Air Barrier & Water-Resistive Barrier System Installation Residential & Light Commercial Buildings Less Than 5 Stories Building Wrap to be Installed After Windows Window & Door Installation Types: Method A & Method B Building Wrap: 9' RainBuster #550 High Performance Air Barrier & Building Wrap Additional Required Installation Materials: RainBuster #501-2.83" Seam Tape 4" RainBuster #440 SubZero Flashing Tape ® RainBuster #900 Polycarbamate Sealant/Adhesive Top Industrial, Inc. • 15010 Keswick St., Van Nuys, CA 91405 • 800.473.1617 • topindustrial.com Drawings Not to Scale pg 1 of 6 May 2018 Our leak & squeak eliminating systems feature high performance sealants, adhesives, flashings, tapes, and building wraps for the entire home. Installation Guideline LEVEL 3 Installation Guideline LEVEL 3 Step 1. Install Building Wrap Product: RainBuster #550 High Performance Air Barrier & Building Wrap 1.A Ensure that wall substrate is flat and free of protrusions and debris that could damage the building wrap. Install flashing at the sheathing/slab interface. Refer to Step 7 for specific directions regarding sheathing/slab sealing at bottom plate. 1.B Position building wrap at base of wall with the printed side facing out. Align the bottom edge with the sill plate. Building wrap should extend below sill plate a minimum of 2". Building wrap should be integrated with weep screed in stucco applications. When starting at a corner, overlap corner by a minimum of 12". Secure building wrap in place using approved fasteners along vertical edge of building wrap. 1.C Unroll building wrap horizontally inte- grating it with windows and doors in a weatherboard (shingled) fashion. Refer to Steps 2 & 3 for specific directions regarding window/door building wrap integration. Secure building wrap in place using approved fasteners. Ensure building wrap is level. 1.D Install upper courses of building wrap overlapping lower courses in a weather board (shingled) fashion. Vertical and horizontal seams must be overlapped a minimum of 6". 24” O.C. MAX. 2” MIN. 2” MIN. 16”-24” O.C. 6” Horizontal Lap 12” Overlap at Corner 6” Vertical Lap Building Wrap/ Window Integration Building Wrap/ Window Integration Alternative Building Wrap/ Window Integration

Installation Guideline LEVEL 3 - Top Industrial

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Air Barrier & Water-Resistive Barrier System InstallationResidential & Light Commercial Buildings Less Than 5 StoriesBuilding Wrap to be Installed After WindowsWindow & Door Installation Types: Method A & Method B

Building Wrap: 9' RainBuster #550 High Performance Air Barrier & Building WrapAdditional Required Installation Materials: RainBuster #501-2.83" Seam Tape4" RainBuster #440 SubZero Flashing Tape® RainBuster #900 Polycarbamate Sealant/Adhesive

Top Industrial, Inc. • 15010 Keswick St., Van Nuys, CA 91405 • 800.473.1617 • topindustrial.com

Drawings Not to Scale pg 1 of 6May 2018

Our leak & squeak eliminating systems feature high performance sealants, adhesives, flashings, tapes, and building wraps for the entire home.

Installation Guideline LEVEL 3Installation GuidelineLEVEL 3

Step 1. Install Building Wrap Product: RainBuster #550 High

Performance Air Barrier & Building Wrap

1.A Ensure that wall substrate is flat and free of protrusions and debris that could damage the building wrap. Install flashing at the sheathing/slab interface. Refer to Step 7 for specific directions regarding sheathing/slab sealing at bottom plate.

1.B Position building wrap at base of wall with the printed side facing out. Align the bottom edge with the sill plate. Building wrap should extend below sill plate a minimum of 2". Building wrap should be integrated with weep screed in stucco applications. When starting at a corner, overlap corner by a minimum of 12". Secure building wrap in place using approved fasteners along vertical edge of building wrap.

1.C Unroll building wrap horizontally inte-grating it with windows and doors in a weatherboard (shingled) fashion. Refer to Steps 2 & 3 for specific directions regarding window/door building wrap integration. Secure building wrap in place using approved fasteners. Ensure building wrap is level.

1.D Install upper courses of building wrap overlapping lower courses in a weather board (shingled) fashion. Vertical and horizontal seams must be overlapped a minimum of 6".

24” O.C. MAX.

2” MIN.

2” MIN.

16”-24” O.C.

6” HorizontalLap

12” Overlapat Corner

6” VerticalLap

24” O.C. MAX.

2” MIN.

2” MIN.

16”-24” O.C.

6” HorizontalLap

12” Overlapat Corner

6” VerticalLap

Building Wrap/Window Integration

Building Wrap/Window Integration

AlternativeBuilding Wrap/Window Integration

Air Barrier & Water-Resistive Barrier System InstallationResidential & Light Commercial Buildings Less Than 5 StoriesBuilding Wrap to be Installed After WindowsWindow & Door Installation Types: Method A & Method B

Building Wrap: 9' RainBuster #550 High Performance Air Barrier & Building WrapAdditional Required Installation Materials: RainBuster #501-2.83" Seam Tape4" RainBuster #440 SubZero Flashing Tape® RainBuster #900 Polycarbamate Sealant/Adhesive

Top Industrial, Inc. • 15010 Keswick St., Van Nuys, CA 91405 • 800.473.1617 • topindustrial.com

Drawings Not to Scale pg 2 of 6May 2018

Our leak & squeak eliminating systems feature high performance sealants, adhesives, flashings, tapes, and building wraps for the entire home.

Installation Guideline LEVEL 3Installation GuidelineLEVEL 3

Step 2. Building Wrap/Window Integration2.A Remove building wrap covering windows by cutting an opening

in the building wrap. The opening should be 2" greater in width and 3" greater in height than the window.

Make a horizontal cut flush with the head of the window extend-ing past each jamb 1". Make a vertical cut 1" from each jamb of the window extending from the head of the window past the sill of the window 3". Make a horizontal cut 3" below the sill of the window extending 12" past each jamb of the window. Remove building wrap exposing the window. Take care to ensure the win-dow flashing is not damaged while removing the building wrap.

2.B Lift the sill flashing through the horizontal cut at the window sill and lap over the building wrap below the window in a weather-board (shingled) fashion.

2.C Tape the horizontal seams at the lower corners of the window en-suring a water tight seal. Tape vertical seams at window jambs. Apply seam tape at the window head overlapping the vertical seams in a weather board (shingled) fashion.

Alternative Building Wrap/Window Integration Building Wrap Width = (Window Width) + 24" Building Wrap Height = (Window Sill Height) + 1"

Install building wrap below window with the printed side facing out. Tuck the building wrap behind the window sill flashing in a weather board (shingled) fashion. Building wrap should extend past each jamb of the window 12". Align bottom edge of the building wrap with the sill plate. Building wrap should extend below the sill plate a minimum of 2". Building wrap should be integrated with the weep screed in stucco applications.

Install building wrap covering window and previously installed build-ing wrap (below the window). Make a horizontal cut flush with the head of the window extending past each jamb 1". Make a vertical cut 1" from each jamb of the window extending from the head of the win-dow to the bottom edge of the building wrap. Tape the vertical seams. Apply seam tape at the window head overlapping the vertical seams in a weather board (shingled) fashion.

R.O.+24”

12”

2” MIN.

2” MIN.2” MIN.

2” MIN.2” MIN.

Building Wrap/Window Integration

Building Wrap/Window Integration

AlternativeBuilding Wrap/Window Integration

AlternativeBuilding Wrap/Window Integration

Air Barrier & Water-Resistive Barrier System InstallationResidential & Light Commercial Buildings Less Than 5 StoriesBuilding Wrap to be Installed After WindowsWindow & Door Installation Types: Method A & Method B

Building Wrap: 9' RainBuster #550 High Performance Air Barrier & Building WrapAdditional Required Installation Materials: RainBuster #501-2.83" Seam Tape4" RainBuster #440 SubZero Flashing Tape® RainBuster #900 Polycarbamate Sealant/Adhesive

Top Industrial, Inc. • 15010 Keswick St., Van Nuys, CA 91405 • 800.473.1617 • topindustrial.com

Drawings Not to Scale pg 3 of 6May 2018

Our leak & squeak eliminating systems feature high performance sealants, adhesives, flashings, tapes, and building wraps for the entire home.

Installation Guideline LEVEL 3Installation GuidelineLEVEL 3

Step 3. Building Wrap/Door Integration3.A Remove building wrap covering doors by cutting an opening in

the building wrap. The opening should be 2" greater in width and the height of the door. Make a horizontal cut flush with the head of the door extending past each jamb 1". Make a vertical cut 1" from each jamb of the door extending past the head of the door 1" and flush with the sill of the door or bottom edge of the building wrap. Remove building wrap exposing door. Take care to ensure the door flashing is not damaged while removing the building wrap. Tape vertical seams. Apply seam tape at the door head overlapping the vertical seams in a weather board (shingled) fashion.

Step 4. Install FastenersProduct: Plastic Capped Nails, Plastic Capped Screws, or

Plastic-Capped Staples (by others)

4.A Install fasteners 16"-24" on center along horizontal edge of building wrap at top and bottom (sill) plates.

4.B Install fasteners 24" on center vertically and horizontally in the field.

4.C Do not install fasteners within 2" of the sill and jambs and within 9" of the head of the window rough openings.

4.D Fasteners should be of sufficient length (minimum 3/8" length) to penetrate framing or fastening substrate securing the build-ing wrap in place.

Step 5. Install Seam TapeProduct: RainBuster #501-2.83" Seam Tape

5.A Beginning at the lower course, tape all vertical seams in the building wrap using seam tape. Horizontal seams should be taped after the vertical seams in a weather board (shingled)

fashion. Continue this sequence of taping the vertical and hori-zontal seams in subsequent courses of building wrap.

5.B Apply skip-taping at building wrap/slab or weep screed.

5.B Apply seam tape using constant and adequate pressure to en-sure maximum adhesion.

Step 6. Building Wrap/Sheathing Sealing at Top PlateProduct: RainBuster #900 Polycarbamate Sealant/ Adhesive

6.A Apply a 3/8"-1/2" continuous bead of sealant to the face of the sheathing at the top plate. Align the continuous bead of sealant with the top edge of the building wrap. Building wrap should lap over sealant bead a minimum of 1".

6.B Embed building wrap into sealant bead and apply constant and adequate pressure to the face of the building wrap to promote adhesion and ensure a continuous seal between the building wrap and sheathing.

24” O.C. MAX.

2” MIN.

1”

3/8”- 1/2” Sealant Behind Building Wrap

Air Barrier & Water-Resistive Barrier System InstallationResidential & Light Commercial Buildings Less Than 5 StoriesBuilding Wrap to be Installed After WindowsWindow & Door Installation Types: Method A & Method B

Building Wrap: 9' RainBuster #550 High Performance Air Barrier & Building WrapAdditional Required Installation Materials: RainBuster #501-2.83" Seam Tape4" RainBuster #440 SubZero Flashing Tape® RainBuster #900 Polycarbamate Sealant/Adhesive

Top Industrial, Inc. • 15010 Keswick St., Van Nuys, CA 91405 • 800.473.1617 • topindustrial.com

Drawings Not to Scale pg 4 of 6May 2018

Our leak & squeak eliminating systems feature high performance sealants, adhesives, flashings, tapes, and building wraps for the entire home.

Installation Guideline LEVEL 3Installation GuidelineLEVEL 3

Alternative Building Wrap/Sheathing Sealing at Top PlateProduct: 4" RainBuster #440 SubZero Flashing Tape®

Install flashing over building wrap and sheathing at the top plate. Flashing should lap over building wrap and onto the sheathing a min-imum of 2". Using a J-Roller, apply pressure and roll entire surface of flashing.

Step 8. Flashing Penetrations with Integral Flanges (Gable Vents, Dryer Vents, Fireplace Vents, Etc…)Product: 4" RainBuster #440 SubZero Flashing Tape®

RainBuster #900 Polycarbamate Sealant/Adhesive

8.A Make 45° diagonal cuts in the building wrap at the upper cor-ners of the of the vent. Raise the flap and temporarily secure with tape.

8.B Install flashing over bottom flange. Flashing should extend past each end of the vent 4".

8.C Install flashing over side flanges. Flashing should extend past the top of the vent 3" and past the bottom of the vent 4".

8.D Install flashing over the top flange. Flashing should extend past each end of the vent 5".

8.E Using a J-Roller, apply pressure and roll entire surface of flashing.

8.F Apply a 3/8" bead of sealant around the entire vent at the vent/flashing joint. Tool to promote adhesion and ensure a water tight seal.

8.G Release the building wrap flap and embed it into the sealant at the top of the vent. Using seam tape, seal the diagonal cuts securing the building wrap flap in its original position.

24” O.C. MAX.

2” MIN.

2”4” Flashing Sealant

Sealant

12 3

4

6 6

5

2” MIN.

Step 7. Sheathing/Slab Sealing at Bottom PlateProduct: 4" RainBuster #440 SubZero Flashing Tape®

7.A Install flashing over sheathing and slab at bottom plate. Flashing should lap over sheathing and onto the slab a minimum of 2". Using a J-Roller, apply pressure and roll entire surface of flashing.

Air Barrier & Water-Resistive Barrier System InstallationResidential & Light Commercial Buildings Less Than 5 StoriesBuilding Wrap to be Installed After WindowsWindow & Door Installation Types: Method A & Method B

Building Wrap: 9' RainBuster #550 High Performance Air Barrier & Building WrapAdditional Required Installation Materials: RainBuster #501-2.83" Seam Tape4" RainBuster #440 SubZero Flashing Tape® RainBuster #900 Polycarbamate Sealant/Adhesive

Top Industrial, Inc. • 15010 Keswick St., Van Nuys, CA 91405 • 800.473.1617 • topindustrial.com

Drawings Not to Scale pg 5 of 6May 2018

Our leak & squeak eliminating systems feature high performance sealants, adhesives, flashings, tapes, and building wraps for the entire home.

Installation Guideline LEVEL 3Installation GuidelineLEVEL 3

Step 9. Sealing Round Penetrations (Pipes, Round Ducts, Exterior Lights, HVAC Lines, Etc…)Product: 4" RainBuster #440 SubZero Flashing Tape®

RainBuster #900 Polycarbamate Sealant/Adhesive

If the joint between the building wrap and the item penetrating it is greater than ¼" proceed to step 9.A. If the joint between the building wrap and the item penetrating it is ¼" or less, apply a ½" bead of sealant and tool it into the joint ensuring a water tight seal between the building wrap and the item penetrating it.

9.A Make 45° diagonal cuts in the building wrap at the upper cor-ners of the penetration. Raise the flap and temporarily secure with tape.

9.B Install flashing over building wrap tight to the bottom of the pen-etration. Flashing should extend past each end of the penetra-tion 4".

9.C Install flashing over building wrap tight to the sides of the pen-etration. If multiple pieces of flashing are required to accom-modate the radius of the penetration they should be installed in weatherboard (shingled) fashion maintaining a minimum 3" lap. Flashing should extend past the top of the penetration 3" and past the bottom of the penetration 4".

9.D Install flashing over sheathing tight to the top of the penetration. Flashing should extend past each end of the vent 5".

9.E Using a J-Roller, apply pressure and roll entire surface of flashing.

9.F Apply a ½"" bead of sealant around the entire penetration at the penetration/flashing joint. Tool to promote adhesion and ensure a water tight seal.

9.G Release the building wrap flap and embed it into the sealant at the top of the penetration. Using seam tape, seal the diagonal cuts securing the building wrap flap in its original position.

General Recommendations

Window & Door InstallationsPlease reference the RainBuster Leak Free Window Installation Procedures, Method A and Method B. Installation procedures must utilize self-adhered flashing membrane or flashing tape (no mechan-ically attached flashings). There are multiple procedures available to address flat wall, shallow recess, and deep recess conditions. For additional information regarding window installation procedures specific to this building wrap installation guideline please call (800) 473-1617 or visit www.topindustrial.com.

Building Wrap Installation SequencingIn this guideline, the building wrap should be installed after the fram-ing is completed and the roof sheathing, step flashing, kick out flash-ings, and windows and doors are installed.

ContinuityBuilding wrap should be installed in a weather board (shingled) fash-ion throughout the building wrap installation to ensure continuity of the water-resistive barrier. Begin by installing the building wrap at the bottom of the structure and continue installing subsequent courses in a weather board (shingled) fashion covering the entire structure including unconditioned spaces.

TerminationsBuilding wrap should lap over step flashing, kick out flashing, roof-to-wall flashing, and thru wall flashings in a weather board (shingled) fashion. Integrate weep screed and expansion joints with flashing and building wrap to maintain continuity of the water-resistive barri-er. Apply seam tape at all terminations.

Sealant

Sealant

12 3

4

6 6

5

Air Barrier & Water-Resistive Barrier System InstallationResidential & Light Commercial Buildings Less Than 5 StoriesBuilding Wrap to be Installed After WindowsWindow & Door Installation Types: Method A & Method B

Building Wrap: 9' RainBuster #550 High Performance Air Barrier & Building WrapAdditional Required Installation Materials: RainBuster #501-2.83" Seam Tape4" RainBuster #440 SubZero Flashing Tape® RainBuster #900 Polycarbamate Sealant/Adhesive

Top Industrial, Inc. • 15010 Keswick St., Van Nuys, CA 91405 • 800.473.1617 • topindustrial.com

Drawings Not to Scale pg 6 of 6May 2018

Our leak & squeak eliminating systems feature high performance sealants, adhesives, flashings, tapes, and building wraps for the entire home.

Installation Guideline LEVEL 3Installation GuidelineLEVEL 3

Build Wrap Integration with Window & Door Head FlashingBuilding wrap should lap over window & door head flashing in a weather board (shingled) fashion. Apply seam tape at all window/door heads.

Repairing Tears and HolesDuring the course of normal construction tears, cuts, and holes in the building wrap may occur. Small repairs (less than 1") can be repaired using seam tape, flashing, or sealant. Larger repairs (greater than 1") can be repaired by cutting a piece of building wrap to cover the hole and integrating it in a weather board (shingled) fashion. Tape all seams created by the repair.

Cantilevered FloorsBegin at the wall area below the cantilevered floor. Install the build-ing wrap up the wall, across the underside of the cantilevered floor, and up the face and sides of the cantilevered wall a minimum of 6". Inside corners should be as tight as possible. Tape all corners. Upper course of building wrap should overlap lower course at the bottom of the cantilevered wall a minimum of 6".

Gable EndsCover entire gable end with building wrap maintaining a 6"-12" overlap at the outside corners. Remove excess building wrap and tape all seams.

3-Coat Stucco (Conventional Stucco) & Stone VeneerWhen building wrap is installed behind 3-coat stucco or stone ve-neer, a second intervening layer of building wrap, Grade D build-ing paper, felt, or the paper backing of paper-backed lath should be installed over the building wrap separating the building wrap from the stucco or stone veneer. The first layer of building wrap (installed directly over the sheathing or studs) serves as the water-resistive barrier and is integrated with the window and door flashing, kick out flashing, roof-to-wall flashing, thru wall flashing, and weep screeds. The lath should be installed over the second intervening layer. The layers should be installed independently creating two separate con-tinuous planes. The water-resistive barrier and integrated flashings are intended to drain between the two layers.

1-Coat StuccoWhen building wrap is installed in 1-coat stucco applications the rigid foam board acts as the intervening, substantially non-water-absorb-ing second layer. The first layer of building wrap (installed directly over the sheathing or studs) serves as the water-resistive barrier and is integrated with the window and door flashing, kick out flashing, roof-to-wall flashing, thru wall flashing, and weep screeds. The lath should be installed over the second intervening layer (ridged foam board). The layers should be installed independently creating two separate continuous planes. The water-resistive barrier and integrat-ed flashings are intended to drain between the two layers.

Special Installation ConsiderationsThis installation guide applies to buildings that are less than 5 stories above grade. These guidelines are not intended to address all pos-sible combinations of construction materials and wall assemblies. The installation information provided is intended only as a general guide for installers, builders, architects, and other design profession-als. Compliance with applicable codes and proper installation of the appropriate products are critical components of preventing water in-trusion. Always verify the intended application is compliant with local building codes.