions on FortisBC’s ability to
source the Claimant from its own embedded cost resources.
Purchase Agreement, with Effective Date of January 27, 2009, 27 January 2009, bates 026183-026184, R-138. 11 Brian Merwin Statement II, fn 30. 12 Dennis Swanson Statement II, ¶¶ 5 and 9-10. 13 Mercer International Group, Celgar Electricity Opportunities, July 2007, at 9-10, R-278.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
5
The Claimant, for this reason, would subsequently request the BCUC to direct12.
FortisBC to develop a matching methodology which would allow FortisBC to supply
Celgar using non-1993 PPA sources of electricity. The Claimant argued that that this
non-PPA electricity could then be “matched” against its load so that it could engage in
below-load sales without arbitraging electricity under the 1993 PPA.14 FortisBC agreed
that this approach might be feasible15 and the BCUC thus directed FortisBC in Order G-
188-11 to develop a rate based on this “matching methodology.” The BCUC also
confirmed that “Celgar is free to sell all or a portion of its generation below the BC
Hydro GBL into the market and supply its mill from FortisBC resources, not including
BC Hydro PPA Power.”16 Indeed, Mr. Merwin would explain to his Board of Directors
that BCUC Order G-188-11 was a “major victory”.17
Mr. Merwin would also write BC Hydro shortly after BCUC Order G-188-11 to13.
request that it exercise the Side Letter Agreement and amend the exclusivity clause from
the EPA.18 BC Hydro was not adverse to this request and contacted FortisBC to discuss
how the accounting would be done for Celgar’s EPA sales to BC Hydro in conjunction
14 Letter from KC Moller to Alanna Gillis, Re: Zellstoff Limited Partnership (“Celgar”) Complaint Regarding the Failure of FortisBC Inc. (“FortisBC”) and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges (the “Complaint”) – Project No. 369836, dated August 15, 2011, attaching “Final Submissions of Zellstoff Celgar Limited Partnership”, p. 30, ¶¶ 6-15, R-529. 15 Letter from Ludmilla Herbst to Alanna Gillis, Re: Zellstoff Limited Partnership (“Celgar”) Complaint Regarding the Failure of FortisBC Inc. (“FortisBC”) and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, dated August 22, 2011, attaching Submissions of FortisBC, ¶ 57, R-530. 16 BCUC, Decision G-188-11, p. 49, R-275. 17[Emphasis in Original.] Memorandum from Management to Mercer International Board of Directors, Re Update on Celgar’s Generator Baseline Issue, 7 December 2011, at MER00191043, R-531. 18 Letter from Brian Merwin to BC Hydro, December 6, 2011, R-485.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
6
with the new rate.19 Regrettably, the Claimant then decided instead that it would file its
Notice of Intent under the NAFTA and never followed-up with its request.20
FortisBC subsequently proposed a “Non-PPA Embedded Cost Power” (“NECP”)14.
rate to facilitate the Claimant’s below-GBL sales.21 The BCUC in Order G-202-12
confirmed that the Claimant could nominate as much as 100% percent of its load22 for
service from FortisBC using the NECP rate.
The Claimant argues in this arbitration that the NECP rate would not reflect15.
“traditional” embedded cost rates and that “[u]nlike all other FortisBC customers, Celgar
would receive none of the benefit of FortisBC’s existing, low cost generation assets.”23
This is not accurate. Mr. Dennis Swanson, Vice President of Corporate Services for
FortisBC, explains that the NECP rate would be sourced from all of FortisBC’s resources
with the exception of BC Hydro’s 1993 PPA electricity.24 These resources would include
FortisBC’s traditional embedded cost power from sources such as its hydro-electric
facilities. He also explains that the NECP rate would have been no higher than the rates
Celgar has received since BCUC Order G-48-09.25
19 Jim Scouras Statement II, ¶ 38. 20 Notice of Intent to Submit a Claim to Arbitration under Chapter Eleven and Articles 1503(2) and 1502(3)(A) of the North American Free Trade Agreement, Mercer International Inc., v Government of Canada, ¶ 20, “[U]ntil November 2011 [i.e., until Order G-188-11] Celgar was the only pulp mill with self-generation capacity in the Province of British Columbia that was restricted from accessing any electric power from its local electric utility company, while selling to the market any of its self-financed, self-generated electric power.” The Claimant’s new position - that it has been “forced” to self-supply - conflicts with its own earlier pleadings. 21 Dennis Swanson Statement II, ¶ 27. 22 BCUC, Order G-202-12 and Decision, in the Matter of FortisBC Inc., Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), December 27, 2012,¶ 3 of the Order, p. 3 of Decision, R-265. 23 Claimant’s Reply, fn. 256. 24 Dennis Swanson Statement II, ¶ 28. 25 Dennis Swanson Statement II, ¶¶ 33-35.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
7
The Claimant’s argument that the BCUC has imposed a “restriction” that has16.
denied it “access” to embedded cost power is thus false.26 The BCUC has in fact made
considerable efforts to accommodate the Claimant’s demands to sell its below-GBL
electricity. The Claimant has criticized the NECP rate even though it suggested this
approach as a solution.27 In any event, the fact that a customer of one utility could have a
slightly higher rate than a customer of anther utility is not a valid ground for a NAFTA
complaint—especially when the customer has requested this rate so that it can secure a
right to sell electricity in a way that no other self-generating customer has in the province.
The Claimant’s intransigence over the NECP rate is also surprising in light of its17.
repeated assertions that it could sell its electricity as “green” or renewable energy at
prices that would surpass the cost of the NECP. For example, Mr. Merwin testifies that he
“targeted as a prospective buyer” and had
“fruitful preliminary discussions.”28 Roger Garrett of Puget Sound, however, testifies that
he has no recollection of the Claimant29 and that Claimant’s electricity would not have, in
any event, qualified as renewable or green energy under Washington state law.30
Canada raised significant concerns in its Counter-Memorial over the Claimant’s18.
failure to provide evidence that it could sell its electricity to third parties.31 In its Reply,
the Claimant again failed to provide any meaningful evidence and merely recycled the
same unsupported claims that it made in its Memorial. Canada thus contacted Michael
26 Claimant’s Memorial, ¶ 369. (“Since Order G-48-09 issued in May 2009, Celgar has been unable to access embedded cost utility electricity below its 2007 load, and thus has been unable to sell any of its below-load electricity.”) 27 Claimant’s letter to BCUC, August 15, 2011, p. 21, R-529. (“FortisBC’s concerns regarding jeopardizing its access to [PPA power] may be addressed through ensuring that any additional Celgar load served by FortisBC following the establishment of a FortisBC GBL is notionally matched to and served from additional third party energy purchases.”) 28 Brian Merwin Statement I, ¶¶ 82 and 144; Claimant’s Memorial, ¶ 298; Claimant’s Reply, ¶ 566. 29 Roger Garratt Statement, ¶¶ 15-16. 30 Roger Garratt Statement, ¶ 18. 31 Canada’s Counter Memorial, ¶ 507.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
8
McDougall, Director of Trade Policy and Information Technology of Powerex, and Dean
Krauss, Director of Business Development and Contract Services for NorthPoint, the
Claimant’s former electricity broker, to determine whether the Claimant could actually
have sold its electricity in the manner that Mr. Merwin and its experts suggest.
Mr. McDougall testifies that Celgar’s electricity was not eligible as renewable19.
electricity in the states of Washington,32 Oregon,33 Montana,34 California,35 New
Mexico,36 and Arizona.37 He also explains that Alberta, Idaho, Wyoming and Utah do
not have renewable energy markets.38 Mr. Krauss also explains that NorthPoint has
never sold “green” or renewable electricity.39 The Claimant thus had no market for this
electricity as renewable energy. Nor did it have a broker that had experience marketing
renewable energy.
Mr. McDougall and Mr. Krauss also explain that U.S. wholesale electricity prices20.
tumbled towards the end of 2008, a few months after the peak prices the Claimant
repeatedly refers to in its pleadings,40 and that these electricity prices have remained low
since that time at first as a result of the U.S. recession and later due to the increase in U.S.
shale gas production.41 Mr. McDougall and Mr. Swanson have also provided NERA’s
32 Michael McDougall Statement I, ¶¶ 73-80. 33 Michael McDougall Statement, ¶ 81. 34 Michael McDougall Statement, ¶¶ 82-83. 35 Michael McDougall Statement, ¶¶ 84-89. 36 Michael McDougall Statement, ¶ 94. 37 Michael McDougall Statement, ¶ 91. 38 Michael McDougall Statement I, ¶¶ 96-97. Mr. McDougall also explains that while it might be theoretically possible to sell to renewable energy in Nevada and Colorado the incentives in those markets have incentives for other forms of domestically produced renewable energy. Moreover, the distance of these renewable energy markets from British Columbia would make these sales impracticable. See Michael McDougall Statement, ¶¶ 93 and 95. 39 Dean Krauss Statement, ¶ 31. 40 Claimant’s Memorial, ¶ 298, Brian Merwin Statement I, ¶ 83, Claimant’s Reply, ¶ 507, and Robert Friesen Statement, ¶ 8. 41 Michael McDougall Statement I, ¶¶ 59-62; and Dean Kraus Statement I, ¶¶ 16 and 24.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
9
Dr. Rosenzweig with data concerning Mid-Columbia market prices, line losses and
transmission costs. Dr. Rosenzweig has “done the math” with this data and concluded
that the Claimant could not have sold its electricity in a profitable manner on the Mid-
Columbia market in the manner described in their Reply from 2009 onwards.42 Mr.
McDougall and Mr. Krauss also explain some of the numerous transmission challenges
the Claimant would face marketing its electricity in the United States.
For this reason, the Claimant is forced in its Reply to claim that BC Hydro would21.
procure all of the Claimant’s below-load electricity absent the measures while in the
same breath stating that BC Hydro is “not legally obligated to buy it.”43 The Claimant’s
argument remains nothing more than a thinly veiled attempt to realize the profits from its
“Arbitrage Project”, which BC Hydro properly rejected in the context of the Bioenergy
Call for Power.
The Claimant spends hundreds of pages alleging that BC Hydro had no GBL22.
methodology,44 that it set the Claimant’s GBL with “no rules”,45 that it has fabricated a
“current normal” GBL methodology,46 that even if such a standard existed it was applied
less favourably to the Claimant,47 and that in any event the energy policies underlying BC
Hydro’s procurement of electricity are “not legitimate.”48 Each one of these baseless
accusations has been made to support a claim that BC Hydro set the Claimant’s GBL
“too high,”49 and that the Claimant should be compensated on the basis of a
“nondiscriminatory GBL.” This is most evident in Table 12 of Mr. Kaczmarek’s most
42 NERA Expert Report II, ¶¶ 144-154. 43 Claimant’s Reply, ¶ 36. 44 Claimant’s Reply, pp. 124-221. 45 Claimant’s Reply, ¶¶ 513-520. 46 Claimant’s Reply, ¶¶ 263 and 266. 47 Claimant’s Reply, ¶ 291. 48 Claimant’s Reply, ¶ 181. 49 Claimant’s Reply, ¶ 553 [Emphasis added]
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
10
recent report which provides the Tribunal with numerous GBL “options,” all of which are
lower than the Claimant’s actual GBL of 40 MW. Mr. Kaczmarek then proceeds to
quantifies damages on the basis that the proper “but-for” world is one where BC Hydro
should have procured additional electricity.50 The Claimant seemly wants to transform
this Tribunal into a “Court of GBLs” asking it to examine these GBLs in granular detail,
frequently without any evidence that another pulp mill in like circumstances received the
same treatment.
The Claimant and its experts continue to allege that BC Hydro afforded the Howe23.
Sound and Skookumchuck pulp mills more favourable treatment when it set their GBLs.
It does so with little regard for the unique technical and operational circumstances of each
mill. Canada has already submitted witness statements from Pierre Lamarche and Fred
Fominoff concerning these critical differences at the Howe Sound pulp mill.51 Mr.
Christian Lague, the Energy Manager at the Skookumchuck pulp mill, has now submitted
a witness statement with this Rejoinder that confirms the basis on which BC Hydro
determined a GBL for the 2009 Tembec EPA.52
The Claimant’s case also fails for an entirely different reason—it is required to24.
use its 52 MW turbine to provide electricity to meet its mill load. This commitment was
made during a proposed expansion of the pulp mill in the early 1990s where the
Claimant’s predecessor, Celgar Pulp Co., repeatedly used energy self-sufficiency as a
selling point for the project’s approval.
Mr. Ostergaard and now Dr. Jon O’Riordan, the former Assistant Deputy25.
Ministers from the Ministries of Energy and Environment, were responsible for
supervising the review of Celgar Pulp Co.’s Energy Project Certificate application and
50 Navigant Expert Report II, p. 62. 51 Pierre Lamarche Statement I, ¶¶ 28-34; Pierre Lamarche Statement II, ¶¶ 4-11; Fred Fominoff Statement I, ¶¶ 15-20. 52 Christian Lague Statement I, ¶¶ 42-52.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
11
both testify that Celgar’s representation that it would use this electricity for the purpose
of load displacement was a critical consideration in approving the application and issuing
the Ministers’ Order.53 Ms. Denise Mullen, the Director of the Projects and Policy
Branch after Mr. Ostergaard, explains that the Ministry would have expected the Celgar
Pulp Co. to request an amendment to the Ministers’ Order if it intended to use the
electricity for a purpose other than load displacement. Rather than request an amendment,
the Claimant has instead raised numerous arguments in an attempt to evade the
obligations imposed by this order, or alternatively, to render it unenforceable.
Finally, Canada will explain the Claimant’s strategy of using BCUC litigation as a26.
means to “ ”54 by raising issues that
would have “ .”55 The Claimant was able to adopt
this strategy because applicants such as FortisBC normally underwrite much of the cost
of intervenors in BCUC proceedings. This improper litigation strategy has contributed to
an annual rate increase of 1.5% for all ratepayers in FortisBC’s service area.56
Canada submits that Claimant’s allegations when properly understood are devoid27.
of factual or legal merit. Canada therefore requests that the Tribunal dismiss these claims
and award Canada its full costs in this arbitration.
B. Measures at Issue
The Claimant’s allegations concern two fundamental measures in this arbitration.28.
First, the Claimant complains that BC Hydro’s setting of a GBL for Celgar during the
Bioenergy Call was arbitrary and discriminatory. It does so while also attempting to
maintain that it is not alleging that BC Hydro was required to procure this electricity.
53 Peter Ostergaard Statement I, ¶ 17; Jon O’Riordan Statement I, ¶ 75. 54 Memorandum from Management to Mercer International Board of Directors, Re Update on Celgar’s Generator Baseline Issue, 7 December 2011, MER00191043 at MER00191044, R-531. 55 Memorandum from Management to Mercer International Board of Directors, Re Update on Celgar’s Generator Baseline Issue, 7 December 2011, MER00191043 at MER00191044, R-531. 56 Dennis Swanson Statement I, ¶ 152.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
12
Second, the Claimant asserts that BC Hydro and BCUC Order G-48-09 imposed29.
“restrictions”, which prevented it from selling its self-generated electricity below its
GBL. In particular, it alleges that BC Hydro forced Celgar to accept an exclusivity
clause in its EPA that prevented it from selling below-GBL electricity (i.e., section 7.4(b)
of the EPA) and that the BCUC, in Order G-48-09, prohibited FortisBC from providing
Celgar with access to “embedded cost electricity” which has meant that it has not been
able to receive the replacement electricity that would be necessary in order for Celgar to
sell to third parties.
The Claimant has mischaracterized the measures at issue, which this section will30.
clarify.
The Claimant alleges that BC Hydro was not required to procure additional31.
electricity from Celgar under its EPA. It asserts that:
● “Mercer makes no claim that BC Hydro was required to procure its below-load self-generated electricity.”57
● “Mercer is not even claiming that BC Hydro was required to have purchasedmore energy from Mercer in the 2009 EPA.”58
● Mercer makes no claim that BC Hydro was “legally obligated to” purchaseCelgar’s below-load electricity.59
The reason for this position is obvious–such a claim would fall under NAFTA32.
Article 1108(7)(a), which provides a procurement exception for state enterprises with
respect to NAFTA Articles 1102 and 1103. The Claimant does, however, maintain that
“BC Hydro established a [GBL] for Celgar in a manner inconsistent with the ‘current
normal operating conditions’ standard”60 and, alternatively, that BC Hydro had “no
57 Claimant’s Reply, ¶ 16. 58 Claimant’s Memorial, ¶¶ 427-428; Claimant’s Reply, fn. 7. 59 Claimant’s Reply, ¶ 36. 60 Claimant’s Reply, ¶ 4.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
13
consistently applied ‘current normal’ standard, but instead it made a series of ad hoc
discretionary determinations in which it treated Celgar less favorably.”61 It then alleges
that these measures resulted in a GBL that was too high and offers a range of purportedly
“non-discriminatory” GBL “options”.62 These measures are the core of the Claimant’s
allegations against Canada under NAFTA Article 1102 and 1103,63 as well as Article
1105.64
Although it attempts to avoid the application of the procurement exception, the33.
Claimant alleges with respect to the damages that:
To the extent BC Hydro set Celgar’s GBL too high even under the “current normal standard,” then the difference between that GBL of 349 GWh/year and Celgar’s proper GBL reflects “new and incremental” electricity that would have been eligible for sale to BC Hydro under the terms of BC Hydro’s Bioenergy Phase I power call. This electricity would have been above-GBL electricity but for BC Hydro’s discriminatory measure in establishing an excessive GBL for Celgar … [I]f Celgar’s nondiscriminatory GBL should have been lower, it is all but certain that BC Hydro would have done what it did in every other EPA with a BC self-generator, and purchased all above-GBL electricity on a firm basis.”65
In short, the Claimant’s argument that BC Hydro set its GBL improperly is as34.
follows:
● BC Hydro infringed NAFTA Articles 1102, 1103, and 1105 when it set aGBL for the Celgar mill during the Bioenergy Call.
61 Claimant’s Reply, ¶ 212. 62 Should the Tribunal find that a “current normal” method existed but was applied inconsistently the Claimant offers various GBLs in Figure 12 (Reply Memorial, ¶ 405) as non-discriminatory “options” for the Tribunal to consider. Should the Tribunal find that no standard existed, the Claimant alleges that it should be accorded a GBL based on the “best in jurisdiction” “below load access percentage” accorded to one of its competitors, which it provides in its Figure 22 (Reply Memorial, ¶ 214). 63 Claimant’s Reply, ¶¶ 32-36. 64 Claimant’s Reply, ¶ 473. 65 [Emphasis Added] Claimant’s Reply, ¶¶ 553-554.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
14
● “But for” the unlawful manner in which BC Hydro set the GBL, the GBLwould be lower.
● To be made whole, the Claimant is entitled to be paid the difference betweenthe lawful and unlawful GBLs under its EPA with BC Hydro.
The Claimant’s assertion that it is “not even claiming that BC Hydro was required35.
to have purchased more energy from Mercer in the 2009 EPA,”66 is therefore false. Its
attempts to obfuscate this simple fact are without merit.
The second measure the Claimant complains about concerns the so-called36.
“restrictions” on selling below-GBL electricity to third parties. The Claimant asserts
that:
One measure (BCUC Order G-48-09) restricts Celgar’s access to embedded cost utility electricity; the other measure (BC Hydro’s GBL and related contractual exclusivity provisions) restricts Celgar sales of below-[GBL] self-generated electricity. Both have the same practical effect — Celgar must self-supply all electricity below [its GBL], Celgar cannot sell any of this below-[GBL] electricity to BC Hydro or a third-party, and Celgar has no access to FortisBC embedded cost electricity while selling electricity.67
These allegations are quite simply false. Neither the BCUC nor BC Hydro have37.
prevented the Claimant from selling its below-GBL electricity to third parties or, to use
the Claimant’s confusing terminology, neither has “forc[ed] Celgar…to use all of it
below-load self-generated electricity to serve its own load.”68
First, the Claimant takes issue “with the restriction BC Hydro placed on Celgar’s38.
sales of its below-GBL energy to third parties …through the … related exclusivity
provisions in Section 7.4(b) of the 2009 EPA.”69 This ignores the fact that every EPA that
66 Claimant’s Memorial, ¶¶ 427-428. 67 Claimant’s Reply, ¶ 35. 68 Claimant’s Reply, ¶ 1. [Emphasis in original] 69 Claimant’s Reply Memorial, ¶ 36. See also e.g. ¶ 35 (“Celgar must self-supply all electricity below the level of its 2007 load of 349 GWh/year [and] cannot sell any of this below-load electricity to BC Hydro or
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
15
BC Hydro has signed with self-generators contains an identical exclusion.70 The Claimant
has been treated no differently this this regard. To the contrary, the Claimant is the only
self-generator with whom BC Hydro has signed a Side Letter Agreement, which permits
the Claimant to sell its below-GBL electricity to third parties if the BCUC determines
that these below-GBL sales are acceptable.71 The Side Letter Agreement provides that
following such a BCUC decision, “section 7.4(b) of the EPA in its present form should
have no force or effect.”72 No other mill has been accorded this type of accommodation.73
Perhaps not surprisingly, the Claimant mentions the Side Letter Agreement only once in a
footnote in its Reply.74
The BCUC has also agreed that the Claimant should be allowed to sell its below-39.
GBL electricity to third parties. In BCUC Order G-188-11 the BCUC agreed to allow the
Claimant to “sell all or a portion of its generation below the BC Hydro GBL into the
market and supply its mill from FortisBC resources.”75 Following this decision, Mr.
a third party.”); ¶ 17 (Section 7.4(b) “preclude[es] Celgar from selling below-GBL electricity…to a third party.”) 70 See e.g. BC Hydro and Howe Sound Pulp and Paper Limited Partnership, Electricity Purchase Agreement, Integrated Power Offer, 7 September 201, bates 016362 to 016499, at section 8.4, R-62; BC Hydro and Domtar Pulp and Paper Products Inc., Electricity Purchase Agreement, Bioenergy Call for Power – Phase I, dated January 27, 2009, bates 065025 to 065132, section 7.4, R-136; BC Hydro and Tembec Electricity Purchase Agreement, 13 August 2009, bates 017023 to 017132, section 7.4, R-198. 71 Side Letter Agreement between BC Hydro and Zellstoff Celgar Limited Partnership, RE: Electricity Purchase Agreement, with Effective Date of January 27, 2009 (“EPA”), dated January 27, 2009, bates 026183-026184, R-138. The Side Letter Agreement allows the Claimant to sell its below-GBL electricity to third parties should the BCUC “in any pending or future regulatory proceeding” determine (1) that FortisBC may supply electricity to the Claimant to serve the Celgar’s Mill Load, in circumstances where the Claimant sells self-generated electricity diverted from serving Mill Load; and (2) that the Claimant may sell such self-generated electricity in those circumstances. 72 Side Letter Agreement between BC Hydro and Zellstoff Celgar Limited Partnership, R-138. 73 Jim Scouras Statement II, ¶ 33. (“[N]o other pulp mill to date in any BC Hydro power procurement process (including the Bioenergy Call for Power Phase I) has been given the same preferential treatment. To the contrary, every mill that has signed an EPA with BC Hydro has been subject to the same exclusivity provision found in section 7.4 of the 2009 EPA with Celgar. No other EPA proponent has been offered a similar Side Letter Agreement with BC Hydro.”) 74 See Claimant’s Reply, fn. 699, where they acknowledge that “resolution of Celgar’s below-GBL sales” were left to the BCUC. 75 BCUC, Decision and Order G-188-11, Zellstoff Celgar Limited Partnership Complaint Regarding the
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
16
Merwin wrote BC Hydro on November 29, 2011, requesting that the Side Letter
Agreement be put into effect and that section 7.4(b) be amended out of its EPA.76 BC
Hydro did not object to putting the Side Letter Agreement into effect; however, while BC
Hydro discussed the details of the amendment with FortisBC (i.e., the rate and service
that would be provided by FortisBC for replacement of the Claimant’s electricity) the
Claimant filed its Notice of Intent under the NAFTA on January 26, 2012. It has not since
followed-up with its request to exercise the Side Letter Agreement.
For these reasons, it is patently false for the Claimant to assert that BC Hydro has40.
unlawfully prevented it from selling below-GBL electricity to third parties as a result of
the exclusivity clause in the EPA. Not only does the Claimant fail to mention the Side
Letter Agreement, it also fails to mention the favorable decisions of the BCUC that allow
it to sell its below-GBL electricity to third parties.
Second, the Claimant is wrong to assert that the BCUC has restricted the41.
Claimant’s “access to FortisBC embedded cost electricity while selling electricity,”77 or
that it has imposed on Celgar “a ‘net-of-load’ access standard that it applied to no other
BC pulp mill.”78 To support its claim, the Claimant focuses solely on, and
mischaracterizes, BCUC Order G-48-09.
The BCUC in Order G-48-09 prohibited FortisBC from purchasing BC Hydro’s42.
1993 PPA electricity to provide to customers that were also selling electricity unless
those customers were “net-of-load” on dynamic basis. BCUC Order G-48-09 did not
prohibit FortisBC from using other resources to supply electricity to customers engaging
Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, November 14, 2011, p. 49, R-275. 76 Letter from B. Merwin to BC Hydro dated December 6, 2011, R-485, (CAN003246) CAN003765. Mr. Merwin requested “that BC Hydro enter into an amendment agreement effecting the changes to the EPA contemplated by the Letter Agreement.” See also, letter from B. Merwin to BC Hydro dated January 23, 2012, R-570. 77 Claimant’s Reply, ¶ 35. 78 Claimant’s Reply, ¶ 4.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
17
in below load sales—FortisBC simply had a difficult time determining how it would
separate BC Hydro’s 1993 PPA electricity from the rest of its resources.
The BCUC determined in Order G-188-11 that “Celgar is free to sell all or a43.
portion of its generation below the BC Hydro GBL into the market and supply its mill
from FortisBC resources, not including BC Hydro PPA Power”79 and subsequently
confirmed that Celgar can in fact sell up to 100% of its load.80
In response to BCUC Orders G-188-11 and G-202-12, FortisBC developed the44.
NECP rate as the replacement cost of power to facilitate sales. FortisBC proposed to
source the NECP electricity from all of its sources with the exception of BC Hydro 1993
PPA power.81 The Claimant alleges that the NECP rate would not reflect “traditional
embedded cost rates”. However, Mr. Dennis Swanson confirms that since 2009 the cost
of the NECP rate would have been no different than FortisBC’s normal rate for industrial
customers (i.e., Rate Schedule 31).82
Thus, the Claimant’s contention that the BCUC unlawfully “impose[d] a net-of-45.
load access standard on Celgar by effectively preventing FortisBC from selling Celgar
any embedded cost electricity from Fortis’ pre-existing resource stack while Celgar is
selling electricity”83 is patently false.
C. Materials Submitted by Canada
Canada’s Rejoinder is accompanied by exhibits and legal authorities. In addition,46.
Canada submits the following Witness Statements and Expert Reports in support of its
Rejoinder:
79 BCUC Decision and Order G-188-11, Reasons for Decision, p. 49, R-275. 80 BCUC Order G-202-12, p. 3, R-265. 81 Dennis Swanson Statement II, ¶ 28. 82 Dennis Swanson Statement II, ¶ 33. 83 Claimant’s Reply, ¶ 33.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
18
Second Witness Statement of Les MacLaren:
● Mr. Les MacLaren, the Assistant Deputy Minister of the Electricity andAlternative Energy Division of the Ministry of Energy, corrects theClaimant’s mischaracterizations of B.C. energy policy, BC Hydro’sprocurement practices and regulation by the BCUC. He also explains thatthe 1991 Ministers’ Order, which requires Celgar to use its self-generatedelectricity to displace its load, remains in force.
Second Witness Statement of Jim Scouras:
● Mr. Jim Scouras, BC Hydro’s former Manager of Commercial Acquisitions,describes the negotiations between BC Hydro and Celgar that led to theexecution of the 2009 Side Letter Agreement, and explains that theexclusivity provision of the EPA cannot be understood without it. He alsocorrects the Claimant’s mischaracterisation of certain facts relating to BCHydro’s procurement processes and Seller Consumed Energy.
Second Witness Statement of Lester Dyck:
● Mr. Lester Dyck, Sector Manager of Pulp & Paper and Customer Generationat BC Hydro, reiterates that BC Hydro uses GBLs to define what constitutesincremental energy that BC Hydro will consider procuring in an EPA. Healso corrects certain of the Claimant’s mischaracterisations relating to thesetting of GBLs for BC Hydro’s EPAs with Celgar, Tembec and HoweSound.
Second Witness Statement of Pierre Lamarche:
● Mr. Pierre Lamarche, formerly Manager – Energy at the Howe Sound mill,explains that Howe Sound and BC Hydro
Second Witness Statement of Dennis Swanson:
● Mr. Dennis Swanson, Vice President of Corporate Services at FortisBC,corrects certain of the Claimant’s mischaracterizations of the negotiations ofthe Power Supply Agreement between Celgar and FortisBC and on theestablishment of a FortisBC GBL for Celgar. He also explains that, underFortisBC’s matching methodology, Celgar would not be prevented fromaccessing low-cost power from FortisBC even when selling its below-loadenergy to market.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
19
Witness Statement of Dr. Jon O’Riordan:
● Dr. O’Riordan, former Assistant Deputy Minister, Environmental Programsat the BC Ministry of Environment, Lands and Parks (1989 to 1994) explainsthat, during the Celgar mill expansion project review, Celgar’srepresentatives touted expected electrical self-sufficiency as an importantfeature of the project.
Witness Statement of Dean Krauss:
● Mr. Krauss is the Director of Business Development and Contract Servicesat NorthPoint Energy Solutions Inc. His statement explains that NorthPointhas never identified sales opportunities in the US for Celgar for a periodgreater than three months, that Mid-C prices tumbled after 2008, and thatNorthPoint has never brokered renewable power on green markets.
Witness Statement of Michael MacDougall (Powerex):
● Mr. MacDougall is the Director of Trade Policy & Information Technologyfor Powerex Corp. and has been employed by Powerex since February 1999.Mr. MacDougall explains that Celgar could not have entered into profitablelong-term sales of self-generated power in the US for lack of propertransmission rights, attractive Mid-C prices, and access to renewablemarkets.
Witness Statement of Roger Garatt (Puget Sound):
● Mr. Garatt, Director Strategic Initiatives at Puget Sound Energy, Inc.,explains that he has no specific recollection of Mercer, and that Puget Soundwas not likely interested in purchasing Celgar’s self-generated electricity.
Witness Statement of Denise Mullen:
● Ms. Mullen, former Director of the Projects and Policy Branch of the B.C.Ministry of Energy, Mines and Petroleum Resources (1988 to 2002),explains how Energy Project Review processes were conducted in BC in thelate 1980s and early 1990s. She confirms that Ministry officials would haveconsidered Celgar’s self-supply commitments to be important.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
20
Witness Statement of Christian Lague:
● Mr. Lague is Engineer, Projects and Energy at Skookumchuck Pulp Inc. andhas been working at the mill since 1987. He describes the terms of Tembec’s1997 EPA with BC Hydro, and explains the circumstances leading to thenegotiation and conclusion of Tembec’s 2009 EPA with BC Hydro,including the setting of the GBL.
Second Expert Report of NERA Economic Consulting:
● Dr. Michael Rosenzweig, Special Consultant with NERA EconomicConsulting, has provided a rebuttal expert report correcting Dr. Fox-Penner’s, Mr. Switlishoff’s and Mr. Kaczmarek’s mischaracterisations andflawed assumptions. His expert report concludes that the challengedmeasures have not caused the Claimant to suffer economic harm.
Second Expert Report of Pöyry Management Consulting Inc.:
● Mr. James Stockard, Senior Consultant with Pöyry Management ConsultingInc, has provided a second expert report analyzing Celgar’s normaloperations, including energy generation in 2007, and concluding that Celgarwould have continued to operate in a similar manner without the FortisBCand NorthPoint sales contracts. He also provides additional analysis of theGBLs set for Tembec and Howe Sound.
Expert Report of David Bursey:
● Mr. David Bursey is a practicing lawyer in British Columbia and an experton energy regulation in the Province. His expert report summarizes theregulatory regime under which the BCUC operates and reviews keyprinciples established by the BCUC to regulate industrial customers’entitlement to receive utility power supply while selling self-generatedpower. He also concludes that the 1991 Ministers’ Order remains in effectand imposes self-sufficiency obligations on Celgar.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
21
II. FACTUAL BACKGROUND
A. The Claimant Has An Obligation to Supply its Mill Energy Needs
As explained in Canada’s Counter-Memorial,84 the Celgar Pulp Company’s47.
(which previously operated the mill) proposed installation of a new turbine in the early
1990s required it to apply for an Energy Project Certificate from the Minister of Energy.
Celgar in its application for the new turbine committed to use the turbine for the purpose
of self-supply. That commitment is still binding today, in effect through a Ministers’
Order that was granted in response to the application, which the Claimant assumed in
2005 when it purchased the mill.
The Claimant dedicates nearly 50 pages of its Reply Memorial to this issue,48.
alleging that no such commitment was either made, or that the commitment should no
longer be of any effect.85 It also filed three new witness statements and a new expert
report to address the issue. The extent of the Claimant’s arguments is telling as to the
implications of the Ministerial Order because the Claimant’s entire NAFTA case depends
on its ability to sell its self-generation from the turbine installed in 1993.
As shown below and through the witness statements of Peter Ostergaard, John49.
O’Riordan, and Denise Mullen, as well as the expert report of David Bursey, the
Claimant’s attempts to sidestep its legal obligation to self-supply have no merit.
1. The Claimant is Required to Displace its Load with the Self-Generation from its Original Turbine under the Terms of theMinisters’ Order
As Canada explained in its Counter Memorial,86 the Celgar pulp mill was50.
operated by Celgar Pulp Co. (“Celgar Pulp”) a joint venture of CITIC B.C. and Power
Consolidated (China) Pulp Inc. in the late 1980s. Celgar Pulp had repeatedly failed to
84 Canada’s Counter-Memorial, ¶¶ 173-187. 85 Claimant’s Reply, ¶¶ 27-64. 86 See generally, Canada’s Counter Memorial, ¶¶ 170-187.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
22
meet provincial emissions standards which forced the Ministry of Environment to issue a
Variance Order that provided it with a limited amount of time to bring its emissions back
into line with provincial regulations.87
Celgar Pulp estimated that the cost of bringing the mill into compliance with51.
provincial environmental regulations would be C$ 110-150 million.88 It determined that it
could only afford to make this investment if it was part of a larger project to modernize
the pulp mill and double its production capacity. This proposal was controversial as the
pulp mill had attracted a considerable amount of negative attention following the
Variance Order and the Kootenay region had a long history of environmental activism.89
Celgar Pulp submitted a Prospectus with its proposal to modernize the pulp mill52.
in accordance with the B.C. Major Projects Review Process in December 1989.90 The
Major Project Review Committee distributed the Prospectus widely to 26 agencies within
the provincial government, the federal government and certain U.S. agencies for
comment; the Committee subsequently determined that the project should proceed to
Stage II and a joint federal-provincial environmental review.91 The Ministry of Energy
also determined that the installation of a large thermal electric plant required a separate
application for Energy Project Certificate (“EPC”).
Celgar Pulp’s Prospectus was also the first in a series of not less than 7 separate53.
representations that it made — often in response to comments from the Ministry of
87 Jon O’Riordan Statement, ¶¶ 16-20. See also B.C. Ministry of Environment and Ministry of Regional and Economic Development, Review of Prospectus for Celgar Pulp Mill Expansion, July 1990, s. I.1, at 1-2, R-327; BC Environment Briefing Note, CITIC (50% owners of Celgar Pulp) to Review Permit Amendments Issued by Order-in-Council June 28, 1991, dated July 10, 1991, at 1, R-328. 88 B.C. Ministry of Environment and Ministry of Regional and Economic Development, Review of Prospectus for Celgar Pulp Mill Expansion, July 1990, s. I.2, at 2, R-327. 89 Jon O’Riordan Statement, ¶¶ 17-18. 90 Celgar Pulp Company, Proposed Modernization and Expansion Project, 1989, R-395. 91 Jon O’Riordan Statement, ¶¶ 25, and 31-35.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
23
Energy — that it would use its self-generation to displace its load so that the pulp mill
would be energy self-sufficient.
Celgar Pulp’s Submissions Concerning Load Displacement
Submission Process Date Representation
Prospectus Major Project Review Process
December1989
The modernized mill will be up to 90% energy self-sufficient, compared to the existing mill which only provides 11% of its own power.92
Environmental Impact Assessment
Major Project Review Process
December 1989
The expanded mill will require 52 megawatts, though the mill will generate 47 megawatts, which is 90% self-sufficient for power requirements compared to the existing mill’s capability to produce 11% of its requirements.93
Stage II Report – Special Interests Public Concerns
Major Project Review Process
July 1990 The modernized mill, as designed, will be 90% energy self-sufficient. This is a large improvement over the existing mill, that produces only 11% of the energy it requires. Only a small amount of electrical energy will be purchased to operate the modernized mill, in addition to stand-by power for start-up requirements. … Celgar will continue to explore all energy alternatives that it believes will help it to achieve even more complete self-
92 [Italics and Bold in original] Celgar Pulp Company, Proposed Modernization and Expansion Project, 1989, p. 7, R-395. 93 Celgar Pulp Company, Bleached Kraft Mill Expansion, Environmental Impact Assessment, December 1989, ss. 2.2.3, “Steam Production and Power Consumption”, p. 13, R-405.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
24
sufficiency in energy and to maximize the efficiency of its energy use.94
Major Project Review Committee Meeting
Major Project Review Process
August 16, 1990
Celgar explains that the proposed energy cogeneration aspects of the pulp mill expansion project would be in the range of 48 MW.95
Draft Energy Project Certificate Application
Energy Project Review Process
September 11, 1990
The expanded mill will require 52 megawatts, though the mill will generate 47 megawatts, which is 90% self-sufficient for power requirements compared to the mill’s existing capacity to produce 11% of its requirements.”96
[…]
The modernized mill will require approximately 54 MVA. The new turbogenerator will be capable of producing 48 MVA and the balance (estimated at 4-6 MVA) will be purchased from West Kootenay Power.”97
Energy Project Certificate Application
Energy Project Review Process
October 12, 1990
The heat generated in burning the black liquor will be used to produce steam. This steam, when passed through a turbo-generator, will under normal conditions supply 100% of the modernized mill’s electrical power
94 [emphasis in original] See Celgar Pulp Company, Proposed Modernization of Bleached Softwood Kraft Pulp Mill Castlegar, B.C., Stage II Report, Volume 1, Overview and Environmental Summary, July 1990, pp. 35-36, R-102. 95 Jon O’Riordan Statement, ¶ 44. 96 Celgar Pulp Company, “Application for an Energy Project Certificate (E.P.C.A.) Under Section 18 of the Utilities Commission Act”, September 11, 1990, p. 13, R-408. 97 Celgar Pulp Company, “Application for an Energy Project Certificate (E.P.C.A.) Under Section 18 of the Utilities Commission Act”, September 11, 1990, p. 7, R-408.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
25
requirements. […]
It is estimated that the expanded mill will require approximately 50 megawatts of power and will be capable of generating 50 megawatts, which will make the mill 100% self-sufficient under normal operating conditions.98
[…]
This fuel, combined with a larger, higher pressure and more efficient recovery boiler affords the opportunity to increase the power generating potential and make the mill more energy self-sufficient. The present mill relies on West Kootenay Power for the majority of its electrical power requirements – approximately 22 MVA. The existing mill operates a 2.5 MW extraction/condensing turbogenerator which supplies the balance. The modernized mill will require approximately 50 megawatts of power. The new turbogenerator will be capable of producing 50 megawatts. An additional tie-transformer (20MVA) is proposed to allow the purchase of the additional power requirements necessary to run the modernized mill during the infrequent, but essential, outages of the 50 [sic] megawatts turbogenerator.
Celgar Expansion Review Panel – Celgar Pulp’s Closing Statement
Celgar Expansion Review Panel – Federal-Provincial
November 9, 1990
The Panel was presented with the following specific examples of state-of-the-art, but proven, technology that will be used in the modernized mill: […]
(viii) a turbo generator will be installed
98 [Emphasis in Original] Affidavit of the General Manager of Celgar, Robert W. Sweeney, October 12,
1990 and Application for an Energy Project Certificate (E.P.C.A.) under section 18 of the Utilities
Commission Act, Celgar Pulp Company (“Celgar 1990 EPC Application”), ss. (b) and (c)(i), R-97
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
26
Environmental Review
which will allow the mill to produce up to 90 percent of its electrical power requirements from by-product steam. The existing mill produces only 11% of its electrical energy requirements.99
These multiple representations emphasized that Celgar Pulp would use its self-54.
generation to displace its load and were used to sell the proposed expansion to the B.C.
government and the general public. This strategy was successful with the joint federal-
provincial review panel expressly recognising self-generation and load displacement as a
pivotal consideration for approving the project while at the same time acknowledging that
the regulation of the new turbine fell primarily under the jurisdiction of the B.C. Energy
Project Review Process.100
2. Celgar Pulp Applies for an Energy Project Certificate
As a result of Celgar Pulp’s representations to the B.C. Major Project Review55.
Committee, Peter Ostergaard, then an Acting Assistant Deputy Minister, wrote to Richard
Wigen, Assistant Project Manager for the Celgar project, to advise him that Celgar Pulp
was required to submit an Energy Project Certificate application for expansion of its
thermal electric plant under the UCA.101 He also emphasized the following policy
concern in his correspondence:
The Ministry of Energy and B.C. Hydro have identified pulp mill expansions as a significant component of incremental electricity demand in British Columbia during the 1990s. The Ministry wants to ensure that load displacement (e.g., through conservation, energy efficiency measures, self-
99 Celgar Pulp Company, Proposed Modernization of Bleached Softwood Kraft Mill, Castlegar, B.C., Closing Statement, 9 November 1990, pp. 42 and 46, R-413. 100 Celgar Expansion Review Panel, Final Report, February 1991, p. 43, R-330. The Claimant ignores the fact that the Celgar Expansion Review Panel did not have jurisdiction over the approval of the thermal electric plant when it observes that the Celgar Expansion Review Panel did not make recommendations with respect to energy self-sufficiency. See Claimant’s Reply, ¶ 88. 101 [Emphasis Added] Letter from Peter Ostergaard to R.C. Wigen, Assistant Project Manager, Celgar Pulp Expansion, dated August 23, 1990, pp. 1-2, R-96. Peter Ostergaard Statement, ¶ 13.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
27
generation and cogeneration) is thoroughly explored before utilities are forced to build new generation resources to serve expanded industrial loads. For this reason, the Ministry supports initiatives to increase the energy efficiency and self-sufficiency of Celgar’s proposed pulp mill expansion.102
Mr. Ostergaard therefore requested that Celgar explain whether it intended to56.
displace its load through self-generation103 so that utilities such as FortisBC were not
forced to build new generation resources.
On October 12, 1990, Celgar Pulp submitted its EPC application in which it stated57.
the following with respect to self-generation:
The heavy black liquor, which contains the lignin and spent cooking chemicals from the digester, will be burned in a new recovery boiler (27). The recovery boiler will burn the organic material (i.e., lignin) in the heavy black liquor and coverts the inorganic chemicals primarily to sodium carbonate and sodium sulphide. The inorganic chemicals will be removed as molten smelt. The heat generated in burning the black liquor will be used to produce steam. This steam, when passed through a turbo-generator, will under normal conditions supply 100% of the modernized mill’s electrical power requirements.
[…]
It is estimated that the expanded mill will require approximately 50 megawatts of power and will be capable of generating 50 megawatts, which will make the mill 100% self-sufficient under normal operating conditions.104
These are the only statements in the entire EPC application, aside from sub-headings, that
were bolded. The EPC application also stated under “Project Justification” that:
102 Letter from Peter Ostergaard to R.C. Wigen, Assistant Project Manager, Celgar Pulp Expansion, dated August 23, 1990, p. 1, R-96. Mr. Allan confirms that this statement reflected the Ministry of Energy policy at this time. See John Allan Statement, ¶¶ 17-18. 103 The production of self-generated electricity is often referred to as cogeneration by the Ministry of Energy in the early 1990s. 104 [Emphasis in Original] Application for an Energy Project Certificate (E.P.C.A.) under section 18 of the Utilities Commission Act, Celgar Pulp Company, pp. 10-11, R-97.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
28
This fuel, combined with a larger, higher pressure and more efficient recovery boiler affords the opportunity to increase the power generating potential and make the mill more energy self-sufficient. The present mill relies on West Kootenay Power for the majority of its electrical power requirements – approximately 22 MVA. The existing mill operates a 2.5 MW extraction/condensing turbogenerator which supplies the balance. The modernized mill will require approximately 50 megawatts of power. The new turbogenerator will be capable of producing 50 megawatts. An additional tie-transformer (20MVA) is proposed to allow the purchase of the additional power requirements necessary to run the modernized mill during the infrequent, but essential, outages of the 50 [sic] megawatts turbogenerator.105
To remove any doubt Lorne Parnell, Vice President of Celgar Pulp, stated in a58.
covering letter submitted with the EPC application that “… the pulp mill will be
essentially self-sufficient in energy as purchased power will be significantly reduced after
the implementation of the electric generation project.”106
On May 23, 1991, the Minister of Energy and the Minister of Environment59.
approved Celgar Pulp’s EPC application to install a new thermal electric generator
through a Ministers’ Order issued pursuant to section 19(1)(c) of the UCA. The
Ministers’ Order required Celgar Pulp to design, locate, construct and operate its thermal
electric plant in accordance with its EPC application.
3. The Evidence Concerning the Ministers’ Order
The Ministers’ Order, the EPC Application and the related contemporaneous60.
correspondence are clear and are also considered the most compelling form of evidence
in an international arbitration.107 Mr. Ostergaard raised policy concerns the Ministry of
105 [Emphasis in Original] Application for an Energy Project Certificate (E.P.C.A.) under section 18 of the Utilities Commission Act, Celgar Pulp Company, p. 17, R-97. 106 Letter from Lorne Parnell to Peter Ostergaard, October 12, 1990 [attached at end of EPC application], R-97. 107 Bin Cheng, General Principles of Law as Applied by International Courts and Tribunals (Cambridge: Grotius Publications, 1987), pp. 318-219, RA-52 (“[D]ocumentary evidence stating, recording, or sometimes even incorporating the facts at issue, written or executed either contemporaneously or shortly after the events in question by persons having direct knowledge thereof, and for purposes other than the
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
29
Energy had with respect to self-generation and load displacement.108 Celgar Pulp
submitted an EPC application that directly addressed these policy concerns. The
Ministers’ Order subsequently directed them to operate their turbine in accordance with
the representations made in the application.
The officials that were involved in or that had direct knowledge of Celgar Pulp’s61.
EPC application have also testified that it was their understanding that Ministers’ Order
required the pulp mill to operate turbine displace its load which would make it 100%
energy self-sufficient in normal conditions.109 Mr. Ostergaard has already testified that he
supported the EPC application for this reason.110 Similarly, Dr. O’Riordan, the Assistant
Deputy Minister, Environmental Programs, at the Ministry of Environment at the time
also recalls personally briefing David Mercier the new Minister of Environment on the
Celgar EPC application.111 Dr. O’Riordan testifies that the fact that the project was
energy self-sufficient was a selling point to himself and Mr. Doug Dryden who was the
Ministry of Environment representative on the Energy Project Coordinating Committee.
The Minister agreed and signed the Ministers’ Order on that basis.112
The Claimant’s witnesses all lack first-hand knowledge of the development of62.
Celgar’s EPC application or the subsequent approval of Ministers’ Order. Mr. Sweeney,
for example, admits that he believes that the EPC Application “… must have been
developed by others and presented to me as a document that was a routine submission for
presentation of a claim or the support of a contention in a suit, is ordinarily free from distrust and considered of higher probative value.”); and Alan Redfern & Martin Hunter, Law and Practice of International Commercial Arbitration, 4th ed. (London, Sweet & Maxwell, 2004), pp. 307-308, RA-53 (“In general, arbitral tribunals tend to give less weight to uncorroborated witness testimony than to evidence contained in contemporaneous documents.”) 108 See Letter from Peter Ostergaard to Mr. R.C. Wigen, Assistant Project Manager, Celgar Pulp Expansion, dated August 23, 1990, R-96. 109 Peter Ostergaard Statement, ¶ 20; and Jon O’Riordan Statement, ¶ 77. 110 Peter Ostergaard Statement, ¶¶ 17, 18-21. 111 Jon O’Riordan Statement, ¶¶ 74-75. 112 Jon O’Riordan Statement, ¶ 75.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
30
governmental approval …”113 Similarly, Mr. Allan, who after leaving the civil service
spent more than 15 years representing the forest products sector,114 admits that he does
“not have a specific recollection of the Order”115 and observes that he is not “a lawyer
and leave[s] to others the legal issues in this case”116—immediately before offering
opinion evidence concerning the interpretation of the Ministers’ Order as a fact
witness.117 Finally, Mr. McLaren, Celgar’s former Environmental Manager, explains that
he was involved in the federal-provincial environmental review, but is ambiguous
concerning his involvement in the EPC application.118 This is because he had no direct
involvement in the process. Dr. O’Riordan relates that Mr. Dryden, the former Director
of the Environmental Assessment Branch, has informed him that he has no recollection of
consulting Mr. McLaren concerning this EPC application.119
Mr. Allan and Mr. McLaren are also not disinterested third party witnesses.63.
Rather, these witnesses are consultants with close business and personal relationships
with the Claimant and direct involvement in its attempt secure energy subsidies from the
B.C. Government and BC Hydro. Mr. Allan casts himself as an “independent”120
consultant. However, he does not disclose in his witness statement that during his time
with the Council of Forest Industries he actively supported the lobbying efforts of the
Pulp and Paper Task Force to convince the B.C. Government to provide the pulp and
113 Robert Sweeney Statement, ¶ 3. 114 John Allan Statement, ¶ 9. 115 John Allan Statement, ¶ 12. 116 John Allan Statement, ¶ 19. 117 John Allan Statement, ¶¶ 19-20. See e.g. Meeting Notes, Pulp and Paper Task Force on Self-Generation, R-532. Allan was present at Task Force meetings between January 2008 to June 2008. See also Draft Terms of Reference, Working Group on Pulp and Paper Self-Generation Sales Policy, March 25, 2008, R-533. 118 See James McLaren Statement, 12 December 2014, ¶ 10. (“I was an official of the Ministry of the Envrionment when Celgar filed its [EPC] Application to expand and modernize the pulp mill.”) 119 Jon O’Riordan Statement, ¶ 81. 120 John Allan Statement, ¶ 9.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
31
paper industry with energy subsidies. Similarly, Mr. McLaren was intimately involved in
assisting Mr. Merwin’s with his “Arbitrage Project” during his tenure in Celgar. His
antipathy to BC Hydro is reflected in some of his contemporaneous internal
communications.121 This Tribunal, therefore, should treat the post hoc evidence provided
by these consultants with caution.
4. The Claimant’s Numerous Allegations Concerning the Ministers’Order
The Claimant first attempts to assert that the Ministers’ Order does not impose a64.
condition to use the turbine to displace its load as the description Celgar Pulp provided in
the EPC application was only an estimate.122 In particular, it relies heavily on one of the
statements in the EPC application which indicates that: “[i]t is estimated that the
expanded mill will require approximately 50 megawatts of power and will be
capable of generating 50 megawatts, which will make the mill 100% self-sufficient
under normal operating conditions.”123
Canada observes that Celgar Pulp’s first representation in the EPC application65.
which is made on the previous page is not qualified as an “estimate”. Celgar Pulp
indicated that: “[t]he heat generated in burning the black liquor will be used to
produce steam. This steam, when passed through a turbo-generator, will under
normal conditions supply 100% of the modernized mill’s electrical power
requirements.124 This statement isn’t ambiguous. Celgar Pulp represented here that the
121 Email from J. MacLaren to B. Merwin, Re: Phase I Request for Proposals: Notice to Customers of GBL, May 4, 2008, R-534 (“Good luck in getting a meeting with Scouras as we need to be blunt regarding their new found belief that we are [sic] their customer. I have had too many re-buffs over the years from BC Hydro telling me that I am not a customer and that I would not get that same treatment as their customers. … If we can’t break the BC Hydro position that the existing TG GBL portion is ineligible, then we must fight to establish our GBL to be as low as credible – I support your logic of picking a GBL of 33 MW to reflect conditions prior to Mercer’s energy investments.”) 122 Claimant’s Reply, ¶ 68. Robert Sweeney Statement, ¶ 6. 123 [Emphasis in Original] Application for an Energy Project Certificate (E.P.C.A.) under section 18 of the Utilities Commission Act, Celgar Pulp Company, p. 11, R-97. 124 [Emphasis in Original] Application for an Energy Project Certificate (E.P.C.A.) under section 18 of the
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
32
steam from burning black liquor in the recovery boiler alone will normally be sufficient
to meet all of the pulp mill’s electrical power requirements.125 Mr. David Bursey,
Canada’s legal expert, concludes that the Ministers’ Order is clear and that requires the
Claimant to use its electricity to supply the mill.126 Nor is this an inflexible requirement
to maintain 100% energy self-sufficiency at all times. Rather, Celgar Pulp indicated that
this would only occur under “normal conditions”.
The Claimant’s assertions also ignore the fact that Celgar Pulp was required to66.
provide specific information in its EPC application by regulation.127 Ms. Denis Mullen,
the former Director of the Project and Policy Branch, at the Ministry of Energy explains
that B.C. Reg. 388/80 and the Guide to the Energy Project Review Process detailed the
information that should be included in an EPC application including a detailed
description of the purpose of the project.128 The purpose of installing the turbine in this
instance is clear – Celgar Pulp planned to use the turbine to displace as much of its load
as possible so that it was essentially self-sufficient in terms of electricity. The Ministers’
Order required Celgar Pulp to operate the turbine for this purpose which is set out in a
clear manner in its application.129
Utilities Commission Act, Celgar Pulp Company, p. 10, R-97. 125 Mr. Sweeney also asserts that Celgar Pulp provided this information as a “good faith” estimate and that never intended to make commitments with respect to energy self-sufficiency. See Robert Sweeney Statement, ¶ 6. Mr. Sweeney, however, has also testified that he has no recollection of the EPC application and that he believes that it was prepared by others. See Robert Sweeney Statement, ¶ 3. This means he has no knowledge of the intent of Celgar Pulp’s counsel and the other staff that prepared the EPC application. Nor is this assertion particularly relevant. Celgar Pulp provided this information in its EPC application in bold font in its Project Description and then repeated it in its Project Justification. The Ministers’ Order then bound them to these representations. The fact that Celgar Pulp hoped that this would not be seen as a commitment is not relevant as to whether one was created. 126 David Bursey Expert Report, ¶¶ 180-185. 127 B.C. Reg. 388/80, s. 1, R-412. 128 Denise Mullen Statement, ¶ 18. 129 The Claimant asserts that load displacement “was the only use possible” for this electricity as British Columbia did not allow self-generators access to transmission at this time. See Claimant’s Reply, ¶ 70. It then rather confusingly admits that Celgar Pulp could sell its electricity to West Kootenay Power. See Claimant’s Reply, ¶ 113 and David Austin Expert Report, ¶ 31. The Claimant’s assertions concerning
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
33
B.C. Reg. 388/80 also required technical studies and information.130 The Guide to67.
the Energy Project Review Process explained that this technical information should
demonstrate the need for the electricity provided by the project by including how much
electricity the project will supply.131 It also indicated that certain projects should provide
“forecasts” and information on regional and provincial supply and demand. This
information could then be used for resource planning purposes (i.e., the acquisition of
new generation assets or transmission lines). Celgar Pulp forecast or “estimated” that the
turbine would provide 50 MW of electricity which would have been sufficient to meet
100% of the pulp mill’s electrical requirements. This did not require a proponent to
predict the precise amount of electricity the turbine would self-generate as a pulp mill’s
energy production using black liquor is directly linked to its pulp production. However,
it did have to provide the Ministry of Energy with a clear estimate of how much energy
the expanded pulp mill would self-supply and periodically consume for resource planning
purposes. This was particularly important given that Celgar Pulp was supplied by West
access to transmission are not entirely accurate. British Columbia’s Open Access Transmission Tariff did not exist at this time. However, Jack Davis, the Minister of Energy, Mines and Petroleum Resources issued a Statement on Power Export Policy in 1989 that indicated that the B.C. Government was willing to issue Export Removal Certificates for long term firm power sales on a project-by-project basis. See Jack Davis Statement on Power Export Policy, November 28, 1989, R-505. BC Hydro and West Kootenay Power were also willing to enter into EPAs with self-generators. For example, the Weyerhaeuser’s pulp mill in Kamloops B.C. proposed installing a thermal electric power plant that would make the pulp mill energy self-sufficient while providing a further of electricity to BC Hydro. Self-Generation Project at Weyerhaeuser Canada Ltd., Kamloops Pulp Mill. Energy Project Certificate Application (Preliminary)”, July 1990, p. 2, R-512. Moreover, West Kootenay Power issued a Call for Power in 1993 as a result of a projected shortfall in electricity. Letter from RG Siddall to Bob Learmouth, “Re: West Kootenay Power’s All Source Supply-Side Power Acquisition Request for Proposal,” June 3, 1993 R-508. Celgar Pulp also entered into a short term electricity sales arrangements with Pope & Talbot. See Fax from Clyde Sharp to Bob Williams/R Koots (Pope and Talbot), Re: Energy and Demand, dated June 15, 1993, R-510. 130 B.C. Reg. 388/80, s. 1(c)(i), R-412. 131 See B.C. Ministry of Energy, Mines and Petroleum Resources, Guide to the Energy Project Review Process (Queen’s Printer for British Columbia, 1982), Appendix 2 – Information Requirements, R-95. Mr. Ostergaard provided Celgar Pulp a copy of Reg. 388/80 and this Guide at the start of the Energy Project Review Process. See Letter from Peter Ostergaard to R.C. Wigen, Assistant Project Manager, Celgar Pulp Expansion, dated August 23, 1990, p. 2, R-96.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
34
Kootenay Power (“WKP”) which had insufficient resources to meet its load and which
was projecting an energy shortfall.132
Mr. Allan and Mr. McLaren confuse this issue further by comparing the policy68.
condition to operate the pulp mill in accordance with the EPC application to prescriptive
environmental regulatory regimes such as the precise effluent and emissions controls
under the B.C. Waste Management Act.133 These regimes have very specific
requirements as they concern public health and environmental protection from harmful
emissions. This is the reason these requirements have their own regulatory regime for
monitoring and reporting as well as an independent statutory decision maker that is
responsible for them.
The Claimant also complains that the B.C. Ministry of Energy did not actively69.
monitor Celgar Pulp’s compliance with its obligation to displace its load and suggests
that there was no enforcement mechanism in the Ministers’ Order. The Claimant’s
complaints ignore the fact that there was no need for the Ministry of Energy to monitor
this commitment at that time. The B.C. electricity sector was very heavily regulated in
the early 1990s. This meant that the Ministry of Energy would have been aware if the
Celgar Pulp decided to put the electricity to another use. For example, the approval of an
EPA with BC Hydro or WKP which would have required approval by the BCUC to
confirm that they were in the public interest.134 Moreover, British Columbia permitted
electricity exports through Powerex but only after a proponent had secured an Energy
Removal Certificate.135 Finally, Celgar Pulp would also have to submit a request for a
132 Peter Ostergaard Statement, ¶ 17; Denise Mullen Statement I, ¶ 35; Letter from RG Siddall to Bob Learmouth, “Re: West Kootenay Power’s All Source Supply-Side Power Acquisition Request for Proposal,” June 3, 1993, R-508. 133 John Allan Statement, ¶ 22; and James McLaren Statement, ¶¶ 15 and 18. 134 Utilities Commission Act, S.B.C. 1980, c. 60, as amended, s. 85.3, R-504. 135 Utilities Commission Act, S.B.C. 1980, c. 60, as amended, s. 22. (“So as to ensure the efficient use of resources and to ensure that the present and future requirements of the Province may be met, no person shall remove from the Province an energy resource produced, manufactured or generated within the Province, except in accordance with an energy removal certificate granted under this Part …”), R-504.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
35
modification to the Ministers’ Order. This regulatory regime meant that there was no
need to put in place an elaborate system to monitor compliance.
Mr. Allan also attempts to suggest that the Ministers’ Order did not create binding70.
commitments with respect to the EPC application as there was no “mechanism for
accountability” and no “consequences for non-compliance.”136 This is not true. First, the
Ministers’ Order itself indicates that:
This Order may be rescinded at the discretion of the Minister [of Energy, Mines and Petroleum Resources] if:
(a) Celgar commits a breach of the Conditions of this Order and fails to rectify the same, to the Minister’s satisfaction, within 30 days after notice requiring remedy is given by the Minister to Celgar.137
The Minister of Energy was empowered under section 124.1 to apply to B.C.71.
Supreme Court to restrain a person from constructing or operating this project in a
manner that was not in accordance with the Order. Finally, section 124(1)(g) made it an
offence to contravene section 17 which could have resulted in a fine of as much as
$10,000 per day.138 These provisions, which Mr. Allan does not appear to be familiar
with, provided a means of enforcing the Ministers’ Order. The Energy Project Review
Process was replaced in 1995 by the new Environmental Assessment Act. The Ministers’
Orders were transitioned under the provisions of this statute which also included
mechanisms for their enforcement.139
136 John Allan Statement, ¶¶ 23-24. 137 In the Matter of an Application by Celgar Pulp Company for an Energy Project Certificate for the Celgar Pulp Mill Expansion, Ministers’ Order dated May 23, 1991, s. 3, R-100. “Minister” is defined in the preamble as the Minister of Energy, Mines and Petroleum Resources. 138 S.B.C. 1980, c. 60, ss. 124(4) and (5) R-504. Denis Mullen Statement, ¶ 16. 139 See Les MacLaren Statement II, ¶¶ 33-32. David Bursey Expert Report, ¶¶ 170-175.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
36
Mr. Allan also argues that the Ministers’ Order does not create obligations in72.
“perpetuity”.140 Canada agrees. The Ministers’ Order remains in force for the lifespan of
the regulated project unless it was rescinded before then.141 This is reflected in section
51(9) of the Environmental Assessment Act, which replaced the UCA and continued to
govern EPCs and Minister’s Orders. According to EAA s. 51(9), Orders remain in effect
for the life of the project in respect of which it was issued.”142 Nor is it difficult to
modify a Ministers’ Order.
Ms. Mullen testifies that proponents frequently requested amendments to Orders73.
issued pursuant to section 19(1)(c) of the UCA.143 For example, if a proponent intended
to change the purpose of a regulated project, which would have affected the analysis of
the need for this electricity it could simply request an amendment pursuant to section 18
of the UCA.144 B.C. Reg. 388/80 set out the information that had to be included in a
request for a modification.145 Proponents made these requests when they wanted to
increase the size of their turbine.146 Similarly, Weyerhaeuser Canada submitted a draft
EPC application in July 1990 to install a 50 MW turbine at its Kamloops pulp mill to
displace its remaining load and sell the remaining of surplus electricity to
140 See e.g., John Allan Statement, ¶¶ 19 and 32; Claimant’s Reply, ¶¶ 77, 82 and 87. 141 See In the Matter of an Application by Celgar Pulp Company for an Energy Project Certificate for the Celgar Pulp Mill Expansion, Ministers’ Order dated May 23, 1991, s.3, pp. 2-3, R-100. 142 Les MacLaren Statement II, ¶¶ 44; Environmental Assessment Act, SBC 2002, c.43, s. 51(9), R-466. Environmental Assessment Act, RSBC 1996, c.119, s. 36, R-94. 143 Denise Mullen Statement, ¶ 55. 144 See e.g. Letter from Doug Dryden to Denise Mullen, Re: Modification to NW Energy Disposition Order, dated April 11, 1990, and attached draft modification order, R-515. See also, Letter from Doug Dryden to Denise Mullen-Dalmer, Re: NW Energy- Revision of Disposition order, dated December 16, 1993, and attached materials, R-516. 145 B.C. Reg. 388/80, s. 2, R-412. 146 Denise Mullen Statement, ¶ 55.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
37
BC Hydro.147 Weyerhaeuser Canada, however, had to resubmit is draft EPC application
in 1994 when it changed the purpose of the project to selling all of its electricity.148
The Claimant through Mr. Austin also claims that the Ministers’ Order could not74.
require its self-generation to be used to displace its load because it was not an energy
“use” project. Mr. Austin in a rather novel argument claims that the Ministry of the
Energy could only regulate how energy was used (i.e., the purpose of a project) if that
project was an energy “use” project. David Bursey, however, disagrees.149 This claim is
not supported by the UCA, B.C. Reg. 388/80 or contemporaneous materials produced by
the B.C. Ministry of Energy concerning energy “use” projects.
The Energy Project Review Process applied to “regulated projects” under Part 275.
of the UCA. Regulated projects are in turn defined to include “energy use projects”
which itself is defined in the following manner:
“energy use project” means a mill, factory, plant, smelter, oil refinery, metal refinery or other undertaking or facility designed to use, convert or process an energy resource or coal, or any combination of them, at the rate of 3 PJ or more a year, and for the purpose of this definition an energy resource other than electricity is used, converted or processed at that rate where it is of a quantity capable of yielding that amount of energy by combustion.150
The entire focus of this definition is on the amount of energy that the project76.
consumes or uses. These provisions were intended to regulate the amount of electricity
147See Weyerhaeuser Canada, Self-Generation Project at Weyerhaeuser Canada Ltd. Kamloops Pulp Mill, Energy Project Certificate Application (Preliminary), July 1990, pp. 1-2, R-512; Denise Mullen Statement, ¶ 46. 148 Weyerhaeuser Canada Ltd., Kamloops Energy Recovery Project, Draft EPC Application, November 1994, pp. 1 and 18, R-509. In particular, Weyerhaeuser Canada proposed selling of its electricity to Portland General Electric with the balance to be sold to other Canadian or U.S. utilities. Weyerhaeuser ultimately withdrew this application. 149 David Bursey Expert Report, ¶¶ 193-201. 150 Section 16 of the UCA defined an “energy resource” as “…natural gas and oil, and all other forms of petroleum and hydrocarbon, in gaseous or liquid state, and electricity.” This definition does not include black liquor.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
38
the proposed project would consume. This is confirmed by the Guide to the Energy
Project Review Process which describes energy “use” projects as:
[A]ny new project capable of using 3 PJ per year, or the addition of 3 PJ to an existing project.151
The Guide then provides examples of projects with such capacity such as Alcan’s77.
smelter in Kitimat. It follows that the “use” in an “energy use project” refers to amount
of energy that consumed and not the use that it was put to.
The Claimant, Mr. Austin and Mr. Allan also assert the rather unusual defense78.
that the Ministers’ Order no longer applies as a result of other subsequent changes in the
regulatory changes in British Columbia. Mr. Bursey, however, concludes that Ministers’
Order remains in force and effect.152 Mr. Bursey and Mr. MacLaren also explain how the
Ministry of Energy transferred responsibility for Ministers’ Order to the Environmental
Assessment Office following the entry into force of the new Environmental Assessment
Act.153 The Claimant, of course, is aware of this as it corresponded with the
Environmental Assessment Office when requested the assignment of the Ministers’ Order
to Celgar in March 2005.154
The Claimant also complains that the Ministers’ Order has not been raised at the79.
BCUC proceedings involving Celgar before this NAFTA arbitration. The Claimant is
correct, but this is understandable for a number of reasons. First, the Ministry of Energy
was no longer responsible for oversight and supervision of the Ministers’ Order. The
Energy Project Review Process was wound up with the repeal of Part 2 of the UCA in
151 See B.C. Ministry of Energy, Mines and Petroleum Resources, Guide to the Energy Project Review Process (Queen’s Printer for British Columbia, 1982), p. 6, R-95. 152 David Bursey Expert Report, ¶ 202(c). 153 David Bursey Expert Report, ¶¶ 170-175; and Les MacLaren Statement II, ¶¶ 31-33. 154 See Letter from Tom Theodorakis, Sangra Moller, Barristers & Solicitors to Joan Hesketh, Executive Director, Environmental Assessment Office, Re Celgar Pulp Company – Minister’s Order, dated February 16, 2005), R-322; and Letter from Joan Hesketh, Executive Director, Environmental Assessment Office to Tom Theodrakis, Sangra Moller Barristers & Solicitors, dated March 2, 2005, R-310.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
39
1995.155 British Columbia then adopted a more comprehensive environmental assessment
process with the promulgation of the Environmental Assessment Act. The provisions of
the new Environmental Assessment Act transitioned Orders issued pursuant to section
19(1)(c) of the UCA so that they remained in force and effect. Moreover, these Orders
were subsequently transferred to the Environmental Assessment Office which was then
responsible for their oversight and supervision in accordance with the Environmental
Assessment Act.156
Second, the BCUC proceedings involving the Ministry of Energy related to but80.
did not directly concern Celgar’s self-generation. The first BCUC proceeding in which
both Celgar and Ministry of Energy were interveners was the proceeding resulting in
BCUC Order G-48-09. This proceeding, however, was initiated in response to an
application by BC Hydro to amend its 1993 PPA with FortisBC.157 The Power Supply
Agreement that the BCUC analyzed in this case was the agreement with the City of
Nelson. The FortisBC-Celgar PSA was certainly discussed and evidence was filed
concerning this proposal, but the proceeding really concerned the overall principle of the
arbitrage of BC Hydro’s Rate Schedule 3808 electricity. The Claimant had withdrawn the
FortisBC-Celgar PSA before this proceeding commenced as both FortisBC and Celgar
believed that it was less likely to survive a challenge than the City of Nelson agreement
which was less commercial and involved smaller amounts of energy.
Third, the BCUC proceedings that followed were, for the most part, a dispute81.
between FortisBC and Celgar. The Ministry of Energy did not believe that it was
necessary to intervene.158 The Ministry of Energy, therefore, did not review the Orders
155 David Bursey Expert Report, ¶171. 156 Les MacLaren Statement II, ¶ 31. 157 Les MacLaren Statement II, ¶ 37. 158 Les MacLaren Statement II, ¶ 38.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
40
associated with the Celgar’s existing 52 MW turbine until the Claimant asserted that it
had never committed to use the electricity from this turbine to displace its load.159
The Claimant fails to mention that this issue of the Ministers’ Order was recently82.
raised before the BCUC. On October 14, 2014, the B.C. Public Interest Advocacy Centre
(“BCPIAC”) wrote to the BCUC requesting permission to file the Ministers’ Order and
the witness statement of Mr. Ostergaard in the context of the BCUC considering a stand-
by rate for Celgar.160 The Claimant indicated that it did not object to the filing of the
Ministers’ Order but quite reasonably opposed the introduction of a witness statement
filed in another proceeding.161 The BCPIAC subsequently withdrew its request to file the
witness statement on October 17, 2014. The BCUC issued an Order G-166-14 amending
the regulatory timetable.162 However, when the BCPIAC filed the Ministers’ Order and
the supporting EPC application the Claimant objected to the introduction of the EPC
application on the basis that it did not form part of the Ministers’ Order and that the
resolution of this issue would require the filing of additional evidence.163 The
159 Les MacLaren Statement II, ¶ 34-35. See also Claimant’s Memorial ¶ 575 (“Celgar never committed to use its self-generated electricity to meet its own load; nevertheless, BC Hydro and the BCUC did not permit Celgar to access embedded cost utility power at all while selling power. See also Brian Merwin Statement, ¶110 (“Celgar has never signed any load displacement or other agreement in which it has committed to use it self-generation to meet its load”). 160 Letter from Tannis Braithwaite, Executive Director to Erica Hamilton, Commission Secretary, Re FortisBC Inc. 2014 Stepped and Stand-by Rates for Transmission Voltage Customers, 14 October 2014, R-535. 161 Letter from Kim Moller, Sangra Moller LLP, to Erica Hamilton, Commission Secretary, Re: Zellstoff Celgar – Submissions re: BCPSO request for extension of time to file Intervener Evidence – FortisBC Inc. Application for Stepped and Stand-by Rates for [sic] Company Transmission Customers, 15 October, 2014, R-536. 162 BCUC Order G-166-13, In the matter of the Utilities Commission Act, R.S.B.C. 1996, Chapter 473 and FortisBC Inc. Application for Stepped and Stand-By Rates for Transmission Voltage Customers, October 27, 2014, ¶ 1, R-537. 163 Letter from Kim Moller, Sangra Moller LLP, to Erica Hamilton, Commission Secretary, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – FortisBC Inc. Application for Stepped and Stand-by Rates for Transmission Customers, 29 October, 2014, pp. 2-3, R-538 and Letter from Kim Moller, Sangra Moller LLP, to Erica Hamilton, Commission Secretary, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – FortisBC Inc. Application for Stepped and Stand-by Rates for Transmission Customers, 14 November 2014, R-539.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
41
BCPIAC,164 FortisBC,165 the B.C. Government,166 and BC Hydro167 all supported the
introduction of this evidence so that the BCUC could resolve this issue. The BCUC,
cognizant of the Claimant’s objections and the delay this could cause ultimately excluded
the EPC application as late evidence.168 The Claimant has therefore thwarted the BCUC
from considering and resolving the interpretation of the Ministers’ Order. The reason is
simple: the BCUC is a professional quasi-judicial tribunal with expertise in this area and
there was simply no chance that they would support the Claimant’s unreasonable
interpretation of the Ministers’ Order.
Finally, Canada would request that this Tribunal exercise caution concerning83.
some of the extreme positions the Claimant has adopted in the context of this arbitration.
The Claimant and its consultants are essentially requesting that this Tribunal find that
part of a domestic regulation is void for vagueness. It was very common for the Ministry
of Energy and the Ministry of Environment to impose a condition when it was regulating
energy and environmental projects that the applicant design and operate its project in
accordance with its application. The Claimant’s suggestion that this is “boilerplate” is
convenient for their desired outcome, but ultimately irresponsible as it does not address
the systemic consequences of such a decision. EPC applications and other applications
relating to other energy and environmental projects may have been incorporated by
164 Letter from Erin Prichard, Barrister & Solicitor to Erica Hamilton, Commission Secretary, Re: FortisBC Inc. (FBC) 2014 Stepped and Stand-by Rates for Transmission Voltage Customers – BCOAPO Submissions on Exhibit C-30, 5 November 2014, R-540. 165 Letter from Diane Roy, Director, Regulatory Services to Erica M. Hamilton, Commission Secretary, FortisBC Inc. (FBC or Company) Application for Stepped and Stand-by Rates for Transmission Voltage Customers, Zellstoff Celgar Limited Partnership (Celgar) Exhibit C2-30, 5 November 2014, R-541. 166 Letter from Josh Walters, Counsel to Erica Hamilton, Commission Secretary, Re: FortisBC Inc. Application for Stepped and Stand-by Rates for Transmission Voltage Customers, 5 November 2014, R-542. 167 Letter from Ian Webb, Lawson Lundell LLP to Erica Hamilton, Commission Secretary, British Columbia Utilities Commission (“Commission”) – FortisBC Inc. 2014 Stepped and Stand-by Rates for Transmission Voltage Customers, 5 November 2014, R-543. 168 BCUC Order G-179-14 and Reasons, Re: In the matter of the Utilities Commission Act, R.S.B.C. 1996, Chapter 473 and FortisBC Inc. Application for Stepped and Stand-By Rates for Transmission Voltage Customers, 17 November 2014, ¶ 1, R-544.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
42
reference into Orders and addressed serious regulatory and environmental issues. This
NAFTA arbitration is being closely followed by other domestic interests and this
Tribunal should not lightly find that B.C.’s regulations void for vagueness or that they are
no longer in force or effect.
B. British Columbia’s Policy Developments with Respect to Self-Generators of Electricity
1. The BCUC Directs BC Hydro to Establish a Short-Term Programto Enable Sales of Self-Generation for Export from BritishColumbia in Order G-38-01
As Canada explained in its Counter-Memorial,169 the 2000 US energy shortage84.
increased exponentially the market price of electricity. Howe Sound looked to capitalize
on these higher energy prices by selling its self-generation into the market, and contacted
BC Hydro to indicate its intentions.170 Howe Sound posited that it was entitled to sell its
self-generated electricity to the U.S. market.171
BC Hydro, however, had serious concerns with Howe Sounds proposals, which it85.
relayed to Howe Sound in a letter on February 11, 2001:
BC Hydro … and most likely the government as its shareholder, will have serious concerns about any potential proposal that will see customer self-generated power sold into market, and with BC Hydro then being required to supply make-up power under Schedule 1821. This will be financially detrimental to BC Hydro and its other ratepayers, both in the short and the long term.172
It also indicated that:86.
169 Canada’s Counter Memorial, ¶¶ 112-113. 170 Chronology of Events for Howe Sound Idle Generation, R-78. 171 Chronology of Events for Howe Sound Idle Generation, R-78.
172 Letter from Craig Folkestad to Jerry Peet, Re: Howe Sound Pulp and Paper (HSPP) Power Export Opportunities, 12 February 2001, p. 1, R-79.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
43
If the situation were one in which incremental power would be made available for sale in the market, ie. power which is not now being produced but the generation of which would be made attractive if it could be sold at market prices, I expect that the situation (and BC Hydro’s view of it) would likely be different. Any incremental power supply in the province, regardless of where it is being sold (in the short term at least) would likely be viewed as positive.173
In light of Howe Sound’s request, BC Hydro sought guidance from the BCUC87.
and requested, on February 23, 2001, that it initiate a proceeding concerning this issue.
BC Hydro explained that:
BC Hydro has been made aware that some … customers are interested in directing their self-generated output to market (BC Hydro’s industrial tariff is $34 per MWh, while market prices are roughly $300 per MWh for a flat block looking ahead to the end of 2003). These customers have also indicated an expectation that any incremental energy required by the plant (i.e., load) would be served by taking additional service under standard tariffs from BC Hydro.
[…]
Were BC Hydro required to replace this 300 MW with additional RS 1821 supply, the cost is conservatively estimated to be in the region of $400 million per year through 2003. This would translate to a general rate increase for all BC Hydro customers of roughly 18 percent.174
BC Hydro requested that the BCUC initiate a Commission led workshop to “bring88.
all interested parties into the process” including groups such as customers without self-
generation who faced material exposure on this issue so that the BCUC could achieve the
“fairest possible resolution to the matter.”175
173 Letter from Craig Folkestad to Jerry Peet, Re: Howe Sound Pulp and Paper (HSPP) Power Export Opportunities, 12 February 2001, p. 1, R-79. 174 Letter from BC Hydro to the British Columbia Utilities Commission, Re: British Columbia Hydro and Power Authority (“BC Hydro”) Obligation to Serve Rate Schedule 1821 (“RS 1821”) Customers with Self-Generating Capability, 23 February, 2001, pp. 1-2, R-81. 175 Letter from BC Hydro to the British Columbia Utilities Commission, Re: British Columbia Hydro and
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
44
The BCUC granted this request and on March 19, 2001, 46 participants, including89.
representatives of the B.C. Government, BC Hydro and a number of pulp and paper
producers, attended the workshop.176 The meeting notes indicated that:
B.C. Hydro indicated that it was looking for ways to bring idle generation on line without increasing the embedded cost load of the self-generating customers. B.C. Hydro did not want to deal with situations that simply resulted in transfers to self-generating customers from other customers.177
Ms. Mullen, Director of the Electricity Development Branch, of the Ministry of
Employment and Investment—which was responsible for the energy portfolio at that
time—explained that: “… the provincial government is primarily concerned that other
ratepayers not being harmed as a result of the activities of Rate Schedule 1821 self-
generating customers.”178
The workshop participants were subsequently provided with an opportunity to90.
comment on the workshop discussion and emphasized that it was in the “interest of all
parties, and the public in general, that idle generation not remain idle in light of the
current shortage of electric power on the west coast of Canada and the United States.”179
On April 5, 2001, the BCUC issued Order G-38-01 which indicated that:91.
[The BCUC] must act to meet the complementary objectives of creating conditions which allow B.C. Hydro to safeguard its own supply to British
Power Authority (“BC Hydro”) Obligation to Serve Rate Schedule 1821 (“RS 1821”) Customers with Self-Generating Capability, 23 February, 2001, p. 3, R-81. 176 KPMG does not appear to have participated as the trustee in bankruptcy for Celgar. 177 Meeting Notes, Workshop, B.C. Utilities Commission Hearing Room, British Columbia Hydro and Power Authority Obligation to Serve Rate Schedule 1821 – Transmission Service Customers with Self-Generation Capability, March 19, 2001, p. 1, R-83. 178 Meeting Notes, Workshop, B.C. Utilities Commission Hearing Room, British Columbia Hydro and Power Authority Obligation to Serve Rate Schedule 1821 – Transmission Service Customers with Self-Generation Capability, March 19, 2001, p. 1, R-83. 179 See e.g., Letter from Brian Wallace on behalf of Howe Sound Pulp and Paper to Robert Pellatt, Commission Secretary, Re: Response to Issues Arising During March 19, 2001, Workshop, March 26, 2001, p. 1, bates 144037-144038, R-545.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
45
Columbians at lowest cost, assisting British Columbia industries with idle self-generation capability to capitalize on current market opportunities, and helping to mitigate the potential energy shortages in the Pacific Northwest and California.180
The BCUC issued Order G-38-01 in short order to permit B.C. self-generators to92.
take advantage of the market opportunity provided by the energy crisis and help mitigate
the energy shortages it caused.
The BCUC provided guidance concerning the establishment of a baseline for self-93.
generators that would prevent the occurrence of harmful arbitrage:
The Commission directs BC Hydro to allow Rate Schedule 1821 customers with idle self-generation capability to sell excess self-generated electricity, provided that the self-generating customers do not arbitrage between embedded cost utility service and market prices. This means that B.C. Hydro is not required to supply any increased embedded cost of service to a RS 1821 customer selling its self-generation output to market. The Commission recognizes that considerable debate may ensue over whether a self-generator has met this principle, but the Commission expects B.C. Hydro to make every effort to agree on a customer baseline, based either on the historical energy consumption of the customer or the historical output of the generator.181
The Staff Report appended to the Order shows that none of the stakeholders that94.
participated in the workshop advocated that self-generators should be able to engage in
harmful arbitrage—a stark contrast with the Claimant’s position in this arbitration.
180 BCUC, Order Number G-38-01, in the Matter of British Columbia Hydro and Power Authority Obligation to Serve Rate Schedule 1821 Customers with Self-Generation Capability, 5 April 2001, p. 1, R-19. 181 BCUC, Order Number G-38-01, in the Matter of British Columbia Hydro and Power Authority Obligation to Serve Rate Schedule 1821 Customers with Self-Generation Capability, 5 April 2001, p 2, R-19. It also provided the following direction concerning the resolution of potential disputes “In an effort toassist both the self-generator and B.C. Hydro/Powerex, the Commission directs that either party may request the views of the Commission staff on any unresolved issues before negotiations are terminated. Commission staff are to advise the Commission if there are any significant issues which the Commission must address to assist it in meeting the objectives of this program. The Commission believes that it would not be timely to debate the issue of filing of contracts within the context of establishing this short-term program of purchases and sales.” [Emphasis Added]
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
46
BCUC Order G-38-01 required BC Hydro to establish a short-term program to95.
facilitate the export of electricity and provided guidance on the principles it should apply
in setting a baseline under this program. It indicated that the “baseline” could be based
on either consumption data or generation data. It did not use the term “generator
baseline” or GBL.
No other self-generator than Howe Sound applied under the program, but the96.
BCUC would subsequently consider a separate request to permit the Riverside sawmill to
export its self-generation in excess of a baseline in BCUC Order G-113-01.182
On March 2, 2002, BC Hydro filed a brief report with the BCUC concerning its97.
experience with the program established by BCUC Order G-38-01. However, as Howe
Sound was the only self-generator that that had taken advantage of the program it had
little to report. BC Hydro had no objection to extending the application of Order G-38-
01. Nor did any other stakeholder raise concerns. Accordingly, the BCUC issued order
G-17-02 which extended the application of this program.183
2. BC Hydro Attempts to Procure Electricity from Self-Generatorsand Develops the Concept of a GBL in the 2002 Customer BasedGeneration Call for Power
On November 22, 2002, the Ministry of Energy and Mines issued the 200298.
Energy Plan which directed BC Hydro to procure domestically-generated clean energy
from the private sector to help meet growing demand for electricity.184 BC Hydro had
concurrently organized the 2002 Customer Based Generation Call for Power to procure
new, competitively-priced electricity from its customers under long-term agreements,
182 See Canada’s Counter-Memorial, ¶¶ 123-127. 183 BCUC, Order G-17-02 in the Matter of British Columbia Hydro and Power Authority Obligation to Serve Rate Schedule 1821 Customers with Self-Generation Capability, 14 March 2002, p. 2, R-256. 184 The 2002 Energy Plan provided that “[t]he private sector [would] develop new electricity generation, with BC Hydro restricted to improvements at existing plants.” Energy For Our Future: A Plan for BC (“2002 Energy Plan”), 25 November 2002, Policy Action No. 13, at 30, R-21.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
47
including customers with existing self-generation capacity.185 It issued its Call for
Tenders on September 2, 2002.
Since, under this Call for Power, BC Hydro would procure electricity from its99.
self-generating customers, it was necessary to determine how to do so without allowing
the arbitrage of embedded cost power, which would run counter to the purpose of the call
and could harm other ratepayers. BC Hydro thus developed the concept of a “generator
baseline” (or “GBL”) based on the principles set out in BCUC Order G-38-01. The GBL
would establish the amount of electricity the self-generator normally produced; any
generation in excess of this amount would be considered incremental and therefore
eligible to be bid into the call.186 Without the GBL concept, BC Hydro would procure
“existing” rather than incremental electricity, which would not add to its resource base
and would in effect transfer wealth from ratepayers to the competing mills.
In order to set GBLs, BC Hydro requested information from the proponents with 100.
self-generation including “historical operating data” for a period of three years,187 and the
peak output for the self-generator over a period of the last 10 years. BC Hydro ultimately
received a limited number of bids for the call (none from NBSK pulp mills) and no self-
generator was awarded a contract.188 BC Hydro subsequently determined that the prices
185 Customer-Based Generation, 2002 Call for Tenders, September 6, 2002, (“2002 Customer-Based Generation CFT”), p. 1, R-109. 186 2002 Customer-Based Generation CFT, p. 12, R-109 (“As noted under Evaluation of Tenders and Prices/Award of EPAs, the proposed electricity supply must be new or incremental. Where the bidder’s project involves an increase in the capacity of, or energy from, existing facilities resulting from capital modifications, it is necessary to determine the generator’s historic generation capability. The historic generation capability is referred to in the Standard EPA as the Generator Baseline or “GBL”. For purposes of determining electricity eligible for sale to BC Hydro, the GBL will be deducted from the metered electricity.”) 187 2002 Customer-Based Generation CFT, p. 40, R-109. 188 Jim Scouras Statement I, ¶ 31.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
48
and terms it offered were not sufficient to incentivize pulp mills to undertake projects to
produce incremental electricity.189
No NBSK pulp mills or other self-generators raised the issue of the sale of their 101.
self-generation until after the B.C. Government announced its 2007 Energy Plan.
3. BC Hydro Procures Electricity from Self-Generators in theBioenergy Call for Power Phase I and the Integrated Power Offer
The 2007 Energy Plana)
On February 27, 2007, the Ministry of Energy issued its 2007 Energy Plan,190 102.
which mandated BC Hydro to achieve electricity self-sufficiency by 2016191 and acquire
an additional 3,000 GWh of “insurance” electricity by 2026.192 The 2007 Energy Plan
directed BC Hydro to issue a Request for Expressions of Interest (“RFEOI”), followed by
a Call for Proposals, for electricity from sawmill residues, logging debris and beetle-
killed timber.193
The 2007 Energy Plan and the RFEOI both rekindled the interest of B.C. pulp 103.
mills in sales of self-generated electricity. The Bioenergy Call would effectively create a
B.C. market for “green” biomass energy where none had previously existed.194 The B.C.
Pulp and Paper Task Force, a lobby group of the pulp and paper industry, viewed this as a
significant financial opportunity.195 Mr. Gandossi, the Claimant’s CFO, and Mr. Allan
were members of the Task Force.
189 Jim Scouras Statement I, ¶ 32. 190 British Columbia Ministry of Energy, Mines and Petroleum Resources, “The BC Energy Plan: A Vision for Clean Energy Leadership” (“2007 Energy Plan”), R-23. 191 2007 Energy Plan p. 39, R-23; Les MacLaren Statement II, ¶ 4; Jim Scouras Statement I, ¶ 34. 192 Les MacLaren Statement II, ¶ 4. 193 Canada’s Counter-Memorial, ¶¶ 139-140; 2007 Energy Plan p. 17, R-23; Les MacLaren Statement II, ¶ 6; Jim Scouras Statement I, ¶ 36. 194 Les MacLaren Statement II, ¶ 7. 195 Les MacLaren Statement II, ¶¶ 7, and 22.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
49
On November 22, 2007, the Task Force provided the B.C. Government with a 104.
position paper concerning Electricity Generation and Conservation. The Task Force took
the position that BC Hydro should procure all of the electricity from NBSK pulp mills,
regardless of whether that electricity was existing or incremental. In particular, it
requested that BC Hydro purchase all existing self-generation at a price equivalent to BC
Hydro’s Tier 2 rate for industrial customers—a more expensive rate which is intended to
encourage industrial customers to conserve energy.196 The Task Force also suggested
that the self-generation of incremental electricity should automatically receive the highest
price paid by BC Hydro for green energy produced by Independent Power Producers.197
From the Province’s perspective, the Task Force proposals would have required 105.
the procurement of all of the self-generation from these industrial customers without
regard as to whether BC Hydro was actually acquiring new electricity for the system.198
The proposal was thus viewed as a request for a subsidy from the government, which
would not contribute to the load-resource gap that BC Hydro had to fill and which also
had the potential to harm other ratepayers.199 Moreover, these proposals would have also
undermined the competitiveness of the Bioenergy Call for Power by pre-determining the
prices paid to pulp mills for their electricity.
On January 31, 2008, British Columbia released its 2008 Bioenergy Strategy 106.
which directed BC Hydro to proceed with a two-part Bioenergy Call for Power.200 The
Ministry of Energy also reiterated a week later to the Claimant and other representatives
196 Pulp and Paper Task Force, “Position Paper on Electricity Conservation & Generation”, 22 November 2007, bates 063271-063285 at 063274, R-28. 197 Pulp and Paper Task Force, “Position Paper on Electricity Conservation & Generation”, 22 November 2007, bates 063271-063285 at 063275, R-28. 198 Les MacLaren Statement II, ¶ 7. 199 Les MacLaren Statement II, ¶ 8. 200 British Columbia Ministry of Energy, Mines and Petroleum Resources, BC Bioenergy Strategy Growing Our Natural Energy Advantage, 2008, p. 8, R-24.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
50
of the pulp and paper industry that BC Hydro would not purchase self-generation that had
historically been used to meet the self-generator’s own load.201
Bioenergy Call for Powerb)
On February 6, 2008, BC Hydro issued its Request for Proposals (“RFP”) for the 107.
Bioenergy Call for Power202 with the intention of procuring 1,000 GWh per year of
electricity. Its terms and conditions were based off of the feedback BC Hydro had
received during the RFEOI process.
BC Hydro’s RFP indicated in section 14 that eligible customer projects included: 108.
[n]ew self-generation, or incremental self-generation, in any event excess of the Customer’s GBL at a Customer’s facility to serve the Customer’s industrial load at the facility (i.e., load displacement) and/or effect net energy export to the System (i.e. Customer Projects), but excluding generation projects, where the current output [was] under contract through a load displacement or demand side management agreement with BC Hydro.203
The RFP was also consistent with the policy position the Ministry of Energy 109.
explained to the Claimant and other representatives of the pulp and paper industry in
concurrent meetings concerning self-generation.204
At the same time, BC Hydro held a series of internal meetings concerning the 110.
GBL concept for the Call for Power which involved members of Key Accounts
Management, Powersmart, and the Transmission Service Rates group.205 BC Hydro
officials recognized that BCUC Order G-38-01 provided important context to the
201 Les MacLaren Statement I, ¶ 94. 202 BC Hydro, Bioenergy Call for Power – Phase I, Request for Proposals, 6 February 2008, R-25. 203 BC Hydro, Bioenergy Call for Power – Phase I, Request for Proposals, 6 February 2008, s. 14, R-25. 204 Les MacLaren Statement I, ¶¶ 92-94. 205 See generally, Lester Dyck Statement I, ¶ 55.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
51
determination of a GBL.206 It also considered its work on the GBL concept from the 2002
Customer Based Generation Call,207 as well as from its draft Standing Offer Program
Rules which, contrary to the Claimant’s assertions,208 have always reflected the same
GBL concept.209 Mr. Keir, the representative of the Transmission Service Rate group,
provided his perspective of some of the important principles that were being developed in
these meetings, including:
● The GBL should reflect a 365 day (annual period)
● The GBL start point is the [Customer Baseline or “CBL”] establishment year
● For most [BC Hydro] customers, calendar 2005 is the CBL establishmentyear
[…]
● The GBL start point is actual calendar 2005 gross metered TG output (365days)
● The GBL may then need to be adjusted for unique customer circumstances(existing LD contracts, EPAs, market sales, etc.)210
206 Email from David Keir to Alex Adams, Lester Dyck re: RE: BioeEnergy Call | Use of GBL and its implication on CBL’s, dated February 12, 2008, R-171. (“BCUC Order G-38-01 provides some important context and background to the establishment of a GBL that I expect will be relevant as things proceed.”). The minutes of a meeting held on February 14, 2008 indicates that the group “Review[ed] the GBL concept in detail” including “Relevant precedents: 1.G38-01, 2. CBG [2002 Customer-Based Generation Call], 3. Other calls”. Email from David Keir, to Lester Dyck et al re: RE: Review detailed design of GBL concept for interaction with TSR for customer and Power Smart program implications | Meeting Minutes, dated February 15, 2008 026774 at 026776, R-172. 207 Email from Janet Stewart to Lester Dyck, GBLv.2.doc, 15 February 2008, enclosing Customer Based Generation 2002 Call for Tenders and Standing Offer for Energy, 18 January 2008, bates 063503 at 060534, R-546. 208 See Claimant’s Reply, fn 3, ¶ 168. 209 Email from Janet Stewart to Lester Dyck, GBLv.2.doc, 15 February 2008, enclosing Customer Based Generation 2002 Call for Tenders and Standing Offer for Energy, 18 January 2008, bates 063503 at 60538, R-546. Jim Scouras Statement II, ¶¶ 42-43; BC Hydro Standing Offer Program Rules, 11 April 2008, pp. 4-5, R-487. 210 Email from David Keir, to Lester Dyck et al re: RE: Review detailed design of GBL concept for interaction with TSR for customer and Power Smart program implications | Meeting Minutes, dated February 15, 2008 at 026774, R-172.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
52
For the Bioenergy Call for Power, BC Hydro determined that the GBL should 111.
reflect a 365 day period. It also decided that the logical starting point for a GBL
determination for BC Hydro industrial customers should be gross metered turbogenerator
output during the customer’s CBL establishment year,211 which for most industrial
customers was 2005.212 This approach, however, could not apply to the Claimant which
was located in FortisBC’s service area and did not have a CBL with BC Hydro.
BC Hydro was also aware that in determining GBLs the unique circumstances of 112.
each mill would have to be considered. This information was reflected in the Registration
Form that proponents were required to fill out prior to submitting a proposal into the call.
Schedule A of that Registration Form, entitled “Preliminary GBL data” provided the
details necessary for proponents to estimate their own GBL
BC Hydro held two information sessions to discuss the parameters of the 113.
Bioenergy Call for Power and to explain its GBL methodology for any proponent that
was interested in submitting a bid.213 BC Hydro also ran an hour-long question and
answer session on GBLs as part of the second information session for all interested
211 Canada explained in its Counter-Memorial that, in 2006, BC Hydro implemented a two-tiered rate schedule for its industrial customers as a mechanism to incentivize energy conservation. See Canada’s Counter-Memorial, ¶ 427. Pursuant to this rate schedule, two different rates apply to different proportions of the customers normal purchases (BC Hydro applies a low Tier 1 rate for the first 90% of the customer’s normal purchases, and a high Tier 2 rate for the remaining 10%.) In application of this rate schedule, BC Hydro determined the customer’s the normal energy consumption of an industrial customer for the purposes of energy billing using a concept of “customer baseline” (or “CBL”). 212 BC Hydro determines a unique customer baseline (CBL) for each of its industrial customers billed for energy under the RS 1823 Stepped Rate. The CBL represents the customer’s normal annual energy purchases over a 365 day period prior to the customer taking service on the RS 1823 Stepped Rate. RS 1823 came into effect on April 1, 2006 and the CBLs for most industrial customers were determined based on calendar 2005 energy purchase data. As a BC Hydro industrial customer’s annual energy purchases are equal to total mill load less self-generation for self-supply, a starting point for determining a GBL (i.e., normal self-generation for self-supply) was the 365 day period used to determine the customer’s CBL (i.e., normal energy purchases) which at that time was 2005 for most customers. 213 See generally, Lester Dyck Statement I, ¶¶ 57-59; BC Hydro’s Bioenergy Call, Kamloops, BC, February 20, 2008 Presentation, R-116; Bioenergy Call Phase I, Proponent Information Session, March 26, 2008 at 62, R-117.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
53
proponents.214 Representatives of the Claimant attended all of the information sessions
and the GBL question and answer forum.215
Mr. Dyck, the Key Accounts Manager responsible for the GBL determinations, 114.
explained during these presentations that only new or incremental self-generation would
be eligible for the Call for Power and not “existing” electricity.216 He also indicated that
proposals to sell self-generated electricity would require a GBL based on historical
generation data that reflected a 365-day annual period of operations.217 Mr. Dyck
explained that BC Hydro was aware that the operations of each pulp mill were unique
and it did not want to adopt an overly prescriptive approach to GBL determinations.218
He also emphasized the importance of proponents submitting reasonable and defensible
technical information in support of the GBL.219 BC Hydro also held several one-on-one
meetings with each proponent over the course of the afternoon on March 26.220
214 Phase I Bioenergy Call Proponent Workshop – Agenda, 26 March 2008, CAN529828, R-527. 215 Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008, R-173. The email summarizes the question and answer session following the March 26, 2008 presentation. The email indicates that the Claimant asked the first question in the GBL question and answer session. See Id., bates 064463, R-173 (“Question: If I am not a BCH customer, do I still need a GBL? Answer: Yes. If you are making electricity today, we need to define an appropriate starting point / reference above which incremental power generation can be measured and allocated to an EPA. Further if you are not a BCH customer, BCH needs to be made aware of any existing tariff requirements or restrictions that may impact the measurement or delivery of energy to an EPA”) 216 BC Hydro’s Bioenergy Call, Kamloops, BC, February 20, 2008 Presentation, p. 22, R-116. (“The purpose of the GBL is to define incremental output that can be considered for a prospective energy sale”). 217 BC Hydro’s Bioenergy Call, Kamloops, BC, February 20, 2008 Presentation, p. 22, R-116. (“The initial customers “estimated GBLs” should reflect a 365 day annual period.”) Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008, R-173. (“For BCH customers, the starting point is the CBL establishment year, which for most customers is calendar 2005”) 218 BC Hydro’s Bioenergy Call, Kamloops, BC, February 20, 2008 Presentation, p. 22, R-116. (“The GBL may have to be adjusted for unique customer circumstances (existing LD contracts, EPAs, market sales, 1880/ad hoc purchases etc)”) Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008, R-173. (“… BCH did not wish to impose an overly prescriptive approach to GBL development that may not have considered every unique circumstance.”)> 219 Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008, R-173. (“The critical requirement is to supply reasonable, defensible, technical information in support of the GBL. Each customer generator and mill operation is unique and has unique operational attributes. … The bottom line is that you know your operations best. Help us to understand the unique
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
54
BC Hydro placed the presentations it made at the information sessions on its 115.
website for the Bioenergy Call.221 BC Hydro officials then engaged in negotiations with
each of the proponents as a GBL was a prerequisite to the submission of a proposal in
context of the Bioenergy Call. The negotiations with Celgar are discussed in more detail
below.
While BC Hydro received 20 proposals from 13 different proponents on June 10, 116.
2008,222 it was ultimately able to award no more than four EPAs for a total of 579
GWh/year of electricity procurement—roughly half of the 1,000 GWh/year it had
intended to procure.223 The Claimant received the largest EPA in the Bioenergy Call
which entitled Celgar to sell 238 GWh/year of firm energy, as compared to 201
GWh/year for Domtar, and 70 GWh/year for Canfor (Prince George).
On February 17, 2009, BC Hydro submitted an application to the BCUC for 117.
approval of these EPAs pursuant to section 71 of the UCA and attached a report on the
Bioenergy Phase I Call explaining how the procurement of this electricity would assist
BC Hydro meet the needs of its customers. The BCUC reviewed all of these EPAs and
asked questions concerning BC Hydro’s GBL methodology.224 The BCUC subsequently
operational conditions that are [sic] imbedded within your annual GBL, such that we can collectively review and understand any specific elements that may be open to refinement.”) 220 Phase I Bioenergy Call Proponent Workshop – Agenda, 26 March 2008, CAN529828, R-527. 221 Lester Dyck Statement I, ¶ 59. See BC Hydro, Workshops & Presentations, online: <http://www.bchydro.com/energy-inbc/acquiring_power/closed_offerings/phase_1_rfp/proponent_sessions.html>. 222 Lester Dyck Statement I, ¶ 53. 223 The successful proponents were: Celgar (Castlegar), PG Interior Waste to Energy Ltd., Canfor Pulp Ltd. Partnership (Prince George) and Domtar Pulp and Paper Products Inc. (Kamloops). BC Hydro Report on Bioenergy Phase I - RFP, R-170. 224 Letter from Joanna Sofield, Chief Regulatory Officer to Ms. Erica Hamilton, Commission Secretary, Re: British Columbia Utilities Commission (BCUC), British Columbia Hydro and Power Authority (BC Hydro), Bioenergy Call Phase 1 Electricity Purchase Agreements, March 27, 2009, BC Hydro Responses to BCUC Information Requests 1.6.1.-1.6.5. at bates 151373-151379, R-547.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
55
approved these EPAs in Order E-8-09 as they were in the public interest with respect to
both the need for and price of the electricity.225
C. The Claimant’s Treatment in the Bioenergy Call for Power
On February 6, 2008, BC Hydro issued its RFP for the Bioenergy Call for Power 118.
Phase I.226 The Claimant submitted its Registration Form for the Bioenergy Call for
Power a month later for two projects – the “Arbitrage” project (under the euphemistic
pseudonym of the “Biomass Realization Project”) and the Green Energy Project.227 BC
Hydro subsequently determined that the Green Energy Project would provide new and
incremental electricity that was eligible for the Call for Power, but rejected the Arbitrage
Project which consisted of electricity that Celgar had used for self-supply.228
1. The Claimant’s False Assertions that BC Hydro Did Not Considerall of the Data and that Celgar Did Not Understand that the GBLwould be Set to Reflect an Annual Period
As explained above, BC Hydro set GBLs by determining the amount of annual 119.
self-generated energy normally used by a customer to self-supply under current
conditions without the prospect of an EPA or LDA.229 Mr. Merwin asserts in his most
recent witness statement that he did not understand what the Claimant has labelled as the
“current normal” standard.230 In particular, he complains that:
[T]he information that BC Hydro did provide concerning its GBL determination standards gave the impression that BC Hydro would
225 See BCUC, Order E-8-09, in the Matter of an Application by BC Hydro for Acceptance of Electricity Purchase Agreements – Bioenergy Call Phase I Request for Proposals, 31 July 2009, R-308. 226 Bioenergy Phase I – RFP, R-25. 227 Celgar, BC Hydro Bioenergy Call for Power (Phase I) – Registration Forms, 6 March 2008 (“Celgar Bioenergy Phase I Registration”), at bates MER00278896 (Celgar Green Energy Project), R-123. 228 Letter from BC Hydro RFP Administrator to Brian Merwin, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project, 2 May 2008, (“May 2, 2008 Letter Re: Celgar Biomass Realization Project”), R-126. 229 Canada’s Counter Memorial, ¶ 99; and Lester Dyck Statement I, ¶ 44. 230 Brian Merwin Statement II, ¶ 15.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
56
consider a number of years – what seemed like an average of three years of operational data – not simply one year of data or only ‘current’ data.”231
Mr. Merwin also claims that he was “particularly shocked and disturbed when Mr. Dyck
informed me that BC Hydro had only considered one year (2007, the year prior to our
BioEnergy Phase I registration) of operational data in assigning Celgar’s GBL.”232 These
claims are not convincing for several reasons.
First, BC Hydro provided the Claimant with information that clearly indicated 120.
that the GBL would represent an annual 365-day period. BC Hydro’s Registration Form
for the Bioenergy Call provided the following instructions to Celgar under the heading
“Preliminary GBL Data”:
2. Provide the information requested in “Section A – Estimated GBL” as follows:
[…]
(d) In the column titled “Annual Energy Output”, insert the annual energy output (in GWh/year) for each Generator for the Proponent’s customer base line (“CBL”) development year (which, for most Proponents will be the 2005 operating year).
(e) In the row titled “Estimated GBL”, insert the total of the Annual Energy Output column.233
This clearly indicated to Celgar that the “Estimated GBL” would reflect a one 121.
year period, which for most proponents would be the 2005 calendar year. BC Hydro
reiterated that the “estimated GBL” should reflect “a 365 day annual period” at its first
information session on February 20, 2008.234 Similarly, BC Hydro explained in the
context of a GBL question and answer period following the March 26, 2008 information
231 Brian Merwin Statement II, ¶ 15. 232 Brian Merwin Statement II, ¶ 16. 233 Celgar, BC Hydro Bioenergy Call for Power (Phase I) – Registration Forms, 6 March 2008, at bates MER00278899 (Celgar Green Energy Project), R-123. 234 BC Hydro’s Bioenergy Call; Kamloops, BC February 20, 2008, p. 22, R-116.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
57
session that the GBL “starting point is the CBL establishment year,” which was “calendar
2005.”235
Mr. Merwin and his counsel attended both of the information sessions on 122.
February 20 and March 26, 2008.236 The Claimant complains that there was only one
slide concerning GBLs in each of the presentations at these information sessions.237 Mr.
Dyck and Mr. Scouras have both indicated that the concept of a GBL was explained in
full during these presentations.238 Perhaps more tellingly, Mr. Merwin provides no
evidence concerning these presentations.
On May 2, 2008, BC Hydro wrote to the Claimant to inform it that its Green 123.
Energy Project would be eligible for the Bioenergy Call but that its Arbitrage Project
would not because it was for the sale of “existing” electricity that the Claimant was using
to self-supply.239 Mr. Merwin wrote in BC Hydro a few days later to request that it
reconsider its decision to reject the Arbitrage Project, and to submit additional data
concerning its GBL.240
Mr. Dyck explains in his second witness statement that this letter shows that Mr. 124.
Merwin had a clear understanding that BC Hydro would set its GBL to reflect a one year
235 Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008, R-173. Lester Dyck Statement I, ¶¶ 57-58; Jim Scouras Statement I, ¶ 42. BC Hydro’s Bioenergy Call; Kamloops, BC February 20, 2008, R-116. 236 BC Hydro, February 23, 2008 Bioenergy Call for Power Phase I Session Registrations, R-118; Email from Brian Merwin to BC Hydro RFP Administrator RE: Information Session, dated March 25, 2008, R-119; Email from Rod Talaifar (Sangra Moller, LLP) to BC Hydro RFP Administrator RE: May 28, 2008 Proponent Workshop (the “Workshohp” [sic]), dated May 15, 2008, R-120. 237 Claimant’s Reply, ¶¶ 255-258. 238 Lester Dyck Statement I, ¶¶ 57-58; Jim Scouras Statement I, ¶ 42; Jim Scouras Statement II, ¶ 6. 239 Letter from BC Hydro RFP Administrator to Brian Merwin, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project, 2 May 2008, (“May 2, 2008 Letter Re: Celgar Biomass Realization Project”), R-126. 240 Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project and Celgar Green Energy Project, dated May 7, 2008 at 019775, R-127.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
58
period.241 In particular, Mr. Merwin proposed a GBL of 33 MW based on Celgar’s
generation data from 2006.242 Mr. Merwin’s strategy at this time was to select 33 MW
based on this period because this would result in a GBL “as low as credible”.243 Mr.
Merwin claims now that it was his impression that BC Hydro would use a multi-year
average, but did not once propose a baseline to BC Hydro using such a calculation.
Mr. Merwin also alleges that he was “shocked and disturbed” because only one 125.
year of operational data was considered in setting the GBL for Celgar. This is quite
simply false. Mr. Dyck explains in his second witness statement that BC Hydro
considered all of the data that it received from Celgar for the period from 2002-2007. He
indicates that he decided to disregard the data from 2002-2004 which reflected a period
when the pulp mill was in bankruptcy.244 He explains that this data would not reflect the
Claimant’s operational decisions or the equipment changes that it subsequently made to
the pulp mill.245 Mr. Dyck also explains that he examined data from 2005 and 2006 but
did not believe that these years reflected normal operations for the pulp mill in 2008 due
to the extensive changes that were made during Project Blue Goose.246
Finally, Mr. Merwin explained to Mr. Dyck that Celgar’s first full operating year 126.
after the operational changes associated with Project Blue Goose was 2007.247 On the
241 Lester Dyck Statement II, ¶¶ 12-14. 242 Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project and Celgar Green Energy Project, May 7, 2008, pp. 019772 and 019775, R-127. 243 Email from J. MacLaren to B. Merwin, Re: Phase I Request for Proposals: Notice to Customers of GBL, May 4, 2008, R-534. 244 Lester Dyck Statement II, ¶ 16. 245 Lester Dyck Statement II, ¶ 16. 246 Lester Dyck Statement II, ¶ 17. 247 Lester Dyck Statement II, ¶ 17. Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project and Celgar Green Energy Project, May 7, 2008, bates pp. 019772 and 019775, R-127. (“It should be noted that $30 million [sic] dollars worth of capital upgrades we only [sic] operational for part of 2006 but all of 2007 … 2007 reflects the full investments that Celgar made into generating incremental biomass steam output,”)
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
59
basis of these representations, Mr. Dyck subsequently set the GBL using operational data
from 2007. Mr. Merwin had represented to Mr. Dyck many times that the mill was
electrically self-sufficient under normal operating conditions, and that the mill sometimes
generated even more electricity than it needed.248 Mr. Dyck set Celgar’s GBL at the level
of the pulp mill’s load in 2007 based on these representations.
As shown below and discussed in greater detail in Pöyry’s second expert report, 127.
Mr. Merwin accurately represented the mill’s normal operations in 2007. The close
correlation between Celgar’s generation output (the blue line below) and its hourly mill
load (the green line below) supports BC Hydro’s decision to set Celgar’s GBL at the
level of its 2007 load:249
Figure 1: Celgar’s 2007 TG2 Hourly Output vs. Mill Load and BCH GBL Assessed250
248 Lester Dyck Statement II, ¶¶ 19-29. 249 Pöyry Expert Report II, ¶¶ 51-64. 250 See Pöyry Expert Report II, Figure 6.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
60
2. Mr. Merwin’s Baseless Claim that He Could Not Describe NormalOperations at the Celgar Pulp Mill
Mr. Merwin does not deny that he told Mr. Dyck that “2007 represented normal 128.
operations for Celgar going forward.”251 However, he complains that he did not
understand what Mr. Dyck meant when he asked him to describe “normal operations” at
the Celgar pulp mill.252 He claims that if he had understood the meaning of “normal” he
would have informed BC Hydro that:
[Celgar] did not have sufficient information on whether [its] 2007 operations were normal. [Celgar] had just installed new equipment and made process improvements as a result of Project Blue Goose, and [it] did not yet have sufficient experience to determine the reliability of the new plant
251 Brian Merwin Statement II, ¶ 18. 252 Lester Dyck Statement I, ¶¶ 81-82.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
61
configuration, nor had [it] had sufficient time to evaluate whether problems might arise.253
This contention strains credulity. As Director of Strategic Initiatives, Mr. Merwin 129.
had to have had an understanding of what normal operations were at the Celgar pulp mill.
Mr. Dyck had numerous conversations with Mr. Merwin to discuss Celgar’s “normal
operations”.254 Mr. Merwin had spent a considerable amount of time becoming familiar
with the energy production at Celgar. He was also directly supported by Mr. Jim
McLaren, who would have had a thorough technical understanding of energy production
at the pulp mill. Perhaps more importantly, Mr. Merwin’s contention that Project Blue
Goose was not fully reliable actually means that the GBL for 2007 was lower than it
should have otherwise been in these circumstances.
Mr. Merwin’s assertions are further undermined by his own submissions to BC 130.
Hydro concerning Celgar’s GBL which indicate that:
Historically, under normal operating conditions Celgar’s load was 38 MW to 39 MW. In 2007, Celgar’s load under normal operating conditions was 43 MW, depending on whether Celgar’s chipping plant is running this number could go as high as 45 MW. During less than ideal operating conditions the mill load would likely be a slightly lower number. As Celgar moves to a higher reliability, meaning running at target rates, there will be a higher frequency when Celgar’s load is equal or greater than 43 MW.255
This letter indicates quite clearly that Mr. Merwin was well aware of what 131.
constituted normal operating conditions at Celgar in 2007. That 2007 reflected normal
operations at the mill is also confirmed by subsequent years of generation at the mill,
which demonstrate even higher levels of generation than 2007:
253 Brian Merwin Statement II, ¶ 19. 254 Lester Dyck Statement II, ¶ 19. 255 Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) - Biomass Realization Project and Celgar Green Energy Project, dated May 7, 2008, p. 4, R-127. [Emphasis Added]
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
62
Table 1: Summary of Total Generation Discrepancy256
3. Celgar’s Negotiations with BC Hydro Concerning the ExclusivityClause and the Side Letter Agreement
Every EPA that BC Hydro has signed with self-generators contains an exclusivity 132.
clause that restricts the sale of below-GBL electricity to third parties.257 The purpose of
the clause is to provide certainty to BC Hydro that it will have the security of supply that
it has contracted for with project proponents. As Mr. Scouras explains:
Without an exclusivity provision a proponent could elect to sell its electricity to a third party and not BC Hydro, even if the proponent would incur liquidated damages under the EPA. Such a scenario would result in BC Hydro not receiving the full benefit of the electricity under the EPA and would, thus, significantly undermine the firmness of the security of supply that BC Hydro is seeking to achieve with an EPA. The exclusivity provision provides greater certainty that BC Hydro will in fact receive the benefit of the electricity under the EPA and protects BC Hydro’s procurement of electricity.258
256 In reviewing Celgar’s monthly and daily operational statistics, Pöyry found that there were certain discrepancies in the data reported there, and the figures reported in the Claimant’s Reply Annex A. See Pöyry Expert Report II, ¶¶ 28-33. 257 Jim Scouras Statement II, ¶ 17, 20. 258 Jim Scouras Statement II, ¶ 9.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
63
During the EPA negotiations with the Claimant, Mr. Merwin requested an 133.
amendment to the exclusivity provision that would allow the Claimant to sell below-GBL
electricity to third parties. BC Hydro had a number of concerns with Mr. Merwin’s the
proposed amendment, including: (1) it would provide the Claimant with a right not being
offered to any other proponent; (2) it could erode the procurement of incremental
electricity from the Claimant under the EPA; (3) it could be construed as an implicit
acceptance of harmful arbitrage; and (4) it could prejudice BC Hydro’s position in front
of the BCUC that FortisBC should not be allowed to purchase power from BC Hydro
under the 1993 Power Purchase Agreement (“1993 PPA”) for the purpose of allowing its
customers to arbitrage that power.259
BC Hydro nonetheless wished to remain responsive to the interests of the 134.
Claimant, and the parties thus negotiated and signed a “Side Letter Agreement” that
would operate in conjunction with the exclusivity provision in the EPA. The Side Letter
Agreement establishes two essential principles. First, it states the exclusivity provision in
the EPA is “without prejudice” to the right of Celgar
(i)…to take a position in any other pending or future regulatory proceeding before the BCUC, the effect of which if such position were to prevail in that proceeding, would be that (A) FortisBC may supply electricity to [Celgar] to serve the [Celgar’s] Mill Load, in circumstances where [Celgar] sells self-generated electricity diverted from serving Mill Load, (B) [Celgar] may sell such self-generated electricity in those circumstances, and (C) section 7.4(b) of the EPA in its present form should have no force or effect.260
Second, the Side Letter Agreement states that 135.
If the BCUC makes an order in any pending or future regulatory proceeding upholding the position described in paragraph (1)(i) above, then subject to the outcome of any reconsideration or appeal thereof, the Parties shall execute
259 Jim Scouras Statement II, ¶¶ 18-23. 260 Side Letter Agreement between BC Hydro and Zellstoff Celgar Limited Partnership, RE: Electricity Purchase Agreement, with Effective Date of January 27, 2009 (“EPA”), dated January 27, 2009, bates 026183-026184, ¶ 1, R-138. [Emphasis added]
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
64
and deliver an agreement amending the EPA to substitute the alternate section 7.4(b) for that section in the present EPA, which amendment shall be filed with the BCUC under section 71 of the UCA and shall be subject to acceptance by the BCUC.261
In short, the Side Letter Agreement allows for an amendment to the exclusivity 136.
clause in the EPA should the BCUC agree that the Claimant should be allowed to sell its
below-GBL electricity third parties. Mr. Scouras explains that
[N]o other pulp mill to date in any BC Hydro power procurement process (including the Bioenergy Call for Power Phase I) has been given the same preferential treatment. To the contrary, every mill that has signed an EPA with BC Hydro has been subject to the same exclusivity provision found in section 7.4 of the 2009 EPA with Celgar. No other EPA proponent has been offered a similar Side Letter Agreement with BC Hydro.262
In its Reply, the Claimant asserts that the “exclusivity provisions in Section 7.4(b) 137.
of Celgar’s 2009 EPA with BC Hydro directly prevent Celgar from selling any power it
generates below its 2007 load, again, not to BC Hydro but to any third party.”263 The
Claimant fails however to account for the Side Letter Agreement. In fact, the Side Letter
Agreement is mentioned only once in a footnote in the Claimant’s Reply.264 In light of
the Agreement, the Claimant’s assertion is factually untrue.
More importantly, the BCUC has agreed that Celgar should be allowed to “sell all 138.
or a portion of its generation below the BC Hydro GBL into the market and supply its
mill from FortisBC resources,”265 a fact that will be further discussed below. In response
261 Side Letter Agreement between BC Hydro and Zellstoff Celgar Limited Partnership, RE: Electricity Purchase Agreement, with Effective Date of January 27, 2009 (“EPA”), dated January 27, 2009, bates 026183-026184, R-138, ¶ 2. [Emphasis added] 262 Jim Scouras Statement II, ¶ 33. 263 Claimant’s Reply, ¶ 34. 264 See Claimant’s Reply, fn. 699, where they acknowledge that “resolution of Celgar’s below-GBL sales” were left to the BCUC. 265 BCUC, Decision and Order G-188-11, Zellstoff Celgar Limited Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, November 14, 2011, p 49, R-275.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
65
to this decision, Mr. Merwin wrote to BC Hydro on November 29, 2011, requesting “that
BC Hydro enter into an amendment agreement effecting the changes to the EPA
contemplated by the Letter Agreement.”266 However, while the parties were arranging to
amend the exclusivity provision in the EPA, the Claimant initiated its NAFTA claim and
has since not followed-up with its request.
D. The Claimant’s Treatment at the BCUC
1. BCUC Order G-48-09
As Canada explained in its Counter-Memorial,267 the proceeding leading up to 139.
BCUC Order G-48-09 was initiated by BC Hydro in response to a set of two agreements
between FortisBC and the City of Nelson. The BCUC determined that FortisBC could not
purchase embedded cost power from BC Hydro under the 1993 Power Purchase
Agreement (“1993 PPA”) for the purpose of allowing its customers (including the City of
Nelson and Celgar) to arbitrage that power. The Order has no effect on FortisBC’s ability
to draw on its other resources to supply embedded cost power to its customers for the
purpose of arbitraging that power.
The Claimant states that “BCUC Order G-48-09 imposes a net-of-load access 140.
standard on Celgar, by effectively preventing FortisBC from selling Celgar any
embedded cost electricity from Fortis’ pre-existing resource stack while Celgar is selling
electricity.”268 The Claimant’s characterization is untrue. In the proceedings leading up to
BCUC Order G-188-11, the Claimant argued that
Order G-48-09 provides that FortisBC will not sell electricity ‘purchased under’ the PPA to Celgar, while Celgar sells self-generation that is not in
266 Letter from Brian Merwin to BC Hydro, Re: Electricity Purchase Agreement (the “EPA”) between Zellstoff Celgar Limited Partnership (“Celgar”) and British Columbia Hydro and Power Authority (“BC Hydro”), December 6, 2011, p. 2, R-485, CAN003246. 267 Canada’s Counter-Memorial, ¶¶ 251-255. 268 Claimant’s Reply Memorial, ¶ 33.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
66
excess of its load. It does not prohibit FortisBC from selling other energy to Celgar, while Celgar sells such self-generation.269
And the BCUC agreed:
Order G-48-09 protects the benefits of BC Hydro PPA Power for all customers of FortisBC. Order G-48-09 does not consider power from FortisBC’s own generation or other non-BC Hydro PPA Power components of its resource stack.270
Thus, the Claimant cannot now possibly sustain an argument that Order G-48-09 141.
prevented FortisBC from selling the Claimant embedded cost electricity from its own
resource stack, even “while Celgar is selling electricity.” That is not what BCUC Order
G-48-09 says and the Claimant was in fact provided this right in subsequent regulatory
proceedings, as will be seen below.
2. Subsequent Proceedings Relating to a FortisBC-Celgar GBL
In proceedings following BCUC Order G-48-09, the BCUC encouraged the 142.
Claimant to negotiate a GBL with FortisBC that could be incorporated into a general
service agreement.271 As Mr. Merwin testifies:
[After Order G-48-09] Celgar consequently requested that FortisBC set a GBL for Celgar that was lower than the GBL BC Hydro had set. We thought
269 Letter from K.C. Moller, Re: Zellstoff Celgar Limited Partnership (“Celgar”) Complaint Regarding the Failure of FortisBC Inc. (“FortisBC”) and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges (the “Complaint”) – Project No. 3698636, dated September 1, 2011, p. 1, R-483. [Emphasis added.] 270 BCUC Order G-188-11 and Decision , in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 14 November 2011 p. 37, R-275. [Emphasis added.] 271 BCUC Order G-188-11 and Decision , in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 14 November 2011, p. 28, R-275. This is consistent with the BCUC’s determination in BCUC Order G-156-10 in which the BCUC declined to set a GBL but noted that the parties were free to arrive at one on their own and submit it to the BCUC for approval. BCUC, Order G-156-10 and Decision, in the Matter of an Application by FortisBC for Approval of a 2009 Rate Design and Cost of Service Analysis, 19 October 2010, p. 115, R-228.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
67
that a FortisBC assigned GBL would serve two purposes: (1) liberate Celgar from the restrictive net-of-load standard; and (2) should the BCUC approve a FortisBC assigned GBL, such BCUC action could be used by Celgar to activate the terms of the side letter to its EPA with BC Hydro, to override the EPA’s restrictions on its below-load sales to third parties.272
FortisBC and the Claimant were not, however, able to reach an agreement on a 143.
GBL. As Mr. Swanson explains:
[T]he BCUC has repeatedly encouraged the Claimant to negotiate a GBL with FortisBC. While FortisBC made reasonable attempts to negotiate a FortisBC GBL, the Claimant continued to take unreasonable positions alleging that it should have a GBL as low as 1.5 MW.273
In light of its failure to reach an agreement with FortisBC, the Claimant filed a 144.
complaint against FortisBC at the BCUC. It alleged that “FortisBC will not voluntarily
negotiate an agreement with Celgar that results in a workable FortisBC GBL without
appropriate direction from the [BCUC]”.274 Contrary to the position taken in this
arbitration, the Claimant stated that “[e]xtensive uncontested evidence has been placed
before the [BCUC] relating to GBLs and methods utilized for establishing GBLs in the
BC Hydro service area that should be sufficient to circumscribe a process for
establishing…a FortisBC GBL.”275 The Claimant thus requested the BCUC to apply BC
Hydro’s GBL methodology,276 recognizing that “it provides an effective means to prevent
272 Brian Merwin Statement I, ¶ 120. 273 Dennis Swanson Statement II, ¶ 37. 274 Celgar, Final Submission in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 15 August, 2011, p. 21, R-376. 275 Celgar, Final Submission in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 15 August, 2011, p. 20, R-376. 276 Sangra Moller LLP on behalf of Zellstoff Celgar, Letter to the BCUC in the Matter of a Complaint Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, March 25, 2011, p. 5, R-264.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
68
arbitrage,”277 “is not based on a set formula,”278 and should “be a negotiated amount
giving consideration to the unique circumstances of the self-generating customer.”279
FortisBC did not object to the determination of a GBL for the Claimant,280 but 145.
argued that a GBL should not be set in a way that causes harm to other ratepayers.281
FortisBC agreed that a GBL should be determined through a process similar to that used
by BC Hydro,282 and proposed a 40 MW GBL.283
However, rather than impose a GBL on the two disputing parties, the BCUC in 146.
Order G-188-11 made an altogether different determination, finding in favor of the
Claimant that it should, as a matter of fact, be allowed to receive service from FortisBC
to enable it to sell its self-generation to third parties:
[I]t is evident that Celgar is free to sell all or a portion of its generation below the BC Hydro GBL into the market and supply its mill from FortisBC resources, not including BC Hydro PPA Power. Under the rates that the
277 Sangra Moller LLP on behalf of Zellstoff Celgar, Letter to the BCUC in the Matter of a Complaint Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, March 25, 2011, at Appendix B-5, R-264. 278 Sangra Moller LLP on behalf of Zellstoff Celgar, Letter to the BCUC in the Matter of a Complaint Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, March 25, 2011, p. 2, R-264. 279 Sangra Moller LLP on behalf of Zellstoff Celgar, Letter to the BCUC in the Matter of a Complaint Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, March 25, 2011, at Appendix B-5, R-264. 280 FortisBC, Final Submission, in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 22 August 2011, p. 4, R-377. 281 FortisBC, Final Submission, in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 22 August 2011, p. 26 R-377. 282 FortisBC, Final Submission, in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 22 August 2011, p. 33, R-377. 283 FortisBC, Final Submission, in the Matter of a Complaint by Zellstoff Celgar Limited Partnership Regarding the Failure of FortisBC and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, 22 August 2011, p. 34, R-377.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
69
[BCUC] has directed FortisBC to implement, a FortisBC GBL should be not required.284
The BCUC thus agreed that the Claimant should have access to FortisBC power 147.
while selling its generation below the BC Hydro GBL, and directed FortisBC to establish
a “rate” for that power “based on RS 31 but excluding BC Hydro PPA Power from its
resource stack” and without setting any limits on the amount of access to that power.
Mr. Merwin proclaimed the BCUC’s decision to be “a major victory.” In a 148.
memorandum to the Mercer International Board of Directors, he confirmed that “Celgar
is able to buy all of its power requirements from FortisBC and free to the [sic] sell the
output of its generation to third parties.”285
In compliance with the BCUC’s request, FortisBC filed “Guidelines for 149.
Establishing Entitlement to Non-PPA Embedded Cost Power” (“NECP”) with the BCUC,
in which it defined NECP as the “embedded cost of power excluding power purchased by
FortisBC from the BC Hydro PPA.”286 (Canada will discuss the details of the NECP rate
in the next section.) FortisBC also affirmed the principle in Order G-188-11:
284 BCUC, Decision and Order G-188-11, Zellstoff Celgar Limited Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, November 14, 2011, p. 49, R-275 “The mere status of being a customer who self-generates should not preclude FortisBC from its obligation to serve that customer. Nor does it automatically exempt such customers from accessing some amount of non-PPA embedded cost power. It would be fair that Celgar receive fair treatment within the FortisBC service area vis-à-vis other industrial customers. Yet, self-generators that sell into power markets do have the potential to negatively impact other FortisBC customers by necessitating acquisitions by the utility of power from other sources in order to supply the power the self-generator elects to purchase from the utility while simultaneously selling into the markets. Therefore, the [BCUC] finds Celgar is entitled to some amount of FortisBC’s non-PPA embedded cost power when selling power. But it is unclear what that level should be. Therefore, the [BCUC] directs FortisBC to consult with all classes of its customers to determine guidelines for the level of non-PPA embedded cost power to which eligible self-generation customers should be entitled.” BCUC, Decision and Order G-188-11, Zellstoff Celgar Limited Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, November 14, 2011, p. 38, R-275. 285 Memorandum from Management to Mercer International Board of Directors, Re Update on Celgar’s Generator Baseline Issue, 7 December 2011, at MER00191043, R-531. 286 Letter from Dennis Swanson, Re: Commission Order G-188-11 in the Matter of Zellstoff Celgar Limited
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
70
[T]here will be power generated by Celgar, below the BC Hydro GBL of 40 MW, available for sale that will be replaced from FortisBC resources. The amount, whether Celgar chooses to self-supply all or no power to its mill, is immaterial in the face of proper pricing. [FortisBC] is of the opinion that the [BCUC] has established the principle that arbitrage of FortisBC non-PPA power is not prohibited out of hand.287
The Ministry of Energy and Mines was concerned with the principle established 150.
in Order G-188-11 and with FortisBC’s submission, which would allow the Claimant to
increase its purchases of embedded cost power for the purpose of arbitrage. On behalf of
the Ministry, Les McLaren wrote:
The Ministry does not support arbitrage of FortisBC Embedded Cost Power (or NECP) by self-generators, just as it does not support arbitrage of BC Hydro embedded cost power…[T]he Ministry submits that arbitrage by self-generators has the potential to harm the interests of FortisBC’s other customers, and precautions are necessary to avoid it. It is not clear why the [BCUC] has restricted arbitrage related to BC Hydro’s embedded cost power delivered to FortisBC under the PPA, while potentially allowing self-generators in FortisBC’s service territory to arbitrage against FortisBC’s NECP.
[…]
FortisBC’s compliance filing introduces another approach to self-generation which, if approved by the [BCUC], would mean that one set of principles governs sales of self-generation in FortisBC’s service area and an entirely different set of principles governs sales of self-generation in BC Hydro’s service area. The Ministry submits that the [BCUC] now has an opportunity to decide whether a set of consistent principles should apply throughout the province instead. The Ministry notes that BC Hydro has recently filed an Information Report with respect to Customer Generator Baselines, including its responses to the [BCUC’s] questions about generator baselines set out in Letter No. L-106-09. It is hoped that this BC Hydro submission could help
Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, April 13, 2012 p. 1 R-497. 287 Letter from Dennis Swanson, Re: Commission Order G-188-11 in the Matter of Zellstoff Celgar Limited Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, April 13, 2012, pp. 3 and 4, R-497.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
71
inform a set of principles that apply consistently throughout British Columbia.288
In response to the Ministry’s proposal to establish a uniform GBL policy across 151.
both utilities, FortisBC wrote to the BCUC stating that it “agrees with the key points of
concern held by the Ministry, and concurs that it’s suggested regulatory framework
provides a workable solution.”289 To that end, using date from 2007-2009, FortisBC
concluded that a “GBL of approximately 41 MW is appropriate for Celgar based on
historical generation and energy consumption” and would mitigate arbitrage of FortisBC
embedded cost power.290
The Claimant, however, resisted the applicability of a uniform GBL policy across 152.
the two utilities, even though it acknowledged that a FortisBC GBL “would be an
acceptable approach to address issues of competitive disadvantage and unfairness as
between customers within FortisBC’s and BC Hydro’s service areas.”291 It is remarkable
that the Claimant made the following statements to the BCUC after it filed its NAFTA
claim against the Government of Canada, where it now launches a complaint against the
lack of a provincial-wide framework:
[T]he Ministry’s recently-articulated desire for regulatory consistency should not be allowed to delay the current compliance proceedings…Order G-188-11 does not require Celgar and FortisBC to agree on a GBL. Accordingly, the BC Hydro approach to GBLs has no application to Celgar’s right to receive
288 Ministry of Energy and Mines, Comments in the Matter of a Filing by FortisBC of Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), 22 June 2012, pp. 4 and 6, R-49. 289 Letter from Dennis Swanson to Erica Hamilton, Re: FortisBC Inc. Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11) – Reply Submissions, July 4, 2012, p.22, R-266. 290 Letter from Dennis Swanson to Erica Hamilton, Re: FortisBC Inc. Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11) – Reply Submissions, July 4, 2012, p. 25, R-266. 291 Letter from KC Moller to Erica Hamilton, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – FortisBC Inc. Project No. 3698675/Order G-54-12; Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), Aug 10, 2012, p. 5, R-499.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
72
FortisBC ECP under Order G-188-11…Furthermore, customers in the FortisBC service area have long operated under different restrictions, opportunities, principles and programs.
[R]ecent [BCUC] Orders G-156-10 and G-188-11 have resulted in the recognition of certain rights afforded Celgar to utility service within the existing regulatory framework – without the need for a broader policy review. The Ministry and BC Hydro chose not to seek reconsideration of, or appeal of those Orders. They should not now be entitled to question or impede the implementation of those Decisions in these compliance proceedings on the premise that a broader Province-wide policy is now required, particularly as they have had years to promote such a policy and have failed to do so.
The Province’s desire for consistent Province-wide policies governing self-generation while laudable, should not delay the current proceedings. The Province has demonstrated no urgency in establishing new policy.292
The Claimant obviously saw benefit to BCUC Order G-188-11 and regarded the 153.
GBL methodology as an impediment to that benefit. In light of the Claimant’s opposition,
the BCUC in Order G-202-12 chose not to adopt the GBL methodology, but instead
reaffirmed that “entitlement to non-BC Hydro PPA embedded cost power by a self-
generating customer may be as high as 100 percent of load as nominated by that
customer.”293 The Commission concluded:
A self-generator is equally entitled to having its load requirements serviced by FortisBC at embedded cost rates, except for BC Hydro PPA power which is specifically excluded by the PPA. A primary concern raised by [the Ministry] with FortisBC’s proposal is how the entitlement would impact other FortisBC ratepayers.294
292 Letter from KC Moller to Erica Hamilton, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – FortisBC Inc. Project No. 3698675/Order G-54-12; Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), Aug 10, 2012, pp. 6 and 7, R-499. 293 BCUC, Decision and Order G-202-12, in the Matter of FortisBC Inc, Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), December 27, 2012, p. 3, R-265. [Emphasis added.] 294 BCUC, Decision and Order G-202-12, in the Matter of FortisBC Inc, Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), December 27, 2012, p. 9, R-265.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
73
[The Ministry] submits that province-wide regulatory principles governing self-generation and mitigating arbitrage are required and suggests the [BCUC] adopt the GBL approach across the province. The [BCUC] has upheld a consistent regulatory principle, that self-generators should not arbitrage power to the detriment of other ratepayers, but has applied different mechanisms to achieve this protection in different circumstances.
GBLs exist between BC Hydro and its self-generating customers because they have been able to reach agreement on their GBLs. FortisBC and Celgar have been unable to reach such an agreement, notwithstanding the repeated encouragement by the [BCUC] to do so. There is currently no basis upon which the [BCUC] is able to force such an agreement or dictate what a GBL should be.295
In this arbitration the Claimant lambasts the BCUC for its alleged failure to 154.
“establish a binding rule governing self-generation applicable province-wide” and to
“review and approve GBL guidelines.”296 In light of the above passages, these
accusations have no merit because it was the Claimant who opposed the application of
such policies in FortisBC territory. Moreover, the Claimant’s characterization of BCUC
Order G-48-09 as “preventing FortisBC from selling Celgar any embedded cost
electricity from Forts’ pre-existing resource stack while Celgar is selling electricity”297 is
clearly false, as will be further demonstrated below.
3. Subsequent Proceedings Relating to the Claimant’s “Access” toFortisBC’s Embedded Cost Power
The Claimant continues to perpetuate the myth that BCUC Order G-48-09 155.
“restricts Celgar’s access to embedded cost utility electricity.”298 As explained above, the
Claimant’s interpretation of that Order conflicts with its statements before the BCUC299
295 BCUC, Decision and Order G-202-12, in the Matter of FortisBC Inc, Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), December 27, 2012, p. 11, R-265. 296 Claimant’s Reply, ¶ 477. 297 Claimant’s Reply, ¶ 33. 298 Claimant’s Reply, ¶ 35. 299 Letter from KC Moller to Alana Gillis, Re: Zellstoff Celgar Limited Partnership (“Celgar”) Complaint
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
74
and completely ignores proceedings that followed BCUC Order G-48-09 and their
outcome.
Before examining these proceedings, however, it must be emphasized that what 156.
the Claimant has successfully sought before the BCUC is a right that no other mill in the
Province holds, which is the right to arbitrage existing self-generation, historically used
for self-supply. In other words, what it has been granted is the right to stop self-
supplying, purchase embedded cost power from its utility, and then sell its previously
self-supplied electricity to a third party. No other mill in BC has such a right.
As explained above, in Order G-188-11, the BCUC agreed that “Celgar is free to 157.
sell all or a portion of its generation below the BC Hydro GBL into the market and
supply its mill from FortisBC resources, not including BC Hydro PPA Power.”300 This
was confirmed by the BCUC, which stated in Order 202-12 that: “entitlement to non-BC
Hydro PPA embedded cost power by a self-generating customer may be as high as 100
percent of load as nominated by that customer.”301 The Claimant recognizes this “major
victory”302 in its Memorial:
In its G-202-12 Decision, the Commission concluded that Celgar was entitled to have FortisBC serve 100 percent of its load with embedded cost power, as long as that embedded cost power excluded BC Hydro PPA power. The type
Regarding FortisBC Inc. (“FortisBC”) and Celgar to complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges (the “Complaint”)- Project No. 3698636 , September 1, 2011, p. 1, R-483: “Order G-48-09 provides that FortisBC will not sell electricity ‘purchased under’ the PPA to Celgar, while Celgar sells self-generation that is not in excess of its load. It does not prohibit FortisBC from selling other energy to Celgar, while Celgar sells such self-generation.” 300 BCUC, Decision and Order G-188-11, Zellstoff Celgar Limited Partnership Complaint Regarding the Failure of FortisBC Inc. and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges, November 14, 2011, p. 49, R-275. 301 BCUC, Decision and Order G-202-12, in the Matter of FortisBC Inc, Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), December 27, 2012, p. 3. R-265. 302 Memo to Mercer International Board of Directors from Management, Re: Update on Celgar’s Generator Baseline Issue, dated December 7, 2011, p. 1, R-531.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
75
of embedded cost power to which Celgar was entitled was termed “non-BC Hydro PPA embedded cost power” or “NECP.”303
In fact, it was the Claimant who proposed the concept of NECP to the BCUC in 158.
the proceedings leading up to G-188-11 that led to this result:
Order G-48-09 provides that FBC will not sell electricity ‘purchased under’ the PPA to Celgar, while Celgar sells SG that is not in excess of its load. It does not prohibit FBC from selling other energy to Celgar, while Celgar sells such self-generation. That is what Celgar proposes as a resolution to the current impasse. In order for the proposed matching purchase to have effect, the underlying premise must be that sales of energy to Celgar, matching the FBC purchases, would not be considered to be energy purchased from BCH under the PPA.304
The BCUC accepted the Claimant’s approach, which, in the Claimant’s own 159.
words “replac[ed] the ‘net of load’ criterion with a principled approach to determining
utility service to a self-generator.”305
Mr. Swanson of FortisBC explains the NECP as follows: 160.
FortisBC planned to source power for the NECP rate using all available resources with the exception of BC Hydro’s PPA power. These sources included surplus from FortisBC’s owned generation (e.g. hydro-electric generating plants), BC Hydro non-PPA power, and the market. The NECP rate would be the difference between two embedded cost calculations with a slightly different resource stack – one with BC Hydro PPA power and one without BC Hydro PPA power. In other words, the NECP would be calculated as the delta between the cost of the replacement electricity (all embedded cost resources excluding PPA power) and the cost of Rate
303 Claimant’s Memorial, ¶ 358. 304 Letter from KC Moller to Alana Gillis, Re: Zellstoff Celgar Limited Partnership (“Celgar”) Complaint Regarding FortisBC Inc. (“FortisBC”) and Celgar to complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges (the “Complaint”)- Project No. 3698636 , September 1, 2011, p. 1. R-483. 305 Letter from KC Moller to Erica Hamilton, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – FortisBC Inc. Project No. 3698675/Order G-54-12; Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), Aug 10, 2012, p. 10, R-499.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
76
Schedule 31 (all embedded cost resources including PPA power). If there was no delta, then no NECP rate would apply.306
The Claimant protests the NECP rate, which it argues would be a higher rate than 161.
“traditional embedded cost rates;”307 i.e., the rate it is charged by FortisBC under Rate
Schedule 31. The Claimant is, however, wrong to protest the NECP for two main reasons.
First, self-generators in BC Hydro territory are not permitted to engage in the type 162.
of arbitrage that the Claimant has been accorded by the BCUC. The BCUC has allowed
the Claimant to nominate up to 100% of its load to be served by NECP. Self-generators
in BC Hydro territory are prohibited from selling any self-generation historically used for
self-supply.
Second, the NECP rate has never been and will likely never be higher than 163.
“traditional embedded cost rates.” As Mr. Swanson explains:
Since 2009, the cost of replacement power (i.e., from owned surplus generation, BC Hydro (non PPA) power, and the market) has predominantly been lower than the cost of Rate Schedule 31 and is expected to remain lower into the future…
Moreover, a large hydroelectric infrastructure project called the Waneta Hydroelectric Expansion Project is expected to come online this Spring, and I anticipate that it will contribute significantly to FortisBC’s capacity surplus. In this context, consider an example where FortisBC has surplus from its owned generation resources sufficient to meet the needs of a self-generating customer looking to sell its entire load, such as Celgar. In this scenario there would be no NECP rate because the cost of serving the load would not be higher than the cost of Rate Schedule 31. Thus, if the Mid-C market climbed above Rate Schedule 31, Celgar could stand to gain a very good return.308
In light of the above, it is difficult (if not impossible) to understand the Claimant’s 164.
assertion that, since G-48-09, “FortisBC has refused to supply Celgar with any embedded
306 Dennis Swanson Statement II, ¶ 28. 307 Claimant’s Memorial, ¶ 363; Claimant’s Reply, ¶ 228, footnote 256. 308 Dennis Swanson Statement II, ¶¶ 33-34.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
77
cost power from its existing resource stack while Celgar is selling its self-generated
electricity, holding Celgar to a net-of-load standard.”309 The subsequent proceedings
before the BCUC and FortisBC’s attempt to find a reasonable solution with its customer
demonstrate that this statement is entirely untrue.
4. The Claimant’s Allegation of “Regulatory Indeterminacy” is aProduct of its Own Making
The Claimant alleges that “the BCUC has subjected Celgar to a period of 165.
discrimination and regulatory uncertainty that began in 2009 and continues to this day.
Since Order G-48-09 was issued in May 2009, Celgar has been unable to access
embedded cost utility electricity below its 2007 load, and thus has been unable to sell any
of its below-load electricity.”310
In light of the above, this cannot possibly be true. Any “indeterminacy” the 166.
Claimant may feel is a product of its own making. Mr. Swanson, of the Claimant’s own
utility, shares his own views:
It is my understanding that the Claimant alleges in this NAFTA case that the BCUC has “prevented” FortisBC from selling Celgar any embedded cost power for its below-load sales. This is wrong for two main reasons. First, the BCUC has repeatedly encouraged the Claimant to negotiate a GBL with FortisBC. While FortisBC made reasonable attempts to negotiate a FortisBC GBL, the Claimant continued to take unreasonable positions alleging that it should have a GBL as low as 1.5 MW. The Claimant’s failure to establish a GBL with FortisBC is not, in my view, the fault of the BCUC but of the Claimant’s own aggressive negotiation tactics.
Second, the BCUC has in fact granted the Claimant access to embedded cost power for its below load sales. The BCUC made this clear in Order G-188-11 and G-202-12. While the Claimant may have been concerned that the proposed NECP rate would be higher than what it refers to as “traditional embedded cost power,” I explain above why the Claimant’s concern is
309 Claimant’s Reply, ¶ 233. 310 Claimant’s Memorial, ¶ 369.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
78
unfounded. In this context, it is hard to comprehend how the BCUC has “prevented” the Claimant from accessing embedded cost power.311
E. BC Hydro’s Treatment of Skookumchuck
1. BC Hydro’s Treatment of Skookumchuck in the 1997 EPA Priorto the Existing Regulatory Framework
Following BC Hydro’s 1994 RFP,312 BC Hydro negotiated an agreement to 167.
purchase electricity generated by a new hog fuel-fired boiler and a new 14
MW turbine generator that would be built on the Skookumchuck mill’s site. The project,
named the Purcell Power Project, would operate as an Independent Power Producer, in
parallel with the mill’s original 15 MW turbine generator (“STG1”).313 BC Hydro and
Purcell Power Corporation signed the EPA on September 5, 1997 (“the 1997 EPA”).314
The 1997 EPA provided for the sale of 10.8 MW 168.
to
BC Hydro at a firm energy price.
The EPA
311 Dennis Swanson Statement II, ¶¶ 37-38. See also, Letter from K.C. Moller to Alana Gillis, Re: Zellstoff Celgar Limited Partnership (“Celgar”) Complaint Regarding the Failure of FortisBC Inc. (“FortisBC”) and Celgar to Complete a General Service Agreement and FortisBC’s Application of Rate Schedule 31 Demand Charges (the “Complaint”) – Project No. 3698636, dated August 29, 2011, attaching Celgar’s Reply Submissions, R-571. Letter from Corey Sinclair to Erica Hamilton, Re: FortisBC Inc. Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11) – Reply Submission, dated August 17, 2012, R-500; BCUC Order G-85-13 , in the Matter of the Utilities Commission Act, R.S.B.C. 1996, Chapter 473 and an Application by FortisBC Inc., for Stepped and Stand-by Rates for Transmission Voltage Customers, May 24, 2013, R-572. Letter from K.C. Moller to Erica Hamilton, Re, FortisBC Inc. Application for Stepped and Standby Rates for Transmission Customers (the “Application”) and Zellstoff Celgar Limited Partnership (“Zellstoff Celgar”), dated August 22, 2013, attaching Zellstoff Celgar’s evidence submission- internal document, R-573; Letter from K.C. Moller to Erica Hamilton, Re: FortisBC Inc. (“FortisBC”) Application for Stepped and Standby Rates for Transmission Voltage Customers – Non-Embedded Cost Power (NECP) Rate Rider, dated June 10, 2014, R-574. 312 See Canada’s Counter-Memorial, ¶ 107. 313 Christian Lague Statement, ¶¶ 9-11, 14. 314 Electricity Purchase Agreement between Purcell Power Corp. and BC Hydro, 5 September 1997, R-190. 315 Christian Lague Statement, ¶¶ 19, 33; Inter-office Memo from David G. Keir to Lester Dyck, Frank Lin, Sylvia von Minden, CBL Governance Team Re: Tembec Skookumchuck Pulp Operations -
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
79
also allowed
The project was designed in large part to replace the mill’s
emissions-heavy natural gas power boiler;317 the 1997 EPA
.318 Because the 1997 EPA required that the
10.8 MWh/h
319 This was consistent with BC Hydro’s EPAs
with IPPs at the time.320
In 1999, Tembec acquired the Skookumchuck mill, along with the 1997 EPA.321 169.
The 14 MW turbine generator foreseen by Purcell Power Corporation had not yet been
purchased, and Tembec decided to purchase a single 43.5 MW turbine generator
CBL/GBL/EPA Analysis, dated April 8, 2009 at bates 037396, R-189. 316 Electricity Purchase Agreement between Purcell Power Corp. and BC Hydro, 5 September 1997, s. 7 and Appendix 1 (“Price Schedule”) at 016977 and 016997, R-190. See also Christian Lague Statement, ¶ 19. 317 Christian Lague Statement, ¶ 10. 318 Christian Lague Statement, ¶ 20. See also Electricity Purchase Agreement between Purcell Power Corp. and BC Hydro, 5 September 1997, s. 16.3
and Appendix 2 (Emission Reductions Computation) at 016986 and 016998, R-190. 319 Electricity Purchase Agreement between Purcell Power Corp. and BC Hydro, 5 September 1997, s. 15 and Figure 1 at 016986 and 017007, R-190. 320 See also Pöyry Expert Report II, ¶ 18 (“The Skookumchuck operation has been configured and operated more akin to a kraft pulp mill with a neighboring power plant operating as an independent power producer. This stands in stark contrast to Celgar’s operations which are more integrated in nature to its recovery boiler.”) 321 The 1997 EPA was assigned from Purcell Power Corporation to Crestbrook Forest Industries, the previous owner of the Skookumchuck mill, on November 19, 1999. Tembec owned Crestbrook Forest Industries at that time. Tembec Industries and Crestbrook Forest Industries amalgamated on October 2, 2000. See Assumption Agreement between Purcell Power Corp., Crestbrook Forest Industries and British Columbia Hydro and Power Authority dated 19 November 1999, R-548; Letter from Bruce Burns to James Ko dated 29 September 2000, R-549.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
80
(“STG2”) both to replace STG1 and to meet the delivery obligations of the 1997 EPA.322
With the new mill configuration, Tembec also needed to negotiate a new Electricity
Supply Agreement (“ESA”) with BC Hydro to determine the terms and conditions under
which BC Hydro would supply the mill with electricity. Through 1999 and 2000, Tembec
and BC Hydro negotiated an accounting mechanism to govern Tembec’s electricity sales
under the 1997 EPA and its electricity purchases under the new ESA.323 The new ESA
was ultimately signed on September 14, 2001, and included an Appendix that set out the
mechanism for accounting under these two agreements.324
As Mr. Lague, the mill’s Energy Manager explains, the mechanism divided 170.
Tembec’s generation into four tranches:325
● Tranche 1: the 10.8 MW the mill generated, which were deemed delivered to BC Hydro under the 1997 EPA.
● Tranche 2: 326
● Tranche 3:
● Tranche 4:
322 Christian Lague Statement, ¶ 15. 323 See Crestbrook Forest Industries Ltd. Minutes of Meeting, Crestbrook Forest Industries Ltd. (CFI) Cogeneration Project Meeting No. 5 dated 30 May 2000, R-550; Christian Lague Statement, ¶ 22. 324 Appendix to Electricity Supply Agreement between British Columbia Hydro and Power Authority and Tembec Industries Inc. (“Determination of Electricity Supplied and Taken Under RS 1821/1880”), 14 September 2001 at 30-31, R-188. 325 Christian Lague Statement, ¶¶ 23-25. 326 Assuming a mill load of MW.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
81
Figure 2: Generation Accounting Under Tembec’s 1997 EPA327
For 171.
example, the 10.8 MW
327 Christian Lague Statement, ¶ 25.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
82
329 Running the boiler at this
level
The ESA included an agreement between the parties that Tembec would 172.
”330
331 Tembec reached COD under the 1997 EPA on September
14, 2001.
2. BC Hydro’s Consideration of Skookumchuck in the 2009 EPA
In 2006, 173.332
333 The mill was
Tembec nonetheless
334 Even with these incentives, however, Mr. Lague
328 Christian Lague Statement, ¶ 26. 329 Christian Lague Statement, ¶ 26. 330 Appendix to Electricity Supply Agreement between British Columbia Hydro and Power Authority and Tembec Industries Inc. (“Determination of Electricity Supplied and Taken Under RS 1821/1880”), 14 September 2001 at 31, R-188. 331 Lester Dyck Statement I, ¶ 98; Inter-office Memo from David G. Keir to Lester Dyck, Frank Lin, Sylvia von Minden, CBL Governance Team Re: Tembec Skookumchuck Pulp Operations - CBL/GBL/EPA Analysis, dated April 8, 2009 at 037395-6, R-189.332 Christian Lague Statement, ¶ 33; Inter-office Memo from David G. Keir to Lester Dyck, Frank Lin, Sylvia von Minden, CBL Governance Team Re: Tembec Skookumchuck Pulp Operations - CBL/GBL/EPA Analysis, dated April 8, 2009 at 037396, R-189. 333 Christian Lague Statement, ¶ 33. 334 For example, BC Hydro’s stepped rates, which came into effect in April 2006,
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
83
testifies that it 335
With the onset of the financial crisis in 2008-9, several sawmills in B.C. curtailed 174.
their production, or shut down their operations completely. The availability of hog fuel
therefore decreased significantly, and prices increased, intensifying Tembec’s situation.
Tembec’s Canal Flats, Elko and Cranbrook sawmills,
were also subject to curtailments.336 Where the
Skookumchuck mill
337
338
As Mr. Lague explains, 175.339
In 2006, the price of hog fuel delivered to the Skookumchuck mill averaged
By 2009, they had 340 In addition,
the quality of hog fuel decreased significantly. As a result, Tembec
Christian Lague Statement, ¶ 33 335 Christian Lague Statement, ¶ 33. 336 See Letter from Marc Barrette to Frank Lin, 9 February 2009, R-551. These three plants were shut down for 8 weeks starting February 9, 2009. 337 Christian Lague Statement, ¶ 34. 338 Christian Lague Statement, ¶ 34. 339 Christian Lague Statement, ¶ 35. 340 Christian Lague Statement, ¶ 35, Figure 2: Price of Hog Fuel Delivered to the Skookumchuck Mill (2006-2012). See also Inter-office Memo from David G. Keir to Lester Dyck, Frank Lin, Sylvia von Minden, CBL Governance Team Re: Tembec Skookumchuck Pulp Operations - CBL/GBL/EPA Analysis, dated April 8, 2009 at 037396, R-189.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
84
These hog
fuel supply conditions persisted until 2012.341
Under these circumstances, Tembec advised BC Hydro 176.342 and
began discussing options for renewing or replacing the agreement in early 2009. BC
Hydro proposed that the parties negotiate a new EPA on the basis of terms and conditions
similar to the Bioenergy Call for Power Phase I awards, including a GBL.343 As Mr.
Dyck testifies, “this form of commercial arrangement better reflected the appropriate risk
allocation, the regulatory environment since BCUC Order G-38-01, and relevant terms
from a recent acquisition process.”344 Tembec agreed to these terms.
BC Hydro and Tembec therefore determined a GBL for the mill on the basis of 177.
what it would generate under normal operating conditions in the absence of the 1997
EPA and in the absence of the prospective 2009 EPA,345 i.e., without the influence of any
incentive. Without the 1997 EPA,
In the GBL negotiations, Tembec took the position that, 178.
sales agreement,
341 Christian Lague Statement, Figure 2 and ¶ 37. 342 See Inter-office Memo from David G. Keir to Lester Dyck, Frank Lin, Sylvia von Minden, CBL Governance Team Re: Tembec Skookumchuck Pulp Operations - CBL/GBL/EPA Analysis, dated April 8, 2009 at 037395, R-189; BC Hydro and Tembec Electricity Purchase Agreement, 13 August 2009 at 017028, R-198. 343 Lester Dyck Statement I, ¶ 104. 344 Lester Dyck Statement I, ¶ 104. 345 Lester Dyck Statement I, ¶¶107, 106-109; Lester Dyck Statement II, ¶ 35.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
85
346 Tembec estimated that the mill would
347
BC Hydro accepted that, without the obligations of the 1997 EPA, 179.
348 As such, under normal operating conditions, without
electricity delivery obligations, the mill would
As Mr. Dyck puts it,
349
BC Hydro’s engineering department ran analysis similar 180.
to the one conducted by Mr. Lague at Tembec,350 and determined
351 BC Hydro proposed a GBL of 14 MWh/h (122.6 GWh/year),
346 Email from Christian Lague to Matt Steele re: Tembec Skookumchuck site GBL calculations, dated March 10, 2009 at 020997, R-193; Christian Lague Statement, ¶ 42; Lester Dyck Statement I, ¶ 108. 347 Email from Christian Lague to Matt Steele re: Tembec Skookumchuck site GBL calculations, dated March 10, 2009 at 020999, R-193. 348 See Lester Dyck Statement II, ¶ 35. 349 Lester Dyck Statement I, ¶ 109. 350 Lester Dyck Statement II, ¶ 43. As explained by Mr. Dyck, Mr. Norman Wild, an engineer at BC Hydro, was consulted early in the GBL negotiations to provide input into the determination of the GBL for Skookumchuck. Mr. Wild’s analyses for the Skookumchuck mill were lost in a file migration, and are not on the record of the proceeding. 351 Lester Dyck Statement II, ¶ 45.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
86
which Tembec accepted. The parties negotiated the remaining terms of the agreement on
this basis.
BC Hydro and Tembec concluded the EPA on August 13, 2009.352 Consistent 181.
with the Bioenergy Call for Power Phase I contracts, the EPA contained an exclusivity
clause in which Tembec agreed not to sell energy it generated below its GBL, unless it
was in excess of the mill’s load.353
F. BC Hydro’s Treatment of Howe Sound Pulp and Paper
1. BC Hydro’s Negotiation of a Generation Threshold with HoweSound Pulp and Paper in 2001
BC Hydro and Howe Sound had engaged in discussions concurrent with the 182.
BCUC regulatory process that led to Order G-38-01 regarding the sale of Howe Sound’s
idle generation. The parties determined that a “baseline” could be established using data
from 354 Howe Sound
had initially advocated before the BCUC that BC Hydro should permit it to sell all of its
electricity above a 35 MW baseline.355 It also contemplated a MW proposal, but
ultimately settled on a MW baseline that took into account 356
352 BC Hydro and Tembec Electricity Purchase Agreement, 13 August 2009, R-198. 353 BC Hydro and Tembec Electricity Purchase Agreement, 13 August 2009, s. 7.4(a) at 017041, R-198. 354 Pierre Lamarche Statement I, ¶¶ 24-25; Pierre Lamarche Statement II, ¶¶ 2-3.
Pierre Lamarche Witness Statement I, ¶¶ 18-23. 355 See Letter from Brian Wallace, Bull, Housser and Tupper, on Behalf of Howe Sound Pulp and Paper to Robert Pellatt, Commission Secretary, Re: British Columbia Hydro and Power Authority (“BC Hydro”) Sales to RS 1821 Customers with Self-Generating Capability, 27 February 2001, p. 2, bates 144040, R-80. Howe Sound’s generation levels Pierre Lamarche Statement II, ¶ 3. 356 Pierre Lamarche Statement I, ¶¶ 36-37; Pierre Lamarche Statement II, ¶ 4. The BC Hydro officials who were responsible for negotiating this baseline are, for the most part, retired or no longer available. The
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
87
BC Hydro and Howe Sound believed that the MW baseline was 183.
conservative as it was based
357 Howe Sound 358 The conservative nature of the calculation meant
that BC Hydro was willing to derive the baseline from a data set 359
On April 12, 2001, BC Hydro, Powerex and Howe Sound entered into a Consent 184.
and Enabling Agreement which permitted Howe Sound to sell electricity to Powerex that
it self-generated above the MW baseline.360 Howe Sound
Rather, Howe Sound
361
remaining personnel do not have a clear recollection of how this baseline was set more than a decade afterwards. Nor did BC Hydro retain records that set out precisely how this baseline was established after such a long period of time. Mr. Lamarche had the clearest recollection of events as they related directly to the Howe Sound. Mr. Dyck also has some knowledge of these events through his previous discussions with personnel that have retired. 357
Pierre Lamarche Statement II, ¶¶ 5-6. 358 See Pierre Lamarche Statement I, ¶¶ 18-23. 359
see Pierre Lamarche Statement I, fn 6; Letter from Shawn Thomas to Russ Fulton, Re: British Columbia Hydro and Power Authority (“BC Hydro”), 16 March 201, R-77. 360 Consent and Electricity Purchase and Sale Agreement between HSPP, Powerex and BC Hydro, 12 April 2001, R-85; Purchase Transaction Enabling Agreement between Powerex Corp and Howe Sound, 12 April 2001, R-84. 361 Benefit sharing s a sharing of sales revenue on a percentage basis, rather than compensation at a fixed price: Lester Dyck Statement I, ¶ 33, fn 21.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
88
Howe Sound also 185.362
363
BC Hydro and Howe Sound the Consent Agreement and Enabling 186.
Agreement 364 In doing so, BC Hydro officials
365
2001 because the circumstances that led to the MW baseline had
not changed: 366 As
Mr. Lamarche explains, natural gas prices did not 367
2. BC Hydro’s Treatment of Howe Sound in the Integrated PowerOffer
Howe Sound’s power boiler 187.
362 Pierre Lamarche Statement I, ¶ 38. 363 See Consent and Electricity Purchase and Sale Agreement between HSPP, Powerex and BC Hydro, 12 April 2001, s. 7
at 021825, R-85. 364 See Pierre Lamarche Statement II, ¶ 7; Lester Dyck Statement I, ¶ 41. See also Pierre Lamarche Statement I, ¶ 40 (showing Howe Sound’s annual sales to Powerex from 2001 to 2007). 365 Lester Dyck Statement II, ¶ 54; Pierre Lamarche Statement II, ¶ 7. See also Letter from Pierre Lamarche to Lester Dyck, 17 March 2004, R-396. 366 Pierre Lamarche Statement II, ¶ 7. 367 Pierre Lamarche Statement II, ¶¶ 9-11.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
89
368 Rather than let significant generation capacity sit idle, BC
Hydro and Howe Sound negotiated an EPA in the context of BC Hydro’s IPO.369
BC Hydro set out the terms on which it was willing to negotiate the EPA in its 188.
Letter of Intent of November 6, 2009.370 One of the terms was that a GBL be set for the
mill to determine what was existing generation that BC Hydro could not purchase in the
EPA, and what was incremental generation that BC Hydro could procure.371 In order to
establish the GBL, BC Hydro and Howe Sound reviewed the mill’s historical generation
data to find a 365-day period that reflected current normal operations.372
On reviewing the data, BC Hydro and Howe Sound 189.
373
374
375
376
368 Fred Fominoff Statement, ¶¶ 17-20. See also Canada’s Counter-Memorial, ¶ 396. 369 See Canada’s Counter-Memorial, ¶¶ 157-161. 370 Letter from BC Hydro Power Authority to Fred Fominoff, dated November 6, 2009, R-63. See also Fred Fominoff Statement, ¶ 30. 371 Letter from BC Hydro Power Authority to Fred Fominoff, dated November 6, 2009, at p. 2, R-63. 372 Lester Dyck Statement I, ¶ 127; Fred Fominoff Statement, ¶ 30. 373 Lester Dyck Statement II, ¶ 49; Lester Dyck Statement I, ¶ 127; Fred Fominoff Statement, ¶¶ 30-32. 374 Lester Dyck Statement I, ¶ 128; Fred Fominoff Statement, ¶¶ 31-32; Lester Dyck Statement II, ¶ 49. 375 Lester Dyck Statement I, ¶ 124; Fred Fominoff Statement, ¶¶ 15-20. 376 Lester Dyck Statement I, fn 136; Lester Dyck Statement II, ¶ 49.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
90
The parties therefore agreed that 190.
was the best available approach to estimating normal operations at the mill at the time of
the EPA negotiations.377 Using data from 378 BC Hydro and Howe Sound agreed to an annual
GBL of GWh/year, and negotiated the remaining terms of the agreement on
that basis.
BC Hydro also required 191.
379 The parties subsequently
negotiated a termination agreement, which was signed on September 7, 2010,
380
BC Hydro and Howe Sound concluded the EPA on September 7, 2010.381 The 192.
EPA contained an exclusivity clause in which Howe Sound agreed not to sell any
electricity below its GBL to a third party unless the mill’s generation levels were greater
than the mill load.382 Howe Sound did not challenge the clause.383
377 Lester Dyck Statement II, ¶ 50. 378
See Fred Fominoff Statement, ¶ 34, fn 17; Lester Dyck Statement I, ¶ 130. 379 Letter from BC Hydro Power Authority to Fred Fominoff, dated November 6, 2009, p. 4, R-63. 380 Termination Agreement, 7 September 2010, s. 3, R-73. See also Fred Fominoff Statement, ¶ 41. 381 BC Hydro and Howe Sound Pulp and Paper Limited Partnership, Electricity Purchase Agreement, Integrated Power Offer, 7 September 2010, R-62. 382 BC Hydro and Howe Sound Pulp and Paper Limited Partnership, Electricity Purchase Agreement, Integrated Power Offer, 7 September 2010, s. 8.4(b), at 016384, R-62. 383 Fred Fominoff Statement, ¶ 39.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
91
G. The BCUC’s Approval of a Baseline Negotiated with FortisBC, the City of Kelowna and Tolko (Riverside)
Up until 2000, the Tolko (Riverside) sawmill in Kelowna operated an old turbine 193.
generator with a limited nameplate capacity, which it used to supply its own load,
typically at levels below 2 MW.384 For instance, the sawmill’s average generation rate
was 1.23 MWh in 1996, and 1.97 MWh in 1997.385 In 1998 and 1999, Tolko conducted a
series of negotiations with its utility, the City of Kelowna, and West Kootenay Power,
toward upgrading the mill’s generation equipment, acquiring a second turbine generator,
and producing incremental energy for exports to third parties.386
Before installing the new generator, Tolko had also undertaken a series of 194.
efficiency initiatives which would increase its generation levels and contribute to make
electricity available for market sales.387 In 1999, Tolko and the City of Kelowna
concluded a Memorandum of Agreement for the purpose of confirming the rate schedules
applicable to Tolko until it increased “its current generation capability, creating surplus
384 Letter from Counsel for Riverside Forest Products Ltd. To the British Columbia Utilities Commission Re: Application by Riverside Forest Products Limited for an Order Pursuant to Section 88(3) of the Utilities Commission Act, May 29, 2001, R-552. 385 Letter agreement between the City of Kelowna and Riverside Forest Products Ltd, Re: Sale of Incremental Electric Energy by Riverside Forest Products Limited, August 21, 200, attached to the Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission, Re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, August 22, 2001, p. 5, R-553. 386 Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, BCUC Staff Information Request No. 1, July 5, 2001, attaching Riverside Forest Product’s answers to the BCUC Staff Information Request No. 1, and supporting exhibits, p. 7, R-554. 387 Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, August 22, 2001, attaching Riverside Forest Product’s answers to the BCUC Staff Information Request No. 2 and the letter agreement between the City of Kelowna and Riverside Forest Products Ltd re: Sale of Incremental Electric Energy by Riverside Forest Products Limited, August 21, 2001, pp. 9-13, R-553.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
92
power”, in which case a new power contract would be entered into “so that the customer
may obtain access to an electrical market to sell that surplus power”.388
Tolko’s efficiency initiatives allowed it to commence third party sales of 195.
electricity in April 2000.389 The installation of the new turbine generator was completed
in May 2000,390 and on August 21, 2001, Tolko and the City of Kelowna entered into a
letter agreement pursuant to which Riverside would be allowed to sell energy above 2
MW in each hour to third parties for exports. The agreement was entered into on a trial
basis, and was set to commence with Riverside Forest Products Ltd. Notifying the City of
Kelowna that it was ready to commence selling incremental energy to third parties and
continue for one year thereafter as a pilot project, subject to the parties subsequently
negotiating a longer-term agreement.391
While Tolko negotiated with its utility the terms of its projected third party sales 196.
before the BCUC issued Order No. G-38-01, Tolko nonetheless applied to the BCUC
thereafter seeking the Commission’s regulatory confirmation of the solution previously
arrived at with the City of Kelowna. In fact, Tolko applied to the BCUC for an exemption
of certain provisions of the UCA in May 2001, one month after the BCUC issued Order
388 Memorandum of Agreement between City of Kelowna and Riverside Forest Product, Ltd., February 25, 1999, at 1, attached (exhibit 2) to the Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, BCUC Staff Information Request No. 1, July 5, 2001, R-554. 389 Electricity generation and consumption chart and Output of Generation graph attached (exhibit 3) to the Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, BCUC Staff Information Request No. 1, July 5, 2001, R-554. 390 Letter from Counsel for Riverside Forest Products Ltd. To the British Columbia Utilities Commission Re: Application by Riverside Forest Products Limited for an Order Pursuant to Section 88(3) of the Utilities Commission Act, May 29, 2001. R-552. 391 Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, August 22, 2001, attaching Riverside Forest Product’s answers to the BCUC Staff Information Request No. 2 and the letter agreement between the City of Kelowna and Riverside Forest Products Ltd re: Sale of Incremental Electric Energy by Riverside Forest Products Limited, August 21, 2001, sections I(G) and II(9), pp. 10-11, R-553.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
93
No. G-38-01. Increasing its generation capacity in order to enter into third party sales of
electricity would bring Tolko within the definition of a regulated “public utility” in
accordance with the UCA, such that the power sales agreements it would enter into would
normally fall within the BCUC’s purview. Tolko therefore sought to be exempted from
BCUC scrutiny and, in so doing, requested the Commission to find that sales above its
historical self-generation level would be considered incremental and therefore eligible for
third-party sales.392 Tolko demonstrated to the BCUC that its average generation level
during the period 1996-1999, absent its initiatives toward increasing self-generation for
exports, amounted to 2 MW.393 Accordingly, the BCUC accorded an exemption to Tolko
for third-party sales above this baseline.394
III. THE TRIBUNAL SHOULD NOT CONSIDER CLAIMS THAT AREINADMISSIBLE OR THAT DO NOT FALL WITHIN ITS JURISDICTION
A. Concise Statement of Canada’s Position
Canada explained in its Counter-Memorial why the Claimant’s allegations 197.
concerning the negotiation and the setting of Celgar’s GBL need not be considered as
these claims are both inadmissible and outside the jurisdiction of the Tribunal. In its
Reply the Claimant asserted that these objections to the admissibility of its claims and the
jurisdiction of the Tribunal “do not withstand even cursory scrutiny” and addressed them
last. 395 But in so doing, the Claimant provided little in the way of compelling argument
as to why its GBL-related claims should not be rejected on for several reasons.
392 Letter from Counsel for Riverside Forest Products Ltd. To the British Columbia Utilities Commission Re: Application by Riverside Forest Products Limited for an Order Pursuant to Section 88(3) of the Utilities Commission Act, May 29, 2001, R-552. 393 Information Response of Riverside Forest Products Limited to the BCUC Staff Information Request No. 2, August 22, 2001, Answer 4.0. pp. 4-6, attached to Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, August 22, 2001, R-553. 394 BCUC, Order G-113-01, in the Matter of an Application by Riverside Forest Products Limited for an Exemption from Certain Provisions of the Utilities Commission Act, November 1, 2001, p. 2, R-20. 395 Claimant’s Reply, ¶ 587.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
94
First, as a contractual term of an EPA that has as its objective the procurement of 198.
electricity, Celgar’s GBL and section 7.4 of the EPA fall squarely within the procurement
exception in Article 1108(7)(a) and cannot breach either Article 1102 (National
Treatment) or Article 1103 (Most Favoured Nation Treatment).
Second, as BC Hydro’s negotiation of the GBL and section 7.4 was not an 199.
exercise of delegated governmental authority by a state enterprise, then pursuant to
Article 1503(2) it is not a measure that falls within the jurisdiction of this Tribunal.
And finally, as BC Hydro and Celgar negotiated the GBL and section 7.4 almost 200.
four years before the Claimant submitted this claim to arbitration, its GBL-related claims
are time-barred pursuant to Article 1116(2) and Article 1117(2).
In the following sections Canada responds to the Claimant’s perfunctory claims 201.
concerning admissibility and jurisdiction, and explains why the Tribunal should find that
these claims are either inadmissible or that it does not have jurisdiction to consider them.
B. NAFTA Articles 1102 and 1103 Do Not Apply to BC Hydro’s Negotiation of Celgar’s GBL and Section 7.4 by Virtue of the Procurement Exception in Article 1108(7)(a)
NAFTA Article 1108(7)(a) provides that the NAFTA Article 1102 (National 202.
Treatment) and Article 1103 (Most Favored Nation Treatment) do not apply to
“procurement by a Party or a state enterprise.” Canada explained in its Counter-
Memorial why Celgar’s GBL, a contractual term establishing the amount of electricity
BC Hydro would purchase under its EPA with Celgar, falls squarely within the
procurement exception of Article 1108(7)(a).396 The Claimant actually agrees with
Canada; in its Reply the Claimant states that “Mercer agrees that if in fact that was all its
396 Canada’s Counter-Memorial, ¶¶ 345-349.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
95
GBL did—nothing more than defining BC Hydro’s purchase obligation—such a measure
would fall within the procurement exception.”397
The Claimant asserts, however, that it is not claiming that BC Hydro was required 203.
to procure additional electricity:
While Celgar did offer BC Hydro its below-load electricity as one of two proposals presented in response to BC Hydro’s Bioenergy Phase I Request for Proposals (“RFP”), BC Hydro explained that such energy was not eligible under the terms of the RFP, and Mercer does not contend that BC Hydro nonetheless was legally obligated to buy it. Mercer takes issue instead with the restriction BC Hydro placed on Celgar’s sales of its below-GBL energy to third parties, effectuated through the GBL and related exclusivity provisions in Section 7.4(b) of the 2009 EPA.398
This is a misleading statement. The Claimant’s entire NAFTA case is premised 204.
on a GBL that it believes is “too high”399 and that BC Hydro was required to procure
more electricity from the Claimant under the EPA. The Claimant itself states that “the
Tribunal’s first task in assessing damages is to determine the GBL that Celgar should
have received absent its less favourable, unfair, and inequitable treatment.”400 It argues
that “if Celgar’s non-discriminatory GBL should have been lower, it is all but certain that
BC Hydro would have done what it did in every other EPA with a BC self-generator, and
purchased all above-GBL electricity on a firm basis.”401
Indeed, the majority of its Reply is directed at attacking BC Hydro’s GBL 205.
methodology and how Celgar’s GBL was set in comparison to other mills. The Claimant
proffers eleven non-discriminatory alternative GBLs for the Tribunal to consider,402 and
397 Claimant’s Reply, ¶ 617 (emphasis added). 398 Claimant Reply, ¶¶ 36, 618, 622. [Emphasis added.] 399 Claimant Reply, ¶ 553. 400 Claimant Reply, ¶ 529. 401 Claimant Reply, ¶ 554. 402 Claimant Reply, ¶ 536.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
96
then quantifies damages on the basis that BC Hydro procures all of the Claimant’s
electricity above each GBL. The Claimant concludes that Canada “has offered no reason
why BC Hydro would not have purchased all electricity above a corrected Celgar
GBL.”403
It is difficult to imagine how these claims could possibly fall outside of the 206.
procurement exception of Article 1108(7)(a). The Claimant’s attempt to evade the
exception by characterizing the “crux”404 of its claim as an alleged prohibition on below-
GBL sales and not sales “to BC Hydro or a Canadian state entity but to third parties,”405
is simply not convincing.
Moreover, the Claimant’s assertion that the alleged restriction on below-GBL 207.
sales to third parties, effectuated through Section 7.4 of the EPA, is not “procurement-
related”406 is also false.
First, Section 7.4 does not impose such a restriction in light of the Side Letter 208.
Agreement the Claimant signed with BC Hydro, which permits such sales with BCUC
approval.407 The BCUC has granted this approval.408 Moreover, FortisBC has developed
the NECP rate which would allow the Claimant to sell all of its below-load electricity.409
Second, even if there was such a restriction it is nonetheless an essential element 209.
to the procurement of electricity by BC Hydro. Mr. Scouras explains that allowing Celgar
403 Claimant Reply, ¶ 554.404 Claimant Reply, ¶ 622. 405 Claimant Reply, ¶ 622. 406 Claimant Reply, ¶ 618. 407 Side Letter Agreement between BC Hydro and Zellstoff Celgar Limited Partnership, Re: Electricity Purchase Agreement, with Effective Date of January 27, 2009 (“EPA”), dated January 27, 2009, bates 026183-026184, R-138. 408 BCUC, Decision G-188-11, p. 49, R-275. BCUC, Order G-202-12, ¶¶ 2-3 and Decision, in the Matter of FortisBC Inc., Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), 27 December 2012, pp. 8 and 15, R-265. 409 Dennis Swanson Statement II, ¶¶ 27-36.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
97
to engage in below-GBL third party sales, this “would result in BC Hydro not receiving
the full benefit of the electricity under the EPA and would, thus, significantly undermine
the firmness of the security of supply that BC Hydro is seeking to achieve with an EPA.”
In this regard, the exclusivity provision of an EPA “provides greater certainty that BC
Hydro will in fact receive the benefit of the electricity under the EPA and protects BC
Hydro’s procurement of electricity.”410 Accordingly, this measure cannot be challenged
under NAFTA Articles 1102 or 1103 and the Claimant’s claims in this regard must be
dismissed.
C. BC Hydro’s Negotiation of the GBL and Section 7.4(b) Was Not An Exercise of Delegated Governmental Authority and Cannot be the Subject of a Claim Under NAFTA Chapter Eleven
The obligation prescribed by Article 1503(2) and recourse to Chapter Eleven 210.
arbitration, are only permitted if a NAFTA Party has delegated a governmental authority
to a state enterprise. Canada explained in its Counter-Memorial why BC Hydro, as a
state enterprise,411 did not exercise “delegated governmental authority” when it
negotiated and established Celgar’s GBL.412 In response the Claimant asserts that in
issuing Order G-38-01 the BCUC provided BC Hydro “with wide discretion and thereby
delegated governmental authority.”413 As the “final arbiter and approver” of a GBL, BC
Hydro is, in the Claimant’s eyes, “the responsible party exercising governmental
authority.”414 The Claimant also asserts that because Celgar could not make below-GBL
sales to third parties, BC Hydro was “not acting in a purely commercial capacity,”415
410 Jim Scouras Statement II, ¶ 9. 411 The Claimant has not taken issue with Canada’s assertion, made in ¶ 321 of its Counter-Memorial, that BC Hydro is a “state enterprise” and not a “privately-owned” or federal “government” monopoly, and that this Tribunal need only consider the potential application of Article 1503(2) in this arbitration. Canada therefore confines its submission in this section to Article 1503(2). 412 Canada’s Counter-Memorial, ¶¶ 323-335. 413 Claimant’s Reply, Part VII.A.1. 414 Claimant’s Reply, ¶ 594. 415 Claimant’s Reply, Part VII.2.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
98
rendering its act an exercise of delegated governmental authority. None of these new
arguments discharge the Claimant’s burden of making out a claim under Article
1503(2).416 Below, Canada explains why the Claimant’s assertions have no bearing on an
interpretation of Article 1503(2), and why they fail to establish that BC Hydro’s
negotiation of Celgar’s GBL was an act of delegated government authority.
1. A State Enterprise Does Not Engage Article 1503(2) MerelyBecause It Has “Wide Discretion” or Because Its Acts Are Not “Purely Commercial”
In its Counter-Memorial Canada explained why activities of state enterprises 211.
having a commercial character rather than a governmental one are not captured by Article
1503(2).417 This interpretation is consistent with the ordinary meaning of the words
“governmental authority” when placed in their context. Moreover, a past NAFTA
Tribunal that gave close consideration to Article 1503(2)—the UPS Tribunal—
interpreted these words as having a “limited scope”418 that does not apply to the rights
and powers of state enterprises “to enter into contracts for purchase or sale and to arrange
and manage their own commercial activities.”419
The Claimant’s arguments in response are neither supported by the text of Article 212.
1503(2) nor by basic rules of treaty interpretation. State enterprises engage in a wide
range of activities, some governmental in nature and some commercial, and like other
commercial actors in the free market they are free to conduct their business affairs. They
are, however, subject to government regulation and their commercial activities often play
essential key role in the proper functioning of the economy or society. Their activities
416 The UPS Tribunal made clear that the Claimant bears the burden of demonstrating Article 1503(2) applies: “A claimant which wishes to invoke … [Article 1503(2)] must establish that the … state enterprise in question is exercising a “regulatory, administrative or other governmental authority that the Party has delegated to it.” See United Parcel Service of America, Inc. v. Government of Canada (UNCITRAL), Award on the Merits and Dissenting Opinion, 24 May 2007, (UPS – Award), ¶ 68, RA-45. 417 Canada’s Counter-Memorial, ¶¶ 321-326. 418 UPS – Award, ¶ 75, RA-45. 419 UPS – Award, ¶ 74, RA-45.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
99
could accordingly be characterized as not being “purely commercial” in nature. But this
kind of general characterization does not necessarily render the activities of state
enterprises exercises of “delegated governmental authority” for the purposes of Article
1503(2).
First, the Claimant’s assertion that BCUC provided BC Hydro with “wide 213.
discretion and thereby delegated governmental authority”420 offers nothing more than a
conclusion without analysis. By focusing only upon the wide latitude exercised by BC
Hydro in its commercial dealings, the Claimant ignores the determination that has to be
made under Article 1503(2), which as the UPS Tribunal explained, is “the scope of the
expression ‘regulatory, administrative or other governmental authority that the Party has
delegated to it.’”421 There is nothing in the text of Article 1503(2), nor in the related
context or object and purpose of the NAFTA, that warrants a conclusion that “wide
discretion” exercised by a state enterprise equates to it exercising a delegated
governmental authority under Article 1503(2).
Regarding the Claimant’s claim that BC Hydro was not acting in a “purely 214.
commercial capacity”422 Canada never contended that it was, and in fact, the “purely
commercial” requirement is of the Claimant’s making.423 Moreover, while the
commercial nature of a state enterprise’s activities is certainly relevant to an
interpretation of Article 1503(2), the provision does not require such activities to be
“purely commercial” in order for them to be excluded from its scope. In UPS for
example, the Claimant argued that a number of Canada Post’s activities violated NAFTA
on the ground that “Canada Post always acts under governmental authority” and that
420 Claimant’s Reply, Part VII.A.1. See also ¶¶ 592-595. 421 UPS – Award, ¶ 71, RA-45. 422 In its Reply Memorial, the Claimant attributes to Canada the argument that “the establishment of a GBL is a purely commercial act.” See Claimant’s Reply, ¶ 597. 423 Claimant’s Memorial, ¶ 418.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
100
“[n]one of its acts are sufficiently commercial to lose their governmental nature.”424 The
Tribunal rejected this proposition, observing that while “Canada Post may be seen as part
of the government system, broadly conceived”425 not all of its acts were exercises of
delegated governmental authority. In UPS the types of acts that were not captured by
Article 1503(2) included a state enterprise’s capacity to enter into purchase agreements
and to manage its commercial affairs.”426
2. BC Hydro’s Negotiation of the GBL and Section 7.4(b) In ItsProcurement of Electricity From Celgar Did Not Engage Article 1503(2)
Canada explained in its Counter-Memorial why BC Hydro’s negotiation of a GBL 215.
in its procurement of electricity from self-generators is a commercial act, not an exercise
of delegated governmental authority.427 In a nutshell, GBLs and exclusivity provisions
are negotiated terms of electricity purchase agreements, voluntarily entered into by BC
Hydro and a self-generator. They are essential to the operation of an EPA, as without
them BC Hydro would have no way of ensuring it achieves what it has set out to do—
procure electricity. The negotiation of a GBL in an EPA prevents against the irrational
outcome, described by BC Hydro’s Lester Dyck, of the utility actually paying for
electricity that it has already supplied to a self-generator.428 No rational commercial actor
would agree to such an outcome. The main purpose of the exclusivity provision is also to
424 UPS – Award, ¶ 71, RA-45. 425 UPS – Award, ¶ 57, RA-45. 426 UPS – Award, ¶ 74, RA-45. 427 Canada’s Counter-Memorial, ¶¶ 331-335. See also Lester Dyck Statement I, wherein Mr. Dyck explained in great detail the inherently commercial considerations that are taken into account in the negotiation of a GBL during the procurement process. With respect to BC Hydro’s application of the GBL concept subsequent to BCUC Order G-38-01 see ¶¶ 42-50. Regarding BC Hydro’s determination of GBLs in the BioEnergy Call for Power Phase 1, including the negotiation of Celgar’s GBL, see ¶¶ 51-91. 428 See Lester Dyck Statement I, ¶ 43.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
101
provide certainty as to “the security of supply that is contracted for with project
proponents.”429
In its Reply Memorial, the Claimant ignores the commercial objectives served by 216.
Celgar’s GBL and exclusivity provision and the inherently commercial process through
which it was negotiated. The Claimant focuses on the fact that “neither BC Hydro nor
anyone else in BC had set GBLs before Order G-38-01.”430 In the Claimant’s view, the
issuance of Order G-38-01 was a delegation of governmental authority given the wide
discretion it conferred on BC Hydro to apply the GBL principle.431 The Claimant also
asserts that BC Hydro was not acting in a “purely commercial capacity” in that it was
only able to “require” a self-generator to self-supply before it can sell to BC Hydro or to
third parties by virtue of a “legal authority” provided to it by the BCUC.”432 Finally, the
Claimant notes that Canada has provided no evidence of private parties agreeing to GBL-
like restrictions in their commercial dealings, and that Canada failed to rebut Mercer’s
argument that such an agreement would violate Canadian competition law.433 Canada
explains below why none of these assertions have any merit and must be rejected.
As a preliminary matter, Order G-38-01 must be placed in its appropriate context 217.
which is far different than the one complained of by the Claimant. The question for BC
Hydro at the time of the G-38-01 proceeding was not the rules it should follow in
procuring electricity from self-generators. It was rather the extent to which BC Hydro
was obligated to serve self-generator customers that wanted to sell self-generated
electricity to third parties. The GBL principle of Order G-38-01 provided guidance as to
how such sales could be made possible from that perspective. The fact that “neither BC
429 Jim Scouras Statement II, ¶ 8. 430 Claimant’s Reply, ¶ 591. 431 Claimant’s Reply, ¶¶ 592-595. 432 Claimant’s Reply, ¶ 599. 433 Claimant’s Reply, ¶ 599.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
102
Hydro nor anyone else in BC had set GBLs before Order G-38-01”434 is not evidence of a
delegation; it only shows that a new issue arose in British Columbia’s electricity market
that required the guidance of the BCUC. BC Hydro later adapted the GBL principle in an
entirely different context some seven years later—the Bio Phase 1 Call for Power435—
and it did so without specific instruction from the BCUC.
The discretion afforded to BC Hydro to develop and apply the GBL principle and 218.
to later apply it in the procurement process that followed the Bio Phase 1 Call for Power
is not surprising. BC Hydro was the commercial actor best situated to gather, weigh and
consider the financial data relating to a GBL, and to work out a GBL with a self-
generator that would enable it to actually procure electricity from a self-generator.436
Moreover, BC Hydro hardly required a “conferral of discretion” in order for it to
negotiate a GBL. Like any other commercial actor in the electricity marketplace, BC
Hydro is free to do business as it sees fit, so long as it complies with applicable law and
BCUC orders such as Order G-38-01.
In this regard, the Claimant confuses BC Hydro’s legal obligation, as a regulated 219.
utility, to negotiate GBLs pursuant to the guidance of the BCUC, with a “legal authority
to establish GBLs for its customers” which the Claimant alleges BC Hydro would not
have had “absent government authorization.”437 Indeed, Mr. David Bursey, Canada’s
legal expert, explains that, at least as a matter of Canadian law, the BCUC’s practice of
434 Claimant’s Reply, ¶ 591. 435 Lester Dyck Statement I, ¶ 42. 436 See for example BC Hydro’s analysis of Celgar’s proposed Biomass Realization Project in the Power Acquisitions Bioenergy RFP-Phase 1 Briefing Note on Celgar, dated April 9, 2008 at bates 020509, R-179. (“If BC Hydro were to agree to the purchase of energy from the existing generator at the Celgar mill, then BC Hydro would essentially be paying Celgar for using energy it generates to serve its own load. Assuming Celgar’s average annual mill load is 300 GWh, BC Hydro’s [RS 3803] tariff rate is $36/MWh and a contract firm energy price of $85/MWh for the [sic] Celgar’s generation output, the net cost to BC Hydro for this arrangement which results in no new energy supply, would be $15 million per year.”). 437 Claimant’s Reply, ¶ 600.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
103
allowing BC Hydro to negotiate a GBL is not a delegation of statutory decision-making
authority or other governmental authority.438
It is a fact of life that commercial actors have to follow countless rules mandated 220.
by government in their commercial dealings—even more so in a highly regulated
environment like the electricity marketplace. The fact that BC Hydro negotiated a GBL
in the course of the procurement process is only evidence that it followed such a rule and
nothing more. It does not transform this step of the procurement process into an exercise
of delegated governmental authority.
Finally, the Claimant’s assertions that Canada has provided no evidence of private 221.
parties agreeing to GBL-like terms in their contracts, and no rebuttal to Mercer’s
argument that such an agreement would be contrary to Canadian competition law, are
also both totally irrelevant to the determination that this Tribunal must make under
Article 1503(2). That a GBL or exclusivity provision might not be mandated in a private
commercial context does not make BC Hydro’s negotiation of those terms any more of an
exercise of delegated governmental authority for the purposes of Article 1503(2).
Further, the issue of a NAFTA Party’s adherence to principles governing competition law
is addressed by another provision of NAFTA Chapter Fifteen, Article 1501, and is in fact
not subject to any form of dispute settlement under the Agreement.439 The Claimant’s
438 David Bursey Expert Report, ¶¶ 120-123. 439 NAFTA Article 1501(3). Moreover, the Claimant’s allegation that the GBL provision in Celgar’s EPA, is prohibited under Canadian competition law is meritless (Claimant’s Reply, ¶419). From the outset, the Claimant’s attempt to characterize Elsey et. al. v J.G. Collins Insurance Agencies Ltd. as “Canadian competition law” is a misnomer. In Canada, competition law is largely governed by the Competition Act (Competition Act, R.S.C. 1985, c. C-34, R-555), which is a federal law administered and enforced by the Competition Bureau (Competition Bureau, “Our Legislation” http://www.competitionbureau.gc.ca/eic/site/cb-bc.nsf/eng/h_00148.html; R-556). In contrast, the decision in Elsey concerned the validity of a restrictive covenant in an employment contract and made no reference to the Competition Act or any other acts administered or enforced by the Competition Bureau (Elsey et. al. v. J.G. Collins Insurance Agencies Ltd., SCC (1978) 2 SCR 916, C-151). Furthermore, Elsey provides nosupport for the Claimant's assertion that there is a general prohibition on covenants in restraint of trade in commercial contracts. In determining that such a provision “is enforceable only if it is reasonable between the parties and with reference to the public interest” , the Supreme Court of Canada stated that “[t]he validity, or otherwise, of a restrictive covenant can be determined only upon an overall assessment of the
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
104
“competition law” based arguments are thus misguided, and have no place in the
determination that must be made here.
BC Hydro made clear from the outset that the negotiation of a GBL440 and 222.
exclusivity provision441 would be an integral part of its EPA negotiations with Celgar.
Without a GBL, the Agreement could not function. BC Hydro and Celgar entered into
negotiations of their own accord, which they did, for example, with the exclusivity
provision and Side Letter Agreement. Both were free to work out the terms of the
Agreement. Both were free to leave the negotiations if they so desired. This freedom of
choice in the parties’ commercial dealings is antithetical to one being subjected to an
exercise of delegated governmental authority at the hands of the other. The Claimant has
failed to demonstrate that BC Hydro exercised a “delegated governmental authority” in
negotiating the GBL and exclusivity provision and accordingly its complaint regarding
the GBL is not one that can be submitted to NAFTA Chapter Eleven arbitration before
this Tribunal.
D. The Claimant’s Claim Related to Section 7.4 and BC Hydro’s Setting of Celgar’s GBL are Time-Barred under Articles 1116(2) and 1117(2)
NAFTA Articles 1116(2) and 1117(2) prohibit a claimant from bringing a claim 223.
more than three years after it first acquired knowledge of a breach and loss.442 The word
“first” means “earliest in occurrence, existence.”443 It identifies the beginning of a period
or event; not the middle or end.
clause, the agreement within which it is found, and all of the surrounding circumstance” (Ibid., at Part II). Courts will normally give effect to such a provision, if it is determined to be reasonable in the circumstances (Ibid.). 440 Lester Dyck Statement I, ¶¶ 56-59; and Jim Scouras Statement I, ¶¶ 40-44. 441 Jim Scouras Statement II, ¶¶7-8, 11-13 and 16-27. 442 North American Free Trade Agreement, U.S.-Can.-Mex., 17 December 1992, 32 ILM 289, 605 (1993), Arts. 1116(2), 1117(2), C-1. 443 Shorter Oxford Dictionary, 5th ed. (Oxford University Press, 2002), p. 965, R-283.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
105
NAFTA Articles 1116(2) and 1117(2) do not require actual knowledge. The time 224.
bar will run equally from the first moment at which an investor “should have” known of a
breach and loss. The Tribunal in Grand River Enterprises v. United States explained that
knowledge will be “imputed to person [sic] if by exercise of reasonable care or diligence,
the person would have known of that fact.”444
Furthermore, loss need not actually have been incurred for the time bar to run. 225.
What is required is knowledge of loss. An “immediate outlay of funds” is unnecessary as
“damages or injury may be incurred even though the amount or extent may not become
known until some future time.”445
The Claimant filed its NAFTA claim on April 30, 2012. The cut-off date 226.
pursuant to NAFTA Articles 1116(2) and 1117(2) is thus April 30, 2009. The Claimant’s
GBL was established on May 30, 2008, well before the cut-off date. The Claimant also
signed the EPA containing the GBL and exclusivity provision on January 27, 2009, also
before the cut-off date. Accordingly, the Claimant’s allegations related to Celgar’s GBL
are time-barred and the Tribunal lacks the jurisdiction to hear them.
In its Reply Memorial, the Claimant acknowledges that “the implications of the 227.
GBL and related restrictions were known to Mercer on [January 27, 2009]”446 but argues
that the EPA, while signed on that date, did not “take effect” until approved by the BCUC
on July 31, 2009.447 Thus, while the Claimant recognizes that it had the requisite
knowledge of breach and loss prior to the cut-off date, that fact should be of no critical
importance to Articles 1116(2) and 1117(2) because the EPA had not yet taken “effect.”
The Claimant even suggests that the limitations period did not start to run until
444 Grand River Enterprises Six Nations, Ltd, et al v. United States of America (UNCITRAL) Decision on Objections to Jurisdiction , 20 July, 2006, (“Grand River - Jurisdiction”) ¶ 59, RA-17. 445 Grand River - Jurisdiction, ¶ 77, RA-17. See also Mondev International Ltd. v. The United States of America (ICSID Case No. ARB(AF)/99/2) Award, 11 October 2002 (“Mondev - Award”), ¶ 87, RA-29. 446 [Emphasis Added] Claimant’s Reply Memorial, ¶ 614. 447 Claimant’s Reply Memorial, ¶ 615.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
106
September 27, 2010, which is the Commercial Operation Date (i.e. start date) of the EPA,
because “the restrictions on sales to third parties did not take effect until” that date.448
NAFTA Articles 1116(2) and 1117(2) do not address the “effect” of measures, 228.
but a Claimant’s constructive knowledge of breach and loss. The Claimant’s reading of
the provisions is not supported by the ordinary meaning of the text. Nor can the Claimant
possibly deny that it had the requisite knowledge of breach and loss before the cut-off
date because the Claimant signed the EPA, which included both the GBL and the
exclusivity provision, with full volition.
In light of this the Claimant is forced to try other arguments such as that it could 229.
not have had requisite knowledge of breach and loss until Tembec’s GBL was
incorporated into its 2009 EPA and Howe Sound’s GBL was incorporated into in its 2010
EPA.449 However, in its pleadings the Claimant insists on comparing its own regulatory
treatment to the treatment that Tembec and Howe Sound received dating back to 1997.450
It is also clear that FortisBC raised the regulatory treatment Howe Sound had received in
its discussions with the Claimant451 and that the Claimant completed its own regulatory
research452 in the context of laying the groundwork for its so-called Arbitrage Project.
The Claimant, therefore, knew, or ought to have known, of Tembec’s and Howe Sound’s
earlier treatment before it received its own GBL from BC Hydro on May 30, 2008. 453
448 Claimant’s Reply Memorial, ¶ 615. 449 Claimant’s Reply, ¶ 609. 450 Claimant’s Memorial, ¶¶ 517, 539, 547, 551. 451 Dennis Swanson Statement II, ¶¶ 9-12. 452 Dennis Swanson Statement II, ¶ 7; and Mercer International Group, Celgar Electricity Opportunities, July 2007, at 9-10, R-278.
453 Letter from RFP Administrator (Bioenergy Call - Phase I) to Brian Merwin Re: Bioenergy Call (Phase I)– GBL, dated May 30, 2008, R-181.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
107
In sum, the Claimant’s allegations concerning the GBL and exclusivity provision 230.
are time-barred. It first knew of both the breach and loss that it complaints before the
cut-off date and the Tribunal has no jurisdiction to hear these claims.
IV. THE CLAIMANT HAS FAILED TO PROVE THAT CANADA HASBREACHED ARTICLE 1102 OR 1103
A. Concise Statement of Canada’s Position
The Claimant dedicates a lengthy 156 pages of its Reply Memorial454 to NAFTA 231.
Articles 1102 and 1103. The “Jackson Pollock” style of advocacy only complicates the
issues. Canada, however, believes that these issues are relatively straightforward:
(1) Did BC Hydro procure incremental electricity under BC’s 2007 Energy Plan from Celgar, Howe Sound and Tembec in a discriminatory manner?
(2) Did BC Hydro restrict the sale of below-GBL electricity (i.e. non-incremental electricity) to third parties in the EPAs it signed with Celgar, Howe Sound and Tembec in a discriminatory manner?
(3) Did the BCUC restrict the Claimant’s access to embedded cost power and, if so, did it do so in a discriminatory manner compared to Howe Sound and Tembec?
Outside of the Claimant’s “hall of funhouse mirrors,”455 it is not only clear that 232.
the Claimant has been accorded identical treatment to Howe Sound and Tembec, but in
some instances has been accorded more favorable treatment. For example, BC Hydro
agreed to a Side Letter Agreement to allow the Claimant to sell its below-GBL electricity
to third parties and the BCUC directed FortisBC to supply the Claimant with embedded
cost power up to 100% of its load to facilitate those sales. No other mill in the Province
has this right.
454 This is 66 more pages than the 90 pages the Claimant dedicates to NAFTA Articles 1102 and 1103 in its Memorial. 455 NERA Expert Report II, ¶ 36.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
108
In its Reply, the Claimant attempts to hide these facts by mischaracterizing the 233.
measures at issue, ignoring relevant evidence, making irrelevant arguments, and attacking
the policies underlying BC Hydro’s procurement activities. The Claimant’s efforts are
without merit. As will be shown below: (1) BC Hydro accorded the same treatment to all
mills when it procured electricity under BC’s 2007 Energy Plan; (2) BC Hydro restricted
the sale of below-GBL electricity to third parties in the same manner for every mill
except Celgar, who faces no such restriction; and (3) unlike Howe Sound and Tembec,
the BCUC has granted the Claimant access to embedded cost power below its GBL for
the purpose of arbitrage.
Prior to engaging these three issues, Canada will first correct the Claimant’s 234.
mischaracterization of the law with respect to NAFTA Articles 1102 and 1103 and the
arguments Canada made in its Counter-Memorial.
B. The Claimant Misunderstands the Law under NAFTA Articles 1102 and 1103
The Claimant misunderstands the law under NAFTA Articles 1102 and 1103 in 235.
three fundamental respects: (1) it misapplies the three-part test; (2) it ignores the role of
nationality; and (3) it argues that a non-discriminatory measure can nonetheless violate
Articles 1102 and 1103 if it “fail[s] to serve any legitimate governmental objective that
could not have been achieved by non-discriminatory means.”456
1. The Claimant Misapplies the Three-Part Test under NAFTAArticles 1102 and 1103
The Claimant states that in order to make out a claim under either NAFTA Article 236.
1102 or 1103 it need only prove “a prima facie violation” by establishing three essential
elements: (1) Canada accorded treatment to its investment; (2) its investment is in like
456 Claimant’s Reply, ¶ 183.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
109
circumstances to other investments; and (3) its investment received less favorable
treatment than those other investments.457
The Claimant is wrong in two fundamental respects. First, the Claimant must do 237.
more than prove “prima facie” the three elements of the test, which would improperly
shift a large part of its evidentiary burden to Canada. It is axiomatic to state that the party
alleging a breach of Articles 1102 and 1103 bears the burden of proof.458 The Claimant’s
efforts to reverse the onus should be rejected.
Second, the Claimant posits that it need only prove that its “investment is in like 238.
circumstances to other investments,”459 without analyzing the circumstances underlying
the treatment accorded to those investments. The Claimant’s approach contradicts the
ordinary meaning of Article 1102, which states that each NAFTA Party “shall accord to
investors of another Party treatment no less favorable than that it accords, in like
circumstances, to its own investors…”460 The Claimant is required to do more than prove
that two “investments” are in like circumstances; it must prove that the treatment
accorded to those investments was also in like circumstances.
In disconnecting the subject of the treatment from the circumstances in which the 239.
treatment was accorded, the Claimant draws inapt comparisons that do not take into
account all of the surrounding facts, including the character of the measure at issue.461
This leads to bizarre results (as will be shown below), such as the Claimant’s comparison
457 Claimant’s Reply, ¶ 130; Claimant’s Memorial, ¶¶ 448, 484. Once it has shown a prima facie violation of Article 1102 or 1103, the Claimant posits that the burden shifts to Canada to demonstrate that the less favourable treatment is justified. 458 UPS –Award, ¶ 84, RA-46. 459 Claimant’s Reply, ¶ 130. 460 NAFTA Article 1102. Similarly, NAFTA Article 1103 states: “Each Party shall accord to investors of another Party treatment no less favorable than that it accords, in like circumstances, to investors of any other Party or of a non-Party…” See e.g. GAMI - Award, ¶ 114; RA-14; Pope & Talbot Inc. v. Canada (UNCITRAL) Award on the Merits of Phase 2, 10 April 2001 (“Pope & Talbot – Merits Award”), ¶ 79, RA-36; Cargill – Award, ¶¶ 204-206, RA-6; UPS – Award, ¶¶ 101, 118, RA-46. 461 S.D. Myers – First Partial Award, ¶ 250, RA-38; Pope & Talbot - Award, ¶ 76, RA-36.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
110
of its treatment by BC Hydro under the 2007 Energy Plan to other BC Hydro contracts
that predate that plan by more than a decade.
The Claimant’s free-floating approach to “like circumstances” must therefore be 240.
rejected as it would open a floodgate of less favorable treatment claims without any
regard to the circumstances under which treatment is accorded. Canada’s approach
properly assesses all of the circumstances underlying the treatment, as required by
Articles 1102 and 1103, to determine whether the treatment at issue is properly compared
and explained.462
2. Nationality is a Critical Factor under NAFTA Articles 1102 and1103
The principle of National Treatment under Article 1102 and of Most-Favoured-241.
Nation Treatment under Article 1103, is “an application of the general prohibition of
discrimination based on nationality.”463 “Nationality” is thus central to determining
whether there has been a breach of these obligations.464
The Claimant alleges that nationality plays no role under Articles 1102 and 1103. 242.
It argues that it need only establish, prima facie, less favorable treatment and then the
burden shifts to Canada to defend its actions. This is inaccurate. First, when any claimant
alleges that a government is motivated by discriminatory intent, it is required to prove its
462 See Canada’s Counter-Memorial, ¶¶ 380-382. The Cargill tribunal noted that both the GAMI and Pope & Talbot tribunals determined “like circumstances” by reference to the rationale for each measure that was challenged. In both cases, the tribunals held that there was no breach of the national treatment obligation because the relevant comparators had not been accorded treatment in like circumstances. The Cargill tribunal proceeded to note that “it is possible that in respect of other, different measures, the mills in GAMI and the lumber producers in Pope & Talbot could have been found to be in ‘like circumstances’.” Cargill - Award, ¶ 206, RA-6. The Parkerings tribunal also adopted this approach: Parkerings - Award, CA-12, ¶¶ 376 et seq. See also GAMI - Award, RA-14; Pope & Talbot - Award, RA-36. 463 ADM - Award, CA-3, ¶¶ 193, 205. 464 Pope & Talbot – Merits Award, ¶ 103, RA-36; Cargill – Award, ¶ 220, RA-6; Apotex Holdings Inc. and Apotex Inc. v. United States of America, (ICSID Case No. ARB(AF)/12/1) Award, 25 August 2014 (“Apotex – Award”), ¶ 8.56, RA-54.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
111
allegation.465 While this Claimant states that it has “not alleged any intent to
discriminate,”466 its pleadings show otherwise:467
● BC Hydro “determined GBLs with virtually unfettered discretion, withoutpublic input, making up rules it did not disclose as it went along...Thissystem design enables BC Hydro to discriminate, which should not beregarded as unintentional.” 468
● “BC Hydro has unequal bargaining power,” which it exercised to favor millswith “political connections and importance.”469
● “BC Hydro had direct financial incentives to afford Howe Sound a morefavourable GBL than Celgar.”470
465 See Claimant’s Reply, ¶¶ 135-138. 466 Claimant’s Reply, ¶ 139. 467 The Claimant’s comment at ¶ 140 of its Reply misses Canada’s point: the Loewen tribunal expressly stated that NAFTA Article 1102 requires less favourable treatment by reason of the claimant’s nationality. The debated paragraph from the Loewen decision reads, in its entirety (emphasis added):
139. Article 1102 bars discrimination against foreign investors and their investments. Article 1102(1) and (2) requires each Party to accord investors and investments of another Party “treatment no less favorable than it accords in like circumstances to its own investors” or their investments. With respect to a state or province Article 1102(3) requires
“treatment no less favorable than the most favorable treatment accorded, in like circumstances, by that state or province to investors, and to investments of investors, of the Party of which it forms part.”
The effect of these provisions, as Respondent’s expert Professor Bilder states, is that a Mississippi court shall not conduct itself less favourably to Loewen, by reason of its Canadian nationality, than it would to an investor involved in similar activities and in a similar lawsuit from another state in the United States or from another location in Mississippi itself. We agree also with Professor Bilder when he says that Article 1102 is direct [sic] only to nationality-based discrimination and that it proscribes only demonstrable and significant indications of bias and prejudice on the basis of nationality, of a nature and consequence likely to have affected the outcome of the trial.
In articulating the test of Article 1102 in reference to the specific facts of the case before it, the Loewen tribunal recognized not once, not twice, but three times, that the nationality of the foreign investor played a central role in assessing whether nationality-based discrimination can be found under Article 1102. Loewen - Award, ¶ 139, RA-22. 468 Claimant’s Memorial, ¶¶ 663, 668. 469 Claimant’s Memorial, ¶ 668.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
112
● The Claimant was “singled out” for “unique and peculiar treatment,”subjecting it to “a different and harsher regulatory standard,” applying a“more restrictive regulatory method[] than other like entities,” and providing“no reasons for administering such differential treatment.”471
● “BC Hydro simply chose to exercise its discretion in ways less favourable toCelgar than it did with others.”472
The Claimant’s pleadings are replete with accusations of intent, directed primarily 243.
at BC Hydro who allegedly “chose” to treat the Claimant less favourably because other
mills had “political connections” and it was able to exercise “unfettered discretion.”
Although these arguments in themselves make little sense (commercially or otherwise),
they are arguments of discriminatory intent, which the Claimant must support with
evidence (it does not).
Second, the absence of evidence of discriminatory intent militates against a 244.
finding of nationality-based discrimination.473 The S.D. Myers tribunal recognized that,
while protectionist intent is “not necessarily decisive on its own”, it is “important”.474
The absence of such intent is thus an equally important factor for the Tribunal to consider
in determining whether the Claimant has suffered discrimination by reason of its
nationality.
470 Claimant’s Memorial, ¶ 669. 471 Claimant’s Memorial, ¶ 683. 472 Claimant’s Reply, ¶ 291. [Emphasis added] 473 Pope & Talbot – Merits Award, ¶¶ 87, 93, 103, RA-36. Similarly, the tribunal in Thunderbird stated that Article 1102 ““contemplates the case where a foreign investor is treated less favourably than a national investor. That case is to be proven by a foreign investor, and, additionally, the reason why there was a less favourable treatment.” International Thunderbird Gaming Corp. v. United Mexican States (UNCITRAL) Final Award, 26 January 2006 (“Thunderbird – Award”), ¶ 177, RA-42 (emphasis added). The Loewen tribunal also expressly stated that NAFTA Article 1102 requires less favourable treatment by reason of the claimant’s nationality: Loewen – Award, ¶ 139, RA-22. See also Apotex – Award, ¶ 8.56, RA-54; Methanex – Award, Part IV, Ch. B, ¶ 12, RA-28; Cargill – Award, ¶ 220, RA-6. In finding that Mexico had breachedits obligations under Article 1102, the Cargill Tribunal explicitly noted “that the discrimination was based on nationality both in intent and effect.” Cargill – Award, ¶ 220, RA-6. See also Corn Products – Decision on Responsibility, ¶ 118, CA-5: “there is a close relationship between whether the State intentionally discriminated on grounds of nationality and the test of like circumstances.” 474 S.D. Myers – Award, ¶ 254, RA-38.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
113
Third, evidence that other U.S. investors were accorded the same treatment as 245.
domestic or third Party investors is evidence against a finding of nationality-based
discrimination. The Claimant does not deny that Domtar (a U.S. based company) was
accorded identical treatment to Howe Sound and Tembec, but quips that “Canada does
not acquire license to discriminate against some U.S. investors by treating one…
American company favorably.”475 This identical treatment, however, provides further
evidence that the measures the Claimant complains of have nothing to do with
nationality-based discrimination.
Finally, where there is evidence that affirms rational government action and no 246.
evidence of any nationality-based preferences, then a claim under NAFTA Articles 1102
and 1103 must be dismissed.
3. An Allegedly Illegitimate Governmental Objective is Not anIndependent Ground for Liability under Article 1102 or 1103
Canada agrees that an analysis of governmental policy objectives may be 247.
instructive when determining whether two investments were accorded treatment in like
circumstances.476 For example, it may be appropriate to consider the government policies
that provide the context for Tembec’s 1997 EPA with the policies motivating BC
Hydro’s acquisition of resources under BC’s 2007 Energy Plan to determine whether
treatment accorded under the former is really “in like circumstances” with treatment
accorded under the latter. Similarly, a measure that results in a difference in treatment
that is explained by non-discriminatory reasons, including underlying factual
circumstances or a rational government objective – to which international law generally
475 Claimant’s Reply, ¶ 152. 476 See Cargill - Award, RA-6, ¶ 206 (“Thus, in both GAMI and Pope & Talbot, ‘like circumstances’ was determined by reference to the rationale for the measure that was being challenged. It was not a determination of ‘like circumstances’ in the abstract. The distinction between those affected by the measure and those who were not affected by the measure could be understood in light of the rationale for the measure and its policy objective.” The tribunal found in that case that there that there was no link between the alleged difference - a difference in economic circumstances - and the rationale and objective of the measure in question (¶ 209)). See also GAMI - Award, RA-14; Pope & Talbot - Award, RA-36.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
114
extends a “high measure of deference”477 – will not amount to a breach of Articles 1102
or 1103.478
That is not, however, the Claimant’s approach to government policy under 248.
NAFTA Articles 1102 and 1103. The Claimant argues that even with a uniform non-
discriminatory application of a measure to all investments, Canada nonetheless bears the
onus of proving that the measure “bear[s] a reasonable nexus to rational government
policies”479 and that the measure “could not be achieved by non-discriminatory
means.”480 The Claimant states:
In sum, even if the Tribunal were to conclude that the challenged measures were not discriminatory because BC consistently applied a uniform access standard to all self-generators in the Province, the resulting discriminatory impact cannot be
477 See S.D. Myers – Partial Award, ¶ 263 RA-38 (“…That determination must be made in the light of the high measure of deference that international law generally extends to the right of domestic authorities to regulate matters within their own borders.”) 478 Pope & Talbot - Award, RA-36, ¶ 78 (“Differences in treatment will presumptively violate Article 1102(2), unless they have a reasonable nexus to rational government policies that (1) do not distinguish, on their face or de facto, between foreign-owned and domestic companies, and (2) do not otherwise unduly undermine the investment liberalizing objectives of NAFTA.”); GAMI - Award, RA-14, ¶ 114 (“The arbitrators are satisfied that a reason exists for the measure which was not itself discriminatory. That measure was plausibly connected with a legitimate goal of policy (ensuring that the sugar industry was in the hands of solvent enterprises and was applied neither in a discriminatory manner nor as a disguised barrier to equal opportunity.”); Cargill - Award, ¶ 206, RA-6 (“Thus, in both GAMI and Pope & Talbot, ‘like circumstances’ was determined by reference to the rationale for the measure that was being challenged. It was not a determination of ‘like circumstances’ in the abstract.”). See also Parkerings - Award, ¶ 371, CA-12 (“The two investors must be treated differently. The difference of treatment must be due to a measure taken by the State. No policy or purpose behind the said measure must apply to the treatment that justifies the different treatments accorded. A contrario, a less favourable treatment is acceptable if a State’s legitimate objective justifies such a different treatment in relation to the specificity of the investment.”); UPS – Award, ¶ 102, RA-46 (listing the “principal factors [such as greater security, time-sensitivity, and the presence of contractual relationships] which demonstrate to the satisfaction of the Tribunal that Customs treatment of international mail is not “in like circumstances” with the treatment accorded to UPS”). Corn Products – Decision on Responsibility, ¶ 118, CA-5 (the Tribunal “must be sensitive to the particular circumstances of each case…it is necessary to consider the entire factual and legal context”). 479 Claimant’s Reply, ¶ 162. 480 Claimant’s Reply, ¶ 210.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
115
justified because BC’s approach failed to serve any legitimate governmental objective that could not have been achieved by non-discriminatory means.481
The Claimant grossly over-extends the role of Articles 1102 and 1103. If a 249.
measure has been found to be “not discriminatory” then there has been no breach of
National Treatment or Most-Favoured Nation Treatment, and the analysis ends there.482
The door does not open to a claimant to attack government policy as being “illegitimate”
and proclaim its own views on what other non-discriminatory means the government
might have chosen in its place to better match the Claimant’s preferences.
Moreover, it is difficult to reconcile the Claimant’s new approach to Articles 1102 250.
and 1103 with its past statements that the “NAFTA does not require the Province to adopt
any particular policy course;”483 or that the “NAFTA does not dictate any particular set of
policy choices for the Province.”484 Canada agrees. States have broad discretion in
choosing when and how to regulate, and the standard for assessing a state’s reasons for
acting, or not acting, is not an exacting one.485 It is not the purview of Articles 1102 and
1103 to attack the legitimacy of a policy objective underlying a non-discriminatory
481 Claimant’s Reply, ¶ 183. 482 See Thunderbird - Award, RA-42, ¶ 182 (“It thus appears from the facts of the case that SEGOB’s policy and actions in enforcing the Ley Federal de Juegos y Sorteos were directed at both Mexican and non-Mexican gambling operations and that they were overall consistent. Accordingly, the Tribunal finds that Thunderbird has not established a breach of the ‘National Treatment’ standard under Article 1102 of the NAFTA.”); AES - Award, CA-2, ¶ 10.3.50 (“The Tribunal thus concludes that neither its low capacity fees, nor its high energy fees suggest discrimination. Both were the logical result of a uniform methodology that was applied equally to all generators, based on their differing assets and operating cost structures.”); Electrabel - Award, RA-12, ¶ 7.153-7.154 (though decided under the Energy Charter Treaty’s non-impairment clause, the principle remains the same: consistent treatment that results in different outcomes does not constitute discrimination “…In short, all Generators were ‘asked’ to adjust their prices in similar terms; and the difference in their adjusted capacity fees reflected only the differences in profit level amongst different Generators. Accordingly, the Tribunal concludes that Electrabel’s allegations have not met the burden of proof required for a measure to be discriminatory in its impairment of an investment under Article 10(1) ECT.”) 483 Claimant’s Memorial, ¶ 186. 484 Request for Arbitration, ¶ 41; Notice of Intent, ¶ 36. 485 See S.D. Myers – Partial Award, ¶ 263, RA-38 (“…That determination must be made in the light of the high measure of deference that international law generally extends to the right of domestic authorities to regulate matters within their own borders.”)
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
116
measure. Nor is it the purview of this NAFTA tribunal to sit retrospectively in judgment
against BC’s procurement policies.486 In asking the Tribunal to do so, the Claimant
fundamentally overreaches.
C. The GBL Setting Methodology Applied by BC Hydro To The Claimant Under The 2007 Energy Plan Was Consistent With NAFTA Articles 1102 and 1103
The Claimant argues that Celgar’s GBL was set in a discriminatory manner, and 251.
that, had BC Hydro not exercised its discretion in a discriminatory manner, Celgar’s GBL
would be lower. The allegation, foreshadows, its claim for damages where the Claimant
asserts that it is entitled to damages equivalent to the price BC Hydro would have paid to
procure the electricity. The Claimant’s GBL claim is thus that BC Hydro was required to
procure more electricity from the Claimant under its EPA. As explained above, these
claims are inadmissible under the Article 1108(7)(a) procurement exception. However,
even if these claims are admissible, they nonetheless have no merit.
The Claimant launches a three-pronged attack against the GBL methodology BC 252.
Hydro employed pursuant to the 2007 Energy Plan when setting GBLs for the Celgar,
Tembec and Howe Sound EPAs.
First, the Claimant argues that BC Hydro employed no methodology when it set 253.
GBLs, alleging instead that BC Hydro had unfettered discretion, which it exercised on an
ad hoc and discriminatory basis.487
486 Electrabel – Award, ¶ 8.35, RA-12. (“Further, the Tribunal’s task is not here to sit retrospectively in judgment upon Hungary’s discretionary exercise of a sovereign power, not made irrationally and not exercised in bad faith towards Dunamenti at the relevant time.”); GAMI - Award, ¶ 114, RA- 13. The GAMI tribunal also recognized this principle and deferred to Mexico’s policy choices. AES – Award, ¶ 10.3.34, CA-2. Pope & Talbot – Merits Award, ¶ 93, 102, RA-36. The Tribunal in S.D. Myers also stressed that “the high measure of deference that international law generally extends to the right of domestic authorities to regulate matters within their own borders” applies within the NAFTA context. S.D. Myers – First Partial Award, ¶ 263, RA-38. See also Compton (Chemtura) Corp. v. Government of Canada (UNCITRAL), Award, 2 August 2010, ¶ 134, RA-55. 487 Claimant’s Reply, ¶ 513. The Claimant contrasts the wrongful act under this prong (i.e., “the existence
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
117
Second, the Claimant argues that if BC Hydro did employ a GBL methodology 254.
that it applied it inconsistently to Celgar in comparison to Tembec and Howe Sound.
Specifically, the Claimant alleges that BC Hydro improperly applied its GBL
methodology to Celgar by: (1) using a formula for calculating load rather than self-
generation applied to load; (2) using an inappropriate baseline year; and (3) failing to
evaluate the “economics” of Celgar’s below-load self-generation.488
Finally, the Claimant argues that if BC Hydro did employ a GBL methodology 255.
when it set GBLs for Celgar, Tembec and Howe Sound, and that it did so consistently, it
nonetheless resulted in a “discriminatory impact” that is inconsistent with Articles 1102
and 1103 because “BC’s approach failed to serve any legitimate governmental objective
that could not have been achieved by non-discriminatory means.”489
The Claimant’s arguments have no merit. The evidence demonstrates that BC 256.
Hydro did in fact apply a consistent, principled GBL methodology when setting GBLs for
its EPAs. The Claimant’s argument to the contrary is illogical in the light of the 2007
Energy Policy and BC Hydro’s commercial interest in procuring electricity. Moreover,
whatever self-proclaimed “discriminatory impact” the Claimant may feel it has suffered,
the procurement of incremental energy serves a legitimate governmental purpose.
To the extent the Tribunal concludes there were differences in treatment between 257.
the mills (e.g., the use of a 2007 baseline for Celgar rather than the
used for Howe Sound), these differences relate to the specific outcomes of the
application of the GBL methodology to each mill, and are explained by the unique
of differential impacts”) against the wrongful act in the other two prongs (i.e. the failure to apply an applicable standard), and contends that, in order to avoid a breach of Articles 1102 or 1103 in the no methodology scenario, BC Hydro was required to set a GBL for Celgar based on the best “Arbitrage Percentage” allocated to another mill: Claimant’s Reply, ¶¶ 212-213. 488 Claimant’s Reply, ¶¶ 362-405. 489 Claimant’s Reply, ¶ 183.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
118
circumstances. As such, they do not amount to a violation of National Treatment or Most-
Favoured Nation Treatment.
1. BC Hydro Applied a GBL Methodology that the ClaimantUnderstood
As Canada explained in its Counter-Memorial, BC’s 2007 Energy Plan reflected 258.
the Government’s objectives of addressing climate change by relying increasingly on
clean and renewable energy, and of making BC Hydro energy self-sufficient.490 BC
Hydro accordingly set out to procure clean electricity from self-generators in the private
sector to help increase its supply.
BC Hydro developed the parameters for the Bioenergy Call to increase its 259.
resources in accordance with the 2007 Energy Plan, in consultation with proponents, the
Ministry of Energy, and the Ministry of Forests. It determined that only “incremental”
generation would be eligible for the Bioenergy Call.491 Projects including “existing”
electricity would not increase BC Hydro’s resource pool, and would, in effect, transfer
money from BC Hydro to the Seller without receiving anything in return.
BC Hydro thus had to devise a method to delineate “existing” from “incremental” 260.
electricity. To that end, BC Hydro held internal consultations in early February 2008 to
draw on expertise from several departments to develop an appropriate mechanism for
setting GBLs.492 BC Hydro relied on the principles of BCUC Order G-38-01 and built on
the precedents that BC Hydro had completed for earlier procurement processes, including
the 2002 Customer-Based Generation program.493 As set out above, the main guiding
490 Les MacLaren Statement I, ¶ 76-77; Les MacLaren Statement II, ¶¶ 4-6. Canada previously described the goals and objectives of the 2007 Energy Plan at ¶¶ 137-143 of Canada’s Counter-Memorial. 491 Jim Scouras Statement I, ¶ 37-38. 492 Lester Dyck Statement I, ¶¶ 54-55. See also Email from David Keir to Alex Adams, Lester Dyck re: RE: BioeEnergy Call | Use of GBL and its implication on CBL’s, dated February 12, 2008, R-171. 493 See Lester Dyck Statement I, ¶¶ 54-55. See also Email from David Keir, to Lester Dyck et al re: RE: Review detailed design of GBL concept for interaction with TSR for customer and Power Smart program implications | Meeting Minutes, dated February 15, 2008, R-172.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
119
principle was that a GBL “defines incremental/surplus/excess TG output that can be
considered for a prospective energy sale.”494 Mr. Dyck explains the factors BC Hydro
considered on a consistent basis when setting GBLs in order to define “incremental”
energy:
To set an appropriate GBL for an EPA…with a self-generating customer, BC Hydro and the customer review the best available information at the time of the power procurement process, including the customer’s historical self-generation output, energy consumption data, and information relating to the customer’s unique manufacturing operations. The goal is to define the amount of annual self-generated energy normally used by the customer to self-supply under current conditions without the prospect of the currently negotiated EPA…When setting a GBL, BC Hydro also accounts for any existing contractual obligations the customer may have that might affect its historical self-generation output.495
In its Reply, the Claimant alleges that BC Hydro employed no methodology when 261.
it set GBLs for the different mills.496 It argues that the GBL setting process lacked
“procedures of any kind, featuring instead ad hoc discretionary determinations,”497 and
that BC Hydro had “unfettered discretion in establishing GBLs for individual self-
generators,”498 and that it “simply chose to exercise its discretion in ways less favorable
to Celgar than it did with others.”499 It alleges that “there were no rules.”500 Or, that if
494 See Email from David Keir, to Lester Dyck et al re: RE: Review detailed design of GBL concept for interaction with TSR for customer and Power Smart program implications | Meeting Minutes, dated February 15, 2008 at 026774, R-172. 495 Lester Dyck Statement I, ¶¶ 44-45. See also Email from David Keir, to Lester Dyck et al re: RE: Review detailed design of GBL concept for interaction with TSR for customer and Power Smart program implications | Meeting Minutes, dated February 15, 2008 at 026774, R-172. 496 Claimant’s Reply, ¶ 212 (“BC [Hydro] had no consistently applied ‘current normal’ standard, but instead it made a series of ad hoc discretionary determinations in which it treated Celgar less favorably than its comparators in setting Celgar’s self-supply obligation.”). 497 Claimant’s Reply, ¶ 212. 498 Claimant Reply, ¶ 467. 499 Claimant’s Reply, ¶ 291. 500 Claimant’s Reply, ¶ 513.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
120
there were rules, that BC Hydro kept them “secret.”501 The Claimant is mistaken on all
counts.
First, to suggest that BC Hydro had “unfettered discretion” defies both evidence 262.
and logic. It is evident that BC Hydro was provided with a mandate to increase its
resource pool with clean energy and initiated procurement processes to incentivize
incremental electricity from self-generators. If there were no rules, then BC Hydro would
have had absolute discretion to procure any electricity, even “existing” electricity and the
entire concept of a GBL would be irrelevant. However, not only would the procurement
of such electricity run afoul of the 2007 Energy Plan, it would also likely be rejected by
the BCUC as contrary to public interest.502
Moreover, the Claimant’s argument ignores that the setting of GBLs involves two 263.
parties. As Mr. Bursey sets out in his expert report, “The agreed baselines were not
arbitrary; they were negotiated”503 by sophisticated technical and commercial parties. In
addition, as Mr. Bursey further observes, “If BC Hydro had sought to impose an arbitrary
unilateral baseline, then the customer had recourse to the BCUC.” 504
Second, the Claimant’s argument that BC Hydro “simply chose” to exercise its 264.
discretion in ways less favourable to Celgar flouts reason. BC Hydro issued the
Bioenergy Call with the aim of procuring approximately 1,000 GWh/year of electricity505
501 Claimant’s Reply, ¶ 524. The Claimant’s argument that BC Hydro kept the factors it considered “a secret” is nonsensical. Of what benefit would that be to BC Hydro? The Claimant cannot argue that BC Hydro wanted to maintain “unequal bargaining power”, because that would be an allegation that BC Hydro intentionally set out to discriminate against mills, a claim the Claimant bears the onus of proving and for which there is no evidence. 502 See Les MacLaren Statement II, ¶¶ 9, 20. See also David Bursey Expert Report, ¶¶ 34 and 135(d)(ii)(c). 503 Bursey Expert Report, ¶ 77 (emphasis added). Mr. Bursey also opines that “It is good regulatory practice, and certainly the practice in British Columbia, for the BCUC to allow BC Hydro and its industrial customers the first opportunity to work out technical bilateral issues, like setting a customer GBL. Both parties have a sophisticated technical understanding of the power consumption at the industrial site.” Bursey Expert Report, ¶ 123. 504 David Bursey Expert Report, ¶ 78. 505 Bioenergy Phase I - RFP, R-25. See also Jim Scouras Statement I, ¶ 38.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
121
and had a vested interest in meeting this target. However, BC Hydro could only procure
incremental electricity, not existing electricity, and in the end, the Bioenergy Call
resulted in only four EPAs that contributed only 579 GWh/year. BC Hydro thus did not
meet its objective. In this context, the Claimant’s argument that BC Hydro “simply
chose” to set a discriminatory 40 MW GBL makes no sense. If the Claimant had
additional incremental electricity to sell, BC Hydro would have been willing to procure it
within the parameters of the Call.
Third, the evidence demonstrates that BC Hydro was anything but “secretive.” 265.
Indeed, BC Hydro provided information to proponents concerning its GBL methodology
in several different ways, including in the GBL Registration Form,506 information
sessions and workshops,507 and in one-on-one meetings and phone calls with
proponents.508 BC Hydro met with Celgar representatives on April 2, 2008 to discuss
their proposed projects. At that meeting, Mr. Dyck offered to act as “Celgar’s unofficial
account manager, giving Celgar a direct channel to resolve and/or clarify issues” as the
process continued to unfold.509 Mr. Merwin and Mr. Dyck subsequently had numerous
506 See Lester Dyck Statement I, ¶¶ 55-56; BC Hydro Bioenergy Call for Power – Phase I, Addendum I, 26 February 2008 at 5, R-113. See also Section II.A.3.b. 507 See Mr. Dyck explained that the “initial customers’ ‘estimated GBLs’ should reflect a 365 day annual period”, and that the 2005 CBL establishment would be the starting point for GBL discussions, but that adjustments might need to be made for a mill’s unique circumstances – for example, “existing LD contracts, EPAs, market sales, 1880/adhoc purchases etc.”: BC Hydro’s Bioenergy Call, Kamloops, BC, February 20, 2008 Presentation at 22, R-116; Bioenergy Call Phase I, Proponent Information Session, March 26, 2008 at 63, R-117; Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008 at 064463, R-173. 508 See Bioenergy Call Phase I, Proponent Information Session, March 26, 2008 at 63, R-117; Lester Dyck Statement II, ¶ 8. This was a logical way of understanding “the unique attributes of each customer situation.” As BC Hydro understood, the mill operators “know [their] operations best. Help us to understand the unique operational conditions that are imbedded within your annual GBL, such that we can collectively review and understand any specific elements that may be open to refinement.” See Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008 at 064463, R-173. 509 Memo from Adrian Hay to Brian Merwin, April 2nd RFP meeting with BC Hydro, 2 April 2008, MER00027734, R-557. See also Lester Dyck Statement I, ¶ 91.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
122
phone calls to discuss operations at the mill, and to arrive at a GBL that represented
normal operating conditions.510
BC Hydro provided ample opportunity for proponents to seek clarification on any 266.
points that they were uncertain about.511 And the Claimant did seek clarification. For
example, a Celgar representative asked BC Hydro at the GBL break out session on March
26, 2008 whether a GBL would be set for a non-BC Hydro customer. BC Hydro
answered yes, and proceeded to explain the principles and factors BC Hydro would
consider in setting such GBLs.512
BC Hydro also made it clear in every instance that the GBL methodology was a 267.
flexible one that was designed to account for the unique operating circumstances of each
mill, so as to reflect what BC Hydro could consider procuring from each under the terms
of the RFP.513 In stark contrast to the Claimant’s current allegations about the insufficient
objectivity of BC Hydro’s GBL methodology,514 the Claimant lauded BC Hydro’s
flexible approach before the BCUC, arguing that “GBLs are not to be determined by any
510 Lester Dyck Statement I, ¶¶ 81-82; Lester Dyck Statement II, ¶¶ 9, 19-30. 511 For example, the GBL Registration Form provided proponents with the option to “attach additional pages” in order to add explanatory information: BC Hydro Bioenergy Call for Power – Phase I, Addendum I, 26 February 2008 at 5, R-113. The Claimant did not provide additional information. Moreover, the attendees at the GBL break-out session held the afternoon of March 26, 2008 discussed the fact that different operational changes affected generation levels differently, and factors such as changes in steam flows, product changes, and weather could affect generation levels: Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008 at 064464, R-173. 512 Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008 at 064463, R-173. 513 See Lester Dyck Statement I, ¶¶ 55, 58; BC Hydro Bioenergy Call for Power – Phase I, Addendum I, 26 February 2008 at 5, R-113; BC Hydro’s Bioenergy Call, Kamloops, BC, February 20, 2008 Presentation at 22, R-116; Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008 at 064463, R-173. 514 Claimant’s Reply, ¶ 283 (“BC Hydro employed “a high-level principle that requires more detailed, refined, substantive guidelines, before it is capable of serving as a standard that can be meaningfully and consistently applied.”); ¶ 286 (The GBL methodology “is too general to ensure that similar conditions are treated by BC Hydro similarly.”).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
123
set formula”,515 and that a “GBL should be made in consideration of the unique customer
circumstances.”516
Fourth, contrary to its argument that “no applicant had a clear understanding of 268.
what data or argument to present to BC Hydro to obtain its lowest possible GBL, because
no one knew what factors BC Hydro would consider,”517 the Claimant did not seem to
have any trouble in May 2008 devising a GBL that would be “as low as credible.”518 If
the Claimant did not believe that BC Hydro had a methodology for setting GBLs, it
would presumably have proposed a GBL of zero. Instead, Celgar’s internal position was
to “build a case” for a GBL of 33 MW,519 which would “reflect conditions prior to
Mercer’s energy investments.” 520
Indeed, Celgar’s proposed GBL of 33 MW demonstrates its understanding of the 269.
factors BC Hydro considered to set GBLs. The proposal was made on the basis of a 365-
day period, demonstrating its understanding that BC Hydro considered a 365-day period
of normal generation.521 Moreover, the Claimant clearly understood that a GBL should
represent what a mill normally generates without an incentive. Celgar’s proposed GBL of
515 Celgar, Evidence Submission, in the Matter of an Application by FortisBC for Approval of a 2009 Rate Design and Cost of Service Analysis, 15 March 2010, pp. 2 and 3, R-280. 516 Celgar, Response to BCUC Information Request No. 1, in the Matter of an Application by FortisBC for Approval of a 2009 Rate Design and Cost of Service Analysis, 15 April 2010, Q 6.1, pp. 16-17, R-372. 517 Claimant’s Reply, ¶ 272. 518 Email from Jim McLaren to Brian Merwin re: Phase I Request for Proposals: Notice to Customers of GBL, 4 May 2008, MER00064460, R-534. 519 Draft Letter from Brian Merwin to RFP Administrator, Re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project and Celgar Green Energy Project, 4 May 2008, (Jim McLaren track changes) at MER00064462, MER00064462, R-534. ( “Brian – we want to build the case that the existing TG will be base loaded to match your defined historical GBL of 33 MW…” The letter also describes that “[O]ur existing generation has been serving an industrial load at our discretion”, at MER00064463.) ] 520 Email from Jim McLaren to Brian Merwin re: Phase I Request for Proposals: Notice to Customers of GBL, 4 May 2008, MER00064460, R-534. 521 As Mr. Dyck comments, “If, as [Mr. Merwin] now says, BC Hydro gave him the impression that it would use an average of three years’ data to set GBLs for proponents, I expect that Mr. Merwin would have proposed a GBL on that basis at the time.” Lester Dyck Statement II, ¶ 14.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
124
33 MW was based on the total gross generation of the mill in 2006, adjusted for excess
natural gas used to generate electricity in excess of the mill’s needs.522 As Mr. Dyck
observes, this proposal “reflects Mr. Merwin’s position of ‘normal’ operations for the
mill during that time frame.”523
Finally, to claim now that Celgar had no way of knowing what information to 270.
provide to BC Hydro is disingenuous. If, as he says now, Mr. Merwin really did not
understand what BC Hydro meant by “normal operations” when he was negotiating the
GBL for Celgar’s EPA,524 he simply could have asked. Mr. Dyck made himself more
than available to Mr. Merwin but, as Mr. Dyck recalls, “In all of my conversations with
Mr. Merwin – and there were many of them during the GBL setting process – he never
once raised any concerns about the meaning of ‘normal’ operations’.”525 Mr. Dyck
believes that this is because Mr. Merwin “understood that the purpose and the principle
of GBLs in the context of BC Hydro’s Bio Phase I process is to identify the mill’s
‘normal’ generation that BC Hydro will not incentivize in the EPA.”526
522 Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) - Biomass Realization Project and Celgar Green Energy Project, dated May 7, 2008, at 5, R-127. Canada notes that in 2007, Celgar’s sales were not made by firing incremental natural gas. Rather, they were primarily the product of the mill’s burning the increased levels of black liquor available following the Blue Goose improvements to pulp production. See Pöyry Expert Report II, ¶¶ 66-78. 523 See Lester Dyck Statement II, ¶ 12. Other internal communications further demonstrate that the Claimant understood that existing sales commitments would be considered by BC Hydro. See Email from Jim McLaren to Brian Merwin, Re: Sale of STG#2 and future STG# Electricity Output, 30 October 2007, R-357 (“[c]reating an historical practice of selling 28 MW of output from STG#2 into the USA before entering the future BC Hydro call next spring has merit.”); and Memo from Adrian Hay to Brian Merwin, April 2nd RFP meeting with BC Hydro, 2 April 2008, MER00027734, R-557 (“From Celgar’s perspective, the lack of existing power obligations means that its GBL is zero and so it should be able to sell all of its generation to BC Hydro.”). 524 Brian Merwin Statement II, ¶¶ 15-19. 525 Lester Dyck Statement II, ¶ 21. 526 Lester Dyck Statement II, ¶ 10.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
125
2. BC Hydro’s GBL Methodology is Reasonably Related toLegitimate Policy Objectives
The Claimant in its Reply now argues that even if BC Hydro did employ a GBL 271.
methodology and even if it employed that methodology consistently to all mills, Canada
nonetheless bears the onus of proving that the methodology has “a reasonable nexus to
rational government policies”527 and that the aims of the policy “could not be achieved by
non-discriminatory means.”528 The Claimant states:
[E]ven if the Tribunal were to conclude that the challenged measures were not discriminatory because BC consistently applied a uniform access standard to all self-generators in the Province, the resulting discriminatory impact cannot be justified because BC’s approach failed to serve any legitimate governmental objective that could not have been achieved by non-discriminatory means.529
Canada has already explained it has the right to regulate matters within its own 272.
borders that its choices in this regard are owed a “high measure of deference,”530 and that
it is not the purview of a NAFTA tribunal to second-guess the non-discriminatory policy
choices of governments. Canada will nonetheless respond to the Claimant’s allegation
that BC Hydro’s GBL methodology does not accord with legitimate government policy.
The Claimant articulates five criticisms. First, it argues that BC Hydro’s GBL 273.
methodology negates the policy objectives of Order G-38-01 by “depart[ing] from the
BCUC’s historical usage standard.”531 However, BC Hydro’s procurement policies exist
527 Claimant’s Reply, ¶ 162. 528 Claimant’s Reply, ¶ 210. 529 Claimant’s Reply, ¶ 183. 530 S.D. Myers – Partial Award, ¶ 263, R-38. 531 Claimant’s Reply, ¶¶ 310-314. The Claimant also fundamentally mischaracterizes Order G-38-01. See Section II.A.1; Bursey Expert Report, ¶¶ 75 (“BCUC Order G-38-01 was not intended to be a comprehensive review of the issues related to self-generators selling power while being supplied by utility service. It set a basic framework for the interested parties to attempt to develop this opportunity, with the BCUC retaining the authority to supervise the program and the resulting outcomes and then adapt its regulatory approach.”).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
126
to meet different policy objectives than those raised by G-38-01.532 As Mr. Dyck
explains, the situation confronting the BCUC in the proceedings leading to Order G-38-
01 “is not tied to procurement by BC Hydro at all.”533 Nor does BC Hydro’s GBL
methodology in any event “negate” G-38-01, as both prevent harmful arbitrage at the
expense of ratepayers.
Second, the Claimant alleges that the GBL methodology does not achieve its 274.
“incentivizing” objective, which could be achieved without restricting third party sales.
The Claimant, however, consistently conflates BC Hydro’s GBL methodology with the
exclusivity clause of its EPA with BC Hydro, which purportedly restricts the sale of
below-GBL electricity to third parties. For example, the Claimant argues that BC
Hydro’s GBL methodology was “completely inappropriate to determine the total amount
of power a self-generator could sell to a third party argument, to implement the non-
procurement related purpose of Order G-38-01.”534 Similarly, the Claimant argues that
BC Hydro’s pursuit of “’incentiviz[ing]’ ‘new or incremental’ generation and ‘idle’
generation, but not existing self-generation already on its system that did not require
incentives”535 does not serve a legitimate purpose because BC Hydro could have
incentivized incremental generation without restricting third party sales.536
532 Claimant’s Reply, ¶ 313 (“Canada’s proffering of this ‘limiting BC Hydro incentives’ rationale proves that the ‘current normal’ standard differs from the ‘historical usage’ standard. Such a rationale was never even suggested at the time of Order G-38-01, and is nowhere embodied in that Order. Indeed, the ‘limiting BC Hydro incentives’ rationale is exclusively a BC Hydro procurement-related policy, and Order G-38-01 and the self-generator policy it embodies had nothing whatsoever to do with BC Hydro procurement much less limiting the volumes of biomass-based green energy BC Hydro would have to purchase form [sic] self-generators. The policy was developed originally to enable Howe Sound to sell its idle generation not to BC Hydro but into the California market.”) 533 Lester Dyck Statement II, ¶ 6. 534 Claimant’s Reply, ¶ 26 (emphasis in original). 535 Claimant’s Reply, ¶ 163. 536 Claimant’s Reply, ¶ 168; Fox-Penner Expert Report, ¶ 111 (“BC and BC Hydro could have subsidized new and incremental generation all they wanted, without restricting Celgar’s ability to sell its self-generated electricity. The restrictions thus cannot be justified by the incentivization policy alone.”).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
127
As explained in Section II.C.4, BC Hydro did not, in fact, restrict the Claimant’s 275.
ability to sell its below-GBL electricity, rendering the Claimant’s criticism of this policy
objective moot. However, even if the exclusivity provision in Celgar’s EPA had restricted
its ability to sell below-GBL electricity, such a restriction is reasonably related to the
procurement of incremental generation as it provides BC Hydro with the certainty that it
will receive the benefit of the EPA.537
Third, the Claimant argues that the policy goal of avoiding harmful arbitrage set 276.
out in Order G-38-01 is “motivated by BC Hydro protecting its profits/and or its rates at
the expense of a more equitable and more economically efficient self-generator sales
policy.”538 This argument is, however, misplaced. The Claimant portends that the BCUC
was confronted with, and decided on, “how to allocate the arbitrage profit that could be
earned by selling electricity generated in BC at relatively low cost into higher-priced
export or domestic markets.”539 However, this is not how either the BCUC approached
the issue it faced in G-38-01, or the manner in which BC Hydro pursues the cost-effective
procurement of incremental generation. Therefore, as Dr. Rosenzweig describes,
“arbitrage allocation” is “only a distraction from the true regulatory issue: the efficient
procurement of incremental generation resources that does not result in harmful
arbitrage,”540 and should be dismissed.
Fourth, the Claimant’s argues that “the restrictions imposed upon Celgar cannot 277.
be justified by BC’s goal of achieving energy security” 541 but ignores that BC Hydro did
537 Jim Scouras Statement II, ¶¶ 8-10. 538 Claimant’s Reply, ¶ 173; Fox-Penner Expert Report, ¶ 40. 539 Claimant’s Reply, ¶ 173; Fox-Penner Expert Report, ¶ 32. 540 NERA Expert Report II, ¶ 56 (“The allocation of arbitrage profits were not even an issue (directly or indirectly) before the BCUC, for the BC Government, or for BCH – this entire concept was devised by Dr. Fox-Penner. I am not aware of any BCUC proceeding (or BCH or BC document) that considers arbitrage from this perspective. As discussed, the objective and economics of BCH’s process were to increase generation capacity cost effectively (at a cost less than BCH’s other procurement options), in order to provide safe, reliable, and ‘clean’ power. …”) 541 Claimant’s Reply, ¶ 169; Fox-Penner, ¶ 112.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
128
not restrict the Claimant’s ability to sell below-GBL electricity to third parties. Moreover,
the Claimant’s argument ignores that the province is “neutral as to where a purchaser of
Celgar’s electricity resides. Whether the electricity remains in BC or is exported out of
the province does not matter.”542
Finally, the Claimant’s argument that the GBL method is not legitimate policy 278.
because it “did not provide the greatest market access to the most efficient self-
generators, but instead awarded benefits and more favorable treatment to self-generators
with economically idle self-generation capacity, that, by definition, were less
efficient,”543 misses the point. The policy objective of the 2007 Energy Plan and of BC
Hydro’s GBL methodology was not to “award benefits” to mills, but to procure
incremental generation. Rather than increasing economic efficiency as an abstract
principle, BC Hydro was procuring additional resources in a cost effective manner.544 In
this light, BC Hydro’s GBL methodology was reasonably related to its procurement of
incremental electricity.545
For these reasons, the Claimant’s attempt to critique legitimate provincial 279.
procurement policies has no merit.
542 Les MacLaren Statement II, ¶ 16. 543 Claimant’s Reply, ¶ 172 544 See Les MacLaren Statement II, ¶ 8. See also NERA Expert Report II, ¶¶ 61-72. Moreover, in pursuing this argument, the Claimant also ignores that “market economics already rewards greater mill efficiency via increased profits.” NERA Expert Report II, ¶ 71. 545 See Canada’s Counter-Memorial, ¶ 366 (“Thus, while the EPA is designed to incentivize generation that would otherwise not have been economically viable for the contracting mills, the GBL is the gauge for the economic efficiency of the incentive. A n incentive that is too low (i.e. a GBL that is too high) would fail to bring about the desired additional generation, while too great of an incentive (i.e. a GBL that is too low) would fail to protect ratepayers.”). See also NERA Expert Report I, ¶ 49.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
129
3. The Claimant Has Failed to Show Less Favourable Treatment
The “Below-Load Access Percentage” is an Inappropriatea)Measure of Less Favourable Treatment
Canada explained in its Counter-Memorial that the Claimant’s “Below-Load 280.
Access Percentage” metric is an inappropriate measure of less favourable treatment
because it ignores the economic, regulatory, and mill-specific circumstances that were
integral and necessary considerations for the development and application of BC Hydro’s
GBL methodology.546
The Claimant’s expert states that he invented the metric “to measure the effect [he 281.
was] interested in measuring,”547 as if he had already concluded the existence of less
favourable treatment, then simply invented a metric to support his conclusion. The
Claimant nonetheless persists with its view that the Below-Load Access Percentage has
relevance, positing that “[i]t simply is a measurement tool for comparing one GBL to
another.”548
BC Hydro does not, however, set GBLs to regulate “access” to embedded cost 282.
electricity, but to determine how much incremental generation it will procure. Adopting
the Claimant’s approach would “completely undermine the policy objectives of the 2007
Energy Plan, which was to increase the resource portfolio of BC Hydro at cost-effective
prices, so as to meet new demand for electricity while ensuring that rate increases are as
low as reasonable.”549
For example, the Claimant alleges that it should have a GBL reflective of Howe 283.
Sound’s Below Load Access Percentage. Assuming Howe Sound has a Below-Load
546 Canada’s Counter-Memorial, ¶¶ 362-366; NERA Expert Report I, ¶¶ 59-61. 547 Switlishoff II, ¶ 15 548 Claimant’s Reply, ¶ 191. 549 Les MacLaren Statement II, ¶ 11.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
130
Access Percentage of 550 the Claimant argues that, in order to avoid
discrimination between the two mills, BC Hydro was required to set a GBL for Celgar
that reflects that same percentage. As the Claimant posits, such a GBL would be
GWh/year.551 However, none of the GWh/year difference
between Celgar’s current 349 GWh/year GBL and this GWh/year GBL
would be new or incremental electricity. It would be “existing” electricity that the
Claimant alleges BC Hydro ought to have procured contrary to the parameters of the
Bioenergy Call for Power.
Adopting the Claimant’s metric would undermine BC Hydro’s procurement 284.
activities and would simply transfer wealth to mills. As Mr. MacLaren explains, “[t]he
Claimant is in effect asking for a subsidy.”552
Moreover, the Claimant has more access to embedded cost power than any other 285.
mill in the Province. The BCUC has directed FortisBC to allow the Claimant to have
100% access to FortisBC’s embedded cost power while the Claimant sells to market.553
The Claimant Below-Load Access Percentage is, in fact, thus 100%, significantly higher
than Howe Sound or Tembec under their current EPAs. Thus, under the Claimant’s very
own metric, it has not received less favourable treatment, but more favourable treatment
than any other mill.
The Claimant Has Not Demonstrated the Absence of ab)Uniform Methodology
The Claimant argues that in order to prove the absence of a uniform GBL 286.
methodology, it need only show “that Celgar and at least one other comparator were
550 See, for example, Claimant’s Memorial, ¶ 698. 551 Claimant’s Memorial, ¶ 698, fn 776. 552 Les MacLaren Statement II, ¶ 13. 553 BCUC, Order G-202-12 and Decision, in the Matter of FortisBC Inc., Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), December 27, 2012,¶ 3 of the Order, p. 3 of Decision, R-265.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
131
treated inconsistently” under the GBL methodology.554 The Claimant thus contends that it
can attack the entire procurement process employed by BC Hydro after the 2007 Energy
Plan, which has resulted in GBLs for at least nine EPAs with various pulp and paper
mills, by focusing on only three (Celgar, Tembec, and Howe Sound) and ignoring the
rest. The Claimant is mistaken. If it wishes to prove that there was no uniform GBL
methodology employed by BC Hydro, then it must provide an analysis of more than just
a small sample of hand-picked mills.
At the Claimant’s request, Canada produced thousands of documents relating to 287.
the GBLs set for a dozen pulp and paper facilities and sawmills that have EPAs with BC
Hydro. The Claimant in turn confirms that it provided its experts with “full access to the
document database provided by Canada.”555 Yet, none of its experts provides any
analysis of the GBLs set for the other mills. Unlike the Claimant, Canada did have its
expert review a large volume of documents relating to other mills, and they confirm that,
in negotiating the GBL provisions in each EPA, BC Hydro consistently applied the same
methodology.556
The Claimant resorts to baseless accusations that Canada’s expert, Dr. 288.
Rosenzweig, is not “independent” but “simply reviewed what BC Hydro told him BC
Hydro did, based on data BC Hydro selected for his review, and then blessed the analysis
he was provided as reasonable.”557 As Dr. Rosenzweig explains, however, for each of the
twelve mills he analyzed, his review included at least the following steps:
I reviewed historical data for each mill, including historical generation, load,purchase and sales.
554 Claimant’s Reply, ¶¶ 212; 160, fn. 179. 555 Claimant’s Reply, ¶ 320. 556 See NERA Expert Report II, ¶¶ 37-39; NERA Expert Report I, ¶¶ 52-56, Appendix 2. 557 Claimant’s Reply, ¶ 301.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
132
I reviewed each mill’s EPA or … LDA with BCH (each of the 12 mills Ireviewed signed such an agreement during the 2009 to 2011 period). Ireviewed GBL, firm sales, or load displacement levels, including shaping (byseason, month, or hour) as well as whether these levels were adjusted basedon outages. I reviewed price terms and penalty terms as well as non-priceterms such as what triggered the beginning of firm energy sales under an EPA(often this was tied to a new or refurbished generation resource coming on-line).
I reviewed electricity-generation related contracts that the various mills hadentered into before their EPAs and LDAs referenced in the previous bulletpoint. I assessed the effect of these contracts on the mills generation and ontheir GBL determination, considering the potentially different effects ofwhether or not the agreement was canceled before the effective date of thenew EPA/LDA. If a contract was canceled, I assessed the terms of thecancelation from an economic-regulatory perspective.558
Similarly, the Claimant accuses Canada’s other expert, Mr. Stockard, of being 289.
“guided by BC Hydro”, and limited by BC Hydro’s data sources.559 But Mr. Stockard,
too, reviewed over 1,500 documents in the preparation of his reports.560 As Mr. Stockard
explains:
Not coincidentally, the majority of documents I requested and reviewed were provided by Canada. These documents encompassed material they had collected in the course of their document collection process as well as material filed by the Claimant as part of its Memorial and subsequently its Reply. These documents contained a wide range of information, including governmental policy directives, contractual agreements, technical discussions, business and process data, and internal and external communications between BC Hydro and the owners of the facilities currently being reviewed, spanning more than 15 years in some instances. In addition to these materials, Canada also provided witness statements for me to review to understand some of the key individuals’ actions supporting the GBL determination process for context.
…
558 See NERA Expert Report II, ¶¶ 38-40 for the other elements of Dr. Rosenzweig’s review. 559 Claimant’s Reply, ¶ 320. 560 Pöyry Expert Report II, ¶ 25.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
133
I have also utilized Poyry’s internal database generated from publicly available information to review the general configuration of these facilities and to understand major design differences between the mills.561
The serious allegations the Claimant makes concerning the independence of 290.
Canada’s experts is inappropriate. This is especially so when the Claimant has retained
experts with which it has a close business relationship562 and has not had these experts
undertake their own analysis. Indeed, the Claimant’s unfounded allegations in this respect
do not rebut the conclusions reached by Canada’s experts that BC Hydro had a GBL
methodology and that it applied the methodology consistently.
BC Hydro Consistently Applied its GBL Methodologyc)
The Claimant argues that if BC Hydro in fact had a GBL methodology, then it 291.
made an error when applying that methodology to Celgar and the less favourable
treatment is “the failure to apply to Celgar the standard [BC Hydro] applied to everyone
else.”563 The Claimant alleges that BC Hydro departed from its GBL methodology “by
(1) using load rather than generation-to-load as the basis for the GBL, (2) using 2007 and
not 2006 as a baseline year, and (3) not considering Celgar’s financial losses as a basis
for concluding that historical generation levels would not reflect current conditions going
forward.”564
The Claimant was not treated less favourably than other mills because BC Hydro 292.
applied its GBL methodology consistently to everyone, including Celgar. BC Hydro
worked with Celgar, as with Tembec and Howe Sound, to determine the amount of
561 Pöyry Expert Report II, ¶ 26. 562 Switlishoff Expert Report I, ¶¶ 13-14. Mr. Switlishoff has billed at least to Celgar over the course of a few years. 563 Claimant’s Reply, ¶ 211. 564 Claimant’s Reply, ¶ 405.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
134
energy the mills normally generated for self-supply, on an annual basis, as of the time of
the procurement process, in the absence of the prospective EPA.565
BC Hydro and Celgar exchanged numerous letters, emails, and phone calls in the 293.
period preceding May 30, 2008, when the GBL was set for the Celgar mill.566 Similarly,
BC Hydro communicated regularly with personnel at the Tembec567 and Howe Sound568
mills prior to the GBLs being set for their mills. In each case, BC Hydro sought input
from those who knew the mill’s operations best to determine what was “normal” for each
of those operations.569 As Mr. Fominoff, the General Manager, Fibre & Energy at Howe
Sound testifies, “BC Hydro wanted to know what Howe Sound generates in a normal
operating year, so that it could determine what electricity would be incremental and thus
eligible for purchase.”570
For each of Celgar, Tembec and Howe Sound, BC Hydro considered historical 294.
data sets in order to identify what was “normal” for the mill at the time of the
procurement process. For Celgar’s 2009 EPA, BC Hydro considered operational data
from 2002 to 2007, as submitted by Celgar.571 For Tembec’s 2009 EPA, BC Hydro
565 See Canada’s Counter-Memorial, ¶ 366; Lester Dyck Statement I, ¶¶ 44-45; Lester Dyck Statement II, ¶¶ 3-5. 566 See Lester Dyck Statement I, ¶¶ 68-83; Lester Dyck Statement II, ¶¶ 19, 21; Merwin Statement I, ¶¶ 81, 82, 85-88; Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project and Celgar Green Energy Project, dated May 7, 2008, R-127. 567 See Email from Chris Lague to Matt Steele re: Tembec Skookumchuck site GBL calculations, dated March 10, 2009, R-193; Email exchange between Chris Lague and Norman Wild, dated 23 March to 25 March 2009, R-526. 568 See Lester Dyck Statement I, ¶¶ 126, 127-131; Fred Fominoff Statement, ¶¶ 25-26, 30-37; email from Scott Janzen to Fred Fominoff re: GBL, dated June 24, 2010, R-70; Howe Sound Pulp and Paper LP, Generation Baseline Calculations, 1 August 2006 to 31 July 2009, R-66. 569 See Email from David Keir to Lester Dyck re: Summary of GBL Discussion – 26 March 2008, dated March 27, 2008 at 064463, R-173. 570 Fred Fominoff Statement, ¶ 30. 571 Lester Dyck Statement II, ¶¶ 15-16 (“I reviewed the broader range of data submitted by Celgar – from 2002 until 2007…”); Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project and Celgar Green Energy Project, dated May
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
135
considered historical data from as submitted by Tembec.572 For Howe
Sound’s 2010 EPA, BC Hydro considered historical generation data from
, as submitted by Howe Sound.573 In addition, BC Hydro relied on statements
made by mill personnel about the mills’ operations going forward to ensure that the GBL
was set at an appropriate level.574
The mill’s actual gross generation data was the starting point for each of these 295.
pulp mills. Adjustments were then made to arrive at a GBL that the parties agreed
reflected how much the mill would normally generate for self-supply on an annual basis.
In some cases, few or no adjustments needed to be made to the mill’s actual gross
generation data. Celgar, for example, represented that it was self-sufficient under normal
operating conditions;575 it also represented that its load was expected to grow, and its
generation levels would grow to meet it.576 Under these circumstances, the mill’s gross
7, 2008 at 019774, R-127. 572 Christian Lague Statement, ¶ 44; Email from Chris Lague to Matt Steele re: Tembec Skookumchuck site GBL calculations, dated March 10, 2009 at 021003, R-193.
see Lester Dyck Statement I, ¶¶ 108-109; Lester Dyck Statement II, ¶¶ 46-47. 573 Lester Dyck Statement II, ¶ 49; Fred Fominoff Statement, ¶¶ 33-34; Howe Sound Pulp and Paper LP, Generation Baseline Calculations, 1 August 2006 – 31 July 2009, R-66. 574 Lester Dyck Statement II, ¶¶ 16 (“Rather than considering ‘only one year’ as Mr. Merwin contends, I reviewed the broader range of data submitted by Celgar -- from 2002 until 2007, in addition to statements Mr. Merwin made about the mill’s projections for future performance”), 35 (“As I explained in my first witness statement, the expected generation at the Skookumchuck mill in the absence of the 1997 EPA (or any incentive agreement) was the basis for setting the GBL for the 2009 EPA.”), 49 (“Unlike with Celgar,
575 Lester Dyck Statement II, ¶ 19 (“To clarify what I was trying to determine, I asked Mr. Merwin specifically whether, in normal circumstances, the mill was completely self-sufficient. His answer was yes.”) See also Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) – Biomass Realization Project and Celgar Green Energy Project, dated May 7, 2008 at 019777, R-127. 576 Lester Dyck Statement II, ¶¶ 25 (“Mr. Merwin did not convey that the mill would decrease steam production without the sales contracts. Quite the opposite – Mr. Merwin described that, as a result of the Blue Goose improvements, the mill would be producing even more steam than it had in the past, using primarily black liquor in its recovery boiler, which was a by-product of increased pulp production.”), 29 (“Mr. Merwin again never mentioned that Celgar might have questions about the reliability of Blue Goose.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
136
generation output in 2007, which was 351 GWh/year, was adjusted slightly down to the
level of its load (349 GWh/year). No other adjustments were necessary, as the parties
agreed this mode of operation represented normal for the mill.577
In Howe Sound’s case, however, 296.
578 The parties were thus required
For
its part, Tembec’s 579 BC Hydro and Tembec were also required
The point remains that even though gross generation was not appropriate as the 297.
ending point in each case, it was the starting point in each case. That BC Hydro arrived at
different end points for different mills to reflect their unique operations does not amount
to less favourable treatment. To the extent that there were differences in the adjustments
made, the differences are the result of the unique factual circumstances of each mill’s
operations, and will be addressed in the “like circumstances” section below.
Moreover, BC Hydro determined “normal” levels of generation for self-supply 298.
using the best available information at the time of the procurement process. As the GBL
is meant to define how much energy BC Hydro will consider purchasing in an EPA, BC
Hydro necessarily assesses what is existing and what is incremental energy at that
To the contrary, he boasted about the efficiency improvements, and communicated to us that the mill’s load would grow, and its generation would grow to match it.”). 577 Lester Dyck Statement II, ¶ 17 (“In follow-up conversations, Mr. Merwin confirmed that 2007 represented normal operations for Celgar going forward.”) 578 Lester Dyck Statement II, ¶¶ 49-50. See also Pöyry Expert Report II, ¶¶ 109-110. 579 Lester Dyck Statement I, ¶ 106; Christian Lague Statement, ¶ 42
See also Pöyry Expert Report II, ¶ 98 the reality of Skookumchuck’s operations would necessarily change.”).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
137
time.580 After reviewing the historical generation data submitted by Celgar, BC Hydro
used 2007 data as the basis for that mill’s GBL. This was the most recent complete year
of operations at the time of the GBL negotiations in 2008, and the data did not contain
anomalies.581 Similarly, BC Hydro used Tembec’s data to
set the GBL for that mill.582
BC Hydro and Howe Sound
This difference, again, does
not constitute evidence of less favourable treatment, but of different factual
circumstances leading to a different outcome under the consistent application of a
uniform methodology.
Finally, BC Hydro does not directly consider any mill’s “economic and financial” 299.
circumstances to set GBLs. Mr. Dyck explains that “[t]he recent historical generation
data of the mill already reflects that mill’s weighing of economic and financial factors in
operating decisions.”583 This approach was the same for all mills. The Claimant greatly
exaggerates the role of
580 Lester Dyck Statement II, ¶¶ 4-5 (“For the purposes of its EPAs, BC Hydro reviews the most recent historical data with a self-generating counterparty in order to agree on what normal operations are for the counterparty at that time.”) 581 While Celgar pointed out what it considered to be “abnormalities” in its operational data in its May 2007 presentation to FortisBC, such information was not conveyed to BC Hydro in either its April 2007 presentation (which contained many similar elements to the presentation given to FortisBC a month later) or in any communications during the GBL discussions in April and May 2008: Pöyry Expert Report II, ¶ 45. See also Mercer International Group, FortisBC Meeting, May 2007, MER00277673, R-558; MercerInternational Group, BC Hydro RFEOI Meeting, April 2007, R-352. 582 Lester Dyck Statement I, ¶ 107; Christian Lague Statement, ¶ 44; Pöyry Expert Report I, ¶¶ 131-132. 583 Lester Dyck Statement II, ¶ 30.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
138
584 While hog fuel conditions led to a
585
586
BC Hydro’s focus for the purpose of setting
GBLs in all cases “was the level of self-generation output that reflects the operating
decisions the mill normally makes, using the best information at the time of negotiating
the EPA.”587
The existence of the 1997 EPA at the Skookumchuck mill, and the absence of a 300.
similar agreement at the Celgar mill, does not demonstrate less favourable treatment.
Rather, it is a unique factual circumstance that 588 As stated
above, any differences in adjustments made are the result of the unique factual
circumstances of each mill’s operations, and will be addressed in the “like
circumstances” section below.
584 Claimant’s Reply, ¶ 399. 585 See Christian Lague Statement, ¶ 52 (“As I explained above, the Skookumchuck mill was operating under the terms of the 1997 EPA and the 2001 ESA,
; Lester Dyck Statement II, ¶ 35 (“The Skookumchuck mill’s operations during May to August 2009
586 See Christian Lague Statement, ¶¶ 33-41. 587 Lester Dyck Statement II, ¶ 30. 588 The Claimant has conceded that “the seasonal shaping issue of which mercer complained involved different GBL-related elections made by Tembec and Celgar such that it raises no discrimination issue separate and distinct from the primary issue concerning the level of Tembec’s GBL and how it was set: Claimant’s Reply, ¶ 417. See also Memo from Brian Merwin to Jimmy Lee and David Gandossi, BC Hydro Bid Price & Associated Terms, 7 June 2008, at MER00071679, MER00071676, R-559.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
139
4. The Different Results of BC Hydro’s Consistent Application of itsGBL Methodology Are Explained by the Unique Circumstancesof Each Mill
Canada maintains that the GBL methodology was consistently applied to all nine 301.
pulp mills that have an EPA and GBL with BC Hydro, and illustrated by the examples
above. In the event the Tribunal finds that there has been a difference in treatment
between Celgar and another mill, Canada contends that the differences are explained not
by reason of Celgar’s nationality, but by the unique factual circumstances of each mill.
Howe Sound (Port Mellon)’s 2010 EPAa)
The Claimant acknowledges that BC Hydro consistently applied its GBL 302.
methodology to Howe Sound in the context of its 2010 EPA.589 The Claimant applauds
BC Hydro’s for Howe Sound, but
contests the 590
For Howe Sound.
The Claimant misunderstands that, 303.
591 In those circumstances,
BC Hydro and Howe Sound thus worked together to
592
589 Claimant’s Reply, ¶ 462. Incidentally, the Claimant has also determined that Howe Sound has received the most favourable treatment of the comparator mills, according to its Below-Load Access Percentage of
590 Claimant’s Reply, ¶ 463. 591 Lester Dyck Statement I, ¶¶ 127-9; Fred Fominoff Statement I, ¶¶ 32-34. See also Pöyry Expert Report II, ¶¶ 109-110. 592 Lester Dyck Statement II, ¶ 51. See also Fred Fominoff Statement, ¶ 33.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
140
These circumstances stand in stark contrast to Celgar’s situation. BC Hydro 304.
looked at all of the data submitted by Celgar, and followed up with several meetings and
phone calls to confirm what were normal operations at the Celgar mill. As Mr. Dyck
testifies, and the documents corroborate, Celgar agreed that 2007 was representative of
normal operations at that time.593 The treatment accorded to each of these mills was thus
not comparable. Indeed, the reason for for Howe Sound and one
year for Celgar is that for Howe Sound, whereas the
parties agreed that one year – 2007 – was normal for Celgar.594
The Claimant further argues that BC Hydro 305.
but did not do the same for Celgar.595 Instead, the
Claimant argues that BC Hydro subtracted Celgar’s sales to NorthPoint and FortisBC, but
then added back in its purchases from FortisBC to arrive at the mill’s load.596 The
Claimant asserts that its sales to NorthPoint and FortisBC were no different
The adjustments made for and Celgar’s 306.
sales to NorthPoint and FortisBC are the result of the different operational realities of
both mills with respect to their sales. In the case of Howe Sound, 597 In the case of Celgar, the mill was
593 Lester Dyck Statement I, ¶ 86; Lester Dyck Statement II, ¶ 17; Letter from Brian Merwin to BC Hydro RFP Administrator, re: Zellstoff Celgar Limited Partnership (“Celgar”) - Biomass Realization Project and Celgar Green Energy Project, dated May 7, 2008, p. 7, R-127 (showing “Celgar Operation 2007” diagram that “represents how Celgar typically operates after Mercer capital investments.” This diagram shows a 2007 “March” mill load of 43 MW, generation levels for the same of 48 MW, and exports of 5 MW.) 594 Lester Dyck Statement II, ¶ 52 (“[Mr. Switlishoff] then asks why BC Hydro did
The answer is simple: the mills’ generation realities were different.”) 595 See Claimant’s Reply, ¶¶ 363, 369. 596 Claimant’s Reply, ¶ 367. 597 Pierre Lamarche Statement II, ¶ 7; Lester Dyck Statement II, fn 38 (“The electricity Celgar sold to FortisBC and NorthPoint was at all times net of mill load. This is in contrast to the below load sales by Howe Sound to Powerex. Moreover, in Howe Sound’s case, the mill was burning extra natural gas specifically to make the sales. Without the opportunity of a sale at the price available under the agreement,
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
141
selling electricity when it produced more in normal operations than its process could use.
The Claimant’s arguments today conflict both with what Celgar was representing to BC
Hydro at the time its GBL was set, and with how the Celgar mill was operating at that
time.
The Claimant asserts now that, without the contractual arrangements in place with 307.
NorthPoint and FortisBC, “Celgar would have
598 However,
setting the GBL at 326.7 GWh/year (representing Celgar’s gross generation less its sales
in 2007), as the Claimant now suggests is appropriate,599 would have been inconsistent
with what Mr. Merwin stated in several conversations with Mr. Dyck and others at BC
Hydro about the generation patterns of the mill at the relevant time.600 Mr. Merwin
repeatedly conveyed that the mill made sales only when it was generating in excess of its
load, and that, in normal operating conditions, the mill was completely self-sufficient.601
Furthermore, the mill’s load was projected to grow, and its generation projected to grow
to meet it.602 Mr. Dyck explains that, based on his understanding of the mill’s operations,
as communicated to him by Mr. Merwin at the time, “the only way the mill could
Howe sound would not have fired the natural gas… This is in contrast to Celgar’s case, where Celgar confirmed that the mill is fully self-sufficient under normal operating conditions (i.e., in the absence of any market sales opportunities.”) 598 Claimant’s Reply, ¶ 368. 599 Claimant’s Reply, ¶ 376. 600 See, for example, the Claimant’s presentation to BC Hydro at the RFEOI stage of the Bioenergy Call process: Mercer International Group, BC Hydro RFEOI Meeting, April 2007 at MER000277705 (“Excess steam is a spin-off benefit of Mercer’s investment”), MER000277707 (“Celgar’s steam production in 2007 will result in large volumes of vented steam”), MER000277708 (“Under normal operating conditions Celgar’s entire steam production will come from biomass.”), R-352. 601 Mr. Merwin also states that, without the FortisBC and NorthPoint contracts, Celgar would not produce any steam in excess of thermal balance: Brian Merwin Statement, ¶¶ 27-29. As Pöyry concludes, however, it is very unlikely that this would have occurred because, following Blue Goose, Celgar realized a number of benefits, including increased pulp production, increased black liquor generation, increased steam production, and increased electricity generation. In addition, Celgar’s improved performance led to energy savings of $10/ADMT; running the mill at thermal balance would have negated this benefit. See Pöyry Expert Report II, ¶¶ 87-89. 602 Lester Dyck Statement I, ¶ 82; Lester Dyck Statement II, ¶ 25-26.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
142
generate 327 GWh/year when operating normally is if the mill was intentionally under-
utilizing its generation capacity by venting steam and wasting thermal energy.”603
Moreover, the Claimant’s own internal documents show that the mill was not 308.
running the power boiler to generate surplus electricity, but to provide operational
benefits.604 As Pöyry explains in its second expert report, Celgar’s power boiler provided
several operational benefits to the mill that demonstrate that Celgar would have operated
it without sales contracts. For example, the power boiler supported steam demand for
pulp production and addressed recovery boiler upsets so as not to affect pulp production,
as well as acted as a cost-effective way to dispose of hog fuel (which it was producing
on-site), and of other waste matters.605
In addition, if what the Claimant now says is true, the 309.
would make a de minimis difference in the mill’s electricity generation because
the power boiler contributes minimal steam to the operation in comparison to the steam
produced by burning black liquor in the recovery boiler. Specifically, the energy content
of Celgar’s steam production in 2007 was attributed to: ~94% black liquor, hog
fuel, and natural gas.606
603 Lester Dyck Statement II, ¶ 27. 604 See e.g. See e.g. Email from Jim McLaren to Brian Merwin, Draft Jan 2006 to March 2007 Energy Review, 23 March 2007, MER00036310, R-560 (
); Energy Cost Path to $25/A Dt then $0/A Dt, 23 March 2007, MER00036311, R-561 (
); Energy Coordinator’s July, 2007 Report to Al Hitzroth, 3 August 2007, MER00091267, R-562 (
605 Pöyry Expert Report II, ¶¶ 81-86. 606 Pöyry Expert Report II, ¶ 69, Table 3: Fuel Consumption for Steam Summary.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
143
Finally, the Claimant’s arguments on this point fundamentally misunderstand the 310.
principle of BC Hydro’s GBL methodology. As BC Hydro has stated before the BCUC,
“the GBL is not calculated from a formula.”607 The Claimant itself has advocated for this
approach before the BCUC.608 Rather, BC Hydro seeks to determine with the proponent
what the self-generator normally generates for self-supply. Celgar was normally
operating to self-supply the entirety of the mill’s electrical needs, and the evidence
strongly suggests that it would not have changed its operations in any meaningful way
without the FortisBC or NorthPoint contracts.
Indeed, Celgar was frequently venting excess steam in 2007, an indication that it 311.
was producing more steam than was necessary to meet its pulping needs under normal
circumstances.609 As Pöyry explains, after Blue Goose,“Celgar’s steam generation
capability surpassed its process steam consumption.” 610 The main drivers of the mill’s
generation were not the sales to NorthPoint or FortisBC – those sales involved dumping
electricity that the mill could not support onto the grid – but an increase in pulp
production, more reliable pulp production,611 and the reduction of energy costs.612 Similar
607 Letter from Joanna Sofield, Chief Regulatory Officer to Ms. Erica Hamilton, Commission Secretary, Re British Columbia Utilities Commission (BCUC) British Columbia Hydro and Power Authority (BC Hydro) March 27, 2009, BC Hydro Response to BCUC Information Requests No. 1.6.1-1.6.4 at 151373, R-547. 608 See Celgar, Evidence Submission, in the Matter of an Application by FortisBC for Approval of a 2009 Rate Design and Cost of Service Analysis, 15 March 2010, pp. 2 and 3, R-280; Celgar, Response to BCUC Information Request No. 1, in the Matter of an Application by FortisBC for Approval of a 2009 Rate Design and Cost of Service Analysis, 15 April 2010, Q 6.1, pp. 16-17, R-372. 609 See Pöyry Expert Report II, ¶ 88 ( [
610 Pöyry Expert Report II, ¶ 88 (“Following the completion of Blue Goose, Celgar substantially improved pulp production in 2007, which increased the amount of black liquor generated in 2007. Celgar disposed of its black liquor by burning it in the recovery boiler, resulting in a higher level of steam generation based on black liquor. … Blue Goose also led to a reduction of Celgar’s process steam demand, which resulted in increasing amounts of steam being vented by the pulp mill.”) 611 Increased pulp production would result in more black liquor production, which could then be burned to produce more steam to generate more electricity. Similarly, more reliable pulp production would result in more black liquor being available more consistently. 612 See Pöyry Expert Report II, ¶ 88.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
144
operational realities were not present at the Howe Sound mill, 613 The reason for adjusting
is therefore not the nationality of either mill.
Rather, it is the different operational realities that render comparison of treatment on this
point inapt. The Claimant has therefore failed to show a breach of Articles 1102 or 1103.
Tembec (Skookumchuck)’s 2009 EPAb)
As set out above, BC Hydro started its GBL assessment for both Celgar and 312.
Tembec with each mill’s actual gross generation data, and then made adjustments for
each as required. The primary reason for the different adjustments made for Celgar and
Skookumchuck is not the nationality of their owners, but the existence of Tembec’s 1997
EPA and the absence of a similar agreement for Celgar.
The Claimant argues that BC Hydro had no reason to 313.
614 particularly when BC Hydro used
actual generation data for Celgar. In short, the Claimant argues that (1) the 1997 EPA did
613 Lester Dyck Statement II, fn 38; Pierre Lamarche Statement I, ¶ 39; Pierre Lamarche Statement II, ¶ 7. Mr. Merwin also states now that, without the FortisBC and NorthPoint sales contracts, the mill would have
: Brian Merwin Statement II, ¶ 28. Not only does this contradict what Mr. Merwin stated in his first witness statement (“A minimal amount of natural gas is needed in the Mill to keep certain equipment operational (much like the function of a pilot light on a home kitchen stove), and to supplement the generation of electricity when the Mill experiences operational upsets. Since 2003, the Mill’s natural gas consumption has been limited to this type of provisional usage.” Brian Merwin Statement I, ¶ 27), but Canada’s expert Pöyry compared the electricity sales prices Celgar received under its contracts against the cost of natural gas in 2007, and found that Celgar was not firing discretionary natural gas to generate substantial additional electricity in 2007. Specifically, Pöyry concludes that “it would not have made economic sense to burn discretionary natural gas to make sales to FortisBC at any point in time in 2007” (¶ 11) and that Celgar had supportive pricing and transmission access for only 1,199 MWh of electricity sales to NorthPoint, which represents 5% of its total sales in 2007 (¶ 12). However, the weighted average fuel mix for those days when Celgar sold to NorthPoint indicated that “only 1.5% of the fuel used in both boilers would have been generated by firing natural gas” (¶ 13). See Pöyry Expert Report II, ¶¶ 66-78. 614 Claimant’s Reply, ¶¶ 418.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
145
not incentivize Skookumchuck to generate 615 and (2)
conditions impacting hog fuel prices led to “rampant speculation” on the part of BC
Hydro 616
The Claimant fundamentally misunderstands the nature of the 314.
and its effect on Tembec’s operations. For example, the Claimant contends that, without
the obligations, Skookumchuck
However, this is a simplistic
view of complex operating decisions.
The 1997 EPA required that 315.
As Mr. Lague explains,
617 In this sense, the Skookumchuck
operation was
618 This stands
in contrast to Celgar, whose hog boiler contributed a mere of the mill’s steam
supply, and was used in 2007 to support the mill’s pulp production process.619
615 See Claimant’s Reply, ¶¶ 420-431. (“Regardless of any incentive the 1997 EPA provided to Tembec for generating 10.8 MW tranche of electricity that BC Hydro purchased, the 1997 EPA provided no marginal incentive to Tembec for any generation after that used by Tembec to meet its own load. Accordingly, the fact that Tembec
¶ 30) 616 Claimant’s Reply, ¶¶ 432-461. 617 Christian Lague Statement, ¶ 50. See also Christian Lague Statement, ¶¶ 20, 26 (“…the 1997 EPA required hog fuel to be the primary fuel source for electricity generated to meet the Tranche 1 obligations.”) 618 Pöyry Expert Report II, ¶ 18. 619 Of those , only was produced by burning hog fuel; the other was produced by burning natural gas. See Pöyry Expert Report II, Table 3: Fuel Consumption for Steam Summary. In contrast, Celgar’s recovery boiler, which is inextricably tied to its pulp production, contributed 95% of the mill’s steam production in 2007. See also Pöyry Expert Report II, ¶ 82 (“…Celgar indicated in numerous
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
146
This also explains why, without the delivery obligation of the 1997 EPA, Tembec 316.
Instead, and much more like Celgar, it would operate its recovery boiler to
produce steam for the mill’s process. Rather than being a
as the
Claimant contends, Mr. Lague explains that “[i]n reality, nothing could be farther from
hypothetical”:
Tembec represented to BC Hydro 621317.
622 As Mr. Lague explains, the power project
communications in 2007 that the power boiler was used that year to support steam demand for pulp production, to address recovery boiler upsets so as not to affect pulp production, to minimize firing of natural gas in the recovery boiler, and to serve as a back-up for the incineration of concentrated non-condensable gases (required by environmental permits) when other processes were down.” [footnotes omitted]). 620 Christian Lague Statement, ¶ 50. 621 Christian Lague Statement, ¶ 40. 622 Christian Lague Statement, ¶¶ 33-40.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
147
623 Mr. Dyck and his GBL team
at BC Hydro were not specifically concerned about the underlying reasons for this
operational decision, only that they had informed the ultimate decision to operate 624
The Claimant points to Tembec’s generation patterns following 318.
event in February 2009 to argue that the 1997 EPA did not provide the
incentive that BC Hydro claimed and that,
Tembec was generated 625 However, the Claimant ignores
the fact that, the mill remained bound by the terms of the 1997
EPA and the 2001 ESA,
626 BC Hydro and Tembec had begun discussions regarding a new EPA,
and both parties agreed that 627
628
623 Christian Lague Statement, ¶¶ 33-40. 624 See Lester Dyck Statement II, ¶ 30. 625 Claimant’s Reply, ¶¶ 449-450. See also Claimant’s Reply, ¶ 454 (“In every single month leading up to the temporary idling and after – months in which hog fuel prices were high – Tembec actually had generated far more than 14 MW – usually more than double that amount.”) 626 Christian Lague Statement, ¶ 52. 627 Christian Lague Statement, ¶ 52; Lester Dyck Statement II, ¶ 35. The 2009 EPA also contained provisions to
see Christian Lague Statement, ¶ 55; Lester Dyck Statement I, fn 123; Justification Report, Tembec EPA Replacement for Incremental Energy Sales from Purcell Power Plant at bates 152597-8, R-192. 628 Lester Dyck Statement II, ¶ 35; Christian Lague Statement, ¶ 52. In addition, Skookumchuck ran a test period in the summer of 2009 to prove to BC Hydro that it could deliver the firm energy contemplated for
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
148
Finally, the Claimant takes issue with certain assumptions 319.
used by Tembec and BC Hydro to determine
Specifically, the Claimant decries the omission of the
used by Tembec, a fact it alleges led to an EPA “incentive” for Tembec’s
existing generation.629
However, the Claimant argues was so unfairly left out was 320.
BC Hydro assumed that Tembec had the
630 Rather than ignoring the reality of at the mill,
BC Hydro maintained that this 631 BC Hydro’s engineering
group ran its own steam analysis, and arrived at an electricity generation level,
>632 BC Hydro agreed that the new EPA should not re-incentivize the
existing generating equipment.
delivery in the 2009 EPA on an hourly basis: see Christian Lague Statement, ¶ 52. 629 Claimant’s Reply, ¶ 444
630 Lester Dyck Statement II, ¶ 45. 631 Lester Dyck Statement II, ¶¶ 46-47 (“I agree with Mr. Switlishoff that the appropriate GBL for the Tembec 2009 EPA needs to be based on the equipment that was installed and operating at Skookumchuck under normal operating conditions at the time of EPA negotiation.
See also Christian Lague Statement, ¶¶ 43-45, 47 (“BC Hydro
632 Lester Dyck Statement II, ¶ 43.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
149
The Claimant’s accusations that “Canada and its witnesses ignore completely the 321.
terms of Tembec’s 1997 EPA, purporting to justify BC Hydro’s actions based on
supposed preexisting ‘incentives’ that simply do not exist”633 are therefore entirely
baseless. The evidence demonstrates that Tembec’s
As Pöyry points
the reality of Skookumchuck’s operations would
necessarily change.”634
With an accurate understanding of the facts, the case is clear: Tembec and Celgar 322.
had fundamentally different circumstances. Tembec had a pre-existing agreement
While Celgar had agreements for short-term,
discretionary sales, under normal circumstances it was still operating without an external
incentive to meet the requirements of its load. Viewed in another light, without the
NorthPoint and FortisBC agreements, the conditions that informed Celgar’s decision to
meet its load with its self-generation remained largely unchanged. This is in contrast to
Tembec,
The facts thus demonstrate that the difference in GBL outcome for Celgar and 323.
Tembec is the result of different operating realities, not of Mercer’s American nationality
or Tembec’s Canadian (at the relevant time) nationality. As such, it does not constitute a
breach of NAFTA Chapter 11’s National Treatment or MFN Treatment obligations.
D. The Claimant has Failed to Show that the Other Instances of GBL-Related Treatment it Identifies are Inconsistent with NAFTA Articles 1102 and 1103
The Claimant inappropriately compares the GBL in its 2009 EPA with three 324.
instances of treatment outside the context of BC Hydro’s procurement of electricity under
the 2007 Energy Plan: Tembec’s 1997 EPA; Howe Sound’s 2001 Consent Agreement;
633 Claimant’s Reply, ¶ 422. See also Claimant’s Reply, ¶¶ 420-432. 634 Pöyry Expert Report II, ¶ 98.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
150
and Tolko (Kelowna)’s 2001 exemption order from the BCUC in Order G-113-01.
Where, as here, there are identical instances of treatment (i.e. contracts with GBLs
concluded through BC Hydro’s procurement processes conducted in accordance with the
2007 Energy Plan), the Tribunal should not use these less identical instances of treatment
for the purposes of assessing whether there has been a breach of Article 1102 or 1103.635
Should the Tribunal nonetheless decide that these instances of treatment are 325.
appropriate for comparison, Canada maintains that none of them constitutes a breach of
Article 1102 or 1103.
1. Tembec (Skookumchuck)’s 1997 EPA
The Claimant contends that Tembec received more favourable treatment in its 326.
1997 EPA because it did not have a GBL, and because Tembec was allowed to sell to BC
Hydro while purchasing all of its electricity needs at embedded cost rates.636 The
Claimant’s argument, however, ignores the commercial reality of Skookumchuck’s
operations under the agreement.
Rather than arbitraging all of its self-generated electricity, 327.
In fact, in order to
make any sales beyond the 10.8 MW to BC Hydro, 637 The Claimant seems to recognize this, spending pages
635 Methanex Corporation v. United States of America (UNCITRAL) Award on Jurisdiction and Merits, 3 August 2005 (“Methanex – Award”), Part IV, Ch. B, ¶ 17 (“[I]t would be as perverse to ignore identical comparators if they were available and to use comparators that were less ‘like,’ as it would be perverse to refuse to find and to apply less ‘like’ comparators when no identical comparators existed.”), RA-28. The Claimant agrees: Claimant’s Memorial, ¶ 450 (“Within the range of comparators that may be in ‘like’ circumstances, the Tribunal must utilize the most appropriate comparators available.”) 636 Claimant’s Reply, ¶¶ 322-323. 637 See Christian Lague Statement, ¶ 25
”); Appendix to Electricity Supply Agreement between British Columbia Hydro and Power Authority and Tembec Industries Inc. (“Determination of Electricity Supplied and Taken Under RS 1821/1880”), 14 September 2001 at 30-31, R-188.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
151
describing the manner in which Tembec operated in the years and months leading to the
2009 EPA,638 but without attributing these operational decisions
As Mr. Lague explains, “[t]he [1997] EPA and the [2001] ESA are tied together, 328.
and cannot operate separately.”639 While different factors affected generation in each
For example,
640
641
As Mr. Lague explains,
there were other factors
642 However, these factors were
considered
The evidence thus demonstrates that Tembec’s arrangement under its 1997 EPA 329.
and 2001 ESA did not result in Tembec arbitraging the 10.8 MW of electricity it sold to
BC Hydro, despite the fact that the agreement did not have a GBL. Instead, Tembec was
638 See, e.g., Claimant’s Reply, ¶¶ 407-461. 639 Christian Lague Statement, ¶ 23. 640 Christian Lague Statement, ¶ 26. 641 Christian Lague Statement, ¶¶ 26-27. 642 See Christian Lague Statement, ¶¶ 26-32.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
152
Finally, the 1997 EPA was concluded prior to BCUC Order G-38-01 and prior to 330.
the introduction of the concept of a GBL in BC Hydro’s procurement processes in 2002.
Moreover, the 1997 EPA was awarded as part of an RFP for Independent Power
Producers, and the project was developed as such.643 When Tembec acquired the
Skookumchuck mill and the Purcell Power Project in 1999, it acquired an already-
concluded agreement. Contrary to the Claimant’s suggestion that “BC Hydro permitted
an agreement plainly inconsistent with Order G-38-01 to be assigned and implemented
after the date of that Order, including by concluding necessary supplemental agreements,
like the ESA, well after the date of Order G-38-01,”644 Tembec and BC Hydro were
discussing the accounting provisions of the 1997 EPA and the 2001 ESA in 1999 and
2000, when Tembec was “making and implementing its capital investment decisions.”645
Indeed, the project had already been implemented by the time G-38-01 was issued.646
The Claimant has therefore failed to demonstrate that the treatment accorded to 331.
Tembec in the 1997 EPA amounts to a breach of NAFTA Article 1102 or 1103.
643 Christian Lague Statement, ¶¶ 10-12, 21 (“BC Hydro had agreed to purchase
See also Pöyry Expert Report II, ¶¶ 18 (“The Skookumchuck operation has been configured and operated more akin
), 91-92. 644 Claimant’s Reply, ¶ 329. 645 Christian Lague Statement, ¶ 22. See also Crestbrook Forest Industries Ltd. Minutes of Meeting, Crestbrook Forest Industries Ltd. (CFI) Cogeneration Project Meeting No. 5 dated 30 May 2000, R-254. 646 See Christian Lague Statement, ¶¶ 16-17 (“The first part of the project, the hog boiler conversion, was completed in 2000. … STG2 was installed in February 2001.”)
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
153
2. Howe Sound’s 2001 Consent Agreement
The Claimant contends that Celgar received less favourable treatment in the 332.
setting of its 2009 GBL than Howe Sound received in the setting of its MW
threshold in 2001. Specifically, the Claimant argues that BC Hydro did not apply its
“current normal” standard to set the threshold for Howe Sound in 2001.647 The
Claimant’s arguments are misplaced for two reasons.
First, the Claimant inappropriately attempts to impose a standard developed for 333.
the purposes of BC Hydro’s long-term procurement of electricity to a threshold defining
BC Hydro’s obligation to serve a customer wishing to sell electricity to third parties. As
described above, these two activities set out to achieve different objectives.
Second, and more importantly, the Claimant ignores the fact that the MW 334.
threshold for Howe Sound was set using 648 If
Celgar’s GBL was set using the same quality of data, its GBL would be even higher.
Given that the Claimant’s entire case centers on having a lower GBL, it is difficult to see
how Howe Sound’s MW threshold constitutes less favourable treatment.
The Claimant’s argument that BC Hydro did not revisit the threshold in 335.
in which the Consent Agreement was renewed, thus demonstrating that BC Hydro
treated Howe Sound more favourably than Celgar, must also be rejected. As set out in
Section II.E, and in the testimony of Mr. Lamarche649 and of Mr. Dyck,650 BC Hydro and
647 See Claimant’s Reply, ¶¶ 336-340. 648 Pierre Lamarche Statement II, ¶ 4 (“As I previously testified, to arrive at MW, Howe Sound used
”), fn 6 (“To reproduce the precise calculations we made at the time would require
As this was almost fifteen years ago, the mill no longer has this detailed information available.”) 649 Pierre Lamarche Statement II, ¶¶ 7.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
154
Howe Sound indeed revisited the GBL in which the Consent Agreement
was renewed. In every year, the circumstances underlying the rationale for the
MW threshold had not changed --
651
This is equally true of 336.652 As Mr. Lamarche explains, the
653
654 Thus, there is no merit to the Claimant’s arguments in this
regard.
Finally, Howe Sound’s MW threshold is not less favourable treatment 337.
because Howe Sound could not
In contrast, Celgar’s ability to sell its below-GBL electricity is
not restricted by a similar threshold. The BCUC has articulated that Celgar can sell the
entire output of TG2. How this could constitute less favourable treatment is perplexing.
650 Lester Dyck Statement II, ¶¶ 54-57. 651 Pierre Lamarche Statement II, ¶ 7. 652 The Claimant suggests that, when the Consent Agreement there would have been “every reason to believe that it would have been economical for Howe Sound to resume burning natural gas and generating electricity at pre-2000 levels, without the incentive of its market price arrangement with Powerex.” Claimant’s Reply, ¶ 342. 653 Pierre Lamarche Statement II, ¶¶ 9-11. 654 Pierre Lamarche Statement II, ¶ 11.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
155
Therefore the Claimant has failed to demonstrate that the treatment accorded to 338.
Howe Sound in its 2001 Consent Agreement, and subsequent renewals, amounts to a
breach of NAFTA Article 1102 or 1103.
3. Tolko Kelowna’s 2001 Exemption Order
The Claimant mischaracterizes Canada’s Counter-Memorial arguments with 339.
respect to Tolko (Kelowna).655 Canada does not argue that BC Hydro’s contracted GBL
methodology should have been applied to Tolko (Kelowna). Indeed, the Claimant’s
suggestion in this regard reflects its incorrect approach to like circumstances. Rather,
Canada contends that Tolko’s Kelowna sawmill offered a more appropriate comparison
for the purposes of assessing the treatment accorded to self-generators in FortisBC’s
service territory, specifically under BCUC Order G-48-09. In that context, as Canada set
out in its Counter-Memorial, Tolko is treated identically to Celgar.656
In any event, the Claimant’s arguments with respect to Tolko’s threshold for 340.
third-party sales are misplaced. The Claimant argues that Tolko’s 2001 threshold was set
more consistently with BCUC Order G-38-01 than Celgar’s 2009 GBL (and all other BC
Hydro procurement GBLs) because it “did not include the incremental generation that
resulted from Tolko’s installation of a new 10 MW steam turbine in April 2000.” 657
The Claimant ignores that, unlike Celgar’s 2009 GBL, Tolko’s threshold was not 341.
negotiated for the purposes of BC Hydro procuring incremental electricity pursuant to the
2007 Energy Plan. Rather, it was a solution negotiated between Tolko and its utility, the
City of Kelowna, for the purposes of allowing Tolko to sell incremental power to third
parties.
655 Claimant’s Reply, ¶ 151 (“As in its Memorial, Mercer contends that the Tolko Kelowna sawmill is not an appropriate comparator, because it does not operate in the same business sector as Celgar. Given Canada’s insistence, Mercer nonetheless welcomes an analysis of the treatment afforded to Tolko, and presents its analysis below.”) 656 Canada’s Counter-Memorial, ¶ 450. 657 Claimant’s Reply, ¶ 353.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
156
Again unlike Celgar and its Blue Goose Project, Tolko initiated these negotiations 342.
with the City of Kelowna and West Kootenay Power prior to investing in increased self-
generation capability.658 Tolko specifically contemplated increasing its generation
capability for the purpose of selling electricity to third parties,659 and relied on the
opportunity of market sales when making the investment. Tolko and the City of Kelowna
had reached an agreement on the conditions under which Tolko could sell incremental
electricity in 1998 and 1999,660 and Tolko simply applied to the BCUC in 2001 to seek
the Commission’s regulatory confirmation of the already-concluded solution in light of
Order G-38-01. The BCUC’s acceptance of the negotiated solution is consistent with the
“flexible case-by-case approach to determine customer baselines” it adopted in Order G-
38-01.661
The Claimant has failed to demonstrate that the treatment accorded to Tolko 343.
(Riverside) in its 2001 threshold amounts to a breach of NAFTA Article 1102 or 1103.
658 Memorandum of Agreement between City of Kelowna and Riverside Forest Product, Ltd., February 25, 1999, at 1, attached (exhibit 2) to the Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, BCUC Staff Information Request No. 1, July 5, 2001, R-563. 659 Information Response of Riverside Forest Products Limited to the BCUC Staff Information Request No. 2, August 22, 2001, Answer 4.0. at 4-6, attached to Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, August 22, 2001, R-553. 660 See Memorandum of Agreement between City of Kelowna and Riverside Forest Product, Ltd., February 25, 1999, at 1, attached (exhibit 2) to the Letter from Counsel for Riverside Forest Products Ltd. to the British Columbia Utilities Commission re: Riverside Forest Product Limited, Application for Exemption of Certain Provisions of the Utilities Commission Act, BCUC Staff Information Request No. 1, July 5, 2001, R-563. 661 See Bursey Expert Report, ¶ 78.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
157
E. The Claimant Has Failed to Prove that the Restriction on Third-Party Sales in Section 7.4(b) of its EPA with BC Hydro is Inconsistent with NAFTA Articles 1102 or 1103
In its Reply, the Claimant argues that, “unlike other BC pulp mills,”662 BC Hydro 344.
has “forced” Celgar to self-supply through section 7.4(b) of its EPA,663 which it alleges
“preclude[s] Celgar from selling its below-GBL self-generated electricity not only to BC
Hydro but also to any third-party.”664 The Claimant states that BC Hydro “had no
authority to set a self-supply obligation for Celgar,”665 and that the provision even
“provides the basis for Mercer’s claim.”666
The Claimant does not, however, address section 7.4(b) under NAFTA Articles 345.
1102 or 1103. It makes no claim relating to section 7.4(b) provision directly, which can
only mean that the Claimant’s allegations against that provision are no more than bluster.
Even if the Claimant were to attempt a claim against section 7.4(b) under NAFTA
Articles 1102 or 1103, that claim would fail. As the Claimant acknowledges in its Reply:
“BC Hydro typically…includes exclusivity provisions that preclude sales to third-
parties.”667 The Claimant then proceeds to cite EPAs between BC Hydro and Howe
Sound,668 Tembec,669 Canfor,670 Cariboo Pulp,671 Domtar,672 Catalyst,673 and Nanaimo.674
662 Claimant’s Reply, ¶ 1. 663 The Claimant argues at ¶ 216 of its Reply that “BCUC Order G-48-09 effectively precludes Celgar from obtaining any energy from FortisBC while Celgar is selling self-generated electricity below its load, and the GBL-related provision in Celgar’s 2009 EPA with BC Hydro preclude Celgar from selling that energy below its 2007 load to any third party. In combination, these measures strand Celgar’s below-GBL self-generated electricity, effectively requiring the mill to use that electricity to self-supply the first 349 GWh/year of its own load.” In light of Celgar’s Side Letter Agreement (discussed in this section), and of the fact that Celgar is allowed to purchase embedded cost electricity from FortisBC while it is selling electricity through the NECP rate rider (discussed in the next section), the Claimant’s argument that BC “took from Celgar services which it paid others [like Howe Sound and Canfor] to provide” holds no water, and must be rejected. 664 Claimant’s Reply, ¶ 358. 665 Claimant’s Reply, ¶ 381. 666 Claimant’s Reply, ¶ 618. 667 Claimant’s Reply, ¶ 554. 668 BC Hydro and HSPP, Electricity Purchase Agreement, Integrated Power Offer (7 September 2010), §
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
158
As Mr. Scouras confirms, “every mill that has signed an EPA with BC Hydro has been
subject to the same exclusivity provision found in section 7.4 of the 2009 EPA with
Celgar.”675
Perhaps more fundamentally, the Claimant has in fact been accorded more 346.
favourable treatment than these other mills because BC Hydro signed a Side Letter
Agreement that permits the Claimant to sell its below-GBL electricity to third parties
with BCUC approval. According to Mr. Scouras, “no other pulp mill to date in any BC
Hydro power procurement process (including the Bioenergy Call for Power Phase I) has
been given the same preferential treatment.”676 Surprisingly, the Claimant mentions the
Side Letter Agreement only once in a footnote in its Reply Memorial.677 It is unclear why
the Claimant would omit this important agreement from discussion in its claim.
In light of the side letter agreement the Claimant’s argument that is being 347.
“forced” by BC Hydro to self-supply is completely false.
8.4(b), C-23. 669 BC Hydro and Tembec Electricity Purchase Agreement (13 August 2009), § 7.4(a), C-145. 670 Electricity Purchase Agreement between BC Hydro and Canfor Pulp Limited Partnership (4 February 2009), § 7.4(b), C-239 671 BC Hydro and Cariboo Pulp and Paper Company Electricity Purchase Agreement (13 December 2010), § 7.4(b), C-277.672 BC Hydro and Domtar Pulp and Paper Products Inc., Electricity Purchase Agreement, Bioenergy Call for Power – Phase I (27 January 2009), § 7.4(b), R-136. 673 BC Hydro and Catalyst Paper Electricity Purchase Agreement (18 February 2011), § 7.4(b), C-279. 674 BC Hydro and Nanaimo Forest Products Ltd. Electricity Purchase Agreement (7 December 2011), § 7.4(b), C-280 675 Jim Scouras Statement II, ¶ 33. 676 Jim Scouras Statement II, ¶ 33. 677 See Claimant’s Reply, fn. 699, where they acknowledge that “resolution of Celgar’s below-GBL sales” were left to the BCUC.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
159
F. The Claimant Has Failed to Prove that BCUC Order G-48-09 is Inconsistent with NAFTA Articles 1102 or 1103
As Canada explained in its Counter-Memorial, BCUC Order G-48-09 has no 348.
effect on FortisBC’s ability to draw on its other resources to supply electricity to its self-
generating customers.678 This is confirmed in subsequent BCUC proceedings. In its
Reply, the Claimant contends that the BCUC “intended to impose a net-of-load
restriction on the self-generator’s access to embedded cost power generally, and not
simply with respect to FortisBC’s purchases of PPA power from BC Hydro.”679 The
Claimant’s divination of the BCUC’s intent is irrelevant in light of subsequent BCUC
proceedings, which the Claimant fails to address.
For example, in the G-188-11 proceedings the BCUC determined that “Celgar is 349.
free to sell all or a portion of its generation below the BC Hydro GBL into the market and
supply its mill from FortisBC resources, not including BC Hydro PPA Power.”680 To that
end, it stated that, “Celgar is entitled to some amount of FortisBC non-PPA embedded
cost power when selling power”681 and directed FortisBC “to consult with all classes of
its customers to determine guidelines for the level of entitlement to non-BC Hydro PPA
embedded cost power.”682
The BCUC thus permitted the Claimant to sell its below-GBL electricity while 350.
purchasing FortisBC’s embedded cost power, contrary to the Claimant’s assertion above.
In fact, Mr. Merwin proclaimed this to be “a major victory”683 to the Mercer International
Board of Directors.
678 Canada’s Counter-Memorial, ¶ 435. 679 Claimant’s Reply, ¶ 230. [Emphasis added] 680 BCUC, Decision and Order G-188-11, November 14, 2011, Reasons for Decision, p. 49, R-275. 681 BCUC Order G-188-11, ¶ 7, R-44. 682 BCUC Order G-188-11, ¶ 8, R-44. 683 Memorandum to Mercer International Board of Directors, December 7, 2011, R-531.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
160
Mr. Merwin’s testimony that the BCUC was “denying Celgar all access to 351.
embedded cost utility power while Celgar is selling its self-generated electricity”684 is
thus patently false. As the BCUC later confirmed, “[t]he entitlement to non-BC Hydro
PPA embedded cost power by [Celgar] may be as high as 100 percent of load as
nominated by [Celgar.]”685
The Claimant alleges that it has been accorded less favourable treatment by the 352.
BCUC when compared to G-38-01, which applies to self-generators in BC Hydro
territory. This is false. The Claimant has received more favourable treatment than self-
generators in BC Hydro territory, who have no ability to sell any below-GBL electricity
to third parties.
The Claimant tries to discredit the more favourable treatment by complaining that 353.
the “non-BC Hydro PPA embedded cost power” they are entitled to purchase from
FortisBC is not “traditional embedded cost electricity.”686 In other words, the Claimant
alleges that the Non-PPA Embedded Cost Power (“NECP”) rate that FortisBC designed
after BCUC Order G-188-11 is more expensive than the rate under FortisBC’s Rate
Schedule 31. This argument is irrelevant because neither Howe Sound nor Tembec have
any right to sell below-GBL electricity. Nevertheless, the argument is also false, as
explained by Mr. Swanson from FortisBC:
Since 2009, the cost of replacement power (i.e., from owned surplus generation, BC Hydro (non PPA) power, and the market) has predominantly been lower than the cost of Rate Schedule 31 and is expected to remain lower into the future…
Moreover, a large hydroelectric infrastructure project called the Waneta Hydroelectric Expansion Project is expected to come online this Spring, and I anticipate that it will contribute significantly to FortisBC’s capacity surplus. In this context, consider an example where FortisBC has surplus from its
684 Merwin Statement I, ¶ 121. 685 BCUC Decision and Order G-202-12, December 27, 2012, Decision, p. 3, R-265. 686 Claimant’s Reply, ¶ 228. [Emphasis added.]
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
161
owned generation resources sufficient to meet the needs of a self-generating customer looking to sell its entire load, such as Celgar. In this scenario there would be no NECP rate because the cost of serving the load would not be higher than the cost of Rate Schedule 31. Thus, if the Mid-C market climbed above Rate Schedule 31, Celgar could stand to gain a very good return.687
The Claimant’s argument that Order G-48-09 accorded it less favourable 354.
treatment is also at odds with its confession that Order cause it no damages: “Mercer does
not claim additional or separate damages resulting from Order G-48-09’s net-of-load
restriction, because, as Canada correctly contends, the Seller Consumed Energy
Adjustment would 688
Finally, for the sake of completion, the Claimant fails to respond to Canada’s 355.
argument that the BCUC had no regard for the nationality of the Claimant when it issued
Order G-48-09 or in any of the other subsequent proceedings. As Canada stated:
The Claimant alleges that the BCUC’s regulatory treatment of FortisBC’s access to Rate Schedule 3808 energy in Order G-48-09 has resulted in de facto nationality-based discrimination. The most relevant comparator in such a case would be other self-generators in the FortisBC service area to determine whether the BCUC Order G-48-09 has somehow caused such discrimination. The fact that the outcome for each of FortisBC’s self-generating customers, including Tolko (Kelowna) and Nelson, is identical to the outcome for the Claimant demonstrates that no such de facto nationality-based discrimination occurred.689
The Claimant offers no rebuttal to this argument, which only further discredits its 356.
claim that the BCUC violated NAFTA Articles 1102 and 1103. It is a serious matter to
question the integrity, impartiality and independence of the regulatory commission and its
members. The Claimant has failed to provide any foundation for its baseless accusations.
687 Dennis Swanson Statement II, ¶¶ 33-34. 688 Claimant’s Reply, ¶ 205. 689 Canada’s Counter-Memorial, ¶ 452.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
162
V. THE CLAIMANT HAS FAILED TO DEMONSTRATE A VIOLATION OF ARTICLE 1105 – THE CUSTOMARY INTERNATIONAL LAW MINIMUM STANDARD OF TREATMENT
A. Concise Statement of Canada’s Position
Canada’s Counter-Memorial explained why the Claimant has failed to discharge 357.
its burden of proving that Canada has breached NAFTA Article 1105(1). In its Reply,
the Claimant engages in a lengthy but needless discourse regarding how the Article
1105(1) standard has evolved from the Neer decision,690 and how tribunals may turn to
relevant jurisprudence to inform their understanding of customary international law;691
Canada put neither of these points in issue in its Counter-Memorial. The Claimant then
criticizes virtually every aspect of the GBL negotiating process but it never really
discharges its burden of demonstrating that the conduct of which it complains violated
rules of customary international law in contravention of Article 1105(1).
In fact, the Claimant’s Reply is nothing more than a repackaging of arguments, 358.
made in its Counter-Memorial, that Canada violated Article 1105(1) through “four
pillars” of conduct that breached the minimum standard of treatment – namely conduct
that was “arbitrary”, “discriminatory”, “non-transparent”, and “idiosyncratic, unfair, or
unjust”.692 The Claimant still fails to properly apply the legal standard applicable under
Article 1105(1), or to demonstrate the kind of treatment of Celgar that might be found to
have breached the minimum standard of treatment. In the sections that follow, Canada
briefly reminds the Tribunal of the principles governing the legal standard under Article
1105(1), and then explains why none of the measures that the Claimant complains of
come close to having violated Canada’s obligation under Article 1105(1).
690 Claimant’s Reply, ¶¶ 480-485. 691 Claimant’s Reply, ¶¶ 486-497. 692 Claimant’s Reply, ¶¶ 503-527.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
163
B. Principles Governing a Claim under NAFTA Article 1105(1)
1. The Claimant Bears the Burden of Proving the Rules of theCustomary International Law Minimum Standard of Treatment It Alleges Have Been Breached
As Canada explained in its Counter-Memorial, it is a well-established principle of 359.
customary international law that the Party alleging the existence of a rule of customary
international law bears the burden of proving it.693 As stipulated by Article 38(1)(b) of
the Statute of the International Court of Justice, the “proof” required to establish a
customary norm of international law is evidence of (i) state practice, and (ii) opinio
juris.694 NAFTA tribunals have also consistently affirmed that, where the claimant asserts
an evolution of the minimum standard of treatment under customary international law, it
is the claimant’s burden to prove that its proposed rule constitutes custom according to
the two-step test described above.695 Without evidence going to each of these
requirements, no custom of international law can be established. It is not a question of
proving “what the law is,” as the Claimant contends,696 but the facts necessary to
693 Canada’s Counter-Memorial, ¶¶ 462-470. 694 International Court of Justice, Statute of the International Court of Justice, 3 Bevans 1179; 59 Stat. 1031; T.S. 993; 39 AJIL Supp. 215 [1945], Article 38(1)(b), online: United Nations, Office of Legal Affairs <http://legal.un.org/avl/pdf/ha/sicj/icj_statute_e.pdf>, RA-41. This principle was repeatedly affirmed in judgments of the International Court of Justice. For example, in North Sea Continental Shelf, Judgment, I.C.J. Reports 1969, p. 3, ¶ 44 RA-56 (“two conditions must be fulfilled. Not only must the acts concerned amount to a settled practice, but they must be such, or be carried out in such a way, as to be evidence of a belief that this practice is rendered obligatory by the existence of a rule of law requiring it”); Jurisdictional Immunities of the State (Germany v. Italy: Greece intervening), Judgment, I.C.J. Reports 2012, p. 99, ¶ 55 RA-57 (“In particular… the existence of a rule of customary international law requires that there be ‘a settled practice’ together with opinion juris”). 695 Glamis - Award, ¶¶ 600-603, RA-15; ADF Group Inc. v. United States of America (ICSID Case No. ARB (AF)/00/1) Award, 9 January 2003 (“ADF – Award”), ¶ 185, RA-1; Cargill, Inc. v. United Mexican States, (ICSID Case No. ARB(AF)/05/2) Award, 18 September 2009 (“Cargill – Award”), ¶¶ 271- 274, RA-6; United Parcel Service v. Government of Canada, (UNCITRAL) Award on Jurisdiction, 22 November 2002 (“UPS – Award on Jurisdiction”) ¶ 84-86, RA-58. 696 Claimant’s Reply, ¶ 497.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
164
establish a custom that forms a binding part of international law. This burden rests with
the party relying on a purported rule of customary international law.697
The Claimant tries to avoid its burden by suggesting that it is the Tribunal, and 360.
not the Claimant, that bears the burden of establishing that a proposed rule is a custom of
international law,698 and it cites the GAMI v. Mexico and Teco v. Guatemala cases in
support.699 Neither award, however, substantiates the Claimant’s view. The passage cited
from GAMI concerns the relevant timeframe within which a tribunal should consider the
application of a domestic measure.700 It does not discuss customary international law.
The passage cited from Teco sets out the framework of the legal analysis attendant upon a
minimum-standard-of-treatment claim under the CAFTA-DR701 and does not address the
issue of burdens at all. In fact, the Claimant in Teco clearly understood that it bore the
burden to “demonstrate” a custom of international law.702 It spent nine pages of its
Memorial attempting to discharge that burden, not denying it. 703
697 Glamis – Award, ¶ 601, RA-15; Cargill - Award, ¶ 273, RA-6; Patrick Dumberry, The Fair and Equitable Treatment Standard: A Guide to NAFTA Case Law on Article 1105 (Frederick, U.S.A.: Kluwer Law International, 2013) at 91, RA-59; Haeri Hussein, “A Tale of Two Standards: ‘Fair and Equitable Treatment’ and the Minimum Standard in International Law” (2011) 27:1 Arbitration International 27 at 41-42, RA-60. In its Reply, the Claimant states that Canada’s reliance on The Case Concerning Rights and Nationals of Morocco, RA-9, is “disturbing” because that decision applies only to the burden of establishing “local custom.” (Claimant Reply Memorial, fn.575). The Claimant does not, however, explain why a different burden should apply for local custom than custom at the international level. The Claimant also alleges that Canada misuses the decision in ADF, which apparently does not impose burden of proof on a party alleging the existence of a customary norm (Claimant Reply Memorial, fn. 575). The Claimant misreads the Award in ADF, which is very clear: “The Investor, of course, in the end has the burden of sustaining its charge of inconsistency with Article 1105(1). That burden has not been discharged here.” ADF – Award, ¶ 185, RA-1. 698 Claimant’s Reply, ¶ 497. 699 Claimant’s Reply, ¶ 497, footnote 574. 700 GAMI – Award, ¶¶ 92, 94, RA-14. 701 Teco Guatemala Holdings LLC v. The Republic of Guatemala, (ICSID Case No. ARB/10/17), Award, 19 December 2013 (“Teco – Award”), ¶ 447-454, RA-61. 702 Teco Guatemala Holdings LLC v. The Republic of Guatemala, (ICSID Case No. ARB/10/23), Claimant’s Reply on the Merits and Counter-Memorial on Jurisdiction and Admissibility, 24 May 2012, ¶ 231, RA-62. 703 Teco Guatemala Holdings LLC v. The Republic of Guatemala, (ICSID Case No. ARB/10/23),
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
165
In sum, just as it is incumbent upon claimants to prove the requisite facts of an 361.
alleged breach, so too is it incumbent upon claimants alleging a violation of the
customary international law minimum standard of treatment to show that the rule on
which they rely is in fact a rule of customary international law for the protection of
aliens. In the absence of this inherent burden, there would be no meaningful limitation on
the content of the minimum standard of treatment under Article 1105(1).
2. Arbitral Case Law Does Not Create Custom
In its Reply, the Claimant argues that international tribunals should be able to 362.
“turn to relevant jurisprudence to inform [their] understanding of the specific parameters
of customary international law.”704 Canada agrees. However, this does not absolve a
Claimant alleging a breach of a rule of customary international law from having to
adduce positive evidence that its proposed rule is both (i) the subject of a concordant
practice among a substantial number of states, and (ii) that it is followed by those states
out of a sense of legal obligation.705 The sources of evidence upon which a claimant can
rely to establish concordant state practice include “treaty ratification language, statements
of governments, treaty practice (e.g., Model BITs), and sometimes [government]
pleadings.”706
Claimant’s Memorial, 23 September 2011, ¶ 229-244, RA-63. 704 Claimant’s Reply, ¶ 489. 705 Glamis - Award, ¶ 602, RA-15; Cargill – Award, ¶ 274, RA-6; Lauterpacht, Sir Hersch, The Development of International Law by the International Court (London: Stevens, 1958) at 20, RA-21. The Claimant’s interpretation of Lauterpacht (Claimant’s Reply, ¶ 490) reveals its confusion about the sources of international law. International custom and decisions of international courts are two different sources of international law. When Lauterpacht writes that “[d]ecisions of international courts are not a source of international law in that sense”, he is referring to his previous paragraph where he described how municipal courts can create international custom through a multitude of uniform and authoritative decisions. Therefore, international courts are not a source of international law “in that sense”, as, regardless of the number of concordant decisions they write, their decisions will never amount to customary international law. Thus, Canada agrees that Lauterpacht stands for the proposition that international court decisions constitute a source of international law, but they are not a source of customary international law. It is customary international law which is at issue under NAFTA article 1105, not international law simpliciter. 706 Glamis - Award, ¶ 603, RA-15. The Tribunal in Cargill rejected the notion that even widespread adoption of “free and equitable treatment” clauses in bilateral investment treaties was sufficient to meet this
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
166
The Claimant proffers no such evidence in connection with the “four pillars” it 363.
invokes in this case. It suggests that it need only cite arbitral awards from investment
tribunals to establish “custom.” But as Canada explained in its Counter-Memorial,
arbitral awards do not create “custom.”707 Arbitral awards are the product of independent
adjudication of international disputes and not state practice. As the Glamis Tribunal held,
discussions of custom in arbitral awards can provide helpful “illustrations of customary
international law if they involve an examination of customary international law.”708
However, “[a]rbitral awards … do not constitute State practice and thus cannot create or
prove customary international law.”709 Only states can engage in those actions which, if
followed out of opinio juris sive necessitatis and in concert with enough other states,
coalesce into binding custom.
3. The Threshold for Establishing a Breach of Article 1105(1) is High
Finally, given the nature of the conduct required to breach the minimum standard, 364.
and the deference that tribunals must accord to domestic authorities in considering such a
claim, the threshold for a violation of the minimum standard of treatment is high. Canada
summarized in its Counter-Memorial how successive NAFTA Tribunals have
consistently recognized both the high threshold required for a breach of the minimum
burden: “the Tribunal does not believe it prudent to accord significant weight to even widespread adoption of such clauses.” See Cargill – Award, ¶ 276, RA-6. 707 Canada Counter-Memorial, ¶¶ 464-465. 708 Glamis - Award, ¶ 605, RA-15. See also International Law Commission, “Second report on identification of customary international law”, May 22, 2014, United Nations Document A/CN.4/672, available online at: http://legal.un.org/ilc/documentation/english/a_cn4_672.pdf, p. 31, R-64 (“While the decisions of international courts and tribunals as to the existence of rules of customary international law and their formulation are not ‘practice’, such decisions serve an important role as ‘subsidiary means for the determination of rules of law’. The pronouncements of the ICJ in particular may carry great weight.”) [Emphasis added, references omitted] 709 Glamis - Award, ¶ 605, RA-15. See also Cargill - Award, ¶ 277, RA-6 and Railroad Development Corporation v. Republic of Guatemala, (ICSID Case No. ARB/07/23), Award, 29 June 2012, ¶ 217, RA-65.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
167
standard of treatment, and the high level of deference to be afforded to domestic
authorities in considering a claim under Article 1105(1).710
In its Reply, the Claimant simply seizes upon the descriptors employed by these 365.
NAFTA Tribunals in explaining the type of conduct that might breach the minimum
standard, and matches them up with the “four pillars” of its claim; the Claimant notes
“the recognition in all of these cases of the four pillars around which investment tribunals
have coalesced to articulate the minimum standard of treatment – namely, conduct that is
“arbitrary,” “discriminatory,” “non-transparent” and “idiosyncratic unfair or unjust” and
blithely concludes, “the jurisprudence cited by Canada proves Mercer’s case.”711
But proving a breach of Article 1105(1) requires more of the Claimant than the 366.
simple matching exercise in which it has engaged here. In addition to establishing the
existence of the alleged rule of customary international law at issue in its claim, the
Claimant must demonstrate that the conduct of which it complains breached the rule by
rising to the threshold required under Article 1105(1). Merely affixing labels to the
conduct in issue is not enough to demonstrate a breach. The Claimant must show that in
light of all of the relevant surrounding facts, the conduct falls below accepted
international standards. And in assessing whether such standards have been breached, a
tribunal must be mindful of the deference to be afforded to domestic authorities in the
conduct of their affairs. To accept anything less—to find a State liable for exercising its
powers in a manner merely perceived as being unfair or inequitable—would ultimately
cripple governments from being able to govern altogether.712
710 Canada’s Counter-Memorial, ¶¶ 457-461. 711 Claimant’s Reply, ¶ 503. 712 Glamis – Award, ¶ 804, RA-15 (“governments must compromise between the interests of competing parties and, if they were bound to please every constituent and address every harm with each piece of legislation, they would be bound and useless.”).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
168
With the fundamental principles governing a claim under Article 1105(1) in mind, 367.
Canada now explains why the Claimant has failed to establish that Canada violated the
minimum standard of treatment.
C. The Claimant Has not Established That Any of the Complained of Measures Rise to the Level Required to Breach Article 1105(1)
As Canada understands it, the Claimant appears to be claiming that Canada 368.
violated Article 1105(1) for the following reasons: First, that BC Hydro was
“discriminatory,” “non-transparent,” “arbitrary,” and “grossly unfair, unjust or
idiosyncratic” in the GBL negotiation process with Celgar;713 second, that the GBL
regime was “unstable” and hence failed to provide a “stable regulatory environment”;714
and, third, that the BCUC failed to exercise any regulatory oversight over BC Hydro and
issued discriminatory, unfair and arbitrary Orders affecting Celgar.715
None of the BC Hydro measures that the Claimant challenges cross the threshold 369.
required for this Tribunal to find a breach of Article 1105. Canada explains why
immediately below. Canada then turns to the alleged failure of the GBL regime in British
Columbia to provide a stable regulatory environment, and the allegation regarding the
acts and omissions of the BCUC. Neither of these allegations withstands even minimal
scrutiny under Article 1105(1) and they must accordingly be rejected.
713 Claimant’s Reply, ¶¶ 507-524. 714 Claimant’s Reply, ¶¶ 504-506. 715 Claimant’s Reply, ¶¶ 525-527.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
169
1. The Acts of BC Hydro Did not Breach Article 1105(1)
The Claimant Fails to Establish that BC Hydroa)“Discriminated” Against the Celgar Mill Contrary to theCustomary International Law Minimum Standard ofTreatment
In its Reply the Claimant alleges that Canada breached Article 1105(1), given BC 370.
Hydro’s “discriminatory” restrictions on Celgar’s access to embedded cost power and
sales of below-load self-generated electricity.716 But it fails to demonstrate that the
customary international law minimum standard of treatment includes a general
prohibition on “discrimination” against foreign investors. In fact, it makes no effort to
establish the existence of a customary norm pertaining to discrimination, and it relies
entirely on the same arguments that it makes in its claim under NAFTA Articles 1102
and 1103—in one short sentence it states that “Mercer covered the discrimination pillar
of the minimum standard of treatment [under Articles 1102 and 1103] above.”717 A
claimant must do more than merely assert its own subjective interpretation of customary
norms under the minimum standard of treatment, and then make a claim on that basis. If
the Claimant’s argument were to succeed here, then NAFTA Articles 1102 and 1103 (and
arguably every other “National Treatment” provision in any bilateral investment treaty)
would be rendered meaningless. So to would the exceptions to those provision listed
under Article 1108.
The Claimant also ignores the fact that NAFTA tribunals have consistently found 371.
that Article 1105(1) does not provide a blanket prohibition on discrimination against
foreign investors or their investments.718 For example, the Glamis Tribunal concluded
716 Claimant’s Reply, ¶ 507. 717 Claimant’s Reply, ¶ 507. 718 Canada’s Counter-Memorial, ¶¶ 467-468. See also Grand River - Award, ¶ 208, RA- 16 (“The language of Article 1105 does not state or suggest a blanket prohibition on discrimination against alien investors’ investments, and one cannot assert such a rule under customary international law.”). The tribunal in Methanex also made clear that, in the absence of a treaty rule to the contrary, customary international law allows States to differentiate in it treatment of nationals and aliens (Methanex – Award, Part IV, Ch C, ¶ 25, RA-28).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
170
that “nationality-based discrimination…falls under the purview of Article 1102,” and not
Article 1105.719 The Tribunal in Methanex reached the same conclusion, finding that “the
plain and natural meaning of the text of Article 1105 does not support the contention that
the minimum standard of treatment precludes governmental differentiations as between
nationals and aliens.”720 While some NAFTA tribunals have interpreted Article 1105(1)
as encompassing other forms of discrimination—for example, the Waste Management
Tribunal commented that a conduct that is “discriminatory and exposes the claimant to
sectional or racial prejudice”721—this would require far more than what the Claimant
alleges here.722
But even if NAFTA Article 1105(1) were to contain a general prohibition on 372.
“discrimination” against foreign investors, the Claimant’s arguments are devoid of any
merit for the reasons Canada explained in Section IV of this Rejoinder. The Claimant has
proffered no evidence whatsoever that any of the alleged discriminatory treatment of
which they complain was accorded on the basis of its nationality. All that the Claimant
has identified are differences in the outcome of the various GBL negotiating processes in
which BC Hydro engaged with various self-generators. Such differences are a fact of life
given the unique situation that each self-generator brings to the table in a negotiation, not
a wrong that needs to be corrected. They do not constitute discrimination under any
standard, let alone the type of “discrimination” that might be found to be a violation of
the minimum standard of treatment. The Claimant’s “discrimination” based Article
1105(1) claim must accordingly be rejected.
719 Glamis - Award, fn. 1087, RA-15. 720 Methanex - Award, Part IV, Ch. C, ¶ 14, RA- 28. 721 Waste Management II – Award, ¶ 98, RA-47 (emphasis added). 722 Commenting on the award in Waste Management, the Methanex Tribunal emphasized that a violation of Article 1105 would not occur as a result of simple discriminatory conduct, but would require “sectional or racial prejudice.” Methanex – Award, Part IV, Ch C, ¶ 26, RA-28.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
171
The Claimant Fails to Establish that BC Hydro Violatedb)the Customary International Law Minimum Standard ofTreatment for Failing to Act “Transparently”
As with its “discrimination” based claim, the Claimant fails to prove that the 373.
customary international law minimum standard of treatment requires a State to act
“transparently.” It merely asserts that under customary international law all States must
act transparently “when taking measures that affect a foreign investor.”723 This is but
another self-professed “customary” norm that should not be accepted as being part of the
minimum standard of treatment of aliens under Article 1105(1).
NAFTA tribunals have expressly rejected the proposition that a principle of 374.
transparency is part of customary international law. For example, the Cargill Tribunal
stated that the “Claimant has not established that a general duty of transparency is
included in the customary international law minimum standard of treatment owed to
foreign investors per Article 1105’s requirement to afford fair and equitable
treatment.”724 The Feldman Tribunal reached the same conclusion, finding that “a denial
of transparency alone … does not constitute a violation of Chapter 11.”725 The Glamis
Tribunal ruled that transparency is not a stand-alone element that imposes any legal
obligation on host states under NAFTA Article 1105.726 All three NAFTA Parties have
also repeatedly rejected the proposition that Article 1105 includes any obligation of
transparency.727 Where the NAFTA parties intended to address transparency, they did so
723 Claimant’s Memorial, ¶ 661. 724 Cargill - Award, ¶ 294, RA-6. See also Merrill & Ring Forestry L.P. v Canada (UNCITRAL) Award, 31 March 2010 (“Merrill & Ring”), ¶ 231, RA-24 (“[A] requirement for transparency may not at present be proven to be part of the customary law standard.”); 725 Marvin Roy Feldman Karpa v. United Mexican States (ICSID Case No. ARB(AF)/99/1) Award, 16 December 2002 (“Feldman – Award”), ¶ 133, RA-13. 726 Glamis - Award, ¶ 561, 619-622, RA-15. By examining transparency in the award’s section dealing with the obligation to protect the investor’s legitimate expectations, the tribunal implicitly rejected the investor’s argument that transparency was a stand-alone element under NAFT Article 1105. 727 See, for example, Glamis Gold, Limited v. The United States of America (UNICTRAL) Rejoinder of the United States of America, p. 155, RA-78 (March 15, 2007); Metalclad, Amended Petition of Mexico to the Supreme Court of British Columbia (Sup. Ct. B.C.), ¶ 72 (Oct. 27, 2000), RA-79; Metalclad¸ Outline of
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
172
expressly.728 It is noteworthy in this regard that Canada’s Model FIPA and the 2004 US
Model BIT both include obligations to remain transparent but in distinct provisions
expressly excluded from any recourse to investor-State arbitration.729
Moreover, none of the cases cited by the Claimant support its view that States 375.
have a general obligation to remain transparent under customary international law. For
example, the Claimant cites the Metalclad Tribunal’s award as “evidence” of such a
customary standard, but fails to mention that the British Columbia Supreme Court
overruled the tribunal’s decision on that very point.730
Putting aside the fact that the Claimant fails to demonstrate the existence of a rule 376.
of transparency under customary international law, Canada has already explained in its
Argument of Intervenor Attorney General of Canada (Sup. Ct. B.C.), ¶¶ 31-33 (Feb. 16, 2001), RA-80. 728 For example, Chapter Eighteen of the NAFTA sets out a number of requirements designed to foster openness, transparency and fairness in the adoption and application of the administrative measures covered by the Agreement, and the NAFTA Parties have not consented to arbitrate any alleged breaches of obligations arising under Chapter Eighteen through Chapter Eleven’s investor State arbitration mechanism. 729 See Canada Model FIPA, Article 19 entitled “Transparency”, RA-66 and 2004 US Model BIT, Articles 10-11, RA-67. 730 United Mexican States v. Metalclad Corp, 2001 BCSC 664, British Columbia Supreme Court Decision (2 May 2001), ¶ 70, RA-68 (“In the present case, however, the Tribunal did not simply interpret the wording of Article 1105. Rather, it misstated the applicable law to include transparency obligations and it then made its decision on the basis of the concept of transparency.”). The fact that transparency is not a stand-alone obligation under NAFTA Article 1105 does not mean that the concept is altogether irrelevant. For example, there may be some aspects of transparency within the minimum standard of treatment in the context of denial of justice. This conclusion seems to be consistent with that reached by the Waste Management tribunal (on which the Claimant also relies) through its referral to a “complete lack of transparency and candour in an administrative process,” not as a stand-alone element of the minimum standard of treatment, but as one illustration of State conduct that “involves a lack of due process leading to an outcome which offends judicial propriety.” (Waste Management, Inc. v United Mexican States (ICSID Case No. ARB(AF)/00/3) Award, 30 April 2004 (“Waste Management – Award”), ¶ 98, RA-47). It is perhaps here where the Claimant gets confused. The Claimant also cites scholars to support its view that “transparency” forms part of the customary international law minimum standard of treatment. For example, they state in his textbook on Article 1105 Patrick Dumberry “identifies protections against discriminatory, arbitrary, grossly unfair, unjust or idiosyncratic, or non-transparent treatment as part of the minimum standard of treatment and collecting scholarly writings on the topic.” (Claimant’s Reply, fn. 579). The Claimant is mistaken. After extensive research Mr. Dumberry concludes that neither “discrimination” nor “transparency” form part of the customary international law minimum standard of treatment, Dumberry, P. The fair and Equitable Treatment Standard: A Guide to NAFTA (Kluwer Law International, 2013) Case Law on Article 1105 The Substantive Content of Article 1105 (Chapter 3) pp. 177-180, 218-222 (CA-49).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
173
Counter-Memorial that BC Hydro acted transparently when it negotiated Celgar’s
GBL.731 And Mr. Lester Dyck has provided a detailed explanation of the transparency
built into the GBL negotiation process.732 Rather than acknowledging these facts, the
Claimant chooses instead to maintain its hyperbolic characterizations of the process,
arguing that “there were no rules”,733 that the negotiations to set GBLs transpired “under
an invisible standard,”734 and that BC Hydro intentionally designed the system this way
so that it could discriminate against the Celgar Mill.735
None of this is true. The GBL setting process was the same for everyone and BC 377.
Hydro walked Celgar and other self-generators through all of the factors that would be
relevant for consideration in the GBL negotiation.736 BC Hydro and Celgar reached an
agreement on the GBL, which the BCUC reviewed and accepted.737 Tellingly, Celgar did
not protest that GBL until well after its EPA was in place, but Celgar’s after-the-fact
disappointment with the outcome of the negotiation does not mean the process was non-
transparent. The Claimant’s transparency based claim under Article 1105(1) is without
merit and should be rejected.
731 Canada’s Counter-Memorial, ¶¶ 480-484. 732 Lester Dyck Statement I, ¶¶ 51-91. 733 Claimant’s Reply, ¶ 513. 734 Claimant’s Reply, ¶ 512. 735 Claimant’s Memorial, ¶¶ 663, 668 (“If one were to set out intentionally to design a regulatory scheme that would not meet the minimum standard of treatment, the BC regulatory scheme is a useful template from which to start…This system design enables BC Hydro to discriminate, which should not be regarded as unintentional.”). 736 Lester Dyck Statement I, ¶¶ 51-91. 737 In its Reply, ¶ 517, the Claimant argues that BC Hydro provided no information to the BCUC regarding its GBL determinations, however this is inaccurate. See Lester Dyck Statement I, ¶¶ 133-140.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
174
The Claimant Fails to Establish that BC Hydro Violatedc)the Customary International Law Minimum Standard ofTreatment for Acting in an “Arbitrary” Manner
The Claimant also argues in its Reply that BC Hydro acted in an “arbitrary” 378.
manner contrary to the customary international law minimum standard of treatment, now
on the ground that Celgar was precluded from selling its below-GBL electricity to third
parties.738 But in order to be arbitrary, a measure must have no legitimate purpose, must
not be based on legal standards or must have intentionally ignored due process and proper
procedure.739 The concept of arbitrariness was succinctly described by the International
Court of Justice in the Elettronica Sicula SpA (ELSI) United States v. Italy case:
Arbitrariness is not so much something opposed to a rule of law, as something opposed to the rule of law…it is willful disregard of due process of law, an act which shocks, or at least surprises a sense of judicial propriety.740
The ICJ’s observation in ELSI was endorsed by the Mondev and Loewen NAFTA
Tribunals.741 Other NAFTA tribunals have similarly found that the concept of
“arbitrariness” must be “manifest” in order to breach the customary international law
minimum standard of treatment.742
In its claim regarding alleged restrictions on below-GBL sales to third parties, the 379.
Claimant not only asks the Tribunal to accept its own subjective definition of
arbitrariness, which does not come close to what past tribunals have required, but it also
738 Claimant’s Reply, ¶ 520. 739 Joseph Charles Lemire, v. Ukraine (ICSID Case No. ARB/06/18) Decision on Jurisdiction and Liability, 14 January 2010, ¶ 262-263, RA-69. 740 Elettronica Sicula S.P.A. (ELSI) (United States of America v. Italy), Judgment of 20 July 1989, I.C.J. Reports 1989, p. 15, ¶ 128, RA-70. 741 Mondev International Ltd. v. The United States of America (ICSID Case No. ARB(AF)/99/2) Award, 11 October 2002 (“Mondev - Award”), ¶ 127, RA-30; Loewen - Award, ¶ 131, RA-22. 742 Glamis - Award, ¶¶ 625-626, RA-15; Cargill - Award, ¶ 291-293, RA-6; Thunderbird - Award, ¶¶ 194, 197, RA-42.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
175
ignores the facts. As Canada has explained above, BC Hydro did not preclude the
Claimant from selling its below-GBL electricity to third parties. Unlike with every other
EPA BC Hydro signed a Side Letter Agreement with the Claimant allowing it to sell
below its GBL with approval from the BCUC who determined that “Celgar is free to sell
all or a portion of its generation below the BC Hydro GBL in the market.”743 The
Claimant thus has no grounds upon which to suggest that BC Hydro has precluded it
from selling its below-GBL electricity to third parties. For these reasons alone, the
Claimant has failed to establish that Canada has breached any prohibition against
arbitrary behaviour under Article 1105(1).
The Claimant Fails to Establish that BC Hydro Violatedd)the Customary International Law Minimum Standard ofTreatment for Acting in a “Grossly Unfair, Unjust orIdiosyncratic” Manner
Finally, the Claimant argues that BC Hydro acted in a “grossly unfair, unjust, and 380.
idiosyncratic” manner contrary to the customary international law minimum standard of
treatment, alleging that BC Hydro used its “unequal bargaining power” to withhold
information from the Claimant in order to provide favorable deals to other mills on the
basis of their “political connections,”744 that BC Hydro set the GBL for the Celgar Mill in
a “highly idiosyncratic context,”745 and that BC Hydro’s decision to “preclude[] Celgar
from selling its below-GBL electricity to any third party” was “singularly
idiosyncratic.”746
Canada has already explained in its Counter-Memorial that “[t]he Claimant 381.
provides no support for these serious accusations of impropriety and political
743 BCUC, Decision G-188-11, p. 49, R-275. 744 Claimant’s Memorial, ¶ 668. 745 Claimant’s Reply, ¶ 511. 746 Claimant’s Reply, ¶ 520.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
176
interference.”747 In reply, the Claimant asserts that “[t]he evidence on which Mercer
relies…speaks for itself,”748 but it fails to provide any evidence of impropriety or political
interference. The Claimant fails to mention that it requested that the B.C. Government
search the offices of several provincial Ministers for documents, presumably to support
such allegations that the province did so and that it found no responsive documents.749
Likewise, the Claimant fails to explain how the GBL setting process for the 382.
Celgar mill was “highly idiosyncratic.”750 As Mr. Dyck explains in his witness
statement,751 and as both the expert reports of Dr. Rosenzweig752 and Mr. Stockard753
confirm, the GBL setting process was the same for every proponent in the Bioenergy Call
for Power Phase I and every subsequent call for power. Nor was section 7.4(b) in
Celgar’s EPA “singularly idiosyncratic.” As Mr. Scouras has explained in his first and
second witness statements,754 the same provision was applied to everyone, with the
exception of Celgar, who received an accommodation through the Side Letter
Agreement. As with all of the other complaints lodged against BC Hydro, this one must
be rejected. There was nothing “grossly unfair, unjust, and idiosyncratic” about the GBL
negotiation process.
747 Canada’s Counter-Memorial, ¶ 487. 748 Claimant’s Reply, fn. 591. 749 Letter from Michael Shor to Michael Owen, Re: Mercer International Inc. v. Canada, Mercer Response to Canada’s Document Request Objections, 17 May 2013, enclosing Claimant’s Redfern Schedule, Document Requests, 1.5, 3.4, 3.5.1, 3.5.2 and 4.5, pp. 22-23, 44-47 and 76-77, R-564. 750 Claimant’s Reply, ¶ 511. 751 Lester Dyck Statement I, ¶¶ 35-91; and Lester Dyck Statement II, ¶ 30. 752 NERA Expert Report, ¶¶ 48-56. 753 Pöyry Expert Report I, ¶¶ 98-99, 120-121, 136 and 153-154; Pöyry Expert Report II, ¶¶ 63-64, 96-98, 102-104, 108-110 and 111. 754 Jim Scouras Statement I, ¶¶ 52-65; Jim Scouras Statement II, ¶¶ 34-40.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
177
2. The Claimant Fails to Establish a Breach of Article 1105(1) due tothe Failure to Provide a “Stable Regulatory Environment”
In its Memorial, the Claimant argued that at the time of its investment, “the only 383.
official governmental pronouncement regarding self-generation was BCUC Order G-38-
01…[which] did not apply to FortisBC or to Celgar”755 and that it had “various legal
protections” under the UCA and the 2002 Heritage Contract to implement its “Arbitrage
Project.”756 Canada explained in its Counter-Memorial that the customary international
law minimum standard of treatment under NAFTA Article 1105 does not entitle the
Claimant to a “stable regulatory framework,”757 and that in any event FortisBC informed
the Claimant that there was only a 50 percent chance that the BCUC would approve its
Arbitrage Project.758 It also appears to have been reflected in the Claimant’s own
assessment of the regulatory risks associated with this project.759 The Claimant was
under no illusion as to the regulatory environment in which it was operating.
In its Reply, the Claimant maintains that it was entitled to a stable regulatory 384.
environment under NAFTA Article 1105, but rather than respond to the overwhelming
evidence that it knew well the regulatory risks associated with the Arbitrage Project, it
now founds its claim on an entirely different allegation−−specifically that the GBL
regime itself was a violation of customary international law because there was “no
written GBL standard or guidelines”760 and it was thus “unstable.”761
755 Claimant’s Memorial, ¶ 666. 756 Claimant’s Memorial, ¶¶ 665, 666, 670, 671. 757 Canada’s Counter-Memorial, ¶ 469. 758 Canada’s Counter-Memorial, ¶¶ 473-475; Dennis Swanson Statement I, ¶¶ 62-65; and Dennis Swanson Statement II, ¶¶ 5-12. 759 See Mercer International Group, Celgar Electricity Opportunities, July 2007, at 9-10, R-278.
760 Claimant’s Reply, ¶ 505.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
178
But once again, the Claimant fails to proffer any evidence, let alone cite even a 385.
single case, to support its claim that at customary international law it was entitled to the
“stable regulatory framework” envisioned by its claim—namely one that would require
BC Hydro to have a “written GBL standard or guidelines.”762 In light of the information
that was provided to all participants in the Bioenergy Phase 1 Call for Power,763 Canada
questions what more could have been provided to Celgar. There was a GBL standard,
there was disclosure of the standard and there was consistency in the application of the
standard. The Claimant’s argument here is essentially the same as the argument it
advances in respect of “transparency,” which Canada has already explained is without
merit.764 Neither the GBL regime nor its application by BC Hydro created an unstable
regulatory framework, and certainly not one that could be found inconsistent with
Canada’s obligation under Article 1105(1).
3. The Claimant Fails to Establish that the Acts and Omissions of theBC Ministry of Energy and the BCUC Violated Article 1105(1)
In its Memorial, the Claimant alleged that certain decisions of the BCUC violated 386.
the customary international law minimum standard of treatment under Article 1105(1).
For example, it claimed that BCUC Order G-48-09 was “egregiously discriminatory and
unfair,”765 “utterly perverse,”766 and “arbitrary,”767 and that the BCUC continued “to
draw additional arbitrary distinctions,” citing Order G-198-11 as one example.768 The
Claimant broadens its complaint in the Reply, and now faults the BCUC not just for its
decisions but for also failing to:
761 Claimant’s Reply, ¶ 506. 762 Claimant’s Reply, ¶ 505. 763 Lester Dyck Statement I, ¶¶ 54-59. 764 Lester Dyck Statement I, ¶¶ 51-91. 765 Claimant’s Memorial, ¶ 675. 766 Claimant’s Memorial, ¶ 676. 767 Claimant’s Memorial, ¶ 673. 768 Claimant’s Memorial, ¶ 673.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
179
(1) establish a binding rule of governing self-generation applicable province-wide, (2) review and approve GBL guidelines, (3) require transparency in BC Hydro’s GBL determinations, and (4) exercise substantive oversight over BC Hydro GBL determinations.769
But neither the acts nor the omissions of the BCUC can provide a foundation for a 387.
claim under Article 1105(1). Canada explained in its Counter-Memorial that a challenge
to the decisions of an administrative tribunal is not a valid basis on which to allege a
violation of the minimum standard of treatment.770 The same conclusion should apply to
complaints regarding an alleged failure of an administrate tribunal to act. Professor
Douglas aptly summarizes the customary international law rule: “Denial of justice is the
sole form of international delictual responsibility towards foreign nationals for acts or
omissions within an adjudicative procedure for which the State is responsible.”771 Thus,
if the Claimant has a complaint regarding the acts or omissions of the BCUC, it does not
belong in this forum. Such a complaint should have first been raised before British
Columbia’s domestic courts and were not. As a State cannot be held liable for the
alleged failings of its legal system when the system has not been given the full
opportunity to correct the defects that are complained of,772 the Claimant’s complaints
regarding the acts and omissions of the BCUC cannot serve as the foundation for a claim
under Article 1105(1).
769 Claimant’s Reply, ¶ 477. 770 Canada Counter-Memorial, ¶ 489. 771 Zachary Douglas, “International Responsibility for Domestic Adjudication: Denial of Justice Deconstructed”, International and Comparative Law Quarterly (ICLQ), pp. 29 and 34, RA-77. 772 See e.g. Christopher Greenwood, “State Responsibility for the Decisions of National Courts,” in Issues of State Responsibility before International Judicial Institutions, pp. 55-73, RA-71. In this regard, NAFTA Tribunals have repeatedly affirmed that they are not courts of appeal. See Mondev - Award, ¶ 136, RA-30 (“[I]nternational tribunals are not courts of appeal”); Robert Azinian, Kenneth Davitian, & Ellen Baca v. The United Mexican States (ICSID Case No. ARB(AF)/97/2) Award, 1 November 1999, ¶ 99, RA-72 (A claimant cannot “seek international review of the national court decisions as though the international jurisdiction seized has plenary appellate jurisdiction”); Loewen - Award, ¶ 134, RA-22 (“[A] NAFTA claim cannot be converted into an appeal against the decisions of municipal courts”); Waste Management II, ¶ 129, RA-47 (“[T]he Tribunal would observe that it is not a further court of appeal”); Thunderbird - Award, ¶ 125, RA-42 (“[I]t is not the Tribunal’s function to act as a court of appeal”).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
180
Perhaps more importantly, the Claimant,773 and Dr. Fox-Penner,774 do not appear 388.
to understand the BCUC’s role or the regulatory framework in British Columbia.775 Mr.
Bursey explains that the BCUC has adopted an approach of regulating only when
required so as not to impede competitive markets.776 He also explains that the B.C. Court
of Appeal has found that the BCUC’s legal authority is limited and that it cannot usurp
the role of public utilities in areas such as resource planning (i.e., procurement).777 In this
respect, the BCUC does not have a U.S-style “command” and “control” approach to the
regulation of public utilities.778
Mr. Bursey and Mr. Les MacLaren explain that the BCUC’s use of principles as 389.
opposed to attempting to dictate the manner in which GBLs were set was reasonable and
appropriate779 given the BCUC’s limited legal authority,780 the small number of self-
generators that were initially involved and the technical and operational complexity of
each of these self-generators.781 Mr. Bursey also observes that industrial self-generators
have historically requested that the BCUC let these customers negotiate a baseline or a
773 Claimant’s Reply, ¶ 477. 774 See, e.g., Fox-Penner Report, ¶¶ 88-97. 775 Les MacLaren Statement II, ¶¶ 23-27. 776 David Bursey Expert Report, ¶¶ 21-22. 777 David Bursey Expert Report, ¶ 51(f); See also British Columbia Hydro and Power Authority v. British Columbia Utilities Commission, [1996] B.C.J. No. 379, 20 B.C.L.R. (3d) 106, 71 B.C.A.C. 27, R-73; Les MacLaren Statement II, ¶ 24. (“In the case of utilities, the onus is on the utility to seek out least cost supply, and for the BCUC to examine the resulting EPAs under section 71 of the Utilities Commission Act … The BUCC, however, is only empowered to accept these EPAs or find them unenforceable, in whole or in part, under this provision. It has no authority to dictate the terms of an EPA.”) 778 David Bursey Expert Report, ¶¶ 52 and 66. (“Dr. Fox-Penner’s perspective that the BCUC did not follow best regulatory practice is based on his view that the BCUC should intervene and direct the market and utility-customer relationship more aggressively than it did. His perspective is not consistent with the British Columbia public utility regulatory regime and the case law that governs the BCUC in the exercise of its mandate.”) 779 David Bursey Expert Report, ¶¶ 63 and 65. 780 David Bursey Expert Report, ¶¶ 67-68; Les MacLaren Statement II, ¶ 25. 781 David Bursey Expert Report, ¶¶ 78-80; Les MacLaren Statement II, ¶ 25.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
181
GBL directly with their utility782—an approach that the Claimant has also advocated for
before the BCUC.783
The Claimant raises similar allegations with respect to the Ministry of Energy’s 390.
supposed failure to regulate in a manner tailored to its liking.784 The Ministry, however,
is only responsible for providing broad policy guidance in the province.785 The Claimant
may dislike the fact that BC Hydro is afforded some latitude in this context but this is not
a licence to criticise Ministry and the BCUC for failing to discharge regulatory
responsibilities that they do not have.
Finally, Canada observes that when Ministry of Energy did intervene before the 391.
BCUC in Order G-202-12 proceeding to advocate that the BCUC adopt a province-wide
approach to GBLs,786 it was the Claimant who successfully opposed this position.787
782 David Bursey Expert Report, ¶¶ 69 and 74. 783 See Letter from Kim Moller, Sangra Moller LLP to Erica M. Hamilton, Commission Secretary, Re: Zellstoff Celgar Limited Partnership Complaint Pursuant to Section 25 of the British Columbia Utilities Act (the “Act”), 25 March 2011, p. 3, R-565. (“Celgar also believes that the process for establishing a service agreement [with a GBL] between FortisBC and Celgar should be similar to that undertaken by BC Hydro in its service area – that is, the process should involve the customer, the utility, the Commission and no others. In the BC Hydro service area, since the implementation of the Clean Energy Act … many of the agreements in which GBLs are established are no longer even subject to Commission review (see the Howe Sound Pulp and Paper transaction discussed in Appendix B), and many of those that have been filed in past years were not made subject to comment or review by ratepayers or other intervenors. Rather, BC Hydro has simply filed the agreement for the Commission’s approval. Celgar submits that a similar process relating to agreements that establish a GBL and a Contract Demand should apply in the FortisBC service area.”) 784 Claimant’s Reply, ¶ 477. 785 Les MacLaren Statement I, ¶¶ 17-22 786 See Letter from Les MacLaren, Assistant Deputy Minister, to Erica Hamilton, Commission Secretary, Re: FortisBC Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (Compliance Filing to Order G-188-11), 22 June 2012, pp. 3-5, R-575. 787 Letter from Kim Moller, Sangra Moller, to Erica Hamilton, Commission Secretary, RE: Zellstoff Celgar Limited Partnership (“Celgar”) – FortisBC Inc. Project No. 3698675/Order G-54-12; Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (“Compliance Filing to Order G-188-11”), 10 August 2012, enclosing Letter from Brian Merwin to Erica Hamilton, Commission Secretary, Re: Zellstoff Celgar Limited Partnership (“Celgar”) and Order G-54-12 – FortisBC Inc. (“FortisBC”) Guidelines for Establishing Entitlement to Non-PPA Embedded Cost Power and Matching Methodology (the “Guidelines”) – Compliance Filing to Order G-188-11, 10 August 2012, pp. 3-7, R-499. (“[R]ecent Commission Orders G-156-10 and G-188-11 have resulted in the recognition of
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
182
D. Conclusions
The Claimant has attempted to convert every one of its complaints regarding the 392.
GBL regime in British Columbia into a violation of the minimum standard of treatment.
But aside from misrepresenting the applicable standard of treatment under Article
1105(1), its claims are really no more than a request that the Tribunal find Canada liable
because of its disappointment with the outcome of a negotiation process in which it
voluntarily engaged. Absolutely none of the Claimant’s claims have a place before this
Tribunal, let alone as the basis for a claim under Article 1105(1), and they should all
accordingly be rejected.
VI. DAMAGES788
The Claimant puts at issue two measures. The first is an alleged “restriction” 393.
placed on the Claimant by both BC Hydro and the BCUC that prevents it from selling its
below-GBL electricity. Specifically, the Claimant alleges that BC Hydro unlawfully
added a clause into the Claimant’s EPA preventing it from selling below-GBL electricity
to third parties (section 7.4(b)) and that the BCUC, through its Order G-48-09, unlawfully
certain rights afforded Celgar to utility service within the existing regulatory framework – without the need for broader policy review. The Ministry and BC Hydro chose not to seek reconsideration of, or appeal of those Orders. They should not now be entitled to question or impede the implementation of those Decisions in these compliance proceedings on the premise that a broader Province-wide policy is now required …”) 788 Before proceeding, Canada addresses the preliminary issue of its position on the level of certainty required for a successful damages claim under NAFTA. Canada set out its position clearly in its Counter Memorial when it argued that a claimant must “establish the quantum of its loss with sufficient certainty” (¶ 495). Based on the applicable jurisprudence, Canada concluded that the quantum alleged “must be probable and not merely possible”, and thus not “remote or speculative” (¶ 495). Canada explained that the standard is the “preponderance of evidence” or the “balance of probabilities” (Counter Memorial, footnote 944). Even the Claimant admits that the parties agree on that point (Claimant’s Reply, ¶ 537, and footnote 614). Nevertheless, in a different paragraph of its Reply (¶ 538), the Claimant misrepresents Canada’s position when it says that “Canada’s main focus is on the certainty of damages, with its damages expert Dr. Rosenzweig dismissing virtually every number on which Mr. Kaczmarek relies as “speculative” simply because it is uncertain. But the damages standard does not require certainty.” There is nothing, however, in either Canada’s Counter Memorial or NERA’s first expert report advocating for a legal standard of certainty for the proof of damages. Indeed, when the Claimant makes this bald allegation in its Reply, it does not point to any supporting passages in Canada’s materials because none exists. In any event, Canada repeats the position set out in its Counter Memorial (¶¶ 504-509, and NERA Expert Report, ¶¶ 128-132) that the Claimant has not met the requisite level of certainty in order to establish its damages claims.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
183
prevented the Claimant from having access to “embedded cost power” that it could use to
replace electricity it wanted to sell to third parties. In light of the restriction on below-
GBL sales, the Claimant alleges that “BC deprived Celgar of additional profit it could
have earned, based on the difference between the value of those additional electricity
sales and the cost of embedded cost replacement electricity.”789
The second measure concerns the setting of the Claimant’s GBL by BC Hydro for 394.
the purpose of the Claimant’s bid into the Bioenergy Call for Power. The Claimant
alleges that, “BC Hydro set Celgar’s GBL too high”790 and thus should be compensated
for the difference between that and a “proper GBL”791 under the EPA. To this end, the
Claimant proffers eleven alternative GBLs for the Tribunal’s consideration in the
quantification of damages.
The Claimant’s entire damages assessment is premised on BC Hydro procuring 395.
additional electricity from the Claimant. While the Claimant alleges that it “makes no
claim that BC Hydro was required to purchase Celgar’s below-load electricity,”792 its
entire damages quantification is founded on that proposition. In essence, the Claimant
asks to be compensated for the refusal of its “Arbitrage Project” under the Bioenergy Call
for Power even though it acknowledges that the refusal of that project was not a breach of
the NAFTA.793
Canada has divided this portion of its Rejoinder into three sections. In Part A, we 396.
explain how the Claimant’s damages related to its below-GBL self-generation are
unfounded. In Part B, we explain how the Claimant’s damages related to its alternative
GBL scenarios are meritless, and summarize the methodological and calculation errors in
789 Claimant’s Reply, ¶ 528. 790 Claimant’s Reply, ¶ 553 791 Claimant’s Reply, ¶ 553. 792 Claimant’s Reply, ¶ 36. 793 Claimant’s Reply, ¶ 36.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
184
Navigant’s second report. Finally, in Part C, we explain how the Claimant does not
independently quantify its Article 1105 damages claim.
E. The Claimant’s Damages Related to Celgar’s Below-GBL Self-Generation are Unfounded
The Claimant alleges that it has effectively and unlawfully been prevented from 397.
selling its below-GBL electricity to BC Hydro or third parties through section 7.4(b) of
the EPA and BCUC Order G-48-09.794 As Canada explained above, the Claimant grossly
mischaracterizes these measures795 – the fact that the Claimant has not yet been able to
sell any of its below-GBL electricity is entirely its own making.796 It is axiomatic to say
that a claimant is not entitled to damages in this context.797
Putting these problems aside, the Claimant’s allegations of loss nonetheless fail 398.
for three reasons:
Celgar had no financially viable market for its below-GBL energy;
BC Hydro would not have purchased Celgar’s below-GBL electricity;
The 1991 Ministers’ Order requires Celgar to use its 52 MW turbine to serve itsown load.
794 It is important to note that, in its Rejoinder, Mercer has now abandoned a separate damages claim under BCUC Order G-48-09. In its Reply, Mercer concedes that it “does not claim additional or separate damages resulting from Order G-48-09’s net-of-load restriction, because, as Canada correctly contends, the
(Reply, ¶ 205). 795 See Measures at Issue section above. 796 Dennis Swanson Statement II, ¶¶ 37-38; and Jim Scouras Statement II, ¶ 40. 797 ILC Draft Articles, Article 39, Commentary 2, RA-19; MTD Equity Sdn. Bhd. v. Chile (ICSID No. ARB/01/7), 25 May 2004, Award, ¶¶ 242-243, RA-74; MTD Equity Sdn. Bhd. & MTD Chile S.A v. Chile (ICSID No.ARB/01/7), Decision on Annulment, ¶¶ 93-101, RA-75; and Bogdanov v. Republic of Moldova, Arbitration Institute of the Stockholm Chamber of Commerce (September 22, 2005), ¶ 5.2, RA-76.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
185
1. Celgar had No Financially Viable Market for its Below-GBLEnergy
Canada’s Counter-Memorial emphasized the lack of evidence underpinning the 399.
Claimant’s damages case, particularly with regard to: (1) customers the Claimant could
have identified for its below-GBL electricity; (2) concrete commitments to a given
amount of electricity; (3) any contract it would have entered into; (4) its capability of
obtaining a permit from the National Energy Board allowing it to export electricity; and
(5) its capability of obtaining transmission access to deliver its electricity at economical
rates.798
Rather than provide the requested evidence in its Reply, the Claimant instead 400.
argues that below-GBL sales to third parties is proven by a submission that BC Hydro
made to the BCUC leading up to Order G-48-09.799 In that submission BC Hydro
estimated the potential cost that could be incurred on an annual basis to generate power
under its PPA with FortisBC, so that the Claimant could engage in its arbitrage scheme.
But the logic of the Claimant’s argument does not follow – that BC Hydro may have
incurred costs to replace the power the Claimant would arbitrage is hardly proof that the
Claimant would have been in a position – absent the challenged measures – to sell this
power to market for profit.800 More importantly, as will be seen below, empirical data in
fact proves that this would have not been the case (and is still not the case in light of
market conditions).
Although the Claimant files a new witness statement from Mr. Robert Friesen, he 401.
offers little insight into any actual third party sales opportunities that may have existed
798 Canada’s Counter-Memorial, ¶ 507. 799 Claimant’s Reply, ¶ 546. 800 In its Reply, the Claimant alleges that Canada should be “estopped” from providing the Tribunal with evidence that no third party sales were available in light of BC Hydro’s submission to the BCUC. The Claimant’s estoppel argument is without merit. The Claimant correctly identifies the test for estoppel under international law. It fails, however, to explain how it relied on BC Hydro’s statement that it could incur costs if the Claimant engaged in arbitrage to its detriment. See Claimant’s Reply, ¶ 548, fn 621.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
186
for the Claimant at the relevant time. In fact, the Claimant merely repeats the same
unsupported allegations that it made in its Memorial, i.e., that it had targeted
as a potential buyer of below-load electricity;801 and that in 2008,
NorthPoint had identified “opportunities” for contracts on Mid-C at
prices in excess of $100/MWh. ]802
The Claimant’s damages expert, Mr. Kaczmarek, also fails to provide any 402.
additional evidence despite Canada’s requests and merely reiterates his unsubstantiated
assertion that the Claimant could have sold into any number of renewable energy
markets, including: Washington State; Oregon State; the State of California, and the
provinces of Ontario and Quebec.803 But merely naming these jurisdictions as
“possibilities” is hardly proof that opportunities for the sale of renewable energy actually
existed.
Neither the Claimant nor its expert is capable of proffering concrete evidence to 403.
support their claims because such evidence does not exist. In fact, Canada demonstrates
below that: (a) while prices for electricity at Mid-C may have yielded profitable
opportunities in 2008 (a point that the Claimant emphasizes),804 none of the challenged
measures in this arbitration prevented Celgar from seizing these opportunities at that
time. More importantly, prices thereafter decreased dramatically, thus eroding the
Claimant’s opportunity to make profitable sales to third parties (i.e. sales at market prices
sufficiently large to cover the cost of replacement electricity from its utility and other
costs associated with transporting the electricity to market); (b) the scarcity of available
firm transmission capacity is such that Celgar cannot sustain long-term sales contracts;
and (c) the Claimant had no sales opportunities to any of the “renewal energy markets”
listed by Mr. Kaczmarek, or anywhere else in the Western Interconnection grid.
801 Claimant’s Reply, ¶ 566. See also Claimant’s Memorial, ¶ 298. Navigant Report II, ¶ 71. 802 Claimant’s Reply, ¶ 567. 803 Navigant Report I, ¶ 102; and Navigant Report II, ¶¶ 71-72 and 80-83. 804 Claimant’s Reply, ¶¶ 567-568.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
187
Celgar Cannot Make Profitable Sales at Mid-Ca)
In its Reply and supporting statements, the Claimant provides no information 404.
relating to the power prices at Mid-C other than that indicated in the witness statements
of Mr. Merwin and Mr. Friesen. Mr. Merwin’s testimony indicates that in mid-2008,
prices at Mid-C exceeded $100/MWh.805 Mr. Friesen testifies that sales opportunities at
that time were “very real,” but provides no further details on what those opportunities
might have entailed.806
Canada thus sought the assistance of Mr. Dean Krauss, currently of NorthPoint 405.
and a former colleague of Mr. Friesen’s, who testifies that the opportunities to which Mr.
Friesen and Mr. Merwin refers would have lasted, at most, three months. Mr. Krauss
states that within NorthPoint Mr. Friesen “was generally responsible for short term
electricity transactions which would include spot, monthly and quarterly (sometimes
referred to as “multi-month”),807 and consistent with Mr. Friesen’s portfolio, 808
The profitability of any transaction concluded thereafter would depend on the evolution
of Mid-C prices. But Mr. Michael MacDougall of Powerex indicates that Mid-C prices in
2008 were abnormally high since electricity prices are generally correlated to the price of
natural gas, and North America expected a shortage of conventional natural gas around
that time.809 However, in light of the 2008 recession and a significant decrease in the
price of natural gas,810 the market data provided by Mr. MacDougall indicates that the
daily prices of electricity at Mid-C plummeted from for around per MWh on
805 Brian Merwin Statement I, ¶ 83. 806 Robert Friesen Statement I, ¶ 9. 807 Dean Krauss Statement I, 31 March 2015 (“Dean Kraus Witness Statement”), ¶ 11. 808 Dean Kraus Statement I, ¶ 24. 809 Michael MacDougall Statement I, ¶ 59. 810 Michael MacDougall Statement I, ¶¶ 59-60.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
188
July 8, 2009 to approximately per MWh on January 27, 2009.811 Prices for
forward sales (i.e., longer term transactions) also decreased correlatively.812
Most importantly, Celgar was not in a position to enter into long-term market 406.
sales of electricity during the summer of 2008 because its PSA with FortisBC was not yet
in force, and without the PSA, it could not purchase the replacement power it needed in
order to sell its entire generation to market. Although Mr. Merwin states these
opportunities were identified “(i)n mid 2008, once we were finalizing our agreement with
FortisBC”,813 Mr. Merwin is also aware that Celgar and FortisBC had both agreed that
they should first seek regulatory approval from the BCUC to gain business certainty with
respect to the PSA.814 In fact, the PSA contained a provision making notional sales to
Celgar conditional on first obtaining the BCUC’s approval.815 That Celgar could not
secure this agreement early enough to take advantage of opportunities yielded by the
unusually high prices at Mid-C is not attributable to Canada.
The Claimant contends that the exclusivity clause in Section 7.4(b) of its EPA 407.
with BC Hydro and BCUC Order G-48-09 prevented Celgar from selling below-GBL
electricity to third parties at the remarkably high prices in mid-2008. However, the EPA
was signed on January 27, 2009, and BCUC Order G-48-09 was issued on May 6, 2009.
Even if these measures could be characterized as imposing a restriction on below-GBL
811 Market Data Workbook, Daily Peak MidC Price (by Day), data provided by the US Energy Information Administration, R-444. See Michael MacDougall Witness Statement, ¶¶ 61, 62. See also Dean Krauss Statement I, ¶ 24. 812 Michael MacDougall Witness Statement, ¶ 62. 813 Brian Merwin Statement II, ¶ 25. 814 Canada’s Counter-Memorial, ¶ 211; Dennis Swanson Statement II, ¶ 10; Don Debienne, Personal Notes, April 18, 2008, R-491. FortisBC had previously explained to the Claimant that there was no legal requirement to file the PSA for approval with the BCUC. 815 Canada’s Counter-Memorial, ¶ 240; FortisBC-Zellstoff Celgar Power Supply Agreement, 21 August 2008, Section 15.1 R-248: “Exporting Electrical Generation Output. The obligations of Celgar and FortisBC hereunder all shall be subject to the satisfaction of each of the following conditions: … (c) all necessary approvals of the BCUC of the Power Agreements, including the BCUC Acceptance, shall have been obtained”.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
189
sales, the prices at Mid-C were at that time insufficiently high to even cover the costs of
the Claimant’s replacement electricity (even at FortisBC’s “traditional embedded cost
rates”816) and other transmission costs,817 let alone to make a profit.
After analyzing actual market data, Canada’s expert Dr. Rosenzweig confirms 408.
that, “between 2009 and 2013, Mid-C rates were quite consistently below Celgar’s cost
of replacing its generation to meet load, even if it were allowed to take power under
FortisBC’s embedded cost Rate Schedule 31”.818 With respect to future Mid-C prices he
concludes:
current forward rates for the Mid-C market are well below the costs that Celgar would incur to sell in that market. While forwards markets are not always a perfect representation of future spot prices, they are generally the best available data. Absent a tectonic shift in the Mid-C market or in FortisBC embedded cost rates, this relationship seems unlikely to invert.819
816 Claimant’s Reply Memorial, ¶ 228. 817 Dennis Swanson of FortisBC indicates that, in the first half of 2009, it would have cost Celgar C $39.07 per MWh for FortisBC to supply the first 36 MWh of electricity, in addition to a corresponding monthly demand charge of C $5.370 per MVA. It would have also cost Celgar something in the range of C $20.89 to C $218.04 per MWh to supply the remaining 4 MW of power for Celgar to sell its entire below-load energy to the market. In addition, the Claimant would have been responsible for the payment of Scheduling fees of C $0.86 per MWh and Reactive and Voltage control charges of C $0.89 per MWh. When adding the transmission costs, line losses and NorthPoint’s brokerage fees, it is evident that Mid-C prices would not have warranted Celgar entering into market sales while facing such costs. See Dennis Swanson Second Statement, ¶¶ 22-24; Michael MacDougall Witness Statement, ¶ 56; Dean Krauss Witness Statement, ¶ 25. See also Market Data Workbook, Daily Peak MidC Price (by Day), data provided by the US Energy Information Administration, R-444. 818 NERA Expert Report II, ¶ 149. 819 NERA Expert Report II, ¶ 150.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
190
Figure 3: Annual Mid-C Forward Price and Forecasted FortisBC RS-31 Tariff 2016 through 2020
In light of the overwhelming evidence to the contrary, the Claimant’s assertion 409.
that it could have entered into long-term sales of its below-GBL electricity to third parties
on the Mid-C market for profit is entirely false.
Celgar Does Not Have the Required Transmission Rights inb)Order to Sustain Profitable Sales in the US in the Long-Run
The Claimant faces additional barriers to the sale of its below-GBL electricity to 410.
third parties. For Celgar to deliver its power to a U.S. buyer, at Mid-C or any other
agreed-upon location in the United States, it must obtain the necessary transmission
rights from its plant to the point of delivery. In addition to transmitting over FortisBC’s
and BC Hydro’s transmission networks, this process entails securing the required
transmission access outside of British Columbia and into the United States.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
191
In its Reply, the Claimant asserts that it could have obtained the required 411.
transmission, relying on the statement of Mr. Friesen and the expert report of Mr.
Kaczmarek to support its assertion.820 Mr. Friesen, however, merely states that such
transmission was available “out of British Columbia,”821 but proffers no support for his
statement. Moreover, the only evidence on which Mr. Kaczmarek relies is data provided
by the Bonneville Power Administration, which allegedly shows that “adequate
transmission capacity appears to have existed for Celgar to export 40 MW of below load
self-generated electricity during 2008-2009.” On this basis, Mr. Kaczmarek concludes
that the Claimant could have secured long-term transmission capacity.
Mr. MacDougall of Powerex explains, however, that while there may have been 412.
some transmission capacity going “out of British Columbia” (i.e., from the point of
receipt in BC until the BC/US border), there was too little firm transmission capacity
available into the US (i.e., from the BC/US border onwards) necessary to sustain long-
term sales. In fact, it is not sufficient to get the electricity to the BC/US border; rather, “it
takes a continuous path from the source to the point of delivery to affect the delivery of
electricity at the quality of service required by the buyer”.822
Moreover, he explains that Mr. Kaczmarek misinterprets the data provided by the 413.
Bonneville Power Administration and in fact long-term firm transmission capacity into
the U.S. was (and is) incredibly scarce.823 For instance, Mr. Krauss explains that, when
NorthPoint performed hourly sales of Celgar’s surplus energy into the US, it typically
820 Claimant’s Reply, ¶ 569, Friesen Witness Statement, ¶ 11, Second Navigant Report, ¶¶ 73-78. 821 Friesen Witness Statement, ¶ 11. 822 In the case where power is exported out of British Columbia into the United States, the transmission facilities are owned and operated by different entities. For example, on the B.C. side transmission facilities are operated by BC Hydro and on the U.S. side by the Bonneville Power Administration. The electrons cannot be held at the border until transmission capacity becomes available, but must be delivered on a continuous basis from source to sink. Reservations for transmission services will be required on both the Canadian side and on the U.S. side of the border in order to send electricity from the point of receipt and the point of delivery. See Michael MacDougall Witness Statement, ¶ 42. 823 Michael MacDougall Statement, ¶¶ 43-46.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
192
used non-firm transmission rights.824 This is consistent with internal Mercer documents
which indicate that “… it is the Company’s view that … trying to sell significant volumes
of power outside the province has substantial challenges because of the lack of
transmission space.” 825
Finally, Mr. MacDougall explains that the Claimant could have turned to non-414.
firm transmission capacity in order to enter into sales of power in the United States.
However, unlike firm transmission which provides the right holders with access to the
transmission path,826 non-firm transmission poses a high risk of curtailment, particularly
when electricity prices are high and transmission services in high demand.827 Even if the
Claimant could find a long-term contract for the sale of its electricity into the U.S., such
an arrangement would be risky using non-firm transmission as the Claimant would be
liable to pay liquidated damages in case of non-delivery, particularly in periods of peak
demand of transmission.828
Celgar’s Energy Does Not Qualify as a Renewable Energyc)Resource in the NorthWest United States.
The Claimant contends that it had opportunities to sell its below-GBL electricity 415.
as a green or renewable biomass-based resource on the market.829 Mr. Merwin testifies
that “Celgar had targeted as a prospective
buyer of Celgar’s existing generation output, and had engaged in fruitful preliminary
discussions with them.”830 Mr. Merwin, however, provides few further details.
824 Dean Krauss Statement , ¶ 23. 825 Letter from Richard Short to Davide Ure, Re Electricity Sale Contract Accounting, 2 March 2009, at MER00192105, R-566. 826 Michael MacDougall Statement I, ¶ 47. 827 Michael MacDougall Statement I, ¶¶ 49-51. Dean Krauss Statement I, ¶ 18. 828 Michael MacDougall Statement I, ¶ 37. See also Dean Krauss Statement I, ¶ 32. 829 Claimant’s Reply, ¶ 18. 830 Brian Merwin Statement I, ¶¶ 82, 144; Claimant’s Memorial, ¶ 298; Claimant’s Reply, ¶ 566.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
193
Canada thus contacted Puget Sound and was put in contact with its Director of 416.
Strategic Initiatives, Mr. Roger Garrett, who was the Director of Resource Acquisition at
the relevant time. Mr. Garrett has no recollection of the Claimant or its energy projects.831
Further, he confirms that the Claimant’s electricity would not have been an eligible
renewable resource that Puget Sound could have procured under Washington’s
Renewables Portfolio Standard.832
Mr. Garratt’s testimony is also consistent with the explanation provided by Mr. 417.
MacDougall of Powerex on the question of potential opportunities for renewable power
sales in the U.S. Northwest. In his testimony, Mr. MacDougall explains that no lucrative
opportunities exist for sales of renewable power outside of statutory compliance markets
in the form of Renewables Portfolio Standard (“RPS”),833 i.e., regulations requiring
electric utilities to “meet a given portion of their load with renewable energy”.834 But
these markets “typically favour in-state generation… and, for this reason, are often more
difficult to access for any facility located outside the jurisdiction concerned”.835
Mr. MacDougall examined whether the Claimant could have sold its electricity 418.
into any number of renewable energy markets in the United States and Canada.836 He
concluded that it is highly unlikely that Celgar could have made sales of renewable
energy into the markets identified by Mr. Kaczmarek (i.e., Washington, Oregon,
California Ontario and Québec).837 Mr. MacDougall also concludes that no other
831 Roger Garratt Statement, ¶¶ 15-16. While Mr. Garratt executed a Mutual Confidentiality and Nondisclosure Agreement on behalf of Puget Sound with Mercer in 2007, he indicates that signing such agreements is merely a precondition for entertaining discussions with Puget Sound staff, but only those opportunities that warrant further consideration are brought to his attention. Roger Garratt Statement, ¶¶ 11-12. 832 Roger Garratt Statement, ¶ 18. 833 Sometimes also called Renewable Energy Standard (“RES”) 834 Michael MacDougall Statement I, ¶ 30. 835 Michael MacDougall Statement I, ¶ 30. 836 Michael MacDougall Statement I, ¶ 72. 837 See Second Navigant Report, ¶¶ 72, 104.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
194
opportunities for renewable sales existed in the U.S. Northwest and Alberta. His
conclusions are summarized below:
Compliance Markets for Renewable Power Jurisdiction Why Celgar cannot access the Renewable Energy Market Washington From 2006 to 2012, Washington’s RPS specifically excluded black
liquor from the definition of “renewable resources”.838 Even after 2012, facilities that commenced operations before March
31, 1999 are not eligible, except for “qualified biomass energy” plants.839
Celgar’s plant does not fit within the definition of “qualified biomassenergy” because it is not directly interconnected with a qualifying utility in Washington.840
Even if Celgar’s turbine had commenced operations after March 31,1999, it would not have been able to deliver its electricity on a real time basis without shaping, storage or integration services, as required.841
Oregon Facilities that commenced operations before January 1, 1995 are noteligible under Oregon’s RPS. 842
Montana Eligible facilities must be located within Montana or another USstate.
Eligible electricity generated from biomass is limited to facilitieswith a nameplate capacity no greater than 5 MW.843
California Biomass facilities that commenced operations after January 1, 2005are not eligible under the RPS.844
It is, in practice, exceedingly difficult for out-of-country biomassplants to obtain an eligibility status from the California EnergyCommission.845
838 Michael MacDougall Statement I, ¶ 74. Initiative 937 (Washington), Section 4, R-402. 839 Michael MacDougall Statement I, ¶¶ 75-77. Washington Revised Code, Title 19, Section 285-030(12)(a), R-447. 840 Michael MacDougall Statement I, ¶ 77. Washington Revised Code, Title 19, Section 285-030(12)(d), (18), and (19), R-447. 841 Michael MacDougall Statement I, ¶¶ 78-79. 842 Michael MacDougall Statement I, ¶ 81. Senate Bill 838 (Oregon), 2007, Section 2, R-449. 843 Michael MacDougall Statement I, ¶ 82. Montana Code Annotated, Section 69-3-2003(10), R-451. 844 Senate Bill No. 107 (California), Section 3, R-453. 845 Michael MacDougall Statement I, ¶ 86.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
195
Compliance Markets for Renewable Power Jurisdiction Why Celgar cannot access the Renewable Energy Market
The transmission challenges faced by Celgar make it unlikely that autility would purchase Celgar’s power in order to comply with theRPS.846
Arizona Facilities commissioned before January 1, 1997 are not eligibleunder the RPS.847
Colorado Colorado’s RES is designed so as to assign a premium to renewableelectricity generated within the state, which renders imports ofrenewable power unlikely.848
New Mexico Facilities brought into service before July 1, 2007 are not eligible.849 Nevada Nevada’s RPS is designed to afford preference to solar generation,
which makes imports of out-of-state biomass-based generationunlikely.850
Idaho, Wyoming and Utah
There are no compliance markets.851
Alberta Alberta has not put in place an RPS. Regulations exist for the offset of greenhouse gas emission occurring
within the province.852
Ontario and Québec
The transmission costs and line losses over such a long distancemake any profitable sales highly unlikely.853
846 Michael MacDougall Statement I, ¶ 90. 847 Michael MacDougall Statement I, ¶ 91. Arizona Administrative Code, Section R14-2-1802(C), R-459. 848 Michael MacDougall Statement I, ¶ 93. 849 Michael MacDougall Statement I, ¶ 94. 850 Michael MacDougall Statement I, ¶ 95. 851 Michael MacDougall Statement I, ¶ 96. Utah has implemented a renewable portfolio “goal” with no imperative standards. Utilities pursue the renewable energy goals to the extent that it is cost-effective to do so, which renders imports of biomass-based generation from British Columbia highly unlikely. 852 Michael MacDougall Statement I, ¶ ¶ 97-99. 853 Michael MacDougall Statement I, ¶ 100
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
196
2. BC Hydro would not have purchased Celgar’s below-GBLelectricity
In light of the unreality of selling its below-GBL electricity to third parties, the 419.
only way the Claimant can salvage its damages case is to assume that BC Hydro would
procure all of its electricity as firm energy at prices reflect in the EPA.854 As Canada
explained in its Counter Memorial, the Claimant’s assumptions on this point “are beyond
speculative, they are total fantasy”.855
In its Reply, the Claimant concedes that BC Hydro was not “legally obligated to 420.
buy” 856 its below-GBL electricity, but continues to muse that, absent section 7.4(b) and
Order G-48-09, BC Hydro was “highly likely” to have procured all of it.857 However, BC
Hydro refused to procure the Claimant’s below-GBL electricity during the Bioenergy
Call not because of section 7.4(b) (which it agreed to amend in any event) or Order G-48-
09 (which was not yet a measure at the time), but because the electricity did not meet the
terms of the Call. The Claimant’s argument is in effect that BC Hydro was required at the
time to buy into the Claimant’s “Arbitrage Project” even though the Claimant confirms
that the rejection of that project was not a violation of the NAFTA.858 In any event, none
of the reasons proffered by the Claimant support the conclusion that BC Hydro would
have procured all of the Claimant’s electricity.
First, the Claimant argues that it is “highly likely” that BC Hydro would have 421.
procured the Claimant’s entire load out of a supposed fear that the electricity would be
“exported out of the Province”.859 However, neither BC Hydro nor the Province care
854 Navigant Report, ¶ 155. 855 Canada’s Counter Memorial, ¶ 504. 856 Claimant’s Reply, ¶ 36. In a subtler perpetuation of its fantasy, the Claimant merely asserts again that “it is highly likely BC Hydro would have done so rather than let that energy leave the Province”. 857 Claimant’s Reply, ¶¶ 36, 206, 551-563. 858 Claimant’s Reply, ¶ 32. 859 Claimant’s Reply, ¶ 555.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
197
whether the Claimant sells its electricity outside of British Columbia. Mr. Les MacLaren
testifies that:
[T]he province is neutral as to where a purchaser of Celgar’s electricity resides. Whether the electricity remains in BC or is exported out of the province does not matter. BC Hydro is required to achieve electricity self-sufficiency, but individual generators are not discouraged from engaging in exports to the extent that there are opportunities to do so.860
Second, the Claimant suggests that, without section 7.4 and Order G-48-09, 422.
Celgar’s below-GBL electricity “would qualify for purchase by BC Hydro under the very
procurement policies in effect at the time.”861 That is an untrue statement, as Mr.
McLaren explains:
[T]he Ministry of Energy was clear throughout the 2008 Pulp and Paper Self-Generation Working Group process that re-pricing of existing generation would not be supported, and that only incremental or new generation would be acquired. In effect, BC Hydro was policy-barred from acquiring existing self-generation. This policy was also clearly set out in the Bioenergy Phase I Call for Power documentation.862
Third, the Claimant alleges that it would have in fact been “inconsistent with 423.
stated BC policy for BC Hydro not to have purchased Celgar’s additional electricity and
instead allow it to be exported”.863 This is a remarkable statement, which Mr. Scouras
confirms is also untrue:
This would be completely contrary to our GBL-based procurement practice for existing self-generators and would contravene government policy and BCUC rulings dealing with arbitrage. Presuming the BCUC concluded that it was permissible for FortisBC to use PPA energy to facility its customers’ export sales
860 Les MacLaren Statement II, ¶ 16. 861 Claimant’s Reply, ¶ 556. 862 Les MacLaren Statement II, ¶ 19; Jim Scouras Statement I, ¶¶ 40 and 44. 863 Claimant’s Reply, ¶ 558.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
198
does not change the eligibility requirements under BC Hydro’s procurement processes.”864
Finally, the Claimant alleges that BC Hydro has had a consistent practice of 424.
procuring electricity in order to increase its resource stack and would thus likely procure
all of the Claimant’s below-GBL electricity.865
Mr. MacLaren, however, explains that: 425.
it would have been almost impossible for BC Hydro to justify the Celgar EPA to the BCUC if it had to effectively pay twice as much for the same set increase in electricity. The BCUC has in the past rejected a significant EPA on the basis that the agreement was not in the public interest [BCUC Order G-176-06]. It would almost certainly find that this one was not justifiable because of such a price. 866
For these reasons, the Claimant has no basis to even suggest that, absent section 426.
7.4(b) and Order G-48-09, BC Hydro would procure the Claimant’s below-GBL
electricity.
3. The Ministers’ Order Required Celgar to Use the TurbineInstalled in 1993 Expansion to Serve its Own Load
If the Tribunal finds that the Claimant should have been permitted to sell its 427.
below-GBL electricity, the Claimant is still bound by the terms of the Ministers’ Order,
864 Jim Scouras Statement II, ¶ 53. 865 Reply Memorial, ¶¶ 557-561. Moreover, since the publication of its 2008 Long Term Acquisition Plan (LTAP), BC Hydro’s projected energy needs have diminished. BC Hydro now actually manages a surplus of power and is projecting lower demand increases into the future, as set out in its Integrated Resource Plan (2013) at Chapter 4.2.1: “there is no need for incremental resources in the near to mid term of [BC Hydro’s] planning horizon”; at 4.2.2, BC Hydro explored various actions to reduce costs including “[r]educe spending on Independent Power Producer (IPP) resources”; at 4.3.4.1, the forecasts regarding BC Hydro’s long term needs are “uncertain”; however, at 4.3.4.2, “BC Hydro is expected to meet the majority of its [long term] load growth through DSM”, C-298. Claimant’s Reply, ¶ 577. Mercer refers to the 2013 IRP in its Reply (¶¶ 577-578), though it fails to raise this aspect of it, presumably because it does not fit into the narrative Mercer wishes to spin. 866 Les MacLaren Statement II, ¶ 20. See also David Bursey Expert Report, ¶ 135(d)(ii)(c). (“Such procurement would not be in the ratepayer or public interest because it would … fail a prudency review before the BCUC under Part 3 when setting BC Hydro rates, because the energy procurement would simply add costs but not add to the power supply resources.”)
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
199
which requires it to use its original turbine867 to serve its own electricity needs.868 As a
result, even if this Tribunal finds that Order G-48-09 or Section 7.4(b) is a violation of
the NAFTA—and it should not— then the Ministers’ Order would still prohibit Celgar
from selling any electricity generated below Celgar’s GBL as electricity from this turbine
was intended for load displacement.869
In its Reply, the Claimant argues in the alternative that, if any such self-428.
sufficiency commitment arose out of the Ministers’ Order, it could not conceivably have
included any increased generation capacity arising out of Celgar’s self-funded Blue
Goose Project, thus capping the Claimant’s damages at Celgar’s average annual
generation to load (minus sales) for the period 1994 to 2006.870 There is, however,
nothing in the language of the Ministers’ Order that restricts its application in that
manner. Nor has the Claimant provided any evidence to support its contention that the
Ministers’ Order should somehow be limited as the other separate parts of the mill
evolved during the lifespan of the new turbine. Consequently, there is no principled
reason to calculate the Claimant’s alleged damages using this alternative rubric.
F. The Claimant’s Damages Related to its Alternative GBL Scenarios are Unfounded
The Claimant’s second basis for damages concerns the setting of its GBL by BC 429.
Hydro, which it alleges was arbitrary and discriminatory. The Claimant proffers eleven
alternative “GBL Scenarios,” each predicated on the Claimant having a lower GBL in its
867 The Celgar pulp mill has two turbines. The first is a 52 MW turbine that was installed in 1993 which is subject to the Ministers’ Order. Its newer, 48 MW turbine was installed in 2010 and is used to generate electricity that is then sold to BC Hydro under the EPA. 868 In the Matter of an Application by Celgar Pulp Company for an Energy Project Certificate for the Celgar Pulp Mill Expansion, Ministers’ Order dated May 23, 1991 (“1991 Ministers’ Order”) p. 2, R-100; Celgar 1990 EPC Application, R-97. Canada has established the validity of the Order. 1991 Ministers’ Order, p. 2, R-100; Celgar 1990 EPC Application, R-97. Counter Memorial, ¶¶ 173-187 and 499-501; Peter Ostergaard Statement I, ¶¶ 20-22; Les MacLaren Statement II, ¶¶ 40-43; David Bursey Expert Report, ¶¶ 182-185; Denise Mullen Statement I, ¶ 62. 869 1991 Ministers’ Order, p. 2, R-100; Celgar’s 1990 EPC Application, R-97. 870 Reply ¶¶ 541-543. The Claimant estimates that this is equivalent to 249.7 GWh/year.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
200
EPA with BC Hydro. The Claimant thus seeks compensation under the EPA for a higher
volume of electricity that it believes BC Hydro was required to have procured.871 It states
that “if Celgar’s nondiscriminatory GBL should have been lower, it is all but certain that
BC Hydro would have done what it did in every other EPA with a BC self-generator, and
purchased all above-GBL electricity on a firm basis.”872
The Claimant’s alternative GBL damages assessments conflict directly with 430.
NAFTA Article 1108(7)(a), which states that Articles 1102 and 1103 “do not apply to:
(a) procurement by a Party or a state enterprise.”873 The Claimant asks to be compensated
on the basis that the BC Hydro procures more electricity from the Claimant in the EPA.
In light of Article 1108(7)(a), that request must be denied.
Putting aside this fatal flaw of the Claimant’s submission, the Claimant’s 431.
assessment of loss under its “alternative GBL scenarios” is in any event unfounded and
overstated because:
The Claimant’s proffered “GBL options” are arbitrary and have no basis inProvincial procurement policy;
The Claimant wrongly assumes that the EPA would be renewed;
Navigant makes numerous quantification errors in its second report; and
The Claimant ignores the effect of the Ministers’ Order.
Nonetheless, Canada quantifies the Claimant’s damages under its various “GBL 432.
scenarios” to correct for the errors and assumptions that the Claimant makes in these
calculations.
871 Claimant Reply Memorial, ¶¶ 553-554. 872 Claimant Reply Memorial, ¶ 554. 873 NAFTA Article 1108(7)(a).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
201
1. The Claimant’s Proposed GBLs are Arbitrary and Have no Basisin Provincial Procurement Policy
The Claimant proffers eleven alternative “GBL scenarios,” which can be found 433.
under Figure 31 of its Reply.874 The Claimant assertion that Canada violated the NAFTA
in eleven different ways does nothing to add confidence to these claims, most of which
are, in any event, completely arbitrary. For example, the Claimant alleges that it should
be compensated on the basis of a GBL set in 2003 when the Province’s Heritage Contract
was enacted. However, none of the Claimant’s comparator mills had a GBL set at that
date. More egregiously, the Claimant alleges that it should have a GBL of “zero,” and
computes damages upwards of $225 million on that basis. However a zero GBL (along
with the other scenarios) has no connection to BC Hydro’s procurement policies. Rather,
this is simply a demand for preferential treatment in the form of an energy subsidy.875
2. The Claimant wrongly assumes that the EPA would be renewed
Not only does the Claimant assume a lower GBL under the current EPA, they also 434.
assume a renewal of the EPA into perpetuity with the same GBL, the same favorable
green energy prices, and the same quantum of electricity being sold. Canada already
explained that the Claimant’s assumption is highly speculative and without merit.876 By
assuming the renewal of their EPA into perpetuity rather than at the end of its term
(which is the year 2020), the Claimant overstates is damages by $77 million in its zero
GBL scenario.
874 Claimant’s Reply, ¶ 535. 875 Les MacLaren Statement II, ¶ 22. 876 Canada’s Counter Memorial, ¶ 506. In its Counter Memorial, Canada points out that “the Claimant’s EPA with BC Hydro terminates in 2020 and it is highly speculative to assume that BC Hydro will both need and be willing to re-contract with the Claimant at the end of its current EPA term. It is also speculative to assume that the Claimant would receive the same electricity price in a subsequent EPA since market conditions may be different in the future.”
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
202
In its Reply, the Claimant continues its assumption that it will sell to BC Hydro 435.
on identical terms forever. The Claimant’s assumption is unfounded and none of its
arguments have merit.
First, the Claimant argues that BC Hydro will renew the EPA at least once 436.
because the parties originally discussed a 20-year term for the Agreement rather than the
10-year term, which currently holds.877 However, it was the Claimant who requested a
10-year rather than 20-year proposal and the Claimant cannot now request compensation
on the basis that it accepted a 20-year term. It is not at all certain that BC Hydro will
renew Celgar’s EPA, let alone on the same terms as those found in the existing
agreement.878
Second, the Claimant argues that BC Hydro will need to procure additional 437.
electricity in 2020, and thus another EPA is likely. However, BC Hydro’s resource stack
is presently in a surplus situation and it is not clear that it will require the procurement of
additional electricity in 2020.879
Third, the Claimant asserts that BC Hydro’s long term resource plan projects that 438.
50% of the existing bioenergy EPAs will be renewed and that, for a variety of reasons,
Celgar is likely to meet BC Hydro’s renewal requirements.880 The Claimant’s confidence
here is misplaced. To begin with, BC Hydro’s IRP lists cost and price as the overriding
877 Claimant’s Reply, ¶¶ 575-576. 878 NERA Report I, ¶ 132; and NERA Report II, ¶ 157. 879 BC Hydro Integrated Resource Plan (November 2013), Chapter 9.2.4., R-567. Indeed, BC Hydro’s 2013 IRP indicates that “the combined IPP supply and targeted DSM results in BC Hydro having an adequate energy supply until F2028 and adequate capacity supply until F2019”. That same IRP notes that BC Hydro’s future resource needs are more modest than it had anticipated back at the time of its 2008 LTAP. BC Hydro Integrated Resource Plan (November 2013), Chapter 4, at 4.2.1, R-568. Moreover, BC Hydro’s self-sufficiency requirement of 3000 GWh “insurance” energy has since been relaxed. See Les MacLaren Statement I ¶ 80, 880 The Claimant argues that (1) Celgar was the second lowest bidder in the first Bioenergy Call for Power; (2) Celgar’s black liquor is a more reliable energy source than Howe Sound’s and Tembec’s hog fuel and natural gas, and Celgar is one of BC’s most modern mills; and (3) Celgar’s mill is highly responsive to BC Hydro’s power needs. See Claimant’s Reply, ¶¶ 577-578.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
203
considerations with respect to the renewal of an EPA. In that respect, the Claimant’s
second and third reasons for renewal are irrelevant.881 Nor is it clear what the Claimant
means when it asserts that Celgar is “responsive” to BC Hydro’s needs—unless it
believes those needs include repeated regulatory challenges to its procurement practices.
Fourth, the Claimant asserts that it is reasonable to assume that Celgar’s EPA will 439.
be renewed at the price that was then in effect under its EPA because BC Hydro was
willing to agree to a 20 year EPA and price in 2009.882 The Claimant claims that, in
every case where BC Hydro has renewed a bioenergy EPA (e.g. Tembec, Canfor, Howe
Sound), it has paid a higher price for self-generated electricity, which is another reason
why Mr. Kaczmarek has assumed such a price increase in its projection.883 The evidence,
however, again shows that the Claimant is wrong. For instance, when BC Hydro
renewed the SEEGEN bioenergy EPA in 2013, it negotiated a considerably lower
price.884 BC Hydro’s 2013 IRP also predicts that BC Hydro will enjoy “an adequate
energy supply until F2028 and adequate capacity supply until F2019.”885 886
881 Although Celgar was the second lowest bidder in the Bioenergy Call, this is no indication that it will be equally as successful at some undefined point in the future. The Claimant’s assertion in this respect is completely speculative. 882 Claimant’s Reply, ¶ 580. 883 Claimant’s Reply, ¶ 584-585. 884 Letter from Janet Fraser, BC Hydro to Erica Hamilton, Commission Secretary, p.5 and Table 1 (p.7), R-, where BC Hydro and SEEGEN agreed to a firm energy price of $43/MWh on a levelized basis, which is considerably lower than the $60/MWh price contained in the original EPA. http://www.bchydro.com/energy-in-bc/meeting_demand_growth/irp/document_centre/reports/november-2013-irp.html]. Additionally, none of the three EPAs referred to here by the Claimant were renewals; they were either new or replacement EPAs, all of which were entered into in 2009/2010 during the bioenergy call period, prior to the release of BC Hydro’s most recent IRP. 885 BC Hydro Integrated Resource Plan (November 2013), Chapter 9.2.4, R-567. As the Claimant acknowledges in its Reply, BC Hydro’s 2013 IRP indicates that it expects to pay less upon the renewal of its EPAs: “[d]ue to the fact that these are existing projects where the IPP’s initial capital investment has been fully or largely recovered over the initial term of the EPA, BC Hydro expects to be able to negotiate a lower energy price”. (BC Hydro, 2013 Integrated Resource Plan (November 2013), Chapter 4.2.5.1, at 4-15, R-568.) Moreover, NERA observes that because “it is unlikely that Celgar would be able to sell to third parties at a price that was economically attractive” … “renewing with BCH is the only realistic option, and this remains a speculative assumption”. See NERA Expert Report, ¶ 157.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
204
Finally, the Claimant says that BC Hydro is wrong to assume (in its 2013 IRP) 440.
that capital costs of new self-generation would be recovered over the turbine’s first ten
years, since turbines are typically depreciated over a 20 year period, which means that
Celgar will still need its electricity sales income post 2020 to offset such depreciation.887
The problem with the Claimant’s proposition here is that, because Bioenergy Call was a
bidding process, BC Hydro was indifferent to amount of time Celgar believed it would
take to recover the capital costs of its projects.888 In the end, like its claim that Celgar
should have been given a lower GBL, this is simply another attempt by the Claimant
unilaterally to amend Celgar’s 2009 EPA.
3. The Claimant Overstates the Damages Relating to its GBL
Putting aside the fact that the Minister’s Order has the effect or rendering the 441.
Claimant’s damages null and the fact that their alternative GBLs have no causal
relationship with BC Hydro’s procurement policies, if the Tribunal nonetheless
determines that Celgar should have been assigned a lower GBL by BC Hydro and that
BC Hydro was required to procure more electricity from the Claimant, then the damages
are as follows:889
886 The Claimant also suggest in its Reply that bioenergy prices will likely rise due to an expected scarcity of wood fibre. While the cost of wood fibre may be a factor in the energy prices that BC Hydro pays under its biomass EPAs, the overriding consideration for renewal is BC Hydro’s demand/supply balance as well as the need for competitive, cost-effective power. See Claimant’s Reply, ¶ 581; and Brian Merwin Statement II, ¶ 34. 887 Claimant’s Reply, ¶¶ 582-583. 888 Presumably, the Bioenergy bidder included in its bid price the cost of servicing the depreciation of its turbine. Moreover, because 90% of Celgar’s investment in its Green Energy Project was subsidized by a $46.8 million grant from the federal government under the PPGTP, presumably Celgar has already recovered the bulk of its net capital investment through EPA revenues. 889 NERA Expert Report II, Table 1, ¶ 188.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
205
4. Like its First Report, Navigant’s Second Damages Report isFatally Flawed
In its Rejoinder Expert Report, NERA provides a detailed rebuttal to Navigant’s 442.
Second Expert Report. In this section, Canada briefly summarizes NERA’s rebuttal
which concludes that Navigant: (1) fails to quantify how the measures have caused
Celgar to suffer negative competitive effects; (2) continues to rely on speculative data
and assumptions; and (3) reprises old errors and commits new ones.
In its second report, Navigant again picks up the Claimant’s claim that Celgar 443.
suffered negative competitive effects as a result of the impugned measures. It argues that
NERA ignored Navigant’s point that Celgar had been “more exposed to fluctuations in
pulp and paper prices than it would have been absent the Measures”.890 NERA, however,
explains that Navigant’s argument is merely an unsubstantiated theory about the different
890 Navigant Expert Report II, ¶ 30.
Mr. Kaczmarek's Damages Scenario GBL
Mr. Kaczmarek's Uncorrected
Damges
Mr. Kaczmarek's
Corrected Damges
Overstatement in Damages
Percentage Overstatment
(MWh) (C$ '000s) (C$ '000s) (C$ '000s) (%)
No Load Displacement Obligation and/orComparable to Skookumchuck Mill's 1997 EPA 71%
Comparable to Tolko Industries Ltd.'s GBL 148,674 147,019 83,388 63,632 76%
Comparable to Howe Sound's 2010 EPA 77%
Celgar's 2001 generation-to-load (Order G-38-01) 186,123 119,783 67,059 52,724 79%
Levels comparable to Skookumchuck Mill's 2009 EP 79%
Celgar's 2002 generation-to-load (2003 Heritage Contract) 220,022 95,062 52,278 42,784 82%
Celgar's avg. 1994-2006 generation- to-load (Ministers' Order) 249,700 73,213 39,337 33,876 86%
Celgar's 2006 generation-to-load (BC Hydro EPA) 268,200 59,519 31,271 28,248 90%
Celgar's avg. 2005 & 2006 generation-to- load (Before Project Blue Goose) 271,095 57,359 30,009 27,351 91%
Celgar's 2007 generation-to-load (BC Hydro EPA) 326,715 15,074 5,747 9,327 162%
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
206
levels of risk that Celgar might face compared to other mills who are able to sell their
below load electricity. Neither Navigant nor the Claimant’s witnesses have provided any
evidence of the same.891 To the contrary, the facts show that, unlike some of its
competitors, Celgar did not shut down during the economic downturn of 2008-2009.892
Moreover, the evidence that the Claimant does rely on is shown to be inherently biased
and unreliable.893
In its second report, Navigant claims that, while its data might be speculative, that 444.
is only so because it was unable to access actual data due to the impugned measures.894
NERA quite rightly dismisses such an excuse because the evidence is clear that the
requisite firm long-term transmission from BC to external markets was simply not
available to Celgar.895 Notwithstanding Navigant’s reliance on evidence from Mr.
Freisen that Celgar could have accessed such markets, Powerex’s evidence conclusively
points to the contrary.896 Navigant claims that it is not speculative to assume that Celgar
could have sold its below GBL output to BC Hydro because: (1) BC Hydro would have
purchased it rather than have the energy be sold outside of BC; (2) of Celgar’s low
production costs; and (3) Celgar would be an attractive green energy source at a time
when BC Hydro’s energy needs are expected to increase.897 NERA debunks each of
these points in its second report.898
891 NERA Expert Report II, ¶ 123. 892 NERA Expert Report II, ¶ 124. 893 NERA Expert Report II, ¶¶ 127-129. 894 Navigant Expert Report II, ¶ 70. 895 NERA Expert Report II, ¶¶ 145-146. 896 NERA Expert Report II, ¶ 145; Roger Garratt Statement, ¶ 18; Michael MacDougall Statement, ¶ 37. 897 Navigant Expert Report II, ¶¶ 51-59. 898 NERA Expert Report, ¶ 155: i) it is unlikely that Celgar would have found such a purchaser and the replacement cost of energy would not have made arbitrage economically attractive; ii) the other Bioenergy call bidders provided incremental energy for which BC Hydro would not have incurred any supply costs; and iii) Celgar would not be adding any incremental resources to meet its load increases.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
207
In its second report, NERA separates Navigant’s errors into three categories: (1) 445.
the ones in Navigant’s first report that it admits to and corrects in its second report;899 (2)
the ones in Navigant’s first report that it fails to admit are errors (but should);900 and (3)
new errors and errors newly identified in Navigant’s second report.901 We commend the
Tribunal to NERA’s second expert report for detailed discussions on each. In any event,
ignoring that NERA has demonstrated that there is no basis for damages, taken in toto,
this multitude of errors calls into question both the accuracy and the reliability of
Navigant’s damages reports.
899 Under the heading of errors admitted: Navigant failed to account for all of the electricity that Celgar produced, thus artificially lowering Mercer’s profits in its actual scenario, which artificially increased damages (Second NERA Report, Appendix 2, ¶ 3); Navigant used an incorrect date to begin calculating Mercer’s damages (Second NERA Report, Appendix 2, ¶ 4); Navigant committed an arithmetical error in its calculation of the average debt to equity ratio of the comparable companies it chose (Second NERA Report, Appendix 2, ¶ 6). 900 Under the heading of errors repeated but not admitted: Navigant continues to rely on speculative data and assumptions (Second NERA Report, ¶¶ 138-140, 144, 151-153, 155-161); Navigant continues to calculate damages in perpetuity (Second NERA Report, ¶¶ 156-161); Navigant incorrectly assumes that BCH would purchase Celgar’s below-GBL electricity (Second NERA Report, ¶ 155); Navigant fails to consider the cost-causality principle in assessing Celgar’s replacement rate (¶ 135-136); Navigant assumes that Celgar could sell its below GBL electricity to third parties at an economically viable rate (Second NERA Report, ¶¶ 144-153); Navigant ignores the nullifying effect on damages of the Side Letter Agreement between Celgar and BC Hydro (Second NERA Report, ¶ 154); Navigant assumes that Celgar’s EPA with BC Hydro will be renewed in 2020 (Second NERA Report, ¶¶ 156-161); Navigant assumes that a potential third party purchase of Celgar would include debt financing (Second NERA Report, Appendix 2, ¶¶ 9-10); Navigant commits technical errors in its calculation of the cost of equity for the hypothetical purchaser of Celgar (Second NERA Report, Appendix 2, ¶¶ 11-19); Navigant ignores Celgar’s under-delivery penalties in its but-for scenario (Second NERA Report, Appendix 2, ¶¶ 20-23); Navigant continues to rely on Mr. Switlishoff’s BLAP to calculate damages even though he himself now denies that it is an indicator of any discriminatory behavior and Navigant ignores or fails to grasp that the same defects of BLAP render it unable to measure the effects of potential discrimination (Second NERA Report, ¶¶ 23 and 167); Navigant agrees that a simpler model would produce the same quantum yet it continues to defend its more involved and complex model (Second NERA Report, Appendix 2, ¶ 8); Navigant ignores the effect of the 1991 Minister’s Order requiring Celgar to self-supply its own load (Second NERA Report, ¶ 162). 901 Under the heading of new errors and errors newly identified: Navigant ignores transmission tariffs that Celgar would have to pay on additional electricity it sold to BCH (or any other customer) (Second NERA Report, Appendix 2, ¶ 25); Navigant has errors in its calculations of the amount of interest accrued on the damages it calculates in the historic period (Second NERA Report, Appendix 2, ¶ 26); Navigant ignores the impact of the upcoming Rate Schedule 37 which will potentially significantly reduce Mercer’s damages by providing Celgar with a refund and lowering its rates (Second NERA Report, ¶ 142); Navigant provides no competitive harm analysis and instead relies on Mr. Merwin’s inapt and flawed cost curves (Second NERA Report, ¶¶ 122-131).
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
208
5. The Claimant ignores the effect of the 1991 Ministers’ Order
As with the other two measures discussed above (the EPA’s exclusivity clause 446.
and Order G-48-09), the effect of a valid 1991 Ministers’ Order on possible damages
arising out of an improperly set GBL would still be to prohibit Celgar from selling any
electricity generated below Celgar’s load because its 52 MW turbine is committed for
self-supply, thus eliminating or virtually eliminating any damages to the Claimant.902
G. The Claimant Fails to Independently Quantify its Article 1105 Damages Claim
The Claimant does not independently quantify damages under Article 1105, 447.
leaving Canada and the Tribunal in the position of having to speculate as to what they
might be. For example, should the Tribunal find that BC Hydro acted non-transparently
when setting the Claimant’s GBL, the Claimant makes no case as to what the GBL would
be had BC Hydro acted transparently. It is not for Canada or the Tribunal to assume the
existence of loss, the burden of proof rests with the Claimant and it has failed to meet that
burden.
VII. COSTS
NAFTA Article 1135 allows a Tribunal to award costs in accordance with the 448.
applicable arbitration rules.
Canada requests that the Tribunal order the Claimant to pay the arbitration costs 449.
for this NAFTA arbitration and to indemnify Canada for its legal fees and costs.
Canada respectfully requests the opportunity to submit a more detailed 450.
submission on costs in the future so that it can fully address all relevant considerations.
902 1991 Ministers’ Order, p. 2, R-100; Celgar 1990 EPC Application, R-97.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
209
VIII. CONCLUSION AND REQUEST FOR RELIEF
For the foregoing reasons, Canada respectfully requests that the Tribunal dismiss 451.
the claims in their entirety and with prejudice, order that the Claimant bear the costs of
this arbitration, including Canada’s costs for legal representation and assistance, and
grant any further relief it deems just and proper.
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED
Mercer International Inc. v. Government of Canada Canada’s Rejoinder Memorial March 31, 2015
210
Respectfully submitted on behalf of the Government of Canada this 31 day of March, 2015.
_________________________ Sylvie Tabet Michael Owen Adam Douglas Louis-Philippe Coulombe Stephen Kurelek Krista Zeman
Counsel for the Respondent Trade Law Bureau (JLTB) Departments of Justice and of Foreign Affairs, Trade and Development
PUBLIC VERSION CONFIDENTIAL AND RESTRICTED ACCESS INFORMATION REDACTED