31
Innovation in Structural Engineering Design The Complete Structural Package TM Douglas G. Fitzpatrick, P.E. Fitzpatrick Engineering Group, PLLC October 14, 2015

Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Innovation in Structural Engineering Design The Complete Structural PackageTM

Douglas G. Fitzpatrick, P.E. Fitzpatrick Engineering Group, PLLC October 14, 2015

Page 2: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Outline •  Current state of the industry – steel delivery

•  Observations about where we are •  Why it needs to be transformed

•  The Complete Structural PackageTM (CSP) •  Criteria to define a design solution •  Transformed deliverable

•  Case Studies •  Liability •  Working relationships

2

Page 3: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Fitzpatrick Engineering Group •  Doug Fitzpatrick, P.E.

–  President and Founder –  Structural design of buildings –  Actively involved in day-to-day engineering –  BIM advocate since 2006

3

London, England Amsterdam, NE

Innovations in Infrastructure Conference Innovation in Structural Engineering

Page 4: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

History •  Process of designing and constructing (commercial)

steel buildings has remained essentially unchanged for decades.

•  “Alternate construction methods” speed up process but don’t make it more efficient

4

Page 5: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Definitions •  Steel fabricator

–  Physically makes the steel that gets delivered to the job site

–  Traditionally hires a detailer and connection engineer as part of that process

•  Most fabricators do NOT have detailing in-house •  Large local fabricator only does ~25% in-house

•  Steel detailer –  Figures out exactly how the pieces go together

for structural plans and details, design intent. – Conveys that info to the fabricator via 2D PDF

shop drawings and CNC files for their equipment

Page 6: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Workflows

6

Structural Design Construction

Fabrication

Detailing

Traditional Design-Bid-Build

Structural Design Construction

Fabrication

Detailing

“Alternate Construction Methods”

May include one-time electronic hand-off of

information

All of this work is completed manually

The earlier the Detailing starts: Less information is available to transfer electronically More data has to be recreated by hand

Time savings Cost savings??

Confusion

Page 7: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Workflows

7

Structural Design Construction

Fabrication

Detailing

“Alternate Construction Methods”

Fabricator selected based on GMP

Opportunities for change orders and RFIs to fuel

change orders

The earlier the Fabricator gets involved: Less accuracy in GMP More opportunities for change orders in the ensuing

confusion as design gets finished

Confusion

Page 8: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Workflows

8

Structural Design Construction

Fabrication

Detailing

“Alternate Construction Methods”

Fabricator selected based on GMP

Opportunities for change orders and RFIs to fuel

change orders

Confusion

The earlier the Fabricator gets involved: Less accuracy in GMP More opportunities for change orders in the

ensuing confusion as design gets finished

Page 9: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Workflows

9

Structural Design Construction

Fabrication

Detailing

“Alternate Construction Methods”

Fabricator selected based on GMP

Opportunities for change orders and RFIs to fuel

change orders

Confusion The earlier the Fabricator gets involved: Less accuracy in GMP More opportunities for change orders in the

ensuing confusion as design gets finished

Page 10: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Workflows

10

Structural Design Construction

Fabrication

Detailing

“Alternate Construction Methods”

Fabricator selected based on GMP

Opportunities for change orders and RFIs to fuel

change orders

Confusion The earlier the Fabricator gets involved: Less accuracy in GMP More opportunities for change orders in the

ensuing confusion as design gets finished

Page 11: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Workflows

11

Structural Design Construction

Fabrication

Detailing

“Alternate Construction Methods”

Fabricator selected based

on GMP

Opportunities for change orders and RFIs to fuel

change orders

Confusion The earlier the Fabricator gets involved:

Less accuracy in GMP

More opportunities for change orders in the ensuing confusion as design gets finished

Page 12: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Workflows

12

Design Construction

Fabrication

Detailing

“Alternate Construction Methods”

Fabricator selected based on GMP

Confusion

There is a limit!

The earlier the Fabricator gets involved:

Less accuracy in GMP

More opportunities for change orders in the ensuing confusion as design gets finished

Page 13: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

The tipping point •  Summer of 2012

–  Fabricator selected based on Guaranteed Maximum Price (GMP) during Design Development (DD)

– Received “pitiful” set of shop drawings –  Sent out incomplete / poorly checked to “maintain the

schedule” –  50% more time checking – Change order was delivered in a spreadsheet in

excruciating detail

13

Page 14: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Reflection

•  If fabricators were using technology to track (justifiable) changes…

•  Why couldn’t we use technology to eliminate opportunities for change orders and make the entire process more efficient? –  Transform the process from scratch

14

Page 15: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Solution Requirements •  Electronic data transfer

•  Sent incrementally

•  Overlap the design phase

•  Reduce or eliminate change orders

•  Leverage inherent efficiencies

•  Be flexible to owner’s process

•  Save significant time

•  Reduce or eliminate RFIs

15

Page 16: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Transfer of Information •  Fall of 2012 found:

– Detailing software package that could incrementally read structural data with global IDs

–  BIM that could reliably export data with global IDs – Detailing partner with same enthusiasm

–  Electronic transfer of information –  Incremental updates – During the design phase –  Fewer opportunities for change orders

16

Page 17: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Fabricator Preferences •  East coast – typical connections •  Changes (outside model) cost detailer time

– Changing in 3D = 1x –  Tracking changes on paper = 3x

•  Change provenance important for AISC certification

•  Solution – stay in 3D as long as possible – Make modifications easily as design changed –  Adapt to selected fabricator’s preferences

•  Leveraging fabricator’s shop efficiencies •  Flexible for bid or negotiated project

17

Page 18: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

FEG Project Data •  Could we save time?

•  Looked at 45 of our existing steel projects –  Time has been tracked in our timesheets –  Knew exactly when CDs were issued –  Knew about when we started receiving shop

drawings to earnest –  Knew about how long to review shop drawings

•  Graphed data (size of building in square feet vs. time) to see where the opportunities might be

18

Preparation time

Review time

Page 19: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

FEG Project Data

19

Shopdrawingprepara.on.meTimetorecreatedataanddeliver2Dshop

drawingsforreview

Page 20: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

FEG Project Data

Shop drawing review time FEG time

20

Page 21: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

•  Preparation 8-9 weeks •  Review by Contractor 1-2 weeks •  Review by Architect 1-2 weeks •  Review by Engineer 6-7 weeks •  Mailing/shipping time 1-2 weeks

•  Total 17-22 weeks

Fabrication package time

21

Page 22: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

•  Preparation 8-9 weeks •  Review by Engineer 6-7 weeks

•  Total 14-16 weeks •  Detailer estimate – 3D to fabrication pkg 5-6 weeks

•  Difference 8 weeks

•  Significant time savings

Fabrication package time

22

Page 23: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Improved Communication •  Phone calls •  Screen sharing •  Direct electronic review of the detailer’s live model

–  Approval mode only – No paper submittals

•  Could we put all of this together and make a difference

Page 24: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Case Studies •  Southeastern MOB

–  Three story, 60,000 sf –  Structural frame 320 tons –  Six (6) week turnaround from

fabricator’s notice to proceed –  No RFIs and no change

orders

–  “This [process] was a lot better for us in the plant and the field. This [process] was by far the best experience I have had in a long time. [The elimination of the RFI process] saved a tremendous amount of time.” Greg Sain, Project Manager, CM Steel (fabricator)

24

Page 25: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Case Studies •  Otarre MOB

–  Two story, 73,000 sf –  Structural frame 318 tons –  Five (5) week turnaround from

fabricator’s notice to proceed

–  No RFIs and no change orders

–  “The detailed drawings were some of the best ever. Any question we had got resolved quickly. All electronic files were excellent…. The whole process was a good experience for D & T. We saved erection time in the field.”

–  Travis Crumpton, President, D&T Steel (fabricator)

25

Page 26: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Case Studies •  Octapharma

–  Two story, 87,000 sf –  Structural frame – 340 tons –  Same process as the previous

two case studies –  No RFIs –  Change orders?

–  Based on previous case studies – similar tonnage

•  Saved 8 weeks = 2 months = $2,000,000 savings to owner

26

Page 27: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Transforming Deliverables

27

StructuralDesign Construc.on

Fabrica.on

Detailing

FEG Process

Detailing complete in 3D model at CDs

5-6 weeks for fabricator optimization

StructuralDesign Construc.on

Fabrica.on

Detailing

Traditional Design-Bid-Build

Time savings Dollar savings 8 weeks

8 weeks

Page 28: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Risk/Liability •  BIM journey started in 2006 •  First BIM project – Level of Detail/Development

(LOD) 300 (beams, columns) –  Shared data with fabricator/detailer

•  All BIM since – LOD 350 – Only difference to detailer’s model is connections

•  Electronic model review lets us focus on the important parts

•  Liability Risk

28

Page 29: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Working Relationships •  Who works for who?

– Detailer works for FEG •  This is not engineers doing shop drawings •  No formal partnership •  Separate entity •  Most fabricators do not have in-house detailing

–  FEG works for •  Architect (during design) •  Contractor (during or after design) •  Owner (during design) •  Fabricator (during or after design)

29

Page 30: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Plus / Delta Delta •  Engineers •  Liability •  Not perfect •  Not easy •  Cannot be just any detailer

Plus •  Proof of concept to shorten schedules •  Flexibility for owner – bid versus

negotiated •  Not a proprietary solution •  Improved communication •  Decreased risk / liability •  Trust based •  Early meaningful involvement of

detailer / fabricator •  Not unique to a single project •  Reduced waste - no paper shop

drawings •  Minimal recreation of structural data •  Flexibility in working relationships •  Upgraded old process into something

more efficient •  FEG engineers think about end goal –

sharing data

Page 31: Innovation in Structural Engineering Design · • Most fabricators do NOT have detailing in-house • Large local fabricator only does ~25% in-house • Steel detailer – Figures

Lean Construction Institute

Structural Steel Fabrication Package A Paradigm Shift

Thank you

Questions?

31