Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
2013
IL&FS ENVIRONMENTAL INFRASTRUCTURE & SERVICES
LTD.
ENVIRONMENTAL AND SOCIAL
POLICY AND FRAMEWORK
IL&FS Environmental Infrastructure & Services Ltd.
ENVIRONMENTAL AND SOCIAL POLICY FRAMEWORK
VERSION 05
May 2018
Page 3 of 111
ESPF Document Revision No.: ESPF/IEISL/Rev/2015/04
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
1 Page 25 5 03.05.2018
Transfer of risk monitoring from ESPF to IMS is reverted
back to ESPF. Risk monitoring frequency reduced to once
a year after IMS is established
2 Page 38 5 03.05.2018
Training and awareness generation made subject to
intensity of business activity
3 Page 39 5 03.05.2018
Intensity of corporate review reduced for High and
Moderate risk rated PTAs and site visit made subject to
management approval
4 Page 84 5 03.05.2018
Sr no. 15 & 16 added to provide additional options for
spatial examination of E&S risk
1 Page 43 5 04.05.2018
Risk assessment criteria point no. 4 in the ESPF manual
has been updated to include compliance risks related to
new regulations such as e-waste rules 2016, plastic waste
rules 2016, MSW rules 2016, hazardous waste rules 2016,
etc.
2 Page 47 5 04.05.2018
Risk assessment criteria no. 18 and 19 in the ESPF manual
have been updated to include ‘Not applicable’ and its
associated risk rating of ‘Low.’
3 Page 44 5 05.05.2018
Risk assessment criteria no. 3 in the ESPF manual has
been updated to include ‘Not applicable’ and its
associated risk rating of ‘Low.’
4 Page 5 05.05.2018
For some projects which have been commissioned,
covenants based on RRCs have not been updated in Form
1 and the covenant section in Form 1 has been left blank.
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
1 Page 26 4 1.11.2017 V. Institutional arrangement, D. Role of project manager
is updated during project transition from ESPF to EMS
2 Page 45 4 1.11.2017
Annexure A: Table A) E&S Risk Rating for Project
Implementation; formation of a separate question related
to ISO 14001 certification
3 Page 90 4 27.02.2017 Form V a column is added to understand the stage of
the project
Page 4 of 111
Changes as suggested in Corporate Review 28.02.2017
1 Page 33 3 15.03.2017 Section VI (C)- Point F inserted about continuing ESPF
scope after implementation of IMS
2 Page 33 3 15.03.2017 Section VI (D) –D(a) Training Need updated
3 Page 40 3 15.03.2017 Business Process mapping for C & T Project inserted in
Annexure A- E & S Risk assessment for C & T Projects
4 Page 64 3 15.03.2017 Annexure D- point II inserted conditions for change in
format of ESPF Form I
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
Changes as suggested in Corporate review findings dated 19-01-2016
1 Page 11, in
Figure 1, 03 08.03.2016 SPV name ‘DDSIL’ added
2 Page 22, VA(I) 03 08.03.2016 Corporate sustainability cell replaced with E&S Cell
3 Page 22 V B
(c) 03 08.03.2016 Conduct replaced with facilitate or Assist
4 Page 23 V C(l),
and V D (k) 03 08.03.2016
Status of E&S compliance of all ongoing project shall be
submitted on quarterly basis to CSC as and when required
- point is not applicable and to be removed
5 Page 25, Fig 3 03 08.03.2016 Institutional Structure- Internal Review replaced with
Corporate review
6 Page28,
Figure 5 03 08.03.2016
Project Cycle Mapping with ESPF – Sole Sourced (Project
Implementation) to be modified - Step 1 for Form-1
generation should be prior/at the time of BAM
7 Page 33, VI (D 03 08.03.2016 Points (a) to (f) in section deleted
8 Page no. 48,
Annexure A 03 08.03.2016
Environmental and Social Risk Rating; Table C) E&S Risk
matrix for Advisory Project is not inline with criteria
specified in table B and modified as per risk rating criteria
specified
9 Page 58 &59 ,
Para C 03 08.03.2016 Reporting format for Project site monitoring to be
modified as format for Project site monitoring during
Page 5 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
1 Page 26 4 1.11.2017 V. Institutional arrangement, D. Role of project manager
is updated during project transition from ESPF to EMS
2 Page 45 4 1.11.2017
Annexure A: Table A) E&S Risk Rating for Project
Implementation; formation of a separate question related
to ISO 14001 certification
3 Page 90 4 27.02.2017 Form V a column is added to understand the stage of
the project
Changes as suggested in Corporate Review 28.02.2017
1 Page 33 3 15.03.2017 Section VI (C)- Point F inserted about continuing ESPF
scope after implementation of IMS
2 Page 33 3 15.03.2017 Section VI (D) –D(a) Training Need updated
3 Page 40 3 15.03.2017 Business Process mapping for C & T Project inserted in
Annexure A- E & S Risk assessment for C & T Projects
4 Page 64 3 15.03.2017 Annexure D- point II inserted conditions for change in
format of ESPF Form I
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
bidding stage and Audit Report table of Content to be
replaced with Site Monitoring Report Table of Content
10
Page 61,
Annexure C
03 08.03.2016
clause/table for E&S Risk Monitoring Periodicity for
Advisory projects ( i) Development of Project and Tender
Documentation ; (ii) during PMC ) is added/modified
11 Page 75 ( I ),
Page 83 (III) : 03 08.03.2016
Clause added "Risk rating will become 'High' for any P/T/A
that becomes sub judicial on E&S aspects"
12 Page 81
section VI 03 08.03.2016
Monitoring periodicity to be modified for advisory projects
( development and PMC period)
13 Page no. 95,
Annexure N 03 08.03.2016 Not applicable and hence deleted
14
Page 33
Section VI (E)-
2
03 05.05.2016 Text modified to bring clarity on Corporate Review
15 Annexure K :
Page 90 03 05.05.2016
Risk Assessment and Monitoring:
Previous column titled “Investment size” replaced with
two columns: one column on “Total Project/Investment
Page 6 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
1 Page 26 4 1.11.2017 V. Institutional arrangement, D. Role of project manager
is updated during project transition from ESPF to EMS
2 Page 45 4 1.11.2017
Annexure A: Table A) E&S Risk Rating for Project
Implementation; formation of a separate question related
to ISO 14001 certification
3 Page 90 4 27.02.2017 Form V a column is added to understand the stage of
the project
Changes as suggested in Corporate Review 28.02.2017
1 Page 33 3 15.03.2017 Section VI (C)- Point F inserted about continuing ESPF
scope after implementation of IMS
2 Page 33 3 15.03.2017 Section VI (D) –D(a) Training Need updated
3 Page 40 3 15.03.2017 Business Process mapping for C & T Project inserted in
Annexure A- E & S Risk assessment for C & T Projects
4 Page 64 3 15.03.2017 Annexure D- point II inserted conditions for change in
format of ESPF Form I
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
Size (Rs. Mn)” and another on “Group Company’s
Investment size (Rs. Mn)”
Additional columns added: “Litigation pertaining to
E&S issues”, “Incident of Social Unrest” - Column on
“Remarks” re-worded: “Other Remarks ('Live'/ 'On
Hold')
16
Annexure F:
Page 81
03 05.05.2016 Environmental Sensitivities and Sources of Information for
India: added for Water stress index
17
Annexure D
Form I: page
64
03 05.05.2016
ESPF Form I - Environmental and Social Risk Assessment for
Projects:
Within E&S Sensitivities section, point xiv. added:Water
stress index
Within Risk Assessment section, ‘Remarks’ column re-
labeled to ‘Remarks/ Details/ Justification to be given’
Changes as suggested in Corporate review findings in 2015
1
Section V:
Institutional
Arrangement-
C: Role of
IEISL E & S
03 23-06-2015
Point (q) inserted:-ESPF form-I has to be finalized by ESPF
coordinator.
Point (j)- Nomenclature for documents changed to –
‘Final Form X short project name Date.abc’
Point (k,i,o)-
Page 7 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
1 Page 26 4 1.11.2017 V. Institutional arrangement, D. Role of project manager
is updated during project transition from ESPF to EMS
2 Page 45 4 1.11.2017
Annexure A: Table A) E&S Risk Rating for Project
Implementation; formation of a separate question related
to ISO 14001 certification
3 Page 90 4 27.02.2017 Form V a column is added to understand the stage of
the project
Changes as suggested in Corporate Review 28.02.2017
1 Page 33 3 15.03.2017 Section VI (C)- Point F inserted about continuing ESPF
scope after implementation of IMS
2 Page 33 3 15.03.2017 Section VI (D) –D(a) Training Need updated
3 Page 40 3 15.03.2017 Business Process mapping for C & T Project inserted in
Annexure A- E & S Risk assessment for C & T Projects
4 Page 64 3 15.03.2017 Annexure D- point II inserted conditions for change in
format of ESPF Form I
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
Cell
2
“Figure 6-
Project Cycle
Mapping with
ESPF-
Advisory
Services
03 23-06-2015 MD Approval Inserted
3
Annexure C:
A: E&S Risk
Monitoring
Periodicity
Depending on
E&S Risk
Rating
03 23-06-2015
A column added for periodicity, prescribed due date for
monitoring in Form II
4 Annexure D:
Form I 03 23-06-2015
Few Additional points added for CSC review of High Risk
Projects
Page 8 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
1 Page 26 4 1.11.2017 V. Institutional arrangement, D. Role of project manager
is updated during project transition from ESPF to EMS
2 Page 45 4 1.11.2017
Annexure A: Table A) E&S Risk Rating for Project
Implementation; formation of a separate question related
to ISO 14001 certification
3 Page 90 4 27.02.2017 Form V a column is added to understand the stage of
the project
Changes as suggested in Corporate Review 28.02.2017
1 Page 33 3 15.03.2017 Section VI (C)- Point F inserted about continuing ESPF
scope after implementation of IMS
2 Page 33 3 15.03.2017 Section VI (D) –D(a) Training Need updated
3 Page 40 3 15.03.2017 Business Process mapping for C & T Project inserted in
Annexure A- E & S Risk assessment for C & T Projects
4 Page 64 3 15.03.2017 Annexure D- point II inserted conditions for change in
format of ESPF Form I
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
5 Annexure E:
Form II 03 23-06-2015 Few Additional points added regarding RRC in Form II
6
Annexure K:
Form V
Master
Database
03 23-06-2015
Risk Assessment and Monitoring column updates:
▫Investment size
▫Revised Risk Rating, if any. With date (under revisions)
Page 9 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
1 Page 26 4 1.11.2017 V. Institutional arrangement, D. Role of project manager
is updated during project transition from ESPF to EMS
2 Page 45 4 1.11.2017
Annexure A: Table A) E&S Risk Rating for Project
Implementation; formation of a separate question related
to ISO 14001 certification
3 Page 90 4 27.02.2017 Form V a column is added to understand the stage of
the project
Changes as suggested in Corporate Review 28.02.2017
1 Page 33 3 15.03.2017 Section VI (C)- Point F inserted about continuing ESPF
scope after implementation of IMS
2 Page 33 3 15.03.2017 Section VI (D) –D(a) Training Need updated
3 Page 40 3 15.03.2017 Business Process mapping for C & T Project inserted in
Annexure A- E & S Risk assessment for C & T Projects
4 Page 64 3 15.03.2017 Annexure D- point II inserted conditions for change in
format of ESPF Form I
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
7
Operationaliz
ation of ESPF
at IEISL:
Section D
03 23-06-2015
(i) Section D: Title changed to Training and Awareness
Generation (ii) Few Points inserted
8
Operationaliz
ation of ESPF
at IEISL:
Section E
03 23-06-2015 Few Points Inserted
9
Document
Control:
Section B
03 23-06-2015 Few Points Inserted
10
Annexure H:
Scope of
Corporate
Review
03 23-06-2015 Inserted scope of review matrix
Page 10 of 111
Table of Contents
I. Environmental and Social Policy and Principles of IL&FS ......................................... 13
A. Background of ESPF ........................................................................................... 13
B. Process for Adaption of ESPF at Associate Companies ................................. 13 II. The IEISL ESPF .................................................................................................................... 14
A. Business Canvas of IEISL ................................................................................... 14
B. Relevance of ESPF to IEISL ................................................................................ 15 III. Environmental and Social Policy for IEISL .................................................................... 15
A. IEISLs E&S Policy Statement ............................................................................. 18
B. IEISL ESPF Principles ......................................................................................... 18
C. Guiding Principles .............................................................................................. 19
D. Operational Principles ........................................................................................ 20
E. Engagement Principles ....................................................................................... 21 IV. E&S Risk Identification and Management Process ....................................................... 21
A. Step 1 – Determine E&S Rating ......................................................................... 24
B. Step 2 – Apply E&S Risk Reduction Controls ................................................. 22
C. Step 3 – Monitor E&S Risk ................................................................................. 22 V. INSTITUTIONAL ARRANGEMENT .............................................................................. 24
A. Composition of the IEISL E&S Cell .................................................................. 24
B. Role of Corporate Sustainability Cell (CSC) .................................................... 25
C. Role of IEISL E&S Cell ........................................................................................ 26
D. Role of Project Manager ..................................................................................... 27 VI. Operationalization of ESPF at IEISL ................................................................................ 30
A. Mapping ESPF Steps to IEISL’S Business Cycle ............................................. 30
B. Integration of ESPF into workflow of IEISL – Project Implementation
andAdvisory Services ................................................................................................... 30
C. Operational Mechanism ..................................................................................... 36
D. Training and Awareness Generation ................................................................ 37
E. Corporate Review and External Audit ............................................................. 38 VII. Document Control ............................................................................................................... 40
A. Information Management .................................................................................. 40
B. Updates and Document Control ....................................................................... 41 Annexure A: Environmental and Social Risk Rating .................................................................. 43 Annexure B: E&S Risk Reduction and Controls ......................................................................... 53 Annexure C: Environmental and Social Monitoring and Periodicity ...................................... 65 Annexure D: ESPF Form I - Environmental and Social Risk Assessment ............................... 67 Annexure E: ESPF Form II - Environmental and Social Action Planning and Monitoring .. 80 Annexure F: Guidance Procedure for E&S Risk Assessment of a Project in ESPF Form I .. 82 Annexure G: Procedure for Monitoring a project in ESPF Form II ........................................... 87 Annexure H: Scope of Corporate Review ..................................................................................... 89 Annexure I: ESPF Form III - Findings of Corporate Review ..................................................... 91 Annexure J: ESPF Form IV - Format for Training Record .......................................................... 92 Annexure K: ESPF Form V - Master Database on Status Implementation of ESPF ............... 93 Annexure L: ESPF Form IIA - Monthly Monitoring from Project Site during Construction96 Annexure M: ESPF Form IIIA - Format for Project Site Review Report .................................. 99 Annexure O: Former Revision Page .............................................................................................. 100
Page 11 of 111
List of Figures
Figure 1: IEISL Organizational Structure based on Business Services ................................. 15
Figure 2: Steps involved in E&S Risk Identification and Management ................................ 24
Figure 4: Project Cycle Mapping with ESPF – Bid Projects (Project Implementation) ....... 29
Figure 5 : Project Cycle Mapping with ESPF – Sole Sourced(Project Implementation) ..... 33
Figure 6: Project Cycle Mapping with ESPF - Advisory Services ........................................ 33
Page 12 of 111
Abbreviations
BAM Bid Approval Memorandum
CRZ Coastal Regulation Zone
DPR Detailed Project Report
EC Environmental Clearance
EIA Environmental Impact Assessment
E&S Environmental and Social
EHS Environmental, Health and Safety
EMP Environmental Management Plan
EPC Engineering, Procurement & Construction
ESPF Environmental and Social Policy Framework
H High E&S Risk
IEISL IL&FS Environmental Infrastructure and Services Limited
IL&FS Infrastructure Leasing and Financial Services Limited
L Low E&S Risk
M Moderate E&S Risk
MSW Municipal Solid Waste
O&M Operation and Maintenance
P Project
RAP Resettlement Action Plan
R&R Resettlement and Rehabilitation
SIA Social Impact Assessment
TAM Transaction Approval Memorandum
Page 13 of 111
I. ENVIRONMENTAL AND SOCIAL POLICY AND PRINCIPLES OF IL&FS
A. Background of ESPF
(a) IL&FS has adopted an Environmental and Social Policy Framework
(ESPF). The IL&FS ESPF was approved by its Board on May 5, 2008
and is applicable to IL&FS, its subsidiaries and associate companies
as suitably adapted to reflect each individual business unit’s
processes in a phased approach of implementation.
(b) The IL&FS ESPF is founded on the concept of Sustainable
Development and recognizes Environmental and Social (E&S)
considerations in its business operations to add value, and minimize
adverse impacts and risks.
(c) The ESPF is being extended to subsidiaries in a phased manner and
IL&FS Environmental Infrastructure and Services Limited
(IEISL)and nine other associate companies are included in phase I
and II of the ESPF implementation.
(d) For overall guidance, advice and coordination related to the ESPF, a
Corporate Environmental and Social (E&S) Cell has been created.
The Corporate Sustainability Cell will take up the responsibilities of
knowledge management, communication and outreach, training (and
workshops) and compliance monitoring for the IL&FS ESPF.
(e) To ensure quality of E&S related services, IL&FS has also empanelled
E&S consultants and Environmental Laboratories. There are ten E&S
consultants and nine Environmental laboratories spread across India
that have been empanelled. The empanelment will be a dynamic
process and the list of empanelled consultants and laboratories will
be updated from time to time. This list of empanelled consultants
and laboratories shall be used to engage in various services as
required by different companies of IL&FS.
B. Process for Adaption of ESPF at Associate Companies
(a) A coordinator was identified in each Subsidiary to coordinate
activities related to the ESPF.
(b) A series of meetings were organized by the Corporate Sustainability
Cell with the Coordinators to understand the business operations
and workflows. The business processes for the various operations in
practice at the Subsidiaries were mapped.
(c) The relevance of the ESPF to the Subsidiary based on its operations
and business perspective was identified. The relevance was
demonstrated through application of the ESPF to live Projects.
Page 14 of 111
All projects where IEISL has ownership of more than 50% will gradually get their site
operations certified for Environmental Management System (EMS) ISO 14001 and
Occupational Hazard and Safety Aspects System (OHSAS) 18001 certification. In preparation
of EMS and OHSAS documentation, RRCs identified by ESPF shall be converted into
Standard Operating Procedures to be followed in the implementation of the project. Once the
project site is certified for both these standards, ESPF monitoring will continue in the form of
EMS/ OHSAS audit conducted by external auditors. All outstanding RRCs will be handed
over to the EMS system. All the details of the projects which have been converted in to EMS
shall be communicated to CSC.
II. The IEISL ESPF
A. Business Canvas of IEISL
(a) IEISL is a developer, operator and advisor on waste management
and urban environmental infrastructure projects, operating from
conceptualization through commissioning to operations and
maintenance. The portfolio includes new waste treatment facilities as
well as up-gradation, operation and maintenance expansion of
existing facilities and marketing of compost.
(b) IEISL has been involved in providing consulting and advisory
services as well as designing and implementing projects in
multimedia waste management in the Public Private Partnership
(PPP) framework in various parts of the country. IEISL has been
assisting urban local bodies in developing integrated waste
management systems.
(c) The key services offered under Advisory and Consulting are:
i. Geographical Information Systems (GIS) based services
ii. Environmental advisory services such as
o environmental impact assessment / management
plans including facilitation for prior environmental
clearance
o preparation of guidance and training manuals
o energy efficiency audits and conservation
o Clean Development Mechanism (PDDs, facilitation
for verification, validation, facilitation in transaction
and trading of CERs / VERs / ERPAs) for own waste
projects as well as other external clients
(d) The key services offered under Waste Management Infrastructure
are:
i. Design, development and execution of integrated municipal
solid waste (MSW) management facilities
ii. Solid waste processing and recycling (composting, bio-
methanation, waste to energy / refuse derived fuels,
Page 15 of 111
construction and demolition waste recycling, e-waste
recycling)
iii. Design and development of engineered sanitary landfills
iv. Dumpsite rehabilitation including closure and landfill
capping
v. Door to door collection, segregation and transportation of
Municipal Solid Waste (MSW)
vi. Waste to energy projects
vii. Clean Development Mechanism (CDM) implementation for
waste management projects of IEISL
(e) The present organizational structure based on the business services
of IEISL is presented in Figure 1.
IWMUST - Integrated Waste Management and Urban Services Company (Tamil Nadu) Ltd; EDWPCL –
East Delhi Waste Processing Company Ltd.; CDM –Clean Development Mechanism; IEWMCL –
Indraprastha Energy and Waste Management Company Pvt. Ltd. ; UWPCL – Unique Waste Processing
Company Ltd.; KRML- Kanak Resource Management Limited; DDSIL- DakshinDilliSwachh Initiatives
ltd.
Figure 1: IEISL Organizational Structure based on Business Services
B. Relevance of ESPF to IEISL
(a) Advisory and Consulting Services. The ESPF provides a framework
to identify risks faced by the services, terms of reference and
checklists for review of outputs for various services aimed towards
maintaining quality and consistency in deliverables. This framework
would support IEISL in delivery of E&S advisory services and
provide a base outline that could be customized to meet client’s
requirements. Depending on the scope of the advisory services, the
formats and checklists provided in the risk management framework
could be utilized in delivering outputs. Any advisory project such as
a DPR prepared for the benefit of environment management is not
within the purview of IEISL’s ESPF policy, as it is a short term project
of 3-5 months. Exposure to the project itself is minimized and as
DDSIL
Page 16 of 111
such, these types of advisory activities do not pose financial and
reputational risks. The complete list of risk prevention and control
measures in ESPF would be applicable to such projects IEISL in their
advisory services based on context and scope of services.
(b) Design and implementation of waste management infrastructure.
The MSW, C&D projects at IEISL could potentially pose significant
risks to environment as well as community and occupational health
& safety. These MSW and C&D management projects are regulated
and mandated under various environmental legal requirements in
India. The land required for construction of new MSW and C&D
treatment and disposal facilities or expansion and modernization of
existing facilities has to be acquired for the purpose. For instance,
i. Environmental Clearance is necessary for all new and
expansion of MSW management Projects. Additionally the
General Conditions1 based on proximity to ecological sensitive
or polluted areas etc. are also applicable.
ii. MSW and C&D Project development also includes land
acquisition which is regulated through the Right to Fair
Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 As per the Act, a
Social Impact Assessment would need to be conducted and
compensation, resettlement and rehabilitation would have to
be undertaken as per the entitlement framework of the Act,
which now also takes into account loss of livelihood in
addition to loss of property.
iii. If funding for the project is being sought from banks that
adhere to an environmental and social policy such as multi-
lateral development banks (MDBs) like World Bank/ Asian
Development Bank or Equator Principles there are additional
requirements on environment, occupational health & safety
and social (EHSS) issues to be conformed with. In the event
IEISL wishes to participate in Projects funded by such MDBs
either in India or abroad, it would benefit from knowledge of
such practices.
iv. Generation of gas and leachates mainly due to microbial
decomposition, climatic conditions, and self characteristics of
the waste, are inevitable consequences of the disposal in
landfills. The risks for the public health due to the potential
exposure to pathogenic agents, toxic substances, and gases,
together with the annoyances derived from the bad odours, the
migration of gases and leachates outside the limits of the
landfill, and their release to the surrounding environment,
1 General Condition (GC) as per EIA Notification 2006 and amendment in 2009: Any project or activity specified in
Category ‘B’ will be treated as Category A, if located in whole or in part within 10 km from the boundary of:
(i) Protected Areas notified under the Wild Life (Protection) Act, 1972;
(ii) Critically Polluted areas as notified by the Central Pollution Control Board from time to time;
(iii) Eco-sensitive areas as notified under Section 3 of the Environment (Protection) Act, 1986;
(iv) Inter-State boundaries and international boundaries.
Page 17 of 111
raise a number of important environmental questions
including the possibility of fire and explosions, damages to the
vegetation, groundwater contamination and atmospheric
pollution.
v. Dumpsite rehabilitation projects that concern open dumpsites
located in close proximity to developed areas are pressurized
to implement stringent closure and post-closure measures.
Along with technical feasibility and financial viability,
environmental soundness with respect to compliance to the
legal requirements as well as acceptability to the society has to
be addressed.
vi. MSW and C&D contains a number of chemical and biological
agents that may expose different populations to health
hazards, ranging from the composting plant workers to the
consumers of vegetable products grown in soils treated with
compost.
vii. Waste-to-energy projects using refuse derived fuels (RDF)
involve segregation of combustible and non-combustible waste
which may be a manual or mechanical or a combined process.
These facilities have to meet regulatory air quality standards.
The fly ash and bottom ash as a by product of the combustion
process has to be disposed as per the regulations and care
should be taken during classification whether they are
hazardous or non-hazardous. The location of these facilities
could conflict with surrounding land uses. The facility could
lead to transportation impacts from numerous truck trips from
the refuse source. The waste-to-energy facility requires sound
planning so as to prevent public opposition due to
uncertainties over health, safety, odour, and traffic impacts;
and avoid possible hazardous materials leakage that may
necessitate site cleanup after facility closure.
viii. E-wasteManagement and Handling Rules 2011 specify
requirements to be fulfilled by collectors, dismantlers and
recyclers. Authorization is to be obtained from the State
Pollution Control Board for such activities. The processes for
dismantling and recycling can pose severe impacts on
environment and health & safety of workers and community
as it required working with hazardous substances.
(c) The tenure of MSW and C&D projects is long term and attracting
liabilities on environment, health, safety and social issues could
indirectly create a risk as they would threaten timely repayment and
damage the company goodwill should such liabilities result in
stalling or closure of projects.
(d) During IEISL’s association with the project, ESPF will provide a
system that checks and plans for environmental compliance of
projects along with risks related to environmental pollution and
health and safety.
Page 18 of 111
III. ENVIRONMENTAL AND SOCIAL POLICY FOR IEISL
A. IEISLs E&S Policy Statement
IEISL has adopted the following E&S policy approved by its Board of Directors in
November 2011:
IL&FS Environmental Infrastructure & Services Limited (IEISL) is driven by its mission to
advise, develop, implement, operate, finance and participate in urban environmental
infrastructure projects, including waste management.
The IL&FS Environmental and Social Policy and Framework (ESPF) is founded on the
concept of Sustainable Development and thereby recognizes Environmental and Social
(E&S) considerations in its business operations to add value, minimize impacts and risks to
increase effectiveness of IEISL’s services on environmental infrastructure projects.
To achieve this, IEISL will establish and implement mechanisms to conserve natural
resources, protect the environment and provide safe and healthy workplace for their
employees and contractual staff, wherever relevant and necessary.
The ESPF applies to the business canvas of IEISL including its subsidiaries.
IEISL is committed to comply with its E&S policy, applicable laws of the land and be
responsive to existing and emerging global E&S concerns on a proactive basis.
Managing Director
Date: __________
B. IEISL ESPF Principles
The E&S policy of IEISL is to be implemented through the application of
Guiding, Operational and Engagement Principles.
(a) The Guiding, Operational and Engagement Principles form the core
of IEISL’s E&S Policy.
(b) IEISL is committed to comply with E&S regulations and legal
requirements with due credence to local, national and global
concerns.
(c) IEISL will also endeavor to move beyond compliance by
incorporating suitable technologies and practices as far as their use is
technically and financially feasible, and cost-effective.
Page 19 of 111
(d) IEISL will reflect the E&S principles followed by its
lenders and partners in its operational procedures in a harmonious
manner.
(e) IEISLrecognizes the importance of ensuring the proper management
of E&S risks for each project. Major E&S problems could adversely
affect operations, earnings of SPV’s and hence returns from
investments. Consequently, IEISL places significant emphasis on not
only E&S impacts, but also on E&S risks identification, assessment,
allocation and management at the project level.
(f) The following sections outline the Guiding Principles, Operational
Principles and Engagement Principles for IEISL’s projects.
C. Guiding Principles
(a) The Guiding Principles embody the spirit of IEISL’s ESPF. They are
non-negotiable and shall apply to IEISL, its subsidiaries and associate
companies. Through its Guiding Principles, IEISL commits to (a)
adding value to projects it undertakes, (b) integrating E&S concerns
into the decision-making process, and (c) minimizing exposure to
E&S risks.
(b) The Guiding Principles (i) through (iii) below are designed such that
they follow an imperative hierarchy. The measures and actions to
address identified impacts/risks will favor the avoidance and
prevention of impacts over minimization, mitigation, or
compensation, wherever technically and financially feasible.
(c) The Guiding Principles (iv) through (vi) below concern the elements
of engagement, compensation, and restoration, and are common to
all projects undertaken by IEISL.
The ESPF commits each project to the following guiding principles
(i) The Precautionary Principle or “do no harm” principle; when an
activity raises threats of harm to human health or the environment,
precautionary measures will be taken even if some cause and effect
relationships may not be fully established on scientific grounds.
(ii) The Preventive Principle; excluding activities which are regulated or
prohibited under International Agreements and by National Laws,
preventing adverse E&S situations by revisiting the project concept,
minimizing the release of polluting wastes to amounts that do not
affect the environment adversely, avoiding or minimizing
resettlement of people due to land acquisition, conserving natural
resources and protecting biodiversity and/or minimizing health and
safety hazards.
(iii) The Mitigative Principle; mitigating adverse E&S impacts by meeting
required State/National Policies and Legislations, incorporating
Page 20 of 111
EMPs and SMPs into the Project Cycle, and following best practices
without affecting the financial viability of the project. This principle
also extends to evaluating the impacts/risks that may result from the
implemented mitigation measures themselves.
(iv) The Participatory Principle; ensuring public participation and
community consultation, which will be free of external manipulation,
interference, or coercion, and intimidation, and conducted on the
basis of timely, relevant, understandable and accessible information.
(v) The Compensatory Principle; assisting project-affected persons in
improving or at least restoring their livelihoodds and standards of
living in real terms relative to pre-displacement levels or to levels
prevailing prior to the beginning of project implementation,
whichever is higher, wherever relevant and within the scope of the
project.
(vi) The Restoration Principle, restoring the natural condition of the
project site after completion of construction and decommissioning,
wherever relevant and within the scope of the project.
D. Operational Principles
1. The Operational Principles provide guidance to IEISL and its
subsidiaries as well as third parties involved in project execution in
enacting the ESPF. They are intended to provide appropriate focus
on E&S viability in projects.
2. These principles are flexible and adaptable; the manner of their
application will be commensurate with the nature of the activities of
IEISL, its services, and the locations and conditions in and under
which it operates.
3. Following steps are to be followed for risk identification, assessment,
categorization and determination of risk control and management
measures by IEISLduring planning and execution of the project:
(a) Examine the likely E&S risks and impacts of the project, by referring
to the E&S risk rating in Annexure A. It determines the typical level of
inherent E&S risk related to a particular business activity and location,
to assist IEISL in judging the appropriate levels of E&S investigation
that should be carried out, suitability of risk prevention and control
measures to be applied, and intensity of E&S risk control and
monitoring to be invoked.
(b) Depending on the outcome of the E&S Risk Rating process and the
impacts/risks involved, conduct an E&S assessment to address the
relevant E&S impacts/risks of the project, and propose suitable
preventive, mitigative, compensatory and restorative measures post
analysis of the impacts/risks of all project alternatives, including the
mitigation measures themselves.
Page 21 of 111
(c) Depending on the outcome of the E&S assessment, where
relevantprepare/implement Environmental Management Plan (EMP)/
Resettlement Action Plan (RAP) drawing on the conclusions of the
E&S assessment, describe and prioritize the actions needed to
implement mitigation measures, corrective actions and/or monitoring
measures necessary to manage the impacts/risks identified in the
assessment, including the provision of safe and healthy working
conditions for project labour.
(d) Depending on the outcome of the E&S Risk Rating process, where
relevant ensure engagement of project-affected persons in a structured
and culturally appropriate manner wherever relevant:
(i) their free, prior and informed consultation and facilitating
their informed participation as a means to establish whether
a project has reasonably incorporated affected peoples’
concerns within the framework of applicable legislation,
(ii) that the process and results of the consultation, including
any actions agreed resulting from the consultation are
documented,
(iii) that information disclosure takes place in a culturally
appropriate manner and in the local language, of requisite
documents at appropriate stages of the project cycle, and
(iv) that depending on the outcome of the categorization, scaled
to the impact/risks of the project, a grievance mechanism is
established as part of the engagement process, to ensure that
consultation, disclosure and community engagement
continues throughout IEISL’s association with that project.
(e) Where relevant, ensure that compensation to project-affected persons
will conform to the applicable National legislations [i.e. Right to Fair
Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013. IEISL will factor the same into the Social
Entitlement Framework.
(f) Where relevant, ensure that Indigenous People are suitably recognized
wherever applicable, conforming to the spirit of National legislations
[Draft Tribal Development Plan (2006), Forest Rights Act (2006) and
Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013]. An Indigenous People’s
Plan will be prepared to ensure their inclusion and active participation
in project benefits in a culturally appropriate manner. Further,
international good practices will be referred to where gaps exist in the
policies at National and State levels in the area of Indigenous People.
(g) Commensurate with the impact/risks of the project/transaction and its
applicable regulatory requirements, to monitor its compliance and
progress towards desired outcomes on a regular basis throughout its
Page 22 of 111
lifetime or till the end of IEISL’s association with the project, whichever
is earlier.
(h) Where relevant, ensure the preparation and implementation of a
decommissioning /closure plan, which must address:
(i) an analysis of impacts/risks at this particular stage of the
Project Cycle,
(ii) where appropriate, application of pollution prevention and
control technologies and practices (techniques) that are best
suited to avoid or where avoidance is not feasible, minimize
or reduce adverse impacts on human health and the
environment while remaining technically and financially
feasible and cost-effective, and
(iii) compensatory and/or restorative measures to be undertaken
for ecological enhancement.
(i) Incorporate E&S covenants in the contract documentation to ensure
that E&S considerations in EMPs and RAPs are duly implemented
and to insulate IEISL against all E&S risks associated with the project.
(j) Comply with all relevant national E&S policies, laws, regulations and
permit requirements. Where a project is not in compliance, work with
the Corporate ESPF Cell of IL&FS to achieve compliance levels.
(k) Periodically update procedures and guidance documents to
incorporate relevant developments in the arena of E&S management.
E. Engagement Principles
(a) In projects where IEISL does not have majority control, IEISL has
devised Engagement Principles for the organization to observe.
(b) The Engagement Principles mirror the ideology of the IEISL ESPF.
They serve to further IEISL’s aspiration to inspire and encourage all
stakeholders, including partners and co-investors towards continual
improvement in their areas of operation.
(c) Accordingly, IEISL while engaging in business with organizations will
encourage them to observe the following:
(i) Comply with national E&S, health and safety-related local
laws, as a minimum,
(ii) Take account of the E&S impact of their operations (through
an E&S Assessment in cases involving loss of biodiversity or
habitat, climate change, deterioration in land, water and/or
air quality, substantial displacement, and other issues where
Page 23 of 111
the negative E&S impacts could be significant) and take steps
to mitigate any E&S risks, and
(iii) Take account of their impact on employees, contractors, the
local community and all others affected by their operations
(through appropriate consultation, and through a Social
Assessment in cases involving involuntary resettlement,
religious/cultural property, vulnerable groups, and other
issues where the negative E&S impacts could be significant)
and take steps to mitigate any E&S risks.
(d) IEISL shall use an E&S risk categorization process for each proposed
project as early as possible, to examine broadly its likely E&S risks
and impacts. This will determine the typical level of inherent E&S risk
related to a particular project, and will assist Project Manager in
judging the appropriate levels of E&S investigation that should be
carried out, and suitability of procedures to be applied, and intensity
of E&S risk control and monitoring (if any) to be invoked.
Page 24 of 111
IV. E&S RISK IDENTIFICATION AND MANAGEMENT PROCESS
The methodology for E&S Risk Identification and Management comprises of the four
steps as shown in Figure 2.
Figure 2: Steps involved in E&S Risk Identification and Management
A. Step 1 – Determine E&S Rating
(a) The process for assigning risk rating involves reviewing Project
details, understanding environmental and social impacts, assessing
exposure and liabilities related to environmental and social non-
compliance. The E&S risk ratings define the extent of follow up
actions and monitoring required for the project to avoid or mitigate
E&S risks.
(b) Based on such assessment, a Project will be assigned any one of the
following E&S Risk Ratings:
(i) L; i.e. the Project poses low E&S risk and can be addressed
through good practices.
(ii) M; i.e. the Project poses moderate E&S risk which can be
prevented and/or mitigated by execution of appropriate
procedures and good practices as guided by the ESPF
followed by periodic monitoring.
(iii) H; i.e. the Project poses high E&S risk requiring application
of more involved procedures (field visits) with good
practices followed by rigorous monitoring.
(c) Risk in ESPF, is interpreted as the extent of obligations to be fulfilled
/ due diligence to be conducted, the absence of which could lead to
Page 25 of 111
liabilities or adverse impacts for the company in the form of legal /
scope unfulfilled, monetary and/or reputational damage.
(d) The E&S risk rating methodology developed for projects at IEISL is
given in Annexure A. Table A gives E&S risk rating criteria for waste
management implementation projects and Table B gives criteria for
advisory services.
(e) The E&S risk rating is a dynamic process which can be elevated or
lowered based on the project’s performance evaluated through
periodic monitoring.
B. Step 2 – Apply E&S Risk Reduction Controls
(a) Depending on the E&S Risk Rating assigned to a particular project,
IEISL/ project proponent / client will need to undertake certain
responsibilities towards managing the identified E&S risks and their
impacts. This will be made possible through the application of
appropriate E&S risk reduction controls.
(b) The contributing criteria to the E&S risk rating will indicate the
application of appropriate E&S risk reduction controls to be applied.
(Refer Annexure B). The applicable risk reduction controls will be
executed by review of environmental, health & safety legal
compliance; conducting E&S studies; incorporating relevant E&S
aspects in detailed project reports; insertion of covenants to this effect
in contract agreements drawn; and communication to client.
(c) Elevated E&S Risk Ratings will attract E&S risk reduction controlsof
a more advanced nature as compared to E&S Risk Ratings lower
down the hierarchy.
C. Step 3 – Monitor E&S Risk
(a) By monitoring E&S risk, IEISL intends to ensure that its E&S risk
reduction controls for each proposed project facility continue to
remain effective and safeguard IEISL against perceived E&S risks
throughout its tenure. E&S risk monitoring periodicity depending on
the risk rating is detailed in Annexure C.
(b) The E&S Risk Reduction Controls Action Planning and Monitoring is
undertaken based on the ESPF Form II attached in Annexure E.
(c) Transfer of risk monitoring from ESPF to IMS is reverted back to ESPF.
Risk monitoring frequency reduced to once a year after IMS is
established
Page 26 of 111
V. INSTITUTIONAL ARRANGEMENT
A. Composition of the IEISL E&S Cell
1. A Corporate Sustainability Cellhas been instituted at IL&FS Corporate
for implementation of ESPF at the holding company level. AnE & S Cell
has also been instituted at IEISL for implementation of ESPF.
2. The IEISL E&S Cell will comprise of an E&S Coordinator supported by
technical expertise (environmental and social specialists), where
required.
3. Technical expertise in environmental and social domains is currently
being built within IEISL and the Corporate Sustainability Cell at IL&FS
will provide this support to the E&S Coordinator in the transition
period.
4. The institutional structure with indicative functions for implementation
of ESPF at IEISL is given in Figure 3. The operational procedure for
implementing (the functions indicated in Figure 3) ESPF in IEISL during
bidding, project development, construction and operation phase is
given in Section VII.
5. The entities as part of the institutional arrangement comprise of; the
Corporate Sustainability Cell, the IEISL E&S Cell, the various teams at
IEISL, client, Special Purpose Vehicle (SPV) created for projects and the
Independent Auditing Agency.
6. The IEISL E&S Cell is the hub of ESPF activities at IEISL. The cell
coordinates with the project managers from different teams at IEISL on
E&S risk assessments and monitoring. It further presents periodic
updates on ESPF implementation to the IEISL Board.
7. The Project Managers are responsible for conducting E&S risk
assessment and monitoring for their respective projects. The role of the
main stakeholders has been listed in the following sections.
B. Role of Corporate SustainabilityCell (CSC)
The role of the Corporate SustainabilityCell (CSC) in implementation of ESPF
at IEISL will be as follows:
(a) Communicate the requirements for establishment of ESPF in IEISL
(b) Assist IEISL in customization and establishment of ESPF
(c) Conduct periodic corporate review of ESPF implementation
(d) Facilitate training sessions for capacity building
(e) Coordinate the conduct of external audit
(f) Assist IEISL in any matter related to Environmental initiatives of the
IL&FS Group and ESPF implementation
C. Role of IEISL E&S Cell
The role of theIEISL E&S Cell will be as follows:
(a) Act as IEISL’s focal point for all ESPF activities
(b) Organize and review required documentation for assessment of
environmental and social impacts
(c) Coordinate corporate reviews and annual external audits
(d) Coordinate training for IEISL staff
Page 27 of 111
(e) Update the ESPF based on operational experience
(f) Prepare a Master database on the status of implementation of ESPF
captured in ESPF Form V attached as Annexure LThe master list in the
excel file format will include all P/T/A assignments irrespective of ESPF
applied to the same.
(g) The ESPF coordinator is required to maintain a master list of all live
P/T/A assignments of the company. The coordinator will send an
updated master list to CSC in the first fortnight of every quarter. The
email communication containing the master list must also be sent to the
CEO of the Group Company.
(h) The ESPF coordinator will give final approval for all forms
(i) Coordinator should ensure that all file names are in the standard
format: ‘Final Form X short project name Date.abc’ abc’ (Applicable for
Form I, II and IIA). Other forms (Forms III, IV & V) are to be
maintained with the word “final” and date but would not have a
project name.
(j) Present findings of corporate review to the Risk Committee for
consideration as per format prescribed in Annexure O
(k) Present findings of external audit to the Board of Directors for appraisal
(l) Coordinators can volunteer as ‘Reviewers’ to conduct review of other
group companies.
(m) The ESPF coordinator has to finalize the ESPF Form I- Environmental
and Social Risk Assessment as per the attached as Annexure D. If
required, CSC review comments are to be discussed by ESPF coordinator
with CSC. Accordingly, comments are to be incorporated in the Final
Form I.
D. Role of Project Manager
The role of Project Manager in implementation of ESPF at IEISL will be to:
(a) Inform IEISL’s ESPF to clients/partners whenever required
(b) Conduct E&S risk assessment of the P/T/A
(c) Monitor the implementation of E&S risk reduction controls
(d) Update the E&S risk assessment in case of modifications in the project
on award of project.
(e) Prepare covenants to reduce environmental and social risks
(f) Engage E&S specialists as required
(g) Appear for corporate reviews and external audits
(h) Assist the E&S Coordinator in any manner as required for
implementing ESPF at IEISL
(i) Attend training sessions conducted by IL&FS CSC and IEISL E&S
Coordinator
(j) Review the periodic modifications carried out in the ESPF document
(k) Regarding projects that are temporarily stopped due to a technical or
financial reason from the client side, will prompt the Manager of that
project, to write a letter to the client asking for clarification of the same
and explaining the problems that may arise due to this action. In such a
case, the project is considered to be ‘on hold’. T respective P/A managers
will be required to send an email to the Vice President of the Project,
E&Scoordinators, Vice –President of Environmentrequesting that the
Master Database and associated forms reflect this.The E&S coordinator
can then consult the MD and other members of senior
Page 28 of 111
managementabout how to proceed with such projects.A project will be
termed ‘closed’, once all deliverables (technical works/support) have
been submitted by IEISL to the client and have received approval for the
same from the client. On the closure of a project, the manager of the
respective project will write an email to the Vice-President of the project,
E&S Coordinator and Vice-President of Environment informing them of
thesame.
(l) During project transition from ESPF to EMS;
a. The project manager will update all the points mentioned in EMS to
EHS sheets
b. The project manager will incorporate all the suggested points before and
after audit
c. The project manager will send the audit report to ESPF coordinator
Page 29 of 111
(m) ESPF activity will only be reinstated for these projects once communication is received from the manager about the revival of the
projects.
Figure 3 : Institutional Structure
Page 30 of 111
VI. OPERATIONALIZATION OF ESPF AT IEISL
A. Mapping ESPF Steps to IEISL’S Business Cycle
(a) The ESPF Steps are mapped to every stage of the project cycle as
applicable (See Figure 4, 5 and 6).
(b) The mapping of Procedures to different stages of the project cycle is
an indicative list of which only some will be applicable at a time
based on the E&S risk rating, scope of project and features of project.
(c) ESPF is mapped for two project cycles of the Project Implementation
Services - projects obtained through answering bids and sole sourced
projects; and one project cycle for the advisory services.
(d) The ESPF is not applicable to GIS services provided by IEISL as no
E&S risks are perceived in these projects.
(e) InCDM services provided by IEISL, the scope of work is limited to
project registration and assistance in monitoring and CER issuance.
Though the project to which IEISL is providing CDM services may
pose E&S risks, however due to their limited scope in these projects,
the E&S risk rating for CDM services has been identified as ‘Low’.
Hence,ESPF will not be applied for each CDM project.
(f) ESPF is also not applicable to energy efficiency projects as the
projects pose very less risk and IEISL has a very limited scope in
these projects. These projects are usually have a low risk rating
(g) Any short term (less than 6 months) advisory project such EIA, DPR
etc. is not within the purview of IEISL’s ESPF policy, , these types of
advisory activities do not pose any E & S risks.
B. Integration of ESPF into workflow of IEISL – Project Implementation and
Advisory Services
The integration of the ESPF into the workflow of Project
Implementation and Advisory Services is shown in Figures4, 5 and
6for IEISL.
Page 31 of 111
Figure 4: Project Cycle Mapping with ESPF – Bid Projects (Project Implementation)
Step 1: Identification of E&S Risk & Risk Rating
(Generate ESPF Form I and Annexe to BAM)
Step 2: Application of E&S Risk Reduction Control
List risk reduction controls for bid stage/studies
Including cost of conduct of E&S studies, EMP and
R&R, and implementation of management measures
Step 3:
Revision of Form I
Conduct of Monitoring (ESPF Form II) and Reporting
Monitoring execution of risk reduction controls in ESPF Form II
EHSS Internal Audit/review EHS performance
Monitoring of implementation and effectiveness of EMP and
corrective actions.
Conduct EIA and obtain EC
Set up EHSS Management System
Include additional covenants on
environmental, health & safety requirements
(as per the risk reduction controls) and EMP in
contract documents
Conduct ESPF Monitoring Reporting
Implement EMP including post EC monitoring
Obtain & comply with applicable
clearance/consent/approval conditions
EHSS Internal Audit
Covenants on EHS of labour in the labour
contract.
Step 2: Application of E&S Risk Reduction
Controls (Revise ESPF Form I) Generate Action
Plan for risk reduction controls in Form II
Request for
Qualification (RFQ)
MD Approval
Business Approval
Memorandum (BAM)
Request for Proposal
(RFP)
Technical and
Financial Bid
Concession
Agreement
Detailed Project
Report
Contractor’s
Agreement
Financial Close
Construction
Labour
Contract
Operation &
Maintenance
Transfer
Page 32 of 111
Figure 5 : Project Cycle Mapping with ESPF – Sole Sourced (Project Implementation)
Step 1: Identification of E&S Risk & Risk Rating
(Generate ESPF Form I and Annexe to BAM)
Step 2: Application of E&S Risk Reduction Control
List risk reduction controls for bid stage/studies
Including cost of conduct of E&S studies, EMP and
R&R, and implementation of management measures
Influencing the client to incorporate measures on
environmental protection; health & safety; & social
acceptance
Step 3: Conduct of Monitoring (ESPF Form II) and
Reporting
Revision of Form I
Monitoring execution of risk reduction controls in
ESPF Form II
EHSS Internal Audit/review EHS performance
Monitoring of implementation and effectiveness
of EMP and corrective actions.
Business
Development
MD Approval
Business Approval
Memorandum (BAM)
Proposal Submission
Letter of Intent
Concession
Agreement
Detailed Project
Report
Contractor’s
Agreement
Financial Close
Construction
Labour
Contract
Operation &
Maintenance
Transfer
Conduct EIA and obtain EC
Set up EHSS Management System
Include additional covenants on
environmental, health & safety requirements
(as per the risk reduction controls) and EMP in
contract documents
Conduct ESPF Monitoring Reporting
Implement EMP including post EC monitoring
Obtain & comply with applicable
clearance/consent/approval conditions
EHSS Internal Audit
Covenants on EHS of labour in the labour
contract.
Step 2: Application of E&S Risk Reduction
Controls (Revise ESPF Form I) Generate Action
Plan for risk reduction controls in Form II
Page 33 of 111
Figure 6: Project Cycle Mapping with ESPF - Advisory Services
Page 34 of 111
Bidding Phase/ proposal development phase
1. In case of a project to be developed through bidding route, on receipt of a
Request for Proposal (RFP), while preparing the technical and financial bid, a
preliminary E&S risk assessment will be carried out and recorded in ESPF
Form I given in Annexure D (A)along with the Bid Approval Memorandum.
2. In case of a project to be developed and sole sourced, a preliminary E&S risk
assessment will be carried out and recorded in ESPF Form I given in
Annexure D (A) and with Transaction Approval Memorandum.
3. When the TAM is being generated for an advisory project, a preliminary E&S
risk assessment will be carried out and recorded in ESPF Form I given in
Annexure D (B).
4. The project manager will enter the information required for carrying out E&S
risk assessment and assign an E&S risk rating (refer Annexure A) based on
the criteria. The project manager will also populate a list of applicable risk
reduction controls (Refer Annexure B) during project proposal submissionor
at bid stage on the basis of the project context and scope.
5. The E&S risk assessment results will be notified by the project manager to
IEISL E&S Cell through an email notification. IEISL E&S Cell will review the
E&S risk assessment results. The risk rating can be modified justifying
reasons for the same. The list of risk reduction controls will be finalized by
the IEISL E&S Cell based on project/ advisory context and scope.
6. A guidance procedure for assessment of a project in ESPF Form I is given in
Annexure F.
7. The entire ESPF Form I will be annexed with the TAM.The risk analysis point
in the TAM will include the (i) risk rating and (ii) risk reduction controls
(RRCs) so that risk perception is easily available to the approver or decision
maker.
8. The ESPF Form I would be revised in case of the following conditions;
(i) Award of project.
(ii) Change in project manager, project location, components, allied
activities and scope of work which render the existing risk rating
and risk reduction controls inappropriate.
(iii) Modification/s for closing corporate review or external audit
findings.
(iv) Revision of E&S risk rating.
(v) Amendments in legal requirements and introduction of new
regulations
Award, Design & Tendering Phase
9. Once the project/ advisory is awarded to IEISL, the ESPF Form I for the
project will be revised to include E&S risk reduction controls for design,
Page 35 of 111
construction and operation phases of the project (refer Annexure B). The
requirements for E&S clearances, approvals, permits applicable to the project
will also be noted at this stage.
10. IEISLE&S Cell will develop an action plan for implementation of risk
reduction controls identified in ESPF Form I. The action plan will include
details on tasks, outputs, responsibility and timelines for each risk reduction
control in ESPF Form II given in Annexure E. The controls applicable on a
one time basis and those requiring periodic action will be identified.
11. The E&S covenants recommended in ESPF Form I will be included in
contractual (tender) documents.
12. Monitoring will be conducted as per the action plan in ESPF Form II before
release of contractual (tender) documents for bidding, to check and record
whether E&S risk reduction controls have been incorporated.
13. The guidance procedure for monitoring of a project using ESPF Form II is
given in Annexure G.
Construction Phase(Applicable to Advisories only if the scope includes
Supervision of Construction/ Project Management Consultancy PMC)
14. IEISL will ensure implementation of all environmental, health & safety
measures specified in various documentation (but not limited to) such as
project legal clearances/ approvals, ESPF Form I and IL&FS construction
environmental management plan manual.
15. The monitoring in ESPF Form II will be conducted as per the periodicity
defined for the project. Any new risks identified during monitoring will be
captured in ESPF Form II with an action plan for subsequent monitoring in
the next cycle. For each monitoring cycle, ESPF Form II will be revised as
per the new format instead of creating a new form II each time.
16. Based on the monitoring results, the E&S risk rating may be elevated as per
the guidance given in Annexure C to ensure close monitoring of the project.
The revised E&S risk rating will be captured in ESPF Form I as a revision
with appropriate justification.
17. IEISL will obtain a monthly reporting on environmental, health & safety
parameters from the project site in ESPF Form IIA ( Refer Annexure L)to
identify new risks. A major incident or fatality occurring at site during
construction will also trigger incident investigation and reporting from the
project site. Similarly, any litigation filed on the company with respect to E&S
issues will also trigger a monitoring and reporting.
18. IEISL may provide the contractor/s with specifications and procedures for
implementation of environmental mitigation measures given in the
IL&FSConstruction EMP Manual, where required.
Page 36 of 111
19. A project-specific legal checklist of clearances and approvals granted as well
as those required at a later stage when the project progresses, will be
maintained at the project site or at IEISL’s Corporate office. For clearances/
approvals granted, the checklist will include reference number, date of issue,
validity and date of renewal (if required). IEISL will ensure that conditions of
clearances and approvals applicable in the construction phase are
implemented at site.
Operation Phase(Applicable to Advisories only if the scope includes Supervision
of O&M)
20. IEISL will ensure implementation of all environmental, health & safety
measures specified in various documentation (but not limited to) such as
project legal clearances/ approvals and ESPF Form I for the operation phase.
21. The monitoring in ESPF Form II will be conducted as per the periodicity
defined for the project. Any new risks and risk reduction controls identified
during monitoring will be captured in ESPF Form II with an action plan for
subsequent monitoring in the next cycle. For each monitoring cycle, a new
ESPF Form II will be created capturing risk reduction controls that need
continuous monitoring. A major incident or fatality occurring at site during
operation will also trigger incident investigation and reporting from the
project site. Similarly, any litigation filed on the company w.r.t. E&S issues
will also trigger a monitoring and reporting.
22. Where required, the E&S risk rating may be elevated or lowered during
monitoring based on the guidance given in Annexure C& E and captured in
ESPF Form II. The revised E&S risk rating will be captured in ESPF Form I
as a revision with appropriate justification.
23. The clearances and approvals granted to the project for commissioning will
be added to the legal checklist along with thereference number, date of issue,
validity and date of renewal (if required). IEISL will ensure that conditions of
clearances and approvals applicable in the operation phase are implemented
at site.
C. Operational Mechanism
(a) The ESPF will be applicable to all projects and advisory services
awarded and ongoing after the date of E&S policy approval by IEISL.
For waste management implementation projects, ESPF will also be
applied at the bidding stage.
(b) E&S issues will be identified for all projects considering the scope of
IEISL in the project. If a significant issue is identified, IEISL will take
suitable actions to address the issue itself or by influencing the client.
(c) In the initial stages CorporateSustainability Cell will play a major
role. The IEISL E&S Cell will be trained to carry out its functions by
the Corporate Sustainability Cell. With time as ESPF matures and
Page 37 of 111
integrates in the operations of IEISL, the role of Corporate
Sustainability Cell will gradually reduce and finally be phased out.
(d) IEISL shall also endeavor to get relevant certifications such as ISO
9000, ISO 14001 and OHSAS 18001 certifications for Environmental
Management System for projects where it has ownership of more
than 50% and can exercise management control. In the event of the
certification of a project site for Environmental Management System,
the ESPF shall cease to be apply to that particular project
(e) Projects / project companies that are commencing operations or have
achieved sustainable operations shall / project companies obtain the
IMS / EHS certification, the ESPF shall be replaced with the
applicable EMS and OHSAS documentation and these shall become
the governing framework for E&S related matters of the respective
projects for the operations phase.
(f) Even after transfer of a project or transaction from ESPF to EMS,
Project Manager continues to report on following aspects on
quarterly basis:
I. Legal notices, fines and litigation - Litigation information is
shared with the CSC.
II. Accidents and safety events - Fatalities if any should be
reported to CSC.
III. Social Unrest - Any event of social unrest against the project
should be reported to CSC
(g) The RRC’s (as per the ESPF) identified and untreated / open on the
date of transition from ESPF to IMS/EHS system will be monitored as
perunder IMS/EHS system through either of the three registers
namely Hazard Identification and Risk Assessment, Aspect Impact
Register, and Legal register as per the project nomenclature
(h) Once a project is transferred to IMS/EHS, it will be subject to
verification in the immediately upcoming internal audit and external
audit only
D. Training and Awareness Generation
(a) IEISL ESPF Cell will conduct a maximum of 1 full day training
sessions customized to train the staff in E&S Risk Rating,
Environment Health and Safety (EHS), Environment Management
System (EMS), Introduction of IMS system and application of risk
reduction controls to their projects.
Page 38 of 111
(b) ESPF will also be introduced into the training organized during
induction of staff at IEISL.
(c) ESPF coordinator shall frame training program/ schedule as per
mandatory online training modules conducted by the CSC ESPF
coordinator shall communicate the training program/ schedule to the
HRD of IEISL.
(d) The records of training conducted will be maintained in the format
attached in Annexure J.
(e) Training and awareness generation to be made subject to intensity of
business activity
E. Corporate Review and External Audit
1. The purpose of the audit includes but is not limited to determining
continued conformance with the requirements of the IEISL’s ESPF. The
audits will take two forms – Corporate Review and External Audit.
2. The Corporate Review will be conducted by the Corporate
Sustainability Cell (CSC).The CSC will conduct Corporate Review
twice a year. The review will comprise of two components- Office
based system review and site inspections where (applicable). The
corporate review shall be presented to the Risk committee.
3. External Audits will be conducted by a third party agency such as
audit firms.
4. Select projects under the purview of the IEISL ESPF will be subjected
to both Corporate Review and External Audits. External audits will
also be conducted at subsidiaries where ESPF is under
implementation. Depending on the risk rating of P/T/A, Corporate
Review will be conducted as per the scheme given in the following
metrics:
HIGH MODERATE LOW
PROJECTS
Form I should be sent to CSC
for review. 100% Corporate
Review with Site Visits at least
once a year
Corporate Review of 100%
cases twice a year
Corporate Review of
25% cases selected at
random twice a year
TRANSACT
IONS
Corporate Review of 100% cases
once a year
- 50% cases at every Corporate
Review
Corporate Review of 25%
cases selected at random
twice a year
Corporate Review of
25% cases selected at
random twice a year
Page 39 of 111
ADVISORY Corporate Review of 25% cases
selected at random once a year
Corporate Review of 25%
cases selected at random
once a year
Only reported in
quarterly Master List
updates. Not
monitored by CSC
5. The scope of the corporate review is given in Annexure H. The findings
from the corporate review will be reported in ESPF Form III designed
for the purpose and is attached in Annexure I. The updated Form III
and IIIA (where applicable) will be shared with CSC & the same will be
discussed by the respective Group Company Coordinator
With the CEO of the CEO of the Group Company
6. A Site Review would also be part of the scope of the corporate review
and will be reported in ESPF Form IIIA and is attached in Annexure
M.
7. Site inspection by CSC will be discontinued in case particular project
site gets certified for ISO 14001 and OHSAS 18001 standards with
RRCsincorporated in the EMS & OHSAS documentation. Exception to
this issites where there is an ongoing litigation on E&S aspects, or
ongoing social unrest or a fatal accident has taken place in the
preceding 12 months. Social unrest refers to ‘an agitation against the
project/ project SPV/ IL&FS or any of its subsidiary/ associate
companies by more than 10 people gathering in one place. It could be a
peaceful protest or sloganeering or any other form of protest’.
8. External audits at IEISL will be conducted before the close of each
financial year. The corporate review will be carried out semi-annually.
9. The scope of external audit will be to review IEISL’s ESPF document to
assess whether design of ESPF is well mapped, relevant and beneficial
to the business canvas of the company.
10. The findings of the Corporate Review and External Audit should be
closed within 4 weeks of the finalization of Review Report.
11. The findings of the Corporate Review to be placed forth the Risk
Committee of the Group Company in immediate next meeting of the
Risk Committee. The findings of the External Audit are to be placed
forth the Board of the Group Company
12. A snapshot of all live P/T/A and details of High rated P/T/A will also
be provided to the Risk Committee as per Annexure
13. Intensity of corporate review reduced for High and Moderate risk
rated PTAs and site visit made subject to management approval
Page 40 of 111
VII. DOCUMENT CONTROL
A. Information Management
1. Records based on formats proposed in the ESPF will be created for
internal approvals and communication. As part of its project
development and E&S due diligence; IEISL will collect large amount of
data and information in the form of reports. It is therefore necessary that
IEISL establishes an information management mechanism to keep
proper records in various forms (hard copies and soft copies) and
maintain controlled copies of all process documents.
2. Final version of all forms shall be maintained by the ESPF coordinator.
If these forms are maintained in print (hard copies), the final version
shall be signed by the coordinator with the date. If they are in electronic
format, each file shall be named as: Final Form X short project name
date.abc. Deviations from this standard format of form names shall only
be done in consultation with CSC.
3. All formats and information that IEISL will maintain in ESPF has been
listed in Table 1.
Table 1: List of Formats and Documents to be recorded
Type Sub Type Stage of Collection
A ESPF Format
ESPF Form I – E&S Risk
Assessment
Before
AAM/BSAM/CIAM
approval
ESPF Form II – E&S Monitoring
and Action Plan
Action Plan part to be
completed after
approval for project
Status on
implementation
during Quarterly/
Semi-Annual/ Annual
Monitoring
ESPF Form IIA –Site Visit EHS
Checklist during construction
Monthly during
construction for
project
implementation
ESPF Form III – Corporate
Review
Semi-Annual
Corporate Review
ESPF Form III A –Project Site
Review Report
As part of the Semi-
Annual Corporate
Review
ESPF Form IV –Training
Records
Conduct of training
sessions
ESPF Form V – Master database Regularly updated on
new projects and at
Page 41 of 111
Type Sub Type Stage of Collection
the time of monitoring
The Master database
will include all LIVE
projects, and
transactions and
advisory assignments,
irrespective of
whether ESPF has
been applied to such
projects, and
transactions and
advisory assignments.
It will also include all
projects and
transactions that are
‘on hold’/ ‘under
suspension’
Annual E&S external audit
report
Annual External
Audit
B
Documents
provided by
client/ self
obtainedfrom
Regulatory
Authority for
waste
management
implementation
projects
Environmental Impact
Assessment Report
Before Financial
Close/ during
preparation of DPR
Environmental Clearance
Before
Commencement of
Construction
Post Environmental Clearance
Monitoring Reports
Construction and
Operation
Consent to Establish
Before
commencement of
construction
Consent to Operate
Before
commencement of
operations
Authorization under Municipal
Solid Waste Rules
Authorization for disposal of
hazardous waste
Other permits/ approvals
Before
commencement of
construction and
operation
B. Updates and Document Control
(a) The findings from the corporate reviews will be presented in the
immediate next Risk Committee meeting after each Corporate
Review and the findings of the external audit will be presented to
the board meeting immediately after the external audit. The ESPF
Page 42 of 111
will be updated to reflect the lessons learnt at planned intervals, to
ensure continuing suitability, adequacy and effectiveness.
(b) The updates to the Policy, Principles and Risk Prevention and
Control measures could also be done in the light of external changes
such as the national laws and regulations and lender’s requirements
or a need to update internal principles and procedures.
(c) The responsibility for updates will lie with the Coordinator in the
IEISL E&S Cell. IEISL shall update the ESPF manual which will then
be reviewed by the Corporate Sustainability Cell. The revised
document shall be submitted back to IEISL E&S Coordinators who
will review the revisions and also be responsible for its circulation
within IEISL.
(d) The ESPF coordinator is required to maintain a master list of all live
P/T/A assignments of the company. The coordinator will send an
updated master list to CSC through the CEO in the first fortnight of
every quarter.
(e) The IEISL ESPF document shall be revised atleast after corporate
reviews and external audit based on corrective and preventive
actions planned to close the findings. The revision carried out in the
document shall be summarized on the ‘Revision Page’, stating
reasons for the same.
(f) The latest revisions would be captured as a separate revision page in
the beginning of the document. The older revisions would be placed
at the end of the document.
(g) A document will have a minimum of review for1revision ina year
with any amount of changes..
(h) Revisions made in a particular version are to be recorded in a table
Page 43 of 111
Annexure A: Environmental and Social Risk Rating
Table A) E&S Risk Rating for Project Implementation
Criteria
No. E&S Risk Rating criteria
Yes/
No E&S risk assigned
Remarks (reasoning for assigning
risk rating)
1.
Does the project involve
Collection and/or transportation
services?
The E&S risk ratings
are as follows:
For projects involving collection and
transportation of waste, the Health and
Safety issues for workers will require
attention. Also, environmental issues
related to spillage, odor and vehicular
emissions will need attention.
Hence, more the possibility of waste
contact “Higher” the Risk Rating
The workers will be required to wear
PPE such as gloves, mask etc. while
handling the waste.
Hence, the risk rating assigned will be
moderate.
a) Collection (Specify
community bins or door to
door collection )
a) Moderate
b) Collection and
Transportation
b) Moderate
c) Only Transportation c) Low
d) None of the above
d) Low
For projects restricted to collection and/or transportation services, Question No.s (2), (3), (9), (10) from the below
mentioned questions need not to be answered.
2.
Does the project pose any
environmental pollution, health
and safety risks due to the
following processing activities:
The E&S risk ratings
are as follows:
Assigned by potential to cause
environmental pollution; and health and
safety risk
a) Composting a) Moderate
b) Bio-methanation b) Moderate
c) Construction and
Demolition waste
c) Moderate
d) Waste to energy (power
generation)
d) Moderate (<20MW)
e) High (>20MW)
e) Refuse Derived Fuel
(producing RDF) f) Moderate
f) Rubber and plastic waste g) High
g) E-waste
h) Moderate
(receiving, auditing,
dismantling,
segregation, resale)
i) High (Processing
and precious metal
recovery)
h) MSW Landfilling g) Moderate
i) Dumpsite closure h) High
j) Hazardous waste treatment
and disposal
i) High
k) Incineration j) High
l) Common Effluent
Treatment Plant
k) Moderate
A. The Highest of the above risk rating in Q 1 to Q 2 will be used.
3.
Is the project included in the
Schedule of Environmental
Impact Assessment Notification
2006?
(Please specify status of
Environmental Clearance)
The E&S risk ratings
are as follows:
a) Common Municipal Solid Waste
Management Facility (Cat. B),
b) Common Effluent Treatment Plants
(Category B),
c) Common Hazardous Waste
Treatment Storage, and Disposal
Facilities (Integrated facility with
incineration and landfill or a) Category A a) High
Page 44 of 111
Criteria
No. E&S Risk Rating criteria
Yes/
No E&S risk assigned
Remarks (reasoning for assigning
risk rating)
b) Category B
c) Not Applicable
b) Moderate
c) Low
incineration: Category A; Landfills:
Category B)
d) Thermal Power Plants based on non
hazardous municipal waste (≥20MW:
Category B; <20 and >15 MW:
Category B)
The above require environmental
clearance as per the Schedule in the EIA
Notification. The clearance is granted
with some conditions that have to be
fulfilled by the project proponent. In case
it is found that there have been serious
violations of the clearance granted, the
same could be suspended/revoked by
the MoEF.
Though projects categorized as B would
have to go through the complete EIA
process, the number of conditions
attached would be lesser and hence a
‘Moderate’ risk rating has been assigned.
If a project does not require EIA or does
not fall under EIA Notification then the
project rating would be Low.
4.
Does the location, design and/or
operational management of the
project facility take into account
the specifications provided by
the MSW (M&H) Rules, 2016 and
C & D Waste management rules
2016 in case of C & D Waste
Management Projects
If ‘Yes’, E & S risk
rating for any type of
project site shall be
‘Low’
If ‘No’, E&S risk rating
for any type of project
site shall be ‘High’
The site location being most critical in
case of landfill sites, and MSW/ C & D
rules compliance in case of design and
operations specification of facilities are
important that would determine
subsequent risks to public health have to
be managed for the project facility.
5.
Is the project located in/traverse
through or is in proximity to any
eco-sensitive zone (ESZ) notified
by MoEF?
If ‘Yes’ and within 10
km of ESZ then E&S
risk rating is ‘High’
If ‘No’then E&S risk
rating is ‘Low’
For projects where Eco-Sensitive zones
exist within the project, clearances from
respective authorities are required as per
the particular ESZ notification are
required and hence rated ‘High’.
6.
Does the proposed project
traverse through or within 10 km
buffer of Protected Areas
(National Parks, Wildlife
Sanctuaries, and Biosphere
Reserves)?
If ‘Yes’ and is within or
traverses through
Protected Areas or in
10 km proximity then
E&S risk rating is
‘High’
If ‘No’then E&S risk
rating is ‘Low’
A 10 km buffer from National parks,
marine parks, sanctuaries, reserve
forests, wildlife habitats and other
protected areas under the provisions of
Wild Life (Protection) Act, 1972
including Biosphere Reserves; have been
declared as eco-fragile areas and these
are regulated by the National Board for
Wildlife.
For projects where clearance from
wildlife board has to be taken, higher
due diligence efforts are required and
hence rated ‘High’.
7.
Is the project site located within
or close to CRZ areas?
If ‘No’, then E&S risk
rating is ‘Low’
If Yes, then the E&S
risk ratings are as
follows:
The risk rating is based on the extent of
the sensitivity to the CRZ / IPZ areas as
defined by the Notification of 2011 is as
follows:
a) Land area from HTL to 500mts on the
landward side
b) Land area between HTL to 100 mts or a) CRZ I a) High
Page 45 of 111
Criteria
No. E&S Risk Rating criteria
Yes/
No E&S risk assigned
Remarks (reasoning for assigning
risk rating)
b) CRZ II b) Moderate width of the creek whichever is less on
the landward side along the tidal
influenced water bodies connected to
the sea
c) Land area between HTL and LTL ‐
intertidal zone
d) Water and the bed area between the
LTL to the territorial water limit (12
nm) in case of sea
e) Water and the bed area between LTL
at the bank to the LTL on the opposite
side of the bank, of tidal influenced
water bodies.
c) CRZ III c) Moderate
d) CRZ IV d) High
e) CRZ for Greater Mumbai e) Moderate
f) Island Protection Zone (IPZ)
f) High
8.
Does the project pass through/
located in tribal areas/scheduled
areas2 or affects their livelihoods?
If ‘Yes’, then E&S risk
rating is ‘High’
If ‘No’ then E&S risk
rating is ‘Low’
Projects passing through /located in
tribal areas/scheduled areas or affecting
their livelihood have to obtain their
consent and share project profits for
tribal development. Obtaining their
consent is a long drawn process and
requires employment of social
development specialists and hence
‘High’ risk rating has been assigned.
9.
Does the proposed project or any
associated activity/component
invoke the provisions of LARR3?
If ‘Yes’ and cause
involuntary
displacement of people
or affect livelihood,
then risk rating “High”
If No then risk rating is
“Low”
LARR provisions are invoked where
land is to be acquired by the government
or private party for public purpose. The
provisions are for land acquisition,
consent, compensation, rehabilitation
and resettlement of persons interested.
The provisions include physical as well
as economic displacement and prescribes
a host of actions to be undertaken based
on nature of land acquisition.
These projects have a greater social risk
and may affect the project development
cycle. Determining public purpose,
conducting Social Impact Assessment
and preparing rehabilitation &
resettlement schemes & plans are key
requirements of the Act.
10.
Does the proposed project lie in
close proximity to archaeological
sites?
If ‘Yes’ and within
100m, then E&S risk
rating is ‘High’
If ‘Yes’and between 100
meters and 1km then
E&S risk rating is
‘Moderate’
If ‘No’, then E&S risk
rating is ‘Low’
100m around an archaeological site is
considered a prohibited zone and
permission from the
ArchaeologicalSurvey of India or from
State Archaeology Department/Office
will be required, hence, a ‘High’ risk
rating has been assigned. And if within
proximity of 1 km considered ‘Moderate’
2 Tribal areas and Scheduled areas mean areas having preponderance of tribal population. These are declared as
under the Fifth and Sixth Schedule of the Constitution of India. 3The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Rehabilitation Act
Page 46 of 111
Criteria
No. E&S Risk Rating criteria
Yes/
No E&S risk assigned
Remarks (reasoning for assigning
risk rating)
11.
Is the proposed project located in
an area susceptible to natural
hazards (earthquake-seismic
zones: IV & V, history of floods,
cyclones, other natural hazards)?
If ‘Yes’, then E&S risk
rating is ‘High’
If ‘No’, then E&S risk
rating is ‘Low’
The sensitivities due to natural hazards
have to be factored in the project design
and planning.
12.
What is the major landuse
around 500m radius of project
site?
The E&S risk ratings
are as follows:
Assigned by sensitivity of the receptors
and potential to cause health and safety
risk
In case of C&T of MSW project, the risk
rating would be assigned low to all a-d
sections, only in case of forest or any
other eco- sensitive zones the risk rating
will be hight.
a) Residential/ Commercial a) High
b) Industrial b) Moderate
c) Institutional (Educational/
Medical) c) High
d) Agricultural
d) High to Moderate
(depending on
topography,
geological
condition, ground
water table and
cultivation)
e) Forest e) High
f) Any other (please specify)
13. Is the project site located in low
lying areas or flood prone areas?
If ‘Yes’, E&S risk rating
assigned is ‘Moderate’
to ‘High’ depending on
the water logging in
rainy season
In case of a site being a low lying area,
any reclamation and filling would alter
the drainage pattern in the area. This
would need to be taken into account
during construction.
14. Is the project site located within
200m of a water body?
If ‘Yes’, E&S risk rating
assigned is ‘High’ to
‘Moderate’ depending
on the use and
sensitivity of the water
body.
In case of the project site being located
close to water bodies, may lead to water
pollution and health impacts. Thus the
risk rating is ‘High’ to ‘Moderate’
depending on its use and sensitivity.
15. Is the project site located in water
scarce/ drought prone regions?
If ‘Yes’, E&S risk rating
assigned is ‘Moderate’
If ‘No’ then E&S risk
rating is ‘Low’
In case project is in areas where;
a) Ground water status Critical and over
exploited
b) Low rainfall areas
c) Non‐perennial rivers/ nallahs as
source of water.
The water withdrawal due to the project
would create further pressure on the
scarce resources.
16.
Is the project site within an
existing dumping site or other
infrastructure facility
(STP/CETP)?
If it is Composting
Facility:
If ‘Yes’ and existing
dumping site, and
The management of activities other than
the project specific ones would
potentially create environmental, health
and safety risks. a) Greater than 300
Ton per Day- “High” b) Less than or equal
to 300 Ton Per Day-
“Moderate”
Page 47 of 111
Criteria
No. E&S Risk Rating criteria
Yes/
No E&S risk assigned
Remarks (reasoning for assigning
risk rating)
If it is C & D
Processing Facility:
If ‘Yes’ and existing
dumping site, and
a) Greater than 500 Ton
per Day- “High”
b) Less than or equal to
500 Ton Per Day-
“Moderate”
If within existing
dumpsite and
STP/CETP, E&S risk
rating assigned is
‘Moderate’
If ‘No’ or “Not
applicable’ then E&S
risk rating is ‘Low’
17.
Is there any electrical
transmission line or electrical
sub-station or gas pipe lines
passing through or adjacent to
project site?
If ‘Yes’, E&S risk rating
assigned is ‘Moderate’
If ‘No’ then E&S risk
rating is ‘Low’
The project activities and fire hazards
would be a safety risk to the installation
and hence need attention.
18.
Does the project involve
segregation of waste within the
scope of activities?
The E&S risk ratings
are as follows: This determines the waste and hazard
exposure to the workers and would lead
to health concerns. Hence, in case
segregation is within the scope and done
manually would mean ‘Higher’ health
risks to the workers.
a) Manual a) Moderate
b) Automated
b) Low
c) Not Applicable c) Low
19.
Are existing rag pickers
integrated within the project
operations?
If ‘No’, E&S risk rating
assigned is ‘Moderate’
If ‘Yes’or “Not
applicable’ then E&S
risk rating is ‘Low’
Private party involvement for waste
management services is a perceived
threat to livelihood of existing rag
pickers. Hence, inclusion of the rag
pickers within the project would ensure
protection of livelihood and mitigate
risks of conflict. Hence, in case rag
pickers are not involved with the project
there are ‘Higher’ reputational risks due
to potential of conflicts.
20.
Does the project site have an
environmental, health & safety
management system established
and required human resources to
implement the system?
If ‘Yes’, E&S risk rating
assigned is ‘Low’.
If ‘No’, E&S risk rating
assigned is ‘Moderate’
Implementation of the projects involves
several impacts on environment and
health and safety of workers and
community. A sound management
system is required to manage these
impacts during construction and
operation of the sites.
Page 48 of 111
Criteria
No. E&S Risk Rating criteria
Yes/
No E&S risk assigned
Remarks (reasoning for assigning
risk rating)
21. Is the project certified under ISO
14001?
If ‘Yes’, E&S risk rating
assigned is ‘Low’.
If ‘No’, E&S risk rating
assigned is ‘Moderate’
Implementation of the projects involves
several impacts on environment and
health and safety of workers and
community. A sound management
system is required to manage these
impacts during construction and
operation of the sites.
22. Any litigation concerning E&S
issues?
If ‘Yes’ then E&S risk
rating is will be ‘High’
or ‘Moderate’ on case
to case basis.
If ‘No’ then E&S risk
rating is ‘Low’
Litigation on E&S aspects should be
checked through web search on the
project or verified from the National
Green Tribunal (NGT) Website4.
Litigations may lead to project delays
and hence, details of the same need to be
sort along with orders if passed by the
Court or the NGT. Depending on the
criticality of the issues and the court
orders passed, the risk rating would be
determined as ‘High’ or ‘Moderate’
B. (i) In case any of the Q3 to Q22 is High, the risk rating arrived at Step A will be elevated to High;
(ii) In case any Five(5)of the Q3 to Q22 will be ‘Moderate’, the risk rating will be elevated to ‘High’
(iii) In case none of the conditions of (i) and (ii) follows then the Highest of the risk rating of Q3 to Q22 shall be
assigned.
(iv) The composting facility less than or equal to300 TPD & C & D Waste Processing Facility less than or equal
to 500 TPD will be kept moderate, despite high rating due to the risk rating arrived from Q3 to Q22 ,until any
eco-sensitive or court issue is not there. If any such things occur, it will be elevated to high.
(v) If the Composting facility & C & D Facility are greater that 300TPD & 500 TPD Capacity respectively then
the risk rating as derived by evaluating Q3 to Q22 will be assigned.
4http://www.greentribunal.in/
Page 49 of 111
Table B) E&S Risk Rating for Advisory Services
Criteria
No. E&S Risk Rating criteria
Yes/
No
E&S risk
assigned
Remarks (reasoning for
assigning risk rating)
1.
Is the project for which
advisory being provided
included in the Schedule of
Environmental Impact
Assessment Notification
2006?
The E&S risk
ratings are as
follows:
If the project is a part of the Schedule
in the EIA Notification, an
Environmental Clearance has to be
obtained. IEISL accordingly needs to
safeguard their clients by informing
them of the compliance requirements
and assistance on the same.
a) Category A a) High
b) Category B b) Moderate
c) None of the above c) Low
2.
What is the type of sector the
project is dealing with?
The E&S risk
ratings are as
follows:
Assigned to the sector as per the
potential to cause environmental
pollution; health and safety risk
a) Municipal Solid Waste
Management a) Moderate
b) Any other waste
management
(Hazardous Waste,
biomedical, e-waste)
b) High
c) E-waste refurbishing c) Moderate
d) E-waste processing d) High
e) Waste to Energy e) High
f) Water Supply and
Waste water f) Moderate
g) Surface Transport and
Transportation Systems g) Moderate
h) Special Economic Zones
& Cluster Development h) Moderate
i) Industries and
Industrial parks i) Moderate
j) Building Construction j) Low
k) Tourism k) Low
l) Ports l) High
m) Power and Hydro
Power m) High
n) Any other (Please
Specify)
n) Assigned as
per EHS issues
3.
What is the type of advisory
service being provided?
The E&S risk
ratings are as
follows: IEISL shall face reputational risk
depending on the criticality of the
advisory project. Hence, risk rating
assigned as per advisory service
provided by potential to cause
reputational risk in case of an issue
with the project
a) Environmental Impact
Assessment a) Moderate
b) Social Impact
Assessment b) Moderate
c) Detailed Project Report c) Moderate
d) Environment
Improvement Plans d) Low
Page 50 of 111
Criteria
No. E&S Risk Rating criteria
Yes/
No
E&S risk
assigned
Remarks (reasoning for
assigning risk rating)
e) Environment
Management Plans/
Master Plans
e) Low
f) Energy Efficiency
Audits
f) Low
g) Clean Development
Mechanism
g) Low
h) Project Management
Consultancy
h) Moderate
i) Establishing
Environmental
Management System
(OHSAS and ISO)
i) Low
j) Research, Training and
Awareness j) Low
4.
Is the project site located
within or close proximity (0-
10km) to E&S Sensitive
areas?
The E&S risk
ratings are as
follows:
Assigned by sensitivity of the
receptors and potential to cause
environmental impacts, as also the
legal compliance requirements.
a) Protected areas a) High
b) Eco-Sensitive Zones b) High
c) Important Bird Areas c) Moderate
d) CRZ areas
d) High for CRZ I
& IV, Moderate
for CRZ II & III
e) ASI Sites e) Moderate
f) Reserved /Protected
Forests
f) High for >40ha
and Moderate
for <40ha
g) Scheduled / Tribal
Areas g) High
h) None of the above h) Low
5.
Does the proposed project or
any associated
activity/component invoke
the provisions of LARR5?
If ‘Yes’ and cause
involuntary
displacement of
people or affect
livelihood, then risk
rating “High”
If No then risk
rating is “Low”
LARR provisions are invoked where
land is to be acquired by the
government or private party for
public purpose. The provisions are
for land acquisition, consent,
compensation, rehabilitation and
resettlement of persons interested.
The provisions include physical as
well as economic displacement and
prescribes a host of actions to be
undertaken based on nature of land
acquisition.
These projects have a greater social
risk and may affect the project
development cycle. Determining
public purpose, conducting Social
Impact Assessment and preparing
5The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act
Page 51 of 111
Criteria
No. E&S Risk Rating criteria
Yes/
No
E&S risk
assigned
Remarks (reasoning for
assigning risk rating)
rehabilitation & resettlement schemes
& plans are key requirements of the
Act.
6.
Is the proposed project
located in an area susceptible
to natural hazards
(earthquake-seismic zones:
IV & V, history of floods,
cyclones, other natural
hazards)?
If ‘Yes’, then E&S
risk rating is ‘High’
to ‘Moderate’ based
on zoning
If ‘No’, then E&S
risk rating is ‘Low’
The sensitivities due to natural
hazards have to be factored in the
project design and planning.
7. Any litigation concerning
E&S issues?
If ‘Yes’ then E&S
risk rating is will be
‘High’ or
‘Moderate’ on case
to case basis.
If ‘No’ then E&S
risk rating is ‘Low’
Litigation on E&S aspects should be
checked through web search on the
project or verified from the National
Green Tribunal (NGT) Website6.
Litigations may lead to project delays
and hence, details of the same need to
be sort along with orders if passed by
the Court or the NGT. Depending on
the criticality of the issues and the
court orders passed, the risk rating
would be determined as ‘High’ or
‘Moderate’
A. The Highest of the above risk rating in Q 1 to Q 7 will be used.
8.
What type of compliance
management is included
within the project scope?
The E&S risk
ratings are as
follows:
IEISL shall face higher risks in case of
legislative requirements to be
obtained and monitored for
compliance.
If project requires land purchases
more than limit stipulated by State
Govt., risk rating will be high. If
project requires land acquisition less
than threshold by State Govt. then it
will be rated low.
a) Environmental
Clearance
a) Moderate
b) Coastal Regulation
Zone Clearance
b) High for CRZ I
& IV, Moderate
for CRZ II & III
c) Wildlife Clearance c) High
d) ESZ Clearance d) High
e) Forest Clearance e) High
f) Facilitation for Land
Acquisition f) High
g) Post EC monitoring g) Moderate
h) Consent to Establish/
Consent to Operate
h) Moderate
i) None of the above i) Low
B. Highest of the risk rating in Question 8 will be taken up along with risk rating at Part A to
arrive at the final risk rating based on the risk rating matrix in Table C below.
C. In case of any court case on that project, the rating will be stepped up to high.
Note:
Once the E&S risk rating has been assigned to a project (implementation or finance) in the
planning stage, it may be revisited during construction or operation phase.
The E&S risk rating may be elevated under any of the following conditions:
a) Consecutive defaults on implementation of E&S risk reduction controls
b) Observations coming to light that have a substantial impact on potential E&S risks
and implications thereof.
6http://www.greentribunal.in/
Page 52 of 111
The E&S risk rating may be lowered under any of the following conditions:
a) A review of the project in the operation phase shows that all legal and administrative
requirements on the E&S front have been fulfilled and regular project activities do
not demand close monitoring.
Table C) E&S Risk Rating Matrix (* Applicable Only for Advisory Projects)
Risk Rating based on answers to criteria in Part A
(Q 1 to 7)
High Moderate Low
Par
t B
(Q 8
)
High High High Moderate
Moderate High Moderate Moderate
Low Moderate Low Low
Special Instructions on Risk Rating:
The risk rating worked out by applying the criteria may be elevated in case some project
sensitivity based on nature, scale, location is identified that is not part of the criteria; citing
reasons for the same. Similarly the risk rating may also be lowered.
Page 53 of 111
Annexure B: E&S Risk Reduction and Controls
I. E&S Risk Reduction Controls for Projects at IEISL based on risks identified
(Advisory or Implementation)
7 NABET – National Accreditation Board for Education and Training
# Project Context/ E&S
Risk E&S Risk Reduction Control
1.
Require Environmental
Clearance, Categorized as
Category ‘A’ or ‘B’ under
EIA Notification, 2006
A. If IEISL is responsible for obtaining Environmental
Clearance for the Client/Project
a) Hire environmental consultants with required
NABET7 accreditation for the relevant sector.
b) Include the cost of implementing the EMP in project
costing.
c) Insert special and general conditions applicable
during construction from the Environmental
Clearance for the project in the Contractors
Agreement for implementation.
d) Incorporate the measures given in the EMP for
planning and design stage in the DPR.
e) The project developer/operator shall implement all
measures recommended in the Environmental
Management Plan attached in Schedule (No.) for the
construction/operation phase
f) Ensure implementation of EMP during project
construction and operation and conduct periodic
monitoring for the same.
g) Refer to the E&S Impacts for municipal waste
management projects and hazardous waste
management projects given in this Annexure B
under Section III A & B.
h) Refer to the IL&FS EMP construction manual
prepared for Construction phase to outline
procedure for implementation of mitigation
measures to be included in Construction Contracts.
B. If IEISL is providing advisory services for a project:
a) IEISL could suggest the use of Green guidelines in
the preparation of DPR such as energy efficiency in
buildings; low energy consuming electrical fixtures;
water efficient fixtures; wastewater treatment
facilities, treated wastewater reuse; waste
management, use of indigenous plantation
b) IEISL should communicate to the developer about
referring to the Zoning atlas prepared by the SPCB
for zoning of industries
c) IEISL should ensure that the Environmental
Page 54 of 111
Clearance conditions for the project applicable to
design are suitably included in the DPR.
2. Project located in CRZ
A. If IEISL is responsible for obtaining CRZ Clearance
for the Client / Project
a) Obtain clearance from MOEF by submitting form
and required information to State Coastal Zone
Management Authority (SCZMA)
b) Implement the recommendations of the MoEF as
applicable during design, construction and
operation of the project.
c) If the project is located in proximity to CRZ I,
incorporate measures during design, implement
measures during construction & operation to
prevent damage to the protected resource.
d) During construction and operation, take measures
to prevent occurrence of prohibited activities in the
CRZ like drawl of ground water, altering sand
dunes/ hills and mining of sand/ rocks.
3.
Project is located within
forest areas and requires
Reserve/ Protected Forest
land
A. If IEISL is responsible for site selection and obtaining
Forest Clearance for the Client / Project
a) For project located in Reserve Forest, identify an
alternative location. Only site specific projects
would receive clearance from the Forest
Department.
b) For projects that have received Stage-I Forest
Clearance, implement all the recommendations to
receive the Stage –II Forest Clearance.
4.
Project Located within or
in 10km proximity to
Protected Areas
A. If IEISL is responsible for site selection and obtaining
Clearance for the Client / Project
a) Obtain approval from National Board for Wildlife if
project is located in proximity to protected areas (10
km from outer boundary termed as eco-sensitive
zone). Follow the conditions put forward by the
Board.
5.
Project Located within or
in 10km proximity to Eco-
sensitive Zones
A. If IEISL is responsible for site selection and obtaining
Clearance for the Client / Project
a) Obtain approval from respective Eco-Sensitive Zone
Authority. Follow the conditions put forward by the
Board.
6.
Project Located within or
in 10km proximity of
Important Bird Areas
A. If IEISL is responsible for site selection and obtaining
Clearance for the Client / Project
a) Verify from local forest department, if there is any
particularly significant areas (bird nesting areas or
bird flight paths) that need to be taken into
consideration while planning the project.
7. Project is located in tribal A. If the project is located in proximity to tribal areas
Page 55 of 111
areas/scheduled area or
affects their livelihoods
and IEISL is responsible for facilitation of land
procurement:
a) It should be verified whether their livelihoods are
affected by obtaining land in the particular location
or conduct of project activity through sample
surveys and focus group discussions.
b) A ‘No Objection Certificate’ should be obtained
from Gram Panchayats or any other documentation
as directed by the Tribal Affairs Department or
under the Forest Rights Act.
c) Where project location/ activities have an impact on
tribal lifestyle or livelihoods, a project-specific
Tribal Development Plan should be prepared.
8. Project requires land
acquisition
A. For projects where the Client is providing land or
IEDCL is investing in equity for a project:
a) Check whether provisions of LARR for land
acquisition, consent, compensation, rehabilitation
and resettlement of persons interested have been
complied with and the land is free of encumbrances.
B. Where IEDCL or its SPV where IEDCL has majority/
management control is responsible for land acquisition:
a) Conduct a Social Impact Assessment and prepare
Rehabilitation &Resettlement Schemes/ Plan for the
project as per LARR Act 2013.
b) If the project is located in a place which has a
history of public objection to infrastructure projects,
conduct a social acceptability study for the project.
c) Ensure that compensation, rehabilitation and
resettlement measures have been satisfactorily
implemented as per the entitlement matrix
approved by the appropriate authority.
C. E&S Risk Reduction controls applicable to both
scenarios, ’A’ & ‘B’
a) Setup a grievance redress cell during construction
with the Contractor and during operation at the
Project Implementation Unit (PIU).
9.
Project is located near
ancient monument or
archaeological site
A. If IEISL is responsible for site selection and obtaining
all Clearances for the Client / Project
a) Obtain permit from Archaeological Survey of India
(ASI) or State Department of Archaeology
b) Follow the guidelines of ASI for activities in
proximity to designated sites.
- Prohibited area - 100 meters area around
Page 56 of 111
surrounding the ASI site wherein no
development, and construction activities
including mining, quarrying, excavation,
blasting are allowed.
- Regulated area - 200 meters
- Buffer Area - 1km beyond core zone boundary
c) In case of a heritage site not designated by ASI,
identify and implement local bye-laws as
applicable.
10.
Project is located in a
hazard prone area
(earthquake, wind,
floods)
Where IEISL is engaged in project development:
a) Elimination of high risk Earthquake, wind &
cyclone and flood prone zones should form part of
site selection criteria.
b) The emergency response plan or disaster
management plan prepared for the project should
include measures to ensure preparedness and
response mechanisms to deal with these natural
hazards.
c) Incorporate design consideration for floods, wind
hazards and earthquakes and in DPR and include
contingency funds for combating such situations.
d) IEISL may evaluate feasibility of constructing wind
barriers on the site.
11.
Litigation filed on the
project on E&S grounds,
show cause notice issued
A. If IEISL is responsible for site selection and obtaining
all Clearances for the Client / Project
a) Identify the subject matter of the litigation and
current status.
b) Follow the directions given by the Court in the
litigation filed.
c) Ensure that the required penalty is paid and
corrective measures are taken to rectify the activity
causing non-compliance to the said regulation.
Achieve the required compliance and report to the
concerned authority to appraise them of the
situation.
12.
Water Stress Index Aqueduct Water Risk tool, WRI: http://bit.ly/1SToFDz
13.
Project involves
Collection and/or
transportation services.
1. IEISL should periodically check the following for
the vehicles:
a) All vehicles have Pollution under Control
Certificates (PUCs)
b) Compliance to Central Motor Vehicles Rules
(CMVR), 1989
c) All drivers have valid driving licenses
d) Renewal of vehicle Fitness Certificates
e) Whether there is any adulteration of fuel
Page 57 of 111
f) Drivers to be covered in ESI scheme
g) Conduct periodic health inspection of all
drivers
h) Incidents related to vehicular accidents
2. IEISL should ensure that no ground water is
extracted for vehicle workshops
3. IEISL should ensure the use of personal protective
equipment by all drivers
4. IEISL should ensure that all vehicles in operation
should be registered and regularly maintained to
mitigate vehicular emissions and cleaned to avoid
odor while leaving the workshop.
5. IEISL Ensure waste oil is treated as Hazardous
waste, obtain authorization from SPCB and dispose
to authorize recyclers/handlers.
14. Project located close to
sensitive land uses
IEISL should ensure no dumping into adjacent
agricultural and residential areas so that ground water
is not impacted.
15.
Project site located in low
lying areas or flood prone
areas.
1. IEISL should ensure no dumping into adjacent low
lying areas.
2. IEISL should provide for storm water drainage
around the site is a must to ensure the highest flood
levels are taken care of. Also, composting pad area
should be an appropriate level and should have a
protective boundary to avoid spillage into drains
during floods(Considering that it is a flood prone
area)
16. Project located within
200m of a water body.
IEISL should take into consideration the proximity of
the water body and accordingly ensure that that the
leachate and waste does not affect the water bodies.
17.
Project located in a water
scare in water scarce/
drought prone region.
IEISL should obtain NOC from State Ground Water
Board in case of water being abstracted from the ground
18. Existence of rag pickers
around project site.
IEISL should endeavor to employ the existing waste
pickers operating in the area within the project activities
to ensure the project does not affect the existing
livelihood of the waste pickers
Page 58 of 111
II. E&S risk reduction controls based on Project Sector and Role of IEISL in the Project
A. IEISL as Project Developer – Waste Management
1. IEISL should ensure the following;
a. Incident reporting related to Environment, Occupational Health and Safety
b. Implementation of the CTE / CTO Conditions
c. Implementation of Environmental Clearance Conditions
d. Implementation of EHS management plan. The contractor/ concessionaire shall
ensure the implementation EHS measures
e. Monitoring Noise, Air, water quality, groundwater & soil parameters;
f. Use of Personal protective equipment (Gum boots, hand gloves) by all workers
g. Conduct periodic health inspection of all workers
h. Prepare a disaster management plan and an onsite and offsite emergency
preparedness & Response Plan for firefighting and natural hazards.
i. Hire a registered contractor and the workers should be registered with the State
Government during construction.
j. Not use banned chemicals and unbonded asbestos during construction and
operation.
k. Ensure health and safety standards for construction labour and staff at all times
as per Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and industry best practice.
l. Harmful or exploitative forms of forced labour or child labour will not be
practiced during construction or operation of the proposed project.
m. Maintain records and file reports for purchase of any ozone depleting substances
for servicing, maintenance of fire extinguishers, transformers, air conditioning.
2. IEISL should obtain and comply with following legal requirements
depending on the project activities;
a. Consent to Establish and Operate from State Pollution Control Board (SPCB)
b. Obtain authorization and compliance as per MSW Rules, 2016/ C & D Waste
Management rules 2016 from SPCB
c. The RDF production facility should comply with conditions of Consent to
Establish, Consent to Operate and Environmental Clearance.
d. The C & D Waste Processing facility should comply with conditions of Consent
to Establish, Consent to Operate, Authorization as per C & D rules 2016 and
Environmental Clearance.
e. Water allocation/approval letter
f. Hazardous Waste handling authorization (waste oil)
g. Approval/license for storage of diesel, lube oil from Chief Controller of
Explosives
h. Approval from SPCB and Chief Inspector of Factories for Chlorine gas and other
chemicals storage and handling (used for maintaining cooling water quality)
i. License from Chief Inspector of Factories
Page 59 of 111
j. Compliance to Central Motor Vehicles Rules, 1989 (Driving License, Vehicle
Registration fitness certificates and PUC)
3. IEISL should ensure the following for waste composting sites;
a. Measures to control manage; treat leachate and runoff from waste storage and
processing areas.
b. Provision of an impermeable base in composting and waste area
c. Provision of storm water drainage around the site is a must to ensure the
highest flood levels are taken care of. Also, composting pad area should be an
appropriate level and should have a protective boundary to avoid spillage into
drains during floods(Considering that it is a flood prone area)
d. Provide for fire-fighting equipment
e. Proper management of waste storage should be undertaken to avoid littering
and clandestine dumping
f. Ensure composting area is demarcated and separated from the main dumping
site area so as to avoid spillage and not affect the composting activities.
g. Measures to mitigate air emissions like dust, bio- aerosols and odors.
h. All vehicles in operation should be registered and regularly maintained to
mitigate vehicular emissions and cleaned to avoid odor while leaving the site.
i. Hazardous sludge storage, handling and disposal take places as per regulations.
j. Measures to reduce odour nuisance to neighboring communities during
dumpsite excavation, composting etc.
B. IEISL providing Advisory Services – Waste Management
a. IEISL should communicate the key legal requirements applicable to the project
during various stages are as follows:
Legal Requirement Project Stage
i. Environmental Clearance Project Development
ii. CRZ Clearance Project Development
iii. Wildlife Clearance Project Development
iv. Land title Project Development
v. MSW Authorization Prior to Operation
vi. Consent to Establish Prior to Construction
vii. Consent to Operate Prior to Operation
viii. Hazardous waste authorization Prior to Operation
ix. License from Chief Inspector of Factories Prior to Operation
b. For projects where IEISL is handling bid process management, incorporate the
following in tender documents:
i. Environmental Management Plan (EMP)
ii. Cost of implementation of EMP, RAP in project cost
Page 60 of 111
iii. Special and general conditions from the Environmental Clearance, Forest
Clearance, Wildlife board Clearance, CRZ Clearance as applicable and
granted to the project
iv. E&S safeguards of international partners of the project, where applicable
III. Checklist of E&S Risk prevention/mitigation measuresto be planed for
Implementation Projects
A. E&S Impacts to be addressed in Municipal Solid WasteProjects
Process Checklist
1. Collection and
Transport
Adequate number of litter bins and refuse collection services to
prevent littering and clandestine dumping
Appropriate measures to mitigate air emissions like dust, bio-
aerosols, odors, and vehicle emissions
2.
Waste Receipt,
Unloading,
Processing, and
Storage
Adequate measures to prevent migration of leachate into soil,
surface water and groundwater
Measures taken to prevent, minimize, and control litter
Adequate measures to mitigate noise and vibration from truck
traffic, loading equipment (e.g., cranes, wheeled loaders),
stationary compactors, balers, grinders, and other treatment and
conveyance systems
3.
Biological
treatment
(Composting)
Adequate measures to control leachate and runoff from waste
storage and processing areas
Take measures to maintain ideal composting conditions i.e.
carbon: nitrogen (C:N) ratio between 25:1 and 35:1, moisture
content of 50 to 60% of total weight, void space to achieve a 10 to
15% oxygen level, temperature levels rangingbetween 32 and 60 oC, pH between 6 and 8.
Measures to mitigate adverse impacts on ambient air quality due
to direct stack emissions, fugitive emissions and emissions from
burning of biogas. The emissions should meet country and
sponsors standards for ambient air emissions
Appropriate measures to prevent combustion of waste during
aerobic degradation or anaerobic digestion.
4. MSW Incineration
Facilities
Emissions from incinerators should meet country and sponsors
standards
Adequate measures to mitigate adverse impacts on ambient air
quality due to emissions from incinerators
Measures taken to prevent, minimize, and control solid waste
from incineration
Ash and other residuals should be disposed in accordance to
country and sponsors specifications
Flue gas from incineration should be treated and disposed in
accordance to country and sponsors specifications
Appropriate measures to mitigate adverse impacts on ambient
noise levels by exhaust fans, cooling system and turbine
generators
5. Land filling The landfill site should be located in accordance to country and
sponsors specifications
Page 61 of 111
Process Checklist
Adequate measures for collection, treatment and disposal of
leachate from landfill
The quantity of leachate generated should be regularly monitored
A landfill gas collection system should be designed and operated
in accordance with applicable national requirements and sponsors
standards
Adequate measures to prevent, minimize, and control dispersal of
litter
Buffer zone should be maintained around the landfill to alleviate
nuisances
6. Health and Safety
Adequate measures to minimize and mitigate health and safety
hazards to workers from toxic gases and hazardous materials on
site
Measures to protect the public and neighborhood from odor,
smoke from fire, diseases transmitted by flies, rodents, insects and
birds etc
B. E&S Impacts to be addressed in Industrial Hazardous Waste Projects
Process Checklist
1. Collection and
Transport
Measures to prevent spills and releases
National and sponsors standards should be followed for
packaging, labeling, and transport of hazardous materials and
wastes
2.
Waste Receipt,
Unloading,
Processing, and
Storage
The incoming waste should be adequately identified and classified
for storage, treatment and disposal
Adequate measures should be taken to prevent spills and releases
during waste storage and handling
Measures should be taken to prevent and control releases of
particulate matter and VOCs from storage vessels and waste
processing equipment
3.
Biological and
Physico-Chemical
Treatment
The facility should be designed and operated in accordance with
applicable national and sponsors requirements
Adequate measures should be taken to control leachate and runoff
from waste storage and processing areas
The ambient air quality to be adversely affected by direct stack
emissions, fugitive emissions and emissions from burning of
biogas should be adequately mitigated. The emissions should
meet country and sponsors standards for ambient air emissions
4. Incineration
Facilities
Measures should be taken to reduce the generation and emission
of polychlorinated dibenzo-dioxins and - furans (PCDDs and
PCDFs
Ash and other residuals should be disposed in accordance to
country and sponsors specifications
The flue gas from incineration should be treated and disposed in
accordance to country and sponsors specifications
5. Land filling
The landfill site should be located, designed and operated in
accordance to country and sponsors specifications
Adequate measures should be taken for collection, treatment and
Page 62 of 111
Process Checklist
disposal of leachate from landfill
The quantity of leachate generated should be regularly monitored
A landfill gas collection system should be designed and operated
in accordance with applicable national requirements and sponsors
standards
6. Health and Safety
Adequate measures to minimize and mitigate health and safety
hazards to workers from toxic gases and hazardous materials on
site
Measures to protect the public and neighborhood from odor,
smoke from fire, diseases transmitted by flies, rodents, insects and
birds etc
Note – ‘Sponsor’ means finance obtained for the project from Multilateral/ Bilateral
Development Banks like World Bank/ Asian Development Bank or finance obtained from
Equator Principle Financing Institutions
C. Reporting Format for Project Site monitoring during Bidding Stage
Task-1:- Preparation of a screening checklist
i. Review all the existing and potential requirements in the environmental, health and
safety (EHS) areas applicable to the project as far as compliance are concerned.
ii. Prepare a screening checklist for the purposes of scoping based on the desk research.
Task-2:– Sensitivity Analysis
i. Conduct sensitivity analysis based on analytical tools to map environmental and social
sensitivity of the said project and in the adjoining areas (to be determined by the type,
scale and location of the project). Should be based on available secondary data and
primary data collected through field visit.
Task-3:– Conduct of site visits
i. Collect information on the environmental settings, locations of the project elements,
present land-use, and environmental components (such as biodiversity, natural
resources, soil, health and safety, etc.) likely to be affected because of the project and
community profile required to prepare EHS Assessment.
Task-4:– Review of legal and other related documentation
i. Identify requirements with State and Central Environmental, Occupational Health &
Safety and Social regulations.
Task-5:– Identify requirements as per IEISL’s ESPF
i. Identify IEISL’s ESPF requirements on screening, risk rating, risk management and
monitoring.
Task-6:– Analysis and Reporting
i. To analyze data/ information accessed during the field studies, interactions and review
for identifying the EHS hazards/ issues.
ii. To determine the risk related to each hazard/ issue.
iii. Incorporate key environmental issues related to the sector
iv. Recommend additional measures, plans and programs required for adequacy and
completeness
v. Identify any further investigations and studies required.
Page 63 of 111
Site Monitoring Report Table of Content
I. Background
General project Information (Site Location and History)
Regulatory Contacts
II. Environmental Setting and Sensitivity Analysis
Environmental Setting
Spatial understanding of surrounding area
Sensitivity of the area for proposed activities
III. EHS Management Plan review
Solid and Hazardous Waste Management
Water (surface and ground) Pollution Control
Air Pollution Control (Including expected/ modeled SOx, NOx, PM and other
pollutants)
Noise Pollution Control (Including expected/ modeled)
Potential Soil and Ground Water Contamination
Occupational health and safety
Occupant / labour welfare & management activities
Emergency Preparedness and Response
IV. Preparedness for compliance with any national/ international/ sector specific guidelines
Comparison of environmental issues with the guidelines
Comparison of the Health and Safety issues with the guidelines
Compliance/ Requirements as per IEISL’s ESPF
V. Findings and conclusions
EHS hazards/ issues identified and the associated risks
Proposed measures / preparedness to control, reduce and monitor these risks
Compliance statements
Suggestions and recommendations
Corrective Action Plan
Appendices
i. Photographs
ii. Documents collated during survey and field visits related to the site/ its occupants and
or nature of liability
iii. Other external origin reports as collected / referred to by the consultant (say external
communiqué from SPCB/SPCC)
IV. E&S Covenants
1. The following clauses should be inserted into the contract for construction, operation and
maintenance additionally among others, as applicable -
a) The Contractor shall not use banned chemicals and unbonded asbestos during the
course of construction
Page 64 of 111
b) The Contractor shall implement all measures recommended in the EMP for the
construction phase
c) The Contractor shall implement the special and general conditions stated in the
Environmental Clearance, Forest Clearance granted for the project
d) The Contractor shall comply with all applicable conditions stated in the Consent to
Establish and Consent to Operate from State Pollution Control Board
e) The Contractor shall provide amenities and follow health and safety standards for
construction labour and staff at all times as per Building and Other Construction
Workers (Regulation of Employment and Conditions of Service) Act, 1996 and
industry best practice
f) The Contractor shall not indulge in harmful or exploitative forms of forced8 labor or
child9 labor
g) The Contractor shall furnish to IEISL immediate notice of information on any major
incident or fatality relating to the project and likely to have a highly adverse effect on
the environment or worker health and safety
h) The Contractor shall furnish immediate notice to IEISL in case any show cause notice
or litigation is filed on the Contractor concerning the project.
i) The Contractor shall provide amenities to the labour hired for the project as per
Contract Labour Act 1970 and amendments thereafter.
j) The Project developer/operator shall follow health and safety practices as per the
State Factories Rules during construction and operation.
k) The contractor shall furnish immediate notice to the Client in case of any major
incident/fatality relating to the Project and likely to have a highly adverse effect on
the environment or worker health and safety.
l) The Project developer/operator shall furnish all documentation submitted to
regulatory agencies/State Pollution Control Boards including Environmental
Statements and periodic monitoring reports to the Project Proponent.
8 Forced labor means all work or services not voluntarily performed, that is, extracted from individuals under threat
of force or penalty. http://www.ilo.org/ilolex/english/convdisp1.htm (scroll down for Convention No. 29)
9 Child labor means the employment of children whose age is below the host country’s statutory minimum age of
employment or employment of children in contravention of International Labor Organization Convention No. 138
“Minimum Age Convention” http://www.ilo.org/ilolex/english/convdisp1.htm (scroll down for Convention No. 138)
Page 65 of 111
Annexure C: Environmental and Social Monitoring and Periodicity
A. E&S Risk Monitoring Periodicity Depending on E&S Risk Rating
I.E&S Risk Monitoring Periodicity for Implementation Projects:
Assigned E&S
Risk Rating
Monitoring Periodicity in the Project Cycle
Planning Construction Operation
H
Once in 6 months or as project
documents/ studies are completed,
whichever is lesser
Once in 3 months Once in 3
months
M
Once in 6 months or as project
documents/ studies are completed,
whichever is lesser
Once in 6 months Once in 6
months
L
Once in 12 months or as project
documents/ studies are completed,
whichever is lesser
Once in 12 months Once in 12
months
II. E&S Risk Monitoring Periodicity for Advisory Projects:
Assigned E&S
Risk Rating
Monitoring Periodicity in the Project Cycle
Development of Project & Tender
Documentation During PMC
H
Once in 6 months or as project documents/
studies are completed, whichever is lesser Once in 3 months
M Once in 6 months or as project documents/
studies are completed, whichever is lesser Once in 6 months
L Once in 12 months or as project documents/
studies are completed, whichever is lesser Once in 12 months
Based on applicability of periodicity, monitoring in Form II will be conducted in the 15 days
preceding the following prescribed due dates::
Every 3 months: May 31, August 31, November 30 and February 28;
Every 6 months: August 31 and February 28;
Every 12 months: February 28
A major incident or fatality occurring at site during construction or operation will also
trigger incident investigation and reporting from the project facility.
Page 66 of 111
The monitoring frequency and scope can be revised on the basis of the findings of the above
reviews during the tenure of the project.
Projects that have an E&S risk rating above ‘L’ may be reviewed on a case to case basis for
requirement of third party E&S audits for checking compliance / conformance with various
E&S requirements as included in the covenants in agreements.
B. Revisiting the E&S risk rating during monitoring
Once the E&S risk rating has been assigned to a project (implementation, advisory or finance)
in the planning stage, it may be revisited during construction or operation phase.
The E&S risk rating may be elevated under any of the following conditions:
a) Consecutive defaults on implementation of E&S risk reduction controls
b) Observations coming to light that have a substantial impact on potential E&S risks
and implications thereof.
The E&S risk rating may be lowered under any of the following conditions:
a) A review of the project in the operation phase shows that all legal and administrative
requirements on the E&S front have been fulfilled and regular project activities do
not demand close monitoring.
Page 67 of 111
Annexure D: ESPF Form I - Environmental and Social Risk Assessment
A checklist can be used for advisory projects, instead of form I. The checklist will
determine whether the Form I is required to be completed for the advisory project.
Form I shall be created for internally awarded assignments (P/T/A) as soon as it is
internally assigned to a person responsible for that assignment.
Form I for High risk rated projects is to be sent to CSC for review for both new projects as
well as any revision in the ongoing High risk rated projects
I. Guidance for Revision of ESPF FormI
The conditions under which ESPF Form I needs revision are:
a) Award of project.
b) Change in project manager, project location, components, allied activities and scope
of work, role, establishment of SPV, change of stake which render the existing risk
rating and risk reduction controls inappropriate.
c) Modification/s for closing corporate review or external audit findings.
d) Revision of E&S risk rating.
e) Amendments in legal requirements and introduction of new regulations
II. Guidance for the revision in Format of ESPF Form I
The conditions under which the format of the ESPF form I shall be revised are:
a) Addition or deletionof E & S Sensitivities b) Addition or deletion in Risk assessment criteria c) Change in rules/government acts etc.
(A) - ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT FORMAT – PROJECT
IMPLEMENTATION
Form No: ESPF/IEISL/P/ (No.)
Revision No.: 00 Date: (DD/MM/YY)
Revision No.: 01 Date:
Revision No.: 02 Date:
Revision No.: 03 Date:
Reason for revision:
A. Project information
Project Title:
Project start date: DD/MM/YY
Date of Bidding:
Date of Award:
Start date of Construction:
Location, State, Country:
Client :
Responsible officer at IEISL:
Period of engagement: (months/years)
Total: _____years
Construction: _____years_____ months
Operation : _____ years_____months
Project Organizational Structure:
Page 68 of 111
Project Proponent:
Concessionaire:
EPC Contractor:
Short project description: (project scale, type, status/stage, scope, components etc.)
Role of IEISL: (Implementation, Construction, Project Management, Finance)
Mention whether IL&FS / IFIN / or any other IL&FS company is investing?
B. Environmental and Social Assessment
1. Land Acquisition
i. Ownership
ii. Type of land
iii. Status of land acquisition
iv. Dependence of livelihood on land acquired
v. Any other related information
2. Does the responsibility for land acquisition lie with an IL&FS entity?
3. Location Features
i. Coordinates:
ii. Village/Town/City, District, State, Country:
iii. Other locational details (Spatial extent, alignment, area, length, proximity to important
features/ locations etc.)
iv. Please attach a map as annexure or a .kml file of the project
4. E&S Sensitivities
S.N. E&S Sensitivities Details
i. 1 Notified Protected Areas (National Parks/ Wildlife
Sanctuaries, Eco-Sensitive Zones, Biosphere
Reserves, Ramsar Sites, Mangrove forests, etc.)
ii. 2 Important Bird Areas
iii. 3 Coastal Regulation Zone
iv. 4 Scheduled Areas
v. 5 State and/or International borders
vi. 6 Hazard Prone Areas (Floods, earthquakes,
wind/cyclones, etc.)
vii. 7 Critically polluted areas
viii. 8 Landuse (e.g. water bodies, reservoirs, natural
drainage, creeks, agriculture, forests, barren lands,
industries, settlements, fishing villages, etc.)
ix. 9 Archeological Survey of India (ASI) site
x. 1
0
Socio-Cultural- Economic activities
(religious/heritage/ cultural sites, tourist interests,
etc.)
xi. Any litigation concerning E&S issues?
xii. Any other sensitivity w.r.t. project activities, sector
and the location
xiii. Identify the tentative number of
Page 69 of 111
villages/towns where displacement may
be caused through spatial analysis.
xiv. Water stress index
(Ref: Aqueduct Water Risk tool, WRI:
http://bit.ly/1SToFDz)
5. Risk Assessment
S.N. E&S Risk Rating Criteria
Yes/
No/
Risk
Rating
(H/ M/ L)
‘Remarks/Details/
Justification to be given
i. 1
a) Does the project involve Collection
and/or transportation services?
a) Collection (Specify community
bins or door to door collection )
b) Collection and Transportation
c) Only Transportation
d) None of the above
ii. 5
Does the project pose any
environmental pollution, health and
safety risks due to the following
processing activities:
a) Composting
b) Bio-methanation
c) Construction and Demolition
waste
d) Waste to energy (power
generation)
e) Refuse Derived Fuel (producing
RDF)
f) Rubber and plastic waste
g) E-waste
h) Landfilling
i) Dumpsite closure
j) Hazardous waste treatment and
disposal
k) Incineration
l) Common Effluent Treatment
Plant
iii.
Is the project included in the Schedule
of Environmental Impact Assessment
Notification 2006?
(Please specify status of
Environmental Clearance)
a) Category A
b) Category B
iv. 1
0
Does the location, design and/or
operational management of the
project facility take into account the
specifications provided by the MSW
Page 70 of 111
(M&H) Rules, 2016? In case of C & D
waste Processing Plant does the
location, design and/or operational
management of the project facility
take into account the specifications
provided by the C & D waste
Management &Handling rules 2016?
v.
Is the project located in/traverse
through or is in proximity to any eco-
sensitive zone (ESZ) notified by
MoEF?
vi.
Does the project is within or in 10 km
proximity to Protected Areas
(national park, wildlife sanctuary and
biospehere reserves)?
vii.
Is the project located within
protected/reserved forests?
a) >40ha
b) <40ha
c) No
viii.
Is the project site located within or
close to CRZ areas?
a) CRZ I
b) CRZ II
c) CRZ III
d) CRZ IV
e) CRZ for Greater Mumbai
f) Island Protection Zone
ix.
Does the project pass through/ located
in tribal areas/scheduled areas or
affects their livelihoods?
x. 1
1
Does the proposed project or any
associated activity/component invoke
the provisions of LARR10?
xi. Does the proposed project lie in close
proximity to archaeological sites?
xii.
Is the proposed project located in an
area susceptible to natural hazards
(earthquake-seismic zones: IV & V,
history of floods, cyclones, other
natural hazards)?
xiii.
What is the major landuse around
1km radius of project site?
g) Residential/ Commercial
h) Industrial
i) Institutional (Educational/
Medical)
j) Agricultural
10The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Rehabilitation Act
Page 71 of 111
k) Forest
l) Any other (please specify)
xiv. Is the project site located in low lying
areas or flood prone areas?
xv. Is the project site located within 200m
of a water body?
xvi.
Is the project site located in a water
scare in water scarce/ drought prone
regions?
xvii.
Is the project site within an existing
dumping site or other infrastructure
facility (STP/CETP)?
xviii.
Is there any electrical transmission
line or electrical sub-station or gas
pipe lines passing through or adjacent
to project site?
xix.
Does the project involve segregation
of waste within the scope of activities?
a) Manual
b) Automated
xx. Are existing rag pickers integrated
within the project operations?
xxi.
Does the project site have an
environmental, health & safety
management system established and
required human resources to
implement the system?
xxii. Is it ISO 14001 certified?
xxiii. Any litigation concerning E&S issues?
The E&S Risk
Rating
by Project Manager
by IEISL E&S Cell
6. Risk Reduction Controls (RRC)
S.N. RRC Remarks
5a.
Covenants based on
RRC (wherever
applicable)
7. Monitoring Periodicity
i. a At Planning Stage
ii. b At Construction Stage
iii. c At Operation Stage
C. Document Management
Prepared by:
Name:
Project Manager
Date:
Assessed By:
Name:
E& S Coordinator
Date:
Page 72 of 111
Instructions: This form shall be attached to PAM/TAM/AAM (depending on the information known
and required) and copies forwarded by the Project Manager to ESPF coordinator and IL&FS Corporate
ESPF Cell. This form will be maintained by ESPF coordinator.
Page 73 of 111
Advisory projects will require the followingchecklistto be filled, which will
determine whether the Advisory Form I is required to be completed.
Any short term (less than 6 months) advisory project such EIA, DPR etc. is not
within the purview of IEISL’s ESPF policy, these types of advisory activities do
not pose any E & S risks.
Environmental Clearance: If IEISL is consulting on environmental clearance
procedures, but not responsibility for getting EC does not lie on IEISL, then Form I
does not have to be filled.
Preparation of EIA: If simply reviewing EIA, then Form I does not have to be
filled. Form I will be applicable only if IEISL is conducting EIA.
Other projects such as collection of primary data from site and representing a
client at National Green Tribunal hearings will not require the filling of Form I.
Criteria
No.
Questions to be
considered Yes/No Reason/Remarks
1.
What is the type of sector
the project is dealing
with?
a) Municipal Solid
Waste Management
b) Other waste
management (bio-
medical, e-waste,
hazardous waste)
c) Waste to energy
d) Water supply &
wastewater
e) Surface transport &
transport systems
f) Special economic
zones & cluster
development
g) Industries &
industrial parks
h) Building construction
i) Tourism
j) Ports
k) Power & Hydro
Power
l) Any other (please
specify)
2.
What is the type of
advisory service being
provided?
Page 74 of 111
a) Environmental
Impact Assessment
b) Social Impact
Assessment
c) Detailed Project
Report
d) Environment
Improvement Plans
e) Environment
Management
Plans/Master Plans
f) Energy Efficiency
Audits
g) Clean Development
Mechanism
h) Project Management
Consultancy
i) Establishing EMS
(ISO & OHSAS)
j) Research, Training &
Awareness
3.
Is the project site located
within or close (0 to 10
km) to E&S sensitive
areas
a) Protected Areas
b) Eco-sensitive Zones
c) Important Bird Areas
d) CRZ Areas
e) ASI Sites
f) Reserved/Protected
Sites
g) Scheduled/Tribal
Areas
h) None of the above
4.
Is the proposed project
located in an area
susceptible to natural
hazards (earthquake –
seismic zones: IV & V,
floods, cyclones, other
natural hazards)
5.
Is the advisory project
included in any of the
categories listed in the
Schedule of EIA
Page 75 of 111
6The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and
Resettlement Act.
Notification, 2006?
a) Category A
b) Category B
6.
Does the proposed
project or any associated
activity/component
invoke the provisions of
the LARR6 act?
7. Is there any litigation
concerning E&S issues?
8.
What type of compliance
management is included
in the project scope?
a) Environmental
Clearance
b) Coastal Regulation
Zone Clearance
c) Wildlife Clearance
d) ESZ Clearance
e) Forest Clearance
f) Facilitation for land
acquisition
g) Post EC monitoring
h) Consent to Establish
i) Consent to Operate
j) None of the above
Page 76 of 111
ESPF Form-I
(B) - ENVIRONMENTAL AND SOCIAL RISK ASSESSMENT FORMAT – ADVISORY SERVICES
Form No: ESPF/IEISL/A/(No.)
Revision No.: 00 Date: (DD/MM/YY)
Revision No.: 01 Date:
Revision No.: 02 Date:
Revision No.: 03 Date:
Reason for revision:
A. Advisory Service information
Advisory Service Title:
Start date: DD/MM/YY
Responsible officer at IEISL:
Client :
Short project description (for which Advisory is being provided):
Current Status of the Project:
Scope (in bullet points) of advisory service : (e.g. to project development, technical and financial
close, project management)
Mention whether any other IL&FS company is involved including financing:
B. Environmental and Social Assessment
1. Land Acquisition
i. Ownership
ii. Type of land
iii. Status of land acquisition
iv. Dependence of livelihood on land acquired
v. Any other related information
2. Does the responsibility for land acquisition lie with an IL&FS entity?
3. Location Features
i. Coordinates:
ii. Village/Town/City, District, State, Country:
iii. Other locational details (Spatial extent, alignment, area, length, proximity to important
features/ locations etc.)
iv. Please attach a map as annexure or a .kml file of the project
4. E&S Sensitivities
S.N. E&S Sensitivities Details
i. 1 Notified Protected Areas (National Parks/ Wildlife
Sanctuaries, Eco-Sensitive Zones, Biosphere
Reserves, Ramsar Sites, Mangrove forests, etc.)
ii. 2 Important Bird Areas
iii. 3 Coastal Regulation Zone
Page 77 of 111
iv. 4 Scheduled Areas
v. 5 State and/or International borders
vi. 6 Hazard Prone Areas (Floods, earthquakes,
wind/cyclones, etc.)
vii. 7 Critically polluted areas
viii. 8 Landuse (eg. water bodies, reservoirs, natural
drainage, creeks, agriculture, forests, barren lands,
industries, settlements, fishing villages, etc.)
ix. 9 Archeological Survey of India (ASI) site
x. 1
0
Socio-Cultural- Economic activities
(religious/heritage/ cultural sites, tourist interests,
etc.)
xi. 1
1
Any other sensitivity w.r.t. project activities, sector
and the location
5. Risk Assessment
S.N. E&S Risk Rating Criteria
Yes/
No/
Risk
Rating
(H/ M/ L)
Remarks
i.
Is the project for which advisory
being provided included in the
Schedule of Environmental Impact
Assessment Notification 2006?
a) Category A
b) Category B
c) None of the above
ii.
What is the type of sector the project
is dealing with?
a) Municipal Solid Waste
Management
b) Any other waste management
(Hazardous Waste, biomedical,
e-waste)
c) Waste to Energy
d) Water Supply and Waste water
e) Surface Transport and
Transportation Systems
f) Special Economic Zones &
Cluster Development
g) Industries and Industrial parks
h) Building Construction
i) Tourism
j) Ports
k) Power and Hydro Power
l) Any other (Please Specify)
iii. 1
What is the type of advisory service
being provided?
a) Environmental Impact
Assessment
b) Social Impact Assessment
c) Detailed Project Report
Page 78 of 111
d) Environment Improvement
Plans
e) Environment Management
Plans/ Master Plans
f) Energy Efficiency Audits
g) Clean Development Mechanism
h) Project Management
Consultancy
i) Establishing Environmental
Management System (OHSAS
and ISO)
j) Research, Training and
Awareness
iv. 3
7
Is the project site located within or
close proximity (0-10km) to E&S
Sensitive areas?
a) Protected areas
b) Eco-Sensitive Zones
c) Important Bird Areas
d) CRZ areas
e) ASI Sites
f) Reserved /Protected Forests
g) Scheduled / Tribal Areas
h) None of the above
v.
Does the proposed project cause
displacement of project affected
people/ families?
vi.
Is the proposed project located in an
area susceptible to natural hazards
(earthquake-seismic zones: IV & V,
history of floods, cyclones, other
natural hazards)?
vii. 8 Any litigation concerning E&S
issues?
viii.
What type of compliance
management is included within the
project scope?
a) Environmental Clearance
b) Coastal Regulation Zone
Clearance
c) Wildlife Clearance
d) ESZ Clearance
e) Forest Clearance
f) Facilitation for Land Acquisition
g) Post EC monitoring
h) Consent to Establish/ Consent to
Operate
i) None of the above
The E&S
Risk Rating
by Project Manager
by IEISL E&S Cell
Page 79 of 111
6. Risk Reduction Controls (RRC)
S.N. RRC Remarks
5 a.
Covenants based on
RRC (wherever
applicable)
7. Monitoring Periodicity
i. Development of
Project and Tender
documentation
ii. During PMC
C. Document Management
Prepared by:
Name:
Project Manager
Date:
Assessed By:
Name:
E& S Coordinator
Date:
Instructions: This form shall be attached to PAM/TAM/AAM (depending on the information known
and required) and copies forwarded by the Project Manager to ESPF coordinator and IL&FS Corporate
ESPF Cell. This form will be maintained by ESPF coordinator.
Page 80 of 111
Annexure E: ESPF Form II - Environmental and Social Action Planning and
Monitoring
ESPF Form II shall be used to carry out monitoring of ongoing projects. The format shall
be filled within an excel sheet and then updated within the same excel sheet as per
required periodicity. The sheet be split into two parts within the same form:
a) Action plan on implementation of RRCs.
b) Monitoring
Form II excel file shall include all RRCs identified in Form I.
(Risk Reduction Controls)RRCs that are closed will continue to exist on the excel file with
comment for ‘closed/ completed’ as applicable with reference to supporting
documentation, if any.
I. Guidance for Elevation or Lowering of E&S Risk Rating during Monitoring
Once the E&S risk rating has been assigned to a project (implementation or finance) in the
planning stage, it may be revisited during construction or operation phase.
The E&S risk rating may be elevated under any of the following conditions:
a) Consecutive defaults on implementation of E&S risk reduction controls
b) Observations coming to light that have a substantial impact on potential E&S risks and
implications thereof.
c) "Risk rating will become 'High' for any P/T/A that becomes sub judicial on E&S aspects"
The E&S risk rating may be lowered under any of the following conditions:
a) A review of the project in the operation phase shows that all legal and administrative
requirements on the E&S front have been fulfilled and regular project activities do not
demand close monitoring.
II. Guidance for Revision of ESPF Form II
The conditions under which ESPF Form II needs revision are:
a) Change in project context leading to revision in risk reduction controls in ESPF Form I.
b) Modification/s for closing corporate review or external audit findings.
c) Amendments in legal requirements and introduction of new regulations.
d) Existing format of Form II shall be used in electronic form only. For every monitoring
cycle, three relevant columns will be added without creating a new file for each form.
Page 81 of 111
Environmental and Social Risks Action Planning and Monitoring
Title: Revision
No.
Scheduled date of
monitoring:
No. ESPF/Company/(P/T/A)/No. Risk Rating Date of Actual
Monitoring
Progress of Project
ACTION PLAN MONITORING
Sr.
No. Risk Reduction Controls
Actions to be taken
for implementation of
RRCs
Primary
Responsibility
Time Line
(Project
Cycle)
Status
RRCs/Actions
Corrective
Actions (if
pending)
Remarks
Monitored by:
(Project Manager)
Reviewed by:
(E&S Coordinator)
This section will be added as additional
columns to the right as per the monitoring
Page 82 of 111
Annexure F: Guidance Procedure for E&S Risk Assessment of a Project in ESPF
Form I
I. Study Project Information
Study the nature, scale and location of the project along with the scope of IEISL’s services
including environmental and social responsibilities. Details on period of project engagement,
organizational structure. The point of entry of IEISL into the project should also be noted.
Further details such as involvement of any group IL&FS group companies and
investment/stake of IEISL in the project and other IL&FS companies.
Fill the above information in the various fields given under Section A: Project Information of
the ESPF Form I.
II. Undertake Environmental and Social Sensitivities Assessment
A. Land Acquisition
Note details on land acquisition aspects to include;
(i) Land ownership,
(ii) Type of land (Such as waste land or fertile land, etc.),
(iii) Status of land acquisition (Complete or partially complete no not initiated, number of
families affected/displacement,
(iv) Dependence of livelihood on land acquired
B. Location Specifics
Note further details on location features of the project such as;
(i) Coordinates,
(ii) Village, district, State, Country
(iii) Locational details ( Spatial extent, area, length, alignment, proximity to features)
(iv) A reference map needs to be attached as an image or as a .kml file.
C. E&S Sensitivities
Conduct a spatial analysis through desk review using freeware tools like Google Earth or
Wikimapia to study the project location and it surrounding area.
Identify and note the following E&S Sensitivities in ESPF Form I;
Project located outside India - For the sensitivities listed below check the aspects on the
website of Ministry of Environment or its equivalent; check for regulations regarding EIA/
CRZ/ tribals/ forests
Projects located in India – check the sources of information given for each aspect
Sensitivities Source of Information
1. Notified Protected Areas
(National Parks/ Wildlife
Sanctuaries, Eco-Sensitive
Zones, Biosphere Reserves,
Ramsar Sites, etc.)
Notified Protected areas can be accessed from the
websites :
http://www.kolkatabirds.com/sanctuaries.htm
http://envfor.nic.in/downloads/public-
information/protected-area-network.pdf
Page 83 of 111
http://envfor.nic.in/division/environment-protection
http://moef.nic.in/division/ramsar-convention-
wetland?theme=moef
http://www.moef.nic.in/sites/default/files/Notificatio
n%20for%20Wetland%20Rules.pdf
2. Important Bird Sites
Important bird sites can be found from the book
entitled “Important Bird Areas in India: Priority sites
for conservation” by BNHS. It can be downloaded
from the link: http://ibcn.in/?page_id=593
3. Coastal Regulation Zone
Coastal Regulation Zone guidelines can be accessed
from http://envfor.nic.in/rules-regulations/crz-
notifications
4. Scheduled Areas or Tribal
Areas
Scheduled areas can be found at
http://tribal.nic.in/Content/StatewiseListofScheduleA
reasProfiles.aspx
Tribal areas can be found at
http://tribal.nic.in/Content/TribalAreasProfiles.aspx
5. State and/or International
borders Check project overlay on State Map
6. Hazard Prone Areas (Floods,
earthquakes, wind/cyclones,
landslides)
Hazard prone areas maps have been prepared and
published as “Vulnerability Atlas of India” by
Building Materials & Technology Promotion Council
and lower scale maps can be accessed from;
Hazard prone areas maps have been prepared and
published as “Vulnerability Atlas of India” by
Building Materials & Technology Promotion Council
and lower scale maps can be accessed from;
(i)Floods:
http://www.bmtpc.org/DataFiles/CMS/file/map%20o
f%20india/flood.pdf
(ii)Earthquakes:
http://www.bmtpc.org/DataFiles/CMS/file/map%20of
%20india/eq-india.pdf
(iii)Wind & cyclones:
http://www.bmtpc.org/DataFiles/CMS/file/map%20of
%20india/wind-india.pdf
(iv)Landslides:
http://www.bmtpc.org/topics.aspx?mid=56&Mid1=18
6
7. Critically polluted areas
CPA sites can be accessed from:
: http://cpcb.nic.in/technical_ess.php or
http://cpcb.nic.in/divisionsofheadoffice/ess/NewItem
_152_Final-Book_2.pdf
8. Landuse Landuse can be studied from Google earth or
Wikimapia
9. Ancient Monuments and (i) World Heritage Sites
Page 84 of 111
Archaeological sites http://asi.nic.in/asi_monu_whs.asp
(ii) List of Protected Monuments
http://asi.nic.in/asi_protected_monu_list.asp (State
Level)
http://asi.nic.in/asi_monu_alphalist.asp (National)
(iii) Excavations http://asi.nic.in/asi_excavations.asp
10. Socio-Cultural- Economic
activities (religious/heritage/
cultural sites, tourist interests,
etc.)
Census and web search
11. Any litigations concerning
E&S issues
National Green Tribunal website
http://www.greentribunal.in/ and google search on
client and project site.
12. Water stress index Aqueduct Water Risk tool, WRI:
http://bit.ly/1SToFDz
13. Any other sensitivity w.r.t
project activities, sector and
the location
Identify as applicable such as proximity to mines etc
14. Identify the tentative number
of villages/towns where
displacement may be caused
through spatial analysis.
Use Geo Database or Google Earth or Wikimapia
15. Bhuvan is software
application which allows users
to explore a 2D/3D
representation of the surface of
the Earth. The browser is
specifically tailored to view
India, offering the highest
resolution in this region and
providing content in four local
languages
http://bhuvan.nrsc.gov.in/gis/thematic/index.php
16. Many of the development
challenges and solutions
require professionals to
visualize data in a spatial
perspective. World Bank
Group is presenting a new
paradigm for easy and
intuitive access to
development data—
highlighting public-domain
online data services from
sources around the world
https://olc.worldbank.org/about-olc/spatial-agent-
world-data-your-fingertips
The items can also be identified using the web-based Geodatabase created for the purpose. The project
Page 85 of 111
has to be created in the system using its latitude and longitude and various attributes linked to the
location is populated in a report format.11
The above links are applicable only to projects located in India. A similar process should be
used for projects located outside India.
III. Assigning an E&S Risk Rating to the project based on the designed criteria
Derive the risk rating for the project using the criteria given in IEISL’s ESPF manual
Annexure A.
The criteria may refer to location in CRZ, EIA Notification or other regulations. Refer to these
regulations while answering the queries and identifying the risk rating.
Use the information identified through the above sources on E&S sensitivities to answer
questions determining the E&S risk rating.
Refer to the combination criteria specified at the end of the list of individual criteria while
deriving the risk rating.
The risk rating worked out by applying the criteria may be elevated in case some project sensitivity
based on nature, scale, location is identified that is not part of the criteria; siting reasons for the same.
Similarly the risk rating may also be lowered.
IV. Identifying risk reduction controls and applying procedures
For each risk identified for a proposed project, identify risk reduction controls given in
Annexure B.
Identify sector specific E&S risks and management measures by referring to additional
sources such as EIA Sectoral Manuals12by MoEF; IFC EHS Sector Guidelines13; Environmental
and Social Risk briefings by UNEP FI14
Where risk reduction controls require implementation by contractors, include those as
covenants in contractual agreements.
Identify the significant impacts that should be avoided/ tracked/mitigated during project
design, construction and operation.
Procedures:
1. Refer the IL&FS EMP Manual for Construction to identify procedures for implementation
of environmental management measures at site. The procedures could be communicated
to Contractors.
2. Use the IL&FS EHSS legal checklist to identify details of regulations applicable to the
project located in India.
V. Identifying Covenants to be inserted in Contractual Agreements
11 The web-based geo-database has been prepared with access currently limited to the IL&FS Corporate E&S cell. 12 EIA sectoral guidance manuals can be accessed at http://environmentclearance.nic.in/ ,
http://environmentclearance.nic.in/writereaddata/Form-
1A/HomeLinks/ommodel2.html&http://environmentclearance.nic.in/writereaddata/Form-1A/HomeLinks/ommodel3.html 13IFC EHS Sector Guidelines can be accessed at
http://www.ifc.org/wps/wcm/connect/Topics_Ext_Content/IFC_External_Corporate_Site/IFC+Sustainability/Sustainability+Framewor
k/Environmental,+Health,+and+Safety+Guidelines/ 14Environmental and Social Risk briefings by UNEP FI can be accessed at http://www.unepfi.org/signatories/toolkit/
Page 86 of 111
Specify the covenants identified that should be inserted in various contractual agreements.
Refer to Annexure B for a general set of covenants.
The covenants should be referred to the company legal department before insertion to contractual
agreements.
VI. Monitoring Periodicity
Specify the monitoring periodicity in the field assigned in ESPF Form I based on E&S risk
rating derived for the project.
I. The monitoring periodicity for Implementation Projects :
a) ‘High’ risk projects during planning phase is 6 months or as project documents are prepared,
construction phase is 3 months, and operation phase is 3 months;
b) ‘Moderate’ risk projects during planning phase is 6 months or as project documents are prepared,
construction and operation phase is 6 months;
c) ‘Low’ risk projects is 12 months or as project documents/ studies are completed, whichever is
lesser
II. The Monitoring Periodicity for Advisory Projects:
a) ‘High’ risk projects during Development of Project and Tender Documentation period is 6 months
or as project documents are prepared & during PMC Phase is 3 months;
b) ‘Moderate’ risk projects during Development of Project and Tender Documentation period is 6
months or as project documents are prepared,& during PMC Phase is 6 months;
c) ‘Low’ risk projects is 12 months or as project documents/ studies are completed, whichever is
lesser
Page 87 of 111
Annexure G: Procedure for Monitoring a project in ESPF Form II
I. Tasks to be carried out immediately after completing project assessment in ESPF Form I
1. List the risk reduction controls specified in ESPF Form I as separate rows in Column 2
of ESPF Form II (in the same excel sheet, using MS excel format for monitoring after
February 2014).
2. Specify the following for each operational control:
a. Mode of Execution: actions to be taken for implementing the risk reduction
controls (e.g. email communication to client; checklist of NABET accredited EIA
consultants, insertion in contractors agreement, terms of reference, etc)
b. name of the person primarily responsible for implementing the risk reduction
control
c. timeline with respect to the project cycle i.e. development/ construction/
operation, where the specified risk reduction control will be applicable
II. Tasks to be carried out during Monitoring of the Project as per the periodicity
1. Obtain a status on the stage of project at the time of monitoring and state the same in
the space provided in the form.
2. Identify risk reduction controls listed in ESPF Form II applicable at that stage and the
previous stages.
3. Identify whether the risk reduction control has been executed based on the stage of
the project.
4. If the risk reduction control has been executed, write ‘Executed’ in the status field.
5. If the risk reduction control has not been executed, inquire about the cause and list it
in the Remarks column.
6. Identify the corrective action/ next steps required for execution of pending risk
reduction control, where applicable. Identify new risk reduction controls for the
same, and add them in the ESPF Form II.
7. During monitoring, check whether any new risks are posed in the project which were
not identified in ESPF Form I. Identify risk reduction controls for the new risks in
ESPF Form II and add them as a separate row in the form. Mention the date of adding
the RRC above it. Prepare an action plan for the RRC (as explained in sub-section I of
this Annexure) and check its status of implementation during the next monitoring
cycle.
8. While monitoring a project for the second or third time and during all subsequent
instances based on the periodicity, check whether the corrective actions and new risk
reduction controls that were recommended during previous monitoring have been
executed.
9. Check whether the E&S risk rating needs to be elevated or lowered.
10. During the course of the project, if any particular RRC becomes ‘not applicable’ due
to change in scope or any other reason, the same should be stated in the ‘Remarks’
column. Such RRCs need not be monitored during subsequent monitoring cycles.
Page 88 of 111
11. In case any risk reduction control has been modified/ revised based on monitoring or
corporate review findings/ observations, the modified RRC should be added as a
separate row in ESPF Form II. The new RRC should be referred to in the remarks of
the old RRC found not applicable. Prepare an action plan for the RRC (as explained in
sub-section I of this Annexure) and check its status of implementation during the
next monitoring cycle.
III. Guidance for Elevation or Lowering of E&S Risk Rating during Monitoring
1. Once the E&S risk rating has been assigned to a project (implementation or finance) in
the planning stage, it may be revisited during construction or operation phase.
2. The E&S risk rating may be elevated under any of the following conditions:
a) Consecutive defaults on implementation of E&S risk reduction controls
b) Observations coming to light that have a substantial impact on potential E&S risks
and implications thereof.
3. The E&S risk rating may be lowered under any of the following conditions:
a) A review of the project in the operation phase shows that all legal and
administrative requirements on the E&S front have been fulfilled and regular
project activities do not demand close monitoring.
4. "Risk rating will become 'High' for any P/T/A that becomes sub judicial on E&S
aspects"
Page 89 of 111
Annexure H: Scope of Corporate Review
High Moderate Low
PROJECTS
Form I should be sent
to CSC for review.
100% Corporate
Review with Site Visits
at least once a year
Corporate Review
of 100% cases
twice a year
Corporate Review
of 25% cases
selected at
random twice a
year
TRANSACTIONS
Corporate Review of
100% cases once a
year - 50% cases at
every Corporate
Review
Corporate Review
of 25% cases
selected at
random twice a
year
Corporate Review
of 25% cases
selected at
random twice a
year
ADVISORY
Corporate Review of
25% cases selected at
random once a year
Corporate Review
of 25% cases
selected at
random once a
year
Only reported in
quarterly Master
List updates. Not
monitored by CSC
I. Office-Based Review
1. The ‘Corporate Review’, will be conducted by the Corporate Sustainability Cell
(CSC). The corporate review report shall be presented to the Risk committee.
2. Review of IEISL ESPF to assess whether design of ESPF is well mapped, relevant and
beneficial to the business canvas of the company
3. Assessment of ESPF coordinators of IEISL on their awareness of E&S issues relevant
to their business. For example, answers to questions on understanding of the
company ESPF document and its application will be reviewed
4. Interview with key project managers to check their awareness and knowledge of
application of ESPF related to their function. For example answers to questions about
business canvas, E&S concerns, mapping between the two and how ESPF system
addresses to safeguard risk will be reviewed
5. Random sampling of ongoing and new projects at IEISL and checking of documents /
records as evidence where ESPF has been applied and E&S risk reduction controls
implemented
6. Review of requirements with respect to previous reviews/audits is fulfilled; namely,
implementation of prescribed corrective / preventive actions which arise as a result of
non-conformances with the ESPF requirements brought to light during the review/
audit.
Page 90 of 111
II. Site-Based Review
1. All projects with a ‘High’ risk rating shall undergo a Site Review.
2. Site visits shall review E&S compliance documentation, safety aspects, emergency
preparedness and status of E&S issues that were faced by projects in the vicinity.
3. Reconnaissance visit of the project and its associated facilities.
4. Review of documents on national environmental and social regulations; and
evidences of implementation of conditions.
5. Review of documents on environmental, health and safety (EHS) systems at site.
6. Interviews on a random sample basis with workers at site, safety stewards, site
supervisors (contractors) to assess their awareness on EHS procedures and practices.
7. Inspection of EHS procedures and practices at site.
8. Site Reviews will not be conducted after the project site is certified for ISO & OHSAS
certificates. However if some litigation with respect to the site occurs the site review
shall be re-continued.
Page 91 of 111
Annexure I: ESPF Form III - Findings of Corporate Review
ESPF Form III: Corporate Review Format
Company Name: Date:
S.
No. Observations/ Findings
Category
Finding or
Observation
Application
of
Observations/
Findings
Root
Cause
Analysis
Corrective
Action
Planned
with time
schedule
Responsibility
Action Taken
Status of
Observation/
Finding
If
Pending,
provide
reason Action Date Status Date
1
2
3
4
5
6
IL&FS Corporate Sustainability Cell Corporate Reviewer: Company E&S Coordinator/s:
Signature: Signature:
Page 92 of 111
Annexure J: ESPF Form IV - Format for Training Record
Company Name:
Venue: Date:
Time Topic (with annotation) Trainer
# List of Participants Signature
S.No. Summary of Feedback Received Action Taken
Page 93 of 111
Annexure K: ESPF Form V - Master Database on Status Implementation of ESPF
1. Risk Assessment and Monitoring
Project ID Project/Transactio
n Title
Name of the
Counterpart/
Client/Partner/Inv
estee
Company scope in the
project (Project/Transation/Advi
sory)
Total Project
Investment Size (in
Mn)
Group Company's Investment
Size (in RsMn) (IEISL
Equity in Project)
Project Manager
Location Bid
Date
Date of E&S Risk Assessme
nt in ESPF
Form I
E&S Risk
Rating
(Current)
Stage of Project
Revision(s) in ESPF Form I
Monitoring
Periodicity
(months)
Award Date
Monitoring Date(s)
Cognizable Safety Events (in nos.) (NA for Advisory)
N/A for Advisory
Other
Remarks ("Live"/
"on- Hold
")
Date Rev No
Revised Risk Rating if any with date
Scheduled
Actual Date
Major
Incidents
Fatalities
Specify Affected
Party (workers/ employees
/public)
Litigation
pertaining
to E & S
issues
Incident of
Social
Unrest
Page 94 of 111
2. Training
Date Location Topics Trainer(s) No. of Participants Business
Vertical
3. Corporate Review
Date Location Reviewer(s) No. of Findings No. of Observations
No. of Findings
/ Observations
Closed before
next Review
No. of Findings
/ Observations
Pending before
next Review System Implementation System Implementation
Page 95 of 111
4. External Audit
Date Location
No. of Observations No. of Findings /
Observations
Closed before
next Review
No. of Findings /
Observations
Pending before
next Review System Implementation
Page 96 of 111
Annexure L: ESPF Form IIA - Monthly Monitoring from Project Site during Construction
ESPF Form IIA - Monthly Reporting from Project Site during Construction
Project Title: Project ID:
Project Site Manager: Date of Monitoring:
# Category # Item Yes
()
No
()
Specific details of when conducted/
reasons why not conducted
1. Regulatory
Requirements 1. Does the project site have all valid clearances/ approvals / permits/ licenses
including those to be obtained by the EPC Contractor?
2. Are the conditions specified in clearances/ approvals / permits being
complied with at site?
3. Have any show cause notices been issued by regulatory authorities for non-
conformance to host country/ local regulations?
2. Environment 4. Are appropriate measures taken to reduce fugitive dust emissions?
5. Is the ambient air quality at site monitored as per host country regulations?
6. Is the noise level at site periodically monitored as per host country
regulations?
7. Have corrective measures been taken to reduce the noise levels at site?
8. Are all wastes generated at site being safely disposed and in conformance
to host country/ local regulations (like construction spoil, excess excavated
material, waste oil, oil soaked cotton etc)?
9. Do the diesel generator sets deployed at site have noise enclosures and
appropriate stack height as per host country regulations?
10. Has the diesel generator sets stack emission been monitored periodically?
Page 97 of 111
# Category # Item Yes
()
No
()
Specific details of when conducted/
reasons why not conducted
11. Are measures being implemented to optimize water consumption during
construction?
3. Occupational
Health and
Safety
12. Is the labour camp provided with amenities like ventilated living spaces;
drinking water; sanitation facilities; fuel for cooking/ common cooking
facility/canteen; waste collection and disposal system; crèche (if female
workers employed); and medical facility?
13. Are all construction equipments and vehicles deployed at site regularly
inspected for proper working condition of all safety devices (like reversing
horn, backlights etc)?
14. Have any major incidents or fatalities occurred at site requiring absence of
work for more than days specified in host country regulations?
15. Has incident investigation been conducted and necessary actions taken to
prevent such incidents?
16. Is a work permit system in operation at site for carrying out hot works,
work at height and work in confined spaces?
17. Are all the construction equipment/ vehicles operators trained for defensive
driving and have appropriate heavy vehicle driving license?
18. Do all construction equipments deployed at site have valid fitness
certificates?
19. Are all workers at site provided personnel protective equipments
appropriate to their job?
20. Are all workers trained in use of safe practices to prevent/reduce incidents
w.r.t. their job work?
Page 98 of 111
# Category # Item Yes
()
No
()
Specific details of when conducted/
reasons why not conducted
4. Emergency
preparedness
and Response
21. Have measures been taken to deploy necessary infrastructure (like fire
extinguishers based on nature of fire, ambulance etc) to handle emergencies
(manmade and natural)?
22. Have the workers and supervisors at site been trained to handle various
emergencies (like fire, natural hazards like cyclone etc) at site?
23. Are mock drills conducted at site to test the functioning of the emergency
response plan?
5. Public Health
and Safety 24. Have any grievances been lodged by the neighboring community due to
ongoing construction activities?
25. Is the traffic on roads adjacent to the site affected due to project
construction managed appropriately to avoid jams, accidents and
inconvenience to other commuters?
6. Institutional
Capacity 26. Is a team on EHS deployed at site adequate in number with defined roles
and responsibilities, competent commensurate to the nature of work?
27. Have health & safety supervisors been deployed at site?
28. Have the workers and supervisors at site been trained to handle various
emergencies (like fire, natural hazards like cyclone etc) at site?
Name:
Signature:
Date:
Page 99 of 111
Annexure M: ESPF Form IIIA - Format for Project Site Review Report
ESPF Form IIIA - Project Site Review Report
IL&FS Company: Project Title:
Project ID: Date of Review: E&S Risk Rating:
Business Vertical: Project Site Manager: Reviewer:
A. Name & Designation of Persons Interviewed:
B. The following list of legal documents were reviewed and found to be in order:
C. The following list of system documents were reviewed and found to be in order:
D. The following EHSS measures implementation were reviewed and found to be in order:
E. Findings/ Observations Corrective and Preventive Action Plan
a) In Legal Documents Corrective & Preventive Actions
Recommended
Responsibility Planned
Timeline
Action Taken Date of
Closing
b) In System Documents Corrective & Preventive Actions
Recommended
Responsibility Planned
Timeline
Action Taken Date of
Closing
c) In Implementation of
EHSS Measures
Corrective & Preventive Actions
Recommended
Responsibility Planned
Timeline
Action Taken Date of
Closing
F. Recommendation on elevation/ lowering/ maintaining E&S Risk Rating:
Page 100 of 111
Annexure O: Former Revision Page
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
Changes as suggested in Corporate review findings dated 19-01-2016
1 Page 11, in
Figure 1, 03 08.03.2016 SPV name ‘DDSIL’ added
2 Page 22, VA(I) 03 08.03.2016 Corporate sustainability cell replaced with E&S Cell
3 Page 22 V B
(c) 03 08.03.2016 Conduct replaced with facilitate or Assist
4 Page 23 V C(l),
and V D (k) 03 08.03.2016
Status of E&S compliance of all ongoing project shall be
submitted on quarterly basis to CSC as and when required
- point is not applicable and to be removed
5 Page 25, Fig 3 03 08.03.2016 Institutional Structure- Internal Review replaced with
Corporate review
6 Page28,
Figure 5 03 08.03.2016
Project Cycle Mapping with ESPF – Sole Sourced (Project
Implementation) to be modified - Step 1 for Form-1
generation should be prior/at the time of BAM
7 Page 33, VI (D 03 08.03.2016 Points (a) to (f) in section deleted
8 Page no. 48,
Annexure A 03 08.03.2016
Environmental and Social Risk Rating; Table C) E&S Risk
matrix for Advisory Project is not inline with criteria
specified in table B and modified as per risk rating criteria
specified
9 Page 58 &59 ,
Para C 03 08.03.2016
Reporting format for Project site monitoring to be
modified as format for Project site monitoring during
bidding stage and Audit Report table of Content to be
Page 101 of 111
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
replaced with Site Monitoring Report Table of Content
10
Page 61,
Annexure C
03 08.03.2016
clause/table for E&S Risk Monitoring Periodicity for
Advisory projects ( i) Development of Project and Tender
Documentation ; (ii) during PMC ) is added/modified
11 Page 75 ( I ),
Page 83 (III) : 03 08.03.2016
Clause added "Risk rating will become 'High' for any P/T/A
that becomes sub judicial on E&S aspects"
12 Page 81
section VI 03 08.03.2016
Monitoring periodicity to be modified for advisory projects
( development and PMC period)
13 Page no. 95,
Annexure N 03 08.03.2016 Not applicable and hence deleted
14
Page 33
Section VI (E)-
2
03 05.05.2016 Text modified to bring clarity on Corporate Review
15 Annexure K :
Page 90 03 05.05.2016
Risk Assessment and Monitoring:
Previous column titled “Investment size” replaced with
two columns: one column on “Total Project/Investment
Size (Rs. Mn)” and another on “Group Company’s
Investment size (Rs. Mn)”
Additional columns added: “Litigation pertaining to
E&S issues”, “Incident of Social Unrest” - Column on
“Remarks” re-worded: “Other Remarks ('Live'/ 'On
Hold')
16
Annexure F:
Page 81
03 05.05.2016 Environmental Sensitivities and Sources of Information for
India: added for Water stress index
17
Annexure D
Form I: page
64
03 05.05.2016
ESPF Form I - Environmental and Social Risk Assessment for
Projects:
Within E&S Sensitivities section, point xiv. added:Water
stress index
Within Risk Assessment section, ‘Remarks’ column re-
labeled to ‘Remarks/ Details/ Justification to be given’
Changes as suggested in Corporate review findings in 2015
Page 102 of 111
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
1
Section V:
Institutional
Arrangement-
C: Role of
IEISL E & S
Cell
03 23-06-2015
Point (q) inserted:-ESPF form-I has to be finalized by ESPF
coordinator.
Point (j)- Nomenclature for documents changed to –
‘Final Form X short project name Date.abc’
Point (k,i,o)-
2
“Figure 6-
Project Cycle
Mapping with
ESPF-
Advisory
Services
03 23-06-2015 MD Approval Inserted
3
Annexure C:
A: E&S Risk
Monitoring
Periodicity
Depending on
E&S Risk
Rating
03 23-06-2015
A column added for periodicity, prescribed due date for
monitoring in Form II
4 Annexure D:
Form I 03 23-06-2015
Few Additional points added for CSC review of High Risk
Projects
5 Annexure E:
Form II 03 23-06-2015 Few Additional points added regarding RRC in Form II
6
Annexure K:
Form V
Master
Database
03 23-06-2015
Risk Assessment and Monitoring column updates:
▫Investment size
▫Revised Risk Rating, if any. With date (under revisions)
Page 103 of 111
Changes dated 31.08.2016
1 Page 33 03 31.08.2016
VI (c)- Operational Mechanism- Points (d), (e), (f), (g)
added about conversion of Project from ESPF to IMS
2 Page 10 03 31.08.2016 Section 1 (B)- Process for Adaptation of ESPF- Introduced
adaptation process from ESPF to IMS
7
Operationaliz
ation of ESPF
at IEISL:
Section D
03 23-06-2015
(iii) Section D: Title changed to Training and Awareness
Generation (iv) Few Points inserted
8
Operationaliz
ation of ESPF
at IEISL:
Section E
03 23-06-2015 Few Points Inserted
9
Document
Control:
Section B
03 23-06-2015 Few Points Inserted
10
Annexure H:
Scope of
Corporate
Review
03 23-06-2015 Inserted scope of review matrix
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
Revisions carried out to incorporate suggestions received during ESPF coordinators’
workshop conducted on 24th June, 2014
1. Overall
document 01 07-07-14 Corporate E&S Cell changed to ‘Corporate Sustainability Cell’
2. Figure 4 & 5 01 07-07-14 Bid submission flowchart modified for implementation and
advisory projects
3. Section V C.
h), i), j), l), o) 01 07-07-14
ESPF coordinator’s responsibilities added to ‘Role of IEISL
E&S Cell’
4. Section V D.
(l) 01 07-07-14 Responsibility of project manager regarding projects on hold
5. Section VI B.
(7) 02 07-07-14 Added points to be included in TAM
6. Section VI D. 01 07-07-14 Specified that CSC will conduct a maximum of 2 full day
training sessions at IEISL
7. Section VI E. 01 07-07-14
Mentioned that CSC will conduct the ‘Corporate Review’ and
EMC will conduct only 1 internal review. The external review
will be conducted by a third party e.g. EY or Deloitte
8. Section VII A. 01 07-07-14
Added point on maintenance of ESPF forms. Final version of
all forms to be maintained and signed by ESPF coordinator.
Each form to be saved as: Final Form X short project name
date.abc
Page 104 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
9. Section VII B. 01 07-07-14 ESPF coordinator to maintain master list & send it to CSC
through CEO in first fortnight of every quarter.
10. Annexure A 03 07-07-14 Addition of few points and modification in risk rating criteria
11. Annexure O 01 07-07-14 Annexure O was removed
12 Section II B
(a) 01 20 – 02 -15
Inclusion of Advisory related Risks (Financial and
Reputational) in accordance with Corporate Review dated 20
– 02 -15
13 Section V(D) 02 20 – 02 -15
Inclusion of Description of ‘On-hold’ and ‘Closed’ projects
and Measures of Communication in accordance with
Corporate Review dated 20 – 02 -15
14 Section VI A
(g) 01 20 – 02 -15
Inclusion of clause regarding filling of Form I for Preparation
of DPRs
15 Section VI B
fig 4 and fig 5 02 20 – 02 -15
Updating Project Cycle Mapping in accordance with
Corporate Review dated 20 – 02 -15, i.e. inclusion of ESPF
Monitoring during Construction Stage and Revision of Form I
during Operation
16
Annexure D:
ESPF Form I
(5)
01 20 – 02 -15 Replacement of ‘ by Project Manager’ and ‘by IEISL E&S Cell’
17
Annexure K:
ESPF Form V
01 20 – 02 -15 Replacement of Master Database into new format as per
IL&FS ESPF Document (Vol II)
18
Annexure D:
Advisory
Projects
Checklist
01 20-02-2015
Inclusion of projects that do not require completion of Form I
depending on IEISL Responsibility and removal of E&S
Column
19
Annexure E:
Environmenta
l and Social
Planning
Form II
03 20-02-2015 Outlining procedure for updating of Form II within the same
excel sheet
20
Annexure G:
Environmenta
l and Social
Planning
Form II
03 20-02-2015 Outlining procedure for updating of Form II within the same
excel sheet
ESPF Document Revision No.: ESPF/IEISL/Rev/2013/01
# Section
Revised
Rev.
No.
Rev.
Date
Brief description of revision and reason for change
1. Section III A 01 13-02-13 Inserted date of approval of E&S Policy by IEISL
Board
2. Section III C
(vi)
01 13-02-13 Changed word ‘habitat’ to ‘condition’ as once project is
implemented restoring natural habitat is practically
not possible and attempt to restore natural condition
is possible
Page 105 of 111
# Section
Revised
Rev.
No.
Rev.
Date
Brief description of revision and reason for change
3. Entire
Document
01 13-02-13 Reworded ‘Risk Prevention and Controls’ to ‘Risk
Reduction Controls’ as the controls specified for
projects are mainly reducing risks rather than
preventing
4. Section IV A
(d)
01 13-02-13 Revised the application of Exclusion List based on
discussion with IL&FS Top Management
5. Section IV B 01 13-02-13 (c) Inserted explanation on ‘Risk in ESPF’ to enhance
clarity
(d) Inserted specific reference to risk rating criteria for
project implementation and advisory services to
enhance clarity
(e) Inserted statement on dynamic nature of risk
rating as per operational experience
6. Section IV C
(b)
01 13-02-13 Inserted method of identifying risk reduction controls
as is being practiced in companies
7. Section V B
& D
01 13-02-13 Inserted ‘Role of Corporate Sustainability Cell and Project
Manager’ to bring clarity on the roles played by these
in implementation of ESPF in response to Internal
Review finding in another group company
8. Section VI
A&B of Rev
00
01 13-02-13 Deleted sections on ‘Dovetailing of ESPF in Business
Processes of IEISL’ and ‘Integration Mechanism’ as these
were found to be repeated in the sub-sections that
followed
9. Figure 4, 5&
6
01 13-02-13 Revised the ESPF Integration in the workflow based
on operational experience
10. Section VI A
(d & e)
01 13-02-13 Inserted justification for excluding GIS and CDM
services from application of ESPF based on Internal
Review observation September 2012 and operational
experience
11. Section VI B
(h)
01 13-02-13 Inserted explanation on monitoring of risk reduction
controls to improve clarity of procedure. Also
inserted trigger for monitoring in case of major
incident or fatality based on Internal Review finding
in another group company
12. Section VI B
(i)
01 13-02-13 Inserted reference to guidance procedures for risk
assessment and monitoring given in the annexures
which was generated as a tool for project managers
13. Section VI C
(g & h)
01 13-02-13 Inserted instructions for preparing action plan and
monitoring of advisory services in ESPF Form II to
complete the procedure
14. Section VI D
(b)
01 13-02-13 Inserted para on applicability of ESPF to projects
awarded to IEISL after board approval based on
external audit comments in March 2012 for another
group company
15. Section VI F 01 13-02-13 Inserted Section on ‘Internal Review and External
Audit’ based on revisions carried out in other group
companies
16. Section VII 01 13-02-13 Inserted Section on ‘Information Management’ to
Page 106 of 111
# Section
Revised
Rev.
No.
Rev.
Date
Brief description of revision and reason for change
A and Table
1
streamline documentation and records
17. Section VII
B (a)
01 13-02-13 Inserted the process of presenting internal review and
external audit findings to top management based on
revisions carried out in other group companies
18. Section VII
B (c & d)
01 13-02-13 Inserted statements defining line of authority and
frequency for updating ESPF documents based on
external audit comments in March 2012 for other
group companies
19. Annexure A 01 13-02-13 Revised the application of Exclusion List based on
discussion with IL&FS Top Management
Note 3 – inserted exception for projects involving
transportation of hazwaste within India based on
discussion during ESPF Corporate Training in
September 2012
20. Annexure B 01 13-02-13 Revised footnote in item 3 on Protected Areas as
‘Refer to websites of respective State Forest
Department for list of wildlife sanctuaries and
national parks’. The urls of the websites that were
given are not in use now
21. Annexure A 01 13-02-13 Revised the E&S risk rating criteria for
implementation projects and advisory services based
on feedback received during training conducted in
January 2013 and operational experience
22. Annexure B 01 13-02-13 Deleted Section I (Rev 00) based on revisions carried
out across other group companies to improve clarity
on implementation of risk reduction controls
Deleted Section II A (Rev 00) as the risk reduction
controls were found to be not applicable to advisory
services
Section II Inserted E&S Covenants based on
operational experience
Section III – Inserted introduction to the list of E&S
studies to improve clarity on application
23. Annexure C 01 13-02-13 Inserted trigger for monitoring in case of major
incident or fatality based on Internal Review finding
in another group company
24. Annexure D 01 13-02-13 Revised the ESPF Form I based on operational
experience
25. Annexure G 01 13-02-13 Inserted fields for Corrective Actions required and
Additional Operational controls in ESPF Form III
required to capture the changes during subsequent
monitoring. Also inserted field on ‘Current Status’ to
enable review at later stages
26. Annexure H 01 13-02-13 Inserted ‘Procedure for Assessment of a Project in ESPF
Form I’ as a guidance to Project Managers
27. Annexure I 01 13-02-13 Inserted ‘Procedure for Monitoring a Project in ESPF
Form II’ as a guidance to Project Managers
Page 107 of 111
# Section
Revised
Rev.
No.
Rev.
Date
Brief description of revision and reason for change
28. Annexure J 01 13-02-13 Inserted format for training records in response to
Internal Review observation in another group
company
29. Annexure L 01 13-02-13 Replaced the format which recorded individual
findings and observations with a tabular format that
records all observations and findings to enable ease of
maintaining records ate the Company
(Signature of IEISL E&S Coordinator)
Name:
Page 108 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
Revisions carried out to incorporate External Audit March 2013 observations, Internal
Review February 2013 findings and overall ESPF system modifications
1. Overall
Document 01 26-07-13
IL&FS Corporate E&S Cell to IL&FS Corporate
Sustainability Cell due to change in title
2. Overall
Document 01 12-07-13
Change in Annexure numbers due to deletion of Annexure
containing Exclusion & Referral list and addition of new
formats.
3. Overall
Document 02 12-07-13
Deletion of Exclusion List form ESPF
All P/T/As taken up by IL&FS and its companies are activities
that are as such within the national legal jurisdiction. The
exclusion list is indicative of the value based choice exercised
by IL&FS, beyond the legally allowed activities. Based on the
application of ESPF in these companies over the last few
years, it has been observed that the items under Exclusion list
have rarely been encountered in the P/T/As assessed. Hence
the Exclusion List has been deleted from the framework.
4. Overall
Document 03 12-07-13
Deletion of Referral List from ESPF
This list had been designed on the assumption that most of
the ESPF application will primarily be carried out at the
company level and only select few involving E&S sensitive
issues / business implications will be escalated to IL&FS
Corporate for advice and direction. However over the past
few years, the referral list is not being operated in practice, as
IL&FS Corporate is conducting the entire assessment. The
practice of referral list will be discontinued till such a capacity
is built in companies of IL&FS. However, the elements of the
list have been considered in the E&S risk rating criteria of the
companies. Hence, the Referral List has been currently
deleted.
5. Section III
D, 3 (a) 02 12-07-13 Deleted reference to Exclusion and Referral List
6. Figure 2 01 12-07-13 Modified to accommodate deletion of the ‘Screening’ step
which included Exclusion and Referral List
7. Section IV
A 01 12-07-13
Deleted ‘Screening’ step which included Exclusion and
Referral List
8. Figure 3 01 26-07-13
Revised the Institutional Structure to include role of SPV and
teams within the Company based on external audit
observations
9. Section V
A (4,5,6,7) 01 26-07-13
Inserted brief description of various entities in the
institutional structure such as SPVs, project managers due to
revision in institutional structure for ESPF implementation
10. Section V B 02 26-07-13
(b) – Deleted ‘Advise IEISL regarding E&S risks and risk
reduction controls for projects where E&S Referral List is triggered’
due to deletion of Referral List
(g) – Inserted function ‘Obtain monthly/periodic review of ESPF
implementation’ based on revision in institutional structure
11. Section V
C
01
12-07-13
Deleted function of IEISL E&S Cell ‘Explain IEISL’s ESPF to
clients whenever required ; Engage E&S specialists as required;
Prepare covenants related to environmental and social safeguards
Page 109 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
00
26-07-13
requirements’ as these are functions to be implemented by the
respective Project Managers
Inserted functions based on revision in institutional functions
and new formats introduced–
(g) Prepare a Master database on the status of
implementation of ESPF captured in ESPF Form V attached as
Annexure L
(h)All activities related to ESPF shall be communicated to
IL&FS Corporate Sustainability Cell
(j)Submit a status on E&S compliance for IEISL ongoing
projects as provided by the Project Managers on a quarterly
basis (refer Annexure O for the format) to IL&FS Corporate
Sustainability Cell
12. Section V
D 02 26-07-13
Inserted additional functions of the Project manager based on
revision on institutional functions for ESPF –
(a) Inform IEISL’s ESPF to clients/partners whenever required
(e) Prepare covenants to reduce environmental and social
risks
(f) Engage E&S specialists as required
(k)Submit an undertaking on E&S compliance for their
projects on a quarterly basis (refer Annexure N for the format)
to IEISL E&S Cell
13. Section VI
B 02 26-07-13
Revision in operational procedure to include specific actions
during bidding, award & design, construction and operation
phase specific for project implementation and advisory
services (scope based specific steps mentioned) based on
Internal review observation and comments received from
Corporate Sustainability Cell
Deleted VI C- Operational procedures for advisory
mentioned in Sec VI B as the ESPF steps are similar.
14. Figure 4, 5
& 6 02 26-07-13
Revised integration of ESPF in business cycle based on
revision in operational procedure and understanding of
business work flows
15. Section VI
E (5-7) 02 12-07-13
Inserted requirement on site reviews as part of internal
review based on Corporate Sustainability Cell direction.
Insert scope of external audit.
16. Section VII
A Table 1 02 26-07-13
Deleted reference to Exclusion and Referral List
Inserted reference to Form IIA, Form IIIA, Form IV, Form V
based on insertion of new formats in the operational
procedure
17. Annexure
A 02 15-07-13
Revision in E&S risk rating criteria to bring more objectivity
based on internal review observations and overall review of
Company ESPF documents across companies
18. Annexure
B 02 15-07-13
Deleted list of E&S studies as they were found to be not
utilized in the last three years
Revision of E&S risk reduction controls –
Item I, II, II - addition and modification of risk reduction
Page 110 of 111
#
Section /
Clause
Revised
Re
v.
no
.
Revision
Date Brief description of revision and reason for change
controls based on operational experience and new risk rating
criteria.
19. Annexure
D 02 12-07-13
Revision in ESPF Form I based on operational experience and
overall review of Company ESPF documents across
companies
20. Annexure
E 02 12-07-13
Revision in ESPF Form II based on operational experience and
overall review of Company ESPF documents across
companies
Insertion of guidance for revision of Form II and revision of
E&S risk rating based on observation by Corporate Cell
during External Audit March 2013
21. Annexure
F 02 12-07-13
Revision in Guidance procedure for filling ESPF Form I owing
to revision in operational procedure
22. Annexure
G 02 12-07-13
Insertion of guidance for revision of E&S risk rating based on
observation by Corporate Cell during External Audit March
2013
23. Annexure
H 00 12-07-13
Insertion in scope of internal review to include site review
and reference to additional forms to be filled.
24. Annexure I 02 12-07-13 Revision of ESPF Form III for internal revoew based on
operational experience
25. Annexure
K 00 28-07-13
Inserted Master database format being used by companies as
a system format based on operational experience and overall
review of Company ESPF documents across companies
26. Annexure
L 00 12-07-13
Inserted ESPF Form II A for reporting from project site during
construction as part of revision of operational procedure
27. Annexure
M 00 12-07-13
Inserted ESPF Form IIIA - Format for Project Site Review
Report to be generated by reviewers during internal review of
ESPF in the Company based on Corporate Cell direction
28. Annexure
N 00 26-07-13
Inserted format for E&S Compliance certificate from Project
Manager to Company E&S Cell based on Corporate Cell
direction
29. Annexure
O 00 26-07-13
Inserted format for E&S Compliance status from Company
E&S Cell to Corporate Sustainability Cell based on latter’s
direction
(Signature of IEISL E&S Coordinator)
Name:
Page 111 of 111
Revisions carried out to incorporate suggestions received during training conducted on 16 th
January, 2014 and Internal Review on 30th January 2014
No.
Section /
Clause
Revised
R
e
v
.
n
o
.
Revision
Date Brief description of revision and reason for change
1 Overall
document
0
1 10-03-14
Reference to Land Acquisition Act 1894 and NRRP (2007)
deleted and replaced with Right to Fair Compensation and
Transparency in Land Acquisition, Rehabilitation and
Resettlement Act, 2013
2 Annexure
A
0
3 10-02-14
Rewording and Revision in E&S risk rating criteria based on
training workshop suggestions and legal changes and
addition of a risk rating matrix table for further clarity.
3 Annexure
B
0
3 10-02-14
Revision in E&S risk reduction control based on legal
changes
4 Annexure
E
0
3 10-03-14
Changes in columns for implementation of Risk reduction
control limited to column on mode of execution based on
internal review suggestion
5 Annexure
F
0
2 10-03-14
Update in Guidance procedure for filling ESPF Form I on
reference links
6 Annexure
G
0
1 10-03-14 Modification of guidance for filling ESPF Form II.
7 Annexure
H
0
1 10-03-14
Insertion in scope of internal review to include site review
and reference to additional forms to be filled.
(Signature of IEISL E&S Coordinator)
Name: