an initial presentation on 16/10/2013
Muhammad Aiman bin Abdul Rahman (006119) Nur Afiqah binti Jamalludin Al Amini (006081) Nik Muhammad Izzat bin Azhar (006154) Stanley Chia Uei Ying (009786) Lau Lee Yeo (009790)
H24A03 Group Design Project 2013/2014
5-STAR MAJESTIC HOTEL
1
8/13/2019 Initial Presentation Group 3
2/37
Documents provided at start
1. Topographic map of the site2. Soil investigation (SI) report
2
8/13/2019 Initial Presentation Group 3
3/37
CONTENT OF THE PRESENTATION
1. Aims and objectiv es2. Concept
3. List of the refurbis hment works4. Conceptual design 5. Construction planning
6. Basement parkin g const ruction7. Cost Estimation8. Environmental Assessment
3
8/13/2019 Initial Presentation Group 3
4/37
Aimsand Objectives To refurbish the existing building To build a new accommodation block To maintain a heritage building with a luxury of a 5-star hotel To come out with design solutions for complex engineering
problems To consider public health and safety, cultural, societal, and
environmental considerations during construction phas e
4
8/13/2019 Initial Presentation Group 3
5/37
A hint of history in a
modern city -concept established from aims
Combination of Neo-classical and art decostyle for the new building New building complements the existing
building
5
8/13/2019 Initial Presentation Group 3
6/37
Refurbishment work-the list of planned activities 1
Structural work Fatigue and cracking
repairs Concrete repair or
strengthening Frame inspection
Bathroom Floor tiling
Wall tiling Plumbing work Electrical work
6
8/13/2019 Initial Presentation Group 3
7/37
Refurbishment work-the list of planned activities 2 (continuation)
Bedroom Carpet Wallpaper Air conditioning Electrical fittings Light fittings Telephone fittings Ceiling Finishing
Floor Hallway Carpet Wallpaper Decorations Light fittings Ceiling Fire doors Sprinkler system
7
8/13/2019 Initial Presentation Group 3
8/37
Conceptual design of existing building- Majestic Wing
8
MajesticWing
The ColonialCafe
The TeaLounge
The BarSuites with
ButlerService
8/13/2019 Initial Presentation Group 3
9/37
Conceptual design of new block- Tower Wing
9
Tower Wing
ReceptionDeluxe
Rooms &
Suites
Opus OneRestaurantGymnasium
SwimmingPool
BallroomMeetingRooms
8/13/2019 Initial Presentation Group 3
10/37
Conceptual design of new block- facilities provided 1
Two parts: Accommodations Management and Leisure
Area Design 1 = 2767 sq.m Area Design 2 = 2400 sq.m 132 deluxe rooms 121 suites
10
8/13/2019 Initial Presentation Group 3
11/37
Conceptual design of new block- facilities provided 2 (continuation)
An administration and staff floor Entertainment floor Roof garden Basement parking
11
8/13/2019 Initial Presentation Group 3
12/37
Sketches of the 1 st design(lobby)- with the location of columns
12
8/13/2019 Initial Presentation Group 3
13/37
Sketches of the 1 st design(2 nd floor)- with the location of columns
13
8/13/2019 Initial Presentation Group 3
14/37
Sketches of the 1 st design(3 rd floor)- with the location of columns
14
8/13/2019 Initial Presentation Group 3
15/37
Sketches of the 1 st design(floor plan A)- with the location of columns
15
22 deluxe rooms4 junior suite5 Premier SuiteThere will be 6 typical floors of
this layout
8/13/2019 Initial Presentation Group 3
16/37
Sketches of the 1 st design(floor plan B)- with the location of columns
16
20 Junior Suite2 Premier Suite
2 typical floors
8/13/2019 Initial Presentation Group 3
17/37
Sketches of the 1 st design(floor plan C)- with the location of columns
17
16 Premier Suite
8/13/2019 Initial Presentation Group 3
18/37
Sketches of the 1 st design(floor plan D)- with the location of columns
18
10 Majestic suite2 Premier suite
8/13/2019 Initial Presentation Group 3
19/37
Sketches of 2 nd Design- with the location of columns 1
19
LobbyRestaurantLounge
Bar
2nd FloorSwimming PoolGymnasiumBallroom
8/13/2019 Initial Presentation Group 3
20/37
Sketches of 2 nd Design- with the location of columns 2 (continuation)
20
Type A LayoutDeluxe roomsMeeting rooms
4 typical floors
Type B LayoutPremier Suites5 typical floors
8/13/2019 Initial Presentation Group 3
21/37
Sketches of 2 nd Design- with the location of columns 3 (continuation)
21
Type C Layout12 Majestic Suites1 typical floors
8/13/2019 Initial Presentation Group 3
22/37
Artist Impression of Majestic Hotel
22
8/13/2019 Initial Presentation Group 3
23/37
Construction planning 1
23
8/13/2019 Initial Presentation Group 3
24/37
Construction planning 2
Provide an access road for the equipment route(traffic management on site)
Determine the site area and provide safetybarrier, warning signs Established an exact location of underground
services (electrical power, sewer pipes,telecommunications cables, etc.) before anyexcavation activity starts
Provide an area for stockpiling on site
24
8/13/2019 Initial Presentation Group 3
25/37
Construction planning- layout plan of the site
25
8/13/2019 Initial Presentation Group 3
26/37
Construction planning- recommended access route
26
8/13/2019 Initial Presentation Group 3
27/37
Construction of Basement
1) Diaphragm wall Reinforced concrete wall
Can be designed to take very high structural load2) Steel sheet pile
Consists of driven interlocked steel panels
Each pile is engaged with and driven in alongsidethe previous one thereby creating an imperviouswall
27
8/13/2019 Initial Presentation Group 3
28/37
Construction of Basement using Diaphragm wall(conceptual installation)
28
8/13/2019 Initial Presentation Group 3
29/37
Construction of Basement using steelsheet pile
29
8/13/2019 Initial Presentation Group 3
30/37
Reason for diaphragm wall asbasement construction method
30
1. Can carry vertical loads too compare with steel sheet pile2. Noise levels limited to engine noise only3. No vibration during installation4. Commonly used in congested areas.5. Can be installed in close proximity to existing structure6. Flexible system in plan layout7. Can be installed to considerable depth8. Easily incorporated into permanent works9. Economic and positive solution for large deep basement in
saturated and unstable soil profiles.
8/13/2019 Initial Presentation Group 3
31/37
Why not steel sheet pile wall?
Sections can rarely be used as part of the permanentstructure
Installation is difficult in soils with boulders or cobbles. Excavation shapes are dictated by the sheet pile section
and interlocking elements Sheet pile driving may cause neighbourhood
disturbance Settlements in adjacent properties may take place due
to installation vibrations
31
8/13/2019 Initial Presentation Group 3
32/37
Cost Estimation
32
8/13/2019 Initial Presentation Group 3
33/37
Environmental Assessment-the impact to the environment during construction phase
Destroy habitat and alter biodiversity. Prevent the growth of native plant species. Change in drainage patterns of the area. Create dust or air pollution. Generates noise pollution.
33
8/13/2019 Initial Presentation Group 3
34/37
Environmental Assessment-measures to control the impact to the environment 1
1. During site clearance Minimize the need for cutting of trees & damage to the native
vegetation. Phase out the site clearing process to only areas that need excavation
initially, this will reduce the dust emission from currently unusedareas.
Vegetate the unused area by growing temporary groundcover plantsor flower beds.
2. During construction of access road Frequent water sprinkling is required to reduce local dust emissions.
3. During excavation On windy days avoid excavation activities to reduce dust emissions Prevent the excavated soil from spilling out of the site boundaries on
to adjoining roads and properties.
34
8/13/2019 Initial Presentation Group 3
35/37
Environmental Assessment-measures to control the impact to the environment 2
4. During drainage works Provide a basic surface drainage system for the site to avoid
water runoff on to the surrounding properties and roads,especially during the monsoon months.
If during excavation, water accumulates in the excavated areas,then it should be pumped out and disposed of either in themunicipal storm water drain or into recharge soak pits of drybore wells.
5. During maintenance of vehicle
Construction vehicles should be properly maintained tominimize smoke in the exhaust emissions Prevent contamination of surface and ground water sources by
accidental spillages of oil and fuel.
35
8/13/2019 Initial Presentation Group 3
36/37
Environmental Assessment-measures to control the impact to the environment 3
6. During loading and unloading material Sweep and clean adjacent roads of the site that
get soiled due to the frequent movement of trucksto and fro from the site, at least once a day. Load and unload trucks on site and not on
surrounding roadside.
36
8/13/2019 Initial Presentation Group 3
37/37
Q/A SESSION
thank you
37
END OF PRESENTATION