Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Illinois Space Society
Student Launch 2015-2016
Maxi-MAV Preliminary Design Review
March 14, 2015
University of Illinois Urbana-Champaign Illinois Space Society
104 S. Wright Street
Room 321D
Urbana, Illinois 61801
1
Table of Contents Acronym Dictionary ....................................................................................................................... 4
General Information ........................................................................................................................ 5
Managers ..................................................................................................................................... 5
Major Subteam 1: Structures and Recovery ............................................................................... 5
Major Subteam 2: AGSE ............................................................................................................ 5
Minor Subteams .......................................................................................................................... 5
NAR Section ............................................................................................................................... 6
I) Summary of FRR report .............................................................................................................. 7
Launch Vehicle Summary........................................................................................................... 7
Payload Summary ....................................................................................................................... 7
II) Changes made since CDR .......................................................................................................... 7
Changes to Structures and Recovery .......................................................................................... 7
Changes to AGSE ....................................................................................................................... 8
CDR Feedback ............................................................................................................................ 8
III) Vehicle Criteria......................................................................................................................... 9
Design and Construction of Vehicle ....................................................................................... 9
System Review.......................................................................................................................... 12
Booster System ..................................................................................................................... 12
Coupler System ..................................................................................................................... 14
Upper Airframe System ........................................................................................................ 16
Subsystem Design and Construction ........................................................................................ 17
Motor Subsystem .................................................................................................................. 17
Fin Subsystem ....................................................................................................................... 20
Avionics/Payload Bay Subsystem ........................................................................................ 21
Rail Button Subsystem .......................................................................................................... 25
Recovery System ...................................................................................................................... 27
Structural Elements ............................................................................................................... 27
Electrical Elements ............................................................................................................... 29
Redundancy........................................................................................................................... 30
Parachute sizing and descent rates ........................................................................................ 30
Main Parachute Terminal Velocity ....................................................................................... 31
Drogue Parachute Terminal Velocity ................................................................................... 32
Ejection Charge Testing and Shear Pins ............................................................................... 32
2
Rocket-locating Transmitters ................................................................................................ 33
Sensitivity of the Recovery System ...................................................................................... 33
Parachute Sizing.................................................................................................................... 33
Safety and Failure Analysis .................................................................................................. 35
Vehicle Dimensioned Drawings ............................................................................................... 36
Mass Report .............................................................................................................................. 39
Mission Performance Predictions ............................................................................................. 41
Kinetic energy of the vehicle during launch ......................................................................... 42
Kinetic Energy of Booster under the Drogue Parachute ....................................................... 42
Kinetic Energy of the Upper Airframe Tube and Coupler under the Drogue Parachute ...... 42
Kinetic Energy of Booster upon Landing ............................................................................. 43
Kinetic Energy of Coupler upon Landing ............................................................................. 43
Kinetic Energy of Upper Airframe Tube upon Landing ....................................................... 43
Stability Margin .................................................................................................................... 43
Nose Cone Terms:................................................................................................................. 43
Fin Terms: ............................................................................................................................. 43
Center of Pressure: ................................................................................................................ 44
Verification ............................................................................................................................... 46
Safety and Environment ............................................................................................................ 54
Safety Officer ........................................................................................................................ 54
NAR Personnel Duties .......................................................................................................... 54
Hazard Recognition .............................................................................................................. 54
Law Compliance ................................................................................................................... 55
Motor and Energetic Device Handling ................................................................................. 55
Preliminary Hazard Analysis ................................................................................................ 56
Environmental Concerns ....................................................................................................... 61
Safety During Construction .................................................................................................. 65
Payload Integration ................................................................................................................... 65
IV) AGSE/Payload Criteria .......................................................................................................... 66
Selection, Design, and Verification of Payload ........................................................................ 66
System Review...................................................................................................................... 66
Payload Design ......................................................................................................................... 84
Design and construction of the payload ................................................................................ 84
Flight performance predictions ............................................................................................. 85
3
Test and verification program ............................................................................................... 85
Verification ............................................................................................................................... 85
Requirements ........................................................................................................................ 85
Safety and Environment ............................................................................................................ 94
Safety and Failure Analysis ...................................................................................................... 94
Payload Concept Features and Definition ................................................................................. 97
Creativity and Originality ..................................................................................................... 97
Uniqueness or significance ................................................................................................... 98
Science Value.......................................................................................................................... 100
Approach to workmanship .................................................................................................. 100
Precision of instrumentation and repeatability ................................................................... 101
V) Launch Operations Procedures .............................................................................................. 102
Checklist ................................................................................................................................. 102
Comprehensive Checklist ................................................................................................... 105
Launch concerns, operation procedures, and Quality Assurance ........................................... 108
Motor preparation ............................................................................................................... 108
Setup on launcher ................................................................................................................ 108
Launch procedure................................................................................................................ 109
Troubleshooting .................................................................................................................. 109
VI) Project Plan........................................................................................................................... 109
Budget Plan ......................................................................................................................... 109
Funding plan ....................................................................................................................... 112
Timeline .............................................................................................................................. 113
Educational Engagement .................................................................................................... 116
VII) Conclusion .......................................................................................................................... 118
Appendix A ................................................................................................................................. 119
Appendix B ................................................................................................................................. 122
Appendix C ................................................................................................................................. 123
Appendix D ................................................................................................................................. 126
Appendix E ................................................................................................................................. 128
4
Acronym Dictionary
AGSE: (Autonomous Ground Support Equipment) This is a combination of crane, rail, and
ignition systems used to robotically accomplish the mission goals.
CAD: (Computer Aided Design) Computer software that allows the design, assembly, and
annotation of rocket and AGSE components.
CDR: (Critical Design Review) A design review that shows that the design is ready for full scale
production and fabrication.
CFC: (Chlorofluorocarbons) Commonly used in aerosol cans until the 1980’s and were
determined to be damaging to the ozone layer.
CIA: (Central Illinois Aerospace) A local rocketry club that assists the team with test launching
the rockets. They also provide their expertise during the design and building phase of the
competition.
ISS: (Illinois Space Society) The parent group of the team competing in the Student Launch
competition.
LPG: (Liquid Propane Gas) The most common propellant used in spray paint cans, and is less
harmful to the ozone than CFC’s.
NAR: (National Association of Rocketry) Governs the use of high powered rocketry to ensure the
safety of the participants, spectators, and the environment.
PDR: (Preliminary Design Review) A design review that shows a feasible concept that will be the
subject of future work.
5
General Information Team Leader
Ian Charter, Project Manager
Phone: (815) 278-1294
Email: [email protected]
Safety Officer
Andrew Koehler
Managers
Project Manager: Ian
Safety Officer: Andrew
Structures and Recovery Manager: Stephen
AGSE Manager: Ben
Webmaster: Lui
Educational Outreach Director: Chris
Major Subteam 1: Structures and Recovery The first main subteam of about 10 students is the Structures and Recovery Team. This
team will be responsible for the design and construction of the vehicle, including systems for
parachute deployment and sample containment. The Structures and Recovery manager is Stephen.
Brian, Alli, Andrew, and David are key technical members for the Structures and Recovery teams.
Specifically, Brian is responsible for the design of the vehicle, and Andrew is responsible for
construction procedures. Alli is charged with management of the recovery systems, and David is
in charge of the sample canister and hatch systems.
Major Subteam 2: AGSE The second major subteam is the Autonomous Ground Support Equipment (AGSE) Team.
This team will be responsible for the design and construction of a robotic system to contain the
sample within the vehicle, as well as systems to erect the rocket from the horizontal position and
install the motor igniter. Ben is the AGSE manager. Brandon, Nick, Chris, and Alex are key
technical personnel for the AGSE systems. Ben is responsible for the compatibility between AGSE
components, and Brandon is in charge of the sample retrieval system. Alex is charged with
managing the ignition system, Nick is in charge of the lifting system, and Chris is in charge of
mass requirements.
Minor Subteams Minor subteams of around 5 students will be responsible for web design, safety planning,
and educational outreach. Each student on these subteams is also a member of either the AGSE or
Structures and Recovery subteams. Lui will manage the web design subteam, Andrew the safety
subteam, and Chris will manage the educational outreach activities.
In general, subteam managers are charged with organizing their respective teams, planning
necessary meetings, and overseeing progress on technical designs. That said, every team member
including managers will play a role in the technical design of their assigned systems. Although
key technical members are listed for the major subteams, whenever possible technical work will
be divided equally between all team members. The team’s goal is to draw on the knowledge of
past members, while also giving new members hands-on experience with the design and build
process.
6
NAR Section The ISS Tech Team will be working with members of Central Illinois Aerospace (CIA) to
facilitate test launches and review system designs. Specifically, Mark Joseph will be the NAR
mentor for the ISS Tech Team. CIA is section 527 of the National Association of Rocketry. The
CIA organizes bi-weekly launches at several locations close to the university, depending on the
time of year and launch field conditions.
Figure 1. Complete CAD drawing of the rocket and AGSE system.
7
I) Summary of FRR report Launch Vehicle Summary
Payload Summary The team will be building off of last year’s design, keeping a similar rail and igniter
insertion system. An actuator will be used to raise up the rail system, with a limit switch at the
base of the launch pad so that when the rail is 5 degrees off of the vertical, the switch will be
triggered stopping the actuator. The igniter system will use a similar actuator, with a “Z” shaped
piece and a thin, wooden rod attached to the opposite end of the piece, with the igniter fashioned
onto the end. The actuator will raise the Z-piece and, in turn, raise the igniter. Screwed onto the
blast plate will be a guide cone that the igniter will rise through to more accurately aim the igniter
into the rocket.
The team has designed a robotic crane-like mechanism to retrieve the payload. The crane
is a three segment structure, with 360° rotation and a vertical arm fashioned at the end of a
horizontal beam jutting outward from the base of the structure. At the bottom of the vertical arm
is an electromagnet holding onto a curved piece cut from the rocket’s body tube, with clips along
the underside. The crane will rotate and pick up the payload by pressing these clips onto said
payload. The arm shall then rotate over to the rocket and shut off the electromagnet, releasing the
payload and hatch door. Finally, the hatch will be sealed with small permanent magnets attached
to the rocket and bay door, along with a tubular latch fastened to the inside of the rocket and will
seal itself to a small, block on the hatch door.
II) Changes made since CDR Changes to Structures and Recovery In order to insure the structural integrity of the motor mount tube during flight, the motor
mount tube is no longer flush with the end of booster tube, but is rather inserted half an inch into
it. This allows a fillet to be added on the underside of the bottom most centering ring to better
connect it to the outer booster tube.
The main parachute was changed from a 72” IRIS Ultra to a 60” IRIS Ultra. This was done
due to concerns about drift distances as well as budget concerns. In order to ensure that the rocket
fell within the required lateral 2500ft the team decided to use a smaller parachute rather than deploy
at a lower altitude, since anything significantly past 450ft AGL poses a potential danger in the
event there is any delay in deployment. Additionally, since Illinois Space Society already owns a
60” IRIS ultra, using it allows for a significant cost decrease (~$250). Kinetic energy analysis
following the change indicates that all segments of the rocket will still fall well under the 75 ftlbf
requirement with some (~15 percent) margin to account for any unexpected behavior.
For the recovery equipment, U-bolts replaced eye bolts at the two ends of the coupler. U-
bolts provide greater functional strength when compared to eye bolts and the bulkhead provided
enough room to properly install a U-bolt.
Following the completion of construction, the discovery was made that the rocket was
significantly under the design mass. In order to achieve satisfactory performance, the team added
ballast mass. This was accomplished by adding a ~1.1 lb mixture of epoxy and lead BB’s into the
channel between the motor mount tube and booster tube on top of the topmost centering ring.
Additional quick links are used at each connection point as well and do not affect the performance
of the recovery equipment. Finally, a threaded and fastened thread of nuts is added to the inside of
8
the nose cone. This combination of ballast allowed us to achieve performance close to design
specifications without affecting the stability of the vehicle.
In order to allow for consistent insertion of the payload, the width of the hole in the
switchband for the hatch door had to be adjusted from 1.5 in to 2. Consequently, the cutout in the
coupler also had to be expanded from 1.25 to 1.5. The corners are still rounded and the fit is tight
so no structural issues are expected.
Changes to AGSE Since CDR the only major change to the AGSE system is the way the crane is being
rotated. Originally the crane was going to rotate via a belt system, but after testing it was
determined that this system is too unreliable. To fix this issue, a bicycle chain and gear system was
implemented. This system allows for a much more precise rotation angle with no slipping
occurring at any of the interface points.
CDR Feedback What was your decision process to remove the active drag system from the rocket design?
The decision to remove the active drag was primarily based on a high level of confidence
in the flight simulations. It was decided that reaching the desired height would be more accurate
by properly construction and ballasting of the rocket rather than an experimental active drag
system.
Overall excellent presentation. We really appreciated you verifying both commercial
simulation programs with custom programs and hand calculations. All questions from PDR
were answered, and any questions we could think of during the presentation were answered
later. This is the sign of a well prepared document, and we commend you on your efforts.
Keep up the great work!
Thank you!
9
III) Vehicle Criteria
Figure 2. Unpainted competition rocket
Design and Construction of Vehicle
Flight Reliability and Confidence It is important that the reliability and confidence of the flight vehicle's design is mature.
The hand calculations, coded simulations, and OpenRocket simulations that the team conducted
of the predicted flight profile all demonstrate the maturity of the flight vehicle's design. The team
is highly confident in the design of the vehicle. Team members met for an average of six hours per
week, and the design was developed among team members throughout this time period. The design
has been overseen and reviewed by team members with significant rocketry experience and by the
team’s NAR mentor.
The subscale launch also played a major role in the team’s confidence. During the subscale
building process, team members were able to get hands on experience in building a high powered
rocket. This experience was further developed with the construction of the full scale vehicle.
The full scale launch will also be a major milestone in proving the team’s design and
ensuring the reliability and safety of the vehicle. Unfortunately, due to unforeseen weather
conditions, the team has not yet been able to launch the rocket. However, the rocket is completely
prepared for a launch which will be rescheduled to be in the upcoming week. This test launch will
10
provide useful data to the team showing if the simulations were accurate in estimating the
performance of the rocket.
Additionally, the team has been able to learn from the past failures and successes of other
teams due to former experience in the competition. ISS has participated in this competition six
times, giving the current team access to a number of old design documents and reports. Critical
parts of the rocket have previously been used by ISS teams and local rocketry clubs. The team
believes the current design defines an advanced system for completing the mission requirements,
without sacrificing confidence in flight safety and reliability.
The vehicle details were continuously analyzed and redefined to achieve the best possible
design meeting all mission requirements for the project. The vehicle is flight ready and the only
construction left is that of the latch-door system and to paint the exterior of the rocket.
Mission Statement
“The mission of the Illinois Space Society Student Launch Team is to safely launch and
recover a reusable high power rocket simulating a Mars Sample Return. This includes design and
construction of an Autonomous Ground Support Equipment system to simulate the loading of a
Martian soil sample and the vehicle launch procedures. The vehicle will be tracked and recovered
after launch. The vehicle will launch to 5,280 feet at which point the drogue will deployed,
followed by the main at 450 feet above ground. The vehicle shall be designed to be reusable upon
recovery, and all components shall land with less than 75 ft-lbf of kinetic energy.”
Requirements Official project requirements and their respective design features and verification methods are
given in the Vehicle Requirement table of this report. However the team has determined several unofficial
requirements to serve as project goals. Many of these are closely related to official requirements.
1.) The vehicle must conform to the highest safety standards at all times.
2.) The vehicle shall attain a maximum altitude of 5,280 ft.
3.) The vehicle shall be highly reusable, such that the ISS may recreationally launch the
vehicle with minimum effort upon competition completion.
4.) The vehicle shall be able to function both with the custom AGSE system, as well as a
standard high power rocketry launch rail configuration.
5.) The vehicle shall have a visually appealing design, reflecting the months of extreme
effort dedicated to its design and construction.
6.) The vehicle design and construction shall serve as a high level learning experience for
team members, providing all team members with significant crucial experience in the real
world design and engineering process.
7.) The vehicle design must be well defined and reports shall be given with the highest
amount of detail possible.
Mission Success Criteria
The team will consider the mission a success if the vehicle fulfills all NASA requirements
and if superior safety standards are maintained throughout the project. During the build process
and launch procedures, mission success will depend heavily on team members following all safety
standards laid out later in this document. Minimizing safety risks for team members and observers
is considered critical for success in the competition. On competition day, the rocket should secure
the sample in its payload bay, launch to an apogee of 5,280 feet, and then land safely at a reasonable
distance from the launch pad. The rocket’s recovery system will be deemed successful if the drogue
11
and main parachutes deploy successfully and if the onboard altimeters record relevant data
throughout the flight.
Approach to Workmanship
As a responsible team, safety as well as the quality of the final product are held in the
highest importance. A detailed agenda and construction procedures has been created to provide
every member with vital knowledge of proper and safe construction techniques. In addition the
team can consult experienced members and the team mentor for further clarification of proper
technique. As well as benefiting safety considerations, these moves create a redundancy in
knowledge that will allow the Illinois Space Society to continue construction uninterrupted and on
schedule in the event that certain personnel are unable to attend a build session. All construction
will be overseen by the safety officer and one veteran member of the group that can provide hands-
on instruction to help both ensure the safety of every participating member and that the work is
being done correctly for a quality build. The aforementioned team mentor will be involved with
the team for every test and will consistently check in on the team during construction to ensure all
proper precautions are being met. The combination of these efforts will allow the team to create a
quality project without endangering any individual on the team. Should any danger arise every
member has been instructed to err on the side of caution and the safety of themselves and of the
team, regardless of any potential impact on the quality of the project itself. In general, ISS strives
to apply proper workmanship both to enhance the probability of mission success, and to mitigate
any safety risks.
Major milestone schedule
The major milestones for the launch vehicle can be seen in Table 1 below. Completed tasks
are shown in green, milestones which are behind schedule are in red, and those which are to be
completed in the future are shown in blue.
Table 1. Major Milestone Schedule
Date Milestone Completion
August 30, 2015 Team compiled and established goals
September 11, 2015 Proposal documentation submitted
November 6, 2015 Preliminary Design Review documentation submitted
November 16, 2015 PDR video teleconference presentation delivered
December 9, 2015 Subscale build begins
December 19, 2015 Subscale is launched and data gathered
January 15, 2016 Critical Design Review documentation submitted
January 18, 2016 Begin finalizing building instructions
January 20, 2016 All parts to be inventoried and inspected, build plan
reviewed
12
January 22, 2016 CDR video teleconference presentation
February 27, 2016 Component testing
Week of March 14, 2016 Full Scale test flight, test recovery system
March 14, 2016 Flight Readiness Review documentation due
April 14, 2016 Launch Readiness Review
April 16, 2016 Launch full scale flight vehicle
April 17, 2016 Review & reflect on flight results and feedback
April 29, 2016 Post Launch Assessment Review document due
System Review
Booster System
The booster system includes everything contained within the rocket’s lower body tube. It
includes complete subsystems for the motor, fins, and rail buttons, and houses the first (drogue)
recovery stage. Here a generalized description of each subsystem will be given, but more detail
can be found in the subsystem descriptions section of this paper.
The overall booster system is 40.75 inches in length, including a 40.25 inch body tube and
a inch motor retainer that hangs .5 inch off the aft end of the rocket. Team members chose to
construct the body tube from 4.014 inch diameter Blue Tube, with the motor mount tube being
made of 3.10 inch diameter Blue Tube. The motor subsystem is located at the rear of the booster
section, and the fins pass through the outer body tube and are secured to the motor mount tube in
between the two lowermost centering rings. The drogue parachute is stored above the motor
subsystem, and rail buttons are secured along one side of the main body tube and attached to
centering rings via plywood blocks.
When designing the overall vehicle, team members researched various materials for
construction of the main body and fins. Initially, aircraft plywood and balsa wood were considered
as possible materials for the fins while Blue Tube, carbon fiber, and fiberglass were evaluated for
possible use in the main body. Each material was later assessed in light of its respective advantages
and disadvantages as seen in Table 2 below. A value of 5 represents the best possible score in a
category, while 1 represents the poorest possible score in a category.
13
Table 2. Material Trade Study
Material Strength Cost Ease of Use Safety
Aircraft plywood 3 2 3 4
Balsa wood 1 5 5 4
Blue Tube 4 4 4 4
Carbon fiber 5 1 2 3
Fiberglass 4 3 2 2
Team members first decided on a material for the main body of the rocket. Blue Tube was
ultimately chosen because it was the most reasonable choice based on strength, cost, ease of use,
and safety. For example, the added strength of carbon fiber was unnecessary and did not justify its
cost. The heat capacity of Blue Tube is sufficient to protect against the heat output of the motor, it
poses fewer safety concerns when it is being cut, and is easier to work with than carbon fiber.
These benefits, combined with its high strength and affordability, led Blue Tube to emerge as the
chosen material for the main body. During last year’s Student Launch competition, the team
decided to use Blue Tube and it was a great success. There were no problems with Blue Tube and
it proved to be a durable, inexpensive, and reliable material.
Focus then shifted to deciding between fiberglass and aircraft plywood for the fins. Team
members decided that the material would have to be moderately strong and relatively easy to work
with, especially because fins require extensive shaping and sanding before being attached to the
rocket. Aircraft plywood is low cost and easy to work with, but is not as strong as fiberglass.
Though pricier than and not as easy to shape as aircraft plywood, fiberglass is much stronger and
last years’ team had success with fiberglass fins. This previous design gave the team valuable
experience with fiberglass fabrication, including necessary safety measures and allows the team to
create a custom shape of the design.
The team has access to a lab that was used previously to manufacture the fiberglass sheets
and then cut out the shape of the fins. Ultimately, the extra strength and reliability led the team to
choose fiberglass as the fin material. The team plans on utilizing the diamond table saw in the
fiberglass lab again this year to custom-cut fiberglass fins.
An Aeropack flanged retainer is employed to ensure the motor casing doesn’t move
forward or aft during the duration of flight. The retainer is installed on the bottom most centering
ring via a series of 12 screws circulating the retainer.
In order to further secure the motor mount tube to the booster tube, the team chose to install
the motor mount tube further into the booster so that the bottom most centering ring is not flush
with the end of the body tube (it’s inserted about .5 in in). This allowed for the installation of a
fillet on the bottom of the lower-most centering ring and further improve the structural integrity of
the system as a whole.
A CAD mock-up of the overall booster design, as well as an inward facing view of the
system that utilizes transparency to see internal components, can be seen below in Figure 3 and
Figure 4.
14
Figure 3. Booster airframe model shown as designed.
Figure 4. Inward view of booster tube.
Coupler System
The coupler system serves as the connection point between the booster system and the
upper airframe system. It contains the complete subsystems for the avionics bay and hatch, as well
as parts of the recovery subsystem. As with the booster section overview, a very general overview
of the subsystems is given here. Additional subsystem details can be found in Subsystem
Descriptions.
The coupler itself is constructed from 3.9 inch diameter Blue Tube, allowing it to slide into
both the booster and upper airframe. To facilitate integration with the rest of vehicle, a 7.125 inch
long piece of 4.014 inch diameter Blue Tube acts as a switch band around the middle of the coupler.
This switch band leaves 3.9375 in of 3.9 inch Blue Tube exposed on each side, and the additional
diameter acts as backstop for the booster and upper airframe when they are slid onto the coupler.
Altogether, the coupler has a total length of 15.5 inches. Nylon shear pins will be drilled into
airframe and coupler tube and utilized to prevent the sections of the rocket from separating prior
15
to previously planned recovery events. Ejection charges will break these shear pins and allow for
the deployment of drogue and main parachutes.
Because we’ve chosen to eject at the nosecone rather than the at the coupler, the upper
airframe is locked to the coupler via 3 3/16” machine screws and matching T-nuts to ensure that
the two pieces will not be separated at any step during flight. This system still allows the coupler
to be fully removed for easy access to the internals as needed.
Inside the coupler, avionics and hatch hardware is mounted via a system of rails and support
boards. Two paired bulkheads cap each end of the coupler, secured in place by nuts at the end of
each rail. These bulkhead caps consist of a 3.733 inch diameter bulkhead (matching the inner
diameter of the coupler tube) and a 3.9 inch diameter bulkhead (matching the inner diameter of
the airframe tubes and outer diameter of the coupler tube) glued together. These bulkheads protect
the altimeters and other delicate electronics, prevents air from entering the coupler to keep the
altimeters accurate, and also provides a place to mount ejection charges for both parachutes. The
altimeters inside the coupler directly control the timing of the ejection charges.
Trimmed coupler bulkheads inside the coupler serve to separate the central payload
containment area from altimeter sleds on either end of the coupler. Additionally, these bulkheads
will serve as a mounting point for mortice latches and magnets that will keep the hatch door
attached to the rocket during flight.
A CAD mock-up of the overall coupler design, as well as internal views, can be seen below
in Figure 5, Figure 6, and Figure 7.
Figure 5. Rocket coupler shown with the hatch (white) attached.
16
Figure 6. Internal components of the rocket coupler. The payload bay is shown in the
center with altimeters placed on either end.
Figure 7. Underside view of coupler internals.
Upper Airframe System The upper airframe system includes all components in the vehicle’s upper body tube and nose cone.
It serves as the storage space for the main parachute, a key part of the recovery subsystem. The upper
airframe is 42.625 inches in length, including the 16.5-inch aerodynamic nose cone fixed to the top of the
body tube. A CAD mock-up of the overall upper airframe design can be seen in Figure 8 below.
17
Figure 8. External view of the upper airframe of the rocket.
Subsystem Design and Construction
Motor Subsystem
The first critical subsystem of the vehicle is the motor subsystem. The motor serves as the
vehicle’s sole propulsion system for the flight. The motor itself used for the flight is the Aerotech
K1000T-P. An Aerotech motor was chosen as they are a highly reputable company that the team
and team mentor have had significant dealings with in the past. Additionally, Aerotech is one of
the most well-known motor manufacturers, and a large number of motor hardware products
compatible with Aerotech products are available. The K1000T-P was chosen over similar motors
such as the Aerotech K780 because the K1000T very quickly reaches its maximum thrust, allowing
a high exit rail velocity that is important for overall flight stability. The thrust curve and other
import aspects of the K1000T are included and discussed in the mission performance section of
this paper.
The main components of the motor subsystem are shown in Figure 9 below. Shown in light
gray is the vehicle’s motor casing inside the motor mount tube, shown in light blue. The eye bolt
for the drogue parachute, which screws directly into the motor case, is shown in light grey.
18
Figure 9. Motor system shown inside the lower airframe.
In terms of safety, the motor case is possibly the most important flight component to
consider. The motor case is designed to contain the propellant grains of the Aerotech reloadable
motor. Due to this, the motor casing (an RMS 75/2560) is professionally fabricated from precisely
machined aluminum. This ensures that the propellant can burn in a proper environment without
adversely affecting the remainder of the vehicle. This component also serves as the lower
attachment point for the drogue parachute shock cord.
Housing the motor case and shown below in Figure 10 is the motor mount tube with its
three centering rings. The motor mount tube is a 3.1 inch diameter piece of Blue Tube, allowing
for the installation of the motor case without adapters, and 20 inches in length. This component is
designed to house the motor case separately from the rest of the vehicle. The vehicle’s centering
rings can be seen in brown. These are used to ensure that the motor mount tube, and thus the motor
casing and motor itself, are seated directly and securely in the center of the vehicle. These rings
are composed of high quality plywood and are designed for the specific purpose of centering the
motor. The vehicle contains three centering rings: one at the extreme aft end of the booster tube,
one at the top surface of the fins, and one near the top of the motor mount tube.
19
Figure 10. Motor mount tube with centering rings attached and the motor case inserted.
The final component of the motor subsystem is the motor retainer, shown below in black
in Figure 11. This is a high strength aluminum component used to prevent the motor from shifting
its position forward or aft during flight. The retainer consists of two pieces: a body and a screw on
cap. The body of the retainer is permanently fixed to the lowest centering ring. After the motor
case is slid into the rocket, the retainer cap securely threads on to the body of the retainer. This
prevents the motor from inadvertently moving during flight and also provides a quick method of
loading and removing the motor casing.
Figure 11. Rear of the rocket showing the motor retainer and motor case.
20
Fin Subsystem
The vehicle’s Fin Subsystem is designed to provide the vehicle with an aerodynamic
restoring force that will stabilize the rocket’s flight path and move the nose back to a stable path.
The design includes three trapezoidal fins spaced 120 degrees apart. Trapezoidal fins were chosen
to allow a larger amount of surface area to be farther away from the fuselage, helping to stabilize
the rocket. It was decided that the fins will have a root chord of 11.813 inches, a height of 5.25
inches, and a tip chord of 6.25 inches. These dimensions were determined through OpenRocket
simulation and a custom matlab script to optimize for stability and to reach the target altitude of
5,280 feet. These software packages allowed the team to obtain an estimate of vehicle stability and
alter dimensions and characteristics of the fins as necessary to achieve suitable stability. The fins
will not extend beyond the aft end of the rocket to ensure that the fins do not break in the event
that the rocket lands on the aft end. The fins will extend through the body of the vehicle and be
epoxied directly to the motor mount tube, as well as to the outer booster tube. To further ensure
structural integrity, the fins will be attached between the lower and middle centering rings,
providing additional contact surfaces where epoxy may be applied. A dimensional drawing of the
fins and a representation of their placement can be seen below in Figure 12 and Figure 13.
Figure 12. Dimensioned drawing of the rocket fins.
21
Figure 13. Rocket cross-section shown from below.
Avionics/Payload Bay Subsystem
The avionics and payload bays are located in the vehicle’s center coupler and contain the
components necessary for securing the sample and deploying the vehicle’s parachutes. The main
coupler piece is composed of 15 inches of Blue Tube designed to function as a coupler for 4.014
inch Blue Tube airframes. It can be seen in light blue in Figure 14 below. Taking into account the
two airframe bulkheads that extend from the coupler, the full length of the coupler subsystem is
15.5 inches. The switch band, a 7.125 inch long piece of 4.014 inch diameter Blue Tube, can be
seen in dark blue wrapped around the coupler. This piece serves as a backstop for the booster and
upper airframe when they are slid onto the coupler, a mounting point for the rotary switches which
arm the vehicle’s avionics, and as a location for small drilled holes to allow for proper operation
of altimeters. The magnetically sealed hatch door can be seen on the switch band in silver in Figure
14.
Figure 14. Main coupler and payload bay.
22
As a supplement for the above image, Figure 15 and Figure 16 below show the avionics
and payload bays stripped of the coupler tube and switch band. The brown disks shown are the
coupler and airframe bulkheads, composed of high quality plywood. These provide a physical
barrier between the recovery electronics and the remainder of the vehicle. Shown in dark gray on
the bulkheads are terminal blocks designed to accommodate the E-matches that will ignite the
ejection charges. Wires connect to one side of these blocks from the altimeters, and the E-matches
are attached to the other side. Also mounted on the bulkhead and shown in white are charge cups
designed to hold the recovery system’s ejection charges. These are small PVC cups that will be
filled with black powder. An E-match will then be inserted into the charge cups. The caps are then
covered with foil tape to contain the powder. The final components mounted to the bulkheads are
the u-bolts and quick links, shown in dark gray. The u-bolts run through the bulkheads and are
attached with a nut and washer on each side, as well as a small amount of epoxy. These provide a
secure attachment point for the parachute shock cords. The quick links, shown below as gray ovals,
are used to attach the parachute shock cords to the u-bolts. These provide for a strong attachment
point that may be easily assembled before flight and removed afterward.
Looking at the inner components, there are two threaded aluminum rails that span the
length of the coupler. These rods are attached to each bulkhead via a nut and washer on each side.
These both hold the bulkheads on the coupler and provide a rail system for which to slide the
payload and avionics sleds into the coupler. The avionics and payload sleds are shown as light
brown rectangles. These are thin sleds composed of aircraft plywood with small tubes linking the
sled to the threaded rods. These tubes will be 3D printed to the specifications by a team member
using their own 3D printer, which the team used in last year’s competition. These tubes serve as
guides, allowing the sled to smoothly slide on the rails and remain fixed within the system. The
Stratologger altimeter and Telemetrum altimeter can be found on either avionics sled and shown
in light gray are. The altimeters are installed on the opposite side of the hatch door to place them
closer to the outward facing rotary switches that will be used to turn on these altimeters on launch
day. These will be used to record the flight profile and deploy the main and drogue parachutes.
The electrical diagram of the altimeters is shown farther down in Figure 17. Once the vehicle
reaches apogee, the altimeters will trigger the drogue ejection charge to release the drogue
parachute. Later during descent, the altimeters will trigger the main ejection charge to release the
main parachute.
Trimmed bulkheads and a payload containment sled serve as a way to isolate the payload
from the recovery equipment in the unlikely event that the gripper on the hatch door fails and drops
the payload inside the rocket. The bulkheads are trimmed to allow for wires to cross the length of
the coupler from either altimeter to the ejection charges and to allow for the installation of a ~6
inch tracking antenna to the Telemetrum altimeter.
23
Figure 15. Side views of coupler internals.
Figure 16. Placement of altimeters in coupler, with Telemetrum on the left sled and
Stratologger on the right sled.
24
Figure 17. Electrical schematic of recovery equipment.
These trimmed bulkheads will also serve as the mounting point for the internal magnets
and mortice latch that will keep the hatch door in place during the flight of the rocket. When the
hatch door is placed into the rocket, the latches will lock into the strike plate blocks install on either
end of the hatch door. The strike plate blocks are shown below in Figure 17 on a payload equipped
hatch door.
Figure 18. Hatch door with strike plate blocks installed on both ends.
25
Rail Button Subsystem
The rail button subsystem is responsible for holding the vehicle to the launch rail during
the initial stage of the flight. The rail buttons will be standard 1515 rail buttons designed to work
on a 1.5 inch slotted rail. Each rail button will be attached to a mounting point secured to one of
the vehicles centering rings. This mounting point will consists of a plywood block with a T-nut.
This allows the rail buttons to easily screw in and out in case one needs to be replaced, but it also
provides for a secure mounting configuration. Additionally, this method mitigates any damage to
the structural integrity of the relatively thin centering rings. A close up of one of the rail buttons
can be seen below in yellow in Figure 19. The mounting hardware can be seen below in Figure 20.
Figure 19. Close-up of 1515 rail button.
26
Figure 20. Rail button mounting hardware.
Two rail buttons were chosen for the rocket. Two will be capable of holding the vehicle to
the launch rail. No more than two rail buttons were chosen, as additional buttons increase the drag
on the rail as the vehicle launches and negatively impacts the exit rail velocity. The placement of
both rail buttons can be seen in Figure 21 below.
Figure 21. Placement of rail buttons along the booster tube.
27
Recovery System
Structural Elements
The recovery systems require the most consideration in regards to safety. All of the
attachment mechanisms have been designed for safety as well as reliability during flight.
The rocket consists of two parachutes, the drogue and the main parachute. The drogue is
stored in the booster section of the rocket. It is located below the avionics bay and above the motor
mount tube. It is attached to the vehicle using a ½” diameter Tubular Kevlar shock cord. To attach
the shock cord to the parachute in a safe and secure way, the shroud lines are passed through a
loop in in the shock cord and then the parachute is passed through the looped shroud lines. The
shock cord is then attached to the motor mount using a steel quick link and a steel eye bolt. The
eye bolt is attached to the top of the motor mount in a slot designed for this purpose. The steel
quick link attaches the Kevlar shock cord to the steel eye bolt. This quick link allows for easy
assembling on launch day as well as increases safety. The drogue is also attached to the avionics
bay. A u-bolt is screwed into a plywood bulkhead that is attached to the avionics bay. The U-bolt
is attached using a nut and washer on each side of the bulkhead. In order to ensure that everything
is structurally sound, epoxy will also be added to the nuts and washers. Pictured below in Figure
22 is an image of the bulkhead parachute attachment point.
Figure 22. Bulkhead parachute attachment point.
28
The rocket’s main parachute is located in the upper airframe. It is positioned above the
avionics bay and under the nose cone. The shock cord attachment technique is the same as above,
but instead of attaching the shock cord for the main parachute to the motor mount, the Kevlar cord
is attached to the nosecone. Slots were cut into the plastic nose cone and a Kevlar strap (½ inch
tubular Kevlar) was threaded through to serve as the attachment point for the quick links. A picture
of this slot is shown below in Figure 23. Using the steel quick link and the u-bolts, the attachment
is the same as for the drogue parachute.
Figure 23. Slots for nosecone attachment point with the shock cord threaded through.
Both of the vehicle’s shock cords will be composed of high strength half inch tubular
Kevlar. Kevlar is significantly stronger than steel, having a tensile strength of about 520,000 psi.
The parachute’s canopies are composed of high strength rip stop nylon. The shroud lines and
bridles are constructed out of high strength spectra, nylon, and Kevlar. All of these material are
sufficiently strong and prove the components to be robust.
Nylon 4-40 shear pins are utilized to keep the rocket in place before the ejection charges
fire. In order to ensure that the shear pins at the nosecone break when the charges fire, pieces of
29
brass shim stock were epoxied to the nosecone. This provides a sharp surface against which the
shear pins will cut away from when the charge blows. A picture of this configuration is shown
below in Figure 24.
Figure 24. Brass fittings on the nose cone to aid separation of the shear pins.
Electrical Elements
The altimeters recording the official competition altitude as well as deploying the main and
drogue parachutes consist of one StratoLogger and one Telemetrum altimeter. These are
commercially available barometric altimeters which meet all competition requirements. These
components have been used many times by the ISS team in the past, and their reliability has been
proven over countless flights.
All altimeters are attached to plywood sleds in their respective avionics bays. On the
opposing side of each sled, 9 volt batteries are fixed with zip ties to ensure stability. Connecting
wires run around the side of the sled and attach to the designated altimeter. Rotary switches which
have been inserted through the vehicle's airframe are also wired to the switch pins of the
corresponding altimeters. These switches allow for greater ease in turning the altimeters on and
off, before and after launch. In order for the ejection charge to function properly, the wires are
30
connected to the terminal blocks via a small hole in the bulkheads. They are attached to one side
of the terminal block, while an electric match is attached to the other side of the terminal block.
This allows for an easy attachment and integration on launch day, as well as providing a secure
connection. These electronic matches set off the ejection charges when triggered by the altimeters.
Electronic testing was completed throughout the duration of construction. Power lifetime
testing is crucial in order to ensure that the vehicle can maintain operation for over an hour. The
altimeters were turned on and left alone overnight to ensure that they had a sufficient power
lifetime
We also tested that the onboard electrical equipment wouldn't interfere with each other and
that nearby pieces such as the mortice latches, threaded rods, and rare earth magnets wouldn’t
interfere with the altimeters. This testing comprised of powering on all electronics in the same area
at a distance apart smaller than how they are installed into the coupler to add in a safety factor. and
then testing the functionality of each of the individual components. Tests confirmed that all
recovery equipment would function within the confines of the coupler.
Redundancy
Redundancy is another critical aspect that the team strived to employ in every part of the
recovery system. Redundant altitude measurement and ejection systems are vital not only to
mission success, but also to the safety of observers on the ground.
All ejection events are triggered by a primary and secondary charge, with primary charges
triggered by one altimeter and secondary charges by a separate altimeter. Each altimeter also has
its own power supply. The redundancy employed in the ejection charges ensures that even with
complete failure of an entire altimeter or battery, all parachutes still have a complete backup
system. The newly added charge-released locking mechanisms on the main parachute are also fully
redundant as well. There is a primary and a secondary mechanism, and again each is linked to its
own altimeter with its own power supply. In the event of failure of one altimeter or mechanism,
the other independent system should perform all the duties needed for a successful recovery.
Parachute sizing and descent rates
The ISS team completed sizing the parachutes in order to determine which parachute would
safely return the rocket to the ground in order for the rocket to be reusable. After the measurements
were taken, the ISS team took inventory of the numerous parachutes currently in the team’s
possession. The team determined the size through various simulations in OpenRocket and the
team’s personal simulation. Through those methods, it was determined that the suitable main
parachute would be the Iris Ultra 60” parachute. The simulated terminal descent speed for this
parachute was 18.7 ft/s. Through these simulations, it was also concluded that the 15” Fruity
Chutes parachute would be the best option for the drogue parachute, with a simulated descent
speed of 91.6 ft/s. Using these parachutes also keeps the rocket within the drift distances required
by the competition. ISS already owns and has used the 60” IRIS ultra in previous flights so the
team is confident in its performance.
Shown below in Figure 25 and Figure 26 are pictures of the chosen main and drogue
parachutes retrieved from the Fruity Chutes website.
31
Figure 25. IRIS Ultra 60 inch parachute.
Figure 26. Drogue parachute (15" Fruity Chutes).
In addition to the OpenRocket simulation data, terminal velocity calculations were
completed by hand. The terminal velocity equation is shown below:
𝑽𝑻 = √𝟐𝒎𝒈
𝒑𝑨𝑪𝒅
Where is the parachute’s terminal velocity, m is the mass of the components descending
under the parachute, g is gravity, p is the air density, A is the frontal area, and is the drag
coefficient. Below are the calculations for the main parachute and the drogue.
Main Parachute Terminal Velocity
m= 21.3 lbm (total)- 2.60625 lbm (propellant)-0.494 lbm (drogue parachute and shock
cord)-.834 lbm (main parachute and shock cord) = 17.37 lbm
g= 32. 174ft/s2
p= 0.0765lbm/ft3
32
A= πr2=(2.5)2= 6.25ft2
Cd= 2.2
VT=18.39ft/s
Drogue Parachute Terminal Velocity
m= 21.3 lbm (total)- 2.60625 lbm (propellant)-0.494 lbm (drogue parachute and shock
cord)= 18.2 lbm
g= 32. 174ft/s2
p= 0.0765lbm/ft3
A= πr2=(0.625)2=0.391ft2
Cd= 1.6
VT=88.257ft/s
If the vehicle lands with a terminal velocity under 25 ft/s, it is generally considered safe.
Both the OpenRocket simulated value of 18.7 ft/s and the hand-calculated value of 18.39 ft/sec
fall short of this upper limit. There is a 0.31 gap between the simulated and the hand-calculated
value, within an acceptable range for this stage in the design. It is also important that the vehicle
does not descend too slowly, as it will increase the drift distances and make retrieving the vehicle
more difficult. All calculated values prove that the vehicle will be within range of safe decent
speeds and will ease recovery of the vehicle post-launch.
Ejection Charge Testing and Shear Pins
Ejection charge testing was completed prior to the planned test flight of the full scale
vehicle. This process was done with the rocket in its launch ready state, including the loaded
parachutes. Fragile components were removed and replaced with a mass of its respective weight.
The only other change in testing compared to actual launches is that instead of connecting the E-
matches to the altimeters, there will be a wire running from the E-match to a remote firing system
controlled by the ISS team. This gives the team the ability to place the vehicle on a test stand and
remotely ignite the ejection charge in order to deploy the parachutes one at a time.
Shear pins are used to keep the vehicle intact before the ejection charges are fired, therefore
it is important to determine the proper amount of shear pins to use. The following line of logic was
used to determine the amount of shear pins to use at each joint:
Joint 1: Upper Airframe and Nosecone 1. Mass of objects that could force the nosecone out during flight:
a) 7oz nosecone
b) 1.6lb attachment equipment (quick links and shock cord)
c) 1.2lb main parachute
d) TOTAL: 3.2 lbs (worst scenario in which everything pushes on nosecone)
2. 50g jerk when drogue shock cord fully expands (generous estimate)
3. 150 lbf on nosecone (F=ma) 4. 4-40 Nylon screws have 50-70lbf of shearing strength 5. 3 Nylon Screws at Joint 1
Joint 2: Booster Subsystem and Coupler
33
1. Weight of sections that could separate early:
a) Coupler Subsection: 4.6lbs
b) Upper Airframe: 3.4 lbs
c) TOTAL: 8 lbs
2. 9g Drag Separation (calculated from OpenRocket data)
3. 72 lbf at joint
4. Safety factor of 100 lbf at joint
5. 4-40 Nylon Screws have 50-70 lbf of shearing strength
6. 2 Nylon Screws at Joint 2
During ejection charge testing, the ISS team also tested how easily the black powder charge is
able to break the pins. An iterative process was followed in which an amount was estimated amount
(using online calculators) and increased up 0.5g at a time until the shear pins reliably broke. It was
found that 1.5 grams for the drogue parachute (Joint 2 above) and 2 for the main (Joint 1 above)
was sufficient to break the shear pins. An increment of 0.5g was added to each charge to serve as
a backup in the event that the main charges fail.
Rocket-locating Transmitters
The team utilizing is the onboard Telemetrum for post-launch tracking, which uses a
frequency of 434.850 MHz (Channel 3) and has a range of 20 miles.
During the team’s planned full-scale test flight, both will get a fix prior to being inserted
in the rocket and properly lock onto a sufficient number (4+) of GPS satellites. To mitigate any
risk of a future failure, the team will be sure that all trackers used will have excellent battery
condition and acquire a good fix on their location prior to being inserted in the rocket.
Sensitivity of the Recovery System
The potential effects of electromagnetic interference were also considered during the
design and building of the vehicle. Any unwanted interference could be detrimental to electrical
components and consequently impact rocket performance, so the team tried to prevent this as much
as possible. The rocket only contains two transmitters that each produce a relatively weak
electromagnetic field, and additional components do not appear to produce excessively strong
fields either. All electrical wires were braided to mitigate the risk of interference, and team
members ensured that no onboard components are overly sensitive to any unpredictable outside
interference.
Parachute Sizing
The parachutes are attached on to the vehicle with the use of steel quick links, as stated
before. These quick links will have the parachute tightly knotted on one end and will attach to the
U-bolt on each side of the coupler. This allows for greater ease in attaching and removing the
parachute before and after launch.
The deployment system for this vehicle is based on a standard dual deployment system. At
apogee, set for around 5,280 feet, the primary altimeter located within the avionics bay will send
a signal to an E-match, igniting the black powder charge on the lower bulkhead of the avionics
bay. This black powder charge will break the shear pins connecting the avionics bay to the booster
airframe and allow for the drogue parachute to deploy. All vehicle components will remain
tethered together during this portion of descent. In the event that the ejection charge is not able to
successfully deploy the drogue parachute, a second altimeter will send a signal to a second E-
match, thus igniting another ejection charge. This signal will be sent a second after apogee. If the
34
first ejection charge does deploy the drogue parachute, the secondary charge will harmlessly ignite
in the open air. Figure 27 depicts the completed drogue parachute deployment.
Figure 27. Deployment of the drogue parachute.
After the vehicle has descended with the drogue parachute to 450 feet above ground level
as seen in Figure 28. The primary altimeter, located in the avionics bay, will send a signal to an E-
match, igniting a black powder charge. This system also uses a redundant deployment method
where all components are fully independent. For the case in which the ejection charge fail at 450
feet, a second charge will be utilized at an altitude of 400 ft. As stated in the changes since CDR
section, the parachute is now ejected from the nose cone. Therefore, when the black powder charge
is ignited, the shear pins between the nosecone and the upper airframe will break and the main
parachute will be released.
Figure 28. Deployment of the main parachute.
The drogue and main parachutes implemented in this vehicle have been used for previous
flights of Illinois Space Society Student Launch projects, and consequently team members have
significant experience with packing these parachutes such that they will properly deploy. With
vehicle construction complete, the team has determined the best method of packing the parachutes
and will include the detailed process within the preflight checklist.
35
Safety and Failure Analysis
Table 3. Safety and Failure Analysis
Risk Impact Probability Mitigation
Working with
tools and
machinery
Can cause physical
harm to team members
that can be permanent.
Low to
Moderate
Each member was required to take a
general lab testing course. The
members will also be trained to use
the tools and machinery by the
safety officer or other members.
Working with
black powder
There can be possible
injuries like skin burns
as well as respiratory
issues.
Low Black powder is only handled with
the team manager or any other
member with certification to work
with black powder.
Parachutes are
not deployed
Can be dangerous to
all participating in the
launch. The rocket
will crash into the
ground, rendering the
rocket unusable.
Low All team members are trained in
how to fold parachutes to minimize
entanglement and ejection charge
testing ensured that the sections
would properly separate
Component(s)
come loose
Either everything else
stays secure or the
component(s) knocks
other components off
Low All items are secured with nuts and
bolts. Other components will be
epoxied in order to ensure that all
components stay secure during
flight.
Parachute
deploys early
The flight could take
another path and drift
outside of the
designated safe area.
Low Multiple people are trained in
setting up and viewing the settings
for each altimeter. Before each
launch the team will consult
software and listen to the beeps
emitting from the altimeter to
confirm that the parachutes will
deploy at the right altitude.
Parachute does
not open all the
way
Can be dangerous to
all participating in the
launch. The rocket
will crash into the
ground, rendering the
rocket not usable.
Low to
Moderate
The ISS team has had a lot of
experience with wrapping
parachutes, and success during
previous launches. Team members
will make sure that the parachutes
are wrapped properly and will test
their deployment when testing the
parachute deployment system
during the test flight.
36
Vehicle Dimensioned Drawings Dimensioned drawings of the vehicle are shown below.
Figure 29. Dimensioned drawing of full vehicle.
37
Figure 30. Dimensioned drawing of the rocket fins.
Figure 31. Dimensioned Drawing of the coupler.
38
Figure 32. RMS 75/2560 motor case dimensions.
39
Mass Report Included in the table below is a breakdown of masses by each individual component. As
the team received materials and the components of the rocket, the masses were verified by the
team using a digital scale. Where parts occur in multiple quantities, the weight given is for the sum
of all of the given part. The only additional mass that will be added to the rocket after this point
will be to add paint to the rocket.
Table 4. Rocket Mass Breakdown
Subsystem Component (Quantity) Material Weight (lbs)
Booster Trapezoidal Fin (3) Fiberglass 2.53
Body Tube Blue Tube 2.0 1.59
Centering Ring (3) Plywood 0.06
Motor Mount Tube Blue Tube 2.0 0.45
Motor Retainer Assembly Aluminum 0.19
Fruity Chutes 15” Drogue Nylon 0.09
Drogue Shock Cord ½” Tubular Kevlar 0.4
Rail Button (2) Delrin-Plastic 0.03
K1000T Motor Assembly* Various 5.67
Epoxy West Systems 1.19
Ballast Lead BB’s and Epoxy 1.10
Booster Total 13.3
Coupler Body Tube Blue Tube 2.0 0.42
Switch band Blue Tube 2.0 0.23
Coupler Bulkhead (4) Plywood 0.46
Tube Bulkhead (2) Plywood 0.24
Eyebolt (2) Forged Steel 0.40
Eyebolt Nut (2) Aluminum 0.10
Eyebolt Washer (2) Aluminum 0.02
40
Stratologger Onboard Altimeter 0.03
Telemetrum Onboard Altimeter 0.03
9V Battery Duracell 0.11
Telemetrum Battery Li-Po 0.20
Battery Clip Plastic 0.05
Threaded Rod (2) Aluminum 0.28
Payload PVC Pipe w/ Sand 0.25
Rotary Switch (2) Plastic 0.03
Charge Cup (4) PVC 0.02
Avionic Sled (2) Plywood 0.20
Coupler Magnet (4) Iron Alloy 0.40
Shear Pin (6) Nylon 0.02
Union 2648 Tubular Latch Zinc Finish 0.44
Strike Plate/Wooden Block Plywood 0.10
Epoxy West Systems 0.11
Ballast QuickLinks 0.46
Coupler Total 4.6
Upper Airframe 4.00” X 16.5 Nosecone Polypropylene Plastic 0.72
Body Tube Blue Tube 2.0 0.86
Iris Ultra 72” Parachute Nylon 0.44
Shock Cord ½” Tubular Kevlar 0.4
Epoxy West Systems .06
Ballast QuickLinks .92
Upper Airframe Total 3.4
41
TOTAL
MASS
21.3
*K1000T Motor Assembly Weight is broken down as follows:
Table 5. Breakdown of K1000T motor assembly by mass
Component Mass (lbs)
Propellant 2.60
RMS-75/2560 Aluminum Motor Case 1.23
Misc. Material 1.84
K1000T Motor Assembly 5.67
Mission Performance Predictions Table 6. Drift Distances at Different Wind Speeds
Wind Speed [mph] OpenRocket Prediction [ft]
0 7
5 312.5
10 675
15 1,125
20 1,600
Worse-case analysis was also performed with a 5 degree launch angle (similar to the launch
rail that will be used) and 20 mph winds acting in the direction of travel. Even at these conditions,
drift was simulated to be 2,482 ft on OpenRocket and 2494 ft on the custom matlab script. A plot
of this data is included in the table below. The team is fully confident in the vehicle’s ability to
stay within 2,500 ft of the launch site come launch day.
42
Figure 33. Lateral distance in worst case scenario.
Kinetic energy of the vehicle during launch
In regards to energy, during launch, as the vehicle rises, the energy is primarily chemical
energy. As it continues to rise, it is converted to kinetic energy. Once the vehicle gets close to
reaching apogee, all of the chemical energy has been changed to kinetic and potential energy. As
the vehicle reaches apogee, almost all of the energy has become potential energy. During the
descent of the vehicle, most of the potential energy is converted to kinetic energy. Shown below
are the calculated kinetic energies during each phase of the rocket during its descent stage: with
the drogue parachute and during landing. These figures were calculated by hand using the
equation for kinetic energy below:
Ek=1/2mv2
Where is the kinetic energy, m is the mass of a given rocket sections, is the terminal
velocity of that respective rocket section. Simulated descent rates were used over the hand
calculated values since they were the larger of the two.
Kinetic Energy of Booster under the Drogue Parachute
m= 11.54 lbm=0.36 slugs
VT= 91.6fts
Ek=1/2(0.36slugs)(91.6fts)2= 1510.3ft-lbf
Kinetic Energy of the Upper Airframe Tube and Coupler descending with the Drogue Parachute
m= 4.6 lbm (mass of coupler)+3.4 lbm (mass of Upper Airframe Tube)=8 lbm= 0.250 slugs
VT= 91.6fts
Ek=1/2(0.250slugs)(91.6fts)2= 1048.82ft-lbf
43
Kinetic Energy of Booster upon Landing
m= 11.54 lbm= 0.358 slugs
VT= 18.7fts
Ek=1/2(0.3652slugs)(18.7fts)2= 57.7 ft-lbf
Kinetic Energy of Coupler upon Landing
m= 4.83 lbm= 0.15 slugs
VT= 18.7fts
Ek=1/2(0.15slugs)(18.7fts)2= 26.23 ft-lbf
Kinetic Energy of Upper Airframe Tube upon Landing
m= 3.54 lbm= 0.11 slugs
VT= 18.7fts
Ek=1/2(0.11slugs)(18.7fts)2= 19.23 ft-lbf
As shown by these calculations, no vehicle section is expected to exceed the 75ft-lbf
limitation of kinetic energy. The heaviest section of the vehicle is expected to fall about 20% under
the maximum energy limit. This certifies that the design has a large safety margin. Kinetic energy
will be measured using actual flight data following the test launch.
Stability Margin The location of the vehicle’s Center of Pressure was determined analytically through the
use of the Barrowman equations. These represent an analytical method of finding the center of
pressure based on vehicle geometry. These equations are given below.
Nose Cone Terms:
(𝐂𝐍)𝐍 = 𝟐
𝐗𝐍=0.466𝐋𝐍
Fin Terms:
(CN)F = [1 +R
R + S]
[
4 ∗ N ∗ (sd)2
1 + √1 + (2 ∗ LF
CR + CT)2
]
XF = XB +XR
3(CR + 2CT
CR + CT) +
1
6[(CR + CT −
CRCT
CR + CT)]
44
Center of Pressure:
Xbar =((CN)NXN + (CN)FXF)
(CN)R
(CN)R is the sum of the coefficients CNN+(CN)T+(CN)F. Xbar is the final answer found
through this analysis, and is a measure of the distance between the center of pressure and the tip
of the vehicle’s nose cone. The meanings of the quantities in the above equations are given
below.
The characteristics of the vehicle are given below:
Table 7. Vehicle Characteristics
Quantity Value (inches)
Ln 16.496
d 4.014
Cr 11.813
Ct 6.25
S 5.25
Lf 5.5241
R 2.007
Xr 4.5
Xb 77.438
45
Quantity Value (inches)
N 3
Note that the all transition terms are zero, since the vehicle airframe has a constant diameter.
(𝐂𝐍)𝐍 = 𝟐
XN=0.466*16.496 = 7.687 inches
(CN)F=[𝟏 +𝟐.𝟎𝟎𝟕
𝟐.𝟎𝟎𝟕+𝟓.𝟐𝟓] ∗ [
𝟒∗𝟑∗(𝟓.𝟐𝟓
𝟒.𝟎𝟏𝟒)𝟐
𝟏+√𝟏+(𝟐∗𝟓.𝟓
𝟏𝟏+.𝟔.𝟐𝟓)𝟐
]= 𝟏𝟐. 𝟎𝟔 𝐢𝐧𝐜𝐡𝐞𝐬
XF=𝟕𝟖. 𝟐𝟓 +𝟒.𝟒𝟎𝟓
𝟑(𝟏𝟏+𝟐∗𝟔.𝟐𝟓
𝟏𝟏+𝟔.𝟐𝟓) +
𝟏
𝟔[(𝟏𝟏 + 𝟔. 𝟐𝟓 −
𝟏𝟏∗𝟔.𝟐𝟓
𝟏𝟏+𝟔.𝟐𝟓)] = 81.79 inches
(𝐂𝐍)𝐑 = 𝟐 + 𝟎 + 𝟏𝟐. 𝟎𝟔 = 𝟏𝟒. 𝟎𝟔𝟒
Xbar= (𝟐∗𝟕.𝟔𝟖𝟕+ 𝟏𝟐.𝟎𝟔∗𝟖𝟏.𝟕𝟗
𝟏𝟒.𝟎𝟔𝟒) = 71.249 inches
The center of pressure as calculated above is 71.2487 inches from the tip of the nose cone.
This is very accurate when compared to the simulated value computed by OpenRocket, which
yields a center of pressure 71.299 inches from the nose cone. For the purposes of center of pressure
location, it is believed that OpenRocket is likely more correct than the manual calculation but
either result will prove sufficient for a stable rocket. Both of these calculations were derived from
actual measurements of the rocket following the completion of construction.
After the construction of the rocket, the actual center of gravity for the completed rocket
was determined experimentally by balancing the rocket after quick links were added for ballast.
This calculation resulted in a center of gravity of 62.125 inches. The OpenRocket and custom
simulator were subsequently adjusted to account for this new
The vehicle stability margin is defined as:
SM = (Cp-Cg)/D
where Cp is the center of pressure, Cg is the center of gravity and D is the rocket diameter. The
standard recommended stability margin is between 2 and 2.5 calibers, where a caliber is defined
as the rocket diameter. An under stable vehicle will experience aerodynamic moments detrimental
to the flight safety and stability, and an overly stable vehicle may turn into the wind causing an
elevated amount of horizontal motion to occur.
The OpenRocket simulation gives a simulated stability margin of 2.28 calibers. Using the
analytically derived Center of Pressure location 71.2487 inches, and diameter 4.014 inches, the
stability margin is calculated to be 2.27 calibers. Both of these values fall within the stable range
46
and gives confidence in the stability of the design. The team trusts both OpenRocket’s calculation
for the center of pressure and the one calculated by hand.
Figure 34. OpenRocket representation of vehicle.
Verification Table 8 given below lists all project requirements placed on the vehicle, as well as the
design features that satisfy these requirements and the methods of verification.
47
Table 8. Vehicle Requirements and Verification
Requirement Design Feature Verification Method Confirmation
Deliver payload to
altitude of 5,280 feet
above ground level.
The combination of the Aerotech
K1000T-P motor and vehicle
geometry will allow the rocket to
reach this target altitude.
Modeling, simulation, and
test flight. A barometric
altimeter will be used to
record official altitude.
Models were further refined after the
subscale launch and will their accuracy
will also be checked following the test
launch of the full scale vehicle.
Designed to be
recoverable and
reusable.
All materials used in
construction have been evaluated
for durability. The rocket will
utilize a dual deployment
recovery system to ensure that
each section of the rocket lands
with less than 75 ft-lbf of kinetic
energy.
Hand calculation of the
kinetic energy of each
rocket section upon
landing; adequate
construction techniques;
visual inspection for any
flaws in vehicle and
components.
Ejection charges were tested to reliably
separate the sections of the rocket. All
materials were inspected as they arrived.
Have a maximum of 4
independent sections.
During apogee and descent, the
rocket has been designed to
break apart into 3 independent
sections: booster, coupler and
upper airframe.
Modeling and visual
inspection.
There are only 3 sections
Rocket limited to a
single stage.
The rocket will only carry one
single-stage motor, the Aerotech
K1000T-P.
Modeling and selection of
correct motor.
There is only one motor installed
Capable of being
prepared for flight
within 2 hours.
Vehicle components such as the
motor retention system and
payload sleds have been chosen
to allow for quick assembly.
Assembly testing and
practice prior to launch
events.
In preparation for the test flight, the team
was able to assemble the full vehicle
minus the motor within an hour
48
Requirement Design Feature Verification Method Confirmation
Capable of remaining
in launch ready
position for 1 hour.
All power supplies are designed
to function for well in excess of
this time limit.
Testing all electronic
components to ensure they
have sufficient power
lifetimes.
As discussed in the recovery section, the
electronics were left on overnight to
ensure sufficiently long power lifetimes.
Capable of being
launched by a 12 volt
direct current firing
system.
The vehicle employs a standard
motor igniter compatible with
the standard 12 volt system.
Design and inspection. Igniter is designed for a 12 volt direct
current firing system
Use a solid motor
propulsion system
using APCP that is
approved and certified.
An Aerotech K1000T-P
reloadable rocket motor will be
used and has been certified by
the TRA.
Design and inspection. K1000T-P is still being used and follows
all certifications and rules
Total impulse provided
by the launch vehicle
should not exceed
5,120 Newton-seconds.
The total impulse of the
Aerotech K1000T-P is 2511.5
Ns.
Design and inspection. K1000T-P has a total impulse of 2511.5
Ns
Team must provide and
inert of replicated
version of the motor,
with matching weight
and size.
A hollow motor shell will be
produced and filled with ballast
to match the weight of the
functional motor.
Design and inspection The 3D-printed shell was filled with
ballast and weighed inside the motor
casing to match the weight of the
functional motor
Burst/Ultimate pressure
Vs. Max Expected
Operating Pressure
shall be 4:1, with
supporting design
documentation.
The vehicle does not contain any
pressure vessels.
Design and inspection. Vehicle does not contain any pressure
vessels
49
Requirement Design Feature Verification Method Confirmation
Pressure vessels must
contain solenoid
pressure relief valves
that sees complete
pressure of tank.
The vehicle does not contain any
pressure vessels.
Design and inspection. The vehicle does not contain any
pressure vessels.
Complete pedigree of
tank must be provided,
its history, number of
pressure cycles put on
the tank, by whom and
when.
The vehicle does not contain any
pressure vessels.
Design and inspection. The vehicle does not contain any
pressure vessels.
Launch and recover a
subscale model of the
full-scale rocket prior
to CDR that should
perform similarly to the
full-scale model.
A subscale rocket was
contruction and launched this
last December. The rocket was
about a 1:2 scale model of the
full scale and closely matched
the aerodynamics of the full
scale design at the time.
Subscale was successfully
launched and recovered on
December 19, 2015.
Shares a similar stability
margin to the full scale
design and is about a 1:2
scale model of the full-
scale.
Subscale was successfully launched and
recovered on December 19, 2015. Shares
a similar stability margin to the full scale
design and is about a 1:2 scale model of
the full-scale.
Prior to FRR, the full-
scale rocket shall be
launched and
recovered, in order to
ensure that the vehicle
and recovery system
function properly, in
fully ballasted
configuration, with no
The team has constructed and
properly ballasted the full scale
vehicle for launch.
With supervision of the
team’s NRA mentor, a test
flight is planned to safely
launch and recover the
vehicle.
Due to unforeseen weather conditions the
launch was delayed. The vehicle will
launch as soon as weather conditions
improve.
50
Requirement Design Feature Verification Method Confirmation
additional
modifications being
made after successful
completion of test
flight.
Maximum budget of
$7,500
The current budget of the final
system is $3851.30 and future
spending will be tracked to
ensure the limit is not exceeded.
Budget planning and
keeping track of expenses.
Current budget is still well within the
requirement
Deploy drogue chute at
apogee.
The primary altimeter will detect
when the rocket has reached
apogee. It will then trigger an E-
match to ignite the black powder
charge on the lower bulkhead of
the coupler, separating the
booster and coupler and
releasing the drogue parachute.
Modeling and testing of
parachute deployment
systems.
Test Flight will confirm if the drogue
chute deploys at apogee. Multiple people
are trained on the altimeters and have
repeatedly checked the settings of the
altimeter to confirm the deployment
altitude.
Deploy main chute at a
lower altitude.
The primary altimeter will detect
when the rocket has descended
to 450 feet. It will then trigger an
E-match to ignite the black
powder charge on the upper
bulkhead of the coupler,
separating the coupler and upper
airframe tube and releasing the
main parachute.
Modeling and testing of
parachute deployment
systems.
Test Flight will fully confirm if the
drogue chute deploys at apogee. Multiple
people are trained on the altimeters and
have repeatedly checked the settings of
the altimeter to confirm the deployment
altitude.
51
Requirement Design Feature Verification Method Confirmation
Each independent
section of the launch
vehicle shall have a
maximum kinetic
energy of 75 ft- lbf.
The main and drogue parachutes
were chosen to provide enough
drag to slow each rocket section
to a terminal velocity that
allowed for an acceptable
maximum kinetic energy. See
Kinetic Energy calculations in
Mission Performance Criteria
section.
Hand calculations of the
kinetic energy of each
rocket section upon
landing. To be confirmed
based on empirical test
data.
Velocity data from test launch will
confirm that the rocket will fall within
limits. More accurate models since CDR
give confidence that it will fulfill this
requirement.
Electrical circuits of the
recovery system shall
be completely
independent of
electrical circuits of the
payload.
The only function of the
recovery electronics are to
record the flight profile and
ignite ejection charges.
Design and inspection. Altimeters still serve the same purposes
The recovery system
must contain
redundant,
commercially available
altimeters.
Each ejection event is controlled
by fully redundant and
independent avionics
components.
Design and inspection. Altimeters are installed and tested.
Dedicated arming
switches shall arm each
altimeter from the
exterior of the rocket.
Both altimeters have a dedicated
rotary switch on the exterior of
the rocket.
Design and inspection. Rotary switches are installed on the
exterior of the rocket.
Altimeters must have
dedicated power
supplies.
Each altimeter has its own
battery power supply.
Design and inspection. The altimeters utilize different types of
batteries so sharing a battery is
functionally impossible
52
Requirement Design Feature Verification Method Confirmation
Arming switches must
be capable of being
locked in the ON
position.
The rotary switches chosen are
capable of being locked in the
ON position.
Design and inspection. Installed rotary switches require a
screwdriver in order to switch between
ON and OFF
Removable shear pins
shall be used for both
the main parachute and
drogue parachute
compartments.
Shear pins connect the booster
and coupler, which separate to
deploy the drogue parachute.
Shear pins also connect the
coupler and upper airframe tube,
which separate to deploy the
main parachute. A final set of
shear pins connects the upper
airframe to the nose cone.
Design and inspection. Removable Nylon shear pins are installed
between the coupler and booster tube and
the upper airframe and nosecone.
Electronic tracking
devices shall be
installed in the launch
vehicle.
The vehicle will utilize the GPS
capabilities of the Telemetrum
altimeter.
Design and inspection. Tracking capabilities of the telemetrum
have been intensively testing at different
lengths. Will be fully tested during test
flight.
Any untethered section
or payload component
shall have its own
electronic tracking
devices.
There are no untethered sections. Design and inspection. There are no untethered sections.
Recovery systems
electronics cannot
interfere with any other
on- board electronic
devices during flight.
No onboard components are
expected to interfere with the
recovery electronics or vice-
versa.
Interference and
functional testing of
recovery components
upon construction of
coupler.
As discussed in the interference section,
no onboard materials suffer from
interference.
53
Requirement Design Feature Verification Method Confirmation
Recovery system
altimeters must be
physically located in a
separate compartment
from other radio
frequency transmitting
and/or magnetic wave
producing devices.
Altimeters are installed into their
own bays, safe from any
interference from the magnets in
the payload bay.
Design and inspection. Altimeters are installed into their own
bays, safe from any interference from the
magnets in the payload bay.
Recovery system
electronics shall be
shielded from onboard
transmitting devices.
The recovery electronics are
located in a physically separate
compartment from the radio
frequency transmitter.
Design and inspection. The recovery electronics are located in a
physically separate compartment from
the radio frequency transmitter.
Recovery system
electronics shall be
shielded from devices
that may generate
magnetic waves.
The recovery system electronics
shall be shielded from the
crane’s electromagnet.
Design and inspection. The recovery electronics are located in a
physically separate compartment from
the payload bay.
Recovery system
electronics shall be
shielded from any other
devices that may
interfere with proper
operation of recovery
system electronics.
No onboard components are
expected to interfere with
recovery electronics. The
electronics are physically
isolated and shielded regardless.
Testing to ensure recovery
systems will function
when all electronics are
running.
As discussed in the interference section,
no onboard materials suffer from
interference.
54
Safety and Environment
Safety Officer
The safety officer this year is Andrew Koehler. He is a sophomore in aerospace engineering
with prior experience working with high power rockets. The safety officer will guarantee that each
member of the group is knowledgeable and informed on the risks inherent to their respective sub-
teams. Every member in the Structures and Recovery team and the AGSE team will complete
essential lab safety training and will be aware of the dangers of handling and disposing of
hazardous materials. As such, Material Safety Data Sheets (MSDS) will be provided for those
working with these dangerous components and materials. Personal Protective Equipment (PPE)
will also be required and provided to all team members working under any sort of risk, mainly
those operating machinery or handling lab substances. The safety officer will supervise all aspects
of construction and ensure that all involved are implementing the proper safety procedures. The
Engineering Student Project Lab (ESPL) will handle larger machinery that the Student Launch
team members do not have qualifications for to ensure that members do not handle equipment
above their training or experience level. In the event that the safety officer or the team mentor
cannot supervise a potentially dangerous situation, the project manager, team leader, or more
experienced individuals in the group are able to supervise and step in.
Before each test and launch of the rocket, all active and involved members will be briefed
and instructed on precautionary measures to remind them of the potential hazards with the launch
and recovery of a high power rocket. The team will coordinate with the local RSO (Range Safety
Officer) and the team mentor to schedule the test launches during the course of the year. A safety
code has been attached to the bottom of this document which will be read to all team members by
the safety officer and understood by all before any construction of the rocket occurs.
NAR Personnel Duties
The team mentor this year will be Mark Joseph (NAR 76446 Level 2), and he has flown
over 15 flights under this certification. Mark has been the Team Mentor for this University’s
Student Launch team in 2011-2012, 2013-2014, and 2014-2015 so he is familiar with the team and
has experience with high power rocketry competitions.
Mark is the team’s NAR mentor and is responsible for the acquisition of FAA permits for
airspace for the subscale and full scale test launches. The permits will provide assurance of clear
skies at the launch and ensure that there will be no impact on commercial aviation. In addition,
they will ensure the group’s compliance with the NAR safety code, which has been attached in
Appendix C. The team mentor will also be in charge of handling all dangerous materials. This
includes, but is not limited to, motor handling, construction, transportation, and use of black
powder ejection charges. The mentor will also be informed of design decisions and construction
work by the team and given the opportunity to provide feedback and suggestions to team members
for safety purposes.
Hazard Recognition
Before any post-design construction or manufacturing commenced on the project, the
safety officer provided a presentation on accident avoidance strategies and recognizing the dangers
involved with both the Structures and Recovery and AGSE teams. The safety officer, team mentor,
and experienced members will also give a presentation on the proper use of the tools and facilities
that will be in use over the course of the project.
The presentation will discuss the various risks that can be encountered while working that
are described above in the Risk Mitigation section. For example, AGSE team members, before
working with any electronics, will be briefed on the process of identifying an improper grounding
55
of a power source or an incorrectly wired system. The Structures and Recovery team would also
receive a briefing on structural dangers that may involve the improper handling of heavy metal
parts or equipment. The emphasis of this presentation will be on recognizing when a certain hazard
can be handled by the members if they are knowledgeable, by the team mentor or safety officer,
or if the situation must be brought to the attention of a higher official. Their safety knowledge will
be greatly enhanced and practiced through machine and lab training conducted by the most
knowledgeable members of the team, including the safety officer and team mentor if needed.
Powerful permanent magnets and electromagnetic components will be used by the crane
to place the sample in the hatch and by the hatch door to secure it during the rocket’s flight. The
Safety Officer will ensure that team members are aware of the dangers of having magnets near
electronics. Appropriate safety measures will be taken, including sealing the hatch section off from
the section with the electronics, ensuring that magnetic components are kept a safe distance from
electronic components.
Briefings will be conducted by the safety officer and team mentor before every test flight,
covering the present risks and hazards involved with launching a large, high power rocket.
This will be similar to the presentation covering general hazards of working with machinery and
equipment or electronics, but the pre-flight briefing will involve rocket launch specifics. A general
lesson of mindfulness will be emphasized, so that if any team member is ever unsure of what to
do in a potentially dangerous situation, they will take necessary precautions and alert the team
leader or a higher official if needed.
Law Compliance
The team’s safety officer will be responsible for educating all involved members of the
regulations regarding the use of airspace: Federal Aviation Regulations 14 CFR, Subchapter F,
Part 101, Subpart C; Amateur Rockets, Code of Federal Regulation 27 Part 55: Commerce in
Explosives; and fire prevention, NFPA1127, “Code for High Power Rocket Motors.”; as well as
all applicable laws. ISS will be contacting the FAA before any test flights are done, but only after
having approval from the local RSO. All of the flights will be suborbital, remain in the United
States, and be evaluated and deemed safe for all members of the team and community.
Only the team mentor will handle, purchase, store, and transport all explosives and motors.
There will also be fire extinguishers on hand in all locations where construction or storage will
take place. The team mentor and safety officer will brief the team on launch procedure etiquette,
as well as accident avoidance and hazard recognition. All team members will be required to review
and sign a team safety agreement and abide by the terms within, which include all pertinent laws
and regulations. Environmental regulations will be referenced during the course of this project to
ensure compliance. The group’s safety officer is responsible for finding these relevant regulations
for the handling and proper disposal of hazardous or environmentally harmful materials.
Motor and Energetic Device Handling
All handling of the motor and other energetic devices will be handled by the team mentor,
Mark Joseph, who has NAR level 2 clearance. Mark will also transport and store the motors for
all the team’s launches and tests. For insurance purposes, Mark will also be the sole owner of the
motor because he is the only one legally allowed to operate the motor and take on liability issues.
56
Preliminary Hazard Analysis
When considering hazards, it is appropriate to consider hazards to personnel as well as
hazards to the vehicle which are found in Table 9. Personnel Hazard Analysis An environmental
hazard analysis is included later on in the section. When doing a hazard analysis, it is appropriate
to consider the hazard, the cause of the hazard, and what the team can do to mitigate this hazard
when working on the rocket and launching the rocket. These hazards were identified partially from
prior knowledge and partially from the material data sheets found on the team’s documents
webpage. The probabilities of the hazard occurring is ranked on a scale from 1-5, the legend of
which can be found under the Preliminary Safety Analysis section. The severity of each hazard is
also ranked on a scale of 1-5, where 1 represents little to no harm being done, and 5 represents
irreparable damage being done.
57
Table 9. Personnel Hazard Analysis
Key Hazard Cause Probability Severity Mitigation
Verification (N/A is
marked if relevant to
rocket’s flight)
H1 Chemical
Burns from
the rocket
motor
Mishandling of
the rocket motor
and/or faulty
installation of the
motor
1 4 Ensure that the team mentor will
be working with all components
related to the motor, as per
regulations, and that the minimum
distance table in consulted before
all launches and tests of the motor.
N/A
H2 Burns from
black
powder
usage
Mishandling of
the black powder
or insufficient
tests done on the
black powder
1 4 Ensure that the team mentor will
be on hand to monitor the tests of
the black powder. Team mentor
will perform the actual handling of
the black powder charges.
N/A
H3 Skin
Irritation
Contact with
epoxy or other
hazardous
materials
1 3 Ensure that all team members that
work with material dangerous
enough to induce chemical burns
are wearing nitrile gloves and the
rest of their skin is covered.
Team members were safe
and careful with their use
of epoxy.
H4 Sensitization
to Epoxy
and
Dermatitis
Contact with
epoxy/ epoxy
fumes
2 4 Ensure that all team members
working with epoxy know not to
breathe in fumes from the epoxy
directly, especially if the epoxy is
highly concentrated.
Team members made
sure to not inhale fumes
while working with
epoxy.
58
H5 Bodily
injury from
heavy
machinery
Improper usage
of machining
equipment or
other tools
2 4 Each team member will be
required to take a general lab
safety course, and team members
using tools they have not used
before will be trained under the
supervision of the safety officer
and/or more experienced members.
Team members were
made sure to follow all
safety protocol and to ask
for help when needed
before using a machine
for the first time.
H6 Electric
hazard such
as electric
shock
Improper usage
of electrical
equipment
2 4 Ensure that all team members have
worked with sensitive electronics
before, and that proper grounding
procedures are followed.
Team members made
sure to always be aware
of the inherent danger in
working with electronics.
H7 Cuts from
rocket
assembly,
use of power
tools
Unsafe practices
in rocket
construction, like
the improper use
of power tools
3 2 Ensure that all team members are
handling power tools and other
tools properly according to the
relevant safety manuals.
Team members were all
properly trained before
they used power tools.
H8 Electric
hazards like
burns from
battery acid
Improper usage
of electrical
equipment
1 3 Ensure old batteries are thrown
out, and that new batteries are not
faulty. Sufficient testing of the
batteries is required.
Team members tested
batteries to make sure
that they were adequate.
H9 Debris from
fiberglass in
eyes
Improper sanding
procedures and
improper use of
PPE
2 3 Stress the importance of drilling
and construction safety, and ensure
that all members working on
sanding follow the safety
guidelines and wear Personal
Protective Equipment.
Team members always
wore safety glasses when
there was a risk of getting
debris in their eyes.
59
H10 Smoke
Inhalation
Members
working on
ejection charge
testing could
inhale smoke
from the charges
1 3 Ensure all members are wearing
personal protective equipment like
smoke masks and goggles. Also
make sure all charge testing is
done with the team mentor.
Team members always
ensured that the room
was properly ventilated
and that they did not
breathe in smoke.
H11 Dust
Inhalation
Members could
inhale dust from
cutting fiberglass
2 3 Ensure that all team members
working on materials with
fiberglass in them understand the
risks and use personal protective
equipment to cover their mouths
from the dust.
Team members always
ensured that the room
was properly ventilated
and that they did not
breathe in dust.
H12 Welding
burns or
damage to
eyes and
lungs
Improper welding
techniques could
cause damage to
the eyes or the
lungs, and also
could cause
severe burns
2 4 Before any member attempts to do
any welding, make sure they know
the risks associated with it, and the
things they can do to be safe when
welding, such as wearing masks,
ear plugs and gloves, as well as
welding with an experienced
welder before completing the first
attempt.
Team members made
sure that they knew what
they were doing before
trying any potentially
dangerous task.
H13 Hearing
damage
from
overuse of
power tools
Improper use of
PPE could cause
hearing damage
when using
power tools
2 2 Ensure that all members that are
going to use power tools wear ear
plugs so their hearing does not get
damaged in any way.
Team members always
wore ear protection when
using loud power tools.
60
H14 Getting
caught in
spinning
tools
Improper use of
spinning
tools/members
not paying
attention.
1 4 Ensure that all members read the
safety statement and be vigilant at
all times when dealing with any
spinning tools.
Team members were
careful and made sure not
to wear loose clothing.
H15 Inhalation of
solder fumes
Long duration
soldering in a
low/no
ventilation area
2 4 Ensure that the room is well
ventilated and that everyone
knows the risk of lead oxide vapor
inhalation.
Team members always
ensured that the room
was properly ventilated
and that they did not
breathe in solder fumes.
H16 Inhalation of
spray paint
propellant
Spray painting a
component with
no ventilation or
little to no airflow
1 4 Ensure that there is proper
ventilation and that all team
members follow the proper safety
measures.
Team members always
ensured that the room
was properly ventilated
and that they did not
breathe in fumes.
H17 Combustion
of spray
paint
propellant
Spray painting a
component near
an open flame or
electrical spark.
1 4 Ensure that there are no open
flames present and that all nearby
electrical components are shut off.
Team members made
sure that there never was
an open flame nearby.
61
The NESC Risk Matrix is a visual representation of the different situations that can
possibly occur. The red squares indicate high risk situations and these situations are to be avoided
whenever possible. The yellow squares indicate moderate risk situations, and the green squares
indicate low risk situations. Below the NESC Risk table can be found for the possible hazards.
NESC Risk Matrix
Pro
bab
ilit
y
5
4 H15
3
H7
2
H13 H9, H11 H4, H5, H6,
H12
1
H3, H8, H10 H1, H2, H14,
H16, H17
1 2 3 4 5
Severity
Environmental Concerns
There are many environmental concerns to be considered when launching from a field. For
instance, on launch day there could be too much wind, causing the launch to be delayed. It could
also have rained in the days before the launch, causing the ground to be muddy and soft. The day
of the launch could be cloudy and the team could potentially lose the rocket if the on board GPS
fails. In addition, the rocket could affect the environment through a rocket motor explosion or an
excess of exhaust, potentially damage its surroundings. If the rocket were to explode, debris would
be all over the field and be potentially harmful if cleanup is not done properly. The rocket could
launch and become unstable, thus posing a threat to nearby spectators and occupied areas. The
parachutes of the rocket could not deploy and cause damage to the surrounding environment
because the rocket then would not be able to achieve a soft landing. There are also several
environmental concerns to be considered during the building of the rocket and AGSE system.
Below are tables of both the effect of the environment on the rocket and the effect of the rocket on
the environment. The impact of these effects and mitigation to the effect are also tabulated. Also
tabulated is the probability of the environmental effect (ranked 1-5 with the legend being found in
the Preliminary Safety Analysis section), and the severity of each environmental effect. A 1
represents no significant environmental effect, and 5 represents a catastrophic environmental
effect.
62
Table 10. Environmental Hazards on the Rocket
Key Environmental
Concern
Impact Probability Severity Mitigation
E1 Wind Too much wind could cause the
rocket to go off target and sight of the
rocket could be lost during the flight
2 3 Delay launch until the wind dies down and
the Field Safety Office gives the go.
E2 Rain before the
launch causes
mud on launch
pad
Could cause the AGSE and/or the
vehicle to sink into the mud, causing
complications of the launch
1 3 Delay launch until conditions are desirable
or move the launch pad to a different area.
E3 Rain on launch
day
Could cause complications with the
AGSE equipment
1 3 Delay set up until rain stops and the Range
Safety Officer gives the go for launch.
E4 Too much cloud
cover
Too much cloud cover could make
locating the rocket difficult if the on
board GPS fails
1 2 Test the GPS to make sure it isn’t faulty as
well as make sure the conditions for
launch are desirable.
E5 High
Temperatures
Different components of the rocket
could warp or overheat
1 4 Keep the rocket in a climate controlled
environment for as long as possible and
don’t bring it into extreme heat
E6 Low
temperatures
Different components could become
icy and fail, or collect condensation
1 3 Keep the rocket in a climate controlled
environment for as long as possible and
don’t bring it into extreme cold
E7 Terrain Different bodies of water or trees
could affect the rocket when it comes
down.
2 4 Ensure the area that is being launched into
has no such terrain issues.
E8 Lightning during
launch day
Could hit the rocket causing damage
to it.
1 3 Do not launch when lightning is present or
even might be present.
63
Table 11. Environmental Hazards on the Environment
Key Environmental
Concern
Impact Probability Severity Mitigation
E9 Rocket Explosion If the vehicle explodes it
could set fire to the
surrounding area and/or cause
bodily harm to the bystanders
1 5 Make sure the team mentor helps in testing
the motor significantly so it is known for
certain that the rocket is safe
E10 Unstable Rocket
Launch causing
damage to
surrounding area
An unstable launch could
cause the rocket to go off its
targeted trajectory and could
do damage to the surrounding
area
1 4 Make sure the launch pad is very stable by
checking the conditions of the ground and
proper testing of the AGSE system.
Ell Parachutes don’t
deploy or deploy too
late
The rocket will come crashing
down and possibly cause
damage to the environment of
the bystanders
2 4 Proper testing of the black powder charges
will occur to ensure the parachutes deploy
on time.
E12 Failure to recover the
rocket
The rocket will stay lying in
the surrounding environment
causing potential damage to
farm equipment and wildlife.
1 2 Ensure GPS is working as well as tracking
the rocket through the air.
E13 Fire from motor
exhaust
A fire could happen if field
conditions are dry enough,
causing damage to the
surrounding environment and
possibly the bystanders
2 4 Ensure people are clear of the exhaust,
there is a large enough blast plate to deflect
the flame, and make sure the surrounding
environment isn’t significantly flammable.
A fire extinguisher will be located nearby
in case a fire does occur.
64
Key Environmental
Concern
Impact Probability Severity Mitigation
E14 Battery acid leak Harmful acid could get into
the ground causing damage to
the field and possibly local
wildlife.
1 3 Make sure proper cleanup procedures
would be followed in the event of a leak
E15 Vapors produced
from soldering
During the soldering of wires
lead oxide vapors are
produced that are toxic to
those that inhale it.
4 1 The amount of soldering that needs to be
done will produce a minimal amount of
harmful gas.
E16 Harmful substances
getting into
groundwater
Improper disposal of batteries,
solder, and chemicals could
contaminate the groundwater
and cause health concerns for
those that use that water.
1 4 All necessary precautions are in place to
ensure the proper disposal of any
substances deemed harmful to the
environment.
E17 Aerosol from the
spray paint
The propellant used in spray
paint cans is harmful to the
ozone layer and can increase
global warming
5 1 The amount or aerosol being released into
the atmosphere is minimal from the few
cans of spray paint that will be used. The
cans will also be checked to ensure they
use LPG propellant rather than the more
damaging CFC.
E18 Improper disposal of
non- biodegradable
material
Materials such as plastics,
fiberglass, and left over epoxy
will not degrade if sent to a
landfill, and could be harmful
to animals in the future.
2 2 Care will be implemented to ensure proper
recycling and disposal of leftover materials
65
Below the NESC Risk table can be found for the possible environmental hazards, the guidelines
of which can be found at the beginning of this section.
NESC Risk Matrix
Pro
bab
ilit
y
5 E17
4 E15
3
2 E18 E1 E7, E11,
E13
1 E4, E12 E2, E3, E6, E8,
E14 E5, E10, E16 E9
1 2 3 4 5
Severity
Safety During Construction
During the construction process safety was the number one priority. Everyone involved
with hands on work used PPE and followed all of the lab safety rules. For example, team members
were careful when using power tools and made sure to always wear gloves and have proper
ventilation in the room when using epoxy. Fortunately, there were no accidents or injuries during
the construction process. This is a validation of the safety plan and construction methods outlined
previously.
Payload Integration The AGSE system, more specifically the crane, will work first to place the sample into the
hatch door. Then the crane will place the entire hatch door onto the rocket, guided to the correct
position by 2 magnets on each side of the hatch door and corresponding internal magnets placed
along the lip of the hole (created by the tube of the coupler as a result of cutting a smaller hole into
it than into the switchband). As the hatch door is placed, mortice latches inside the bay will
interface with strike plate blocks on the hatch door and lock the door into place for the duration of
flight. These latches can be disengaged after flight via holes cut into the coupler tube and the
insertion of rods to unlock them.
There will be an interface physically, as well, between the vehicle and the AGSE. The
vehicle will be connected to the AGSE system via rail buttons that are meant to slide up and down
the rail. This connection will allow the AGSE to raise the vehicle to the five degrees off of vertical
and also give it guidance when it is launched. From the perspective of the rocket and the rail, this
system is no different than the interface between a standard high power rocket and a launch rail.
This significantly simplifies integration procedures.
66
The other way the vehicle interfaces physically with the AGSE is through the ignition
system. The AGSE will autonomously interface with the vehicle when the igniter system is used
to insert the igniter into the vehicle’s motor. This interface is necessary to ignite the motor which
makes the ignition system a critical portion of the AGSE’s design. This interface requires the
vehicle be held steady during the igniter insertion. As the vehicle is fixed to the rail, the motion is
restricted by default.
The payload containment bay itself is composed of Blue Tube and high strength aircraft
grade plywood. The housing is slotted on guide rails to fix the assembly in place. All permanent
attachments are reinforced through the use of high strength epoxy.
IV) AGSE/Payload Criteria
Figure 35. Fully assembled AGSE system with the rocket in the 5 degree from vertical
launch position.
Selection, Design, and Verification of Payload
System Review
The Autonomous Ground Support Equipment (AGSE) system is designed to collect a
sample, place it firmly in the rocket, raise the rocket from a horizontal orientation to a vertical
orientation, and insert the igniter into the rocket motor. The sample will be collected from a
67
predetermined location and orientation, so the autonomous movements of the system are all
preprogrammed and are not dynamic.
A successful run of the system will see the sample payload lifted from a predetermined
position 12 inches away from the AGSE and outer mold line of the launch vehicle and placed
safety into the hatch. Following this, the rocket will autonomously raise to a position 5 degrees
off of vertical. The igniter will be positioned to the top of the motor fuel grain within the rocket
and then the system will await launch approval from the range safety officer. The AGSE system
is divided into five subsystems which all function together to complete the operations listed
above. The remainder of this section contains a brief system description, while the following
sections describe each of these subsystems in greater detail.
The first of these subsystems is the sample collection crane, which contains the sample
collection arm with its imbedded hatch door. This system is required to perform the actions of
collecting the sample, and firmly attaching the sample and hatch door to the rocket body. The
sample collection crane consists of an aluminum base made primarily of the same 8020 rail used
for the launch rail system. The actual crane will be constructed on a rotary steel bearing, made
primarily of carbon fiber tubes. The two degrees of freedom of this crane will be controlled by
belts attached to stepper motors. An electromagnet will be placed on the end of the crane and
used to hold the hatch and clip system into place until it is powered down.
Second is the launch pad and rail system, which contains the main structure of the launch
pad, as well as the rail that is used to hold the rocket straight during its ascent. The launch pad
and rail system also includes the rail support placed several feet out from the pad itself which
supports the rocket and rail in the horizontal start orientation. The launch pad system is
constructed of aluminum 8020 rail with a 1” thickness. The launch pad itself is constructed of ⅜”
steel to withstand the blast of the rocket engine. The launch rail uses a thicker 1.5” 8020 rail to
hold the rocket stable during the first several feet of flight.
Next, the igniter subsystem is located on the base of the launch pad, and is used to insert
the motor igniter prior to launch. This system consists of a linear actuator that performs the
insertion, as well as a bent aluminum piece that is used to hold the igniter below the motor.
Fourth, the hatch and clip system that is used as the end effector of the robotic crane. The rocket
hatch is included within this system, as it is directly used to pick up the sample before being
attached to the rocket. The hatch itself is made of blue tube, as it will be cut from the rocket
body. Magnets will be included into the top and bottom of this hatch piece to allow for
attachment both to the crane and to the rocket body.
The fifth subsystem is the electronics system which controls and powers all of the
components in the above three systems. This system is controlled by an Arduino and several
motor controls. A series of limit switches, resistors, LED’s, and momentary switches will also be
implemented to accomplish mission goals. Along with these, two stepper motors, two linear
actuators, and one electromagnet will be integral to the AGSE’s success. The electronics are all
powered by a 3 cell Lithium Polymer battery.
The creativity in the team’s design comes from the electromagnet and hatch system. It’s
innovative design allows the team to overcome the challenge provided by a non-gravity assisted
system. It still allows for direct placement of the payload without letting it fall. That aside, it’s
different from a basic claw/crane system design. Because the system’s retrieval capabilities is
based around an electromagnet, it is possible to change the hatch to something that can pick up a
payload of many different shapes and sizes, making the design malleable and adaptable. A step-
by-step procedure for the AGSE system can be found below:
68
1. The robotic crane will start with the electromagnet situated above the hatch door.
2. Power is run through the system, activating the electromagnet and attaching the hatch
to the electromagnet.
3. The robotic crane will rotate to a position over the payload.
4. The vertical arm piece will lower and push the clips securely onto the payload.
5. The vertical arm will rise back up to a height just above the rocket.
6. The crane shall then rotate over to the vehicle.
7. The vertical crane piece will be lowered into the vehicle bay.
8. When the hatch door is flush with the vehicle, the magnets inside the rocket will grip
the steel on the hatch door.
9. A tubular latch bolted on the inside of the rocket will slide and lock the hatch, securing
it firmly in place.
10. Power to the electromagnet will be shut off, releasing the hatch from the crane.
11. The vertical crane piece will be raised slightly, in order to avoid contact with the
rocket when the crane rotating away from the rocket.
12. The crane will rotate away from the rail system and vehicle.
13. The rail system actuator will raise the vehicle to a position of 5° off of the vertical.
14. The igniter system actuator will raise the dowel rod until the igniter is in the tube,
triggering a limit switch when enough pressure is applied.
Figure 36. Assembled AGSE system in horizontal position without rocket.
Mission Success Criteria
The primary goal for the team is the safe retrieval of the payload, placement of the payload
in the rocket, and successfully preparing the rocket for launch by rising the rail system to 5 degrees
off the vertical and then inserting the igniter into the vehicle. Mission success is achieved when
the payload is safely and securely placed into the vehicle, the vehicle is correctly angled to its
69
launch position, and the igniter is correctly inserted into the vehicle. An essential aspect of the
AGSE system is reusability. All parts shall be undamaged and not require human interaction
between each run. This is achieved by meticulous testing to assure no subsystem is damaged. With
everything being automated, there is no need for outside interference except during the initial
setup. All subsystems are isolated and monitored through the Arduino, to ensure that no subsystem
is a threat to any other subsystem. The team has also implemented LED lights to indicate activity
and power. This is a vital safety measure, both for the structure, and the team operating the
structure, giving a clear and concise idea of what is going on.
The purpose of the AGSE system is imitating a sample return mission on Mars, or
somewhere else with gravity significantly less than that of earth. Because of these constraints,
the AGSE is designed to be gravity independent, atmosphere independent, magnetic field
independent, and fully autonomous. The AGSE will be able to pick up a sample payload and
place is in a rocket, just as it would in a sample return mission. The conditions during the
competition are not the same as the conditions on Mars so the test is not perfect. However, the
design would still function in a Martian environment. Some of the components would need to be
swapped for similarly functioning ones due to radiation and extreme temperatures but the cost of
such components is too high for this project.
The rocket is not the size of a rocket to land on Mars or elsewhere, but the design of the
payload holding system could be scaled up for an actual Mars mission rocket. The rocket used
for the competition will show the design used in the system could be implemented in a sample
return mission.
A potential flaw in the accuracy of the system with relevance to the Mars simulation is
the team’s assumption that the ground will be flat, and that the payload will be stationary in a
specific radius from the crane. In a realistic situation, it would be difficult to place the payload or
crane system in a position where the crane could reach the payload. Again, this is under the
assumption that this operates on a flat surface.
The mission will be considered successful if the AGSE system is able to pick up the
sample, secure it in the rocket, lift the rocket, and ignite the rocket all autonomously. The success
will be measured visually by seeing the payload is secured in the rocket and with a digital level
to ensure the correct final position of the rocket.
AGSE Design and Subsystem Overview Crane System
The base for the robotic crane system is a 1’x1’x2’ rectangular prism made up of 1” square
80/20 rails. There is a 1’ square aluminum plate with a thickness of ⅛” attached to the top of the
base and a wooden shelf with dimensions 12”x10”x1/4” mounted inside this base to hold
electronics. This shelf was chosen to be wood to prevent issues with shorting out the electronic
components on a metal plate. It also allows for easy mounting of electronic components as the
material is simple to drill through. Wood is also lightweight which is important to make sure that
the AGSE is under the competition weight limit.
70
Figure 37. Electronics and mounting plate showing all of the motor drivers.
A 4” steel turntable is mounted to the center of the top aluminum plate. An ABS plastic 3D
printed mount is attached to the top of this turntable using four screws. This mount has a square
1” hole which holds a square carbon fiber tube. A NEMA 17 stepper motor attached to a 3D printed
mount on top of the aluminum plate operates a gear and chain system attached to this carbon fiber
segment, giving the crane a full 360 degrees of rotation using the steel turntable. Surrounding the
vertical crane piece is a 3D printed gear, wrapped around by a bike chain fitted to the teeth of the
gears. The chain will loop around to the motor and another gear, allowing the crane to rotate on
top of the ball bearings.
71
Figure 38. The drive system that allows the crane to rotate.
The horizontal segment of the crane arm is a 1” square carbon fiber tube mounted on top
of the first segment. This mount is a custom made ABS plastic 3D printed piece which allows for
the attachment of both carbon fiber rods, and also has a mount for the second NEMA 17 stepper
motor.
At the end of the vertical carbon fiber tube is another custom 3D printed piece, where two
0.25” diameter carbon fiber rods are run through in a vertical orientation. This 3D printed mount
has two sets of two holes offset vertically to constrain the movement of the carbon fiber rods to a
single dimension. At the top end, the rods are held stationary together with a 3D printed cap that
is press-fit onto the ends of both rods. At the bottom, they attach to the electromagnet via an ABS
plastic 3D printed piece. The rods are epoxied into place on this end, and the electromagnet is
attached to the same piece via two screws.
A NEMA 17 stepper motor is attached to the rear of the horizontal carbon fiber tube with
a plastic mount. This stepper motor controls a pulley system that extends above and below the
horizontal crane arm, through a slot cut in the first vertical carbon fiber tube, and attaches on one
end to the aluminum cap and at the other end to the mount of the electromagnetic hatch system. A
diagram of the robotic crane system is shown below.
72
Figure 39. Top view of dimensions for AGSE.
Figure 40. Robotic crane system for sample placement.
Rail System The rail system harbors the rocket horizontally and secures it via rail buttons until the crane
system places the payload within the rocket. The system then the raises the rocket from its
horizontal position to 5° off vertical for launch. When that final position is reached, a limit switch
is triggered to tell the Arduino computer to halt movement of the actuator. Due to the design of
73
the actuator, even when the power is cut to it there is enough friction within the gears of the actuator
itself to keep the rail secure and the actuator locked into position. There is concern for the wobbling
of the system as the rocket raises due to the length of the rail and the weight of the rocket. To
address this problem, there is a stabilizing rail attached to the base of the system extending in the
same direction as the rail holding the rocket. This rail ensures that the system will not tip over
because the center of gravity of the system is not outside the base railing. When the AGSE was
tested to raise the rocket, very little out of plane movement occurred and the system proved to be
stable.
Figure 41. Mechanism to lift the launch rail and rocket.
The system is comprised of the following: an 8’ long 1.5” thick rail made from 80/20
aluminum; a linear actuator with an 18” stroke and 400 lbs of maximum output force all powered
by a 12V DC motor; the stabilizing rail and three hinges to connect the rail to the base plate; the
rail to the actuator; and the actuator to a base stabilizing rail.
The base of the actuator is placed 4.6” in front of the hinge on the base plate and is 24.3”
below it. The tip of the actuator is placed about 20.1” along the launch rail giving the actuator an
unextended length of 28.8”. For simplification in force calculation, the maximum extended
length of the actuator was conservatively calculated when the rail is perfectly vertical, as
opposed to 5° off vertical. At this extended length the actuator will be 39.1”. This means that
with the actuator extending at 0.6” per second, the total runtime of the system is approximately
17 seconds.
74
Figure 42. Actuator in position to raise the rail.
The 80/20 aluminum was chosen for the rail because it is strong enough to support the
weight of the rocket, lightweight enough so as to not impose weight penalties as per competition
restrictions, and it is relatively cheap and reliable. The 8’ rail weighs 10.75 lb and has a center of
mass 4’ from the pivot point; the rocket weighs 22.51 lb and the base of the rocket rests 6” above
the pivot on the base plate. This puts the combined center of mass for both the rocket and the rail
at 41.57” from the pivot on the base plate. The base stabilizing rail is intended to keep the AGSE
from tipping over, so the rail extends after this point to ensure stability as the rail is relatively
lightweight and does not add any volume to the system.
Using Python, the geometric constraints, and the weights of the components, the force
exerted by the actuator on the rail was found and plotted as an equation of time and can be seen
below. The maximum force needed by the actuator is only 82.75 lb which is significantly lower
75
than the team’s previous, successful design. This difference is due to the rail being ⅔ the length
of last year’s and the rocket being both smaller and more lightweight. The script for this
calculation is located in Appendix D.
Figure 43. Force vs. Time for actuator lifting the rail and rocket.
Figure 44. Dimensions of launch pads with segments cut out to lower mass.
76
Igniter System The igniter is attached to the end of a wooden rod which is inserted into the rocket. The
rod then goes into a plastic connection piece designed to hold the rod above the limit switch,
which is attached to one end of a piece of aluminum in a “Z” shape. A linear actuator is attached
to the other end of the “Z” piece. This configuration ensures that the linear actuator will be far
enough away to not be damaged when the rocket is fired. The linear actuator has a 24 inch stroke
and a strength of 35 pounds force which is sufficient to raise the igniter and insert it into the
rocket and more than sufficient to lift the igniter, wooden rod, and “Z” piece. Out of the insertion
point there is a cone to guide the igniter to the proper spot and ensure it enters the motor. The
igniter will start just above the launch pad through a hole created to allow the passage of the
igniter and wooden rod. The linear actuator moves at a speed of 0.6 inches per second, so it will
take approximately 40 seconds to lift the igniter the full 24 inches into the motor. Once the
igniter reaches the top of the motor it will trigger the limit switch attached to the rod and the
linear actuator will stop. The connection piece ensures that the limit switch will not be pressed
as the linear actuator is raising the wooden rod. The friction between the inside of the piece and
the surface of the wooden rod is sufficient such that the rod will not move farther into the
connection piece until the top of the motor is preventing it raising any higher. This will not only
ensure the igniter gets all the way to the top of the motor, but will also stop the igniter if it got
caught on anything inside the motor so as not to cause damage to the fuel grain. The whole
system is tilted to a five degree angle from the vertical to match the rocket in its final position.
Figure 45. Ignition system lowered and ready to raise.
77
Electromagnetic Hatch System
An electromagnet is used to pick up and deposit the hatch onto the body of the rocket. This
system allows the hatch to detach cleanly from the AGSE without the use of any unreliable
mechanical components.
The electromagnet is powered by the same 12 V Lithium Polymer battery that services the
other components of the AGSE system. The logic of when to turn the electromagnet on and off
will be handed by the same Arduino Mega that is controlling the motors in the crane system. A
relay will be wired to a digital pin on the Arduino that way the 5 V signal of the Arduino can
control the more powerful 12 V supplied to the electromagnet. Since the physical design of the
clips and the precision of the stepper motors involved allows the AGSES system to run without
any complicated sensors (Cameras, IR, pressure, etc.) there is no decision making for the system
to spend valuable time and power on. Its dimensions are shown in Figure 46 below. The magnet
is mostly rectangular, with a few divots for screws and a connector for wires, shown in blue.
Figure 46. Dimensions of the electromagnet (inches).
The AGSE system is designed so that the hatch-piece (consisting of the rectangular piece
of Blue Tube), plastic clips, steel strip, and 4 permanent magnets--starts clip-side-down on the
ground. The crane, consisting of the electromagnet and guiding piece, is then lowered into position
over the hatch-piece. The Arduino then sends a 5 V signal via digital pin to a relay, causing 12 V
of power to be sent to the electromagnet, turning it on. The guiding piece here will ensure
consistent orientation of the hatch-piece when attached to the electromagnet. The crane then moves
this whole assembly (now consisting of clips, steel strip, permanent magnets, Blue Tube,
electromagnet and guiding piece) over top of the payload. The assembly is then lowered onto the
payload, causing the clips to grab the payload and clip it into place. The crane then lifts upward,
and positions the apparatus over top of the hole in the rocket. The hatch-piece with attached
payload is then slowly lowered into its position. The permanent magnets on the hatch-piece will
help it snap into position, and the latches on the rocket will cause the hatch to lock into its proper
position in the rocket. The electromagnet is then shut off via the Arduino, and the arm of the crane
(now consisting of only the magnet and guide-piece) is moved out of the way of the rocket before
the rails lift it into launch position.
The piece of Blue Tube cut out to make the hatch is geometrically described as a segment
taken from a hollow cylinder. Seen from the top, it is a 6 inch by 2 inch rectangle with the 6 inch
side along the long axis of the rocket. The weight of the hatch-piece is approximately 0.03 pounds.
For the hatch, Blue Tube was chosen because the most logical way of making a hatch that fits
perfectly into a hole cut into the side of the rocket is to use the piece that was cut. Since it was
decided Blue Tube was the best material for the main body of the rocket, by extension, the hatch
was Blue Tube as well.
78
Figure 47. Mechanism of the electromagnetic hatch and clips to pick up payload
Figure 48. The clips attached to the payload which will eventually be attached to the hatch
The steel strip is a 3” by 1” by 1/10” strip of metal attached to the underside of the hatch,
between the clips. Steel was chosen because it is cheap, common, and ferromagnetic. This piece
was added so that the electromagnet will have something to cling to on the hatch itself. The team
used plain steel and not permanent magnets so that when the time comes for the crane to let go of
the hatch, the bond could be easily severed by turning off the electromagnet, and not having to
worry about the hatch sticking to the crane. It is estimated to weigh approximately 0.02 lbs.
79
The purpose of the guide piece is to ensure that when the electromagnet picks up the hatch
and temporarily attaches it to the crane, that the orientation of the hatch and clips is the same every
time. This will allow more precision when fine-tuning the AGSE commands. The material for the
guide piece needed to be easy to work with, and strong enough to attach the vertical arm bar of the
crane to. The guide piece will be an arc of steel designed to fit over top of the Blue Tube. It will
be 1/10” thick, 5” long, and 1 ⅜” wide and have a weight of 0.20 lbs.
The use of ABS plastic in the clips was because the task required a strong material that
could be easily formed into the specific shape, and have some flexibility to it. Since the Illinois
Space Society has ample access to 3D printers, a 3D printable plastic was the obvious choice.
Additionally, using 3D printed ABS allows for cheap rapid prototyping, meaning many minor
variations of the gripper design can be tested, and the design can be fine-tuned for maximum
reliability. Weight estimates are 0.02 lbs each, 0.04 lbs for both clips combined. The exact weight
of the clips will be dependent on the 3D printing fill percentage that produces the most reliable
results.
Iron alloy magnets were significantly cheaper than their rare earth counterparts, and are
strong enough for these needs. Additionally, the magnets could not be too strong, as too strong of
a magnet would run the risk of interfering with the flight electronics. They are 0.01 lbs each, a
total of 0.04 lbs for four of them. Last year, two of these magnets were used to keep a hatch door
on a hinge shut. These were the same magnets in the same position relative to the flight electronics.
This produced no interference with the flight equipment. However, in the unlikely event that
testing reveals the magnets interfere with any flight electronics, the addition of the mortice latches
means the strength of the magnets could be decreased and the latches would still hold the hatch
door in place.
The mortice latches were a change added from PDR when one of the reviewers brought up
the concern that the magnets were not enough to prevent the hatch door from flying off during the
launch. Mortice latches were chosen for their reliability and one-way operation. They allow the
crane to easily slide the hatch into place, but make it incredibly difficult for the hatch to fly off
during launch. This system is speedy and effective, allowing a safer launch while only sacrificing
negligible AGSE speed. They weigh 0.22 lbs each. Dimensions are in Figure 49.The latches will
be modified so that they do not interfere with the rest of the operation.
Figure 49. Dimensions of the latches
80
Electronics The entire electronics subsystem will be powered by a single 11.1 V 5200 mAh Flite Pro
LiPO battery, with all of the programming being operated through an Arduino Mega. The
Arduino will be wired up to a solderless breadboard, with all other electronic components wired
up to said breadboard. This includes the two Nema 17 Stepper Motors, an electromagnet, two
linear actuators, two limit switches, and two LED indicators. Finally, there will be a handmade,
wooden control box housing the safety switches and LED indicators. One indicator will be
orange, lighting up when there is power to the system. If the system is active, it will blink, and if
the system is paused it will stay a solid orange. The other LED shall be green to show when the
system is finished and ready to launch.
Along with the LED lights, the wooden controller has two switches, a master switch and
a pause switch. The master switch shall be placed in series between the battery and all other
components. With that in place, the operator of the AGSE system will then have the ability to cut
power to all AGSE components instantly in the case of an emergency. This switch will be used
to activate the system and later to completely shut it down. The other switch is a push-button
pause switch, which can pause the system at any time and then be resumed by triggering the
switch again. Due to the importance of the LED indicators and the switches, power will be
supplied to LEDs at all times and be constantly updated to match the state of the switches. Both
limit switches and the pause switch will have pull up resistors so that a steady signal is read by
the computer. Further LED’s may be added to ensure power is reaching all aspects of the AGSE
system as well to show that switches are in working order. The wattage at all of the limit
switches and the pause switch will be minimal because they are used for signals. The LED’s also
have a small consumption of 100 mW per diode. For the master switch the largest wattage it
would experience would be no more than 200 Watts, the sum of the total power draw of all
components.
For the sample retrieval system, two electric motors will be connected to motor
controllers that will in turn be controlled by the Arduino. The first of these stepper motors will be
placed at the base of the main tower for the crane, allowing the crane to rotate the horizontal arm
from a position over the payload to one above the hatch. The second would be higher up on the
tower, and through use of a belt will allow the crane to raise and lower vertical arm holding the
hatch. The lower motor is stationary and will not require any kind of special wiring
considerations. Wiring for the motor on top of the first vertical piece will be run up through the
central carbon fiber tube, allowing free rotation of the crane without putting the wires at risk of
breaking.
An electromagnet will be attached to the end of the vertical bar, and will be used to pick
up the payload. The wiring for this electromagnet will be run up though the first vertical piece of
the crane, in an identical fashion to the upper-most stepper motor, from there, these wires will be
run along the horizontal arm of the crane and down to the electromagnet itself. The power for the
electromagnet will flow through a relay, allowing control over whether or not the electromagnet
is active. Sufficient length of wiring will be included to allow for the electromagnet to reach all
the way to the ground when picking up the hatch. When the crane is raised to place the hatch
onto the rocket, this wiring will be run over a horizontal bar which is located at the halfway point
of the crane, keeping it from being severed or getting in the way of operations.
The next subsystem is a linear actuator placed at the base of the launch pad with a limit
switch placed underneath the launch pad to be triggered when the actuator is 5 degrees off of the
vertical as desired. The wiring for these components has already been run in past years, and will
81
be run inside the upper channel of the 80/20 rail to avoid tripping hazards. Lastly, the igniter
system will also have a linear actuator and a limit switch to control its system, the wiring for
these components will be run in an identical fashion to those for the rail actuator. All of the
wiring can be seen in Figure 50.
The coding for all subsystems will be executed via the Arduino Mega. Each subsystem
will be isolated from one another, with a function for each task. No function will run without a
proper signal received from each previous task. That is, no subsystem will run unless all previous
subsystems successfully ran. This ensures safety through the knowledge that if one task fails, the
system itself stops. The crane will be programmed to move based on absolute angles, instead of
operation time or relative angles, so the crane will run to the exact positions each time. The
linear actuators run continuously, stopping when a limit switch is triggered, giving precise
positions the team can physically see and change when needed.
Figure 50. AGSE Electrical Wiring Diagram
The power provided by the battery for the AGSE system must meet two key requirements.
Power must be provided at the voltage required by each individual component, and the total current
provided by the battery must be sufficient to power.
The voltages required by each component have been tracked throughout the design process
to ensure complete compatibility of the system. Table 12below shows the voltages of each
electronic component.
82
Table 12. Voltage of Electronic Components on AGSE
Component Input Voltage [V]
Arduino Mega 7-12
Nema 17 Stepper Motors 4.2
Electromagnet 110 lb 12
Linear Actuators 12
As can be seen from the above table, all of the components can receive power from the
11.1 V battery being used to power the system, with the exception of the Nema 17 stepper motors.
These motors will be powered from an Arduino shield, which has a built in DC-DC converter to
take 11. V power and switch it down to the approximately 5 V required by the motors. As such,
all components will be receiving power at their required voltages from the currently planned
system.
The power modes of the system have also been identified to calculate the maximum current
draw required from the battery, to ensure the system is capable of operating in its full power mode.
These power modes are summarized in Table 13 below.
Table 13. Power Modes of the Electronic Components of the AGSE
Component Idle [A] Crane Operating [A] Linear Actuator Operating [A]
Arduino Mega 0.25 0.25 0.25
Nema 17 Stepper Motors (2) 0.00 3.00 0.00
Electromagnet 110 lb 0.00 0.50 0.00
Linear Actuator 0.00 0.00 5.00
Total 0.25 3.75 5.25
The table shows that the largest power requirement during any mode is when one of the
linear actuators is active. The linear actuators will not be active at the same time as any other major
component, as the movements they perform must be sequential. The lithium-polymer battery
chosen for the system is capable of providing power at a rate of 260 A continuously, more than
sufficient for the purposes of the AGSE system as designed.
Components and Mass Statement The AGSE system relies heavily on each individual subsystem’s success. Therefore, it is
imperative that each subsystem consists of reliable and reusable parts. The crane subsystem is built
on a 1’x1’x2’ base, with a 4” roundtable mounted on top. The crane is composed of carbon fiber
tubes and rods, and attached with aluminum braces. These are known to be structurally sturdy and
lightweight, the driving attributes behind the team’s choice. The crane will be moved via 2 stepper
83
motors. Again, these are lightweight and compact, but more importantly they have the capability
to output more than the required torque to move the subsystem.
Both the igniter and rail subsystems consist of 80/20 rails and a single linear actuator in
each subsystem. The 80/20 rails are perfect for rail buttons and are easily worked with. They can
be attached together with simple aluminum or steel pieces and screws. The actuators are strong
and reliable. They can consistently output the same force at the same rate every time, drawing
exactly the same amount of power that the team’s LiPo battery can provide. The final subsystem
to consider is the hatch and electromagnet subsystem. The electromagnet is consistent, aiding in
the reliability and repeatability of the system as a whole.
The most important thing the team needed to pay attention to was the weight of this
subsystem, since it can affect the performance of the crane subsystem. Therefore, it is constructed
of lightweight magnetic strips, a guide system, and a reliable electromagnet. The electromagnet is
ideal in picking up the payload and releasing it as it can easily be turned on and off by allowing or
disconnecting power.
Table 14. Mass Statement for AGSE
Component Per Unit Mass [lb] Quantity Total Mass [lb]
Linear Actuator for Igniter System 4.00 1 4.00
MB3U Bracket 2.00 2 4.00
1515 Aluminum Launch Rail 72” 8.06 1 8.06
1515 Aluminum Launch Rail 24” 2.69 1 2.69
Launch Rail Hinge 2.00 1 2.00
Linear Actuator for Rail System 4.00 1 4.00
Electric Wires, Connectors, and LED’s 0.50 1 0.50
XT-60 Wire Connectors (1 pair) 0.32 20 6.40
Electronic switches (Kill, Limit, Pause) 0.50 1 0.50
Blast Plate 25.00 1 25.00
Structure 80/20’s 1010 Rail - 72” 3.10 11 34.10
Z Piece for Igniter System 2.00 1 2.00
Dow Rod 0.02 1 .02
3D Printed Dow Rod Guide Tube .01 1 .01
3 Cell Lipo Battery 0.84 1 0.84
Bread Board 0.07 1 0.07
Arduino Mega 0.08 1 0.08
84
M/M Jumpers 0.03 1 0.03
Square Turntable 1.00 1 1.00
Chain 0.39 1 0.39
3D Printed Gear 0.06 1 0.06
Carbon Fiber Bar Stock 0.05 1 0.05
12V Electromagnet - 110 lbs 0.75 1 0.75
0.236 OD Pultruded Rod 0.13 2 0.26
Arduino Expansion Shield 0.08 1 0.08
Stepper motor controller 0.08 1 0.08
NEMA 17 Stepper Motor 0.75 2 1.50
GT2 Belt and Pulleys 0.25 1 0.25
¼-20 0.500 screw and nut 10s 0.02 20 0.40
¼-20 0.375 screw 10s 0.01 20 0.20
¼-20 t-nut 10s 0.01 15 0.15
¼-20 t-nut 15s 0.01 5 0.05
Square Carbon Fiber Tube 1.03 1 1.03
Total Mass 100.55
Payload Design
Design and construction of the payload
Our team will be competing in the MAV centennial challenge so the payload will be
provided by the judges. The payload will be a capsule with sand in it. The capsule will be made
out of a PVC pipe with two PVC caps on either side. Because the payload will be provided to the
team by the judges, no design or construction will be needed.
However, the design involves a unique design in which the payload will be picked up and
attached inside the rocket by a hatch and clips. This hatch will involve cutting a portion of body
tube, attaching metal strips onto it, and also attaching clips onto it. This allows the AGSE system
to pick up the payload off of the ground and securely attach it to the body of the rocket via magnets.
The clips have been 3D printed and the hatch section of the body tube has also been cut. The team
will assembly the parts together and test the mechanism in the upcoming weeks.
85
Flight performance predictions
The payload has no function during the launch inside of the rocket. The AGSE and rocket
system is a proof of concept designing a payload retrieval, containment, and launching system.
The payload is designed and expected to stay attached to the clip on the hatch at all times during
the flight.
The rocket will experience large amounts of vibration during the ascent though so there is
a slight possibility that the payload may become detached from the clips. However, this is not a
major concern as the payload will still be contained in the small payload compartment. The payload
will rattle inside the payload compartment but this will not damage crucial rocket components as
the payload is isolated by plywood bulkheads and sheets from the electronics, recovery system,
and other components. The payload may rattle around but this should not affect the performance
of the flight as the payload weights very little compared to other parts of the rocket.
During the flight of the rocket, the hatch door may try to open. This could be caused by the
turbulence outside the rocket or the payload bouncing around the internal payload compartment.
However, the team has ensured that this will happen in the design and construction of the hatch.
The hatch will be firmly attached to the body of a rocket with strong magnetic strips. If the team
finds that the hatch is not attached securely enough, duct tape will be used to attach the hatch to
the body.
Test and verification program
The payload and hatch system will go through extensive testing as it could cause safety
concerns if not handles properly. First, the team will test the clips and make sure that they grip the
payload tightly enough that it wouldn’t fall off even with a substantial amount of force and
vibration. The clips should attach firmly but they should not be too tight that the crane can’t pick
the payload up. Second, the team will test the attachment of the hatch to the body tube. The team
will attempt to shake the rocket and also manually try to take off the hatch door. The hatch should
not easily come off because the launch will try to rip off the hatch with much more strength.
Verification
Requirements
Table 15. AGSE Requirements and Verification
Requirement Solution Component Verification Status
Launch vehicle must be placed horizontally on the AGSE
The launch vehicle will be placed onto the rail in the horizontal position and left to be erected autonomously
Launch Rail The AGSE system is constructed such that the rest position of the rail is perfectly horizontal, and rests horizontally supported by the actuator and a specific support beam at the end of the rail. A level will also be
Confirmed. Rocket was placed on the rail that was lowered all the way down and was parallel to the ground.
86
used to check that the rocket is horizontal
A master switch must activate power to all autonomous procedures and subroutines
The AGSE system will include a master switch which controls all power distribution
Master kill switch
The master kill switch only allows power to the system when closed and will immediately terminate power once opened
To be tested after all the electronics are assembled and launch box is made.
A pause switch will halt all AGSE subroutines
The AGSE system will include a pause switch, enabling the safe pause and resumption of all AGSE activity
Pause switch On the control box there is a pause switch that functions as required and can be used also to continue operation of the system when unpaused
To be tested after all the electronics are assembled and launch box is made.
The AGSE will be a maximum weight of 150 pounds and no more than 12 feet in height x 12 feet in length x 10 feet in width
The AGSE will be constructed to meet the weight and size requirements
All components
Measure the dimensions of the AGSE system at the beginning and end of the procedures to confirm whether it is within the dimension bounds or not.
All components of the AGSE have been measured for both size and weight and do not overstep the bounds put forth by the competition.
The AGSE will complete the required tasks in the required order
The AGSE will be programmed to complete the tasks in order
Arduino A computer will be pre programmed with instructions to complete all necessary AGSE actions and procedures.
To be confirmed. Once all the electronic components are assembled, a runthrough test will be conducted
The AGSE system will be designed to theoretically
The AGSE system will not include magnetometers, sound based
All components
The AGSE contains no parts that are reliant upon gravity to function and planning, building, and testing have all been
To be confirmed. Once the entire structure is
87
be operable in the Martian environment
sensors, GPS, pneumatics or air breathing systems
done with this restriction in mind.
assembled, the AGSE will go through the entire process and team members will confirm that it will work in a Martian environment.
The launch vehicle must have a space to contain the payload and seal the payload containment area
The rocket payload bay has been designed to accommodate the given payload size as well as seal the vessel completely after the payload is placed inside
Hatch and clip The hatch covering and clip will attach to the crane picking up the payload and eliminates extra components to allow for maximum room inside the rocket for the payload. Magnetic forces are used to seal the payload and hatch with respect to the rocket.
The electromagnet and hatch system has been manually been tested and confirmed. The process must now be tested and confirmed to work autonomously
The payload must not contain any means to grab it outside of its original design
The payload will remain unmodified by the team and will be kept in its original state
Robotic crane and clip
The team will make sure that the design does not require any modification of the payload.
Confirmed. The team has not altered and will not need to alter the original payload.
The payload must be placed at least 12 inches from the AGSE and outer mold line of the launch vehicle
The team will place the payload at least 12 inches away from the AGSE and the outer mold line of the launch vehicle
All components
Run through the entire autonomous process and make sure that the crane can pick up the payload when it is more than 12 inches from any structure at the beginning of the process.
Confirmed. A measuring tape has been used to ensure the payload can be at least 12 inches away from any part of the structure at the starting position.
88
Gravity-assist shall not be used to place the payload within the rocket
The payload will be placed in the rocket without the use of gravity using a claw and lifting system
Clip and Electromagnet
An electromagnet will be used to secure the payload inside the rocket after being retrieved with a clip and this combination will be pushed into the rocket with the crane, negating gravity.
Confirmed. It has been observed that none of the procedures within the autonomous system will require any form of gravity assist.
Each team will be given 10 minutes to complete the autonomous portion of the competition
The team will ensure the full autonomous portion will take significantly less than 10 minutes as a safety measure
Arduino The computer will be programmed such that all required actions are completed within the time frame.
To be confirmed. Once all of the structure and electronics have been assembled, the team will run a full autonomous cycle of the of the process and make sure that that it is under the ten minute time limit.
A master switch which controls power to all parts of AGSE must be easily accessible
The AGSE system will include a master kill switch which directly can cut power to all systems, placed in a safe location
Master kill switch
Master kill switch will be connected to the computer that controls all AGSE actions and procedures and will be labeled clearly on the control box.
To be confirmed. Once the whole electronic system and launch box has been assembled, the team will test the kill switch and ensure that it is easily accessible.
A pause switch which terminates
A pause switch will be placed on the AGSE
Pause switch Pause button will be connected to the computer that controls all
To be confirmed. Once the
89
AGSE actions must be included and easily accessible
alongside the master kill switch which will terminate all AGSE procedures
AGSE actions and procedures and will be labeled clearly on the control box.
whole electronic system and launch box has been assembled, the team will test the pause switch and ensure that it is easily accessible.
An orange safety light must be included which indicates power is on, flashing when active and solid while paused
The team will include and orange safety light on the main AGSE system to display the current state of the system
Orange LED light
The LED will be connected to the computer that controls the whole AGSE ensuring the correct response for the correct state
To be confirmed. Once the whole electronic system and launch box has been assembled, the team will test the different modes with the LED lights.
An all systems go light must be included to verify all systems have passed safety verifications and the rocket is ready to launch
The team will include an all systems go light that verifies that the system has passed all verifications and is prepped for launch
LED light The LED will be connected to the computer that controls the AGSE actions and procedures ensuring it will light up at the correct time
To be confirmed. Once the whole electronic system and launch box has been assembled, the team will test the different modes with the LED lights.
Testing plan
Team members will conduct extensive tests on the AGSE components as the system
requires a high level of precision, tolerances for different situations, and many competition
90
requirements. The lifting mechanism and igniter system has been tested and successfully worked
in last year’s Student Launch competition. With the minor modifications added to this year’s
design, these functions will again be tested to ensure that it either has equal or better performance
than before. The robotic crane is a completely new design, so the team will go through extensive
testing of the mechanism. Specifically, the precision of the crane will need to be tested as its motion
needs to be accurate in picking up the payload and attaching the hatch onto the rocket. The
electromagnetic hatch system is a unique design and will need continuous testing, modifying, and
calibrating. As the construction of the AGSE progresses, tests will continuously be run to make
sure that everything works the way it was designed to. By conducting these tests, the team will be
able to find problems and fix them or improve the design. At the test launch of the rocket, some
components of the AGSE will be tested as well. The launch pad, lifting mechanism, and igniter
mechanism will be used at the test launch because it is easy to test, will provide useful feedback,
and is already mostly constructed.
Table 16. AGSE Testing Plan and Results
Function Being
Tested
Method of Testing Testing results
Securing the
payload in the
clip
Make sure the payload fits tightly into
the clips and does not fall out. Test
manually by pushing the clips onto the
payload and shake it vigorously to ensure
a tight grip. Also test the tolerance of the
placement of the clips so minor errors in
the position of the crane will not be
critical to securing the payload
Various clips have been 3D
printed and attached to the
payload to test the force
required to attach to payload to
the clip. The team has
successfully found a clip that
finds a nice balance between
force required to attach and
effective holding force
Crane can
securely hold
on to the hatch
and payload
while in motion
Run through the process of picking up
the payload and rotating the crane. Make
sure the crane can smoothly rotate while
carrying the mass. Attempt the motion
with a slightly heavier payload for
margin and make sure the crane can pick
up the competition payload easily. After
the crane has grasped the payload, shake
the arm and try to pry the hatch off the
crane. It should not come off easily while
the electromagnet is turned on.
Working in conjunction with the
force required to secure the clip
to the payload, how effective
the clip is at keeping the
payload secure is compared clip
by clip. A nice balance was
struck between the two forces,
insuring that the payload can be
attached with little difficulty,
but not be easily removed
Crane rotating
to the correct
position
After programming the movement of the
crane, make sure the position can be
accurately set and altered. Rotate the
crane’s arm towards the rocket and test if
the placement of the arm will allow the
To be tested in the near future.
Once the entire structure and all
of the electronics have been
assembled, the team will run a
full test of the process the crane
91
hatch to be attached to the specific part
on the rocket body tube. This process
will be a continuous testing process
where the team will experiment with
different inputs on the programming of
the crane.
is involved in. By doing this the
team will be able to test the
rotation of the crane.
Hatch being
securely
attached to the
rocket
Attach the hatch onto the rocket in the
configuration it will be during the
launch. Shake the rocket vigorously to
ensure that the hatch is attached securely
and it does not fall off or move around
during flight.
The electromagnet and hatch
has been manually tested to
make sure that the it snugly fits.
The team will test this process
autonomously in the coming
weeks.
Electromagnetic
hatch system
successfully
works and does
not damage any
electronics on
board
The electromagnetic hatch idea is a
unique solution to the competition
requirements. Repetitive testing will
confirm that the mechanism successfully
works. Other electronic equipment such
as altimeters and GPS trackers will be
tested to make sure that they won’t be
damaged by the electromagnet.
The electromagnet has been
turned on near flight hardware,
specifically the stratologger.
There seems to be no effect on
the quality of the altimeter.
Further testing will be
conducted as this is a major risk
to safety and mission success.
Rocket can be
lifted by the
linear actuator
Place the rocket onto the launch rail and
place in the horizontal position. Add at
least 5 pounds extra to the expected
rocket mass to allow margin of error. Lift
the rocket with the linear actuator and
make sure that the motion is smooth and
continuous.
The rail system of the AGSE
has been tested with the rocket
plus some mass on the rail
positioned correctly and works
just as modeled, taking about 17
seconds to complete
Launch pad not
tipping over
during the
lifting of the
rocket
Along with the testing process written in
the box above, lift the rocket with
additional mass from the horizontal
position. Observe the launch pad base
and make sure that it does not lean or tip
over at all.
The launch pad does tip over
slightly when the actuator first
begins raising the rocket;
however, the tipping is
minimized by rails extending
from the launch pad, and will
not endanger anybody nearby or
cause the mission to fail.
Rocket
obtaining the 5
degrees from
vertical position
Run through the lifting process of the rail
and test to make sure the actuator stops
once the limit switch is triggered. After
the actuator stops, measure the angle of
the launch rail with a level. Test to see if
the angle is near 5 degrees from the
vertical. If not, adjust the location of the
The actuator has been tested
extensively and measured for
accuracy, and the position of the
actuator and limit switch has
been found such that the rail
successfully stops at 5 degrees
off vertical.
92
limit switch and rerun the test until the 5
degrees is obtained repeatedly.
Igniter
smoothly
entering the
nozzle of the
motor
With the rocket on the launch rail in the
5 degrees from vertical position, run the
linear actuator that lifts the igniter.
Observe and make sure that the cone
underneath the launch pad guides the
wooden dowel and igniter smoothly into
the nozzle of the rocket. Repeat tests to
ensure that it works repeatedly.
The igniter system was tested
numerous times with the guide
funnel and has shown success a
vast majority of runs, with an
exception when the dowel rod
was bent and not straight. So
long as the dowel rod remains
straight however, the system
will be successful.
After the igniter
is fully inserted
in the motor, a
launch control
box can
successfully
ignite the motor
The only opportunity to test this will be
during the test flight. The AGSE launch
pad will be used during this test flight
and the lifting and igniter system will be
tested. After the AGSE has completed its
procedure, team members will check that
the igniter is properly inserted. The
motor will then be ignited from a launch
box to make sure it properly fires.
This system specifically has not
been tested in this year, but the
same system has been
implemented in prior years and
has operated without problem.
Linear actuator
raising the
igniter stops
after it gets to
the top of the
motor
Test to make sure that the actuator stops
after the wooden dowel is pushed down
and triggers the limit switch. If that test
is passed, test process on a fake motor.
Ensure that the wooden dowel smoothly
enters the nozzle and stops at the end of
the fuel grain. If this test is passed, test
on the actual motor with only the
wooden dowel and make sure the fuel
grains do not get damaged.
The test has not been run on an
actual motor but has worked
successfully with the fake motor
numerous times and the team
has no concerns that the system
will be unsuccessful when it
comes to the actual motor.
The AGSE can
be paused
Test the pause switch on the control box
at all significant times during AGSE
operations. Make sure that when the
pause switch is pressed, all components
of the structure remains stably in place.
Pausing has been tested at
various critical positions such as
while the rail is raising,
throughout the motion of the
arm (both raising and rotating),
while securing the payload, and
while the ignition system is
rising. All points remained
stable after pausing and
continued without hitch
The AGSE can
be powered off
Test the kill switch on the control box
many times at different times during the
The team hit the kill switch at a
few times during the AGSE run
93
completely with
a kill switch
process. Make sure that when the pause
switch is pressed, all components of the
structure remain stably in place.
and all points mentioned just
above are stable with the
exception of the crane. The
stepper motors can cause the
chains to droop while off, but
this creates no danger and is still
safe.
Repeatability Run the entire process multiple times.
After the process is completed once,
return all the components to the original
position and rerun the process. Make
sure the process is easily returned to
original position and repeatable.
Running the AGSE numerous
times shows that systems such
as the rail and igniter systems
are easily reset, the crane can be
run in reverse until the starting
position is hit, and the
programming can be easily run
again from the start.
LED and
switches on the
control box
Run through the AGSE procedure and
test to make sure that the correct LED
lights turn on in the correct situations
(run and pause). Also test all the
switches and make sure they send the
correct commands to the AGSE.
The LED lights have been tested
while the AGSE runs and they
work as expected. Switches are
labeled correctly and function
properly.
Assembly of the
AGSE in under
60 minutes
The AGSE team will practice assembling
the entire AGSE structure, aiming for a
total time of 30 minutes. Because the
team must transport the AGSE in a few
separate pieces, it must be reassembled
at the judging and the launch. Test to
make sure that after each assembly, the
AGSE is stable and works as designed.
Most of the AGSE will be
constructed in transporting to
the competition, and many of
the parts that need to be
assembled are parts that the
team regularly attaches and
detaches to the rest of the
system due to space constraints
in the team’s work space,
usually well within 30 minutes.
The time the
AGSE process
takes is
minimized
The team will observe and time the
autonomous procedure of the AGSE
system. The time should be at least less
than 2 minutes 30 seconds from the
team’s predictions. The team will
attempt to minimize the time it takes
while maintaining the integrity of other
aspects of the system.
Many systems of the AGSE are
placed such that minimum
movement is required within the
actuators and the crane, some
changes in the positions of key
components have been tested
and the team believes it has
found an effective setup.
Launch pad can
withstand the
effects from the
This has been already tested with last
year’s competition and test launch.
However this will be tested again at the
The launch pad is the same as
last years, which worked
successfully every time, but
94
rocket motor
blast
test launch this year to make sure the
launch pad and rail is still in good
condition.
now there are holes cut into the
blast plate. This is of little
concern to the team however, as
video of last year shows that all
systems underneath the blast
plate should not be affected.
Rocket
smoothly leaves
the launch rail
and the launch
buttons do not
get caught
Because the launch rail is in two parts,
the attachment point can be dangerous
because the rail button may get caught.
After the two parts of the launch rail is
put together, slide the rocket with its
launch buttons up and down the rail and
make sure that it is smooth. This will be
tested prior to the test flight as well.
The rocket was run up and
down the rail buttons, both in
vertical and horizontal positions
and the movement itself was
smooth and uninhibited along
the rail.
Safety and Environment
Safety and Failure Analysis
To ensure the safety and success of the AGSE system during the competition judging, the
team must set up a plan to address these points. In terms of safety, the team has to keep in mind
the safety of members while working on the project, the safety of the components of the AGSE,
and the safety of the surrounding environment.
For the safety of team members while working on the AGSE system, the safety officer or
a subteam lead will be present at every construction event to supervise. All team members will
also be through a safety briefing by the safety officer. Because the construction of the AGSE
system involves dangerous power tools such as the drill press, circular sander, and electrical saws,
team members must be careful and attentive at all times. The safety of the team members is the
most important in regards to this project.
It is important to keep the AGSE system and surrounding environment safe as well. The
AGSE has critical components that are valuable and crucial to the mission that must be protected
such as actuators and electromagnets. Precaution will be taken to keep the components safe both
physically and electronically. Team members will also keep in mind the safety of the environment
around the AGSE during storage, construction, assembly, testing, judging, and launching. The
safety officer will make sure that it does not put anyone or the environment around at risk.
As with any project there are points that could fail. Team members have predicted areas
that could likely fail and have addressed those concerns. To make sure that any of the procedures
do not fail, the team will conduct extensive tests. There will be a lengthy process of trial and error
completing the full system successfully, but the team will persevere to ensure the AGSE runs
safely and successfully. Below is a table with specifics on the safety and failure analysis.
95
Table 17. Failure and Mission Assurance for AGSE
Failure Mode Effect Probability Mitigation
Use of power tools in
construction of
AGSE components
Team members could be
seriously injured if tools
are not used properly.
Low Members will go through safety
training in using machining tools
and will follow the safety code.
Safety officer or team lead will be
present at all building events.
Use of lithium-
polymer battery Electronic components can
be permanently damaged.
Members could be injured
if battery is not handled
properly.
Low When wiring, properly check the
specifications of electronic
hardware and the circuits. Store
and handle the battery as instructed
by the safety precautions provided
by the supplier.
The AGSE base
being unstable The rocket may not be
successfully lifted to the
launch position. During
launch, complications may
occur if base is unstable.
Low-
Moderate Extensive testing lifting the rocket
and additional weight for margin.
Stress and load test on the base to
ensure any load or shaking that
could be involved in the operation
would deform the AGSE.
Components from
the AGSE getting
loose during launch
Loose components of the
AGSE during launch could
be dangerous to those at
the launch site and the
environment close to the
pad.
Low Make sure that there are no loose
components on the AGSE that
would be dangerous and be blast
off. Conduct stress tests of many
components by shaking and adding
force. During launch, make sure
standard launch safety protocol is
observed and observers are far
from the launch pad.
Construction with
carbon fiber material Improper safety
procedures when handling
carbon fiber materials can
cause health hazards
Low Members working with carbon
fiber materials will be trained and
educated on how to handle the
material including safety gloves
and masks.
The electromagnetic
hatch is not securely
attached to the rocket
body
If the hatch becomes
dislodged, misplaced, or
removed during launch,
the rocket will be unstable
and its flight path will be
unpredictable and
dangerous.
Moderate Confirm that the hatch can be
securely attached to the rocket.
Test extensively by shaking the
rocket and purposely trying to
remove the hatch. It should not be
easily removable. Team members
will review the rocket between
completion of the AGSE process
and launch.
96
Igniter system gets
caught on the way up
and gets stuck
This may harm the fuel
grain of the rocket and the
igniter will not be fully
inserted into the motor.
This will cause the motor
to ignite in an unusual
way.
Moderate The igniter system will have a
function in which if the limit
switch is triggered, the actuator
will lower, which will passively
realign the wooden dowel and go
up again until it is triggered. This
will be repeated a few times to
make sure the igniter is fully at the
top of the motor. The limit switch
will extensively be tested and
made sure that it triggers properly
every time.
The launch rail is
unstable When the rocket leaves the
rail, if the rail is wobbly,
the rocket will not be able
to safely get off the pad
and may launch in a
different direction. This
may be dangerous to
people at the launch and
the environment around
the pad.
Low After the construction of the
launch pad and rail, the rail will be
tested for wobble. If the launch rail
is too loose and wobbly, supports
will be added and the bolts will be
tightened. Team members will
forcefully shake the launch rail and
make sure it wouldn’t interfere
with the launch.
A rail button getting
caught on the launch
rail
The rocket will not be able
to safely get of the launch
rail. This is mission
critical and could be
dangerous to the AGSE
system because it will
experience the burning
motor for an extensive
amount of time
Low Make sure the connection between
the two segments of the launch
rails are smooth and that the
launch buttons do not get caught.
Test before every launch, practice
the assembly, and test at the test
launch as well.
AGSE performs
unplanned actions If the AGSE runs
differently from planned
and acts unusually, it may
harm critical components
such as actuators and the
crane components
Low In the case these things may
happen, a team member will be
holding a control box so they can
pause the process or shut down the
power to the AGSE. The control
box will be completed and tested
before any other tests are
conducted.
Electromagnetic
hatch interfering with
other electronic
equipment such as
altimeters and GPS
tracking
This would be mission
critical because if the
altimeter or GPS tracking
is harmed, the rocket will
not be able to deploy
parachutes, measure data,
or be found.
Low-
Moderate All the flight hardware will be
tested against the electromagnet
holding the hatch to make sure
they do not get harmed at the
distance they will be in during the
AGSE process.
97
Storage of the AGSE
system Because of the size of the
AGSE system, it could be
a hazard unless stored and
worked on properly. Also,
the electronic components
could be a hazard if not
stored property.
Low The AGSE system will be stored
and worked on in a spacious
indoor area. The University of
Illinois Aerospace Department
provides student societies with a
working and storage area. The area
is locked so only authorized
persons can get in. It is a dry,
clean, cool, and well ventilated
area adequate for storage and
work.
Most Hazardous Risks of Failure
The first truly hazardous risk is the electromagnetic hatch not securely attaching to the
rocket body. This could come from hatch misplacement, insecure placement, and the like. If this
were to happen, the rocket will have an unpredictable flight path, as well as possibly lose the
payload. To mitigate said failure, the team will extensively confirm that the hatch can be secured
to the rocket, with an extensive testing of the hatch magnets, especially between full completion
of the AGSE and the launch during the competition.
Next is concerning the igniter system being caught.on the way up. If this were to happen,
the fuel could ignite in an uncontrollable or sporadic manner, or possibly not at all. This has a
moderate chance of happening, due to the simple nature of the igniter system. The team’s solution
is to have a limit switch, triggering upon any form of pressure and halting the progression of the
igniter actuator. This is used to also tell when the igniter is safely within the motor.
Another big concern would be an unstable AGSE base. With a similar system design from
last year, the team knew the structural issues to overcome through experience, and this came as a
moderate to low risk probability, but still a chance at occurring. Therefore, the team put in place
80/20 rails extending from the base for larger contact surface area without compromising weight
or too much space.
With the inclusion of a strong electromagnet, the team had to take into consideration the
effect it might have on the rocketry systems, such as the altimeters and GPS tracking devices. If
this were to harm any of those, the rocket would be difficult to obtain, and may corrupt any
measureable data. This is a low to moderate possibility, but the team will test the effects of the
electromagnetic hatch on the hardware at the known distance from the time of the completion of
the system to the day of the competition’s launch.
Finally, the risk of power tools during construction of the system is always a concern, but
a lower probability of impacting the team due to rigorous safety training. Each member has
undergone proper procedure training for all possible devices one might need to use. The safety
officer and/or team lead will also be present for all building sessions, consistently aware of proper
procedures.
Payload Concept Features and Definition
Creativity and Originality
Members of the Illinois Space Society have collaborated for weeks in order to create a
unique and creative design for the AGSE system. Due to the changes in the competition rules, the
team was forced to adjust the system to better fit the needs of this year’s challenge proposal. The
98
Centennial Challenge Mars Ascent Vehicle (MAV) prize requires a collection of a prepositioned
sample which will then be placed into a rocket for raising, igniter insertions, and finally, a launch.
The prepositioned nature of this sample allows for a simplistic design to be used for sample
collection.
The new and improved design for this year’s AGSE system will have the capability to
obtain a sample with a minimum of a foot away from the structure, allowing for pick up and then
insertion into the rocket without any reliance on gravity, as stated by the Centennial Challenge.
The crane-like system of the AGSE has been designed using a total of only two motors and an
electromagnet, making the system simplistic in design and application. Using only these two
motors for the crane-system, the team will be able to collect a sample and place it inside the
rocket. The unique and simplistic design allows for minimal points of failure to ensure a
successful operation of the system.
A significant redesign of the AGSE system was required to bring the system within the
constraints of the new competition. Improving and perfecting the already built structure will be a
challenge for the team as well.
The new crane system deals with a complex belt system and an advanced electronics
system. The electromagnetic hatch that picks up the payload and attaches itself onto the rocket
also poses mechanical and electronic challenges. Timing the entire procedure within the code
and finding the specific location at which the crane must be located will be designed, calculated,
tested for repeatability.
Most of the challenges the team faces lie in minimizing the mass and volume of the
structure while maintaining the time of the procedure to be carried out. The team needs to be able
to find the balance between these factors while also maintaining cost efficiency, manufacturing
ease, and reliability, all which prove to be difficult. However, collaboration between the team
members provides many unique and creative ideas in order to come up with solutions to the
challenges faced, all while still providing a solid design that will strongly compete with the
submissions from other universities and institutions.
Uniqueness or significance
The Autonomous Ground Support Equipment (AGSE) system is designed to collect a
sample, place it firmly in the rocket, raise the rocket from a horizontal orientation to a vertical
orientation, and insert the igniter into the rocket motor. The sample will be collected from a
predetermined location and orientation, so the autonomous movements of the system are all
preprogrammed and are not dynamic.
A successful run of the system will see the sample payload lifted from a predetermined
position 12 inches away from the AGSE and outer mold line of the launch vehicle and placed
safety into the hatch. Following this, the rocket will autonomously raise to a position 5 degrees
off of vertical. The igniter will be positioned to the top of the motor fuel grain within the rocket
and then the system will await launch approval from the range safety officer. The AGSE system
is divided into five subsystems which all function together to complete the operations listed
above. The remainder of this section contains a brief system description, while the following
sections describe each of these subsystems in greater detail.
The first of these subsystems is the sample collection crane, which contains the sample
collection arm with its imbedded hatch door. This system is required to perform the actions of
collecting the sample, and firmly attaching the sample and hatch door to the rocket body. The
sample collection crane consists of an aluminum base made primarily of the same 8020 rail used
99
for the launch rail system. The actual crane will be constructed on a rotary steel bearing, made
primarily of carbon fiber tubes. The two degrees of freedom of this crane will be controlled by
belts attached to stepper motors. An electromagnet will be placed on the end of the crane and
used to hold the hatch and clip system into place until it is powered down.
Second is the launch pad and rail system, which contains the main structure of the launch
pad, as well as the rail that is used to hold the rocket straight during its ascent. The launch pad
and rail system also includes the rail support placed several feet out from the pad itself which
supports the rocket and rail in the horizontal start orientation. The launch pad system is
constructed of aluminum 8020 rail with a 1” thickness. The launch pad itself is constructed of ⅜”
steel to withstand the blast of the rocket engine. The launch rail uses a thicker 1.5” 8020 rail to
hold the rocket stable during the first several feet of flight.
Next, the igniter subsystem is located on the base of the launch pad, and is used to insert
the motor igniter prior to launch. This system consists of a linear actuator that performs the
insertion, as well as a bent aluminum piece that is used to hold the igniter below the motor.
Fourth, the hatch and clip system that is used as the end effector of the robotic crane. The rocket
hatch is included within this system, as it is directly used to pick up the sample before being
attached to the rocket. The hatch itself is made of blue tube, as it will be cut from the rocket
body. Magnets will be included into the top and bottom of this hatch piece to allow for
attachment both to the crane and to the rocket body.
The fifth subsystem is the electronics system which controls and powers all of the
components in the above three systems. This system is controlled by an Arduino and several
motor controls. A series of limit switches, resistors, LED’s, and momentary switches will also be
implemented to accomplish mission goals. Along with these, two stepper motors, two linear
actuators, and one electromagnet will be integral to the AGSE’s success. The electronics are all
powered by a 3 cell Lithium Polymer battery.
The creativity in the team’s design comes from the electromagnet and hatch system. It’s
innovative design allows the team to overcome the challenge provided by a non-gravity assisted
system. It still allows for direct placement of the payload without letting it fall. That aside, it’s
different from a basic claw/crane system design. Because the system’s retrieval capabilities is
based around an electromagnet, it is possible to change the hatch to something that can pick up a
payload of many different shapes and sizes, making the design malleable and adaptable. A step-
by-step procedure for the AGSE system can be found below:
1. The robotic crane will start with the electromagnet situated above the hatch door.
2. Power is run through the system, activating the electromagnet and attaching the hatch
to the electromagnet.
3. The robotic crane will rotate to a position over the payload.
4. The vertical arm piece will lower and push the clips securely onto the payload.
5. The vertical arm will rise back up to a height just above the rocket.
6. The crane shall then rotate over to the vehicle.
7. The vertical crane piece will be lowered into the vehicle bay.
8. When the hatch door is flush with the vehicle, the magnets inside the rocket will grip
the steel on the hatch door.
9. A tubular latch bolted on the inside of the rocket will slide and lock the hatch, securing
it firmly in place.
10. Power to the electromagnet will be shut off, releasing the hatch from the crane.
100
11. The vertical crane piece will be raised slightly, in order to avoid contact with the
rocket when the crane rotating away from the rocket.
12. The crane will rotate away from the rail system and vehicle.
13. The rail system actuator will raise the vehicle to a position of 5° off of the vertical.
14. The igniter system actuator will raise the dowel rod until the igniter is in the tube,
triggering a limit switch when enough pressure is applied.
Science Value
The primary goal for the team is the safe retrieval of the payload, placement of the payload
in the rocket, and successfully preparing the rocket for launch by rising the rail system to 5 degrees
off the vertical and then inserting the igniter into the vehicle. An essential aspect of the AGSE
system is reusability. All parts shall be undamaged and not require human interaction between
each run. This is achieved by meticulous testing to assure no subsystem is damaged. With
everything being automated, there is no need for outside interference except during the initial
setup. All subsystems are isolated and monitored through the Arduino, to ensure that no subsystem
is a threat to any other subsystem. The team has also implemented LED lights to indicate activity
and power. This is a vital safety measure, both for the structure, and the team operating the
structure, giving a clear and concise idea of what is going on.
The purpose of the AGSE system is imitating a sample return mission on Mars, or
somewhere else with gravity significantly less than that of earth. Because of these constraints, the
AGSE is designed to be gravity independent, atmosphere independent, magnetic field independent,
and fully autonomous. The AGSE will be able to pick up a sample payload and place is in a rocket,
just as it would in a sample return mission. The conditions during the competition are not the same
as the conditions on Mars so the test is not perfect, however the design would still function in a
Martian environment. Some of the components would need to be swapped for similarly
functioning ones due to radiation and extreme temperatures but the cost of such components is too
high for this project.
The rocket is not the size of a rocket to land on Mars or elsewhere, but the design of the
payload holding system could be scaled up for an actual Mars mission rocket. The rocket used for
the competition will show the design used in the system could be implemented in a sample return
mission.
The mission will be considered successful if the AGSE system is able to pick up the sample,
secure it in the rocket, lift the rocket, and ignite the rocket all autonomously. The success will be
measured visually by seeing the payload is secured in the rocket and with a digital level to ensure
the correct final position of the rocket.
Approach to workmanship
The Student Launch team is comprised of many students coming from many different
majors. With the majority of the team in Aerospace Engineering, the team is confident in the
calculations as well as the part selection for both the rocket system and AGSE system. Also, with
enough experienced members, the team can rely on their input to see what would work best on
certain occasions.
The individual subteams have dedicated times to meet and discuss, collaborate, and
propose solutions to the various problems faced and talk about how to achieve the goals set all in
a timely manner. The team has plans and deadlines due for each week in what needs to be done
and the subteam lead is there to help oversee the team’s schedule and to promote healthy discussion
101
among the teams. Despite following a rigorous schedule, the team will take time to double and
triple check calculations in order to minimize errors wherever possible as well as ensuring a
successful operation in the future. Whatever measurements members make will be made twice so
members will only have to cut once. Members test multiple times to make sure the repeatability of
the processes are not due to chance.
Overall, the Student Launch team demonstrates a professional, yet fun environment for
practicality and technicality. As a team working together on one project, the team works
efficiently, in a timely manner, and in the best way possible. The team is confident they will
succeed during the Student Launch competition this April.
Precision of instrumentation and repeatability
When designing the system and choosing components proper integration was always taken
into consideration to ensure the repeatability of the processes of the system. There will be multiple
test of components on their own and the system as a whole to ensure it can run as desired many
times.
The AGSE will be designed to be tolerant to some inaccuracies in all segments of its
operation. In all cases, as much precision as was technically feasible was included in the design,
but as in all real systems, some level of inaccuracy will always exist. This section details the
considerations that went into creating the AGSE system in such a way that it was tolerant to these
kinds of small inaccuracies.
As a part of the payload collection system, a sample payload must be collected from a
prepositioned ground location, simulating the AGSE taking a sample from a Mars rover or
equivalent. This system must be able reliably rotate and lower itself to collect the sample. The
motor used in the crane has a precision of 1/1600 of a rotation. This high accuracy assures that the
crane will be able to both retrieve the payload and secure it in the rocket in every run of the system.
Despite this, the system features clips which are shaped to allow for large inaccuracies (~ 0.25
inches in any direction) in the placement of the sample or the rotation and lowering of the crane as
an added safety. The clip design will guide the sample into the desired orientation from any slight
deviations. The magnets used to hold the hatch and payload in place are strong enough that if the
crane were to be slightly off in placing it, the magnets on the rocket will be strong enough to snap
the hatch and payload into place.
The rail lifting system, which will raise the rocket to five degrees from the vertical after
sample insertion, has several contingencies to account for uncertainty in measurements. The rail
has some freedom to move in the plane perpendicular to the desired lifting motion of the rail
causing some risk of missing the limit switch to stop lifting. To ensure the rail will hit the limit
switch, a set of aluminum brackets bent at an angle guide the rail into its correct position. This also
ensures the repeatability and consistency of the lifting process.
The accuracy of the five degree from the vertical measurement will be ensured by thorough
testing prior to actual use. This measurement is driven by the correct placement of the limit switch
that halts the raising of the rail. With the position of this limit switch correctly tuned, the rocket
should be able to be within 0.5 degrees of the desired angle based on past results.
For the igniter, a cone is used to guide the igniter into its correct position below the motor.
This cone will have bottom diameter of 2 inches to allow for 1 inch of imprecision in either
direction for the igniter tip. The wooden dowel rod that will be used to hold the igniter rigidly
inside of the motor will also be marked to show the correct depth to which the igniter must be
102
inserted. This will be inspected visually prior to launch to ensure the igniter is fully inserted
properly.
V) Launch Operations Procedures Checklist
Recovery Preparation Checklist
1. Prepare Recovery Electronics
a. Assemble avionics bay payload sleds, check that all connections are secure
i. Altimeters should be wired to switches, batteries, and two terminal blocks
ii. Insert and connect fresh batteries
b. Lock altimeter switches in off position
c. Attach e-matches to altimeters via terminal blocks
d. Turn on altimeters and check continuity, then turn off altimeters (3 beeps for
continuity)
e. Slide avionics sleds into couplers and attach bulkheads
i. Insert sleds so that the altimeters face the key switches
ii. Thread a nut and washer on each bulkhead on each rail (4 total nuts and 4
washers)
f. Check that altimeters are off, and attach ejection charges to terminal blocks
2. Pack drogue parachute
a. Packing Procedure to be determined through assembly, testing, and practice
3. Insert Drogue parachute into booster airframe
a. Attach quick link to eyebolt on motor case, confirm quick link is closed
b. Insert wrapped shock cord into booster, pack down firmly
c. Push packed drogue parachute into booster, with the protector facing upwards
d. If the parachute is too tight, adjust packing to make the package wider or longer
as necessary
e. Attach the upper quick link to the bottom eyebolt of the avionics bay, ensure the
link is closed
4. Pack main parachute and flame retardants
a. Packing procedure to be determined through assembly testing and practice
5. Insert main parachute into airframe
a. Attach quick link to avionics bay, confirm quick link is closed
b. Insert wrapped shock cord into airframe, pack down firmly
c. Push packed main parachute into airframe, with the protector facing downwards
d. If the parachute is too tight, re-adjust packing to make the package wider or
longer as necessary
Motor Preparation Checklist (Assembly to be completed by Mentor)
Adapted from Manufacturer's instructions
103
1. Assemble Forward Closure
a. Apply lubricant to all threads and O-rings
b. Insert the smoke charge insulator into the smoke charge cavity
c. Lubricate one end of the smoke charge element and insert it into the smoke charge
cavity
2. Assemble Case
a. Deburr the inside edges of the liner tube
b. Insert the larger diameter portion of the nozzle into one end of the liner, with the
nozzle liner flange seated against the liner.
c. Install the propellant grains into the liner, seated against the nozzle grain flange.
d. Place the greased forward seal disk O-ring into the groove in the forward seal
disk.
e. Insert the smaller end of the seal disk into the open end of the liner tube until the
seal disk flange is seated against the end of the liner.
f. Push the liner assembly into the motor case until the nozzle protrudes
approximately 1- 3/4” from the end of the case.
g. Place the greased forward (1/8" thick X 2-3/4" O.D.) O-ring into the forward
(bulkhead) end of the case until it is seated against the forward seal disk.
h. Thread the forward closure assembly into the forward end of the motor case by
hand until it is seated against the case
i. Place the greased aft O-ring into the groove in the nozzle
j. Thread the aft closure into the aft end of the motor case by hand until it is seated
against the case
Launcher Setup Checklist
1. Lower the launch rail
2. Slide the rocket on the launch rail
a. Ensure team members are supporting the weight of the rocket
b. If the rail buttons do not slide smoothly, rotate the vehicle rather than applying
more pressure
3. Power on the AGSE
a. Master switch will be turned on
b. The computer will receive power
i. LED flashes showing power is connected to the computer
c. The commands will be paused once the computer is booted up
4. Pause button will be pressed
a. AGSE will start its commands
i. Sample payload will be picked up by the robot
ii. Sample payload and hatch door will be placed in the rocket
iii. Rocket will be erected to 5 degrees off of vertical
104
iv. Linear actuator will lock it into position
v. Igniter will be inserted into the motor
5. Turn on altimeters and check settings and continuity
a. Primary altimeter:
i. 3,1,10,10,10 beeps for main deployment altitude
ii. Series of beeps for last flight data
iii. Series of beeps for battery voltage (Volts, tenths of Volts)
iv. Three quick beeps for continuity
b. Secondary Altimeter
i. 4,9,10,10 beeps for main deployment altitude
ii. 5 second siren for apogee delay
iii. Series of beeps for last flight data
iv. Series of beeps for battery voltage (Volts, tenths of volts)
v. Three quick beeps for continuity
6. Attach the launch controller to the motor igniter
7. The all systems go light will be activated after passing safety verifications
Launch Procedures
1. 1. Proceed to the safe area
2. Acquire signal from the vehicle's transmitters
3. Launch the Vehicle
Troubleshooting
1. Altimeters
a. If incorrect settings are reported, connect altimeters to a computer to reset settings
b. If continuity is not confirmed, check that connections between altimeters, terminal
blocks, and E-matches are secure
c. If the altimeter doesn't power on, check key switch and power supply wiring
2. Motor Doesn't Ignite
a. Wait for RSO clearance to approach the pad
b. Confirm that launch controller is connected to igniter
c. If so, disconnect launch controller and remove/inspect igniter
d. If necessary, disarm altimeters and remove the rocket from the rail for further
inspection of the motor assembly
Post flight inspection
1. Wait for rocket to land
2. Upon range clear: retrieve rocket and check for undetonated charges.
105
3. Return to safe area
4. Remove altimeters from coupler and collect data
5. Turn off all avionics and store for transport
6. When travel back is finished, clean all dirty components, remove power sources from
avionics, and store all materials for future flights
Comprehensive Checklist
Pre-Launch - Day Before:
1. Check that mentor has:
a. Correct Aerotech K1000T
b. Correct charge size for each separation event. Charge sizes to be determined
2. Check that all flight hardware is stored for transportation to launch site
a. Booster Airframe
b. Motor casing
c. Motor Adapter (three pieces)
d. Motor Forward Seal Disk
e. Main and Drogue Parachutes
f. Main and Drogue shock cords
g. 8 quick links
h. Coupler (assembled with sled, end-cap bulkheads, and altimeters)
i. Flat Screwdriver for Rotary Switches
j. Upper Airframe
k. Screws for upper Airframe attachment
l. Payload fairing (assembled with electronics)
m. Shear Pins
n. Motor retainer ring
3. Check that all backup equipment and tools are prepared to complete any necessary final
fixes or alterations
a. Phillips screwdriver for screws
b. Small screwdriver for altimeter contacts
c. Adjustable wrenches
d. Allen wrenches
4. Check that all ground support equipment is packed
a. Ground Station Antenna
b. Laptop with ground station software
c. Micro USB Cable
d. GPS tracker
e. Binoculars
5. Check that all team members have read or heard safety briefing and are informed of their
responsibilities
106
Pre-Launch - Day of
1. Pack equipment for travel, as listed above
2. Travel to launch location
3. Unpack equipment at launch site
4. Perform preflight checks of AGSE and Hatch Systems
a. AGSE
i. Make sure power reaches all components
ii. Ensure safety switch pauses commands
iii. Check that master switch functions properly
iv. Check that limit switches will stop the actuators
v. Test that the motors run
vi. Complete a dry run of the system
5. Assemble avionics bay and hatch payload sleds, check that all connections are secure
a. Altimeters should be wired to switches, batteries, and two terminal blocks each
b. Insert and connect fresh batteries
6. Lock altimeter switches in off position
7. Attach e-matches to altimeters via terminal blocks
8. Turn on altimeters and check continuity, then turn off altimeters (3 beeps for continuity)
9. Slide avionics sled into coupler and attach bulkheads
a. Insert sled so that the altimeters face the key switches
b. Thread a nut and washer on each bulkhead on each rail (4 total nuts and 4
washers)
10. Check altimeters are off, and attach ejection charges to terminal blocks
11. Pack drogue parachute Packing procedure to be determined through assembly testing and
practice
12. Insert Drogue parachute into booster airframe
a. Attach quick link to eyebolt on motor case, confirm quick link is closed
b. Insert wrapped shock cord into booster, pack down firmly
c. Push packed drogue parachute into booster, with the protector facing upwards
d. If the parachute is too tight, adjust packing to make the package wider or longer
as necessary
e. Attach the upper quick link to the bottom eyebolt of the avionics bay, ensure the
link is closed
13. Attach coupler and insert shear pins for drogue parachute
a. Refer to labeling on coupler (This end down, shear pin alignment marks)
b. Push coupler into booster airframe
c. Rotate as necessary to line up shear pin holes
d. Insert three shear pins
107
14. Pack main parachute and flame retardants. Packing procedure to be determined through
assembly testing and practice
15. Attach upper airframe to coupler
a. Refer to alignment marks
b. Insert three screws
16. Insert main parachute into airframe
a. Attach quick link to avionics bay, confirm quick link is closed
b. Insert wrapped shock cord into airframe, pack down firmly
c. Push packed main parachute into airframe, with the protector facing downwards
d. If the parachute is too tight, readjust packing to make the package wider or longer
as necessary
17. Attach nosecone to upper airframe
a. Refer to alignment marks
b. Insert four shear pins
18. Insert motor into booster airframe
a. Attach the adapter rings (three pieces)
b. Insert into motor mount
c. Screw on retainer ring, confirming the motor is secure
19. Bring rocket to RSO for safety inspection
20. Make changes as specified by RSO
Launch
1. After RSO approval, wait for range clear
2. When range is clear, move rocket to pad
3. Lower launch rod and mount rocket on the rod
a. Ensure team members are supporting the weight of the rocket
b. Rail button should slide easily along rail. If not, don't apply pressure, rather rotate
the rocket
4. Raise rod and rocket to upright position, be sure to support the rocket while lifting
5. One at a time, turn the key switches; listen for continuity, settings check
a. Payload altimeter:
i. Verify the altimeter turns on
b. Payload computer:
i. Verify ground station receiving from transmitter
c. Primary altimeter:
i. 3,1, 10, 10,10 beeps for main deployment altitude
ii. Series of beeps for last flight data
iii. Series of beeps for battery voltage (Volts, tenths of Volts)
iv. Three quick beeps for continuity
d. Secondary Altimeter
108
i. 4,9,0,0 beeps for main deployment altitude
ii. 5 second siren for apogee delay
iii. Series of beeps for last flight data
iv. Series of beeps for battery voltage (Volts, tenths of volts)
v. Three quick beeps for continuity
6. Check pad power is off and attach igniter to pad controller
7. Insert igniter into motor and plug
8. Leave range and wait for launch
9. Acquire signals from GPS transmitters and camera system before launch
10. Launch rocket
11. At apogee, wait for separation
12. Wait for rocket to land
13. Upon range clear: retrieve rocket, check for undetonated charges and remove
14. Return to safe area
Post Launch
1. Remove altimeters from coupler and collect data
2. Turn off all avionics and store for transport
When travel is finished, clean all dirty components, remove power sources from avionics, and
store all materials for future flights
Launch concerns, operation procedures, and Quality Assurance The safety officer this year will be Andrew Koehler. He is a student studying Aerospace
Engineering at the University of Illinois. He worked with the 2014-2015 SLI Structures and
Recovery team, and as such he has worked on projects similar to this in the past.
Recovery preparation In order to recover our rocket, the on board GPS will need to be activated and tested to see if it is
working properly. We also will need to make sure our parachutes deploy, so sufficient charge
testing has been done to ensure that our parachute will separate from the rocket and land safely.
Motor preparation
Motor storage, transportation, and preparation will be in accordance with the National Fire
Protection Agency, specifically NFPA code 1127. The motor shall be stored in a Type 3 or Type
4 indoor magazine because the chosen rocket motor is under 50 lbs. Transportation of the motor
will comply with 49 CFR Subchapter C Hazardous Materials Regulation, which covers the
packaging, handling, and transportation of High Powered Rocket Motors. The operations manual
for the motor will be posted on the website as soon as the motor arrives. All rocket handling will
be performed by the team mentor.
Setup on launcher
In order for the rocket to be properly set up on the launcher, the structures and recovery
team and the AGSE team has determined the best was for this to be done. As such, a list has been
109
created and every instruction on it will be consulted before the rocket is put on the launcher. Igniter
installation The igniter installation will be set up when the rocket is about to be launched and right
before the launch sequence is activated. This is to ensure the igniter can never be ignited
prematurely and that our rocket doesn’t go off unexpectedly early (i.e. when is on the launch pad
and we don’t have the go for launch).
Launch procedure
In order to ensure that our rocket and AGSE subsystems stay intact and that no hazards
arise from the launch procedure, a coherent list of steps to be taken before launch has been
compiled. This list accounts for every part of the launch sequence, so that nothing is overlooked
in the process of the launch. This list will be consulted by everyone working with the rocket and
AGSE subsystems on launch day.
Troubleshooting
When troubleshooting any problem on either the rocket or AGSE subsystem, everything
will be turned off except the part that is needed to be fixed. This is so that no accidents occur and
no premature rocket launch. The range safety officer will be consulted before doing any
troubleshooting on the launch pad.
VI) Project Plan Budget Plan
An itemized budget for the 2015-2016 Illinois Space Society Student Launch team can be
found below. This budget shows all of the parts that will be used by the team in the rocket, the
AGSE system, educational outreach activities, and travel to Huntsville, Alabama for the
competition. Many of the items used are already owned by the Illinois Space Society, but their off-
the-shelf costs have been included to calculate the total cost of all parts in the system, showing this
cost is well below the competition limit of $7,500. The value in the rightmost column is the total
cost to the Illinois Space Society, which must be obtained through a combination of University
and corporate sponsorship outlined in the Funding Plan section of this report.
Table 18. Budget spreadsheet
Item Cost Each [USD] Quantity Total Cost
[USD]
Cost to Team
[USD]
Full Scale Rocket
Material
4.00" X 16.5 Nosecone $21.95 1 $21.95 $0.00
Upper Airframe Tube $38.95 1 $38.95 $38.95
Iris Ultra 72" Parachute $210.00 1 $210.00 $210.00
Main Parachute Shock
Cord
$18.75 1 $18.75 $0.00
110
Item Cost Each [USD] Quantity Total Cost
[USD]
Cost to Team
[USD]
Coupler Body $39.95 1 $39.95 $39.95
Switch Band $38.95 1 $38.95 $38.95
Coupler Bulkheads $4.05 4 $16.20 $16.20
Body Tube BulkHeads $4.05 2 $8.10 $8.10
Rotary Switches $9.46 2 $18.92 $18.92
Charge Cups $1.50 4 $6.00 $6.00
Union 2648 Tubular
Latch
$17.35 2 $34.70 $34.70
Stratologger $79.95 3 $239.85 $0.00
Telemetrum $321.00 1 $321.00 $0.00
9V Battery $6.98 1 $6.98 $6.98
Trapezoidal Fins (3) $0.00 3 $0.00 $0.00
Booster Tube $38.95 1 $38.95 $38.95
Centering Rings (3) $4.05 3 $12.15 $12.15
Motor Mount Tube $29.95 1 $29.95 $29.95
75mm Motor Retainer $53.50 1 $53.50 $53.50
15" FruityChutes Drogue $50.00 1 $50.00 $50.00
Drogue Parachute Shock
Cord
$11.25 1 $11.25 $0.00
Rail buttons $4.43 2 $8.86 $8.86
Motor (K1000T) Without
Propellent
$154.99 1 $154.99 $154.99
Proline Epoxy System
4100 Gallon
$119.99 1 $119.99 $119.99
Motor Case RMS-
75/2560
$235.40 1 $235.40 $0.00
Miscellaneous Parts $200.00 1 $200.00 $200.00
Subscale Rocket
Material
$0.00
Rocket Nosecone $11.95 1 $11.95 $11.95
Rocket Body $23.95 2 $47.90 $47.90
Coupler $8.95 1 $8.95 $8.95
Bulkhead $2.65 2 $5.30 $5.30
Centering Rings $4.75 2 $9.50 $9.50
Motor $23.39 1 $23.39 $23.39
Motor Mount Tube $16.49 1 $16.49 $16.49
Motor Retainer $24.61 1 $24.61 $24.61
Fins $28.34 1 $28.34 $28.34
Rail Buttons $3.07 1 $3.07 $3.07
111
Item Cost Each [USD] Quantity Total Cost
[USD]
Cost to Team
[USD]
AGSE Materials
Linear Actuator for
Igniter System
$119.99 1 $119.99 $0.00
MB3U Bracket $12.00 2 $24.00 $0.00
1515 Aluminum Launch
Rail 72"
$38.16 2 $76.32 $0.00
Launch Rail Hinge $24.95 1 $24.95 $0.00
Linear Actuator for Rail
System
$129.99 1 $129.99 $0.00
Red Stranded Wire 100' $9.95 1 $9.95 $0.00
Black Stranded Wire 100' $9.95 1 $9.95 $0.00
Green Stranded Wire
100'
$9.95 1 $9.95 $0.00
XT-60 Wire Connectors
(1 pair)
$0.71 20 $14.20 $14.20
Green LED $0.59 3 $1.77 $0.00
Amber LED $0.59 3 $1.77 $0.00
Yellow LED $0.59 3 $1.77 $0.00
Kill Switch $11.98 1 $11.98 $0.00
Pause Switch $0.83 1 $0.83 $0.00
Limit Switch $0.99 4 $3.96 $0.00
Blast Plate $23.52 1 $23.52 $0.00
Structure 8020's 1010
Rail (per inch)
$0.23 800 $184.00 $0.00
Z Piece for Igniter
System
$19.86 1 $19.86 $0.00
3 Cell Lipo Battery $49.95 1 $49.95 $49.95
Bread Board $2.31 1 $2.31 $2.31
Arduino Mega $44.95 1 $44.95 $44.95
M/M Jumpers $1.95 1 $1.95 $1.95
Square Turntable $2.12 1 $2.12 $2.12
Carbon Fiber Bar Stock $6.71 1 $6.71 $6.71
12V Electromagnet -
110lbs
$117.00 1 $117.00 $117.00
.236 OD Pultruded Rod $16.99 2 $33.98 $33.98
Arduino Expansion
Shield
$17.95 1 $17.95 $17.95
Stepper motor controller $19.50 1 $19.50 $19.50
NEMA 17 Stepper Motor $22.90 2 $45.80 $45.80
GT2 Belt and Pulleys $16.69 1 $16.69 $16.69
1/4-20 .500 screw and
nut 10s
$0.50 20 $10.00 $10.00
1/4-20 .375 screw 10s $0.39 20 $7.80 $7.80
112
Item Cost Each [USD] Quantity Total Cost
[USD]
Cost to Team
[USD]
1/4-20 t-nut 10s $0.21 15 $3.15 $3.15
1/4-20 t-nut 15s $0.27 5 $1.35 $1.35
Square Carbon Fiber
Tube
$158.99 1 $158.99 $158.99
Black 3D Plastic $21.55 1 $21.55 $21.55
Educational Outreach
Viking Model Rockets
(pack of 12)
$54.99 6 $329.94 $329.94
A8-3 Rocket Engines
(pack of 24)
$49.49 3 $148.47 $148.47
Estes Portable Launch
Pad
$13.77 2 $27.54 $0.00
Travel and
Accommodations
$2,475.00 $2,475.00 $2,475.00
Cost as it sits on the
pad
$3,851.30 $2,321.00
Total Cost $6,326.30 $4,796.00
As can be seen in Table 18, the overall cost to the team will be $4,796.00. This amount
will be easily covered by the funding plan, which can be found in the following section. The cost
of this system, excluding travel, will be $3851.30 including the material the team already owns.
This $3851.30 is well below the $7,500 maximum, and the team is confident that it will remain
below that limit.
Funding plan
As a technical project team under the Illinois Space Society, the Student Launch
Competition will be funded by the registered student organization. The funding plan developed by
the Illinois Space Society treasurer and approved by the executive board is shown below in Table
19.
Table 19. Student Launch Project Funding Plan
Source Amount in US Dollars
Student Organization Resource Fee 1,500
Engineering Council 1,050
University of Illinois at Urbana Champaign Aerospace Department 1,000
113
Source Amount in US Dollars
Corporate Sponsorship / Illinois Space Society 1,450
TOTAL 5,000
As it can be seen above, the funding for the Student Launch competition will come from a
wide variety of sources. The Student Organization Resource Fee (SORF) is a mandatory fee
collected each semester from all University of Illinois at Urbana Champaign students. The resource
fee is then allocated among Registered Student Organizations. The organizations go through an
application process after which the SORF board determines the amount of funding and the
organizations that receives the funding. These funds can be used for purchasing equipment and
travel expenses related to the project. The Illinois Space Society plans to request a funding of
$1500 from SORF to be used both for equipment and travel expenses. Engineering Council is the
umbrella organization of all engineering Registered Student Organizations on campus. They do a
variety of things such as give awards, host events, and provide funding. For funding, Engineering
Council awards a grant of $525 to deserving organizations for projects each season. Illinois Space
Society will ask Engineering Council for the funding of Student Launch in the fall season.
Engineering Council also gives out separate funding for trips to conferences and other professional
events. Illinois Space Society will ask for a funding of $525 in the spring period to fund the trip of
team members to Huntsville, Alabama. The aerospace department at UIUC also provides funding
for technical projects by aerospace student organizations. ISS has received funding of $1000 for
this Student Launch competition. This money will be used to purchase components to build the
AGSE and rocket. The remaining cost of $1,450 will be covered by corporate sponsors and the
Illinois Space Society. ISS is constantly searching for outside sponsors to help fund technical
projects, educational outreach, and other events. The technical director of ISS will specifically
market the Student Launch competition to try and get corporate or other outside sponsors for this
project. As it can be difficult to find outside funding and to estimate an amount, the rest of the cost
of this project will be provided by ISS. ISS and the Student Launch team will aim to reduce costs
and obtain funding from outside resources such as companies in the aerospace industry in
exchange for publicity. The team will consider putting advertising on hardware with stickers and
also inviting company representatives to have informational sessions on campus.
Timeline
The critical path to completion of both the rocket and AGSE components of the
competition can be clearly seen in the Gantt chart on the following page. Planned tasks are shown
in blue, completed tasks in green, behind schedule tasks in red, and tasks that are currently
underway are in yellow. Due to inclement weather during the planned test launch dates, the test
launch is behind schedule as of FRR. The rocket is fully constructed and is ready for launch with
charge testing already performed, and an effort will be made by the team to find a launch window
that fits both weather and the constraints of the team’s mentor during the week following the FRR
due date.
The AGSE crane construction is currently still underway, with the rail, igniter, and
electrical subsystems all having reached effective completion. The first joint of the crane has been
completed and is functional, with some continuing work needed to set up the correct alignments
114
of the components to accomplish mission goals. Mounts for the other portions of the crane have
been created and the remaining pieces will be integrated and tested in the coming weeks.
115
116
Educational Engagement
The ISS team has been increasing its presence in the community through various
educational outreach activities in the Champaign-Urbana area. The plan has been to reach out to
K-12 students within the community, introduce them to rocketry, and show them what the ISS
team is currently working on.
On Saturday, March 5th, the ISS team helped a local Boy Scout troop, Troop 309, obtain their
space exploration badges by teaching a 5 hour class at a local elementary school. The program
consisted of, first, giving the attendees a brief history of space and the landmark people/companies
that aided in the growth of space exploration. Next, team members discussed the new ideas that
have been presented by private and commercial companies, regarding the future of space travel.
Following these informational presentations, students were split up into groups with an ISS team
member and began to put together their model rockets, using an A class motor that would be
launched at the end of the class, as the glue needed to dry. Once the rockets were finished, they
were put to dry. The team was then able to present the project, introducing them to the different
parts of a high powered rocket and presented videos from past NASA Student Launch
competitions. The students were then given the task to design their own habitat or spacecraft and
detail all the important components that are necessary to keep that spacecraft/habitat suitable for
human living and for mission completion. The students presented their ideas, mixing their
creativity while stating the important components, like radiation shielding, life support systems,
and power sources. After all of the students ideas were presented, team members added more
important components and went over their significance. The ISS Student Launch Team ended the
day by launching the model rockets. All of the group’s rockets launched successfully. The group
had some issues with rockets landing on the trees, but were able to recover a majority of them. The
day ended discussing what went right and what went wrong with the rocket launches.
This weekend the team members participated in the College of Engineering’s Engineering
Open House. In this event, thousands of K-12 students come to campus with their families to learn
more about engineering at Illinois as well as to see the variety of technical projects from different
engineering departments. This event expects over 1,000 students from primarily Illinois. The
University of Illinois’s NASA Student Launch team exhibited their vehicle from last year’s
competition at Engineering Open House. As attendees came to the Student Launch exhibit, team
members explained the different parts of the rocket, the objectives for the competition, as well as
videos from past years. Attendees were then able to touch the rocket and ask any questions they
had about the project. Over a thousand students and parents came and listened to the Student
Launch members present their project and other exhibits.
117
Figure 51. The ISS Student Launch team manager presenting the current vehicle design to
the Boy Scout troop.
Figure 52. The ISS Student Launch team launching the small model rockets that they
helped build with the Boy Scouts.
118
Figure 53. The ISS Student Launch team presenting a hybrid rocket engine and rockets at
the University of Illinois Engineering Open House
VII) Conclusion The Illinois Space Society is highly committed to the future of rocketry both from an
industrial and a hobbyist standpoint. The team is proud to once again compete in the Student
Launch competition and intends to do so for the foreseeable future. Team members from many
different majors and departments throughout the University have already dedicated several
hundred engineer-hours to the design and documentation of these systems. Most importantly, over
half of these team members are first or second year students with little to no previous rocketry
experience. Under the guidance of the team mentor and more experienced team members, these
new team members have already gained a significant amount of valuable insight into both high
power rocketry and, more importantly, the real world processes of design and engineering. This
personal growth will only be magnified once the construction of the systems themselves is
initiated. In previous years, the ISS team has treated this competition as an extracurricular activity
for students. Although this is technically still the case, the team intends to put forth a significantly
higher degree of effort and a more highly defined design than in previous years. Whether it is
through writing custom simulation code, presenting hand calculations, or a higher degree of detail
in models and drawings, the team has and intends to continue to work put forth significant effort
and treat this competition with the attention it deserves. Student Launch provides an opportunity
for students to participate in a high profile, real world engineering experience with many technical
challenges. This type of opportunity is not common in the world of undergraduate education, and
the ISS team does not take this experience for granted.
119
Appendix A Illinois Space Society Tech Team Safety Policy
All students are to sign and date the present document indicating that they read, understand, and will
abide by the contained policy before they enter the Illinois Space Society (ISS). These requirements apply
to day to day meetings, construction in and outside of the Engineering Student Projects Lab (ESPL),
testing, and any additional meetings that may occur as part of ISS Tech Team activities. The signed forms
are to be collected by the team safety officer, recorded, and submitted to the Technical Projects Manager. I. ESPL Rules: Required training to gain access to ESPL
General Lab and Electrical Safety training through the U of I Division or Research Safety is
mandatory for all individuals before they enter ESPL and participate in Design Council
supported projects. Both interactive training modules are online and available at the following
link: http://www.drs.illinois.edu/Training?section=GeneralLabSafety
Upon completion of the training modules the students must print, sign, date each form and give to
the designated safety officer who will keep record of their training and then give promptly to
ESPL Laboratory Supervisor. It is also required that all students read the present document and
sign and date it. Card access to ESPL will be granted after the ESPL Laboratory Supervisor has
the General Lab and Electrical Safety training forms and the present document signed and dated
on file.
Required training to use any tools/equipment in ESPL Students must receive training from The ESPL Laboratory Supervisor and fill out the
ESPL General Use Compliance Form and the ESPL Machine Shop use Compliance Form
before they use any tool/equipment on the respective forms or any potentially dangerous
tools/equipment. Tools shall not be brought into ESPL without the consent of the ESPL
Laboratory Supervisor. Any potentially dangerous tools or equipment not listed on the forms
should be added to the ESPL General Use Compliance Form list. Students may not work on
equipment until the ESPL Laboratory Supervisor has signed and dated the pertinent compliance
forms. A student must not use tools/equipment she/he was not trained for.
Each student group must designate a safety officer. The name, email, and cell phone
number of the safety officer must be distributed to each team member.
The safety officer must: Make sure that all individuals in the team are working in a safe manner and in compliance with
the Design Council Safety Policy. They will keep up to date record of the signed Safety Policy
forms for each team member
Be familiar with the daily activities of the team
Maintain a complete list of MSDS sheets for all potentially hazardous materials and their
respective quantities
All students must abide by the following ESPL General Use Rules:
1. A Laboratory Supervisor will oversee the Engineering Student Project Laboratory, including
the Machine Shop. 2. Students may not operate any power tool unless there is somebody else in the same work area
of the laboratory or shop. 3. Each student must wear safety glasses with side shield at all times while in any of the ESPL
work areas. 4. Hearing protection is required by anyone near loud equipment.
120
5. When in the work areas one must wear appropriate clothing: closed toed shoes, pants, no loose
clothing, jewelry, or hair is allowed that can potentially be caught in equipment. Do not wear ties,
rings, or watches. 6. Students must not lift heavy objects without the aid of an appropriate lifting device and hold
heavy objects in place using appropriate equipment such as jack stands. 7. When using power tools to cut materials, all parts must be properly clamped in a vise or
clamped to a table. Never hold a piece by hand when attempting to cut or drill it. 8. Never leave any tool or equipment running unattended. This includes electronic equipment,
soldering irons, etc. When you finish using anything, turn it off. 9. People welding or assisting in welding operations must wear welding masks or yellow tinted
safety glasses. You may only watch the welding process if you are wearing a mask. Students who
are welding or using grinders must use appropriate shields to protect others. 10. Compressed gases used for welding or other purposes pose several hazards. Users of
compressed gases must read and follow the recommendations of Compressed Gas Safety
available at https://www.drs.illinois.edu/SafetyLibrary/CompressedGasCylinderSafety 11. Shop doors must not be propped open. 12. Waste chemicals must be properly discarded, See the Laboratory Supervisor. 13. Store potentially hazardous liquids, chemicals and materials in appropriate containers and
cabinets 14. Students are responsible for the order and cleanness of their work space and benches
according to the rule: If you make a mess, clean it up. The same rule will apply to the common
areas of the laboratory including the designated “dirty” space, paint booth, and welding areas.
15. Work in a clean, uncluttered environment with appropriate amounts of work space and check
tools and workspace for problems/hazards before working with them. 16. Know the location of all fire extinguishers, emergency showers, eye rinse stations, and first
aid kits. 17. If you fill the garbage can, empty it in the dumpster outside. 18. The Laboratory Supervisor will decide how to proceed in the case of any situations not
covered by the preceding rules.
ESPL Machine Shop Rules (for all students using the ESPL Machine Shop):
1. Any user of the ESPL Machine Shop must read, understand, and abide by the ESPL General
Use Rules. 2. The Laboratory Supervisor controls card access to the ESPL Machine Shop. No student can
use any machine tool until he/she has demonstrated competence on that machine to the
Laboratory Supervisor. 3. No student may enter or remain in the Machine Tool Workshop unless accompanied by the
Laboratory Supervisor or a student who is authorized to use the Shop. The authorized user is
responsible for the visitor while he/she remains on the Shop. 4. Students may not operate any machine tool unless there is somebody else in the Machine Tool
Workshop. 5. Each student must wear safety glasses at all times. 6. When operating machine tools, long hair, long sleeves, or baggy clothing must be pulled back.
Do not wear gloves, ties, rings, or watches in the ESPL Machine Shop. 7. When using power tools to cut materials, all parts must be properly clamped in a vise or
clamped to a table. Never hold a piece by hand when attempting to cut or drill it. 8. Be aware of what is going on around you. 9. Concentrate on what you're doing. If you get tired while you're working, leave the work until
you're able to fully concentrate—don't rush. If you catch yourself rushing, slow down. 10. Don't rush speeds and feeds. You'll end up damaging your part, the tools, and maybe the
machine itself.
121
11. Listen to the machine, if something doesn't sound right, turn the machine off. 12. Don't let someone else talk you into doing something dangerous. 13. Don't attempt to measure a part that's moving. 14. Before you start a machine:
a. Study the machine. Know which parts move, which are stationary, and which are
sharp. b. Double check that your workpiece is securely held. c. Remove chuck keys and wrenches.
15. If you don't know how to do something, ask someone who does. 16. Clean up all messes made during construction
a. A dirty machine is unsafe and difficult to operate properly. b. Vacuum or sweep debris from the machine. c. Do not use compressed air.
17. Do not leave machines running unattended. 18. The Laboratory Supervisor will decide how to proceed in the case of any situations not
covered by the preceding rules.
122
Appendix B
Illinois Space Society Student Launch
Educational Feedback Form
How interesting was the demonstration? (1 – Boring, 10 – Extremely Interesting)
1 2 3 4 5 6 7 8 9 10
How much did you learn from this demonstration? (1 – Nothing, 10 – A Lot)
1 2 3 4 5 6 7 8 9 10
How interesting was the presentation? (1 – Boring, 10 – Extremely Interesting)
1 2 3 4 5 6 7 8 9 10
How much did you learn from this presentation? (1 – Nothing, 10 – A Lot)
1 2 3 4 5 6 7 8 9 10
What did you enjoy from your time with us?
What was your least favorite part of your time with us?
123
Appendix C
NAR HIGH POWERED ROCKET SAFETY CODE
EFFECTIVE AUGUST 2012
1. Certification. I will only fly high power rockets or possess high power rocket motors that
are within the scope of my user certification and required licensing.
2. Materials. I will use only lightweight materials such as paper, wood, rubber, plastic,
fiberglass, or when necessary ductile metal, for the construction of my rocket.
3. Motors. I will use only certified, commercially made rocket motors, and will not tamper
with these motors or use them for any purposes except those recommended by the
manufacturer. I will not allow smoking, open flames, nor heat sources within 25 feet of
these motors.
4. Ignition System. I will launch my rockets with an electrical launch system, and with
electrical motor igniters that are installed in the motor only after my rocket is at the launch
pad or in a designated prepping area. My launch system will have a safety interlock that is
in series with the launch switch that is not installed until my rocket is ready for launch, and
will use a launch switch that returns to the “off” position when released. The function of
onboard energetics and firing circuits will be inhibited except when my rocket is in the
launching position.
5. Misfires. If my rocket does not launch when I press the button of my electrical launch
system, I will remove the launcher’s safety interlock or disconnect its battery, and will wait
60 seconds after the last launch attempt before allowing anyone to approach the rocket.
6. Launch Safety. I will use a 5-second countdown before launch. I will ensure that a means
is available to warn participants and spectators in the event of a problem. I will ensure that
no person is closer to the launch pad than allowed by the accompanying Minimum Distance
Table. When arming onboard energetics and firing circuits I will ensure that no person is
at the pad except safety personnel and those required for arming and disarming operations.
I will check the stability of my rocket before flight and will not fly it if it cannot be
determined to be stable. When conducting a simultaneous launch of more than one high
power rocket I will observe the additional requirements of NFPA 1127.
7. Launcher. I will launch my rocket from a stable device that provides rigid guidance until
the rocket has attained a speed that ensures a stable flight, and that is pointed to within 20
degrees of vertical. If the wind speed exceeds 5 miles per hour I will use a launcher length
that permits the rocket to attain a safe velocity before separation from the launcher. I will
use a blast deflector to prevent the motor’s exhaust from hitting the ground. I will ensure
that dry grass is cleared around each launch pad in accordance with the accompanying
Minimum Distance table, and will increase this distance by a factor of 1.5 and clear that
area of all combustible material if the rocket motor being launched uses titanium sponge
in the propellant.
8. Size. My rocket will not contain any combination of motors that total more than 40,960 N-
sec (9208 pound-seconds) of total impulse. My rocket will not weigh more at liftoff than
one-third of the certified average thrust of the high power rocket motor(s) intended to be
ignited at launch.
9. Flight Safety. I will not launch my rocket at targets, into clouds, near airplanes, nor on
trajectories that take it directly over the heads of spectators or beyond the boundaries of
the launch site, and will not put any flammable or explosive payload in my rocket. I will
124
not launch my rockets if wind speeds exceed 20 miles per hour. I will comply with Federal
Aviation Administration airspace regulations when flying, and will ensure that my rocket
will not exceed any applicable altitude limit in effect at that launch site.
10. Launch Site. I will launch my rocket outdoors, in an open area where trees, power lines,
occupied buildings, and persons not involved in the launch do not present a hazard, and
that is at least as large on its smallest dimension as one-half of the maximum altitude to
which rockets are allowed to be flown at that site or 1500 feet, whichever is greater, or
1000 feet for rockets with a combined total impulse of less than 160 N-sec, a total liftoff
weight of less than 1500 grams, and a maximum expected altitude of less than 610 meters
(2000 feet).
11. Launcher Location. My launcher will be 1500 feet from any occupied building or from any
public highway on which traffic flow exceeds 10 vehicles per hour, not including traffic
flow related to the launch. It will also be no closer than the appropriate Minimum Personnel
Distance from the accompanying table from any boundary of the launch site.
12. Recovery System. I will use a recovery system such as a parachute in my rocket so that all
parts of my rocket return safely and undamaged and can be flown again, and I will use only
flame-resistant or fireproof recovery system wadding in my rocket.
13. Recovery Safety. I will not attempt to recover my rocket from power lines, tall trees, or
other dangerous places, fly it under conditions where it is likely to recover in spectator
areas or outside the launch site, nor attempt to catch it as it approaches the ground.
125
Installed Total
Impulse
(Newton-
Seconds)
Equivalent High
Power Motor
Type
Minimum
Diameter of
Cleared Area
(ft.)
Minimum
Personnel
Distance (ft.)
Minimum
Personnel Distance
(Complex Rocket)
(ft.)
0 — 320.00 H or smaller 50 100 200
320.01 — 640.00 I 50 100 200
640.01 — 1,280.00 J 50 100 200
1,280.01 —
2,560.00 K 75 200 300
2,560.01 —
5,120.00 L 100 300 500
5,120.01 —
10,240.00 M 125 500 1000
10,240.01 —
20,480.00 N 125 1000 1500
20,480.01 —
40,960.00 O 125 1500 2000
MINIMUM DISTANCE TABLE
126
Appendix D
Rail Calculations Python Script #all distances in inches, all weights in pounds, and all times in seconds
from math import cos #import relevant python tools and packages
from math import acos
from math import sin
from math import pi
import matplotlib.pyplot as plt
import numpy as np
f=24.682 #distance from hinge on base plate to hinge on ground
act_len_int=28.775 #initial actuator length
piv2piv=20.088 #distance from hinge on base plate to hinge on launch rail
da_dt=0.6 #how fast actuator extends in inches/second
act_len=np.linspace(28.775,39.111,100) #list of 100 points between initial and final actuator
lengths
alpha=[] #this list will be the angle between rail and actuator for every given length of the
actuator
def law_cos_ang(a,b,c): #use to find angle between rail and actuator using law of cosines
angle=acos((a**2+b**2-c**2)/(2*a*b))
return angle
for a in act_len: #fills 'alpha' list with appropriate angles in radians
alpha.append(law_cos_ang(a,piv2piv,f))
RocW=22.51 #weight of rocket
CGRoc=38.5 #CG of rocket from the pivot point on the base plate
CGRail=48.0 #CG of rail from pivot on base plate
RailW=10.7467 #weight of the 8' launch rail
TotW=33.2567 #weight of rail and rocket
CGComb=41.57 #CG of rail and rocket combined from pivot on base plate
act_force=[] #will be the list of forces to be graphed later
beta=np.linspace(0,pi/2,100) #angle off pi/2 that TotW acts w/ respect to the launch rail
momentCG=[]
#will be list of moments created by TotW, given actuator length. Measured from pivot at base
for angle in beta:
M=TotW*CGComb*cos(angle)
momentCG.append(M)
#determines the force required in the same direction as the actuator extends
for moment,angle in zip(momentCG,alpha):
AF=(moment/(piv2piv*sin(angle)))
act_force.append(AF)
127
time=np.linspace(0,(act_len[-1]-act_len[0])/da_dt,100) #plots actuator force as function of time
plt.plot(time,act_force,'ro')
plt.xlabel('Time(s)') #labeling axes
plt.ylabel('Force(lb)')
plt.title('Force vs. Time for Rail Lifting Actuator')
plt.show()
128
Appendix E
Rocket Profile Simulation Coded in MATLAB
%Flight Simulator for Illinois Space Society's NASA Student Launch Maxi-MAV
%competition, 2015-2016
%Based on Simulation created by David Knourek
%The current version of this simulator loads thrust curve values for the
%Aerotech K828, and K1000 motors, stored as .mat files called mass, thrust and time. These files
%hold vectors called Mass, Thrust and Time respectively, holding the obvious motor parameters.
These values are
%passed to the ODE45 ordinary differential equation solver. The program
%then parses the ODE solution to remove non-physical values that occur
%after the vehicle has landed, and plots the relevant data.
%For ease of use, calculations are completed in metric units, and converted
%to imperial units for output puropses
clc
clear
close all
%Load the Thrust curve characteristics
%These need to be altered if the motor is changed
%K1000
load('MassK1000.mat')
load('ThrustK1000.mat')
load('TimeK1000.mat')
MassK1000 = massimpulsewieghted(ThrustK1000,MassK1000);
%Store the thrust characteristics
%RHS are the vectors stored in the .mat files
%Mass is propellant mass
%This then loads the desired paramters into the variables used in ODE45
m=MassK1000;
T=ThrustK1000;
t=TimeK1000;
totalmass=10.2058;
%totalmass is mass of rocket with motor in kg
129
%Add extra times for after the motor has burnt out
%Also adds zeros for additional thrust and propellant mass values
n=1000; %Choose how many additional points to use
dt=.01; %Choose how long the additional time steps will be
xMass=zeros(n,1);
xThrust=zeros(n,1);
xTime=t(end)+dt:dt:t(end)+n*dt; %Can't just add 0 to times, need to add dt
xTime=xTime';
%Concatenate thrust curve values and additional values
m=[m; xMass];
T=[T;xThrust];
t=[t; xTime];
%Set the wind speed in mph, and convert to fps
%1mph = .44704 m/s
%Positive wind value assumes wind is blowing against the rocket's direction
%of travel
wind=5*.44704;
%Set the times over which to integrate
tspan=linspace(0,500,5000);
% Reference the "event" which will stop the integration when the rocket
% lands
options=odeset('Event',@crashevent);
%Solve the 2nd order ODE (See eomfun)
[times,Y]=ode45(@eomfun,tspan,[0 0 0 0],options,m,T,t,wind,totalmass);
% Find the time at which the altitude is first less than 0 during descent
% This is the landing time
endtime=find(Y(10:length(Y(:,1)),2)<0, 1 );
% Set Velocites to 0 if the rocket has landed
Y(endtime:length(Y(:,1)),3)=0;
Y(endtime:length(Y(:,1)),4)=0;
%Find velocity off of the rail, at 10 feet
130
railvelocity=interp1(Y(:,2),Y(:,4),8/3.28)*3.28;
%Output
fprintf('Rail Exit Velocity is %f feet/s \n',railvelocity);
P=00; %number of points after landing to plot
%Set times to plot over, start at ignition, end P timesteps after landing
plottimes=times;
%Extract flight characteristics and convert to feet
horizposition=Y(:,1)*3.28;
altitude=Y(:,2)*3.28;
MaxAltitude=max(altitude);
fprintf('Max Altitude is %f feet \n',MaxAltitude)
horizvelocity=Y(:,3)*3.28;
vertvelocity=Y(:,4)*3.28;
velocity=(horizvelocity.^2+vertvelocity.^2).^(1/2);
MaxVelocity=max(velocity);
fprintf('Max Velocity is %f feet/s \n',MaxVelocity)
fprintf('The Dift Distance is %f feet/s \n',abs(horizposition(end)))
%Load OpenRocket simulated values to plot a comparison
load('k1000.mat')
load('k1000wind.mat')
load('rocksimfull')
%Time(s) Altitude (ft) Vertical velocity (ft/s) Lateral distance (ft) Lateral velocity (ft/s)
%Plot Altitude
figure(1)
plot(plottimes,altitude,k1000wind(:,1),k1000wind(:,2),rocksimfull(:,1),rocksimfull(:,2),'linewidt
h',2)
xlabel('Time (seconds)')
ylabel('Altitude (feet)')
legend('Custom Sim','OpenRocket','RockSim')
%Plot Horizontal Position
figure(2)
plot(plottimes,abs(horizposition),k1000wind(:,1),k1000wind(:,4),'linewidth',2)
xlabel('Time (seconds)')
ylabel('Horizontal Position (feet)')
legend('Custom Sim','OpenRocket')
131
%Plot Horizontal Velocity
figure(3)
plot(plottimes,abs(horizvelocity)-20,k1000wind(:,1),k1000wind(:,5),'linewidth',2)
xlabel('Time (seconds)')
ylabel('Horizontal Velocity (feet/s)')
legend('Custom Sim','OpenRocket')
%Plot Vertical Velocity
figure(4)
plot(plottimes,vertvelocity,k1000(:,1),k1000(:,3),'linewidth',2)
xlabel('Time (seconds)')
ylabel('Vertical Velocity (feet/s)')
legend('Custom Sim','OpenRocket')
function dy = eomfun(t,Y,pmass,T,time,wind,totalmass)
%Flight Equations of Motion for Illinois Space Society's NASA Student Launch Maxi-MAV
%competition, 2015-2016
%Version 1.4
%The current version of these EOM takes as inputs the current position and velocity
%of the vehicle in the vertical and horizontal directions, and well as the
%thrust and the mass of the motor at all times, and the current time. It
%also takes the wind speed and total mass as imputs
%The program finds the current thrust, vehicle mass and drag, and uses
%these quantities to define the equations of motion. The derivatives of the
%input state Y are then passed out to ODE45, and used to solve the
%equations of motion.
%Based on Simulation created by David Knourek
%Define states
%Y=[x;y;vx;vy]
x=Y(1);
y=Y(2);
vx=Y(3);
vy=Y(4);
%Get x velocity wrt wind in the case that wind exists
%Positive wind value assumes wind is blowing against the rocket
vxrel=vx+wind;
132
%Find the direction of travel, used for direction of drag force
if y<100
theta=0*pi/180;
else
theta=atan2(vxrel,vy);
end
%if we have landed, set velocities and accelerations to zero and return
if t>5&&y<0
dy=[0;0;0;0];
return
end
%Set constant values, metric units
g=9.81;
rho=1.225;
%Calculate Frontal Area for Drag
finheight= .0857;
finthickness=.00635;
finarea=finheight*finthickness*3;
diameterinch=4;
radiusm=diameterinch/3.28/12/2;
areabody=pi*(radiusm^2);
areanochute=areabody+finarea; %Area used for drag (in initial simulation)
area=areanochute;
%Determine the propellant mass at the current time, convert to kg
%interpolates between known propellant masses at known times
if t>2.55
propmass=0; %short circuit interpolation after burnout
else
propmass=interp1(time,pmass,t);
end
propmass=propmass/1000;
%calculate drymass using the full vehicle mass minus initial prop mass
drymass=totalmass-pmass(1)/1000;
%Calculate the current mass of the vehicle, including current propellant
currentmass=drymass+propmass;
133
% % Parachutes
%Adds drag and area for each event
if vy<0 && y>=(500/3.28) && t>5 %Drogue Deployment from Apogee to 1000 feet
cd=.8;
area=areanochute+pi*(1.67/(3.28*2))^2;
elseif vy<0 && y<(500/3.28) && t>5 %Main Deployment at 1000 feet and below
cd=1.89;
area=areanochute+pi*(6/(3.28*2))^2;
else
cd=0.75;
end
%Find Thrust at the current time
%Interpolated between the known thrust values at known times
if t>5
Thrust =0; %Short circuit the interpolation after burnout
else
Thrust=interp1(time,T,t);
end
%Converts the 2nd order ODE into two 1st order ODEs
%Sets the derivative of the first state to the 3rd state
%Sets derivative of 2nd state to the 4th state
xdot=vx;
ydot=vy;
%Calculates the velocity magnitude
%uses the relative x velocity wrt wind since this value is used for drag
v=sqrt(vxrel^2+vy^2);
%Calculates Drag
%To Do: Implement area as a function of orientation and travel direction
D=.5*rho*v^2*cd*area;
%Drag has to be limited to some finite value, no matter how large. Otherwise drag may
%have an instantaneously infitie value and crash the simulation
if D>20000000000000000
D=200000000000000;
134
end
%X acceleration equation of motion, a_x=(F_x)/m
% ax=(1/currentmass)*(Thrust-D)*sin(theta);
ax=(1/currentmass)*((Thrust*sin(-5*pi/180)-D*sin(theta)));
%Sets derivative of x velocity as x accleration
vxdot=ax;
%Y accleration equation of motion, a_y=(F_y)/m
ay=(1/currentmass)*((Thrust*cos(-5*pi/180))-D*cos(theta))-g;
%Sets derivative of y velocity as y acceleration
vydot=ay;
%Store the derivatives of the input state, to be returned to ODE45
dy=[xdot; ydot; vxdot; vydot];
end
function [ massnew ] = massimpulsewieghted( thrust,mass)
%Takes in propellent mass and thrust vector and weigths a new mass vector
% thrust = thrust curve values
% mass = mass of the motor
% massnew = a weighted mass vector based on thrust values
totalimpulse=sum(thrust);
totalmass=mass;
massnew=zeros(length(thrust)+1,1);
massnew(1)=totalmass;
for i=2:length(thrust)+1
massnew(i) = massnew(i-1) -(totalmass*thrust(i-1)/totalimpulse);
end
massnew=massnew(2:end);
end
135
Appendix E
Matlab code for cp and cg simulation clc
clear all
Ln = 16.496;
D = 4.014;
Cr = 11.813;
Ct = 6.25;
S = 5.25;
Xr = 4.5;
Xb = 77.438;
N = 3;
L = 90.5;
sweeplength = 4.5;
middledist = Ct/2 + sweeplength - Cr/2;
Lf = sqrt(middledist^2 + S^2);
R = D/2;
CNN = 2;
XN = .466*Ln;
CNF = (1 + R/(R+S))*((4*N*(S/D)^2)/(1+sqrt(1+(2*Lf/(Cr+Ct))^2)));
XF = Xb + Xr/3*(Cr + 2*Ct)/(Cr + Ct) + 1/6*((Cr + Ct - Cr*Ct/(Cr + Ct)));
CNT = 0;
CNR = CNN + CNT + CNF;
xbar = (CNN*XN + CNF*XF)/(CNR