4
update 0 Maddocks Information Communications & Technology Update MARCH 2011 Information Communications & Technology WHEN DIAMONDS AREN’T A CONTRACTOR’S BEST FRIEND In December 2010, the Technology and Construction Court in London handed down its decision in De Beers UK Limited (Formerly: The Diamond Trading Company Limited) and ATOS Origin IT Services UK Limited 2010 EWHC 3276 (TCC), in which De Beers was awarded substantial damages in the context of a failed IT project. The succinct and accessible judgment is commended to all IT project managers and lawyers. Many familiar themes emerge from it, as well as some salutary lessons – both for customers and suppliers. In this note we wanted to draw out some of the salient points from the customer’s point of view. BACKGROUND Following a competitive tender process and a round of Best and Final Offers (BAFO) De Beers UK Limited (formerly the Diamond Trading Company Limited) (De Beers) engaged the UK arm of an international IT outsourcing company, ATOS Origin IT Services UK Limited (ATOS) to design and deliver a major IT systems upgrade. The project was intended to deliver to De Beers streamlined diamond handling processes across its international operations. The project was an ambitious and complex undertaking which required the integration of business processes across a number of functionally independent and geographically dispersed business units. To deliver the system sought by De Beers was going to require an intimate knowledge of its business processes and practices. The complexity of the project appears to have been a factor in a previous failed attempt to deliver an integrated stock management system. Accenture was engaged to do this work but according to the judgment handed down by the court, 1 after three years this earlier project “was terminated without achieving most of its objectives”. 1 Paragraph 11 of the judgement. IN THIS ISSUE WHEN DIAMONDS AREN’T A CONTRACTOR’S BEST FRIEND It was a prudent strategy on the part of De Beers then, before moving to the full project contract in November 2007, to enter into a Letter of Intent with ATOS under which ATOS conducted a requirements analysis exercise between June and October 2007. The laudable intent of this exercise was to clarify De Beers’ business and process requirements, to enable ATOS to enter into a fixed price, fixed scope contract on an accurate basis. However as the court remarks, this turned out to be a flawed exercise which in no small part sowed the seeds for the failure of the project a little more than six months after contract signature, with ATOS staff downing tools and handing in their security passes at the end of the day on Friday 6 June 2008. What led to this drastic situation so soon? Disputes over scope change and performance ensued soon after contract signing and quickly escalated. In March 2008 De Beers withheld a significant milestone payment. Under the terms of the project agreement, De Beers was entitled to withhold payment of disputed amounts. ATOS responded quite aggressively to this state of affairs. It wrote to De Beers stating that its conduct in withholding the milestone payment amounted to repudiation. ATOS informed De Beers that it “accepted” the repudiation, bringing the contract to an end, paving (so it hoped) the way for a damages claim against De Beers. However the court disagreed. While it doubted the contractual right to withhold the entire milestone payment had in fact crystallised, the court found that in writing to De Beers in this manner ATOS had itself repudiated the agreement. De Beers was ultimately awarded approximately £1.4 million in damages. While this award is not insignificant, it was significantly less than the £8.7 million claimed by De Beers.

Information Communications & Technology

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Information Communications & Technology

update

0�  Maddocks Information Communications & Technology Update

MarCh 2011

Information Communications & Technology

W h e n d i a m o n d s a r e n ’ t a contractor’s best friend

In  December  2010,  the  Technology  and Construction Court in London handed down its decision in De Beers UK Limited (Formerly: The Diamond Trading Company Limited) and ATOS Origin IT Services UK Limited 2010 EWHC 3276 (TCC), in which De Beers was  awarded  substantial  damages  in  the context of a failed IT project.

The  succinct  and  accessible  judgment  is commended  to  all  IT  project  managers  and lawyers.  Many  familiar  themes  emerge  from it,  as  well  as  some  salutary  lessons  –  both for customers and suppliers.  In  this note we wanted to draw out some of the salient points from the customer’s point of view.

BaCkgroUnD

Following  a  competitive  tender  process  and a round of Best and Final offers (BAFO) De Beers Uk Limited (formerly the Diamond Trading Company Limited) (De Beers) engaged the Uk arm of an international IT outsourcing company, aToS origin IT Services Uk Limited (ATOS) to design and deliver a major IT systems upgrade. The project was intended to deliver to De Beers streamlined  diamond  handling  processes across its international operations.

The  project  was  an  ambitious  and  complex undertaking  which  required  the  integration of  business  processes  across  a  number  of functionally  independent  and  geographically dispersed business units. To deliver the system sought by De Beers was going to require an intimate knowledge of its business processes and practices.

The complexity of the project appears to have been  a  factor  in  a  previous  failed  attempt to  deliver  an  integrated  stock  management system.  accenture  was  engaged  to  do  this work but according  to  the  judgment handed down by the court,1  after three years this earlier project “was terminated without achieving most of its objectives”.

1 Paragraph 11 of the judgement.

in this issUeWhen DIaMonDS aren’T a ConTraCTor’S BeST FrIenD

–It  was  a  prudent  strategy  on  the  part  of  De Beers  then, before moving to  the  full project contract  in  november  2007,  to  enter  into  a Letter of Intent with aToS under which aToS conducted  a  requirements  analysis  exercise between June and october 2007. 

The laudable intent of this exercise was to clarify De Beers’ business and process requirements, to enable aToS to enter into a fixed price, fixed scope contract on an accurate basis.

however as the court remarks, this turned out to be a flawed exercise which in no small part sowed the seeds for the failure of the project a  little  more  than  six  months  after  contract signature, with aToS staff downing tools and handing in their security passes at the end of the day on Friday 6 June 2008.

What led to this drastic situation so soon?Disputes over scope change and performance ensued soon after contract signing and quickly escalated.  In March 2008 De Beers withheld a significant milestone payment. Under the terms of the project agreement, De Beers was entitled to withhold payment of disputed amounts. 

aToS  responded  quite  aggressively  to  this state  of  affairs.  It  wrote  to  De  Beers  stating that  its conduct  in withholding  the milestone payment  amounted  to  repudiation.  aToS informed  De  Beers  that  it  “accepted”  the repudiation, bringing  the contract  to an end, paving  (so  it  hoped)  the way  for a damages claim against De Beers. 

however the court disagreed. While it doubted the  contractual  right  to  withhold  the  entire milestone  payment  had  in  fact  crystallised, the court found that in writing to De Beers in this  manner  aToS  had  itself  repudiated  the agreement.

De Beers was ultimately awarded approximately £1.4 million in damages. While this award is not insignificant, it was significantly less than the £8.7 million claimed by De Beers.

Page 2: Information Communications & Technology

update

0�  Maddocks Information Communications & Technology Update

MarCh 2011

Information Communications & Technology

ProJeCT  ManageMenT  LeSSonS FroM ThIS CaSe

Managing Contract Change ProposalsMany  IT Project Managers will  have had  the experience  of  receiving  their  first  Contract Change  Proposal  (CCP)  almost,  it  seems, before the ink is dry on the contract signatures. In a fixed price, fixed scope contract, this can come as something of a shock. But CCP001 is likely to be the first of many. how should a project manager respond?

obviously every contract  is different. But the judgment in this case provides a very pithy and useful  analysis  of  the  question  of  when  and whether a contractor  is entitled  to additional payment for scope change.2 

The  provisions  of  the  contract  dealing  with contract change, as set out  in  the  judgment, were fairly typical. For this reason the court’s discussion of contract change contains some useful  principles  that  can  be  applied  more broadly to fixed price and scope contracts.

an expert witness called by aToS distinguished between changes in scope which are changes in “breadth”, and those which are changes in “depth”.

Changes in “breadth” were “true” changes in scope, introducing new functionality. Changes in “depth”, on the other hand, were changes adding  “scale  or  complexity”  but  without “extend(ing) functionality into whole new areas.” This  is  where  the  familiar  danger  of  “scope creep” manifests itself.

The  court  regarded  this  characterisation  as being  a  little  simplistic,  instead  preferring  to ask  whether  additional  work  was  required that  could  not  “fairly  be  said  to  fall  within” the contracted specifications. If this test was satisfied, the contractor would be entitled to a CCP and to additional payment for that work.

2  See  paragraphs  237  -  241  of  the judgement.

In  this  case  there  were  numerous  change requests  raised by aToS. De Beers did  not consent  to all of  them, and the court agreed that aToS was not  entitled  to be paid extra under change requests unless the work truly represented a change in scope.

aToS argued that  in respect of a number of change requests, it was entitled to be paid for extra work where the high level requirements phase  had  not  revealed  the  full  extent  of detailed work  required  to deliver a particular aspect of the project. 

The court disagreed. While there was reason to  believe  aToS  had  not  fully  appreciated the scope of work required as a result of the requirements phase, and De Beers may have been  aware  of  this,  the  court  observed  that aToS should have included a contingency in its price and delivery timetable to address any such uncertainties. The court also held that the risk that detailed requirements analysis would reveal a need for more work to be done, was a risk for aToS, not De Beers.

Lesson 1: Manage change requests carefully. Reject change requests that do not address a need for a change in scope as originally contracted.

Lesson 2: Consider whether to structure your project with a pre-contract requirements analysis phase.

Customer inputsThe court felt that both parties should accept some responsibility for the failure of the project. What is clear is that in a major IT project, where the contractor requires an intimate knowledge of  the  customer’s  business  to  deliver  the outcomes sought,  the customer simply must share the responsibility for making the project happen.

as noted at the outset, this was a relatively large, relatively  risky  implementation  where  aToS needed  to  undertake  an  extensive  business analysis exercise in order to design the system for delivery. For this process to be successful, aToS needed to have relatively open access to De Beers subject matter experts, and  the terms of the agreement reflected this. 

a factor  in  the failure of  this project appears to have been, at various times, the lack of De Beers staff to provide subject matter expertise, and also at times, the inability of De Beers to agree  and  communicate  requirements  and specifications. 

The provisions of the agreement dealing with this issue as reported in the judgment, placed a  significant  but  undefined  obligation  on  De Beers to provide assistance.3 

De  Beers  was  required,  for  example,  to “promptly  provide  ...  accurate  and  complete information  concerning  its  operations  and activities  ...  as  the  Supplier  may  reasonably require.”

This  might  sound  innocuous  enough  at  first glance. however many – and perhaps most – organisations simply will not have documented their business processes and practices to the extent where  these can  readily be  translated into system specifications. So once a project kicks off and the contractor starts asking for this information, the customer may suddenly find it does not have it on hand. What is to be done? either  the  customer  must  find  the  internal resources  to  prepare  this  documentation – probably without sufficient time to do the job properly - or the contractor must do the work. The contractor will not only want to be paid for this work, worse, it may also be tempted to point to this as a delay factor or as a factor otherwise excusing its non-performance.

We would recommend that as much definition as possible be given to customer obligations, by, for example:

avoiding  open-ended  obligations  such  as those described above;expressly  defining  “Customer  Inputs”  and setting them out in a Schedule; andexpressly  defining  what  human  resources the customer is to provide, at what levels, with what skills, and for how many hours or days during the project.

3 See paragraph 202 of the judgment. 

Page 3: Information Communications & Technology

update

0�  Maddocks Information Communications & Technology Update

MarCh 2011

Information Communications & Technology

one  excellent  article  on  this  case  suggests “reverse kPIs” – key performance indicators that  the  customer  signs  up  to,  to  provide some certainty around what is expected of the customer.4 

Ultimately this issue did not figure significantly in the damages claim, but as a general comment, in order for a complex implementation involving a  detailed  business  analysis/requirements gathering process  to succeed,  the customer must  ensure  that  relevant  resources  are available,  that  it  makes  decisions  in  a  timely manner when required to do so, and that it is able to satisfactorily define or communicate its requirements.

Lesson 3: If possible, avoid agreeing to ill-defined or open-ended requirements to provide inputs or assistance.

Lesson 4: Make sure you have adequate resources available to manage the implementation and the contractor’s performance, and to respond to requests for information or assistance.

Fixed fees, fixed scopeFixed  fee,   f i xed  scope  is  a  common enough  commercial  basis  for  complex  IT implementations. however such arrangements carry within them an inherent pressure. If the contractor embarks on  the project  and  finds that the job has been under-priced, they may seek to recover their position by raising change control  requests.  If  these  are  resisted,  the contractor may be faced with the unpalatable prospect of having to perform an uneconomic project. It may be better (financially) for them to abandon it than to continue.

4  See  Bierce  and  Jones,  “Failed  Software Development - De Beers Debacle”, available at http://www.outsourcing-law.com/tag/breach-of-contract/ 

Lesson 5: For a fixed price contract, ensure that your requirements have been sufficiently identified to enable the supplier to price appropriately.

Lesson 6: See Lesson 4.

Repudiation

It is trite law that a party evincing an intention not to be bound by a contract which it has entered into may be taken by the other party as having abandoned or repudiated the contract. In such circumstances the aggrieved party may elect to accept the other party’s repudiation, bringing the contract to an end and (more than likely) giving rise to an entitlement to damages.

This beguilingly simple principle needs to be handled  with  caution  however,  as  this  case demonstrates.

as noted at the outset, aToS became repudiator rather than repudiatee because the court found that De Beers had not  in  fact done anything that amounted to repudiation. aToS therefore exposed itself to a claim for damages.

This  in  fact  may  have  ultimately  played  to aToS’s  advantage.  The  court  observed  that the amount of damages awarded by it may well have been “less than the additional costs that aToS would have incurred if it had continued to perform the Contract to completion”.�

This was due in no small part to a mysterious issue that could not be disclosed - even to the court - referred to cryptically in the judgement as  the  “blank”  issue. Because of  the  “blank” issue, the court could not find that De Beers intended  to  procure  a  replacement  system, meaning  that  the  court  could  not  award  a substantial  component  of  damages  claimed by  De  Beers.  Were  it  not  for  this  issue,  the damages  award  may  have  been  significantly higher.

� See paragraph 380 of the judgment.

This  illustrates that the  international diamond trade is a mysterious and intriguing business, but  more  relevant  to  this  article,  it  suggests that  repudiation  can  be  a  dangerous  and indiscriminate weapon, and should be treated with caution, by customer and supplier alike.

Lesson 7: Consider your position carefully before suspending or withholding payment.

Lesson 8: Be very sure of your position if you want to allege repudiation.

Lesson 9: Don’t do anything that puts you in the position of repudiating the agreement – unless you are very sure that is your strategy.

Lesson 10: Seek legal advice.

author: Sean Field, Senior associate

Page 4: Information Communications & Technology

0�  Maddocks Information Communications & Technology Update

The material contained in this Update is of the nature of general comment only. No reader should rely on it without seeking legal advice. If you do not wish to receive further Updates from us, please email [email protected].

maddocks Lawyers Angel Place140 William Street 123 Pitt Street Melbourne Victoria 3000 Sydney New South Wales 2000 Australia AustraliaTelephone 61 3 9288 0555 Telephone 61 2 8223 4100Facsimile 61 3 9288 0666 Facsimile 61 2 9221 0872

Email [email protected] www.maddocks.com.au

affiliated officesAdelaide, Auckland, Beijing, Brisbane, Colombo, Dubai, Hong Kong, Jakarta, Kuala Lumpur, Manila, Mumbai, New Delhi, Perth, Singapore, Tianjin

0�  Maddocks Information Communications & Technology Update

brendan coadyPartner61 2 922� 62�[email protected]

Peter francisPartner61 3 9288 [email protected]

robert GregoryPartner61 3 9240 [email protected]

Kevin PhelanPartner61 3 9288 0�8�[email protected]

James smartPartner61 3 9288 0632 [email protected]

maddocKs information, commUnications & technoloGy GroUPFor further information regarding any of the articles in this Update, please contact a member of our team below:

michelle burridgeSenior associate61 3 9288 0�[email protected]

sean fieldSenior associate61 3 861� 0397 [email protected]

Jeff GoodallSenior associate61 2 922� [email protected]

andrew WhitesideSenior associate61 3 861� 03�[email protected]

sonia sharmaassociate61 2 8223 [email protected]