91
INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN IN MANUFACTURING SYSTEM DEVELOPMENT by Anna W. Mierzejewska B.S., Mechanical Engineering, 1998 Massachusetts Institute of Technology Submitted to the Department of Mechanical Engineering in partial fulfillment of the requirement for the degree of Master of Science in Mechanical Engineering at the Massachusetts Institute of Technology June 2000 0 2000 Massachusetts Institute of Technology All rights reserved A uth or ........................................................ .. ...... Department of Mechanical Ejgineering ay 5, 2000 C ertified b y .................................................................................. David S. Cochran Assistant Professor of Mechanical Engineering Thesis Supervisor A ccepted by ............................................ Ain A. Sonin Chairman, Departme 7 on Graduate Students MASSACHUSETTS INSTITUTE OFTECHNOLOGY SEP 2 0 2000 I LIBRARIES

INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

INTEGRATING INFORMATION FLOWWITH LINKED-CELL DESIGN

IN MANUFACTURING SYSTEM DEVELOPMENT

by

Anna W. Mierzejewska

B.S., Mechanical Engineering, 1998Massachusetts Institute of Technology

Submitted to the Department of Mechanical Engineeringin partial fulfillment of the requirement for the degree of

Master of Science in Mechanical Engineeringat the

Massachusetts Institute of Technology

June 2000

0 2000 Massachusetts Institute of TechnologyAll rights reserved

A uth or ........................................................ .. ......Department of Mechanical Ejgineering

ay 5, 2000

C ertified b y ..................................................................................David S. Cochran

Assistant Professor of Mechanical EngineeringThesis Supervisor

A ccepted by ............................................Ain A. Sonin

Chairman, Departme 7 on Graduate StudentsMASSACHUSETTS INSTITUTE

OFTECHNOLOGY

SEP 2 0 2000

I LIBRARIES

Page 2: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

I

Page 3: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

INTEGRATING INFORMATION FLOWWITH LINKED-CELL DESIGN

IN MANUFACTURING SYSTEM DEVELOPMENT

by

Anna W. Mierzejewska

Submitted to the Department of Mechanical Engineeringon May 5, 2000 in partial fulfillment of the requirement forthe degree of Master of Science in Mechanical Engineering

Abstract

In order to stay competitive, manufacturing companies have to face the challenge of beingresponsive to customer's needs by reducing cost, improving quality, and shrinking leadtimes. To achieve these objectives, a manufacturing system should be developed based on aclear understanding of the difference between value-adding and wasteful tasks.

In a linked-cell system, the flow of material and information through all the production unitsdetermines system performance in terms of efficiency and responsiveness. Although sourcesof waste in material flow are easier to observe and thus eliminate, information flow pattern isusually given less attention and the effect that the information flow has on the material flowhas been less understood. Thus, system development and implementation usually starts withdecisions about equipment purchases and their layout, and system information flow is usuallyforgotten until the end of the system development process.

This work attempts to show how information flow influences material flow and thus,performance of the overall system. The objective of this thesis is to present the integration ofinformation and material flow in the conveyance (withdrawal-replenishment) system and itsrole in design of the production system. Various types of conveyance systems are presentedand a discussion on their applicability is included. A case study is described to illustrate theneed for change and some of the difficulties in the implementation process.

Thesis Supervisor: David. S. CochranTitle: Assistant Professor of Mechanical Engineering

3

Page 4: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

4

Page 5: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Acknowledgements

I would like to thank Professor David S. Cochran for giving me the opportunity to do my

research in this area and to be part of the Production System Design Laboratory at MIT -

which I have greatly enjoyed. My thanks also go to Visteon Monroe for giving me the

motivation for research and for sponsoring my project. During my assignment at Monroe, I

have received much support and friendship from many people, but especially from Ed Umin,

for whom I have particular respect, Tim Rosengarten, Phil Wylie, Bill Nolan, Ed Patino, Ray

Carravallah, and Karen Smith, to name a few. I also enjoyed working on the project with

Jeff Smith and Steve Rupp - thank you for helping me learn. The brainstorming with

Brandon Carrus enriched my stay there and kept me sane.

I would also like to thank all the lab members for putting up with me and providing me with

valuable advice on survival and research, especially Jorge Arinez and Jim Duda. My words

of appreciation go to Pat Smethurst for her help in so many things and also for taking her

time to proof read my thesis.

I give my special thanks to Jose Israel Castafteda-Vega for his support, encouragement and

advice but most importantly his valuable time. Without you, it would not be the same.

Thank you for helping me through it and always giving me new ideas as well as your

patience. I hope you finish soon.

Finally, I would like to thank my entire family for their support but most especially my father

for sharing his passion for engineering and my mother for everlasting support and

encouragement. Thank you for your teachings and support. B6g zapla.

5

Page 6: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

6

Page 7: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Table of Contents

ABSTRACT............................................................................................................................. 3

ACKNOW LEDGEM ENTS ................................................................................................ 5

TABLE OF CONTENTS ................................................................................................... 7

1 INTRODUCTION...................................................................................................... 11

1.1 THESIS OBJECTIVE.................................................................................................. 12

1.2 THESIS OUTLINE ................................................................................................... 13

2 BACKGROUND ........................................................................................................ 15

2.1 IMPORTANCE OF MANUFACTURING AS COMPETITIVE ADVANTAGE ...................... 15

2.2 DEFINITION OF MANUFACTURING SYSTEM ........................................................... 17

2.3 HOLISTIC VIEW OF THE SYSTEM ............................................................................ 18

2.4 COMPONENTS OF MANUFACTURING SYSTEM.......................................................... 21

2.4.1 E lem ents..................................................................................................... . 2 1

2.4.2 C onnections................................................................................................. . 22

2.5 LINKED-CELL SYSTEM .......................................................................................... 23

3 DECOMPOSITION FRAMEWORK IN PRODUCTION SYSTEM DESIGN..... 25

3.1 AXIOMATIC DESIGN APPROACH IN PRODUCTION SYSTEM DESIGN DECOMPOSITION25

3.2 FR'S AND DP's OF INFORMATION AND MATERIAL FLOWS ................................... 28

3.2.1 Material Flow ............................................................................................... 30

3.2.2 Information Flow ........................................................................................ 31

3.2.3 G eneral ....................................................................................................... . 32

7

Page 8: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

3.3 INTERRELATION BETWEEN MATERIAL AND INFORMATION FLOWS....................... 33

3.3.1 Controllability of the Production at the Line................................................ 33

3.3.2 Impact of the information and materialflows on the system performance..... 34

4 INFORMATION SYSTEM ...................................................................... 35

4.1 MODES OF MATERIAL FLOW ................................................................................... 38

4.2 INVENTORY STRATEGIES ...................................................................................... 41

4.3 PATTERNS OF INFORMATION FLOW UNDER VARIOUS CONTROL POLICIES ................. 43

5 CONVEYANCE METHODS IN LINKED-CELL SYSTEMS ............................. 47

5.1 CONVEYANCE: WITHDRAWAL, REPLENISHMENT ...................................................... 47

5.2 KANBAN AS A TOOL .............................................................................................. 50

5.2.1 Types of kanban .......................................................................................... 50

5.2.2 Kanban systems........................................................................................... 52

5.2.3 Specifications of kanban systems ................................................................. 54

5.3 CONVEYANCE METHODS ........................................................................................ 58

5.3.1 Mechanism of conveyance ........................................................................... 58

5.3.2 Pacemaker element withdrawal.................................................................. 60

5.3.3 Types of conveyance methods ...................................................................... 61

5.3.4 Examples of withdrawal systems ................................................................. 63

6 CASE STUDY ............................................................................................................... 67

6.1 INITIAL SYSTEM ..................................................................................................... 68

6.1.1 Information flow - the initial system .......................................................... 69

6.1.2 Material flow - the initial system.................................................................. 70

6.2 REDESIGNED SYSTEM - TOWARDS THE IDEAL STATE ............................................ 73

6.2.1 System level - redesigned system.................................................................. 74

6.2.2 Line level - redesigned system.................................................................... 78

6.3 PRESENT SYSTEM - TRANSITION STATE.................................................................. 81

6.4 FURTHER DEVELOPMENT ....................................................................................... 84

7 CONCLUSIONS ........................................................................................................ 87

REFERENCES ...................................................................................................................... 89

8

Page 9: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

9

Page 10: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

10

Page 11: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

1 Introduction

In today's world market, companies compete fiercely to gain and retain customers.

However, customers are becoming more finicky; ultimately they want to get their product for

free, they want it perfect, and they want it now [Hartman and Rodin, 1999]. In order to

compete, the manufacturing companies have to face this challenge with ever-increasing

dedication, by reducing cost, improving quality, and shrinking lead times. This challenge

places significant requirements on the manufacturing system to be responsive to customer

needs.

Responsiveness to customer needs has been the underlying objective of the Toyota

Production System (TPS) [Ohno, 1988], causing Toyota to be the most benchmarked

manufacturing company in the world today [Spear and Bowen, 1999]. The basic concept of

TPS is the elimination of activities that do not add value to the product, or elimination of

waste in the system. The following categories of waste have been identified [Ohno, 1988]:

" Overproduction - waste of resources needed to produce something that the customer

does not request at the moment; it will also cause additional waste in other areas, such

as transportation, and inventory.

" Waiting - waste of operator time.

- Transportation - waste of resources (including labor) on non-value adding activity.

" Additional processing - waste of labor and machine resources on additional

operations, such as rework.

- Inventory - waste of space and labor resources associated with inventory

management.

11

Page 12: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

" Movement - waste of labor resources on activities that do not add value to the

product.

- Non-perfect yield - waste of resources used to make parts that cannot be sold because

they are defective or need to be reworked (requiring additional resources).

The elimination of sources of waste in the system improves its efficiency, in terms of the

quality of the products, the response time to the demand, and the cost [Ohno, 1988].

1.1 Thesis Objective

Because the performance of a manufacturing system depends to a great extent on the

underlying design of the system, the elimination of waste also places requirements on the

production system development to prevent waste from occurring in the first place. Designing

the value stream, i.e. all actions performed to manufacture a product [Rother and Shook,

1998], should be done to ensure that these actions in the value stream are in fact value

adding.

The value stream is comprised both of material flow, i.e. actions associated with the

processing and movement of material, and of information flow which dictates and controls

the flow of the material. Although sources of waste in material flow are easier to observe

and eliminate, the information flow pattern is usually given less attention and the effect that

the information flow has on the material flow has been less understood. Thus, the system

development and implementation usually starts with decisions about equipment purchases

and their layout, and the information flow in the system is usually forgotten until the end of

the system development.

This work attempts to show how information flow influences material flow and thus, the

performance of the overall system. The objective of this thesis is to present the integration of

information and material flow in the conveyance (withdrawal-replenishment) system and its

role in the production system design. Various types of conveyance systems are presented

and a discussion on their applicability is included.

12

Page 13: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

1.2 Thesis Outline

This thesis starts with the background information in Chapter 2, which discusses the

importance of manufacturing and defines manufacturing system. This chapter also presents

the scope of the manufacturing systems analyzed and introduces the value stream mapping

method used throughout this work to illustrate material and information flows. Finally, the

linked-cell system, which is the focus of the scope of this thesis, is defined.

Chapter 3 presents the decomposition framework used in this thesis to analyze the

requirements that overall system design places on information and material flows. The

interdependence of information and material flows is discussed.

Information systems are the subject of Chapter 4. Various modes of material and

information flows are presented and their patterns under various control policies are

described. Chapter 5 focuses on conveyance methods. First, the conveyance is defined and

its mechanism is described in detail. Kanban systems are presented to illustrate how the

information authorizes and controls material flow in conveyance. Finally, various

conveyance methods are described in detail, and a discussion of their applicability is

provided.

The motivation for this work is presented in Chapter 6. This case study describes an initial

manufacturing system in an existing plant, displaying various types of waste and the need for

a system redesign. The redesigned system is then presented, along with the principles

underlying its design. Finally, the transition state is described, with a discussion of the

difficulties of implementation of the redesigned system and further recommendations

provided.

Finally, Chapter 7 concludes this thesis by providing a summary and the recommendation for

further work.

13

Page 14: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

14

Page 15: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

2 Background

Manufacturing is the prime activity of many companies. Because of its role in value-adding

transformation of goods, it is critical in satisfying customer needs. This chapter discusses the

importance of manufacturing as a competitive advantage, defines what a manufacturing

system is, introduces the graphical representation of manufacturing systems used in this work

and specifies the scope of this work by presenting the manufacturing system types

considered.

2.1 Importance of Manufacturing as a Competitive Advantage

Any enterprise can be viewed as a chain of capabilities that enable it to satisfy the customer's

demand [Fine, 1999], as shown in Figure 2-1. This view goes beyond the organizational or

technological structure of a traditionally defined supply chain. Rather, it looks at activities

that are necessary under system development and not only system execution. As for any

chain, a prevalent principle holds true: a chain is only as strong as its weakest link.

Therefore, all components of the capability chain, whether owned by the company or

external to it, should be taken into consideration as key to gain advantage over the

competition. Manufacturing is one of those links.

Wheelwright and Hayes list four stages of the strategic role of manufacturing [Hayes and

Wheelwright, 1985]:

1. Internally neutral: minimize the negative effect of manufacturing. Outside experts are

called in to make decisions about strategic manufacturing issues. Internal, detailed

management control systems are the primary means for monitoring manufacturing

performance. Manufacturing is kept flexible and reactive.

15

Page 16: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

2. Externally neutral: achieve parity with competitors. Industry practice is followed. The

planning horizon for manufacturing investment decisions is extended to incorporate a

single-business cycle. Capital investment is the primary means for catching up with

competition or achieving a competitive edge.

3. Internally supportive: provide support to the business strategy. Manufacturing

investments are screened for consistency with the business strategy. A manufacturing

strategy is formulated and pursued. Longer-term manufacturing developments and

trends are addressed systematically.

4. Externally supportive: manufacturing contributes significantly to competitive advantage.

Efforts are made to anticipate the potential of new manufacturing practices and

technologies. Manufacturing is involved "up front" in major marketing and engineering

decision. Long-range programs are pursued in order to acquire capabilities in advance

of needs.

Manufacturing, being one of the links in the chain of capabilities, can be therefore a source of

competitive advantage, provided that the manufacturing strategy is aligned with overall

business strategy.

Organizational Supply Chain

4th Tier 3rd TierSupplier Supplier

Technology Supply Chain

cheitry Casting Valve lifters

2nd Tier 1st Tier Assembler DealerSupplier Supplier

Cars

Capability Chain

Machine EquipmentControls DevelopmentDesign

Line DesignProduction

System DesignSupply ChainManufacturing Management

Figure 2-1. Supply chain mapping illustrating elements required to satisfy customer's needs(adapted from [Fine, 1999]).

16

engines

Page 17: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

However, because the world we live in is constantly changing, especially in a business sense,

no single capability should be viewed as a sustainable advantage [Fine, 1999]. Because of

the increasing speed of change in industry, each company needs to reinvent itself over and

over again. This necessity places an important requirement on manufacturing strategy: not

only to provide a competitive advantage now, but also to develop new capabilities for the

future. In the case of manufacturing, this necessity relates not only to processes and

technology development but also to the organization and its ability to change. This flexibility

and anticipation of windows of opportunity to gain competitive advantage is the ultimate

core competency of business.

2.2 Definition of a Manufacturing System

Manufacturing can be defined as the transformation of material into something useful and

portable [Gershwin, 1994]. A manufacturing system, however, encompasses not only a

sequence of operations that add value to a product through transformation, but also some

other required tasks such as storage, inspection and transportation, which do not take part in

the transformation but are required to complete the process, as well as the policies governing

those processes.

Manufacturing systems can be classified according to their process structure [Hayes and

Wheelwright, 1979]:

- Job shops

" Disconnected flow lines - batching

- Connected flow lines

" Continuous flow processes

The process structure defines how the material flows through the plant and is usually related

to the type of product produced, as shown in Figure 2-2. The manufacturing systems

considered in this work are continuous flow lines, intended for repetitive production of

discrete items. They are characterized by a defined part routing and are connected by a

paced material handling system.

17

Page 18: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Process structure

Jumbled flow(job shop)

Disconnectedline flow(batch)

Connectedline flow

(lines or cells)

Continuous flow

low s ardization Multiple products Few major products high stndardization

onelow volume higher volume commodity products

Ship building

Heavy equipment

Auto assembly

Sugar refinery

Figure 2-2. Matrix of manufacturing systems' process structure (adapted

Wheelwright, 1979]).

from [Hayes and

2.3 Holistic View of the System

In order to analyze the behavior of the entire manufacturing system it is important to take a

holistic view, rather than view it from a reductionist perspective [Hopp and Spearman, 1996].

This broad view allows for overall understanding of system behavior rather than one with

limited impact caused by a narrow focus. It prevents local optimization and instead seeks

overall system optimization. By relating customer requirements to system requirements, the

holistic view of the system allows concentrated analysis or design of the system based on the

parameters that have the greatest impact on overall system performance relevant to the

customer.

The system view recognizes that an understanding of entire system behavior requires

understanding its components. Therefore, any system, in this case manufacturing, is seen to

consist of various subsystems. Analyzing the parameters influencing the behavior of those

subsystems and the principles governing their interrelations provides an understanding of the

entire system. During the design of a system, the holistic view allows the overall system

18

Page 19: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

objectives as seen by the customers to relate to the requirements for subsystem design. This

decomposition of the requirements and design parameters is further discussed in Chapter 3.

Viewing a system as a set of interacting subsystems also permits one to look at various levels

of detail, as shown in Figure 2-3. The overall system can be viewed at the inter-company

level of supply chain management, where decisions are aimed maximizing end-customer

satisfaction, at the same time maximizing profit shared over the entire chain beyond the

borders of the given company [Fine, 1999]. Those decisions which will greatly impact

customer satisfaction should not only include the supply chain design, including supplier

selection, relationships and transportation, but also issues such as product design and variety

portfolio. Furthermore, the supply chain view shows the impact that decisions at the

company level have on performance of the entire chain. Company level objectives can be

further broken down into the objectives of particular facilities, which should be aligned with

the company's business strategy. Furthermore, the level of detail can go down to line/cell,

and finally station/machine.

In this work, three levels of detail in manufacturing system design will be considered, as

shown in Figure 2-3:

- Plant - door-to-door view

- Cell/Line

* Station/Machine

The door-to-door view of the plant is chosen as the highest level of detail because of its

relevance to immediate implementation. However, it is important to remember that this level

should be looked at in the broader perspective of requirements specified by the supply-chain

system view. Because of this choice of the initial level of detail, certain characteristics of

manufacturing, such as customer relations, product design, manufacturing process selection

etc. are going to be looked at as fixed inputs to a design or redesign effort. This work

attempts to show how this higher level of detail impacts decisions on cell/line design and

further station/machine design.

19

Page 20: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Supply Chain

7

Company

7

Facility

Raw material End CustomerSuC mBpr

Company C CmayB Company A NIA

Company B

Q LINE ASSEMBLY

Line or Cell

Station

Component Pr9diction InformationMarket

Incoming Material Finished Par

Material flow

Gomez, 1999

Figure 2-3. Various levels of detail for manufacturing system analysis.

20

f _No-_Am

Page 21: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

2.4 Components of a Manufacturing System

A manufacturing system can be represented graphically by means of value stream mapping

[Rother and Shook, 1998], Figure 2-4. This simple method allows one to visualize the

material and information flows between components of a manufacturing system. The

following sections describe the different components of value-stream mapping and its

graphical representation.

4-

Manufacturing Process

Outside Sources

Manual Information Flow

Electronic Information Flow

Signal Kanban

- P' Material Flow

Truck Shipments 0 Physical Pull

Movement of FinishedGoods to Customer

Inventory

Part Market

Physical Push

-FIFO- Transfer of ControlledQuantities of Material in aFirst-In-First-Out Sequence

15 mi. Load Leveling of Volume and Mix

over a specified period of Time

Figure 2-4. Value stream mapping symbols [Rother and Shook, 1998].

2.4.1 Elements

The main elements of a manufacturing system are units of production, which keep a constant

amount of material in process (WIP). They could be stand alone machines or cells and lines,

given that all of the machines in the unit operate at a common production rate and operating

pattern. A sample manufacturing system is shown in Figure 2-5. In a manufacturing system,

21

ASSEMBLY

CUSTOMERS

'4 --- 7 ----

Page 22: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

any such element has its suppliers (either internal suppliers - its upstream operations or

external - outside suppliers delivering raw material or components) as well as its customers

(either internal customers - its downstream processes, or external customers receiving end

products). At the same time, each element itself is a customer and a supplier to internal and

external elements. If a given element has multiple suppliers, it is generally an assembly

operation; if it has a single supplier, it is likely to be a machining line or a stand-alone

process such as a stamping press.

Connections

--- ROCEASSEMBLSUPPLIER -__ CUTOMEIRS

Figure 2-5. Sample manufacturing system with its elements and connections.

2.4.2 Connections

The connection between adjacent elements in a manufacturing system consists of two

components: material flow and information flow. Material connection describes how the

material is moved between various elements of the system. Its characteristics include:

" location and size of the inventory

" material movement prioritization policies (FIFO, FISFO, random, etc)

" material movement batch size (related to container size for transportation and the

capacity of the transport medium).

The information connection determines how the production schedule is communicated to all

elements of the system. This information consists of what needs to be produced and when it

needs to be produced. The main parameters describing the flow of information in a

manufacturing system are:

" number of the instruction points, where the information is released to the system

(either single or multiple)

" instruction points location (finished goods inventory, its components inventory, the

last or the first operation of the cell)

22

Page 23: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

m information transfer medium (production authorization card, electronic)

m information transfer frequency

2.5 Linked-Cell System

A linked-cell system is a manufacturing system composed of manufacturing and assembly

cells linked by a pull system, thus providing a continuous flow and smooth movement of

materials through the plant [Black, 1991]. A linked-cell system has a single instruction

point, from which production requirement information is issued to upstream processes, in a

direction opposite to the material flow. Therefore, production is based on actual usage

downstream, rather than a forecast requirement.

The cells can be linked directly to each other by placing them directly at the point of use or

indirectly by the pull system of material control called kanban [Black, 1991], described in

detail in Section 4.3. The buffers between cells are used to protect downstream elements

from delays in upstream cells, providing a self-correcting mechanism for production

requirement information to compensate for variations in the system.

The linked-cell system requires a defined and constant internal customer - supplier structure

for a given product type; a given product type has a defined part routing - a sequence of

machines and a path it always takes in its manufacturing process, which is essential in the

flow line process structure. This type of the manufacturing system will be primarily

discussed in this work.

23

Page 24: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

24

Page 25: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

3 Decomposition Framework in

Production System Design

As mentioned in the previous chapter, a holistic system view in production system design

gives the relation between system objectives, as seen by the customer, and the requirements

for subsystem design. Such a relation helps to prevent local sub-optimization. An approach

to relate these objectives is the decomposition method provided by the axiomatic design

theory [Suh, 1990], which can be understood as a top-down analysis of objectives and

requirements [Duda, 1999].

3.1 Axiomatic Design Approach in Production System Design Decomposition

The design decomposition approach using axiomatic design is a formalized methodology to

structure the design process. Its goal is to answer two questions:

" What are the objectives of the subsystem?

" How can given objective be achieved?

By answering these two questions, Functional Requirements (FR) and Design Parameters

(DP), respectively, are established. The pairs of FRs and DPs can be further decomposed into

lower levels of details by again answering the above questions. Additionally, the answer to

the question:

- How can performance against the given objective be measured?

appoints a performance measurable (PM), which can be used to evaluate how well the given

DP meets related FR.

25

Page 26: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

In the decomposition of the design, it is important to adhere to the two Axioms that govern

the design process:

1. Independence Axiom: Maintain the independence of the Functional Requirements

2. Information Axiom: Minimize the information content of the design.

The independence axiom demands that any given DP satisfies a unique FR. Information

axiom states the necessity for simplicity in the design.

The Production System Design Decomposition (PSDD) [PSD, 2000] has been developed

using the axiomatic design approach to relate higher-level business objectives to the

requirements of production system elements. The complete PSDD is shown in the insert at

the end of this thesis. The initial decomposition, shown in detail in Figure 3-1, branches out

to the four fundamental dimensions of manufacturing [Hill, 1994]: quality, cost, response

time and reliability, which define classifications for the lower levels of the PSDD hierarchy.

The top-down analysis of the PSDD highlights the fact that a manufacturing system and the

specifications for its design should be seen as the result of a complex set of dependencies and

constraints and is influenced by the way its performance is measured. Consequently, there

are many options for making use of manufacturing resources; many ways to have time,

inventory, equipment and people work in the system, in order meet the requirements (quality,

cost, response time, response reliability) [Castafieda-Vega, et al., 2000]. Meeting those

requirements also establishes requirements for the information and material flow within the

system. The option selected should result naturally from the high-level performance metrics

employed and reflect the business strategy.

With the aid of the PSDD, the designer can make better decisions during the development or

improvement processes because of being able to see where a design parameter with its

related functional requirements and performance metrics is located in the entire system

hierarchy. The PSDD groups similar characteristics of production systems in a way that can

be used to formulate new system designs, evaluate current performance, guide the redesign

of an existing system or help make informed decisions regarding changes to be made [Carrus

and Cochran, 1998].

26

Page 27: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

FR I

Maximize long-term return oninvestment

PM1

Return on investment oversystem lifecycle

DP I

Manufacturing System Design

FR 13

Minimize investmentover productionsystem lifecycle

PM 13

Investment oversystem Iifecycle

---------------------- ----- --[:::::====-,-- -DPI11 DPI12 DPI13

Production to Elimination of Investment basedmaximize customer non-value adding on a long-termsatisfaction sources of cost strategy

FR112 FR 113

re products Deliver products on Meet customer Investmentesign time expected lead timeons n 440 DP.E

PM 112PM11

PM 111 Percentage on-time Difference betweenProcess capability deliveries mean throughput

time and customer'sexpected lead time

DP111 DP112 DPI12

Production processes Throughput time Mean throughputwith minimal variation variation reduction time reductionfrom target

r - I--I

Figure 3-1. Highest levels of PSDD branching out to the four fundamental dimensions of

manufacturing.

27

FR 11

Maximize salesrevenue

PM 11

Sales revenue

FR 12

Minimize productioncosts

PM 12

Manufacturing costs

FR 111

Manufactuto target dspecificati

Page 28: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

3.2 FRs and DPs of Information and Material Flows

A complete version of PSDD reveals the requirements placed on material and information

flows for a given production system. The location of these requirements in the overall PSDD

structure is highlighted in Figure 3-2. It can be seen that they mostly reside in two branches

of the decomposition: Predictable Output and Response Time. However, their influence on

the performance of the system, as it will be discussed in Section 3.3, spans many branches.

Figure 3-2. Location of requirements placed on material and information flows in the overall

PSDD structure [PSD, 2000].

The above mentioned requirements are shown in detail in Figure 3-3. They can be divided

into the following functional categories:

1. Material flow:

= Incoming material requirements

" Finished parts movement requirements

2. Information flow:

- Production information content and availability requirements

3. General:

" Requirements for replenishment interaction with other resources

" Simplicity requirement.

28

Page 29: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

The applicability of these categories in the physical system is schematically shown in Figure

3-4. The requirements are described separately in sections below and their mutual influence

is discussed in Section 3.3.

Predctabe IDelayPreictble FR-Fl Reduction

Output IA1,

(S.1

PM-PuPM-P1

-P-

FR-P141 FR- Pl4

PM-11P M-PM14 l

-ktb d- W.

Ua.Pdt Pa .... d

ft, p.-o for a.,.

-- a--- a----------

.ya,. 1 D gP b

FR-fl FR-fl FRIJI

d... Iw ".)

PM-T2 PM-fl PU-TI

bP" - w"d Pa...Um

OP-TI OP-fl OP-TI

II IM th .. doobe din .a.Ow~~ UM9 e wv

FR-Tfl FR-fl1 FR-TSI FR-Tm3.. b a ba*. po A E w -

.q~b.* S, d-d

Ow V a - 1

PM-flS PM-TII PM-Tm3

.55. bk-Ta. f.ft ,- P.qn W

,WW 5 FShhi.bd- .I.-f

.*Mpf b.S.& p. a

-P a.. a-

55gb ~~N "" d..I"-

O5 a.

Figure 3-3. Branches of PSDD with requirements placed on material and information flows.

29

Indirect I ILabor FkR-12

PM-42

,,qk.b

Wo"I

-AMq)

Page 30: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

General Requirements

FR-T51 FR-T53 FR-12Ensure that Ensure that Eliminatesupport support informationresources don't resources don't disruptionsinterfere with interfere withproduction one anotherresources

Componjnt ---

Marke FR-P14Ensurematerialavaility

Incoming Material

- -l

FR-T31FR-P11 Provide

Aq . Ensure knowledge of

/demandedproduct mix(part types andQuantities)

I---arrival rate isequal to servicerate (ra=r,)

Finished Parts>

I-------------------------------I

Figure 3-4. Physical system with applicable requirements on material and information flows.

3.2.1 Material Flow

The main necessity for material flow expressed by FR-P14 is that the material must be

available at the line, see Figure 3-5. This requirement is answered by the DP-P14, which

calls for a standard material replenishment system in whichFR-P14Ensure material availability replenishment worker(s) (replenishers) will deliver required

Number of disruptions due materials to the line. In order to achieve this designto material shortages,amount of interruption time parameter, its prerequisites are that the parts actually befor material shortages

available to the material handlers (FR-P141), which can be

Standard material achieved through market places linked with the line and theirre lenishment system

supplying upstream processes (DP-P141), and that part

FR-P141 FR-PI42 arrival is properly timed (FR-P142), according toEnsure that parts are Ensure proper timing ofavailable to the material part arrivals pitch (DP-P142). This initiates the definition of thehandlers

PM-P141 PM-P142 replenisher's or material handler's job, where he isNumber of occurrences of Parts demanded - partsmarketplace shortages delivered -responsible for delivering the material to the line,

DP-P141 DP-P42 according to its needs during the designated deliveryStandard work in process Parts moved tobetween sub-systems downstream operations pitch.

according to pitch

Figure 3-5. Requirements for incoming material.

30

Page 31: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Another part of the material flow is the movement of finished parts from the line, as well as

delivery of empty containers, if applicable, see Figure 3-6. This is addressed by FR-T23,

which asks that the part arrival rate to the downstream

FR-T23 customer - or part departure rate from the supplier process -Ensure that part arrival rate is be equal to the demand rate expressed by service rate. Thisequal to service rate (ra=rs)

PM-T23 can be achieved by movement of parts according to pitch

Difference between arrival and (DP-T23). The physical movement associated with this pitchservice rates

(retrieval pitch) will also act to pace the production, which is

especially important with the issue of controllability of theDP-T23Arrival of parts at downstream line. This topic will be further discussed in Section 3.3.operations according to pitch

Figure 3-6. Requirements for finished parts movement.

3.2.2 Information Flow

The PSDD expresses the importance of information flow, see Figure 3-7. Functional

Requirement FR-P 11 declares the necessity for relevant production information to be

available at the line. Designing and implementing a capable and reliable information system

(DP-P1 1) will allow that important prerequisite for predictable output of the line. PSDD also

specifies what kind of information is required by stating the need for knowledge of

demanded product mix to the

FR-P11 FR-T31 production line (FR-T3 1).Ensure availability of Provide knowledge ofrelevant production demanded product mix Therefore, information flow frominformation (part types and quantities)

the customer (DP-T3 1) will dictatePM-Ph1 PM-T31Number of occurrences of Has this information been not only the quantity of demandedinformation disruptions, provided? (Yes/No)Amount of interruption time products but also the mix specifyingfor information disruptions

111 part variety called for, as well as

DP-P1 1 DP-T31 timing of the order to ensure the

Capable and reliable Information expected response time.information system flow from downstream

customer

Figure 3-7. Requirements for flow of production information.

31

Page 32: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

3.2.3 General

The PSDD also places requirements of a general nature on both the material and information

flows external to the line, as listed in Figure 3-8. Because material and information

movements involve indirect labor, FR-12 requires the elimination of information disruptions,

which will help reduce the indirect labor tasks (DP122). This can be achieved by

implementing a visual factory (DP-12), which simplifies the tasks performed by support

resources such as replenishers. FR-T51 and FR-T52 require that the support resources that

aid in the material and information flows do not interfere with production in the line and with

other support resources. DP-T51 ensures that the production line is designed to prevent

disruptive part delivery or disruptive part changeover, whereas DP-T53 proposes task

separation and coordination to prevent ambiguity in function performed by each support

person. This design parameter proves to be quite important in ensuring reliability of the

material and information flows as well as controllability of the line and, therefore, of the

entire system.

FR-T51 FR-T53Ensure that support Ensure that supportresources don't interfere resources don't interferewith production resources with one another FR-12

PM-T51 PM-T53 Eliminate information disruptions

Production time lost due to Production time lost due to PM-12support resources support resources Amount of indirect labor requiredinterferences with interferences with one to schedule systemproduction resources another

DP-T51 DP-T53 DP-12

Subsystems and Ensure coordination and Seamless information flow

equipment configured to separation of support work (visual factory)separate support and patternsproduction accessrequests

Figure 3-8. General requirements for replenishment.

32

Page 33: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

3.3 Interrelation Between Material and Information Flows

Although the requirements for information and material flows are listed throughout the

PSDD branches, they seemed to be discussed separately. This section attempts to point out

their interdependence and mutual influence.

3.3.1 Controllability of the Production at the Line

As described in Section 3.2.1, the retrieval pitch - the frequency with which end products are

removed from the line to be delivered to the immediate customer - has an important role in

the performance of the system. Although it is directly related to material movement, it also

has information content; every time a material handler comes to pick up finished goods, an

evaluation of the production status can be made: are the parts ready to be picked up, or is the

line falling behind schedule? This assessment can be further substantiated if the same

material handler brings empty containers to the line. The equal exchange of empty

containers for filled ones validates the status of production. For example, if two empty

containers are brought to the line at the specified time but only one container is ready, it is

clear that the line is behind. The coupling of finished goods pickup and empty container

delivery also controls overproduction; since only a specified number of containers is

delivered, the line has to wait for the next retrieval pitch to continue production. Therefore,

this coupling is implementation of a self-controlling system to prevent overproduction.

The key point in the controllability of the line is, however, the above mentioned information

content of the material movement. The knowledge of the behind/ahead status of the line is

important information that can be used to react to system problems. If the material handler,

aside from material movement, is also responsible for bringing production information to the

line, the production status can be delivered to the scheduler with every retrieval pitch. This

brings the following benefits:

- Responsiveness: the scheduler can take action according to production status

information; for example, if the line is behind, additional resources can be sent to

solve the problem, line capacity can be increased (by reducing takt time), the

schedule can be re-sequenced according to priorities, arrangements for overtime can

be initiated, or customers can be contacted early on about possible delays.

33

Page 34: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

x Reliability: since one person is obligated to deliver information and remove finished

goods, there is no ambiguity about who is accountable, and even a sense of ownership

can be developed, where the material handler is solely responsible for the connection

between the two elements in the system, shown in Figure 2-5.

For these reasons, it is beneficial to tie the material and information flows together, having a

single person perform both tasks at a given linkage in the system. A similar connection can

be done with line replenishment, where the replenisher brings necessary material to the line.

Here, the information content, which might easily get lost, is related to the quality of

incoming material. If material is delivered in prescribed quantities in every delivery pitch

interval, any quality problems are easily noticeable and can be tracked down and

communicated promptly to suppliers. This is especially important with internal suppliers, for

which immediate feedback can improve output quality. With external suppliers, the feedback

cannot be as rapid and, therefore, this approach might prove less valuable. In either case,

although the information content on incoming material quality might serve an important role,

it is also essential to design robustness against possible defects in incoming material into the

replenishment system to deal with problems that may arise and prevent down time of the line.

Section 5.3 provides a more detail description of possible replenishment options, as well as a

discussion of some of the factors that will influence the choice.

3.3.2 Impact of Information and Material Flows on the System Performance

From the above discussion, it can be seen that material and information flows might impact

many PSDD branches spanning all four fundamental dimensions of manufacturing. Since

the FRs discussed in Section 3.2 come from the Predictable Output, Delay Reduction and

Indirect Labor branches, their impact on those dimensions is obvious, see Figure 3-2.

However, as Section 3.3.1 suggests, the combined material and information flow strategy

will also have impact on the ability to identify and resolve problems of over- or under-

production by frequent information conveyance. Also, by providing robustness against

incoming material quality problems, a well-designed replenishment system will improve the

quality output of the manufacturing system. Thus, the material and information flow

requirements span all major branches of PSDD.

34

Page 35: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

4 Information System Design

In general sense, information is a piece of knowledge represented by data that can be

interpreted and used by humans [Solvberg and Kung, 1993]. In the context of a

manufacturing system, not all of the information is actually used. Hence, information can be

divided into formal information -which is recognized, communicated and cultivated within

the organization, as well as informal information -which is comprehended or collected by

individuals, but not communicated, at least not in a formal manner, with others, not utilized

in the enterprise.

One of the goals of production system design is to recognize what information should be

formalized and how it should be communicated. Therefore, a complete information system

not only collects, stores, processes, and distributes information [Solvberg and Kung, 1993]

but also defines how and what information is created, how it flows in the physical system,

and how it is utilized and executed to impact production. Therefore, the information system

is not merely a computerized information system such as many companies implement, but

also the physical aspect of it, including human interaction in conveying the information, and

physical movement and interaction with other production resources. Indeed, information

system is intertwined with the physical part of the production system. These two subsystems:

the physical system - represented by the material flow, and information system - represented

by information flow, are integral parts of the entire production system and, therefore, greatly

impact one another in the design process. Hence, the layout of the physical elements will

influence how the information flows and vice-versa - how and what information is

communicated will influence the required physical system layout. This interconnection of

material and information systems also makes it difficult to discuss information flow patterns

35

Page 36: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

without describing the material flow that it induces. Section 4.3 discusses both information

and material flows together under various control policies.

The complete information system of an enterprise has many subsystems, which encompass

all of the functional elements of the enterprise, as shown in Figure 4-1. The manufacturing

information system is one of those subsystems, interacting with other subsystems shown.

The goal of a manufacturing information system is, as shown in Figure 4-1, to plan, schedule,

control, monitor, and facilitate various aspects of production, which refer to various level of

detail, as discussed in Figure 2-3. This work will consider the aspects pertinent to the line and

facility level of detail. Those details are shown in a rectangle in Figure 4-1. The set of these

elements is going to be referred to in this work as the information system in the production

system.

Enterprise Information System

Engineering Manufacturing Human Resources Marketing Other ...Information System Information System Information System Information System

Planning, che ling, ontr 1, M itori , Facilitating of

Process Production / Material Material Inventory ProductionControl Capacity Movement Requisition Resources

Figure 4-1. Elements of enterprise information system.

36

Page 37: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

In order to understand the impact of the manufacturing information system on the production

environment, it is useful to break it down along the time dimension. Time scale defines

planning horizon hierarchy in the decision-making process, shown in Figure 4-2. The three

decision levels - strategic, tactical, and operational, concern all aspects of manufacturing,

such as capacity, material movement, material requisition, and inventory from Figure 4-1.

For example, material requisition at the strategic level requires selecting suppliers and

defining the type of relationship. At the tactical level, purchasing policy - frequency and

method of material ordering - needs to be established. Finally, at the operational level,

facilitating delivery of ordered materials is required. At all of the above mentioned levels,

information is crucial in making the decisions.

CompetitiveStrategy

S e Strategic

Inventory Strategyand

Process Technology

Tactical

Production System Designand

Control & Scheduling

Operational

Figure 4-2. Planning horizon hierarchy in decision-making process (adapted from [Wein,2000]).

This work is mainly concerned with the operational and tactical level of decision-making.

This chapter presents issues such as mechanisms of material and information flows, selection

of instruction point in the system, inventory strategy and the basic types of information

patterns. Those decisions at the tactical level will impact the operation of the production

system. Therefore, this chapter discusses the information system in terms of the

requirements for information flow rather than as a computerized tool for information system

management.

37

Page 38: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

4.1 Modes of Material Flow

In a production facility, the movement of material is often compared to the flow of a fluid

([Hopp and Spearman, 1996], [Rother and Shook, 1998], [Black, 1991], [Bonvik, 1996]).

This model is an accurate representation of material movement in continuous processes, but

even for production of discrete parts this model is a close approximation, especially on the

conceptual level. This comparison between material movement and fluid flow in discrete-part

production is discussed below.

Following this model, the flow is characterized by its velocity or by its volume flow rate, Q.In a production facility, the volume flow rate can be compared to the production rate, or

production throughput. When the flow accumulates in a tank, the concept of capacity is

introduced. Its equivalent in production is inventory, which is also characterized by its

capacity. Furthermore, the fluid can accumulate in terms of increased density, p i.e.

increased particle (mass) count in given volume, which in the production environment is

accumulation of Work-in-Process (WIP) within a production unit, causing material flow

congestion.

The fluid moves or flows because of a pressure difference across the length or as a result of

flow source. Three basic scenarios can be visualized: flow caused by low pressure source,

flow induced by high pressure source and flow initiated by flow source, shown in Figure 4-3.

In manufacturing, those three scenarios correspond to the pull, push and stream local flows

and they depend on the information flow in the system and more precisely how the

production is authorized.

In a pull mechanism, most typically a production unit will initiate production in response to

withdrawal of a part by its immediate customer. This situation is best illustrated by flow

caused by a low-pressure source, Figure 4-3(a). When a downstream process or customer

withdraws a part, a low pressure is created - the need to replenish that part. This condition

initiates the production and flow of parts. Through this mechanism, the output of the unit is

parallel to what has been requested, corresponding to the low pressure imposed.

38

Page 39: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Low pressurea) Pressure gradient source

High pressure) Congestionb) source

Flow Uniform flowC) source

Figure 4-3. Scenarios for fluid flow: a) low-pressure flow, b) high-pressure flow, c) flow

source flow.

Under the push mechanism, the production unit produces according to a schedule or available

incoming material. This condition corresponds to the high-pressure source flow scenario in

Figure 4-3(b), where the parts are pushed through the system "under pressure". This

situation often causes congestion of the flow resulting in WIP buildup and, similarly to the

compressible fluid flow, non-linearity in the production performance. Thus, the unit output

might significantly vary in quantity and time from the actual requirements. After the parts are

produced, they are pushed further downstream.

Another local material flow mechanism is stream flow, compared to the velocity source flow

in Figure 4-3(c). In this scenario, production is initiated by material coming in at a steady

rate, so no WIP buildup is possible. Parts are not pushed downstream; rather they flow

steadily downstream. Adhering to the First-In-First-Out (FIFO) policy for part processing

allows the production output to be predictable in terms of quantity, sequence and timing. This

mode of local material flow is used in CONWIP control policy as described in Section 4.3.

Which of these modes of local material flow will actually occur in a given production system

depends to a great extent upon the information flow in that system and more specifically the

production control policy adopted. Figure 4-4 presents three systems that demonstrate three

39

Page 40: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

different material and information flow patterns. As mentioned in Section 2.4.2, one of the

main parameters characterizing the flow of information in a manufacturing system is the

number and location of instruction points.

Instruction point

a) pull pull

- ~ ~ -P R O E S A S S E M B L Y

UPPLIER F GCUSTOMERS

Instruction points Central

............ Schdln

push a ooCrs push ASSEMBLY

SUPPLIER f.PRCS t-CUSTOMERS

Instruction pointnt

pull pull sto c io

PROCESSASMLrSUPPLIER G CUSTOMERS

Figure 4-4. Various material flow patterns: a) pull flow, b) push flow, c) pull and stream

flows.

The instruction point specifies the element in the production system at which scheduling

information enters the system specifying quantity and time of required production. The

system shown in Figure 4-4(b) displays multiple instruction points to which the information

from the customer is distributed through central scheduling. This multiple location of

instruction points is responsible for creating the high-pressure sources, which initiate the

push flow mechanism of material movement. Systems in Figure 4-4(a) and (c), on the other

hand, have a single instruction point from the customer.

40

Page 41: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

4.2 Inventory Strategies

Whereas the number of instruction points in a system determines to a great extent the mode

of material flow, the exact location of instruction points reflects the inventory strategy

chosen. Two major inventory strategies exist: build-to-stock (BTS) or build-to-order (BTO)

[Hopp and Spearman, 1996]. Figure 4-5 shows both of those strategies.

S PROCESS

SUPPIEJRS

ASSEMBLY

CUSTOMERS

bi)

S PROCESS

SUPPIERS

ASSEMBLY

CUSTOMERS

b2)

SUPER

PROCESS ASSEMBLY

CUSTOMERS

Figure 4-5. Manufacturing systems with different inventory strategies: a) build-to-stock

(BTS), bI) build-to-order (BTO), b2) assemble-to-order (ATO).

Build-to-stock strategy requires that the finished goods inventory (FGI) be kept at the end of

the value stream. That inventory allows delivery lead times shorter than manufacturing

throughput time, i.e. the time it takes one part to go through all processes. It also provides a

buffer against variations in production, demand forecast errors and enables batch production.

The BTS strategy also makes it possible to build ahead to cope with seasonality of demand

[Hopp and Spearman, 1996].

However, holding finished goods inventory is impractical or infeasible if there is a wide

product range, products are large and difficult to store or if the inventory is likely to become

41

Page 42: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

obsolete. In this situation, build-to-order strategy can be implemented. Under this strategy,

the parts are made for a specific order received and directly after their production, they are

sent to the customer. A variation of this strategy is assembly-to-order, where the parts are

assembled to a specific order and shipped to the customer but the components themselves are

prefabricated or build-to-stock.

Table 1. Linking Manufacturing Strategy to inventory strategy choice (from [Hill, 1994]).Arrows signify the location in the spectrum between two characteristics.

Strategic Variables Inventory StrategyBuild-to-Order Assemble-to-Order Build-to-Stock

Type Custom-made Standard

PredeterminedRange Wide and narrow

Product volume Low-runner High-runnerper period Low-runner___High-runner

Speed Difficult Easy

Reliability Difficult Easy

Process choice Job shop Line flow

Managing changesMaaging hand x Order backlog WIP or FGI FGIS in sales and mix

Meeting delivery Through rescheduling Reduces process Eliminatesspeed requirement requirements lead time process lead time

Inventory strategy - decision at the tactical level - is an important influence on both material

and information flows. Table 1 presents some of the strategic variables that influence the

choice of inventory strategy.

Depending on product characteristics, if the product is highly customized, BTO inventory

strategy should be used (job shop process structure is often used in these circumstances). As

the product becomes more standardized, ATO or BTS strategy might become feasible (line

flow should be the choice for process structure). The choice of inventory strategy is also

affected by the range of products. If the product range is wide, it might be infeasible to hold

all types of parts in FGI and, therefore, BTO or ATO strategies are necessary. As the product

42

Page 43: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

range becomes narrow and predetermined, BTS strategy becomes feasible. Oftentimes, the

product range consists of parts produced in high volume (so called high-runners) and parts

produced less frequently (low-runners). In order to prevent holding inventory that is not

needed for long periods of time, the low-runners should be managed under BTO strategy,

whereas the high-runners might be managed under BTS strategy.

BTS strategy generally offers short lead times and more reliable delivery, since the parts

requested by the customer can be simply withdrawn from the FGI. In the ATO and BTO

strategies, since the processing time is included in the lead time, fast and reliable delivery

becomes more difficult to achieve and the delivery speed requirement is met through

rescheduling. FGI present under the BTS strategy allows to easily manage minor changes in

demand volume and mix. Under the ATO strategy, the demand fluctuations might be

managed to some degree with WIP before assembly, whereas BTO strategy requires keeping

order backlog.

4.3 Patterns of Information Flow Under Various Control Policies

Both the number of instruction points in the system and the inventory strategy mentioned in

the previous sections are decisions which often are determined by the control policy of the

system. A control policy is a mechanism by which the production at the shop floor is

scheduled and controlled [Bonvik, 1996]. The information flow pattern dictated by the

chosen control policy will therefore affect the material flow as well.

One of the fundamental control policies used in industry is a push system [Hopp and

Spearman, 1996]. Under that policy the information is delivered to many locations, i.e. the

system has multiple instruction points. Material Requirement Planning or its later version -

Manufacturing Resources Planning - (MRP) is a tool used for implementation of push

policy, where it schedules the release of work based on demand or forecast. The push

control policy controls throughput and observes WIP and inventory levels [Hopp and

Spearman, 1996] and by doing so initiates the push mode of material flow.

43

Page 44: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

In contrast, the pull system has a single instruction point in the system. This single

instruction point, which can initiate both pull and stream modes of material flow, has an

important role in system performance since it is the only point in the entire system at which

customer demand information is communicated. This point is called the pacemaker element,

because how production is controlled at this element sets the pace for all the upstream

processes [Rother and Shook, 1998], as shown in Figure 4-6. From that point in the system,

the demand information is issued to upstream elements based on actual downstream

consumption, following the direction opposite to that of the material flow. Hence, the control

information is self-compensated against variation amplification at every stage of production.

Kanban is a tool commonly used with pull systems. It authorizes the release of work based

on system status, therefore, it controls WIP and inventory levels and observes throughput

[Hopp and Spearman, 1996].

a) pull pull pull

PROCESS 1 PROCESS 2 PROCESS 3 ASSEMLY

-- -- CUTOMRS

b) pull pull pull

PROCESS 1 PROCESS 2 PROCESS 3 ASSEMBLY

CUSTOMERS

c) pull

PROCESS 1 PROCESS 2 PROCESS 3 ASSEMBLY

] FIFO, -FIFO+ USTMER

Figure 4-6. Different locations for pacemaker element and resulting control policies in a

linked-cell system: a) pure pull, b) sequenced pull, c) CONWIP, (adapted from

[Rother and Shook, 1998]).

44

Page 45: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Because the location of the pacemaker element determines the pattern of information flow in

the factory, it also sets the control policy in the system, such as pure pull, sequenced pull or

CONWIP [Rother and Shook, 1998] summarized below.

Pure pull control policy, Figure 4-6(a), locates the pacemaker element at the last stage of the

value stream, the finished goods inventory. This location of the pacemaker makes all

upstream processes to work to replenish actual consumption by implementing build-to-stock

inventory strategy. Customer lead time becomes the time it takes to withdraw and transport

material from the finished goods inventory. This control policy causes the material to flow

according to the pull mechanism.

When holding finished goods inventory becomes impractical, possibly due to a high number

or variations or large parts used infrequently, the sequenced pull could be a better control

policy [Rother and Shook, 1998]. Instead of holding the parts in the supermarket, the

pacemaker element (still at the end of the value stream) is instructed to make the parts to

order under ATO inventory strategy, Figure 4-6(b). This policy is feasible only if the

supplying process's lead-time is fast enough, as it will become part of the overall customer

lead time. Under this policy the material flows in both pull and stream flow modes, as shown

in Figure 4-6(b).

Another approach is locating the pacemaker element further upstream. The resulting control

policy is called CONWIP [Hopp and Spearman, 1996]. From the chosen pacemaker element,

the material flows in a FIFO sequence in the stream mode, limiting inventory between

downstream processes, Figure 4-6(c). The location of the pacemaker element will determine

the elements of the value stream that become part of the lead time of the system. This policy

requires a perfect quality yield from the processes downstream from the pacemaker, or a

system dealing with the quality problems by providing feedback information to achieve right

quantity in order to keep the FIFO sequence. Otherwise, quality problems will result in un-

met customer demand.

45

Page 46: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Although the effects of control policies have been studied extensively [Bonvik, 1996], the

choices for material withdrawal, the factors for its implementation and the impact of various

conveyance methods on the overall behavior of the manufacturing system seem to have

gotten less attention. The material withdrawal refers to the exact location of the instruction

point within the selected pacemaker element and how the information is translated into

material flow. Chapter 5 discusses withdrawal and replenishment methods in a linked-cell

system.

46

Page 47: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

5 Conveyance Methods in Linked-

Cell Systems

A linked-cell system consists of multiple production units linked through local information

and material flow connections, Figure 4-6. Execution of those local connections is referred to

as conveyance. The goal of conveyance is to move the material between production units or

their storage market places and to transmit relevant production information. Those local

connections exist under various control policies in linked-cell system (pure pull, sequential

pull and CONWIP), as discussed in the previous chapter.

5.1 Conveyance: Withdrawal, Replenishment

Conveyance is the action of transmitting something between two elements - the origin and

the destination. In manufacturing, the entity being transmitted can be material or information

whereas the origin and destination elements can be either production units or inventory

market places, as Figure 5-1 shows.

As discussed in Section 3.3, information and material flow paces production, thus preventing

overproduction and allowing quick reaction to problems, thus counteracting underproduction.

This controllability of production elements, i.e. monitoring the performance in terms of

ahead/behind status and quick reaction to solving problems, is made possible by the feedback

loop created by coupling the material and information flow between two given elements of a

manufacturing system. This coupling is embodied in conveyance itself.

47

Page 48: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

info

PROCESS 1

material

Pickp material transport Do f

Withdrawal Conveyance ReplenishmentFigure 5-1. Conveyance loop: withdrawal from origin and replenishment at the destination.

The main goal of the conveyance system is a frequent and cost-effective movement of

material and transmission of information [Monden, 1998]. The more frequent the

conveyance, the tighter control over production, with the optimal being a single piece

conveyance. However, these two objectives: increased frequency and cost effectiveness, can

be conflicting if increasing frequency requires additional resources. Therefore, the preferred

approach to increasing frequency is to shorten the conveyance time itself and thus release the

resources to perform more frequent conveyance. Another tactic for achieving frequent

conveyance is use of mixed loading, where instead of infrequent deliveries from each

supplier, more frequent joined supplier deliveries are practiced. The shortening of the

conveyance time is also important to shortening production lead time, especially because

conveyance is a non value adding task required in the production process. When single piece

conveyance is still not achievable, a less frequent "batch" conveyance is necessary. A

commonly chosen conveyance frequency within a given facility is one hour [Monden, 1998].

The action of conveyance consists of three stages shown in Figure 5-1. First, the entity

transmitted must be picked up from an element, its origin, then it is transported between the

elements, and finally it is dropped off at the destination element. However, it is important to

note that since the conveyance of material and information, which flow in opposite

48

Page 49: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

directions, is often done in a loop by the one person, the drop-off point for the material is also

the origin of the information and the destination point for the information is also the origin of

the material for the given loop. In fact, the information conveyed in the loop is often the

instruction as to what material needs to be picked up at the upstream element. Therefore, in a

linked-cell system the pick-up of the material (and drop-off of the information) is referred to

as withdrawal and the drop-off of material (and pick up of information) is referred to as

replenishment.

Under a control policy such as CONWIP local information connections not always exist, see

Figure 4-6. In this case the given conveyance loop will transport material based on what is

available in FIFO sequence at the origin. However, there is still information that can be

conveyed: for example, the loop can be used to monitor the production status of the upstream

process and communicate developing problems, as discussed earlier.

Replenishment loop Withdrawal loop

info info

PROCESS

material maerial

Figure 5-2. Conveyance loops as seen from the particular element: upstream loop -

replenishment, downstream loop - withdrawal.

As described above, each conveyance loop performs withdrawal (pick-up of material at the

origin) as well as replenishment (drop-off of material at the destination). However, when

looking at a particular production element, such as a manufacturing cell, its upstream

conveyance loop can be labeled as replenishment (delivery of necessary material) and its

downstream conveyance loop as withdrawal (removal of finished parts), see Figure 5-2. This

definition of replenishment and withdrawal is mostly used in this work, whereas conveyance

49

Page 50: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

refers to both actions of replenishment and withdrawal performed at the given loop between

two elements.

5.2 Kanban as a Tool

Kanban is a tool used in linked-cell systems to facilitate information flow under various

control policies. The principle behind the kanban system is to provide a direct and

standardized connection between elements that will prevent ambiguity in its outcome

resulting in a binary yes/no connection [Spear and Bowen, 1999]. This connection requires

conveyance of both the product and the information. The kanban system unambiguously

initiates release and production of parts, i.e. withdrawal and replenishment of parts.

5.2.1 Types of Kanban

Kanbans are essentially cards attached to part containers. They specify the part type,

quantity, destination and origin locations for the container with parts. Since the kanbans

perform many functions, there are many variations of kanbans. The most general

classification of kanban types is shown in Figure 5-3. Material withdrawal kanbans are used

to authorize pickup of material and initiate the conveyance of material. The kanban card

specifies what parts are needed, how many should be transported, where they should be

picked up from and where they should be delivered. Production authorization kanban, on the

other hand, signals to initiate production and thus constitutes information flow between

production elements. This kanban card specifies what part type is required, how many parts

are asked for, where the request is coming from (the local customer for the parts) and to

which manufacturing unit the information is going (the supplier for the parts).

The withdrawal kanban and production kanban are used for conveyance of material and

information for discrete parts in a relatively small container, or production run size. This

allows frequent conveyance of small quantities of material. For processes that require large

lot production, such as stamping press, material requisition and signal kanbans are used as

equivalent in function to withdrawal and production kanbans, respectively. The signal

kanban aggregates requests from individual production kanbans and authorizes production

50

Page 51: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

when the required lot size is reached. Material requisition kanban is then used to request

material for the production of the entire run size.

Kanban FunctionMaterial Withdrawal Production Authorization

-4

D

Figure 5-3. Classification of kanban types based on its function and production lot size.

Other types of commonly used kanbans include supplier kanban, express kanban, emergency

kanban, through kanban, and job-order kanban [Monden, 1998]. Supplier kanban is a type of

a withdrawal kanban tailored to use of obtaining component parts from the suppliers. In

addition to the information every withdrawal kanban contains, the supplier kanban also

specifies the frequency of supplier delivery as well as the information that allows accounting

transactions to take place between supplier and the customer. Express kanban is used to

notify of unexpected shortage of a component and to prioritize its production, whereas

emergency kanban schedules production to make up defective units or unexpected down

time. Both express and emergency kanbans are one-time cards, which need to be removed

from the system after their use. When local information flow is not present, such as under

CONWIP control policy, a through kanban is used to identify the parts and specify their

movement between processes, restricting amount of WIP present by keeping it constant.

Finally, job-order kanban is used to schedule and authorize non-repetitive production or

services usually in support of production, such as tool or fixture procurement.

51

Withdrawal ProductionKanban Kanban

Supplier Kanban

Material Requisition Signal KanbanKanban

Page 52: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

5.2.2 Kanban Systems

In normal circumstances, the flow of withdrawal and production kanbans is sufficient to fully

authorize and control production of the system. Such kanban system is called a two-kanban

system and it is shown schematically in Figure 5-4. It consists of two conveyance loops:

withdrawal loop (marked by W), which uses withdrawal kanbans and replenishment loop

(marked by R), which uses production kanbans.

Replenishment loop Withdrawal loop

Pro tionordering post

PROCESS

Coll etingpost

With rawal Ipost

PROCESS

Figure 5-4. Movement of kanbans in the two kanban system:

- - o production kanban, - . * withdrawal kanban.

The withdrawal kanbans are collected from the downstream production unit in a withdrawal

post, shown in Figure 5-4, step W1. They are picked up by the conveyance person in the

withdrawal loop and are taken to the component market, W2. At the market, the appropriate

containers, as specified by the withdrawal kanbans, are acquired and the production kanbans

attached to them are removed and placed in the collecting post. The withdrawal kanbans are

then attached to the containers, W3, which are then transported to the next production unit,

W4. At the production unit, as the parts from these containers are used up, the withdrawal

kanbans are removed from them and placed in the withdrawal post, W1, to complete their

cycle.

The production kanbans accumulating at the collecting post at the component market, R1, are

picked up and brought to the upstream production unit, R2. There, they are placed in the

52

Page 53: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

production ordering post from which they are moved at a frequency set by a pace to the

production line to initiate the production, R3. As the production of the required parts is

completed, the production kanbans are attached to the appropriate containers, R4. The

containers are then taken to the downstream component market and placed there, R5, thus

completing the cycle of production kanbans.

The separation of the production kanbans from withdrawal kanbans allows autonomy of

replenishment and withdrawal loops, with the inventory market usually under the

administration of the production unit supplying it, the upstream unit. Each set of kanban

cards, production and withdrawal, can be managed separately, by defining the route,

frequency of the conveyance cycle as well as number of cards in the system. However, when

the production processes are a short distance from each other and they are under jurisdiction

of the same supervisor, a common kanban system can be used, thus simplifying the

management by the use of one set of cards, instead of two.

In the common kanban system, although there are still two separate conveyance loops of

replenishment and withdrawal, the same kanban is used for both of those actions. As shown

in Figure 5-4, kanbans are collected from the downstream production unit in a withdrawal

post, Wi. They are picked up by the conveyance person in the withdrawal loop and are taken

to the component market, W2. At the market, the appropriate containers, as specified by the

kanbans, are acquired and the kanbans brought are placed in the collecting post, Rl, where

they are picked up and brought to the upstream production unit by the replenishment person,

R2. There, as in the two-kanban system, they are placed in the production ordering post from

which they are moved at a pace to the line itself to initiate production, R3. As production of

the required parts is completed, kanbans are attached to the appropriate containers, R4, which

are then taken to the downstream component market, R5. From the market they are picked

up by the withdrawal loop conveyance person, W3, and are then transported to the following

production unit, W4. At the production unit, as the parts from these containers are used up,

the kanbans are removed from them and placed in the withdrawal post, Wi, to complete their

cycle.

53

Page 54: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

In this common kanban system, since only one type of kanban card is used at any time, the

containers themselves can be used as kanbans, provided that they unambiguously specify all

necessary information, such as the part type, quantity, origin and destination location. An

empty container then signifies a production order, whereas a full container initiates material

delivery.

5.2.3 Specifications of Kanban Systems

The kanban system is an information system, which harmoniously controls the production

quantities in every process and manages the Just-In-Time (JIT) production method [Monden,

1998]. The system operates by circulation of cards described in previous section, which

authorize conveyance of both material and information, thus pacing and controlling

production.

The kanban system performs multiple functions in the manufacturing system [Monden,

1998]:

" Instruction

m Self-control

" Visual control

" Improvement

" Reduction of managerial costs

Those functions are discussed hereafter.

The flow of kanbans is the means of communication between various production elements

and instruction for the entire system at a local/micro level, through direct connections

between subsequent production units, as well as at a macro level, through the single

instruction point. The kanban cards provide instruction for production by specifying the part

type and quantity requested by the customer. The kanbans also instruct conveyance by

specifying where the parts are picked up and where they need to be delivered.

The circulation of kanbans in the system also provides a self-control function for the system.

By having a closed loop of kanban flow, the number of kanban cards in the system can be

controlled and kept constant. This automatically controls the amount of inventory in the

54

Page 55: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

system and prevents overproduction. Also, since the system has a single instruction point, it

is able to respond quickly to demand changes in a self-controlled manner. In fact, the kanban

system is capable of handling ±10% fluctuations in demand volume, so called fine-tuning of

production [Monden, 1998]. More significant demand changes usually require an alteration

in the number of kanbans, which can be performed less frequently.

The kanban system also provides visual control of production levels and inventory counts.

Since each kanban card represents a container, the constant number of cards in circulation

allows easy and visual control of the production status. An accumulation of cards signals

problems, which can be quickly detected and counteracted. Because the kanban system is a

decentralized control system, the characteristic of being visual makes it transparent, which is

especially essential at the interface between local units, for example at the component market

place between the replenishment loop in its upstream unit and withdrawal loop in its

downstream unit.

The kanban system also serves to improve the process and manual operations. The close

control of production status through frequent conveyance of information in the kanban

system communicates problems quickly and allows the focus of additional resources to

overcome the obstacles. By increasing the frequency of conveyance, the instruction interval

for production and conveyance is greatly reduced at the same time, striving toward one piece

production and conveyance, which leads to true single piece flow of material as well as

information.

Finally, the single instruction point and the self-controlling property of the kanban system

allows for reduction of managerial costs. The kanban system, although requiring rigor in its

implementation, is simple to use. The role of the scheduler is greatly simplified, compared to

a conventional central control system; here, only one point needs to be informed of customer

demand and the demand information will propagate through the system via the kanban flow.

55

Page 56: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

The implementation of the kanban system requires specifications of certain parameters to

completely characterize the operation of this production control system. Table 2 lists some

of those design factors.

Table 2. Kanban System Operation Design Factors [Berkley, 1992].

1. Kanban numbers2. Container processing (run) time distributions3. Setup time distributions4. Finished-goods demand5. Supply of purchased raw material6. Line configuration/Part routings7. Station blocking mechanism8. Number of part types9. Part yields10. Part container size11. Batch sizes (in containers)12. Station container sequencing rule13. Number of machines per station14. Machine reliability15. Worker flexibility16. Worker assignment rule17. Material handling trigger18. Material handling frequency19. Number of part-carriers20. Availability of part-carriers/Part-carrier assignment rule21. Part-carrier capacity22. Material-handling operation time distribution23. Material-handling operation blocking mechanism24. Material-handling operation container sequencing rule

By defining these parameters, the kanban system can be designed and implemented.

However, in order for it to perform satisfactorily, diligence is required. The following

application rules of a kanban system [Monden, 1998] depict this diligence:

A process should withdraw the necessary products from the preceding process in the

necessary quantities at the correct time. This rule is necessary to prevent ambiguity in the

connection, as mentioned at the beginning of Section 5.2. For this purpose the kanban card

explicitly specifies the part type, quantity and location (both of origin and destination). This

56

Page 57: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

rule also requires that people performing the conveyance follow these instructions on the

card and their designated routes.

The preceding process should produce its products in quantities withdrawn by the subsequent

process. This rule, similar to the previous one, is necessary to prevent ambiguity in the

connection. It specifies that production should only be initiated in response to receiving a

production instruction for a specific part type and only the requested number of parts should

be produced, as specified by the received production kanban.

Defective products should never be passed to the next process. Otherwise, a shortage of

parts will be created downstream or defective product will be produced, resulting in costly

scrap or rework. This rule complements the previous two in preventing ambiguity in the

connections between production units. If a request for a given quantity of parts is sent, it

signifies the exact quantity of good parts that should be conveyed.

The number of kanbans should be minimized. Since the number of kanbans determines the

size of the inventory held, the reduction in the number of kanban will yield cost reductions.

Although the number of kanbans is calculated according to specific formulas based on

customer demand (described in Section 5.3.3), the line supervisor makes the final decision on

how many kanbans should be circulating, based on the knowledge of process capability of

the given area. Too small number of kanbans will lead to delivery shortages, whereas an

excessive number of kanbans will create inventory build up, material stagnation and slack in

the conveyance.

Kanbans should be used to adapt to small fluctuations in the demand (fine-tuning of

production). The self-control characteristic of the kanban system, therefore, apart from

managing the fluctuations in demand, should be used to detect problems with purpose of

resolving them, rather than their concealment. The system does need to be designed with

robustness against defects; this, however, should be done through error-proofing devices,

called poka-yoke, as well as express or emergency kanbans rather than compensation for

defects through delivery of extra parts. The kanban system is also capable of managing

57

Page 58: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

delivery of parts that have by nature unstable usage, such as weights used to balance

irregularities in shaft rotation.

The actual quantity of parts contained in a box or packed in a load must be equal to the

quantity written on the kanban. This rule complements rule 1 in preventing ambiguity. Since

the kanban card explicitly specifies part quantity, each container for the given part type

should contain a constant quantity and no partially filled containers are allowed.

The essence of the above rules specifies the connection between production elements in a

direct and standardized manner and prevents ambiguity, thus providing a binary yes/no

connection in material and information flow. Adherence to these rules will ensure proper

performance of the kanban system to its full advantage, thus providing a complete production

control system.

5.3 Conveyance Methods

The conveyance between production elements and their market places, i.e. the replenishment

of used parts with parts withdrawn from the previous element, is critical to the performance

of the system as it executes material and information flow between them and provides

instruction for production throughout the system. The conveyance frequency determines the

management time frame for the system, i.e. the interval at which the performance can be

monitored and, if necessary, adjusted [Rother and Shook, 1998].

5.3.1 Mechanism of Conveyance

The execution of both withdrawal and replenishment is shown schematically in Figure 5-4.

The withdrawal loop starts at the withdrawal post, from which the conveyance person

performing the loop picks up accumulated kanban cards, Wi. The cards together with empty

containers, if applicable, are then taken to the upstream component market, W2, from which

the required parts are withdrawn and empty containers dropped off, W3, and at the same time

information to replenish them is sent upstream, Ri. The withdrawn parts are then taken to

the line requesting them, W3. The conveyance person then proceeds to the withdrawal post,

Wi, and continues another cycle of the withdrawal loop. One conveyance person usually

58

Page 59: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

performs this entire loop, provided that the distance between the production element and the

market place is sufficiently short to allow for frequent conveyance. However, a withdrawal

in a given loop can be done for multiple types of components and the same conveyance

person can stop at multiple market places or even service multiple lines during a complete

cycle, as long as the loop route can be standardized.

The replenishment is initiated with the withdrawal of the parts from the component market

described above, W3, and the request to replenish them. This request signal is manifested by

cards accumulated in the collecting post, Ri, where the replenishment loop starts. Here the

cards are picked up and sequenced in the production ordering post, R2 from which they are

delivered in a specified interval (production ordering pitch) to the line, R3. At the end of the

line, the parts can then be picked up, R4 and delivered to the market place. The pickup of

parts is usually accompanied by delivery of empty containers to store produced parts. In

order to ensure constant WIP within the given production unit as well as monitor its

production status to prevent unexpected delays in production, the pickup of parts should be

done in terms of equal exchange of empty containers with full ones. Also, the interval at

which the withdrawal of parts from the production unit is performed (retrieval pitch) should

be equal to the production ordering pitch. This sometimes is reinforced by the above

mentioned equal exchange of empty and full containers, where an empty container is an

additional authorization to produce parts and its absence stops further production and thus

prevents overproduction.

It is important to mention that the market place is usually under the jurisdiction of its

immediate supplier and is therefore placed close to it. This allows for an easy visual control

and a sense of ownership, which helps promote process improvements leading to inventory

reduction. Because of the market location close to the supplying production unit, usually the

replenishment loop for the market is much shorter and thus a more frequent monitoring of the

production is possible. The withdrawal loop, however, is longer, which often advocates

withdrawals of multiple parts in a single route (mixed loading).

59

Page 60: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

5.3.2 Pacemaker Element Withdrawal

An important element of a linked manufacturing system is a consistent, level production

scheduling of small quantities of work, called paced withdrawal [Rother and Shook, 1998],

which allows for frequent and regular monitoring the performance of the entire system to

customer demand. The pacemaker element of the system - the single instruction point in the

linked-cell system - receives the demand information and propagates it upstream through the

local connections between the elements. Thus, the pacemaker element sets the pace for

production in the entire system.

The pacemaker element receives leveled demand information through paced withdrawal.

Thus, the withdrawal loop for the pacemaker element is crucial for the performance of the

entire system. A tool used by some companies to implement level schedules in mix and

volume is called a heijunka box [Cochran, 1998], shown in Figure 5-5. The heijunka also

serves to instruct the paced withdrawal of material at a given frequency as defined by the

withdrawal pitch.

Figure 5-5. Heijunka: tool for leveled scheduling and paced withdrawal.

60

Page 61: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

PACEMAKER SHIPPINGELEMENT

Figure 5-6. Paced withdrawal loop from heijunka to pacemaker element.

A withdrawal mechanism is shown in Figure 5-6. The paced withdrawal loop starts at the

heijunka box (1), from which the conveyance person performing the loop picks up the

kanban cards for the given pitch interval. The heijunka determines the frequency of

conveyance, as specified by the withdrawal pitch, the quantity conveyed, and the sequence of

the production during the next pitch interval. The remainder of the loop follows similarly to

any withdrawal loop from a production element (or replenishment to a market place as

described in Section 5.3.1) allowing replenishment of the parts market.

5.3.3 Types of Conveyance Methods

In order to manage minor ( 10%) fluctuations in demand, the withdrawal and replenishment

systems cannot be over-constrained; the conveyance frequency and the quantity conveyed in

each cycle cannot stay the same when the demand changes. This is a necessary characteristic

for production fine-tuning in the kanban system. Therefore, two general types of conveyance

methods are commonly used [Monden, 1998]:

" Constant cycle (non-constant quantity)

- Constant quantity (non-constant cycle)

In the constant cycle conveyance, the withdrawal or replenishment loop is performed always

at the same frequency, for example, once every hour. Depending on the demand, however, a

different number of kanbans will be picked up at the kanban post (W1, Ri, R2 in Figure 5-4),

resulting in conveyance of non-constant quantity (although always in accordance with the

number of cards picked up). This method is especially applicable when a single conveyance

61

Page 62: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

loop services various production units. With constant cycle conveyance, when demand

fluctuation causes the production rate of one of the units to change, the number of the cards

picked up and quantity of parts conveyed every cycle will change, but the other units will not

be affected. Constant cycle conveyance is also required for parts with unstable usage, as

described in Section 5.2.3, which by nature have a varying quantity of consumption and

therefore conveyance.

In constant quantity conveyance, on the other hand, the conveyance will occur when a

predetermined quantity of parts is requested and thus when a predetermined number of

kanbans is collected. However, depending on the demand, the frequency with which the

conveyance takes place will change. This method is especially applicable if the conveyance

loop services a single production unit but many market places. If the production rate changes

due to demand fluctuations, the same quantity can still be conveyed but the frequency will

change based on the production rate change. This method, however, requires continuous

monitoring of inventory or number of collected kanbans, since the conveyance is initiated

when a specified number is reached.

The number of kanban required in the system in the constant cycle conveyance is given by

formula [Monden, 1998]:

Total Number of Kanbans = Dx(LT+CC+SP)CD

and for the constant quantity conveyance is given by formula:

Total Number of Kanbans = Dx(LT+SP)CD

where D is the average daily demand, LT is the lead time, CC is a conveyance cycle or

interval, SP is a safety factor, and CD is container density or capacity. Lead time, LT is

defined as:

LT = (processing + waiting + conveyance + kanban collecting) time.

The difference between these two formulas is the inclusion of the conveyance interval in the

calculation of number of kanbans for the constant cycle method, which will increase the

number of kanbans required for this method relative to the constant quantity method. The

reason for this difference is that whereas in the constant quantity method, as soon as the parts

62

Page 63: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

are used, their replenishment is initiated, in the constant cycle method, the request has to wait

up to a full conveyance interval before being picked up and fulfilled.

For example if the average daily demand is D = 60000 pcs./day, LT = (processing + waiting

+ conveyance + kanban collecting) time = 3h + 0.5h + lh + 0.5h = 5h, and CD = 10 pcs.,

with SP = 3h, total number of kanbans for the constant quantity conveyance method = 2000,

and for the constant cycle conveyance method with CC = lh, total number of kanbans =

2250. The final number of kanbans, although based on the above formulas and calculated as

shown in the example above, is subject to change by the supervisor [Monden, 1998]. Those

adjustments are usually done through changing of safety factor, SP, which allows increase in

the number of kanbans depending on process capability.

5.3.4 Examples of Withdrawal Systems

The conveyance method - constant cycle vs. constant quantity - specifies the mechanism by

which the system adjusts to the changes in customer demand: either by varying the quantity

conveyed or varying the conveyance frequency. However, how the replenishment and

withdrawal is actually performed also depends on other issues, such as local inventory

strategy and the control policy adopted.

Figure 5-7 shows various examples of conveyance loops. Figure 5-7(a) depicts a system

similar to the one discussed in Section 5.3.1 and presented in Figure 5-4. This system

operates under pure pull control policy with build-to-stock (BTS) inventory policy. Figure

5-7(b) represents conveyance under sequential pull, where the inventory strategy is build-to-

order, BTO. Figure 5-7(c) shows CONWIP control policy with BTO inventory strategy. All

the above mentioned conveyance routes can be performed using either of the two conveyance

methods described in Section 5.3.3, either constant cycle or constant quantity. Also, it is

interesting to note, that customer lead time is different in each case, and is determined by the

length of the conveyance loop itself and, in case of sequential pull and CONWIP control

policies, also by the processing time which is included in the route.

63

Page 64: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

PRCS SHIPPING

b)-

PROCESS PROCESS SHIPPING

PROCESS PROCESS SHIPPING

- FIFO --

Figure 5-7. Various conveyance loops: a) pure pull/BTS, b) sequential pull/ATO,

c) CONWIP/BTO.

Two commonly used withdrawal systems are later replenishment withdrawal and sequenced

withdrawal [Monden, 1998]. The later replenishment system operates under the BTS

inventory strategy, where the components are stored in a market place (as in Figure 5-7(a))

and then withdrawn based on a constant cycle withdrawal loop. The components specified

by the withdrawal kanbans brought from the local customer by the conveyance person will be

delivered to this customer just one cycle later, when the conveyance person finishes the loop.

The market place from which the parts were withdrawn will be replenished later, after the

production ordering kanbans make their loop. Due to the necessity for inventory in the

market place under this system, it is usually used for small components with few varieties.

64

Page 65: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

When the size of inventory required in a market becomes an issue, making it infeasible to

implement BTS strategy, the sequenced withdrawal system is used. This system performs

under the constant quantity conveyance method and is usually used for components such as

engines or transmissions in the automotive industry [Monden, 1998] - large parts with many

variations. This system works under BTO strategy, as shown in Figure 5-7(b), (c). The

kanban cards are taken to the supplying production element; however, the corresponding

components are not brought back until a few conveyance cycles later, when the production of

those components is completed. This system avoids costly inventory, however it requires

that production lead time of the supplying production element is sufficiently short to supply

the parts on time. Another way to shorten the response time in this system is by sending the

requirements instantaneously via fax or electronically, so that the kanban conveyance time of

information between customer and supplier is shortened. This system, however, also

requires that from the moment the withdrawal loop is initiated, the production sequence of

the customer cannot change and thus the production sequence at the supplier does not have to

be readjusted.

65

Page 66: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

66

Page 67: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

6 Case Study

The case study project for this work took place at Visteon Automotive Systems in Monroe,

Michigan. Monroe plant is a facility of 1.5 million ft2 employing around 2200 workers with

a strong unions presence. It supplies various automotive components to 47 different

customers. The main product areas are steel wheels, coil springs, stabilizer bars, catalytic

converters, body components and hot stampings, with an annual production of 38 million

components.

The manufacturing system studied is a production line for catalytic converters for over 8500

F-series and Econoline trucks, supplying multiple customer plants. The product, shown in

Figure 6-1, weights up to 30 lb and is up to 5 ft long. It comes in 20 varieties and consists of

up to 11 different components. Some of those components are common to all types of

converters (mat mount and seal), some are complementary and not required on all types of

converters (hanger rod, upper shield), and the rest come in different varieties (three varieties

of inlet pipe, eight varieties of outlet pipe, five varieties of catalyst, etc.). The components

are delivered by various external suppliers, from few times daily to once a month, and a

single internal supplier twice a week.

The planned annual production volume for the line in 1998 was 350000 parts. The parts are

supplied to two main customers and few other customers on less regular basis. The line

produces components for current model cars - amounting to 91% of the total production, as

well as parts for service - 9% of the production.

67

Page 68: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

MAT MOUNT (3) UPPER SHIELD

AIRADATERCATALIST (3) (6 UPPER SHELL

INLET PIPE

ID PLATE L[E SELOUTLET PIPE

LOWER SHIELD

Figure 6-1. Catalytic converter - product considered in the study and its major components.

This chapter describes the initial production system (circa June 1998), the redesigned system,

as well as the transition state in the implementation (circa August 1999), with focus on the

information system.

6.1 Initial System

The initial manufacturing system is illustrated in Figure 6-2. It shows information and

material flows between all elements that participate in the manufacturing process, from the

moment the raw material enters the plant from the suppliers to the moment the finished

converters leave the plant to be delivered to the customers - for the entire value stream.

The initial system consists of seven major elements: shipping, central scheduling, assembly

line, sub-assembly station, piercing operation, stamping press and purchasing department.

The material flow in the initial system is under a push mode, with a central production

control system (Figure 6-2: 4) that sends out information on what and when to produce. The

system has multiple instruction points; the control information is sent separately to different

stages in the material flow. Because of this, the different stages of the value stream are only

linked through the central production control system and scheduling. The material and

information flows between the various stages in the value stream are decoupled not only

68

Page 69: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

through the information system but also through the use of a central hi-density inventory

(Figure 6-2: 11) where parts and components in various production stages are being stored.

PURCHASING SCHEDULING CENTRALy~)4 PRODUCTIONCONTROL

monthly and weeklproduction plan

weekly ad daiy (

SU -productio n sc ltle s 5~

ASSEMBLY

SUPPPLIERS ICUSTOMERS

G ASSEMBLY SHIPPING 2daily

Staging

STAMPING PIERCING

Figure 6-2. The initial manufacturing system at the facility level: information and material

flow [Br6te, et al. 1999].

6.1.1 Information Flow - the Initial System

Starting at the customer's side of the value stream, the customer sends its one-year forecast

schedule, one-month firm schedule, and its final one-week schedule for all products needed

to the central control system (Figure 6-2: 1). This information is sent to the plant - to its

scheduling and shipping departments. The one-year forecast is used for capacity planning for

the line at the tactical level. The one-month firm schedule and final one-week schedule are

used to schedule the production and introduce last minute changes to the schedule at the

operational decision making level.

The shipping department uses the customer demand information to schedule its shipping

windows, i.e. what and when to ship (Figure 6-2: 2). The shipping department pulls the

products to ship from the finished goods inventory or in some cases ship whatever is on

hand, in a push mode. In emergencies, when product is not ready, the shipping department

69

Page 70: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

contacts the scheduling department (Figure 6-2: 3) to determine the status of the parts and to

let them know how many parts are needed. The scheduling department receives the same

information from the customer as the shipping department. The scheduling department

compares the release of the customer demand for the given week with the balance on hand

(BOH) - the finished goods inventory - for all different products (Figure 6-2: 4). Based on

differences between the customer release and the BOH, production in the required production

areas is scheduled for the entire week. The scheduling department manually distributes the

weekly schedule to the managers of the various production areas (Figure 6-2: 5). The area

managers are responsible for adjusting the production schedule to react to line downtime

(Figure 6-2: 7,8,9,10) caused by such problems as component shortage, machine failures, or

workers absenteeism. At the end of each day, the scheduling department is informed of the

on-time status of the production areas, enabling the scheduling department to further adjust

the schedule and plan for overtime.

The scheduling department is also responsible for scheduling the production or purchase of

necessary components based on the one-month customer schedule (Figure 6-2: 6). The

monthly component demands are calculated by breaking the customer monthly demand into

its components. If the balance on hand for a component is less than the monthly demand or if

the BOH reaches its required minimum level, production will be scheduled or the purchasing

department will be informed to purchase more parts. The same system is used for the

scheduling of the purchase of raw material. For the press area (Figure 6-2: 10) the

scheduling department determines and informs the purchasing department as to how many,

how large and when the new steel coils are needed. Because of the system of infrequent

ordering and a minimum level of BOH triggering the scheduling department to schedule

production and inform the purchasing department, the purchase of components is only

vaguely coupled to actual usage of components. Since the production of components is not

scheduled based on the actual usage, all manufacturing areas have to be scheduled separately

and lack predictability - thus often leading to component unavailability.

6.1.2 Material Flow - the Initial System

The material flow for the value stream selected for the study is described below, starting

downstream, with the customers. The finished goods are shipped to each customer once a

70

Page 71: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

day. As described in the previous section, the shipping department pulls the products to ship

from the finished goods inventory (Figure 6-2: 2).

The assembly line (Figure 6-2: 7) delivers its finished goods, in containers holding between

76 and 98 parts, to the finished goods inventory where they are stored until the next shipping

window. The container size varies for different finished goods parts, with the result that it

cannot serve as a standard production unit. This inconsistent pack size creates several

problems with material flow in the plant. First, it introduces inconsistency of throughput

time into the system, since each container might take a different production lead time. This

causes unpredictable intervals between container deliveries among the elements of the

system downstream from the assembly cells, including the customer. Second, each part type

has a different pack quantity requiring a different pitch, or time interval between production

signals. Because of the central scheduling system, the important link between information

and material flow is lost throughout most of the value stream in the plant. Without constant

pack quantities across all finished goods, standards for pack quantities for purchased parts

and parts supplied in-house cannot be established. Thus, creating a pull system using tools

such as kanban is difficult.

TIPUP P UP

Material flow

WIP accumulation

Figure 6-3. The initial assembly line layout.

71

Page 72: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

The assembly line (Figure 6-2: 7) operates at two shifts a day, five days a week. Based on

the demanded volumes from the customers, the line has to produce 90 parts an hour, or at a

takt time of 40 seconds. Since the line is designed for mass production and 90 parts an hour

is close to the maximum production rate of the line, each operator is tied to one machine

making the line inflexible to volume changes. The line layout, presented in Figure 6-3,

shows that the material flow through the line is complicated and difficult to follow making

defect detection and tracking difficult.

Since each machine in the assembly line has a different cycle time (ranging from 5 to 40

seconds) and the assembly line has not been balanced to a specific takt-time, there is a

substantial amount of work-in-process (WIP) between the stations that decouples the demand

from one station to another. Conveyors holding WIP parts between several of the stations

prevent reinforcing the principles of first-in-first-out (FIFO) which together with high WIP

levels makes it difficult to detect and prevent production of defects at their source, even

though the production runs with a batch size of one piece. Since there are 20 variations of the

final product, with different components and variations of components between them, there

are multiple decision points in the manufacturing process, which determine final product type

and where the information has to be delivered. Production instruction is partly controlled

through changeovers, where the new parts to be used are brought to the line and the parts not

to be used are taken away. Since there is no common container quantity for the components,

which vary in number between 250 and 1700, the parts taken away from the line are stored as

partials. Most of the parts and components being used are purchased parts, which upon

delivery from the suppliers are stored in hi-density storage (Figure 6-2: 11). The other

components being used come from sub-assembly (Figure 6-2: 8) and from stamping/piercing

operations (Figure 6-2: 9,10).

The sub-assembly station (Figure 6-2: 8) consists only of manual operations, but due to the

operating mode, it runs and produces the required quantity on a one-shift-per-day pattern.

The sub-assembly station is scheduled separately from the assembly line and has its own

local part-inventory for components and finished sub-assemblies (Figure 6-2: 12). Because

72

Page 73: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

some of the components used in subassembly are easily damaged, the multiple transportation

and storage creates many quality problems.

The stamped parts used in the assembly line are brought from hi-density inventory (Figure

6-2: 11). The stamping area runs stampings twice a week (Figure 6-2: 10), limiting the

inventory level to a half-week's demand plus safety stock. Some of the parts are also

required to go through a piercing operation (Figure 6-2: 9). These parts are pushed through

the piercing operation prior to storing them in the hi-density storage. Besides the parts

produced for the assembly line, the stamping press runs eleven other parts - all shipped to

external customers, total of twelve parts. Among the other eleven parts, six are high runners

(high volume production) that are produced every week. The other five parts are scheduled

when needed to run either during one shift or the other in a week. The press runs at two shifts

per day and five days a week, with production scheduled in a sequence that minimizes

inventory. Since six of the seven high runners are produced for an external customer, the

production of these parts is sequenced in such a way that the parts are shipped when

produced with the schedule optimized to the shipping windows. The shipping windows for

the stamped parts are Monday, Tuesday and Friday.

6.2 Redesigned System - Towards the Ideal State

The initial system described in the previous section has been redesigned using the PSDD

framework. The overall goal of the new design has been to reduce waste and create a

manufacturing system with deterministic output, following the objective of minimizing mean

delivery time and its variation, and thus making the system responsive to customer

requirements. Such a system exhibits leveled production according to the actual demand as

specified by takt time and is capable of volume flexibility. It also has a reduced amount of

WIP, which shortens lead time. The goal is also to achieve single piece production and

conveyance at all points in the system - true single piece flow throughout. The redesigned

system described below is a first step towards this ideal.

73

Page 74: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

In the newly designed linked-cell system, shown in Figure 6-4, the subassembly element

(Figure 6-2: 8) has been integrated into the assembly line (Figure 6-2: 7) and thus is

represented in a single unit as the assembly cells (Figure 6-4: 7). The assembly cells unit is

also a pacemaker element of the system.

rSUCUSTOMERS

dailyy

F C ~FIFO+- Staging

STAMPING _

PIERCING

@

Figure 6-4. Redesigned system at the facility level: information and material flow.

An important enabler to the redesigned system is the establishment of a constant pack density

of the finished goods, or a constant number of parts, regardless of type, in a container. A

quantity of 72 has been picked as it can accommodate all part types. This constant quantity

makes it possible to treat a container as a production unit with predictable production lead

time, enabling implementation of a kanban system.

6.2.1 System Level - Redesigned System

The information flow in the redesigned system starts with the customer. Based on the actual

demand, the customer sends the demand information to the plant via kanban cards, which

specify how many containers of what part type are requested (Figure 6-4: 1). This

information conveyance takes place daily when the parts from the previous order are

delivered (Figure 6-4: 2). Therefore, the system operates under BTO strategy with no

74

Page 75: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

finished goods inventory. Upon their arrival in the plant, the cards are delivered to the

shipping/scheduling unit, where they are sorted and deposited in the leveling box (Figure 6-4:

3). The leveling box makes it possible to schedule the ordered parts into specific time slots

for the day.

It has been shown that the great demand variations in the initial system were mostly caused

by internal variability in production. The customer plant is designed to produce at a constant

pace, incapable of frequent rebalance, meaning that the customer is steady and paced and the

only way to increase production is through changing operating time. Volume fluctuations are

therefore easy to predict and plan for. The demand mix - the ratio of demand for different

part types - does fluctuate within a ±10% range depending on component availability from

other suppliers. Therefore, with leveled scheduling and simplified value stream, the demand

variations have been shown not to exceed ±10% in mix and volume. Thus, the leveling box

can be established once a month, based on the monthly forecast, but actual consumption,

communicated daily, is used to load the box and schedule the production, using the fine-

tuning characteristic of a kanban system to manage minor variations.

The pitch of the paced withdrawal is 1.5 hours, due to the large distance between the

assembly cells unit and the shipping unit. The conveyance operates under a constant cycle

method and is shown schematically in Figure 6-5. During this pitch, the conveyance person

picks up the kanban cards for the next pitch interval from the box and an equivalent number

of empty containers and delivers them to the assembly production unit drop off area. From

there, the equivalent number of full containers is picked up and delivered back to the

shipping, where they are staged waiting for delivery to the customer. The shipping staging

area uses visual monitoring of the production status, based on how many containers are

waiting. It is important to note that, since the conveyance person operates on a constant

cycle conveyance method, more than one production unit can be serviced by the same loop in

mixed loading, as shown in Figure 6-5 and thus increase efficiency of the conveyance loop.

75

Page 76: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Basket Staging Area

............. . ........

-.lu- 36 34

37 35

Shipping

3dSchedu in Box

Pitch Clock

h: min

1:30

Figure 6-5. Pacemaker conveyance loop from shipping to the assembly element.

The filled containers are brought to the drop off area by a forklift, one by one. The forklift

can service many production units similar to the above mentioned conveyance loop, and it

can operate on demand. As a line completes a container and starts to fill a new one, the

forklift is informed and it picks up the full container and leaves an empty one. This dual

conveyance: first by the external withdrawal loop and then by forklift and internal

replenishment loop (described below) - was chosen because of the great distance between

the shipping and production units. Hence the containers cannot be taken to shipping one by

one and need to be taken in a train, which is done in the external conveyance loop.

From the assembly production unit drop off area in Figure 6-5, the kanbans are then brought

to the assembly production unit itself. Here, the kanban cards instruct the material

replenisher as to what components are needed. Thus, the replenishment of material is

coupled with the conveyance of customer demand. Material replenishment, therefore,

provides production authorization and instructions to the workers by giving them the material

necessary to produce a specific product. Since the material replenishment loop is the

system's instruction point, downstream operations are performed in a stream flow mode.

76

Delivers informationFrom Heijunka in Shipping

- To Cells

Removes finished goods- Takes away full containers- Brings empties

Page 77: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

This internal conveyance loop makes it possible to increase the conveyance frequency to the

cell and thus keep tighter control of production status. Every internal pitch (usually every 15

min.), the replenishment person delivers the required components in the required quantity.

This conveyance loop operates on a constant quantity method, with the same amount of

material always being delivered (components necessary for 18 parts which is % of the

finished goods container size), although frequency of the conveyance might vary depending

on the demand variation. The constant quantity method was used because of the great variety

of components and their size as compared to the available space at the cell. Due to the

number of parts needed to produce all the variations of the end item, the floor space needed

to hold even one container of each type would exceed the floor space available. By linking

the customer order point to material replenishment and supplying material to the cell in

constant quantities, only the parts that are needed will be in the cell racks. This also

eliminates possible quality problems caused by operators using incorrect components.

Delivering only the necessary types of components in small quantities also helps to eliminate

lengthy material changeovers (initially up to 30 minutes) between different part type runs.

However, in order to make the system robust against incoming material defect problems, an

emergency system is required to allow replenishment of additional parts, when need. This

can be done with an express kanban or an Andon display that communicates shortages and

instructs redelivery of certain parts. It should be noted, however, that incoming quality

problems were insignificant to begin with, compared to internal quality problems; this source

of defects was eliminated through the integration of the processes and reduced WIP in the

redesigned line as described later.

Components delivered to the assembly cells in the internal replenishment loop are picked

from a component line side market located close to the cells (Figure 6-4: 12). From that

market, as the components are consumed, the withdrawal kanbans instruct suppliers to

replenish them (Figure 6-4: 6). The internally procured parts (stampings) are delivered to the

assembly unit from the stamping press market (Figure 6-4: 11). From this market, a signal

kanban is used to schedule production when the level of a given component reaches a

77

Page 78: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

minimum quantity. The signal kanban is sequenced together with signal kanbans for other

parts that are produced in that specific press. This sequence determines the operating pattern

at the press, i.e. which parts, what quantity, and in what order to produce. The sequencing

board also indicates when to make changeovers, as well as when and what kinds of coils are

needed. As the parts leave the press, they go through the piercing operation (Figure 6-4: 9),

if required, before they are placed in the market. The steel for the stampings is obtained from

the coil market using material requisition kanban. From that market, the information is sent

to the supplier to replenished used coils (Figure 6-4: 8).

6.2.2 Line Level - Redesigned System

The redesigned production unit layout is shown in Figure 6-6. As mentioned earlier, the sub-

assembly production unit has been integrated with the assembly line and rearranged into a U-

shaped cell configuration. The subassembly operation has been redesigned and balanced

with the cycle time of the rest of the cell to equalize the production operating pattern of both

of those production units.

Line side component market

PNL

IIc

Material flow

Figure 6-6. The redesigned assembly cells layout.

In order to design a value stream that is able to produce at the customers' demand cycle time,

the cell has been designed as a linked part of the value stream with a focus on the customers'

demand volumes and their variations for all parts produced within that cell [Br6te, et al.

78

FIFIFT-1

PW MR

iM-7

EF I F1 F-I F-I 1-1 El

Page 79: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

1999]. Hence, the cell should enable a flow of parts at the ideal range of cycle time.

Consideration has also been given to volume fluctuations; the cell must be able to operate

within a range of demand fluctuations. The maximum level of expected demand puts a

requirement on the minimal takt time, a time at which all machines within the cell must be

able to operate. Since the product design has been held constant within the scope of the

project, the machines chosen for the project must be able to meet the requirements of the

existing product design, and at the same time be able to operate at the recommended

minimum takt time. If the cell is to operate and adjust to different demand levels efficiently,

it must be able to increase and decrease its capacity in small incremental steps. The ability to

increase and decrease production capacity within the cell corresponds to the need to operate

at different takt times in order to avoid the waste of overproduction. The cellular layout,

together with the decoupling of operators from the machines through SWIP, enables the cell

to be run at different takt times just by adding or reducing the number of operators in the cell.

In this way production volumes can be increased or decreased incrementally.

The decoupling of operators from the machines is done by autonomation. Autonomation is

used so that the operators start the manufacturing or assembly operation by loading the

machines, activate it by pushing the start button, and then walk to the next machine without

waiting for the machine to finish its cycle. The machines run and often even unload

themselves during the machine cycle time. This decoupling of operators from machines

allows for better utilization of the operators' time. An example of autonomation in the

redesigned cell is the seam welding station. After loading, the operator starts the cycle by

pushing a button and walks away with the previous part to the next station. Due to existing

equipment limitations, however, the seam welding machine is not equipped with the auto

unload feature. Upon return, therefore, the operator has to manually unload the previous part

before loading the next one. Since the machine cycle time is less than takt time, the cell is

able to always run at takt time. This way the throughput time - the time it takes one part to

go through all operations - is always the same and therefore predictable.

One of the goals for the system and cell design is to obtain predictable output in terms of

time and quality. The predictability of output requires a low scrap rate, which can be

79

Page 80: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

obtained by visualizing the material flow and thus enables fast failure detection and quick

response. Alternative material flow should be avoided so that the machines that produce the

defect can be easily identified. The use of standard operation work sheets, which tell the

operators what tasks to perform to achieve various takt times, also describes the work content

for the different operations so that they will be performed in a consistent manner.

Two independent cells were formed for reason of increased capacity requirement, Figure 6-6.

Both cells have machines placed close one to another in a U-shaped configuration. The close

placement of the machines not only minimizes walk time for the operators but also reduces

the amount of WIP and reinforces FIFO flow in the cell. No conveyors are present between

stations, only a simple slide rail, which aids the operators as they move the parts between

stations, walking. The amount of incoming material is under tighter control. The parts are

delivered to the line in small batches (18 parts). Material delivery is performed through flow

racks from the outside of the cell so that material replenishment is non-disruptive to

production and workloop pathways. The parts delivery through flow racks also improves the

presentation of parts to the workers. They are easily accessible on the path between stations

or at the stations themselves.

Since the changeovers will be done sequentially as the new material is delivered to the cell,

there is a need for a visual changeover sign to inform that a changeover is in progress [Br~te,

et al. 1999]. Changeovers in this system are indicated in two ways. First, there is a

changeover card highlighting changeovers to the material replenisher as the material is

delivered. To instruct the operators that a changeover should take place, a wooden stick is

placed between parts being used for the previous product and parts being used for the new

product. In this way, the operators are given a signal to perform the changeover.

The location of the line side component market directly next to the line makes the

components easily accessible to the replenisher. The replenishment can be performed by a

single person, servicing both cells, and the component market can be visually managed from

the line.

80

Page 81: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

6.3 Present System - Transition State

PURCHASING SCHEDULING PRODUCTON

CONTROL

Ar ~p ouc *ion sc ules

SUPPPLIERSt

daily XOX ASEBYSHIUING

-FIFO+ Staging

STAMPING PIERCING

Figure 6-7. Present system state at the facility level: information and material flow.

motly and weekiproduction plan

=CUSTOMERS

The present state is a description of the system in August 1999, and is only considered to be

one step in the process towards the designed system or the ideal. The implemented system is

shown in Figure 6-7. This section describes the implementation status of the system by

listing successfully executed elements as well as a discussion of issues that inhibited

progress. Table 3 compares the performance of the system before and after initial

implementation of changes.

Table 3. Comparison of system

implementation.

performance measurements before and after initial

Performance Measurements State of the SystemBefore Implementation After Implementation

Production volume 1600 parts per day 1600 parts per dayWork in Process ~1000 parts 15 partsInventory Large and variable 3 daysFloor space consumed 5000 ft' 4600 ft2

Throughput time (Dock-to-dock) 182 hours 92 hoursNumber of defects per month 300 parts 100 partsFirst time Through (no defects) 26% 52%Number of workers (direct/indirect) 14/6 11/4Material replenishment interval 2 hours 20 min.

81

Page 82: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

One of the most successful implementations was reconfiguration of the assembly line and the

integration of the subassembly process into the new production unit, Figure 6-6. In addition,

the material flow within the production unit was examined and splitting the line into two

independent cells eliminated any parallel flow, allowing failure detection and quick response

to production disruption to be supported. Since there are two major customers for the

products, the best way to design the cells would be to have each cell dedicated to one

customer and responding to its needs. However, constrained by the equipment available and

due to financial restrictions, the cells had to be divided by type of process. This required both

cells to be scheduled together although the takt time for both cells is different and it is of

course a limitation to the flexibility of both cells. Having two cells instead of one increases

the takt time per cell since customer demand cycle time is divided between two cells. In the

case of this project, the split of the line gave production rates of 72 and 21 parts an hour for

each cell, respectively, equaling 90 parts per hour in total. The slower production rates -

longer takt time - makes it possible to run the machines at a slower machine cycle time,

which may improve product quality and reduce the wear on the machines and tools.

Both cells were installed using mostly existing equipment without additional investment.

The close configuration of the machines reduced greatly the amount of WIP, from over 1000

pieces down to 15. This WIP reduction not only shortened the lead time of the process from

hours down to minutes, but also improved detection of defects in the cell and communication

among workers. The result is improved quality in terms of overall defects as well as first

time through, as shown in Table 3. Overall, the reduced quantity of WIP made the

production output more predictable in terms of both the quality and lead time.

Predictable production resources regarding both human and machines are, of course,

necessary, [Br6te, et al. 1999]. Causes of unplanned downtime should be documented and

analyzed to prevent their reoccurrence. In general, solutions to downtime problems can be

classified as design change, preventative maintenance scheduling or repair when down. The

degree to which the system can respond quickly to downtime will greatly influence the

information and material flow side of the system design and its performance. With high rates

82

Page 83: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

of downtime, the system becomes less responsive to customer demand and both functional

requirements of the system are negatively affected.

The configuration of the cell, with machines placed close together and absence of conveyors

between stations, allowed implementation of workloops in which some operators are able to

perform more than one operation during cycle time. However, there were some limitations in

the implementation. Firstly, since the cell consists of previously purchased equipment, the

distance between some of the stations is larger than optimal because of the size of some of

the machines. This increases the walking distance for the operators performing workloops

increasing non-value-adding movement. Secondly, because of the existing restrictions in

workers' task division, some operations could not be combined into a single workloop and

have to be performed by different operators. This restricted implementation to some degree,

preventing the full balance of the workloops in the cell. Overall, however, implementation of

workloops not only enabled volume flexibility, i.e. the ability of the cell to adjust to the

required production rate, but also allowed increased efficiency of the workers and required

fewer operators and support staff to operate the new system.

The implementation of flow racks delivering material to the cell not only reduced the

incoming material WIP in the cell but also greatly improved the ergonomics of handling of

the parts by operators. From the flow racks, they are easier to reach and are closer to the

stations at which they are used. Since the parts are delivered in small quantities,

replenishment can be performed more frequently and is non-disruptive to cell production.

The line side market placed in the vicinity of the cells also made frequent replenishment

possible. However, there were many limitations to its implementation. The design of the

new system called for all inventory for this production unit to be placed in a single location,

permitting visual management. In the vision of the future system design, the central market

should be eliminated and the suppliers would deliver their products directly to the line-side

market (Figure 6-4: 12). The line-side market would then be linked to the suppliers through

another information/kanban loop (Figure 6-4: 6), eliminating intermediate inventories and

allowing better control over the inventory levels of parts. However, due to the large initial

83

Page 84: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

inventory size and limited space at the site of implementation, this was not carried out. Only

a single container of each type of component is staged at the line side market, and as the parts

are used up, a new container is brought from central inventory storage. Because of this, the

inventory coming from the external suppliers is managed as in the initial system - based on

the forecast of the part consumption from the central scheduling.

The future development for the system is to provide links between shipping and assembly

production unit, as well as continue those links with the rest of the system, such as presses

and suppliers. Currently, the production authorization for both the cells and the instruction of

the stamping press area are still done centrally and separately. The cells are still scheduled

based on the forecast demand. Although the internal replenishment loop has been

implemented, paced withdrawal has not. Therefore, the replenisher does not instruct the cell

based on leveled demand. In fact, the leveling box has not been implemented. The stamping

area is also scheduled separately, i.e. operates on push-production mode and the pull system

using signal kanban is not yet in place. A market of stamped parts should be located near the

press and conveyed to the assembly unit based on demand.

6.4 Further Development

The implementation thus far of the redesigned system has brought many benefits, as shown

in Table 3, such as improved quality and reduced lead time. However, much more is to be

gained through implementation of the other elements as well.

The biggest benefit will come from the control of purchased parts. Currently, they are placed

in a central storage location, which makes it difficult to control their levels and manage them

visually. They are ordered based on a forecast from central scheduling and delivered to the

line side market. In fact, the purchased components are a "hidden problem". They take up

floor space and require additional resources to transport them from the receiving dock to

storage and from storage to the production units, often many times back and forth. This

additional movement also increases the chance of creating defects. Some of those

components are also costly. Controlling inventory levels would bring, therefore, many

benefits.

84

Page 85: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

However, before implementing the kanban pull system to order parts from suppliers based on

actual usage, first the production of the assembly needs to be leveled [Monden, 1998]. The

implementation of the leveling box and establishment of material and information

connections between shipping and assembly is required. The leveled production of small run

sizes of parts as well as their frequent conveyance will make it possible to reduce the

incoming material inventory, as mentioned earlier. This linkage, therefore, should be the

focus of immediate implementation because leveling will allow implementation of other

linkages in the system.

The implementation of paced withdrawal will also improve the ability of frequent monitoring

of systems performance. This, in turn, will help achieve predictable output. Another key

element of predictable output issue is the analysis of down time. Although the machines in

assembly are serviced for maintenance, it is mostly done in a "fire-fighting" mode, giving

attention to the unit only when one of the machines is down and production has stopped.

Little preventive maintenance is done. A dedicated support staff for this production system

would ensure better availability of resources and would allow continuity in the preventive

maintenance for the system and elimination of the root causes.

85

Page 86: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

86

Page 87: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

7 Conclusions

In manufacturing system development, in order to make the system efficient, it is important

to eliminate waste throughout the entire value stream. Thus, it has been shown, based on the

Production System Design Decomposition, that overall system design places important

requirements on material and information flows through the system. In fact, these two flows

significantly affect the performance of the system, in terms of cost, quality and response

time. However, it is also important to note the interdependence of the information flow and

material flow as discussed in Section 3.3.

Traditionally, information flow is designed after the physical elements have been laid out and

after the material flow has been established. However, some of the strategic decisions in

information flow design discussed in this thesis, such as the inventory strategy, pacemaker

element selection and control policies, will impact how the material flows. For example,

depending on the chosen location of the instruction points in the system, certain production

elements could or could not be integrated into a single unit - the information flow should

influence the relative placement of the elements, depending on the kind of connections

needed between them. Therefore, the design of the information flow will in fact affect the

physical layout of the system and both information and material flows should be designed

concurrently, at the system level.

In the linked-cell system, the interdependence of the material and information flows is

especially visible in the transmission of information and material between production units,

or conveyance. This thesis presents various conveyance methods and discusses the

circumstances in which they might be most useful. Because the conveyance is responsible

87

Page 88: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

not only for delivery of the necessary material but also performs production control, it should

be regarded as a critical part of the manufacturing system development.

The role of conveyance in production control can be divided into two functions:

- Authorization of production

- Monitoring of performance

The conveyance also provides a feedback loop, which allows taking necessary actions and

maintaining controllability of the system, thus improving its performance. The frequency of

this feedback loop is a critical characteristic for controllability. However, little work has

been done so far to define controllability and to determine the optimal frequency of

conveyance in place of a commonly used rule of thumb, one-hour conveyance [Monden,

1998].

Although this thesis listed many factors that will influence the choice of information flow

and thus conveyance method used, it was not an intention to provide strict rules for

conveyance method selection or design. Instead, a discussion of the requirements some of

these factors place on the information flow has been provided as guidelines in decision-

making process. The information flow design is a strategic decision, which will greatly

impact the performance of the entire system.

88

Page 89: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

4. s~e~i~n-n--.~- - r~~scereie I.-n~eeen sure ,ccsui n-ru- iii , e-iuun-reru eiiu ,u - ~-i--s~ r4uuaiIu sun-uIuKPASrn-t-,uesIusuru-rAsun-iun-n-rsisrususuuiuruin-ruiuruuW0uiruGuiisn-sun-n-Si' new suite. Is I 'C isresssetsueeeess tnSSSususCG EeSiStt 5W - 5515 neW 155tn515 ne esesSuceSiSinW - - SW e5155 - tAGS eaten-is. 5W5fl5t5s55 eW. . suM Asu

FR1Madmie

long-termInvesh a tPullReanm oniNvestment over

DPIMandaciudngSystem Design

Mel sssteeSeWniMSlatsuis Wi5WtAthisSSise 5W 55555 uSWil? llteetAGl*5. Meats 55W

Madmnizealsrrmeue

PS 11Selea ravne

~MuII Paslealel to I

Imal1=1

PR12

mmtfacbrirgCoo

PM12M52 g

FRi 'MiSManufacture Doiverprduars to pmduas ontagt deon tespenecalonsP12

P1111 PencenagePiecesan-rne

capailtydebarms

------------ -------------- - - - - - - - - - - ------ -------------------------- ------- -- -- --------- - --- -----

S- - - - --- - -- --

OP-111 1DP12Praducanm Tfnughputpmcuesearh fmevadMonminimal reducionverWedan from

e trget

'ailsMat ua mer

mpecMd leadIkNePK13m

MrmqlgmePdullumms

Sload

Meantwoughputtinereduclon

:jfllst

.r _- -

Level IV s4biR estyyngcdFR1 FR-a FRAS - FRA1 FR441

PM-aP91 PM- Vaenue enPMR P4

earaert Cnter press Reces etpTmNud..ee.as.ern e, e V ock nc nDpo

-peaawem " pawn u eeee

::::Hgn ;.-7 progtd cilon dsupin

4-1 09-03 0P9-P-0 PS

Eminon" Proceps RessoneAeemMe pareeter procesenode dtacefn, prsduten

casese el uimwr reaposeete eoreweeen predan (peo.

I~s ora Proces-isn0

F"-13

E3411

nedrenl

DP541:caesn

fleappetsase

Se pm

Emkamtieon ofbnon-veluewadding sources

FM FRI22 FR23Reduce VoteReduM eoiNMinkimirein died labor in indired labor facilifs cost

PM12Perc~n d &PMV2 P111121WpereDWOrnomAmoun of Facifiescantspotan requiredwaieddtrades indrect laborand vvmng

Efirination of Redution t adtonnon-vW eindiect bor consumred flooraddigmonal talks spacetalks

3 T 4H T R-R R-i4 Pe431 PR-rm PR-i FR-12 PR-RP3 FR-1 FR-M2 FR-43 FR-44

S Etdnem Reduce msed Reduceerine Rapidly Csmmunrcte Salve problems Ensure Ensure Ensure Ensure materiale el in process of inp oieon recegerze problemstthe Imnlemly availablitof predi ale p sable avalabily

be esegneble Pin"S processoutput production ntpeople relevant equie merntweroutputcauses disruptions produclion oluput

Pu-Gm P3412 PM-U infrmanI P9414 P9-031 Outpul P9MI Timwtflme tembeen P9912

Numbertda iVanetof vern-s/ -Thhene idrsalironor supportreospr P9-11 Nunbert PM413 PMP14en pernpets processnputs - edege esset fht amannerant eNumbern sacoencesor Numberef NuastSe selipe tohe tnili ant Cllni4anirp ton tam Iocurrences oft bRred eupsansa E ai 0undueto

aSS i*at rrsiclet suppeotreasuat S:eupiand na eteinene Operae aingctitm' haste 1 nli e-l-g flnon ofneln de , Aet ettetagesSarp f wilMs reenom ecn At AwAlourt ofn-erme umet

upan is apmem lael rapear uepson ameairiiwoen ert for"Isteal

DP414 DP-W1 D4M 0411 9MDP 2 DPM3 OP5PP12P3 DP4&OM Supplerquay Conversin of Robust proess Sintsyte Process for Standard Capable and Maintenance of Motivatedwrk- Stendrd

pasgram coratni deep conni5 5n to fee ack of -nthod a . reliable equipent ftrcet materialcausesinto eme ta operton's ideontyand - <- . rimen en rae btry pnteineing replenitanert

eegenble a rtcho stem tSm esmn rw twslten slandardwork sysa"Mcauses n"ea cause

FR- a21-FR-W PFR4-12Mn 111 FRa112 FR-R13 FRAM FR-22 FR123 FRP21 FR-nP122 FRM31 FR-P32 FRP33 FR-141 FR-M42Ensure rt e Ensre t Enmure that i. - d-la y deity Idenflfywhat Identfy correct Minizedelay m tnnume tn Enererhat Service Reduce Enaure Dorot interrupt Ensurethet Ensure proper

- epattre -s apewmr apertsrlaann - daadi desupew :thedisruption is support in contacng ile PaIsaue e pmn p variabity of avalaabity atf produconr pn pmse t mingatf partleweledge S - c....dnly anrido,.a me -wheney uesne they resourws c.n ppmot , aeegarlytea c.erple an met' an-u *a l "'h-regledlett permamSta r anlam occur Ccuret resaurces m eM rtime allarncas maeml

PM11ERIi P5aM112 P11311 P913 121 PM-MM43-PNumbero01 n1bend 133femern trMain e1".2 =1Teaeboeen T flbetweent f t M e' Time uelroasI aI aVatarne Aqntedm eapede iance in task occurrences of Niu"f of PM1u"41 PMe142du spor n ,Nisoir Wualtr ofoccur" eand Ornklmo rt rialnd I of nne ielCabo" se enre reue eiig compleion tirnm operator CdWIPnGIVICAnBDue Number of Pats

Pfltc5ky aspern lefCf spern recagnine hat 1 n M r w andcortactaO easpat eaic tene., WS"E accencesof demanded-mtpmtata pe ufky percesalty - - - iestm c cesc eapatdean eeigee dima - malkaplece purts deveredetthPtscasedtby Paiscalm b d Nast M eO eS and correctsupport earM spaementA reountof amno, dtea'ammwi aw e t "lhe '""" """ I of una nding Meas "htagesabout. occurrediwh . are sucap.cr e ,geeosmatr" *""" '"'" '"aon la"te'n'e"s

- ---. - - f~-I 5~f Z lj~~.~zffl- -...DP-21 0P41 0 -iDP41P23411i A1112 DP413 UP-1121 1104"n2 0P4123 DOP4421 DPin2 DP-MO31 DP-132 D0133 0P-141 09-PM42

Trtneng Sndltwtrk Mate prasi - lmreaaed Saeeed Com t end Speciied Rapidsuppoit Systeethat Minhmums egrlr Slde k Perlect MutalReel Standardwork Partsmresedtprga mtosoperatesoram maeriallow senstive support contact ctmreys what III nefor prvnae lhdt Atendance Sysernwilh insprcess domnemm

(Poke-Yer) samping remn fpaths leeback resourmesfor procedure the disruption is Sevieaily me eneance Program cross-ined between sub . opertionsequapent neachfalre pr1ram n workers systems accorringto

Generai notes:Ad xbrand siger arprom landsth putltnmSh= matres tor higher leels

Production System Design LaboratoryLaboratDry for Manuactuwing and ProductivtyMaSachsetmallls tiU TechnologyOtkctor Pe- David S. Codian

77 MASSACHUSETTS AVENUE, BUILDING 35-135CAMBRIDGE, MA 02139PHONE: (617) 231811 FAX: (817) 268-TM WES: hI:.d.rt.fd

'MANUFACTURING SYSTEMDESIGN DECOMPOSITION

O MIT 2000DATESrlME FIl.ENAME PAGE OF PAGES

3/27)00 11:57 AM MSD Decomposition v5.1 with PM's.ppt I I

Level I

FROMw'minAcresmwit awn

symm itrede

---- ---- --- ---- ---- --- ---- - - -- ---- -i-

DP13bagelmenlmgmenm enemlgy

-M42

ignle

1412

a sperntenagae

-rN412

n apepors

FR-il FRBmisa Eimche pi

~cas cal

P9411 Pb

Snspurn apa msepbe .. pmmapaNent t

0P-411 D

FdIre m.dijSti

aed teas from

-nal 7L

4 wwras ra a emirw- Wem asenm -am .,ci

MINNSO"im M - -- - - , !IF -o"40 a M'". I ROM I ikv liflay - I

w

ILevel 11

Level II

Page 90: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

References

Berkley, B.J., 1992, A Review of the Kanban Production Control Research Literature,Production and Operations management, Vol. 1, No. 4, Fall 1992. ISBN 1059-1478

Black J T., The Design of the Factory with a Future, Mc Graw-Hill, Inc., 1991. ISBN 0-07-005550-5

Bonvik, A.M., 1996, Performance Analysis of Manufacturing Systems Under Hybrid controlPolicies. PhD Thesis, Operations Research Center, Massachusetts Institute of Technology,Cambridge, Massachusetts.

Br6te, S., Cochran, D.S., Mierzejewska, A.W., Carrus, B., 1999, Integrating the ProductionInformation System with Manufacturing Cell Design - A Lean, Linked-cell ProductionSystem Design Implementation, SAE Technical paper 1999-01-1634, presented at eh Societyof Automotive Engineers International Automotive Manufacturing Conference, Detroit,Michigan, 1999.

Carrus, B., Cochran, D., 1998, Application of a Design Methodology for ProductionSystems, Annals of the Second International Conference on Engineering Design andAutomation, Maui, Hawaii.

Castafieda-Vega, J.I., Mierzejewska, A.W., Cochran, D.S., 2000, Evaluation ofTransportation Scheduling Policy Effects on the Performance of Manufacturing Systems,Proceedings of the Third World Congress on Intelligent Manufacturing Processes & Systems.

Cochran, D.S, 1998, Lean Production System Design - Industry Course Materials,Production System Design Laboratory, Massachusetts Institute of Technology, Cambridge,Massachusetts.

Duda, J., 1999, Production System Design Decomposition Doctoral Committee Meeting,Mechanical Engineering Department, Massachusetts Institute of Technology, Cambridge,Massachusetts.

Fine C.H., Clockspeed, Perseus Books, 1999. ISBN 0-738201-53-7

89

Page 91: INTEGRATING INFORMATION FLOW WITH LINKED-CELL DESIGN …

Gershwin S.B., Manufacturing Systems Engineering, Englewood Cliffs, New Jersey: PTRPrentice Hall, 1994. ISBN 0-13-560608-X

Hartman C., Rodin R., Free, Perfect, and Now, Simon & Schuster, 1999. ISBN 0-684850222

Hayes, R.H., Wheelwright, S.C., 1979, Link Manufacturing Process and Product Life Cycles,Harvard Business Review, January-February 1979.

Hayes, R.H., Wheelwright, S.C., 1985, Competing Through Manufacturing, HarvardBusiness Review, January-February 1985.

Hill T., Manufacturing Strategy, Boston, Massachusetts: Irwin/McGraw-Hill, 1994. ISBN 0-256-10666-5

Hopp W.J., Spearman M.L., Factory Physics, Boston, Massachusetts: Irwin/McGraw-Hill,1996. ISBN 0-256-15464-3

Monden Y., Toyota Production System, Norcross, Georgia: Engineering & ManagementPress, 1998. ISBN 0-89806-180-6

Ohno T., Toyota Production System, Portland, Oregon: Productivity Press, 1988. ISBN 0-915299-14-3

Production System Design Research Group, 2000, Production System DesignDecomposition, v. 5.1, Internal Publication, Massachusetts Institute of Technology,Cambridge, Massachusetts.

Rother M., Shook J., Learning to See, Brookline, Massachusetts: The Lean EnterpriseInstitute, 1998. ISBN 0-9667843-0-8

Solvberg A., Kung D.C., Information Systems Engineering, New York: Springer-Verlag,1993. ISBN 3-540-56310-5

Spear, S., Bowen, H.K., 1999, Decoding the DNA of the Toyota Production System, HarvardBusiness Review, September-October 1999.

Suh N.P., The Principles ofDesign, New York: Oxford University Press, 1990. ISBN 0-19-504345-6

Wein, L., 2000, Introduction to Operations Management Course Notes, Sloan School ofManagement, Massachusetts Institute of Technology, Cambridge, Massachusetts.

90