INSPECTION ACTIVITIES STEPS REVIEW FOR TURNAROUND SHUTDOWN MANAGEMENT

Inspection activities linked

Embed Size (px)

Citation preview

Page 1: Inspection activities linked

INSPECTION ACTIVITIES STEPS REVIEW

FORTURNAROUND SHUTDOWN MANAGEMENT

Page 2: Inspection activities linked

Activity: A task or process to be accomplished in a set period of time as part of working towards a large project goal.

What is an Activity?

Page 3: Inspection activities linked

Correct Resource usage . Schedule remains under control & Focus required

on lagging areas can be easily identified. Accuracy in reporting to management for taking

effective decision on timely manner. Forecast to prepare yourself to avoid any uneven

situations. To keep your project under allocated cost & budget.

Outcomes of Proper Activity

Page 4: Inspection activities linked

Inspection activities under a Statutory Equipment.

Last S/D Planning Strategy

Page 5: Inspection activities linked

73%

27%

Last S/D, Heat Exchanger

Maitenance ActivitiesInspection Activities

Share of Inspection Act. In Stat Equipment task list

Page 6: Inspection activities linked

26 Number of resources assigned to Inspection activities.

As primavera provides you the accessibility to assign any number of resources to an activity.

Optimization in number of activities. Less number of activities against SAP and

effectively tracked & Controlled.

Last SD Positive Outcomes

Page 7: Inspection activities linked

Comparison B/W SAP & P6 Act.

Page 8: Inspection activities linked

The total Number of activities for a Stat. Equipment is already reaching up to 30Nos with covering max. data for the Equipment.

Addition of More activities to be consider precisely, as if Resources is the Logic we can assign any number of resources to an activity which will cover the sub activity.

If activity added also it must be reported by the activity owner .Delay in updating activity may affect the overall progress which may lead to Justification of delay.

As per Primavera concept for resource no need to add separate activity for resource which leads to Optimization of schedule.

Addition of More Insp. Act.

Page 9: Inspection activities linked

Schedule With Additional Inspection Activities

Page 10: Inspection activities linked

53%

47%

For Upcoming S/D, Heat Exchanger

Maintenance Activities

Inspection Activities

Share of Inspection after Additional Data

Page 11: Inspection activities linked

Affect of on Overall schedule

UPCOMING S/D

UPCOMING S/D

Last S/D

Last S/D

UPCOMING S/D

For UPCOMING S/D

Page 12: Inspection activities linked

Plant Turnaround Shutdown

Prepared By: Vivek Chaube,PMPPosition: Planning EngineerDep't: Project Controls

Prepared By: Vivek Chaube,PMPPosition: Planning EngineerDep't: Project Controls