Upload
mahesh-mohanan
View
221
Download
0
Embed Size (px)
Citation preview
8/6/2019 Institute of Professional Education and Research
1/10
INSTITUTE OF PROFESSIONAL EDUCATION
AND RESEARCH
PGDM- 2010-12
REPORT
ON
Strategic implementation of Delhi Metro
Submitted to : - SUBMITTED By :-
PROF. Mahesh Soni Mahesh Mohanan
8/6/2019 Institute of Professional Education and Research
2/10
Introduction
About Metro Rail in Delhi Delhi, the capital city of India is one of the fastest growing cities in
the world with a population of 13 million as reported in the Census of India Report for the year
2000. Until recently, it was perhaps the only city of its size in the world depending almost
entirely on roads as the sole mode of mass transport. The total length of the road network in
Delhi has increased from a mere 652 km in 1981 to 1122 km in 2001 and it is expected to grow
to 1340 km in the year 2021. This increase in road length is not at par with the phenomenal
growth in the number of vehicles on these roads in Delhi. The cumulative figure of registered
private and government buses, the main means of public transport, is 41,872 in 1990 and it is
expected to increase to 81,603 by the year 2011. The number of personal motor vehicles has
increased from 5.4 lakhs in 1981 to 30 lakhs in 1998 and is projected to go up to 35 lakhs by
2011. With gradual horizontal expansion of the city, the average trip length of buses has gone up
to 13 km and the increased congestion on roads has made the corresponding journey time of
about one hour. Delhi has now become the fourth most polluted city in the world, with
automobiles contributing more than two thirds of the total atmospheric pollution. In this context,
the decision of the Government of India to develop a mass transport system for Delhi providing
alternative modes of transport to the passengers was most appropriate.
With a 6.5 km section of Line 3 becoming operational in April 2006, Phase I of the Delhi
Metro3 project was nearing completion. Of the total length of 65.16 km of the first phase, 62 km
had been completed and opened for service. This phase was set to cost Rs. 98 billion. As of early
2006, around 450,000 passengers were traveling by the Delhi Metro every day.
The Delhi Metro was meant to solve Delhi's traffic problems, which had become almost
unmanageable. The first steps to build a metro system in the city were taken in the early 1990s.
In 1995, the Government of India (GoI) and the Government of the National Capital Territory of
Delhi (GNCTD) formed the Delhi Metro Rail Corporation Ltd (DMRC) under the Companies
Act to construct the Delhi Metro.
8/6/2019 Institute of Professional Education and Research
3/10
Conceived as a social sector project, a significant portion of the project cost was funded through
a soft loan provided by the Japanese government through Japan Bank International Corporation
(JBIC)4. The rest was contributed by GoI and GNCTD through equity.
E. Sreedharan (Sreedharan) was appointed managing director (MD) of the DMRC and projectmanager for Phase I of the project in November 1997. Work on Line 1 of Phase I started in
October 1998. DMRC formed consortiums to advise it on the project and to provide it with the
latest technology. It also saw to it that the foreign companies worked with the Indian companies
to ensure that the latter assimilated their expertise and technological know-how.
The DMRC faced any number of technical and systemic challenges during the construction of
the metro. The organizational culture was based on punctuality, honesty, and a strict adherence
to deadlines. The DMRC successfully managed the various stakeholders in the project like the
general public, government bodies, etc., and also ensured that the project was environmentally
safe. With Phase I of the Delhi Metro project nearing completion, the GoI decided to extend the
metro network and work on Phase II of the Delhi Metro project was set to commence in
September 2006. National Capital Territory of Delhi (NCTD), with an area of 1486 km2 has a
population of about 15 million. Buses are the sole mode of public transport in the NCTD, which
are inadequate andovercrowded. For want of an efficient mass transport system, the number of
motor vehicles isaround 4 million. The result is extreme congestion on Delhi roads, ever slowing
speeds, increasein road accidents (5 persons killed and 13 injured everyday), fuel wastage and
environmental pollution with motorized vehicles alone contributing to about two thirds of the
atmospheric pollution.
The mixed traffic in the city has resulted in road accidents, killing 5 persons and injuring
13persons a day on an average. The situation is expected to deteriorate further in the years
tocome.
Different Phase of Metro
8/6/2019 Institute of Professional Education and Research
4/10
The project is being implemented in Phases I, II. III & IV. for a sketch map of Delhi Metro Rail.
Phase I,
Now under execution comprises of 65.11 km of route length with 13.07 km
underground and 47.54 km elevated rail and 4.56 surface rail with 59 stations. It consists of 3
lines as follows:
Line 1: 22.06 km Shahdara-Tri Nagar-Rithala Line with 18 stations (Partly Elevated, Partly Surface)
Line 2: 10.84 km Vishwa Vidyalaya-Central Secretariat Line with 10 stations (Underground)
Line 3: 22.90 km Barakhamba Road-Connaught Place-Dwaraka Line with 22 stations (Partly Underground/ PartlyElevated)
The following extensions are proposed which are yet to be approved.
1.Proposed Line 1: Extension 6 km Rithala-Barwala (Partly Elevated, Partly Surface)
2.Proposed Line 2 Extension: 4 km Vishwa Vidyalaya-New Azadpur (Elevated)
3.Proposed Line 3 Extension: 4 km Barakhamba Road-Indraprastha Estate
4.Proposed Line 3 Extension: 6.5 km Dwaraka- Dwaraka Subcity Extension
Phase II: The detailed project report is under preparation. RITES will prepare the DPR, which
will
take about two years time. Full-fledged work will begin by January 2005 and has been
completed in March 2010.
Phase II is 42 km long will be essentially extensions to Line 1, Line 2 and Line 3 of Phase I
either in one or both directions. It comprises the following.
Vishwa, Vidyalaya-Jahangirpuri (6.59 km)Central Secretariat - Qutab Minar (10.97 km)
Indraprastha- NOIDA City Centre (16.2 km) There will be 7 stations between Vishwa Vidyalaya-
New Azadpur to Sanjay Gandhi Transport Nagar, 18 stations in the Central Secretariat-Vasant
Kunj section and 12 stations in the Barakhamba Road-Noida.
The first concrete step in the launching of an Integrated Multi Mode Mass Rapid Transport
System (MRTS) for Delhi was taken when a feasibility study for developing a multi-modal
8/6/2019 Institute of Professional Education and Research
5/10
MRTS system was commissioned by the Government of the National Capital Territory of Delhi
(GNCTD) at the instance of the Government of India in 1989 and completed by Rail India
Technical and Economic Services Limited in 1995 (RITES, 1995a, 1995b). The Delhi Metro
(DM) planned in four phases is part of the MRTS. The work of Phase I and part of Phase II is
now complete while that of phase III is in progress. The first phase of DM consists of 3 corridors
divided in to eight sections with a total route of 65.1 kms, of which 13.17 kms has been planned
as an underground corridor, 47.43 kms as elevated corridors and 4.5 kms as a grade rail
corridor. The second phase covers 53.02 kilometers of which the underground portion, grade
and elevated section are expected to be 8.93 kilometers, 1.85 kilometers and 42.24 kilometers
respectively. The construction of the first phase of DM was spread over 10 years during 1995-
96 to 2004-05 while that of the second phase, which started in 2005-2006 is expected to be
complete by 2010-11. The total capital cost of DM at 2004 prices for Phase I and Phase II areestimated as Rs. 64,060 and Rs. 80,260 million, respectively. Phases III and IV of DM will
cover most of the remaining parts of Delhi and even extend its services to some areas such as
Noida and Gurgaon belonging to the neighbouring states of Delhi.
When E Sreedharan took over as the managing director of Delhi Metro Rail Corporation in
November 1997, two doubts were raised about the subway rail venture: was it worth the effort?
Equally important, would it finish on time? It faced the challenge of relocating a large number of
utilities like water pipes, sewerage lines, telephone and electric cables to facilitate the
construction work, apart from the overwhelming challenge of relocating people.
Delhi Approved 3 Metro Corridors under Phase III
The Delhi government has cleared three of the six corridors of phase-III of the Delhi Metro. The
corridors are Mukundpur- Rajouri Garden, Central Secretariat-Red Fort and Jehangirpuri-Badli.
8/6/2019 Institute of Professional Education and Research
6/10
Three routes, including the two corridors from Noida, Sector-18, in Uttar Pradesh, to Janakpuri
in West Delhi, and Rajouri Garden in West Delhi to Dhaula Kuan and Outer Ring Road in South
Delhi, were not finalized. The state transport department has been asked to prepare a DPR for
these three routes.
After clearance, the phase-III plan will be submitted to the Group of Ministers of the Union
Cabinet, which will then decide on funding for the construction of the six routes.
Phase-III, which will have nearly 70 km of track length, is estimated to cost `2,468 crore and
completed within five years.
Delhi Metro runs a fleet of 129 trains on a network of 138 km that has 117 stations. The average
daily ridership on weekdays has crossed the 15 lakh figure. The Airport Express Line, likely to
be inaugurated by October-end, is the last project in phase-II.
The Delhi government also plans to connect Anand Vihar in East Delhi to Dhaula Kuan in
Southwest Delhi in phase-III of the metro rail network. According to the proposal, the total
length of this corridor is 25.66 km. Of this, 12.52 km of the line will be underground while the
rest 13.14 km will be elevated. It is estimated to cost around `6,261 crore.
What makes the Delhi Metro project truly phenomenal is the way in which a foreign dependent
project was localised and re-engineered, by involving both Indian companies as well as
consortium members at each stage of the project. Amongst the chief capabilities transferred
seamlessly were project management processes, manufacturing rust-proof and fibre-reinforced
interiors steel coaches.
Not only has the DMRC stuck within the completion targets, some stretches have finished six
months ahead of time and the entire project is expected to be completed by December 2005.
Rivalling similar services in London, Seoul and New York, DMRC is a perfect case study for
both India and the world, on how to put together a world-class project within a world-class
timeframe.
8/6/2019 Institute of Professional Education and Research
7/10
Phase IV
Phase IV has a 2020 deadline, and tentatively includes further extensions to Sonia Vihar, Reola
Khanpur, Palam, Najafgarh, Ghazipur, Noida Sector 62, Gurgaon and Faridabad, having a total
length of 108.5 km (67.4 mi). Apart from these lines in Phases I to IV, plans have been mooted
to construct a new line from Noida Sector 62 to Greater Noida which will intersect Indraprastha
Noida Sector 32 line. The Ghaziabad Development Authority is planning to extend Delhi
Metro lines deeper into Ghaziabad in three phases, including the extension of the Blue Line
from Anand Vihar to Vaishali, and subsequently to Mehrauli via Indirapuram, as well as the
extension of the Red Line from Dilshad Garden to the new Ghaziabad bus stand. The
independently operated Gurgaon Metro, work on which is going on and has a deadline of 2013,
will also interchange with the Delhi Metro.
Delhi Metro Project is the biggest urban intervention in India since Independence in 1947.
Project had to be executed in very difficult urban environments.
Being in the capital city all actions under close scrutiny of VVIPs
The Project implementation period compressed from 10 years to 7 years.
Metro being constructed to world class standards with frontline technologies.
The expertise and technology not available in the country. Legal cover needed for
construction and operations not in position.
Economic Benefits
The Delhi MRTS is essentially a "social" sector project, whose benefits will pervade wide
sections of economy. The modified first phase will generate substantial benefits to the economy
by the way of:
Time saving for commuters
Reliable and safe journey
Reduction in atmospheric pollution
Reduction in accident
8/6/2019 Institute of Professional Education and Research
8/10
Reduced fuel consumption
Reduced vehicle operating costs
Increase in the average speed of road vehicles
Improvement in the quality of life
More attractive city for economic investment and growth
Economic IRR of the project works out to 21.4%, even though the financial IRR is less than 3%
Delhi Metro registers highest ridership of more than 15 lakh
As fear of getting stuck in maddening traffic jams due to the dedicated Commonwealth Gameslanes prompted hundreds of people to avoid buses, Delhi Metro registered its highest-ever
ridership of over 15 lakh.
Ever since the Central Secretariat-Qutub Minar corridor was integrated with the Qutub Minar-
HUDA City Centre (Gurgaon) line, Delhi Metro ridership has been increasing day by day.
With the Delhi Traffic Police earmarking some lanes on major roads exclusively for the use of
CWG athletes and delegates, people parked their vehicles at home and took Metro to reach their
respective destinations on time.
The sudden surge in the ridership can be attributed to the fear of getting stuck in traffic jams due
to the dedicated lanes for the Commonwealth Games and the Delhi Governments decision to
withdraw blue line buses from near the CWG venues.
The over-crowded Line 3 that connects Dwarka Sub-city with Delhis satellite city of Noida and
Anand Vihar, which is close to another satellite city Ghaziabad, recorded the maximum
ridership at 5.62 lakh.
The Line 2 (Jahangirpuri-HUDA City Centre) registered a ridership of 5,31,337 and Line 1
(Rithala-Dilshad Garden) at 2,88,276.
The ridership is set to increase with the opening of two lines - the showcase Airport Express
Line and the Central Secretariat-Badarpur corridor - before the October 3 Games extravaganza
begins.
Trains on the Central Secretariat-Badarpur corridor, which connects the Jawaharlal Nehru
Stadium, will run at a frequency of 2.25 minutes.
8/6/2019 Institute of Professional Education and Research
9/10
By the end of the year, DMRC expects its ridership to reach 20 lakh a day.
Currently, over 130 train sets are in operation on the five lines of Delhi Metro with a new train
being added to the system every 10 to 15 days. Delhi Metro trains make over 2,300 trips on the
five operational lines covering 138 km.
Conclusion
The Delhi Metro planned in four phases is part of an Integrated Multi Mode Mass Rapid
Transport System (MRTS) planned for dealing with the fast growing passenger traffic demand
in Delhi. It provides an alternative safe and comfortable mode of transport by rail to a large
fraction of passengers using the road transport in Delhi. It reduces the travel time of people
using the road and Metro, number of accidents on roads and the atmospheric pollution. The
financial cost-benefit ratio of the Metro is estimated as 2.30 and 1.92 at 8 percent and 10 percent
discount rates respectively while its financial internal rate of return is estimated as 17 percent.
The financial evaluation of the Metro is done considering the financial flows of the project
8/6/2019 Institute of Professional Education and Research
10/10
comprising the annual revenue earned and flows of investments and operation and maintenance
costs. The shares of debt, equity and internal resource mobilization in investments made on
Metro are 60, 30 and 10 percent, respectively.
The social cost-benefit analysis of the Metro requires the identification of benefits and the
economic agents affected by it. The incremental changes in the incomes of various economic
agents: passengers, transporters, public and government and unskilled labour due to the Metro
could be estimated by considering the Delhi economy with and without the Metro. It is found
that there are income gains to the government, public, passengers and unskilled labour while
there are substantial income losses to the transporters because of the metro.
Delhi Metro provides incremental income to the Delhi public which has a per capita income
more than two times the national per capita income. Therefore, accounting for income
distributional effects of the Metro has resulted in the reduction of the social rate of return to 22.7percent.