Page 1: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EASTSALT LAKE CITY, UT

Presented to University of Utah Department of Campus Design and Construction by:

Student Engineering Associates

January 28, 2014

Page 2: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Courtesy of SEA

Page 3: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

PROJECT MANAGEMENT TEAMKatharine Smith

Page 4: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

• Leadership Experience in Student Organizations• Experienced in Microsoft Project and Office Suite

Aaron Womble Jem Locquiao Katharine Smith Daniel Sudbury

Page 5: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

Ensure SEA provides a cost effective solution to improve the flow of pedestrian, vehicular, and TRAX traffic in the area of South Campus Drive near 1800 East, across from the Huntsman Center

Page 6: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Project Scheduling

• Project Cost Estimate

• Technical Oversight

Courtesy of SEA

Page 7: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Project Scheduling

• Gantt Chart• Track progress for all deliverables across each team

• Reviewed weekly

Courtesy of SEA

Page 8: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Project Cost Estimate

• Individual cost estimates reported to PMT

• Assemble overall project cost estimate

• Budget oversight• Reviewed weekly

Courtesy of SEA

Page 9: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Technical Oversight

• Application of analytic measures

• Review drawings and calculations

• Aid in development of design alternatives

Courtesy of SEA

Page 10: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

SITE PLAN AND DRAINAGE TEAM Riley Ford

Page 11: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

• Experienced in Detention Design• Experienced with AutoCAD• Engineering Background

Jacob Nelsen William Holley Riley Ford

Page 12: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

Design site grading to detain and properly release storm water runoff

[1]

Page 13: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Existing Site Plan

• Design Phase

• Final Drawings

[2]

Page 14: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Existing Site Plan

• Investigate existing site drainage

• Prepare drawings showing locations of all existing structures and utilities

Courtesy of SEA

Page 15: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Design Phase

• Develop alternatives

• Determine alternatives’ effects on site runoff/drainage

• Provide feedback

[3]

Page 16: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Final Drawings

• Lay out final design location

• Determine new drainage conditions

• Prepare final professional drawings for client

[4]

Page 17: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

UTILITIES AND PERMIT TEAMGuy Evans

Page 18: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

• 4 Years of Experience as Quality Control Field Inspector, TEA Group

• Over 7 Years of Surveying Utilities Experience• Past Experience of Working With UDOT and Cities

Concerning Utilities

Guy Evans T.J. Owens Jeffery Beverly

Page 19: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

Responsible for utilities and all necessary permits

[5]

Page 20: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Identify Utilities• Aid Design Process• Determine Necessary Permits

[6]

Page 21: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Identify Utilities

• Review utility maps obtained from Facilities Management.

• Evaluate current conditions of utilities and consider upgrades

• Reach out to agencies: UDOT, Salt Lake City and UTA, and Blue Stakes

[7]

Page 22: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Design Process

• Advise design teams on limitations based on utility layout

• Work Close with the Aid in the optimization of the designs

• Design new utility lines

Courtesy of SEA

Page 23: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Determine Necessary Permits

• Establish any necessary permits needed

• Identify who is responsible for acquiring them

[8]

Page 24: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

TRAX TEAMMingde Lin

Page 25: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

• Conducted Traffic Research for Transportation Project • Proficient with Computer Aid Software for the task:

SAP2000, ArcGIS, AutoCAD• Ten Years Experience in Construction Management

Mason Clark Anthony Quach Adam Andre Mingde Lin

Page 26: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

Research and provide information on regulations,related future plans and implementations of UTA for SEA

Courtesy of SEA

Page 27: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Research UTA Regulations

• Provide Reliable Resources

• Analyze Alternative TRAX Lines

Courtesy of SEA

Page 28: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Research UTA Regulations

• Pedestrian safety

• Work zone regulation

• TRAX construction regulation

[8]

Page 29: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Provide Reliable Resources

• Pedestrian and Traffic Team

• TRAX Structures Team• Huntsman Structures Team

• Geotechnical Team

Courtesy of SEA

Page 30: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Analyze Alternative TRAX Lines

• Modification, reallocation of TRAX station

• Realignment of TRAX line

• Impact on traffic

• Estimate cost analysis[9]

Page 31: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

PEDESTRIAN AND TRAFFIC TEAMMichael Butler

Page 32: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

• Six Years of Internship Experience for Parsons Engineering, Project Engineering Consultants and Engineering Ambassador

• Worked within AASHTO constraints, Performed Traffic Safety Analysis

Michael Butler Crystal Orantes Derek Hatfield

Page 33: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

Safely maintain vehicle and pedestrian flow

Courtesy of SEA

Page 34: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Safety Evaluations

• Relieve Vehicle Congestion

• Maintain Pedestrian Flow

[10]

Page 35: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Safety Analysis

• AASHTO Highway Safety Manual

• Pedestrian – Vehicle collisions per year

• Roadway geometry and characteristics, traffic volumes [11]

Page 36: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Minimize Vehicle Congestion

• Rerouting of traffic

• UDOT standards

[12]

Page 37: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Pedestrian Access and Mobility

• Pedestrian routes are easily accessible

• ADA compliance

[13]

Page 38: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

GEOTECHNICAL TEAMCameron Brink

Page 39: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

Cameron Brink Alexsys Smith Dane Hirst

• Leadership and Drafting Experience• Structural Design Experience• Foundation Analysis through courses provided

Page 40: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

To perform necessary drafting and seismic related analysis of either a structure or tunnel alternative

Courtesy of SEA

Page 41: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Site Soil Analysis• Code• Teams• Foundation Analysis• Tunnel Design

Courtesy of SEA

Page 42: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Site Soil Analysis

•Obtaining underground infrastructure maps and a campus master plan

•Geotechnical reports from previous projects

•Possible analysis

–Liquefaction

–Seismic stability

–Slope stability

–Soil classification[14]

Page 43: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Codes

[18]

[15]

[16]

[17]

Page 44: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Teams

•Structural Teams

–Foundation design

•Utilities

–What utilities affect the site

•Site Plan and Drainage

–Drainage locations

[19]

[20]

Page 45: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Foundation Analysis

•Deep or shallow

•Backfill

•Seismic/slope stability

•Time and cost analysis

[21]

Page 46: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Tunnel Design

•Feasibility

•Structural capacity

–Seismic

[22]

Page 47: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

HUNTSMAN STRUCTURES TEAMD. Lukas Politis

Page 48: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

Blake Golding D. Lukas Politis Chris May

• Seven Years Structural Analysis• Four Years Alternative Design• Drafting and Design Software

Page 49: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

[23]

Page 50: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

To design a structure for pedestrian and bicycle traffic, which connects the Jon M. Huntsman Center

Courtesy of SEA

Page 51: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

[23]

Page 52: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Determine Alternatives• Structural Analysis• Performance Analysis

[24]

Page 53: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Determine Alternatives

• Improved access to the U

• The front door approach

[25]

Page 54: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Bridge Picture

[26]

Page 55: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Tunnel Picture

Courtesy of SEA

Page 56: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Structural Analysis

• SAP2000• AutoCAD• Columns• Beams• Walls• Slabs

Page 57: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Performance Analysis• Bike and pedestrian traffic• Aesthetics• Life cycle• Short term• Long term

Page 58: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

[23]

Page 59: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

TRAX STRUCTURES TEAM Jack Miller

Page 60: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Team Qualifications

• Construction Expertise• Previous Design of Structures• Design Experience at the University of Utah• Developed Spreadsheets and SAP2000

Jack Miller Chad Hall Kelly Johnston

Page 61: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Scope

Design a structure that connects the TRAX station to the U of U campus

[27]

Page 62: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Approach

• Determine Dimensions and Constraints

• Develop Alternatives• Structural Analysis

[28]

Page 63: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Determine Dimensions and Constraints

• Traffic• TRAX• Utilities• Geotechnical• Site Plan and Drainage

[29][28]

Page 64: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and
Page 65: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Determine Alternatives

Based on data feasible alternatives will be proposed

[28]

Page 66: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Structural Analysis

Perform structural and cost analysis on proposed alternatives

[30]

[31]

Page 67: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Decision Matrix

• Allows team to make a non biased decision• Stratifies alternatives to identify best option• Helps identify potential flaws or hurdles

Page 68: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Preliminary Proposed MatrixPrimary Objectives Balancing Objectives

Design Cost AestheticsFunctionality Primary Sum SustainabilityConstructibility Constructio

n Time Phasing Safety Balancing Sum

Weight 2 1.5 1.5   0.75 0.75 1 1 1.25  

I 10 5 9 41 8 7 9 8 10 81.75

II 5 10 7 35.5 7 8 7 6 7 68.5

III 6 7 6 31.5 9 6 5 6 7 62.5

IV 7 8 10 41 9 8 5 9 8 77.75

Page 69: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Courtesy of SEA

Page 70: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Image References[1] www.businessweek.com

[2] www.southportland.org

[3] sudsnet.abertay.ac.uk/

[4] www.cadpilot.com

[5] http://www.hartzophotography.com/architectural/

[6] http://www.basinandrangewatch.org/OcotilloWind.html

[7] http://www.civilconstructors.com/services.php

[8] www.rideuta.com

[9] http://utah.subwaynut.com/trax/university_s_campus/index.php

[10] http://www.ksl.com/index.php?sid=20240322&nid=460&page=1#8

[11] bookstore.transportation.org/collection_detail.aspx?ID=33

[12] footage.shutterstock.com

[13] http://trinitylafayette.org/wp-content/uploads/2012/06/trinity-handicap.png

[14] http://phamilynews.net/say-it-with-me-liquefaction/

[15] search.ebay.com/Saponification

[16] rtands.com

Page 71: IMPROVEMENTS TO THE INTERSECTION AT EAST SOUTH CAMPUS AND 1800 EAST SALT LAKE CITY, UT Presented to University of Utah Department of Campus Design and

Image References[17] www.betterroads.com

[18] http://www.amazon.com/2012-International-Building-Code-Council/dp/1609830407

[19] http://www.amazon.com/Wood-Architecture-Now-Philip-Jodidio/dp/3836523299

[20] http://versatileexcavatingct.com/services/drainage-utilities/

[21] http://www.rawell.co.uk/structural_waterproofing_product_applications/lift_pits.php

[22] http://vancouverisawesome.com/2009/01/page/8/

[23] Google Earth

[24] http://images.umc.utah.edu/netpub/server.np ind&catalog=catalog&template=

detail.np&field=Itemid&op=matches&value=3033&site=photobank

[25] www.en.wikipedia.org

[26] http://images.utah.edu/uploads/view/22

[27] www.utah.edu

[28] www.subwaynut.com

[29] nationwideequipment.com

[30] www.csiamerica.com

[31] www.office.about.com