Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
6/17/2015
1
Innovation in Customized Energy
Programs for Business
John R. Buckley, Plant Engineer
The Siemon Company – Watertown, CT
Facilities Background
Company Location Position Experience
(Years)
Ensign-Bickford Simsbury Plant Engineer 8
OFS Specialty Fiber
Optics
Avon Facilities
Manager
8
Holy Family Monastery
& Retreat Center
West
Hartford
Director of
Physical Plant
5
The Siemon Company Watertown Plant Engineer 3+
6/17/2015
2
Perspective on CT Energy Programs
• The Eversource Account Executives have been outstanding
• Eversource’s annual large customer meetings have always
been well done
• Qualified vendors and suppliers access to program funding is
straight forward
• Help is always available
• Keeping it real makes it happen easier - relationships
• I have been fortunate to work for places who are onboard with
reducing energy & costs
Lessons Learned
• Energy Measurement & Monitoring
• Management of Change # 1
– Talking to the stakeholders
– Establishing a sense of urgency
– Everyone on the team
• Detailed Planning
• Contact Eversource – Account Exec
• Engage qualified vendors
• Manage the project
• Close out with Eversource
• Monitor performance
6/17/2015
3
Project List Summary
• Lighting
– 150 Watt “Jelly Jars” to 30 Watt HPS
– Fluorescent – T12 to T8
– Lighting – Compact Fluorescent Ceiling “Cans”
– Lighting Control – Occupancy Sensors
• Variable Frequency Drives (VFD)
– Air Compressors
– Pumps
Project List Summary
• Compressed Air
– Higher Efficiency Air Compressors
– Compressor Consolidation
– Compressed Air Monitoring
– Compressed Air Control Valves
• Building Automation System (BAS)
• Old Fashioned Checklists to turn off energy wasters
6/17/2015
4
BUILDING AUTOMATION SYSTEM
(BAS)
Depot
Mall Dynamic Manufacturing
The Siemon Companies – Campus
Watertown, CT
Assembly
Manufacturing
& Offices
Princeton
Building -
West
Princeton
Building -
East
6/17/2015
5
Assembly Building Floor Plan
FIRST
FLOOR
RTU 01
RTU 04
RTU 07
RTU 08
RTU 09
CU 11
SECOND
FLOOR
RTU 02
RTU 03
RTU 05
RTU 06
RTU 10
CU 12
CU 14
Typical Roof Top Unit (RTU)
RA = Return Air
(from space) SA = Supply Air
(to space)
OA = Outside
Air
Heating Unit
Cooling Coil
Supply
Air Fan
6/17/2015
6
Dynamic Building – Process Cooling and
EDM Chilled Water System
Main Thrust (March 2014)
• NO COST – LOW COST Tactical Actions – NOW!
• If we turn off unnecessary systems and equipment, we don’t
have to pay for the energy they use
• But . . . Things are left on which equals a base load that we
want to reduce or eliminate
• We want to “zero base” the base load
– What is on?
– Why is it on?
– Can it be turned off without harming the process?
• Requires communication and cooperation
6/17/2015
7
WEEKEND – March 2014
• Turn off more items during the weekends
– Manually
– Automatically
• Install Building Automation System (BAS)
• Wring out waste with BAS – ASAP
A weekend is 29% of a week – how many things
can we shut off during the weekend?
The BAS Made Me Do It
• Once BAS on line – looked at HVAC & Pump Status
• Asked self why things were on or off & when
• Established trends – Asked why again
• Weekend Shut Down – GO! Manual
– Dynamic Molding - 3rd Shift – Saturday Shutdown
– Dynamic EDM – 4 Machines, 2 Chillers and Process
Cooling System
– Assembly – 2nd shift – Friday Night Shutdown
6/17/2015
8
The BAS Made Me Do It
• Weekend Shut Down – Automatic
– Dynamic Molding – Wittmann Dyer – Ben M – Timer Enabled
– Dynamic New Air Compressors and Controls – November
2014
• Nights and Holidays
– Vigilance – any opportunity – snow, light work – 01/02/2015
– Turn stuff off or set up (summer) & setback (winter)
– Creates a “Sixth Sense” of how the plant operates
• LESS LOAD = MORE SOLAR CREDITS directly off invoice
3,756,240
3,451,704
2,778,735
3,109,566
2,974,681 2,892,611
2,748,001
2,346,445
2,200,000
2,400,000
2,600,000
2,800,000
3,000,000
3,200,000
3,400,000
3,600,000
3,800,000
4,000,000
2007 2008 2009 2010 2011 2012 2013 2014
KW
H
The Siemon Company - Dynamic Building - PAST 7 YEARS Annual
-41% vs 2007 (Before Solar PV)
-16%
vs
2013
6/17/2015
9
SIMPLE CHECKLIST TO TURN
ENERGY USERS OFF
6/17/2015
10
WEEKEND SHUTDOWN CHECKLIST as of 05/24/2014
A. PROCESS COOLING LOOP
1. Unplug solenoid valve from hanging outlet (right side of skid around back)
2. Observe water treatment system flow meters go to zero
3. Variable Frequency Drive (VFD) - Process Cooling Pump - Press the "OFF" button
4. Observe VFD speed % drop to 0.00% (this ensures that the pump is not dead headed)
5. Close Heat Exchanger Process Discharge Valve
6. Verify that the process tank does not continue to fill up
B. TOWER LOOP
1. Variable Frequency Drive (VFD) - Process Cooling Pump - Press the "OFF" button
2. Observe VFD speed % drop to 0.00%
C. PROCESS COOLING
MAIN WATER SHUTOFF
Close the MAIN water supply to ALL equipment
In the back corner to the right side
D. SHUT OFF BOTH AIR COMPRESSORS
E. TURN OFF THE WITTMANN DRYER
E. TURN OFF THE NUCONN VACUUM BLOWERS
These are under Mezzanine towards the
Wittmann Dryer
PLEASE SEE REVERSE SIDE FOR MORE - THANK YOU
F. TURN OFF THE MOTON VACUUM BLOWERS
These are on top of the Mezzanine
at the north end by main door
IF IN DOUBT DO NOT HESITATE TO CALL
HAVE A GREAT MEMORIAL DAY!
THANK YOU!!
John Buckley = 860-944-3060 - CELL
DYNAMIC
BUILDING
WEEKEND
SHUTDOWN
CHECKLIST –
“You Can Do It
Award” for Tim
Farland’s exceptional
attention to detail
and consistency ASSEMBLY
BUILDING
WEEKEND
SHUTDOWN
OWN LIST
“You Can Do It
Award” for Geoff
Platt and David
Leary’s exceptional
attention to detail
and consistency
REFLECTIVE WHITE ROOF
SARNAFIL BRAND
THERMOPLASTIC
6/17/2015
11
Before & After
PROCESS HEATING FOR
INJECTION MOLDING
6/17/2015
12
6/17/2015
13
NEW – “HIGH TECH” AIR
COMPRESSORS
Dynamic Air Compressors - Too much
inefficiency to bear – NOT ANY MORE! We wake up our big, 200 HP
Compressor to do a little work
What we need – smaller, right
sized, nimble, flexible
6/17/2015
14
250
260
270
280
290
300
310
320
330
340
350
0:0
5:0
0
0:1
5:0
0
0:2
5:0
0
0:3
5:0
0
0:4
5:0
0
0:5
5:0
0
1:0
5:0
0
1:1
5:0
0
1:2
5:0
0
1:3
5:0
0
1:4
5:0
0
1:5
5:0
0
2:0
5:0
0
2:1
5:0
0
2:2
5:0
0
2:3
5:0
0
2:4
5:0
0
2:5
5:0
0
3:0
5:0
0
3:1
5:0
0
3:2
5:0
0
3:3
5:0
0
3:4
5:0
0
3:5
5:0
0
4:0
5:0
0
4:1
5:0
0
4:2
5:0
0
4:3
5:0
0
4:4
5:0
0
4:5
5:0
0
5:0
5:0
0
5:1
5:0
0
5:2
5:0
0
5:3
5:0
0
5:4
5:0
0
5:5
5:0
0
6:0
5:0
0
6:1
5:0
0
6:2
5:0
0
Dynamic Building - 200 HP vs. Nirvana Night Test
2/6/2015 Nirvana Average Linear (2/6/2015) Linear (Nirvana Average)
9.4% Less
184,614
167,371 150,000
200,000
250,000
300,000
350,000
400,000
Usa
ge
The Siemon Company - Dynamic Building kWh Usage - Month to Month
2007 2008 2009 2010 2011 2012 2013 2014 2015
6/17/2015
15
COMPRESSOR AIR SYSTEM
MONITOR
6/17/2015
16
Siemon Company - Compressed Air
Case Study – J Buckley
50 HP on at
night now!
USED TO
BE THE 75
HP
50 HP
takes a nap
in the
evening
Closing Off the South End – Easter Weekend
• No 2nd Shift Metal Stamping
or Sheet Metal
• Climbed up in the attic
• Shut off valves to south end
• Easter Monday –
compressors come on for
Motan @ 12:30 AM
• Normally the 50 & the 75
pump up the system and the
75 shuts off
• Then due to no leaks . . .
At times they both were off!
Cool!
Siemon Company - Compressed Air
Case Study – J Buckley
6/17/2015
17
COMPRESSED AIR SYSTEM
CONTROLS
The Siemon Company - Dynamic Building - SIMPLIFIED Compressed Air Functional Flow Diagram - FUTURE
CFM 75 HP 50 HP
Control Load UnLoad Control Load UnLoad
1st Shift 485 Lead 109 114 Trim 105 114
2nd Shift 337 Lead 109 114 Trim 105 114
3rd Shift 237 Back Up 105 114 Lead 109 114
8
MoldingPress
Tower
4
MoldingPress
Tower
200
HPAir
75 HP
Air Comp
Compressed
Air Dryer
METAL STAMPING,
SECONDARY & CLIP ROOM
MOLDING North 3"
Copper Loop
MOLDING Plastic
Material Drying
EDM
2 x 2
2 HP Compressor
CompressedAir Dryer
CompressedAir Hose
Sheet Metal
Loop
50 HP
Air Comp
Expand Air
Control Valve
6/17/2015
18
The Siemon Company - Dynamic Building - 2014 Compressor Upgrade Project
Compressor Control Squence of Operation COMPRESSORS *
Control
Configuration Time Production Need Description 75 HP 50 HPMotan
Dryers Molding
Metal
Stamping
Sheet
Metal
Monday AM
Start Up
0200-0600 Motan and Wittmann raw
material drying system
turns on
1. Timer turns on 50 HP with
pressure setpoints as lead
Lag Lead Open Closed Closed Closed2. Timer turns on 75 HP with
pressure setpoints as lag (back
up for 50 HP)
1st Shift 0600-1500 Molding & Metal
Stamping starts up
1. Control switches 75 HP to
lead machineLead Trim Open Open Open Closed
(Mon-Fri) 2. Control switches 50 HP to lag
/ trim machine
0700 -
1530
Sheet Metal Starts Up Same configuration as 0600
Lead Trim Open Open Open Open
2nd Shift
(Mon-Fri)
1500-2330 Molding & Sheet Metal
only
Anticipate 75 HP holding its
own with Metal Stamping goneLead Lag Open Open Closed Open
3rd Shift
(Tue-Sat)
2330-0700 Sheet Metal leaves -
Molding Dept Only
1. Timer turns on 50 HP with
pressure setpoints as leadTrim Lead Open Open Closed Closed
2. Timer turns on 75 HP with
pressure setpoints as lag
Weekend
(Sat-Mon AM)
0700 Sat -
0200 Mon
No compressed air
required
Timer turns off both 50 and 75
Off Off Closed Closed Closed Closed
"Lag"
"Lead"
"Trim" The compressor is most likely operating below full load but could be at full load if needed
"Off" The compressor is off on a hard timer function and/or an "UnOccupied" command from BAS
"Open" The control valve for that particular loop is in the closed position
"Closed" The control valve for that particular loop is in the opend position
LOOP CONTROL VALVES - CONTROLLED By
HONEYWELL - Building Automation System
(BAS)
The compressor is in auto re-start but most likely not operating
The compressor is in lead role - running the current plant configuration
NOTES AND DEFINITIONS - * in all configurations, the existing IR - SSR - 200 HorsePower compressor is the back up
Compressed Air Rated - High Quality
Control Valves
120 Volt Actuator Motor Stainless Steel Body
Pro Press joints
6/17/2015
19
BUILDING AUTOMATION SYSTEM
(BAS) EXPANSION
The Siemon Company - Watertown, CT
Honeywell EBI Building Automation System (BAS) - Phase 2 Blue color are left overs from original project
Honeywell
PRIORITY System
Project ID
Number Components Quantity Remarks
Chiller Chiller 2015-04 Small Chiller - Start Stop 2 Have 2 pair going to these now monitoring Return Water Temp and
On/Off Status. Phase 1 did have other point but they were for a larger
chiller so we re-invested in some other points.
Control Control 2013-81 Assembly Building RTU 02 - Static Pressure,
etc programming
1 New development due to new VFD and information from Carrier tech.
Carrier CCN being replaced by Honeywell. Quality Mech (Scott) and Hon
(Vinny) felt it could be done. In the past it was not determined to be the
safest way (Hon-Matt).
Control Control 2015-05 Dynamic RTU 03 - Temperature Averaging 1 Add a sensor in the Maintenance shop to average with the temperature in
the tool room for Metal Stamping. Average them to try and get more
cooling in to the Maint Shop
Control Control 2015-09 Showroom Control - Control that room? ConvergeIT - Possibly add a controller to control the VAV boxes, lighting,
CDU and chiller remotely as a demo for customer demonstrations.
Control Control 2015-10 Heated side walk - North & South 2 Would like to remote read whatever the controller can give us. Would
like to remotely start / stop this equipment
Control Control 2015-11 Tie in to new air compressor control
package
1 Most likely will a robust system from Ingersoll-Rand called X8I - "system
Modbus Gateway"
Control Control 2015-12 Compressed Air Pressure Loop Control
Valves
3 + TBD Simply install control signal to open and close a motorized valve for
various compressed air loops
Control Control 2015-14 EDM Waste Heat Removal 1 Turn on an attic fan(?) to take heat from plant in colder weather to cool
EDM rather than run RTU 07. EDM seems to heat up the internal office
space like a wood stove.
Control Control 2015-15 Motan Drying Waste Heat Removal 1 It is warm / hot in the Motan drying area. It may be feasible for this heat
to be sent towards the north loading dock door in the winter. Could
consider the use of a vent sock.
Control Control 2015-16 Air compressor waste heat 1 New equipment being installed
Control Control 2015-17 Process cooling remote control 2 Process cooling system - pumps on and off remotely
Lighting Lighting 2015-08 Lighting - All Over RIBs?? Wiring
Meter Meter 2013-80 Assembly Building Meter working 1
Meters Meters 2015-01 Water Meters 5 Need BAS capable water meters - tie back to software in EBI
Meters Meters 2015-02 Natural Gas Meters - Honeywell Brand 2 Would like to remote read these / capture information
Monitor Monitor 2015-03 Compressed Air Pressure Transducer 2 Simple?
Monitor Monitor 2015-06 Assembly - Clean Room Temperature 1 Monitor
Monitor Monitor 2015-07 Assembly - Clean Room Dew Point 1 Monitor
Program Program 2013-90 Smart Phone - Mobile App ON 1 Left over item - need licensing cost
Program Program 2015-13 Demand Limiting - Programming 2 Both Assembly & Dynamic determine what is required to
Program Program 2015-18 Process cooling remote control 1 Process cooling system - tie in to Red Lion "brain"?
Schedule Schedule 2013-00 Global Scheduling working 100% 1 Carl G from NJ has a plan to re-beam up the global sked. Either Vinny or
he needs to get this done (or someone else)
Training Training 2013-91 EBI - 5 Day Training 1 Winter travel not desired - not clear what course I need
6/17/2015
20
Thank you
John R. Buckley, Plant Engineer
The Siemon Company – Watertown, CT