    PROJE T REPORT

    ON

    INDUSTRIAL VISIT AT WANAKBORI (T.P.S)

    Submitted in accordance with the INDUSTRIAL VI SIT r equirements for

    5thsemester of the BE cour se

    I n the branch of

    ELECTRICAL ENGINEERING

    Of

    GUJARAT TECHNOLOGICAL UNIVERSITY

    YEAR 2013

    Submitted By:-

    Mr. D.A.DIVRANIA

    Mr. B.G.RADADIA

  • 8/10/2019 Industrial Visit Electrical TPS

    2/20

    W.T.P.S

    Page 2

    ACKNOWLEDGEMENT

    We are gladly thankful to our Principal Dr. H. M. Nimbark, H.O.D Mr. Rahul A. Parmar and our

    staff members who give us a great guidance regarding training and instruct us the importance of training

    in electrical field. So we decided to take visit in thermal power plant which is situated at Wanakbori.

    We are especially thankful to respected chief engineer. Thermal power station, Wanakbori

    because we granted us permission for taking visit in wonderful campus.

  • 8/10/2019 Industrial Visit Electrical TPS

    3/20

    W.T.P.S

    Page 3

    INDEX

    1 Introduction (5)

    2 Purpose of Visit (6)

    3 Block diagram of power plant (6)

    4 Working Power Plant Models (9)

    5 Future (10)

    6 Equipments Details (11)

    7 Switch Yard (12)

    8 Other Details (16)

    9 Control Room (17)

    10 Conclusion (18)

  • 8/10/2019 Industrial Visit Electrical TPS

    4/20

    W.T.P.S

    Page 4

    INTRODUCTION:-

    W.T.P.S is the biggest power plant in GUJARAT .

    Wanakbori Thermal Power Stationis acoal-fired power station inGujarat,India. It is located on

    the bank ofMahiriver inKhedadistrict.

    There are 7 Turbo Generator sets each of 210MW out of which first 3 units are equipped with

    Russian Turbines and other 4 Units are equipped with German Turbines. Unit no 7 is entirely

    Computerised and well advanced. All the above units are of BHEL make.

    Unit Number Installed Capacity (MW) Date of Commissioning Status

    Stage I 1 210 March 1982 Running

    Stage I 2 210 January, 1983 Running

    Stage I 3 210 March, 1984 Running

    Stage I 4 210 March, 1986 Running

    Stage I 5 210 September 1986 Running

    Stage I 6 210 November 1987 Running

    Stage II 7 210 December 1998 Running

    http://en.wikipedia.org/wiki/Coalhttp://en.wikipedia.org/wiki/Coalhttp://en.wikipedia.org/wiki/Coalhttp://en.wikipedia.org/wiki/Gujarathttp://en.wikipedia.org/wiki/Gujarathttp://en.wikipedia.org/wiki/Gujarathttp://en.wikipedia.org/wiki/Mahihttp://en.wikipedia.org/wiki/Mahihttp://en.wikipedia.org/wiki/Mahihttp://en.wikipedia.org/wiki/Khedahttp://en.wikipedia.org/wiki/Khedahttp://en.wikipedia.org/wiki/Khedahttp://en.wikipedia.org/wiki/Watt#Megawatthttp://en.wikipedia.org/wiki/Watt#Megawatthttp://en.wikipedia.org/wiki/Watt#Megawatthttp://en.wikipedia.org/wiki/Watt#Megawatthttp://en.wikipedia.org/wiki/Khedahttp://en.wikipedia.org/wiki/Mahihttp://en.wikipedia.org/wiki/Gujarathttp://en.wikipedia.org/wiki/Coal
  • 8/10/2019 Industrial Visit Electrical TPS

    5/20

    W.T.P.S

    Page 5

    PURPOSE OF VISIT:-

    Electrical Engineering Dept. of OM Engineering College, Junagadh decided to arrange one dayindustrial visit for 5th Electrical Engineering students to improve practical knowledge and get benefitedtheir theoretical knowledge

    In W.T.P.S, Students will get benefit regarding their theoretical subject of conventional powerengineering, Electrical Power and Electrical & Electronic Measurement

    BLOCK DIAGRAM OF POWER PLANT:-

    Coal to Electricity Process

  • 8/10/2019 Industrial Visit Electrical TPS

    6/20

    W.T.P.S

    Page 6

    Energy Balance

  • 8/10/2019 Industrial Visit Electrical TPS

    7/20

    W.T.P.S

    Page 7

    Feed Water & Steam Flow Diagram:-

  • 8/10/2019 Industrial Visit Electrical TPS

    8/20

    W.T.P.S

    Page 8

    WORKING POWER PLANT MODELS:-

    Generator, Generator Transformer

    Turbine

    Boiler, Boiler Drum

    Boiler Burners, Dampers arrangement

    Boiler Feed Pump

    Air Pre-heater

    ID Fan, FD Fan, PA Fan

    Coal Mill

    FW Pump

  • 8/10/2019 Industrial Visit Electrical TPS

    9/20

    W.T.P.S

    Page 9

    FEATURES:-

    Installed Capacity : 7 210 = 1470 MW

    Total Area of Project : 1571 Acres

    PLF % : Between 84.64 to 91.24%

    Plant Area : 626.2 ha

    Ash Dump Area : 215.7 ha

    Cooling Water Quantity Required : From

    Canal of Mahi River Reservoir 60 to 70 Cusecs / month

    Cooling Tower Heights :

    Stage I & II112 Mtrs, Stage III118 Mtrs.

  • 8/10/2019 Industrial Visit Electrical TPS

    10/20

    W.T.P.S

    Page 10

    EQUIPMENT DETAILS:-

    Fuel Details:-

    Fuel: Bituminous Coal

    Linked Coal Mines : Coal India

    From Bihar, Orissa, M.P., West Bengal, Andhra Pradesh

    Generally 400 Wagons [ 07 Racks ] received per day

    Record of Unloading Wagons : 650 Wagons / Day

    Gross Calorific Value of Coal : 4400 Kcal/Kg

    Nos of Wagon Tipplers: 05 NOS.

    Coal Quantity Required :

    With Design Coal : 16000 MT / Day

    With Actual Coal: 18000 MT / Day

    Stock Yard: Storage Capacity: 02 Lacks MT (Approx.)

    Area : 48000 m2

    Oil : LSHS / LDO

  • 8/10/2019 Industrial Visit Electrical TPS

    11/20

    W.T.P.S

    Page 11

    Boiler Details:-

    Stage I & II : Tangentially Fired, Balance Draft,

    Natural Circulation, Radiant Reheat Type

    Stage III : Vertically Suspended Water Tubes,

    Radiant Reheat Cycle, Natural Circulation

    Capacity : 700 Tones / hr / unit

    Feed Water Temp. : 241 C

    Steam Pressures at Boiler Outlets :

    [1] SH: 137 Kg / Cm2

    [2] RH: 25.8 Kg / Cm2

  • 8/10/2019 Industrial Visit Electrical TPS

    12/20

    W.T.P.S

    Page 12

    Turbine Details:-

    Type: Three Cylinders Condensing Tandem,

    Compound Horizontal Reheat Type.

    Makes: LMW (Russian), KWU (German). Nos. of Stages:

    1. Stage I: HP12, IP -11,

    LPDouble Flow each having 4 stages.

    2. Stage II: HP25,

    IPDouble Flow each having 20 stages,

    LPDouble Flow each having 4 stages

    Generator Details:-

    Type: THW - 2102B (Water & Hydrogen Cooled Turbo Generator)

    Rated Capacity: 210 MW, 247 MVA

    Power Factor: 0.85 Lag

    Stator: 15.75 Volts, 9050 A

    Rotor: 310 V DC, 2600 A

    Excitation System: Static

    Type of Cooling: Water, Hydrogen

    Hydrogen Pressure: 3.5 Kg / Cm2

  • 8/10/2019 Industrial Visit Electrical TPS

    13/20

    W.T.P.S

    Page 13

    Transformers Details:-

    Generator Transformer:

    Stage I: 250 MVA, 15.75 / 220KV

    Stage II: 250 MVA, 15.75/400KV

    Interconnection Transformer: 500 MVA (167 x 4, 3+1 St by), 220 / 400 KV

    Station Transformers: 25 MVA, 220 / 07 KV

    Unit Auxiliary Transformers: 15 MVA, 15.75 / 07 KV

    Unit Service Transformers: 07 KV / 433 Volts

    Station Service Transformers: 02 MVA, 07 KV / 433 Volts

  • 8/10/2019 Industrial Visit Electrical TPS

    14/20

    W.T.P.S

    Page 14

    SWITCH YARD:-

    The control room, in case of remote control, houses all the necessary measuring instruments for eachpanel or alternator and feeder, synchronizing gear, protective gear, automatic voltage regulator,

    communication arrangement etc

    Switch Yard.

    The switchyard houses transformers, circuit breaker sand switches for connecting and disconnecting thetransformers and circuit breakers. It also has lightning arrestors for the protection of the power station

    against lighting strokes.

  • 8/10/2019 Industrial Visit Electrical TPS

    15/20

    W.T.P.S

    Page 15

    OTHER DETAILS:-

    D.M.Water Requirement:

    35 M3/hr/Unit

    Ash Evacuation:

    Fly AshDry Wet/Vacuum

    Bottom AshMechanical

  • 8/10/2019 Industrial Visit Electrical TPS

    16/20

    W.T.P.S

    Page 16

    CONTROL ROOM:-

    Types of Control Panel

    Fuel Gas Panel

    Combustion Air Panel

    Primary Air & Coal Panel

    Steam Panel(Boiler)

    Feed Water panel

    Condensate & Cooling Water Panel

    Turbovisory Panel

  • 8/10/2019 Industrial Visit Electrical TPS

    17/20

    W.T.P.S

    Page 17

    CONCLUSION:-

    After visit at the Wanakbori Thermal Power Station I can say that one can visualize the complex

    study of power generation using coal as a fuel, which will help me a lot in future in many field & I can

    understand the function of each component in thermal power station, their importance, their arrangement

    & precautions that to be used for the safety in the plant.

    At last I will only say that I really enjoyed my visit over here and I again want to thank all my

    faculties, staff of Wanakbori Thermal Power Station to give me this great pleasure of the training.

  • 8/10/2019 Industrial Visit Electrical TPS

    18/20

    W.T.P.S

    Page 18

  • 8/10/2019 Industrial Visit Electrical TPS

    19/20

    W.T.P.S

    Page 19

  • 8/10/2019 Industrial Visit Electrical TPS

    20/20

    W.T.P.S

    Page 20

    Thank you