Upload
vuongkhue
View
216
Download
0
Embed Size (px)
Citation preview
IMPROVEMENT OF SHELTER CONDITIONS
AND EXPANSION WORKS OF THE
POVOA DE VARZIM MARINA PROJECT
Extended Abstract
João Miguel Barros
Project for the Degree of Master of
Civil Engineering
Supervisors
Prof. António Alexandre Trigo Teixeira
July 2012
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
1
1 Introduction The Povoa de Varzim Marina, located on the southern embankment of the Povoa de Varzim
Harbor, began operating in 1998. Since it opened, the operational capability has experienced
severe performance restraints due to the penetration of excessive wave agitation when exposed
to storm conditions on the outside of the harbor basin, particularly when the incident waves
proceed from the W – SW quadrant. The marina, which is designed to allow the mooring of 241
vessels on its waterfront and similar amount on land, registers today just over half that value in
mooring vessels on water and it is up to full capability on its land space. This is due to the
security issues on half of the 6 floating pontoons dedicated to the mooring when exposed to this
kind of agitation. This limitation contrasts with the increased demand that the marina
administration registers from local and regional level, especially in the Class IV, V and VI
segments (10 - 18m), precisely those that the marina has a bigger challenge accommodating
due to its mooring being only allowed in those pontoons that are more exposed to the harsh
wave climate condition.
The primary goal of this project is to improve the sheltering condition of the Povoa de Varzim
Marina by creating a smaller harbor basin for it within the Povoa de Varzim Harbor one, which is
achieved with the construction of an internal breakwater on the front of the marina. The second
goal to this project is to expand the mooring capability of the marina within the limits of its new
basin to be able to respond to the increase in demand.
2 Basic project data
2.1 Description of the Povoa de Varzim harbor and marina
The Povoa de Varzim Harbor spreads through two distinct embankments, located on each
extremity of the Povoa de Varzim harbor. The fishing harbor is located on the northern
embankment while the southern embankment harbors both the Marina and a small shipyard
dedicated to the repair of small fishing boats and pleasure vessels. The north and south
breakwaters that shelter the Povoa de Varzim Harbor root on these embankments, with the
north pier developing along the direction of NNW and the south pier along the direction of SSW,
being able to provide appropriate shelter against the wave agitation that is coming from the
dominate direction of NW. The marina occupies the most of the available space on the southern
embankment, except for space dedicated to the small shipyard on the northern side, with the
stability of the embankment being assured by rock armored retentions with a 3:2 (H:V) slope.
The marina faces the south pier in an approximately parallel direction, developing itself across
the waterfront through two independent floating structures for the mooring of pleasure boats and
a small wharf for the reception of new boats and gas station.
Extended Abstract
2
2.2 Main constraints to the operation of the marina
2.2.1 Harbor shelter
Although the shelter provided by the breakwaters is suited to withstand the dominant wave
agitation from NW that hits the Povoa do Varzim Harbor, the combination of the bathymetry
around the harbor basin entrance and of the disposition of said entrance along SSW allows the
penetration into the harbor basin of wave agitation coming from the W-SW quadrant, particularly
from W-20ºS. The excessive wave energy that reaches the harbor basin, due to its open ocean
exposure on storm conditions, is able to generate wave agitation with wave height that exceeds
1 m (CEHIDRO, 2009), particularly in the area north of the Marina embankment, which prevents
the mooring of boats on the floating pontoons situated closer to the harbor entrance.
2.2.2 Geological constraints
The rocky nature of the coast where the Povoa de Varzim Harbor is situated reveals itself as an
obstacle to the development of the marina, given the lack of natural funds for the mooring of
vessels and the predominance of granite rock outcrops whose recognition on open eye sight
depends on the position of the tide, thus becoming a major concern to safe navigation within the
basin. The expansion of the marina requires a substantial dredging effort settled around the
southern embankment, which carries a major financial investment due to the cost of the
considerable amount of solid granite rock that has to be dismantled and removed for the
conclusion of the plan.
2.3 Design guideline data The design of the different structures that compose this project are conditioned by the maximum
tidal range, determined from the available data in the original project and the data provided by
the national Hydrographic Institute (Instituto Hidrográfico) to the Viana do Castelo Harbor. The
following limits were assumed:
- MPMAV: +3,95 (ZH), meaning 3,95 m above the base hydrographic level;
- MBMAV: +0,10 (ZH), meaning 0,10 m above the base hydrographic level.
The position of the inner breakwater was pre-determined in previous studies by Pipa (2008) and
CEHIDRO (2009), being shown in Figure 1.
Based on the results of the mathematical model applied in Pipa (2008) and reported in
CEHIDRO (2009) for the most severe storm condition scenario, considering wave agitation with
wave period T=18s and wave height Hm0=10m on the outside of the harbor, were considered
the following values for the design wave height for the inner breakwater and the retention works:
- H = 1,6 m for the design of the cross-section of the inner breakwater’s body and of the
cross-section of the head;
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
3
- H = 1.4 m for the design of the cross-section of the retention works.
Figura 1 – Posicionamento da obra de abrigo e bacia da Marina da Povoa
3 Marina layout
3.1 Statistical analysis of vessel dimensions Before beginning the process of designing the expansion layout of the marina it was elaborated
a statistical study of the vessel dimensions, particularly the relation of the beam and draft of the
vessel to its length overall (LOA), in order to determine the appropriate dimensions for mooring
berths for current vessel models on the market.
Graph 1 – LOA/Beam ratio for monohull vessels
Using the 2009 annual review edition of Bateaux magazine, which includes a total sample of
1189 different pleasure vessel models with 884 monohull vessels and 305 multihull ones, were
elaborated two different graphics for both types of vessels, one that relates the LOA with the
y = 2E-06x4 - 8E-05x3 - 0,0033x2 + 0,3379x + 0,3461
R² = 0,9351
y = 0,2287x + 0,9217
R² = 0,9116 y = 0,5799x0,7515
R² = 0,9076
0
1
2
3
4
5
6
7
8
9
10
11
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42
Be
am
(m
)
LOA (m)
Extended Abstract
4
beam and other that relates the LOA with the draft. From the available data it was tried to
extract useable functions that gave back a value of beam or draft with the input of a value of
LOA, what was done by applying three types of equations to the results – linear, 4th order
polynomial and potencial. The results are presented from Graphic 1 to Graphic 4.
3.2 Fleet distribution The administration of the Povoa de Varzim Marina expressed interest of expanding the mooring
space with a different fleet distribution from the one presently applied. According to them, the
focus should be on the mooring of vessels with LOA between 9 and 12 m, representing 55% of
the total, dedicating 30% of the mooring berth to vessels with LOA under 9 m and 15% of the
berths to vessels with LOA above 15 m and up to 18 m. The distribution adopted is shown in
Table 1.
Graph 2 – LOA/Draft ratio for monohull vessels
Graph 3 - LOA/Beam ratio for multihull vessels
y = 2E-06x4 - 8E-05x3 - 0,0029x2 + 0,2378x - 0,6024
R² = 0,6687
y = 0,1385x - 0,0603
R² = 0,637
y = 0,0391x1,4585
R² = 0,6196
0
1
2
3
4
5
6
7
8
9
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42
Dra
ft (
m)
LOA (m)
y = -6E-06x4 + 0,0009x3 - 0,0432x2 + 1,1512x - 1,9264
R² = 0,9318
y = 0,4194x + 1,2807
R² = 0,876 y = 0,6129x0,947
R² = 0,9015
0
2
4
6
8
10
12
14
16
18
20
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52
Be
am
(m
)
LOA (m)
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
5
Graph 4 - LOA/Draft ratio for multihull vessels
Table 1 – New fleet distribution for the Povoa de Varzim Marina
LOA (m) Vessel Class Distribution
≤ 9 I, II, III 30%
9 a 10,5 III, IV 25%
10,5 a 12 IV 30%
12,0 a 15 V 12%
15,0 a 18 VI 3%
3.3 Study of alternatives for fleet disposition Based on the graphs presented in 3.1 and the fleet distribution presented in Table 1 it were
defined the dimensions for the mooring berth for each vessel class, which are presented in
Table 2.
Table 2 – Adopted dimensions for mooring berths
Vessel Class LOA (m) Mooring Berth Dimensions
Width (m) Depth (m)
I, II, III ≤ 9,00 3,6 2,0
III, IV 9,01 – 10,50 4,0 2,3
IV 10,51 – 12,00 4,4 2,7
V 12,01 – 15,00 5,2 3,0
VI 15,01 – 18,00 6,0 3,5
A group of seven alternatives were considered for the arrangement of the floating pontoons and
mooring berths which are shown in Figure 2 and whose capacities and features are detailed in
Table 3 and Table 4. The decision on which alternative to apply on the expansion of the marina
was based on factors such as the total number of mooring berths generated, the ratio of
y = 7E-05x3 - 0,0056x2 + 0,197x - 0,7621
R² = 0,6739
y = 0,0647x + 0,1182
R² = 0,653
y = 0,0598x1,0565
R² = 0,6034
0
0,5
1
1,5
2
2,5
3
3,5
4
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52
Dra
ft (
m)
LOA (m)
Extended Abstract
6
mooring berth per meter of floating pontoon and the exposure to wave agitation on the marina
basin entrance. Based on these factors, the option ended up to be on Alternative 5.
Table 3 – Total mooring berths created by each alternative scenario
Vessel
Class LOA (m)
Number of mooring berths (Total)
Alt. 1 a) Alt. 1 b) Alt. 2 a) Alt. 2 b) Alt. 3 Alt. 4 Alt. 5
I, II ≤ 9 147 143 149 145 143 146 151
III 9 a 10,5 123 120 125 121 120 121 126
IV 10,5 a 12 147 144 149 145 143 146 152
V 12,0 a 15 59 58 59 58 57 58 61
VI 15,0 a 18 15 14 15 15 14 15 15
Total 491 479 497 484 477 486 505
Table 4 – Determination of the number of mooring berths by meter of floating pontoon
Alternatives
Number of mooring
berths created
Floating pontoon
total length (m)
Number of mooring
berths (/m)
Zone 1 Zone 2 Total Zone 1 Zone 2 Total Zone 1 Zone 2 Total
1 a) 100 150 250 506 846 1352 0,198 0,177 0,185
1 b) 87 151 238 663 841 1503 0,131 0,180 0,158
2 a) 101 155 256 506 900 1407 0,200 0,172 0,182
2 b) 87 156 243 655 901 1556 0,133 0,173 0,156
3 99 137 236 515 778 1293 0,192 0,176 0,183
4 101 144 245 518 739 1257 0,195 0,195 0,195
5 103 161 264 504 907 1411 0,204 0,178 0,187
Alternative 1, scenario a) Alternative 1, scenario b)
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
7
Alternative 2, scenario a) Alternative 2, scenario b)
Alternative 3 Alternative 4
Alternative 5
Figure 2 – Layout alternatives for the Povoa de Varzim Marina expansion works
Extended Abstract
8
4 Inner breakwater design
4.1 Design of the trunk cross-section It is considered that, despite of the precision of the mathematical model used to determine the
wave heights inside of the harbor basin, the wave height considered in 2.3 does not reflect the
concentration of energy created by the confinement of the harbor basin with the introduction of
an inner breakwater, thus choosing to design this structure to withstand waves with H=1,7m.
The calculation of the weight of the armored layer blocks and the thickness of said layer, and
also of the supporting underlayer beneath it, was done through the Hudson design formula
(SPM, 1984), assuming that the armored layer would be assembled with rock blocks
(γ=2.6kN/m3) with a 4:3 (H:V) slope. The weight of the rock blocks that compose the armored
layer on the inner side of the breakwater will be a tenth of the ones on the armored layer on the
outer side. The weights considered and the thicknesses of the layers are presented below.
Outer Side
���������� = 2,6 × 1,703
2 × ( 2,61,023 − 1)
3× 43= 1,33� = 13,3��
11 ≤ ���� �!"!#$ ≤ 16%��&
��������� = 2 × 1 × '1,332,6 (1 3)
= 1,6�
The weight of the blocks that compose the underlayer will be a tenth of the ones on the armored
layer, having the following characteristics:
1,1 ≤ �*+"!�,�-!�!#$ ≤ 1,6%��&
��.���/�0��� = 2 × 1 × '0,1332,6 (1 3)
= 0,71� ≈ 0,75�
Inner Side
1,1 ≤ ���� �!"3+$ ≤ 1,6%�� �4⁄ &
��������6. = 2 × 1 × '0,1332,6 (1 3)
= 0,71� ≈ 0,75�
110 ≤ �*+"!�,�-!�3+$ ≤ 160%� �4⁄ &
��.���/�0��6. = 2 × 1 × '0,0132,6 (1 3)
= 0,34� ≈ 0,35�
Based on the dimensions and weights given by the calculations were formulated three solutions
for the base cross-section of the body of the breakwater, respectively a high crested
breakwater, a low crested breakwater and a modified reef breakwater. Taking in concern the
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
9
need of occupying the least area possible and the moderate wave agitation on the harbor basin
the Alternative 3 was chosen, which is presented in Figure 3.
Figure 3 – Base cross-section of the body of the inner breakwater
4.2 Design of the head’s rotational cross-section The rotational cross-section of the inner breakwater’s head was designed taking in
consideration the design of the body cross-section, being approximately half of the body’s
cross-section. The cross-section’s slope remains the same of the body’s one because of the
already mentioned necessity to occupy the least space possible. The weights considered and
the thicknesses of the layers are presented below.
Armored Layer
���������� = 2,6 × 1,703
1,6 × ( 2,61,023 − 1)
3× 43= 1,67.� = 16,7��
13 ≤ ���� �!"� $ ≤ 20%��&
���������� = 2 × 1 × '1,672,6 (1 3)
= 1,72� ≈ 1,75�
Underlayer
1,3 ≤ �*+"!�,�-!�� $ ≤ 2,0%��&
��.���/�0���� = 2 × 1 × '0,1672,6 (1 3)
= 0,8�
4.3 Design of the hydraulic passage It was decided to insert a hydraulic passage on the inner breakwater’s body, which consists of a
pre-fabricated concrete caisson with two rectangular cross-sectioned openings (3,85 x 2,1 m)
from inner to outer side, in order to promote a more frequent renovation of the water inside the
marina basin. The data considered and the calculations done to determine the dimensions of
each opening’s cross-section are shown in Table 5 and Table 6.
Extended Abstract
10
Table 5 – Determination of the water volume for the design of the hydraulic passage
HwaterMPMAV (m) Bbasin (m2) Gtotaltide (m
3) Gdesignhyd.pass
(m3)
3,85 100354 386363 193182
Table 6 – Determination of the width of the rectangular cross-sections on the hydraulic passage
T = 6 h T = 12 h
vmax = 3 knot vmax = 2,5 knot vmax = 2 knot vmax = 3 knot vmax = 2,5 knot vmax = 2 knot
Q (m3/s) 8,94 4,47
v (m/s) 1,54 1,29 1,03 1,54 1,29 1,03
S (m2) 5,8 7,0 8,7 2,90 3,48 4,35
h (m) 3,35 3,35
b (m) 1,7 2,1 2,6 0,9 1,0 1,3
5 Retention works design
5.1 Design of the retention works cross-section The construction of the new embankment on the inner side of the south pier and the
modification of the geometry of the southern embankment do require the employment of
seawalls to provide containment, protection and stability to these structures. The procedure of
determination of the design wave height for the retentions is the same that was applied in the
case of the inner breakwater, where the design wave height was based on the results of the
mathematical model referred in 2.3. Following the same criteria already adopted in that case,
the design wave height was set on H=1,5m.
Just as in the case of the inner breakwater, there were considered several scenarios for the
base cross-section of the seawall, more precisely four: keeping the original cross-section,
which has a 3:2 (H:V) slope; adopt a similar cross-section to the outer side of a high crested
breakwater that features an armored layer and underlayer with a 4:3 (H:V) slope and a rubble
core; to maintain the blueprint of the original cross-section but changing to a 4:3 (H:V) slope; to
maintain the blueprint of the original cross-section and the 3:2 (H:V) slope with an adjustment to
the gradation of the rock used and the thickness of the layers. The third alternative, shown on
Figure 4, seems to be the one that offers more stability for a lesser area occupation, ending up
being the chosen one. The weight of the rock blocks and the thickness of the layers are the
following:
���� �!"!#$ = 2,6 × 1,542 × ( 2,6
1,023 − 1)4 × 43= 0,83.� = 8,3��
6,5 ≤ ���� �!"!#$ ≤ 10%��&
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
11
���� �!"!#$ = 2 × 1 × '0,832,6 (P 4) = 1,37� ≈ 1,4�
Following the same criteria applied to the armored layers of the inner breakwater, the weight of
the blocks of the support layer will be a tenth of those on the armored layer:
0,65 ≤ �*+"!�,�-!�!#$ ≤ 1,0%��&
�*+"!�,�-!�!#$ = 2 × 1 × '0,0832,6 (P 4) = 0,63� ≈ 0,65�
5.2 Design of the modified cross-sections for the insertion of gangways The connection between the embankments and the floating pontoons is assured by the
installation of steel gangways with a length of 18 m, which verifies the maximum slope limit of
1:4 (V:H). The gangways are attached to the embankment by the insertion of a modified cross-
section featuring concrete caissons where the steel access ramp is fixed to header beams with
an 1x0,8 cross-section. These caissons feature a rectangular or trapezoidal plant cross-section,
with hollow cells on the inside filled with rubble. Despite the different dimensions of the three
distinct caissons that were applied, they all feature walls and bottom slabs with, respectably, 0,3
and 0,2 m of thickness. The major modification to the cross-section of the seawall is the size
and shape of the rubble toe berm where the caissons lay down, having at least 1 m of thickness
and extending 1 m on each direction of the caisson’s edge.
Figure 4 – Base cross-section adopted for the seawalls
5.3 Design of the transition cross-section between the breakwater and
the seawall The connection between of the inner breakwater and the new embankment by the south pier
requires a modification of the cross-section to allow not only a greater protection on the
external face of the embankment but also to level the difference of elevation between these two
structures. The designed solution, shown in Figure 5, results on a cross-section that joins the
external face of the inner breakwater revetment with the cross-section of the embankment’s
seawall on the inner side of the marina basin, both integrated on the faces of a rubble core with
Extended Abstract
12
variable width. The gap of elevation on the external face of the breakwater is overcome with the
insertion of a concrete header beam with 1,05x0,8 m cross-section.
6 Selection of the mooring of the floating structure
6.1 Pre-design of the steel piles The fixation of the position of the existing floating pontoons was ensured by drilling and inserting
steel piles into the marina basin and attaching them to said pontoons, allowing the variation of
the vertical position along with the rise or drop of the tide. It was decided to use the same
solution on the expansion of the marina, using class S355GP tubular steel piles.
The pre-design of the diameter of the steel piles takes in concern the worst case scenario in
terms of stability and sheer resistance, which regards to the floating pontoons closer to the
entrance of the marina basin during high tide. Since this area is dedicated to the mooring of the
vessels with greater length that will mean that the steel piles will be lengthier and suffer a bigger
impulse from their attached floating pontoons.
Figure 5 – Transitional cross-section between the inner breakwater and the south pier embankment
The maximum force applied on the steel piles is calculated through the equation infLSP
d⋅= ,
considering that it is applied at a maximum elevation of +4,1 (ZH) and determining Sd according
to the Security and Action Regulation (RSA). Having determined the torque on the base of the
pile that is created by the actuating force, it proceeded to search for the diameter that
guaranteed the structural safety of the steel piles when these are spaced 25 to 30 m from each
other, being this distance given by the geometric constraints created by the mooring berths. The
solution ended up to be the use of 610 mm diameter steel piles with 19 mm of plate thickness.
The summaries of the data used and of the calculations of the structural safety of the solution
are shown in Table 7 and Table 8.
Table 7 – Characteristics of the chosen steel pile and of its insertion
fy D e I W Mrd ElevationTop ElevationBottom ElevationImpact
(MPa) (mm) (mm) (mm4) (cm3) (kN) (ZH) (ZH) (ZH)
355 610 19,01 154252,25 5057,45 1795 5,5 -3,5 4,1
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
13
Table 8 – Maximum torque applied and structural safety calculations
FAverage LPile hS Wk A δf
Sw K
Sd Linf P Msd Msd/Mrd
fmax
(m) (m) (m) (kN/m3) (m) (kN/m2) (kN/m) (m) (kN) (kN) (cm)
5 14 9,27 1,08 3,5 1,2 4,54 1,5 6,8 28 190,50 1765 0,98 10,60
7 Dredging plan
7.1 Design of the dredging plan The dredging plan for this project comprises three basic components: the modulation of the
bottom of the marina basin and the creation of a new access channel to the marina; excavation
of the area occupied by the shipyard on the northern face of the marina embankment; creation
of the new embankment on the inner side of the south pier.
The modulation of the marina basin lies on the definition of several platforms at different
elevations, going from -2,0 (ZH) on the inner area to -3,5 (ZH) at the entrance of the marina
basin, with intermediate platforms at -2,7 (ZH) and -3,0 (ZH). The transition between these
platforms is assured with 1:3 (H:V) slope. The access channel develops parallel to the inner
breakwater within a safety distance of 20 m, being established on all extension at the same
elevation as the marina basin’s entrance, i.e. -3,5 (ZH). Regarding the lateral slopes at the
excavation of the marina embankment, the existing barriers – the marina’s reception building
and the main avenue next to the harbor at an higher elevation – and the restrict area available
requires that a minimum safety distance of 4 m is ensured by the side of the building, which
leads to establishing the lateral slope at 3:2 (H:V). The nourishment of the new embankment on
the inner side of the south pier is established at an elevation of +5,0 (ZH).The dredging plan’s
plant is shown in Figure 6.
7.2 Estimation of total dredged material volume The estimated volumes of sand and granite rock to be dredged from the bottom of the marina
basin, presented in Table 12, follow the overall assessment of the basin’s nature provided by a
group of 50 cross-sections made of the bottom of the marina basin, which were based on the
data provided by a large survey campaign of the area during the construction of the south pier.
Having the longitudinal cross-section of the position of the top face of the granite rock mass in
this area, it was possible to define cross-section of the basin every 15 m starting from the
interior of the marina basin towards the edge of the south pier. With the data obtained from
these cross-sections it was established a Vsand/Vrock ratio so that a estimation of the volumes
of granite rock and sand to be dredged on the areas where no data was available of the position
of the rock mass. Looking at the areas north of the marina embankment, particularly the zone of
the marina basin entrance and of the access channel, since no precise data is available and the
topography is more regular than in the inner area of the marina, the definition of cross-sections
was spaced a bit wider to 20 m between each pair of them.
Extended Abstract
14
8 Quantities maps and budget estimative The summaries for the total quantities of materials used on the different stages of the project
are shown between Table 9 and Table 12.
Table 9 - Summary of the quantities of materials used on the construction of the floating structures
Designation Unit Quantities
Zone 1 Zone 2 Total
Floating Pontoon 7,5x2 m m 135 315 450
Floating Pontoon 11,5x2 m m 333,5 506 839,5
Fingers 12x1 m m 0 60 60
Fingers 9x1 m m 0 81 81
Fingers 7,5x0,75 m m 82,5 277,5 360
Fingers 6x0,75 m m 216 37,5 253,5
Gangways 18x1,5 m un 2 2 4
Steel Piles φ610 mm un 17 25 42
Figure 6 – Dredging plan plant
Table 10 - Summary of the quantities of materials used on the construction of the inner breakwater
Designation Unit Quantities
Rock (Riprap) 11,0-16,0 kN m3 12129
Rock (Riprap) 1,10-1,60 kN m3 13376
Rubble m3 7886
Concrete m3 119
Leveling gravel m3 13
Sinalization marker un 15
Improvement of shelter conditions and expansion works of the Povoa de Varzim Marina project
15
Table 11 – Summary of the quantities of materials used on the construction of the seawalls
Designation Unit Quantities
Zone 1 Zone 2 Total
Rock (Riprap) 6,50-10,0 kN m3 5878 7537 13415
Rock (Riprap) 0,65-1,00 kN m3 6044 6628 12672
Rock (Riprap) 11,0-16,0 kN m3 1182 0 1182
Rock (Riprap) 1,10-1,60 kN m3 586 0 586
Rubble m3 10474 120 10594
Nourishment soil m3 32039 10572 42611
Leveling gravel m3 108 78 186
Concrete m3 270 267 536
Geotextile panel m3 5443 6606 12050
Table 12 – Summary of the quantities of materials dredged from the bottom of the harbor basin
Designation Unit
Quantities
Zone 1 Zone 2
Total Access and Main Channel Shipyard
Sand m3 46029 112045 99512 257586
Granite Rock m3 12869 20606 27823 61298
To finalize this chapter, the summary of the budget estimative is presented on Table 13,
showing the costs for the construction of the full project and for the different components of the
project.
Table 13 – Total costs and per mooring berth generated by the different components of the project
Project componentes Cost
[€] [€/berth]
Permanent costs 210.000,00 -
Detached inner breakwater 2.444.858,00 -
Inner breakwater + Zone 1 3.226.511,00 31.325,00
Inner breakwater + Zone 2 5.789.790,00 35.961,00
Full project 8.297.368,00 31.429,00
Bibliography Projecto de execução da Marina da Povoa do Varzim. Hidrotécnica Portuguesa, 1991
Marina da Povoa de Varzim – Obras de Expansão e Melhoria das Condições de Abrigo. Estudo
Prévio, CEHIDRO, Março 2009
Tobiasson, B.O./Kollmeyer, R.C. – “Marinas and Small Craft Harbors”, Van Nostrand Reinhold,
New York, Second edition, 2000
Extended Abstract
16
PIANC – “Examen de norms sélectionnées applicable à lá conception d´appontements
flottants”, Rapport Spécial de la Comission pour la Navigation de Sport et de Plaisance, 1997
Pipa, Inês – “Melhoria das condições de abrigo na marina da Povoa de Varzim. Estudos em
modelo matemático.”, Dissertação de Mestrado em Engenharia Civil, Outubro 2008
Bateux Magazine, Dezembro 2009