PRE-COMMISSIONING TESTS REPORT
FOR
A PROPOSED 1 X 15MVA, 33/11KV INJECTION SUBSTATION A IN LAGOS, NIGERIA
BY ENGR . C. ENEH
PRE-COMMISSIONING TEST REPORT ON 1X15MVA,33/11KV INJECTION SUBSTATION A. 1.0 POWER TRANSFORMER REPORT1.1Transformer ParticularLocation: Lagos injection substation ASerial No: 12 35 206Make: Power system technology ltdRating: 15MVA Ratio: 33000/11000 VImpedance: 10.12%Vector: Dyn 1Primary current (Ip): 262.4AmpsSecondary current (Is): 787.3Amps Year: 12 - 5
1.2INSPECTION, CHECKS AND OPERATIONSS/NDescriptionOk
Not okNot Applicable
1Oil Sample from bottom of main tankOk
2Oil Sample from top of main tankOk
3Oil Sample from OLTCOk
4Oil Level in the Conservator TankOk
5Oil Level in the On Load Tap Changer Ok
6Buchholz Relay/OSR valves are openOk
7Transport Lock in Buchholtz Relay removedOk
8Colour of Silica Gels in Main Tank Breather Ok
9Colour of Silica Gels in OLTC Breather Ok
10Oil cup of Main Tank Breather is filled and up to level markOk
11Oil cup of OLTC Breather is filled and up to level markOk
12Sealing Cap of Main Tank Breather is removedOk
13Sealing Cap of OLTC Breather is removedOk
14All Radiator shut off valves (Top and Bottom) are openOk
15All sampling, drain and filtration valves are closedOk
16There is no oil leakage from any gasket/weld jointOk
17Explosion vent diaphragms are intact and there is no oil explosion vent Ok
18Oil is filled in OTI/WTI pocketsOk
19Air Released from:1. All Bushings1. All Bushing Pockets1. Buchholz Relay and OSR1. Main Tank Cover1. All Radiators1. Main Tank1. OLTC1. ConservatorOkOkOkOkOkOkOkOk
20OLTC/ Off Circuit Tap Switch is in the desired positionOk
21Tank Earthing is firmly connectedOk
22Neutral Bushing Earthing is connectedOk
23CT secondary terminals if not used are shorted and earthedOk
24Alarm and Trip contacts of all instruments are setOk
25Cable Glands as appropriate are used and securedOk
2633kV and 11kV line connections are duly tightenedOk
27Remote and Local Operation of the Tap ChangerOk
1.3LIST OF VALVES & SERVICE POSITIONS/NDescriptionService position
1Drain valve for Main Tank (Top & Bottom)Shut
2Filter Valve for Main Tank (Top & Bottom)Shut
3Sampling Valve for Main Tank (Top & Bottom)Shut
4Drain Valve for OLTCShut
5Conservator Drain ValveShut
6OLTC conservator drain valveShut
7Radiator ValveOpen
8Buchholz Relay ValveOpen
9Oil Surge Relay ValveOpen
10Breathing ValveOpen
1.4TRANSFORMER INSULATION TEST5KV MEGGERSIDEMeasured valueDurationRemark
HV - E3.34G60secso.k
LV E3.8G60secso.k
HV - LV4.23G60secso.k
REMARKS: okay.
1.5RATIO TEST THREE PHASE RATIOMETERTAPTRatVRatI (mA)P () (%)
15.45353.14862.3-0.03-0.04
5.45393.14881.8-0.02-0.04
5.45533.14963.4-0.03-0.01
35.19542.99952.5-0.02-0.02
5.19572.99972.0-0.03-0.01
5.19693.00043.7-0.030.01
54.93822.85112.7-0.022.60
4.93842.85122.2-0.022.61
4.93952.85184.1-0.022.63
REMARKS: okay.1.6SINGLE PHASE RATIO TEST
RYYBBRryybbrrnynbn
RY227.5115.199.466.664.30.622.743.721.2
YB178.4226.141.629.881.250.67.135.843.8
BR180.139.0225.279.529.150.743.534.87.9
REMARKS: okay.1.7CONTINUITY AND WINDING RESISTANCE TESTHigh voltage sideLow voltage side
PhasesResistance ()phasesResistance ()phasesResistance ()
R - Y0.04r y0.04r N0.04
Y B0.04y b0.04y N0.04
B - R0.04b - r0.04b - N0.04
REMARKS: okay.
1.8SINGLE PHASE SHORT CIRCUIT TEST
RYBrYBn
14.323.948.124.10.1
14.324.223.948.20.2
14.248.024.424.10.2
REMARKS: okay.1.9FUNCTIONING TEST ON TRANSFORMER PROTECTION1.9.1BUCCHOLZALARM-O.KTRIP-O.K1.9.2OIL TEMPERATUREALARM-O.KTRIP-O.K1.9.3WINDING TEMPERATUREALARM-O.KTRIP-O.K
1.9.4PRVTRIP-O.KREMARKS: okay.
2.0PRESSURE TEST RESULT ON 11KV CABLE TO INCOMER PANELTERMINALINJECTED VOLTAGELEAKAGE CURRENTREMARK
R - E25KV0.05mAo.k
Y - E25KV0.02mAo.k
B - E25KV0.04mAo.k
3.0PRESSURE TEST RESULT ON 33KV CONDUCTOR WITH THE ISOLATORS AND OUTDOOR BREAKER IN CLOSED POSITION
R-55KV= 0.06mAfor120secsY-55KV= 0.03mAfor120secsB-55KV= 0.04mAfor120secsREMARKS: okay.
4.0EARTH RESISTANCE MEASUREMENTi) Transformer Body=4.3ii) Lightning Arrester=0.7iii) Transformer Isolator=36.5iv) Transformer Current Transformer=0.7v) Transformer Circuit Breaker=36.6 vi) Bus Isolator 1=0.26 vii) Bus bar=0.35viii) Bus bar Circuit Breaker=overloadix) Bus Isolator 2=0.23 x) Bus Current Transformer=0.96xi) Line Current Transformer=0.96xii) Line Circuit Breaker=30.3xiii) Line Circuit Breaker Isolator=26.5xiv) Voltage Transformer=overloadAverage =9.88Earth resistance value of the station transformer =0.34REMARKS: fail.5.033KV TRANSFORMER VACUUM CIRCUIT BREAKER TEST REPORT5.1INSPECTION, CHECKS AND OPERATIONS
S/No.DescriptionRemark
1Manual Opening of Transformer Breaker from Local PositionOk
2Manual Closing of Transformer Breaker from Local Position Ok
3Auto opening of Transformer Breaker from Remote PositionOk
4Auto Closing of Transformer Breaker from Remote PositionOk
5Pressure of SF6 Gas in Transformer BreakerOk
6Spring Charging Mechanism of Transformer BreakerOk
POLARITY TEST -O.K CB FUNCTION TEST -O.K CLOSE & TRIP FUNCTION TEST-O.K CONDITION OF THE INDICATION-O.K LOCAL & REMOTE MODE TEST-O.K CONDITION OF THE SPRING CHARGING MOTOR-O.KREMARKS: okay.
6.033KV CURRENT TRANSFORMERS TEST REPORT 6.133KV TRANSFORMER SIDE: CT1 - RATIO TEST ( 400/200-1A) used 400A(A)INSPECTION RESULTSS/No.DescriptionRemark
1Oil Level in Transformer Current TransformersOK
2No oil Leakage from Transformer Current TransformersYES
(B)PRIMARY INJECTION TEST RESULTS
PHASEPRIMARY INJECTED CURRENT (A)SECONDARY MEASURED CURRENT (A)
R1000.24
Y1000.25
B1000.24
REMARKS: okay.
6.233KV BUS COUPLER SIDE: CT2 : RATIO TEST ( 400/200 - 1A) - used 400A(A)INSPECTION RESULTSS/No.DescriptionRemark
1Oil Level in Bus Coupler Current Transformers OK
2No oil Leakage from Bus Coupler Current TransformerYES
(B)PRIMARY INJECTION TEST RESULTSPHASEPRIMARY INJECTED CURRENT (A)SECONDARY MEASURED CURRENT (A)
R1000.24
Y1000.25
B1000.24
REMARKS: okay.
7.033KV COUPLER VACUUM CIRCUIT BREAKER TEST REPORT7.1INSPECTION AND FUNCTIONAL TEST RESULTS
S/No.DescriptionRemark
1Manual Opening of Bus Coupler Breaker from Local PositionOK
2Manual Closing of Bus Coupler Breaker from Local Position Ok
3Auto opening of Bus Coupler Breaker from Remote PositionOk
4Auto Closing of Bus Coupler Breaker from Remote PositionOk
9Pressure of SF6 Gas in Bus Coupler BreakerOk
11Spring Charging Mechanism of Bus Coupler BreakerOk
POLARITY TEST -O.K CB FUNCTION TEST -O.K CLOSE & TRIP FUNCTION TEST-O.K CONDITION OF THE INDICATION-O.K LOCAL & REMOTE MODE TEST-O.K CONDITION OF THE SPRING CHARGING MOTOR-O.KREMARKS: okay.8.011KV CURRENT TRANSFORMERS TEST REPORT
8.1INCOMER : RATIO TEST (800/400 - 5A) used 800APHASEPRIMARY INJECTED CURRENT (A)SECONDARY MEASURED CURRENT (A)
R1000.625
Y1000.622
B1000.621
REMARKS: okay. 8.1RATIO TEST (400/200 - 5A) used 400APHASEPRIMARY INJECTED CURRENT (A)SECONDARY MEASURED CURRENT (A)
R1001.25
Y1001.25
B1001.25
REMARKS: okay.
9.0PROTECTION TRIP TEST REPORTLOCATION: 11KV OUTGOINGS POLARITY TEST -O.K VCB FUNCTION TEST -O.K MANUAL CLOSE & TRIP FUNCTION TEST-O.K REMOTE CLOSE & TRIP FUNCTION TEST-O.K CONDITION OF THE INDICATIONS-O.K RACK-IN & RACK-OUT TEST-O.K METERING DISPLAY - O.K CONDITION OF THE SPRING CHARGING MOTOR-O.KREMARKS: okay.
10.0ISOLATORS TEST REPORT
10.1INSPECTION, CHECKS AND OPERATIONS
S/No.DescriptionRemark
1Opening of Bus Isolators OK
2Closing of Bus Isolators OK
3Opening of Transformer Isolators OK
4Closing of Transformer Isolators 0K
ISOLATOR BEFORE TRANSFORMER VCB
OPEN AND CLOSE CONDITION -OKAY BUS ISOLATOR
OPEN AND CLOSE CONDITION -OKAY ISOLATOR AFTER BUS-COUPLER VCB
OPEN AND CLOSE CONDITION -OKAY ISOLATOR BEFORE BUS-COUPLER VCB
OPEN AND CLOSE CONDITION -OKAYREMARKS: okay.
11.0TRANSFORMER OIL TEST REPORT1 (KV)2 (KV)3 (KV)4 (KV)5 (KV)6 (KV)Total (KV)Average (KV)
60606060606036060
REMARKS: okay.
12.0OPERATIONAL AND RELAY TEST REPORTS12.1TRANSFORMER VACUUM CIRCUIT BREAKERS/No.DescriptionRemark
1Manual Closing Ok
2Remote Closing Ok
3Manual Tripping Ok
4Remote TrippingOk
5Tripping Through RelayOk
6Inter-lockingOk
7Remarks / observation Annunciation Alarm Ok or Not Ok
REMARKS: okay.12.211KV INCOMER CIRCUIT BREAKER
S/No.DescriptionRemark
1Manual Closing Ok
2Remote Closing Ok
3Manual Tripping Ok
4Remote TrippingOk
5Tripping Through RelayOk
6Inter-lockingOk
7Remarks / observation Annunciation Alarm Ok or Not Ok
REMARKS: okay.
12.311KV OUTGOING 1 CIRCUIT BREAKERS/No.DescriptionRemark
1Manual Closing Ok
2Remote Closing Ok
3Manual Tripping Ok
4Remote TrippingOk
5Tripping Through RelayOk
6Inter-lockingOk
7Remarks / observation Annunciation Alarm Ok or Not Ok
REMARKS: okay.
12.411KV OUTGOING 2 CIRCUIT BREAKERS/No.DescriptionRemark
1Manual Closing Ok
2Remote Closing Ok
3Manual Tripping Ok
4Remote TrippingOk
5Tripping Through RelayOk
6Inter-lockingOk
7Remarks / observation Annunciation Alarm Ok or Not Ok
REMARKS: okay.
12.511KV PANELS FINAL RELAY SETTINGSS/No.NAME OF FEEDERSPHASESETTING (%)TIME SETTING (seconds)
1INCOMER RYB6060600.10.10.1
2OUTGOING 1 RYB7575750.050.050.05
3OUTGOING 2 RYB7575750.050.050.05
REMARKS: okay.12.611KV PANELS SECONDARY INJECTION TEST (RELAY CHARACTERISTIC CHECKS)
S/No.NAME OF FEEDERSTYPE OF RELAYPHASEPICK UPCURRENT(A)INJECTEDCURRENT(A)FLAG OPERATIONOBSERVATION: whether breaker tripped or not alarm indication
1INCOMER ABBRedYellowBlue4.24.14.2555OkOkOkTrippedTrippedTripped
2OUTGOING 1 RedYellowBlue4.14.24.1555OkOkOkTrippedTrippedTripped
3OUTGOING 2 RedYellowBlue4.24.24.2555OkOkOkTrippedTrippedTripped
REMARKS: okay.
13.0STATION SUPPLY TRANSFORMER TEST REPORT 13.1TRANSFORMER PARTICULAR
Serial No: S 700/33Make: NIPPRating: 200KVARatio: 33000/415KVImpedance: 4.21%Vector: Dyn 11Ip: 3.49AmpsIs: 278.2AmpsYear: 2008
13.2INSULATION TEST
HV G=2.0GLV G=689.5MHV LV=389.9M
13.3SINGLE PHASE RATIO TEST
RYYBBRryybbrrnynbn
RY234.557.119.52.50.72.11.41.20.4
YB39.7236.351.41.91.70.10.41.40.9
BR17.560.5235.80.82.31.20.51.21.5
13.4SHORT CIRCUIT TESTRYBrybn
0.235.516.416.40.7
0.216.433.616.40.3
0.216.816.032.50.3
13.5EXCITATIONr n =3.9Ay n =1.7Ab n=3.8A
REMARKS: The transformer was tested okay.
14.0 ADDITIONAL REMARKS
(a) Wiring checks were carried out on the panels and confirmed okay.(b) All fuses and MCBS in the panels were checked okay.(c) 110VDC and 230VAC were supplied to the panels to confirm the indications and alarms on the panels e.g spring charging, breaker off etc. The motor was also spring charging electrically.(d) Close and open operation of the breaker was carried out both electrically and mechanically.(e) The protection relays on all the circuits checked okay. 15.0CONCLUSION: The results of all various tests carried out on the equipment stated therein, are clearly in conformity with the acceptable international standards and therefore recommend for the tie-in of the substation to the national grid.
THANK YOU.