Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
Photo courtesy of PPM Energy
Integrating Renewable Resourcesinto the Electric Grid
BPA Operational Experiences December 13, 2010
Terry OliverChief Technology Innovation Officer
Bonneville Power Administration
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N
2
Introduction to BPA: System Map
McNary
Dworshak
Anderson Ranch
Palisades
Ice Harbor
GrandCoulee
Revelstroke
LowerMonumental
LittleGoose
John Day
The Dalles
Minidoka
Lower Granite
Chandler
Rosa
Albeni Falls
BlackCanyon
Boise Diversion
Mica
Keenleyside
Duncan
BPA Service AreaColumbia Basin
Federal Dams
Canadian Dams
Montana
Wyom
ingUtahNevada
California
Oregon Idaho
WashingtonCanadaU.S.A.
Non-Federal Dams
Chief Joseph
Priest Rapids
WanapumRock Island
Rocky Reach
Wells
Hells CanyonOxbow
Brownlee
Swan FallsC J Strike
American Falls
BlissUpper Salmon
Falls
BPA Transmission Grid
Libby Hungry Horse
Corps of EngineersDept. Of Reclamation
Bonneville
Green Springs
Lost Creek
Hills Creek
Lookout PointCougarDexter
Green PeterFoster Detroit
Big Cliff
Federal Columbia River Power SystemColumbia River Basin & BPA Service Area• Congress created the Bonneville Power
Administration (BPA) in 1937 to market and transmit the power produced by Bonneville Dam. Today, BPA markets power and transmission services from 31 Federal dams, one non-federal nuclear plant, and 75% (15,000 miles) of the high-voltage lines in the Pacific Northwest.
• The dams and the electrical system are known as the Federal Columbia River Power System (FCRPS)
• BPA’s 300,000 square mile service area includes Oregon, Washington, Idaho, western Montana and small parts of Wyoming, Nevada, Utah, California and eastern Montana
• BPA sells wholesale power to publicly owned and investor-owned utilities, as well as to some large industries BPA also sells or exchanges power with utilities in Canada and other parts of the Western United States
• BPA is a self-funded, not-for-profit federal agency within DOE
• $3.5 billion in annual revenues• Headquarters in Portland, OR
3
Changing Paradigm Strong movement from conventional to variable energy resources In today’s environment, planning is a combination of art and science
– Balance reliability, economic, environmental, renewable integration, & the other public purpose objectives to optimize transmission and resources to meet the needs of the region
– How can transmission & resources be optimized to best meet the needs?
Increased coordination and collaboration required among various sub-regional organization (i.e., ColumbiaGrid, NTTG, WestConnect, CAISO) and WECC TEPPC efforts.
3
44
Wind power is growing fastWIND GENERATION CAPACITY IN THE BPA BALANCING AUTHORITY AREASequential Increases in Capacity, Based on Date When Actual Generation First Exceeded 50% of Nameplate
10/5/07
10/15/07
1/1/09
8/11/10
8/11/106/30/10
1/1/10
6/28/05
11/25/05
10/4/06
6/18/0212/18/01 1/16/02
11/26/07 5/10/084/29/08
6/6/08 12/7/08
2/12/091/27/09
11/17/07
10/25/98
8/10/06
3/22/095/1/09
8/6/099/21/09
11/30/0912/16/09
1/15/106/6/10
0
250
500
750
1000
1250
1500
1750
2000
2250
2500
2750
3000
3250
3500
1/1/
1998
7/2/
1998
1/1/
1999
7/2/
1999
1/1/
2000
7/2/
2000
12/3
1/20
00
7/2/
2001
12/3
1/20
01
7/2/
2002
1/1/
2003
7/2/
2003
1/1/
2004
7/1/
2004
12/3
1/20
04
7/2/
2005
12/3
1/20
05
7/2/
2006
12/3
1/20
06
7/2/
2007
1/1/
2008
7/1/
2008
12/3
1/20
08
7/1/
2009
12/3
1/20
09
7/2/
2010
12/3
1/20
10
7/2/
2011
12/3
1/20
11
MW
3011 MWPlantNameplate
Capacity MW
Date When Actual Gen First Exceeded
1/2 of Current Nameplate Capacity
Cumulative Nameplate
Capacity MWVansycle 25 10/25/1998 25Stateline 90 12/18/2001 115
Klondike I 24 1/16/2002 139Condon 50 6/18/2002 189
Klondike II 76 6/28/2005 265Hopkins Ridge 157 11/25/2005 422
Leaning Juniper 100 8/10/2006 522Big Horn 200 10/4/2006 722
White Creek 200 10/5/2007 922Klondike III 226 10/15/2007 1148
Biglow Canyon 126 11/17/2007 1274Nine Canyon @ 28% 27 11/26/2007 1301
Goodnoe Hills 96 4/29/2008 1397Nine Canyon @ 52% 24 5/10/2008 1421
Klondike 3a 75 6/6/2008 1496Arlington 103 12/7/2008 1599
Willow Creek 72 1/1/2009 1671Pebble Springs 100 1/27/2009 1771
Hay Canyon 100 2/12/2009 1871Wheatfield 97 3/22/2009 1968Tuolumne 137 5/1/2009 2105
Biglow Canyon Phase 2 149 8/6/2009 2254Windy Flats Dooley (phase 1) 30 9/21/2009 2284Windy Flats Dooley (phase 2) 233 11/30/2009 2517
Harvest 100 12/16/2009 2617Combine Hills 63 1/1/2010 2680
Star Point 100 1/15/2010 2780Linden Farm 50 6/6/2010 2830
Coastal Energy 6 6/30/2010 2836Biglow Canyon Phase 2 (add'l) 14 8/11/2010 2850
Biglow Canyon Phase 3 161 8/11/2010 3011
5
Wind Generation Capacity Connected to BPA’s Transmission System is Growing
66
Much of the Wind Resource Serving Load Outside BPA Balancing Authority (BA)
Location of Load Being Served
BPA BA Other NW BA
California (33% RPS)
Unknown Customer
2010 3,600 475 775 2,350 N/A2012 5,950 800 2,075 3,075 N/A2020
Scenario 9,800 1,200 1,700 2,100 4,800
Year
Wind Generation Inside BPA Balancing Authority
77
Wind Generation Experiences Significant Ramps
8
Inaccuracy in Wind Generation Forecasts Increase the Need for Other Generation Resources to Maintain Reliability
1. Hour Ending 11 scheduling window closes2. Hour Ending 11 intra-hour scheduling window closes3. Hour Ending 11 intra-hour schedule
1
32
Legend
Total Schedule without Intra-Hour
Total Schedule With Intra-Hour
Total Generation
Solutions (to date)
Add transmission capacity Fixed reserves + DSO216 Situation awareness – wind desk + data Changed operations – ½ hour schedules Experiments:
– Gen imbalance self supply – Dynamic transfer schedules
9
Next Gen Solutions
6 dimension wind visualization (pat pending) Synchrophasors applications for grid
control Technical operations improvements
– Predictive state estimation– Faster resolution of uncertainty
Control beyond impedence
10
11
New WrinkleWhile the water supply volume for the Columbia River has been below average for 10 of the past 11
years, generation oversupply can occur in even below average water years.Years in red had at least one week of non-fish spill at Grand Coulee and Chief Joseph in light load hours.
Water Year Runoff (Oct-Sep) at The Dalles1929-2010*
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
210
220
1929
1931
1933
1935
1937
1939
1941
1943
1945
1947
1949
1951
1953
1955
1957
1959
1961
1963
1965
1967
1969
1971
1973
1975
1977
1979
1981
1983
1985
1987
1989
1991
1993
1995
1997
1999
2001
2003
2005
2007
2009
Octo
ber -
Sep
tem
ber R
unof
f (m
af)
Average = 135 maf*WY 2010: Observed Oct-Aug, Estimated for September as of 9/26
12
Hydro IntegrationThe timing of the runoff is a huge factor in FCRPS operations
Unregulated April-August Flows at The Dalles Dam
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
4/1 5/1 6/1 7/1 8/1
cfs
2010flows
top-25%avg¹
dailymedian,1929-99
NWRFCMay MMFcst²
¹ Average daily flows of the 18 highest April-August volume years (top 25%), 1929-99.
² May Mid-Month forecast for April-August volume from the NW River Forecast Center; plotting April observed and distributing remainder of forecast equally by month based on percent of average flows.
13
Background Due to the inherent uncertainty in weather, the forecasted water supply volume can vary
significantly over the course of a year.– Yellow shaded areas mark periods when the forecast changed by 10 Maf or more within two
months.– If there is sufficient turbine capability and load, 10 Maf could be as much as 8200 MW-months
of FCRPS generation in the Spring.
Jan - Jul Monthly Final Volume Forecasts at The Dalles (Maf)
2003 2004 2005 2010January 80.5 103.0 85.6 88.5February 75.6 100.0 82.4 79.2March 74.9 92.9 70.7 71.8April 85.3 84.2 73.8 69.7May 90.2 79.5 74.7 70.9June 89.3 85.1 79.8 74.0July 89.3 83.7 81.2 81.9ACTUAL 87.7 83.0 81.3 84.7
14
Weather Conditions in June 2010
Extremely wet and cool weather pattern dominated Pacific Northwest weather.
Most of the region saw precipitation amounts significantly above average.
In addition to precipitation, normal snow melt would have contributed between 3 and 7 1/2 inches across the basin, but the precipitation took an additional 1/2 to 3 inches of the snow pack with it.
Seattle/Portland/Spokane (BPA’s “load centers”) temperatures averaged 2.6 degrees below normal during this period.– In June, below average temperatures implies below average loads.
Division Averages JUN TO DAY 14 Obs'd Depart % avg
COLUMBIA ABOVE COULEE 1.96 0.85 176% SNAKE RV AB ICE HARBOR 1.98 1.30 291% COLUMBIA AB THE DALLES 2.02 1.18 241%
15
Short-Term Forecasts The combination of the natural weather-induced streamflows and the
increased discharge at upstream reservoirs resulted in a significant increase in the “regulated” inflows into Lower Granite and Grand Coulee during this period.
16
Short-Term Forecasts Combining the Columbia and Lower Snake pieces resulted in the following picture of “regulated”
flows into McNary.– The highest 7-day average McNary flows in this period was 355 kcfs.– HYDSIM 70-year studies indicate that there is a 1-in-3 chance of reaching these levels of McNary flow for a
month or longer.
17
Power Market Conditions Mid-Columbia off-peak prices were negative June 9 – 14. The California ISO reported that prices were as low as -20 $/MWh.
Mid-C Peak and Off-Peak weighted average day-ahead prices with High and Low BandsSource: Intercontinental Exchange (ICE) --- June 2010
-$8
-$6
-$4
-$2
$0
$2
$4
$6
$8
$10
$12
$14
$16
$18
$20
$22
$24
$26
$28
$30
$32
$34
$36
6/1 6/2 6/3 6/4 6/5 6/6 6/7 6/8 6/9 6/10 6/11 6/12 6/13 6/14 6/15 6/16 6/17 6/18 6/19 6/20 6/21 6/22 6/23 6/24 6/25 6/26 6/27 6/28 6/29 6/30
Date
Pric
e ($
/MW
-hr)
On-Peak Prices Off-Peak Prices
18
Power Market Conditions BPA balancing authority generation significantly
exceeded load in early June.– Federal and non-federal resources are shown
19
Transmission Operations Intermittent outages and reduced capacity on both AC and DC interties to California Intermittent 25% derates on the Northern Intertie to British Columbia Reductions in transmission availability limited BPA’s ability to find power demand and resulted
in increased lack of market spill BPA declared a “no touch” condition from June 11-14 for control system automation.
– No computer system updates or testing to ensure no interruption to transmission dispatcher computer systems.
20
Impacts of Wind Generation Balancing Reserves
– Because of concern about exceeding system TDG levels, BPA reduced balancing reserves• Approximately 75 hours of DEC reserve reductions and 1 hour of INC reserve reduction• Reducing DEC reserves allowed the FCRPS to generate at higher levels during wind ramps and had a
minor impact on lack of market spill– In hindsight, a more effective way to manage system TDG levels may be to reduce the amount
of INC reserves• This would have allowed for the potential to increase on-peak hydro generation, thus decreasing spill
BPA balancing authority wind data