TERNA ENGINEERING COLLEGE, NERUL, NAVI MUMBAI
Date : 12/12/2011C.No. : TEC-1112-168
Academic Calendar
Activity plan for the year 2011-2012 (Even Sem.) (II/IV/VI/VIII/PG II)- First Half of 2012
Sr.No.
Date Activity Dept. Responsibility Remarks
Pre Commencement Activities
A 15/12/11 Accreditation Internal Audits All HODs
B 16/12/12 &
19/12/11
Faculty Development Programme All Dean Academics
C 19/12/11 Faculty Appraisal for previousSemester
All HODs
D 20/12/11 Interviews for Faculty/staff /Lab AsstRecruitment
Admin Registrar
E 20/12/11 Completion of Preventive / BreakdownMaintenance, Calibration, Installation
of software etc.
Admin Maintenance EngineerSystem Staff,
Technical/Lab assts
Lab in charges should be in touch with systemstaff.
F 22/12/11 Announcement of Probable Placement
Calendar
Admin TPO With probable employers, their eligibility and datesof recruitments & past history.
G 22/12/11 Time table for students and staff to bedisplayed
All Dean Academics On web site also
H 22/12/11 Display of Divisions/Roll No/ Batches SE/TE/BE
in all depts..
Registrar
I 22/12/11 Declaration of Department wise
Program specific Academic Calendar
All depts. HODs/APC Programmewise
J 22/12/11 Declaration of Soft skill /Highereducation Calendar for FH 2011
Declaration of Placement TALKS /Training /Seminars calendar
All Counselor
TPO
As per Activities mentioned across all semesterAs per academic calendar of depts.In coordination with HODs /APCs
k 26/12/11 Governing Body – Meeting Admin Principal and
Management
Coordinator
Followed by respective committee’s Meeting
L 26/12/11 Alumni Meet All Counselor –HEC /TPO
8/3/2019 InstituteACFH2012
http://slidepdf.com/reader/full/instituteacfh2012 2/5
2
M 27/12/11 Academic Advisory Body Meeting Admin Registrar
N 30/12/11 Completion of
a. Procurement of journals /equipments / stationery etc.
b. Estate/Class Room Maintenance
c. Student facilities and amenities
Admin
Store Officer
Registrar
Registrar
HODs should notify to authorities, in time andmonitor the Progress
O 04/01/12 Address by Principal to faculties All Dean Academics
P 05/01/12 New Faculty/staff Joining Admin Registrar
Q 05/01/12
To
06/01/12
a. Orientation of Subjects with
teaching plans.
b. Lab work Orientationc. Class Room /Lab Arrangements
All HODs
Registrar /HODs
R 06/01/12 Submission and display of approved
teaching plans/ Bar Charts as persyllabus.
Display of Total Assignments,Experiments on Notice Board in Each
lab
All All faculties , Lab in
charges
HODs would verify.
Commencement
1
2
09/01/12
for UG
12/01/12for PG
Commencement of Term
Address of Head of Department to thestudent with faculty introduction.
(in each class)Theory and Lab period as per time
table.
First week, in labs, revision of
relevant lab work or introductionis expected.
All depts.
UG-FE/SE/TE/BE
PG- ME-II
HODs
HODs
All faculties
Small Orientation lecture are to be organized andcourse content with industry relevance to beillustrated for all classes- without disturbinglectures. Rules- regulations to be explained too.
3 13/01/12 Review of UG/PG Projects by
Industry Panel
All Dean III
4 26/01/12 Holiday – Republic Day
5 27/01/12 Student Council meeting& Feedback from Council members on
general things
In charge studentActivities
8/3/2019 InstituteACFH2012
http://slidepdf.com/reader/full/instituteacfh2012 3/5
3
6 31/01/12 Tentative Result declaration of SE/TE
Display of Examination activity
calendar
Result declaration of University
examinations
ALL Exam In charge
Exam In charge
Exam In charge
This is maximum date. Should be tried prior tothis.
Need to be coordinated with University
7 05/02/12 Holiday – ID-E-Milad
8 10/02/12 to20/02/12
Industrial visit – one day SE/BE/ME HODs Local Industries onlyTake help from TPO /III Members
9 14/02/12 Display of defaulter’s list-I
(09-01-2012 To 13-02-2012)
All Class Advisors/HODs Reports to be generated through Ezschool
10 15/02/12 Meeting of defaulters with teachers. All Class Advisors/HODs Parents may informed to watch performance
11 16, 17,18/02/12
Unit Test-I FE/SE/TE/BE/ME
12 19/02/12 Holiday – Chhatrapati Shivaji Maharaj Jayanti
13 20/02/12 Holiday - Mahashivratri
14 28/02/12 Submission of Class Test performance to class advisors All
FE/SE/TE/BE/ME
Faculties
15 28/02/12 Submission of Project Progress to
Project Review Committee
All
BE / ME-IV Students
HODs / Project
Coordinators / Guides
Dean Academics to Coordinate
16 01/03/12 to
04/03/12
Orientation to TE- VI /ME II students
about Projects OF NEXT SEM (ME- III
/VII Sem)
TE- VI /ME II HODs / Project
Coordinator
It is expected that HODs give detail idea abouthow projects are to be selected, executed andwhat is importance of projects in Engg and guidesrole.Even Project Management principles needs to bebriefed
17 08/03/12 Holiday - Holi (Second Day)
18 12/03/12 Display of list of Internal guides ( forTE/ ME Second Sem students)
available with their area of expertisefor project guidance for next Academic
Year.( if possible available projects)
TE/ME II HODs TE & ME Second Sem students are expectedto form a group ( max 4) go through
possible area of proposed projects andidentify internal guide from dept with
relevant area looking at list
19 12/03/12 to
20/03/12
TE/ME II Students about probable
projects
TE/ME II Project Coordinators
20 13/03/12 to17/03/12
Parent Teacher interaction meet All HODs/APC
21 13/03/12 to17/03/12
Techno-cultural festival and SportsRESONANACE
All In charge- StudentActivities &
Student Council
8/3/2019 InstituteACFH2012
http://slidepdf.com/reader/full/instituteacfh2012 4/5
4
22 15/03/12 Second Defaulter’s list (09-01-2012 To 14-03-2012)
All HODs
23 15/03/12 to
20/03/12
Project Review II (by Industry Panel ) All
BE & ME II students
HODs Dean III shall assist
24 16/03/12 to17/03/12
Meeting of Parents of defaulterstudents to HOD
All Class advisers/APC
25 20/03/12 to30/03/12
Online Test All DeanAcademics/Network
Admin
An on line test for all students of all subjectstogether on syllabus covered in the class till15/03/11. MCQ type with negative marking andcan be given from anywhere beyond college
timings. Schedule shall be displayed later.26 23/03/12 Holiday - Gudi Padwa
27 01/04/12 Holiday – Ram Navmi
28 02/04/12 to
04 /04 /12
Projects Review-II (by DEPT level
Committee)
All BE/ME-IV
students
Internal guides
Project coordinators
29 02/04/12 to
09/04/12
Student Feedback All Sys Admin On line
30 05/04/12 Holiday –Mahavir Jayanti
31 06/04/12 Holiday – Good Friday
32 12/04/12 Third Defaulter list (09/01/12 to11/04/12)
All HOD
33 13/04/12 Student Council Meeting In charge StudentActivities
Review of Feedbacks
34 13/04/12 Submission of project area withconsent of internal guide to project
coordinator
TE/ME II Project Coordinator Not more than 2 projects for one guide
35 14/04/12 Holiday – Dr.Babasaheb AmbedkarJayanti
36 16/04/11,17/04/11,
18/04/11
Unit Test – II FE/SE/TE/BE/ME
37 20/04/12 Display of term work / performance All Lab In charges ,
Faculties associated
with Labs , tuts
38 20/04/12 Display of Viva Schedule All Exam In chargeDean Academics
As per University schedule
39 20/04/12 Display of detention list HODs
40 23/04/12 Final certification and Submission
of term work
All HOD As per University schedule
41 25/04/12 Display of list for next AY of Guidesand group of students.
TE/ME II Project Coordinator Consider failed students also
42 25/04/12 TO02/05/12
Remedial classes All Dean Academics withHoDs
For weaker students
8/3/2019 InstituteACFH2012
http://slidepdf.com/reader/full/instituteacfh2012 5/5
5
43 25/04/12 to02/05/12
Practical exam /Viva All Faculties As per University schedule
44 29/04/12
Onwards
Vacation for Faculties All Exam in charge As per University schedule
45 01/05/12 Holiday –Maharashtra Day
46 06/05/12 Holiday – Buddha Pournima
47 15/05/12 University Examination All Exam in charge As per University schedule
Sd/-
(Mr.N.S.Killarikar) (Dr.L.K.Ragha)Dean Academics I/C Principal
Copy to
1. CEO, TPCT2. Management Coordinator
3. Deans / All HOD’s - for necessary action4. Dean Academics for co ordination
5. All Sectional in charges (TP/LIB./EXAM/Maintenance/Store/Registrar) – for necessary action
6. Staff Circulation Copy
7. Office Copy8. Notice Board9. Web Copy
Summary: 1) Total Working Weeks: 16 2) Total Working days (excluding examination): 80
3) Total Working Days for teaching : 70
4) Available Periods for teaching = (if 3 per week) @42, = (if 4 per week)@56, = if 5 per week) @70