WaterAid Tanzania Policy Programme Strengthening Design, Finance and Delivery of Water Supply and Sanitation Programmes under PRSPs February 2004 Kampala. The PRS and Water. Indicator: Proportion of households with access to safe drinking water (in rural and urban areas). Target: - PowerPoint PPT Presentation
Citation preview
WaterAid Tanzania Policy Programme
Strengthening Design, Finance and Delivery of
Water Supply and Sanitation Programmes under PRSPs
February 2004Kampala
Indicator:Proportion of households with access to safe drinking water (in rural and urban areas).
Target:Raise the proportion of the rural population that has access to safe and clean water from 48.5 percent in 2000 to 55 percent in 2003.
Initiative:Rehabilitation of malfunctioning water supply schemes, protection of water sources, and some expansion of new schemes (to be determined by local communities);
The PRS and Water
There are no explicit references to :
1. Affordability
2. Time or distance to source
3. Sanitation indicators or targets
4. Water resources and water for livelihoods
The PRS and Water - Some limitations
Public spending on water
and sanitation
Livelihood outcomes
Analysing policy implementation
Composition of spending
Public provision of
services
Total consumption of
servicesBudget
Analysis
Benefit Incidence
Public Expenditure
Review
Expenditure Tracking
Detailed impact studies
Composition of service
providers
Percentage of rural households using improved water sources
Regional variation in access to improved Regional variation in access to improved water sourceswater sources
0
20
40
60
80
100
120
2000/1 2001/2 2002/3 2003/4 2004/5 2005/6
Tanzanian Shillings (billions)
Development Donor
Development GoT
Recurrent Local Councils
Recurrent OC - MoW
Recurrent PE - MoW
Expenditure on water - actual and planned
Development Expenditure: Actual, Approved and Planned (2000/01 - 2002/03)
Item Project Name 2000/2001 2001/2002 2002/2003 L/G Donor
Total Dev. Local Foreign Total Dev Local Foreign Total Dev Local Foreign
3228 Training on Specialized Skills
18,000,000 18,000,000 0 19,517,000 19,517,000 0 19,517,000 19,517,000 0
3267 Water Sector Coordination & Monitoring
116,500,000 111,500,000 5,000,000 0 0 0 246,319,500 163,902,000 82,417,500 G UNICEF
3378 Design and Studies 1,029,000,000 279,000,000 750,000,000 777,356,000 252,356,000 525,000,000 187,556,000 187,556,000 0 L ADB
2310 Nile River basin Initiative (NRBI)
20,000,000 20,000,000 0 21,687,000 21,687,000 0 23,687,000 23,687,000 0
4981 River Basin Mang. And Small Irrigation
2,310,000,000 210,000,000 2,100,000,000 227,709,000 227,709,000 0 995,664,600 220,709,000 774,955,600 L W/B
3211 L. Victoria Environ. Manag. Project
1,896,500,000 46,500,000 1,850,000,000 50,421,000 50,421,000 0 35,421,000 35,421,000 0 L W/B
3280 Rural Water Supply and Sanitation Project
1,615,000,000 50,000,000 1,565,000,000 54,216,000 54,216,000 0 2,235,000,000 75,000,000 2,160,000,000 L IDA
3307 Construction of Urbarn Water Supply
0 - 0 5,827,166,000 272,166,000 5,555,000,000 115,040,000 115,040,000 0 L IDA
4931 L. Victoria Shinyanga Kahama
0 0 0 - 0 0 390,000,000 390,000,000 0
5450 Constr & Rehab. Of Sewerage Systems
0 0 0 1,152,082,000 264,082,000 888,000,000 2,653,793,800 160,082,000 2,493,711,800 G EU
4980 Management of Country Water Basins
7,000 7,000 0 150,962,000 70,481,000 80,481,000 80,481,000 80,481,000 0
3223 Borehole Drilling and dam Construction
390,000,000 390,000,000 0 422,889,000 422,889,000 0 379,766,000 379,766,000 0
FRG
NETHER
CHINA
ADF
JAP
FRANCE
FRANCE
ADF
IDA
FRG
CHINA
EU
FRANCE
4359 Water Resources Institute
45,000,000 45,000,000 0 48,795,000 48,795,000 0 41,795,000 41,795,000 0
3204 Rehabilitation of Earth Moving Equip.
180,000,000 180,000,000 0 195,179,000 195,179,000 0 165,000,000 165,000,000 0
18,854,007,000 2,334,007,000 16,520,000,000 14,414,964,000 2,966,483,000 11,448,481,000 41,400,687,600 3,164,256,000 38,236,431,600
Source: Kitabu cha Nne Makadirio ya Fedha za Serikali Mipango ya Maendeleo (Wizara na Mikoa) June 2003
Total Expenditure Water Sector
Actual Expenditure
20,351,588,100 154,300,0003306 Urbarn Water Supply Rehabilitation
8,470,000,000 420,000,000
5,339,096,100 511000000
G8,050,000,000 4,855,419,000 455,419,000 4,400,000,000
91,084,000 91,084,000 0
20,197,288,100
205,000,000 5,715,772,000 G
3261 DAWASA 2,284,000,000 84,000,000 4,828,096,100 L2,200,000,000
G
3216 Expansion of Rural Water Supply
276,000,000 276,000,000 0 299,275,000 299,275,000 0 5,920,772,000
3252 Rehabilitation of Rural Water Supply
204,000,000 204,000,000
Approved Expenditure Estimates
0 221,207,000 221,207,000 0 2,220,190,500 236,000,000 1,984,190,500
Development Expenditure: Actual, Approved and Planned (2000/01 - 2002/03)
Item Project Name 2000/2001 2001/2002 2002/2003 L/G Donor
Total Dev. Local Foreign Total Dev Local Foreign Total Dev Local Foreign
3228 Training on Specialized Skills
18,000,000 18,000,000 0 19,517,000 19,517,000 0 19,517,000 19,517,000 0
3267 Water Sector Coordination & Monitoring
116,500,000 111,500,000 5,000,000 0 0 0 246,319,500 163,902,000 82,417,500 G UNICEF
3378 Design and Studies 1,029,000,000 279,000,000 750,000,000 777,356,000 252,356,000 525,000,000 187,556,000 187,556,000 0 L ADB
2310 Nile River basin Initiative (NRBI)
20,000,000 20,000,000 0 21,687,000 21,687,000 0 23,687,000 23,687,000 0
4981 River Basin Mang. And Small Irrigation
2,310,000,000 210,000,000 2,100,000,000 227,709,000 227,709,000 0 995,664,600 220,709,000 774,955,600 L W/B
3211 L. Victoria Environ. Manag. Project
1,896,500,000 46,500,000 1,850,000,000 50,421,000 50,421,000 0 35,421,000 35,421,000 0 L W/B
3280 Rural Water Supply and Sanitation Project
1,615,000,000 50,000,000 1,565,000,000 54,216,000 54,216,000 0 2,235,000,000 75,000,000 2,160,000,000 L IDA
3307 Construction of Urbarn Water Supply
0 - 0 5,827,166,000 272,166,000 5,555,000,000 115,040,000 115,040,000 0 L IDA
4931 L. Victoria Shinyanga Kahama
0 0 0 - 0 0 390,000,000 390,000,000 0
5450 Constr & Rehab. Of Sewerage Systems
0 0 0 1,152,082,000 264,082,000 888,000,000 2,653,793,800 160,082,000 2,493,711,800 G EU
4980 Management of Country Water Basins
7,000 7,000 0 150,962,000 70,481,000 80,481,000 80,481,000 80,481,000 0
3223 Borehole Drilling and dam Construction
390,000,000 390,000,000 0 422,889,000 422,889,000 0 379,766,000 379,766,000 0
FRG
NETHER
CHINA
ADF
JAP
FRANCE
FRANCE
ADF
IDA
FRG
CHINA
EU
FRANCE
4359 Water Resources Institute
45,000,000 45,000,000 0 48,795,000 48,795,000 0 41,795,000 41,795,000 0
3204 Rehabilitation of Earth Moving Equip.
180,000,000 180,000,000 0 195,179,000 195,179,000 0 165,000,000 165,000,000 0
18,854,007,000 2,334,007,000 16,520,000,000 14,414,964,000 2,966,483,000 11,448,481,000 41,400,687,600 3,164,256,000 38,236,431,600
Source: Kitabu cha Nne Makadirio ya Fedha za Serikali Mipango ya Maendeleo (Wizara na Mikoa) June 2003
Total Expenditure Water Sector
Actual Expenditure
20,351,588,100 154,300,0003306 Urbarn Water Supply Rehabilitation
8,470,000,000 420,000,000
5,339,096,100 511000000
G8,050,000,000 4,855,419,000 455,419,000 4,400,000,000
91,084,000 91,084,000 0
20,197,288,100
205,000,000 5,715,772,000 G
3261 DAWASA 2,284,000,000 84,000,000 4,828,096,100 L2,200,000,000
G
3216 Expansion of Rural Water Supply
276,000,000 276,000,000 0 299,275,000 299,275,000 0 5,920,772,000
3252 Rehabilitation of Rural Water Supply
204,000,000 204,000,000
Approved Expenditure Estimates
0 221,207,000 221,207,000 0 2,220,190,500 236,000,000 1,984,190,500
23.7
24.2
26.3
31.2
36.1
17.7
18.5
17.0
19.0
15.9
58.5
56.4
56.1
49.2
45.8
0.1
0.9
0.5
0.7
2.1
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0
1
2
3
4
5
Quintile
Proportion by type of sourcePiped Other protected Unprotected Other
Lowerincome
Higherincome
Household use of water source by expenditure quintile for rural Tanzania
• Anything with a tap was ‘piped’
• Household sizes larger for poorer quintiles
• Wealthier quintiles buy more water so unit subsidy greater
• Piped investments 10 times that of protected investments
Equity and subsidies Piped and Protected Water Supplies
Per capita investment costs by investment typeName of the Project All Piped Mainly Piped Piped and
ProtectedMainly
protectedAll protected
Health through Sanitation and Water Project (HESAWA -SIDA) 6,084 Rural Water Supply Project in Iringa, Ruvuma andMbeya Regions, Tanzania (DANIDA) 62,690 Hai District Water Supply Project III (GTZ/KfW)
143,636 Rural Water Supply East Kilimanjairo Ph. I (GTZ/KFW)
48,333 Monduli District Water supply (ADB)
217,466 Kilosa, Mpwapwa, Morogoro Rural, Kongwa and Rufiji(ADF) 40,000 Dodama, Manyara, Tabora, Singida, DSM (WaterAid)
18,924 Chalinze (China)
140,952 Rural water Supply Singida rural, Hanang, Manyoni andIgunga 2002 (JICA) 143,942 Rural Water Supply and Sanitation Project - Mpwapwa(IDA) 36,933
Average per capita investment by category 118,077 103,316 27,929 6,084
Kilimanjaro 60/15
Kigoma 41/13
Dodoma 54/6
Coast 10/13
Mara 13/17
Lindi 8/3
Tanga 16/25
Tabora 9/4Kagera 8/21
Shinyanga 22/15
Mwanza 20/25
Mtwara 10/34
Arusha 35/13
Iringa 44/7
Ruvuma 36/10
Morogoro 27/35Mbeya 50/16
Singida 31/28
Rukwa 36/12
0
500
1000
1500
2000
2500
3000
3500
4000
0 20 40 60 80 100
% of households using improved water sources
Estimated rehabilitation costs
(Tsh millions)
Estimated regional rehabilitation costs against regional coverage (piped + protected)
203/04 2004/05 2005/06 2006/07
Budget RQ CeilingCeiling as
Percent of RQ RQProposed Allocation RQ
Proposed Allocation
District Level: Rehabilitation of rural water supply schemes 17,130.00 17,130.00 100% 17,986.50 17,986.50 18,885.80 18,885.80 Expansion of rural water supply schemes 10,520.00 10,520.00 100% 11,046.00 11,046.00 11,598.30 11,598.30 Construction of new rural water supply schemes 18,510.00 18,510.00 100% 19,435.50 19,435.50 20,407.30 20,407.30 Promotion of rain water harvesting 750 750 100% 787.5 787.5 826.9 826.9 Promotion of sanitation in rural areas 672 672 100% 705.6 705.6 740.9 740.9 Protection of water sources 741.6 741.6 100% 216.3 216.3 227.1 227.1 Capacity building 1,678.50 1,678.50 100% 1,791.80 1,791.80 1,881.40 1,881.40 Gender mainstreaming & good governance 791 395.5 50% 830.6 415.3 872.1 436 General Administration, retooling & rehab. 3,347.50 1,673.80 50% 5,948.30 5,948.30 6,245.70 6,245.70 Total of Districts Level 54,140.60 52,071.40 96% 58,748.00 58,332.80 61,685.40 61,249.40
Ministerial Level: Rehabilitation of national rural water supply schemes 546.6 546.6 100% 573.9 134.8 602.6 51 Rehabilitation of urban water supply schemes 11,595.00 4,505.00 39% 27,724.30 6,510.20 142,568.00 12,074.40 Promotion of rain water harvesting technology 750 291.4 39% 787.5 184.9 826.9 70 Strengthening of borehole drilling & dam construction 1,725.00 670.2 39% 1,811.30 425.3 1,901.80 161.1 Expand urban water supply system 2,890.20 1,122.90 39% 3,034.70 712.6 3,186.40 269.9 Constructions of new urban water supply systems 1,400.00 543.9 39% 2,272.50 533.6 2,358.10 199.7 Lake Victoria -Kahama & Shnyanga water supply 29,025.00 11,277.10 39% 25,026.30 5,876.70 20,027.60 1,696.20 Strengthening Water resources management 2,732.20 1,061.60 39% 2,868.80 673.7 3,012.30 255.1 Rehabilitation and expansion of sewerage facilities 16,166.00 6,281.00 39% 21,349.80 5,013.40 27,272.30 2,309.80 Protection of water sources 492.4 191.3 39% 646.8 151.9 679.1 57.5 Water quality management 1,224.30 475.7 39% 1,285.60 301.9 1,349.80 114.3
Policy & regulatory framework 850 330.3 39% 955.5 224.4 1,003.30 85 Staff capacity building 2,155.10 837.3 39% 2,262.90 531.4 2,376.00 201.2 Gender mainstreaming & good governance 432 167.8 39% 453.6 106.5 476.3 40.3 General Administration, retooling & rehab. 495 192.3 39% 519.8 122 545.7 46.2 Water sector information 230 89.4 39% 241.5 56.7 253.6 21.5 Total of Ministerial Level: 72,708.90 28,583.90 39% 91,814.60 21,559.90 208,439.80 17,653.30Grand Total 126,849.50 80,655.20 64% 150,562.60 79,892.70 270,125.30 78,902.60
Total Resources 66,495.90 126,849.50 87,749.50 69% 150,562.60 84,871.50 270,125.30 83,303.60 o/w Total Recurrent 18,102.90 20,634.40 21,145.40 21,440.10 Personnel Emoluments 5,325.00 5,540.20 5,761.80 5,901.20 Other Charges 12,777.90 15,094.20 15,383.60 15,538.90 Total Development 48,393.00 67,115.20 63,726.20 61,863.40 Local 6,487.40 6,487.40 6,508.50 7,237.50 Foreign 41,905.60 60,627.80 57,217.60 54,625.90
GRAND TOTAL 66,495.90 126,849.50 87,749.50 69% 150,562.60 84,871.50 270,125.30 83,303.60
Budget Guidelines for Water Sector 2004/5
203/04 2004/05 2005/06 2006/07
Budget RQ CeilingCeiling as
Percent of RQ RQProposed Allocation RQ
Proposed Allocation
District Level: Rehabilitation of rural water supply schemes 17,130.00 17,130.00 100% 17,986.50 17,986.50 18,885.80 18,885.80 Expansion of rural water supply schemes 10,520.00 10,520.00 100% 11,046.00 11,046.00 11,598.30 11,598.30 Construction of new rural water supply schemes 18,510.00 18,510.00 100% 19,435.50 19,435.50 20,407.30 20,407.30 Promotion of rain water harvesting 750 750 100% 787.5 787.5 826.9 826.9 Promotion of sanitation in rural areas 672 672 100% 705.6 705.6 740.9 740.9 Protection of water sources 741.6 741.6 100% 216.3 216.3 227.1 227.1 Capacity building 1,678.50 1,678.50 100% 1,791.80 1,791.80 1,881.40 1,881.40 Gender mainstreaming & good governance 791 395.5 50% 830.6 415.3 872.1 436 General Administration, retooling & rehab. 3,347.50 1,673.80 50% 5,948.30 5,948.30 6,245.70 6,245.70 Total of Districts Level 54,140.60 52,071.40 96% 58,748.00 58,332.80 61,685.40 61,249.40
Ministerial Level: Rehabilitation of national rural water supply schemes 546.6 546.6 100% 573.9 134.8 602.6 51 Rehabilitation of urban water supply schemes 11,595.00 4,505.00 39% 27,724.30 6,510.20 142,568.00 12,074.40 Promotion of rain water harvesting technology 750 291.4 39% 787.5 184.9 826.9 70 Strengthening of borehole drilling & dam construction 1,725.00 670.2 39% 1,811.30 425.3 1,901.80 161.1 Expand urban water supply system 2,890.20 1,122.90 39% 3,034.70 712.6 3,186.40 269.9 Constructions of new urban water supply systems 1,400.00 543.9 39% 2,272.50 533.6 2,358.10 199.7 Lake Victoria -Kahama & Shnyanga water supply 29,025.00 11,277.10 39% 25,026.30 5,876.70 20,027.60 1,696.20 Strengthening Water resources management 2,732.20 1,061.60 39% 2,868.80 673.7 3,012.30 255.1 Rehabilitation and expansion of sewerage facilities 16,166.00 6,281.00 39% 21,349.80 5,013.40 27,272.30 2,309.80 Protection of water sources 492.4 191.3 39% 646.8 151.9 679.1 57.5 Water quality management 1,224.30 475.7 39% 1,285.60 301.9 1,349.80 114.3
Policy & regulatory framework 850 330.3 39% 955.5 224.4 1,003.30 85 Staff capacity building 2,155.10 837.3 39% 2,262.90 531.4 2,376.00 201.2 Gender mainstreaming & good governance 432 167.8 39% 453.6 106.5 476.3 40.3 General Administration, retooling & rehab. 495 192.3 39% 519.8 122 545.7 46.2 Water sector information 230 89.4 39% 241.5 56.7 253.6 21.5 Total of Ministerial Level: 72,708.90 28,583.90 39% 91,814.60 21,559.90 208,439.80 17,653.30Grand Total 126,849.50 80,655.20 64% 150,562.60 79,892.70 270,125.30 78,902.60
Total Resources 66,495.90 126,849.50 87,749.50 69% 150,562.60 84,871.50 270,125.30 83,303.60 o/w Total Recurrent 18,102.90 20,634.40 21,145.40 21,440.10 Personnel Emoluments 5,325.00 5,540.20 5,761.80 5,901.20 Other Charges 12,777.90 15,094.20 15,383.60 15,538.90 Total Development 48,393.00 67,115.20 63,726.20 61,863.40 Local 6,487.40 6,487.40 6,508.50 7,237.50 Foreign 41,905.60 60,627.80 57,217.60 54,625.90
GRAND TOTAL 66,495.90 126,849.50 87,749.50 69% 150,562.60 84,871.50 270,125.30 83,303.60
Budget Guidelines for Water Sector 2004/5
Restructuring of Input to Budget Guidelines - District water transfers
Increase in rural water supply allocations
Budget Guidelines 2004/5
2003/4
allocation Tsh
2004/5
allocation Tsh
Rural 17.3 bn 52.5 bn
Urban 21.3 bn 23.0 bn
Implementation Capacity?
Budget Guidelines 2004/5…
Pro-Poor Targeting - Piped versus protected investments?
Sanitation
Contentious sub-votes - Lake victoria, DDCA, Other Charges
Comparing across sectorsThe 31% rise in overall ceiling for the water sector is matched by the following rises in other priority sectors; Education +10%, Health +35%, Judiciary +7%, Agriculture +25%, Roads +25%, HIV/AIDS +100%
Foreign flexibility?
Time spent fetching water Time spent fetching water (to go, wait, collect and return home -(to go, wait, collect and return home - not necessarily dry season
source)
From the National Water Policy:The new strategy, in conformity with ongoing reforms in the public sector, is for Government to change its role from being implementer to a regulator, facilitator and coordinator.
Building Blocks
From the PRSP:Reform of the public sector (including central and local Government), being supported under PRGF, PSAC-I, Public Service Reform Programme (PSRC) and by other initiatives supported by international partners