Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Embed Size (px)

Citation preview

Page 1: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Information Technology Department

Bond Program Implementation Plan

January 22, 2013

1

West Contra Costa Unified School District

Page 2: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Agenda

• Project Selection Drivers• Fund Allocation and Schedule Determinants• Funding Need Schedule• Budget for 2013• Project Implementation Schedule

2

Page 3: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Project Selection Drivers

• Compliance• Instructional Technology• Infrastructure

3

Page 4: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Fund Allocation and Schedule Determinants

• Online Assessment compliance by 2014• Common Core requirements• Curriculum & Technology Integration• Digital Equity and Access

4

Page 5: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Funding Need Schedule

5

Year Amount ($M) Cumulative ($M)

2013 20 20

2015 8 28

2017 5 33

2019 2 35

Page 6: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Budget for 2013

6

* Requires legal vetting

Scheduled Technology Projects for the First Two (2) Years

Project Sites Projected Budget

Wireless All $ 6,775,000.00

Refresh of Student Desktop Computers All $ 800,000.00

Virtual Desktop Infrastructure (VDI) All $ 5,280,000.00

E-mail Archiving All $ 200,000.00

Professional Development * All $ 1,000,000.00

Cloud Initiative All $ 1,000,000.00

Educational Software All $ 600,000.00

Help Desk Management All $ 600,000.00

Single- Sign -On (Completion) All $ 250,000.00

Website Enhancements All $ 100,000.00

Resource Augmentation * All $ 580,000.00

Document SOP All $ 500,000.00

Relocate Data Center All $ 1,000,000.00

Upgrade Wiring to Fire Code Standards All $ 300,000.00

Project Management $ 1,015,000.00 Projected Total: $20,000,000.00

Page 7: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Project Implementation Schedule

7

No. Project Start End Duration

Days

1 Wireless 1/1/2013 7/31/2015 720.00

2 Help Desk Management 1/1/2013 7/31/2015 941.00

3 Single Sign-On 1/1/2013 8/1/2013 212.00

4 Document SOP 2/1/2013 7/31/2014 545.00

5 Refresh of Student Desktop Computers 2/1/2013 7/1/2013 150.00

6 Website Enhancements 2/1/2013 7/31/2015 910.00

7 Upgrade All Wiring to Fire Code Standards 3/1/2013 12/31/2013 305.00

8 Professional Development 8/1/2013 7/31/2015 729.00

9 Resource Augmentation 8/1/2013 7/31/2015 729.00

10 Relocate Data Center 8/1/2013 7/31/2015 729.00

11 Educational Software 9/1/2013 12/31/2014 486.00

12 Virtual Desktop Infrastructure (VDI) 1/1/2014 12/31/2014 360.00

13 Cloud Initiative 8/1/2014 7/31/2015 364.00

14 E-mail Archiving 8/1/2014 7/31/2015 364.00

Page 8: Information Technology Department Bond Program Implementation Plan January 22, 2013 1 West Contra Costa Unified School District

Thank You

8