Page 1: ILC Accelerator R&D and AAR&D at NML

f

ILC Accelerator R&D and AAR&D at NML ILC Accelerator R&D and AAR&D at NML

Sergei NagaitsevFRA Visiting Committee Review

April 20/21 2007

Page 2: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 2

f IntroductionIntroduction

What is important? Beam energy; ability to scan the energy; knowing the

beam energy to 0.1 % Peak luminosity: beam-spot at collision, beam current Integrated luminosity: system integration, low rate of

failures, multiple feed-back and feed-forward loops Can we afford it?

Luminosity requires beam power; Superconducting RF is the most effective way to create

high power beams Proven design:

1.3 GHz sheet metal cavities ILC - Each cavity delivers 285 KW to 9mA beam ILC - fill time 38% total pulse ILC - linac efficiency (RF to beam): 50%

• Fill time, distribution and feedback overhead Large irises minimal emittance growth with

achievable tolerances If we can achieve tighter assembly/tuning tolerances, can

improve efficiency

Page 3: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 3

f From TESLA to ILCFrom TESLA to ILC

Capitalize on momentum of the DESY-centered development 1992 to presentCopy, Develop, Extend, Deploy full system

Test• Unprecedented scale ILC >16000 cavities

US labs / universities:Will appropriate and perfect ‘large scale’

preparation technology• (‘RD – scale’ systems to date)

Are suited for this task:• Substantial expertise – distributed –• JLab, Cornell, ANL, MSU, LANL, FNAL, SLAC…

(Cavities, Cryo, RF)

Page 4: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 4

f Setting the ScaleSetting the Scale

For ILC: produce 4 to 6 cryomodules in the next 4 years ~ 50 cavities used; additional needed for development and testing

International (ILC/GDE) coordination: S0 ‘tight loop’ task force:

• Process and re-process the inside surface of a limited number of cavities, repeatedly, testing each time… (~100 procedures/year for several years)

• Answers due 08, 09 guidance for a final gradient recommendation

S1 ‘cryomodule’ task force :• 31.5 MV/m OPERATING cryomodule

S2 ‘string test’ task force :• Put it all together• Run ILC-like beam• Various critical tasks

Page 5: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 5

f SCRF Cavity Gradient RDSCRF Cavity Gradient RD

“S0 / S1” GDE charge: Provide the information needed

to make a gradient decision for TDR. Challenge: Cavity surface processing

variability (yield) Secondary: the rest of the fabrication effort

• From the mine to the cryomodule (‘production-like RD’)

Focused charge, well defined deliverable, broad base, expensive task with excellent cost / benefit

US labs are heavily involved but expertise is scattered; Fermilab is playing a “catch-up” game.

Page 6: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 6

f String test (S2)String test (S2)

Charge: Recommend a string test strategy; follow up responsibility not defined;

Extremely expensive Poorly quantified deliverables Many duplication / competition /

standardization issues between DESY, KEK, FNAL

Cross threaded with mass-production issues, ‘regional interest’ and lab ambitions

R or D? What is the balance? Fermilab role – develop constructive, practical

string test Score success for GDE / ILC community: can we do it?

Page 7: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 7

f S2 is a referendum on the readiness of SRF S2 is a referendum on the readiness of SRF ‘systems’ for ILC‘systems’ for ILC

Also on the interdependencies of ILC / XFEL XFEL system design / projectization effort now

underway

The more CM changes we make, more we need S2 for technical reasons

For example: XFEL will develop and test cryomodule type 3 ILC is designing CM type 4

• Cost reduction may mandate additional design effort – CM5

Is a separate string test needed for the new type? Why?

Are the changes cost effective, including the cost / risk of the system test?

Page 8: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 8

f S2 Executive SummaryS2 Executive Summary

The TTF facility at DESY has provided valuable system tests of many elements of the ILC technology. More tests can and should be performed there. Further testing activities for the XFEL, as well as the complete XFEL, will continue to provide valuable experience.

However several important changes to the TTF design are being planned for the ILC. These include a higher gradient, relocation of the quad to the center of the cryomodule, shortening of the cavity end-group, and a new tuner design. Also under discussion are different modulators, klystrons, and cavity shapes among other developments. These design changes are numerous and major enough that a further system test is warranted.

The basic building block of the ILC linac is one RF unit containing three cryomodules with full RF power controlled as in the final linac. The minimum size system test needed to confirm the performance of a new design is a single RF unit with ILC like beam. As many tests are statistical in nature, a longer string test with several RF units or multiple tests with one RF unit would be better. The primary reason beam is needed is to check that higher order modes (HOMs) are coupled out and absorbed so they do not cause a significant heat load at liquid helium temperature.

Page 9: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 9

f S2 Executive SummaryS2 Executive Summary

All three regions have expressed a desire for command of basic ILC SCRF technology and are preparing to manufacture cryomodules locally. Local test facilities at the scale of 1 RF unit are under construction in Asia and the Americas. Europe is trying to increase its ILC related efforts with a forthcoming proposal to the European Commission (FP7). The proposal will be based on expanding the usage of existing infrastructures.

As construction of the project starts, a test facility (or facilities) will be needed to qualify manufactured RF unit components of the final consolidated ILC linac system design. These components may be built at industries in different regions. One of the possible scenarios is to build a test string with contributions of a total of several RF units from the three regional teams. There are many factors that will influence the choice of the size of the string and whether the goals can be accomplished instead through several smaller tests or one long string. These factors will be coupled to the future industrialization strategy adopted for ILC main linac components. Therefore we cannot at this stage determine the ideal scale of this second phase of system tests.

Page 10: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 10

f Rough S2 ScheduleRough S2 Schedule

PhaseCompletion date Description

0 2005TTF/FLASH, not final cavity design, type 3 cryomodule, not full gradient, has beam

0.5 2008 Extra tests at TTF/FLASH with same type cryomodules as phase 0

1 20081 cryomodule, not final cavity design, type 3 cryomodule (and/or) STF type cryomodule, not full gradient, no beam

1.1 2009

1 RF unit, not all final cavity design, not all type 4 cryomodules, not full gradient, beam not needed for tests, but should be built so it and the LLRF are debugged for the next step

1.2 20101 RF unit (replacing cryomodules of phase 1.1), final cavity design, full gradient, type 4 cryomodules, with beam

1.3 20111 RF unit (replacing cryomodules of phase 1.1), final cavity design, full gradient, type DFM cryomodules, with beam

1.4 2011Tunnel mockup above ground. 1 RF unit perhaps built with parts taken from earlier tests. Includes RTML and e+ transport, no beam

2 2013N RF units at one site (of the final ILC?) as a system test of final designs from multiple manufacturers, no beam

3 2013 XFEL

Page 11: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 11

f Fermilab NML plansFermilab NML plans

The NML is being constructed to address primarily the S2 R&D list However, our plans go beyond S2. We would like to

include elements of S4 R&D tasks (crab-cavities), diagnostics development, personnel training, and accelerator R&D.

The NML facility is staged (1 CM, 2 CMs etc); when complete, it would include 1 (or 2) rf units running ILC-like beam at 5 Hz.

The S2 schedule of having phase 1.3 complete at NML in 2011 is quite challenging Only early stages of NML (up to 2 CMs) are well

planned 3 CMs (1 rf unit) requires building an extension

tunnel and a new cryo-plant The progress is resource limited, thus the schedule

has to stretch to accommodate the scope

Page 12: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 12

f LocationLocation

New Muon Lab

Page 13: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 13

f New Muon Lab buildingNew Muon Lab building

Page 14: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 14

f NML inside (before)NML inside (before)

Page 15: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 15

f NML inside (now)NML inside (now)

Page 16: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 16

f Outline of our plansOutline of our plans

Cryomodule delivery 1st (Type 3+) cryomodule is planned to be delivered

in fall, 2007 2nd (Type 3+) CM – summer 2008 3rd (ILC Type 4) CM – Mid FY09 Replace all three CMs with ILC Type 4+ in FY2010

The NML facility will start as a Cryomodule Test Stand in FY07-08

FY08: add beam; start civil construction of the building extension

Convert to an ILC RF Unit beam test facility in FY11

Page 17: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 17

f NML Schedule (Phase-1)NML Schedule (Phase-1)

Phase - 1 (FY07 thru early FY08) Prepare Facility for Testing of Capture Cavity II (CCII)

and 1st Cryomodule (CM1) without Beam• Building Infrastructure (AC Power, Water, Air,

Mechanical)• Electrical Infrastructure (Racks, Trays, Cables)• Build Cave to Test these Devices (~ 3/4 of Full Cave)• RF Systems (3MW for CM and 300kW for CCII)• Cryogenic System (1st Refrigerator, Feed Can, Feed

Cap, End Cap, Distribution)• Control Room• LLRF, Controls, Safety Systems, Instrumentation (non-

beam) Move CCII from Meson Detector Building (MDB) to

NML• Cool-down and Power Testing

Page 18: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 18

f Phase 1: 1st CM (end of CY07)Phase 1: 1st CM (end of CY07)

Capture cavity 2 in its final location for the injector

Type 3+ cryomodule

A used 3-MW Klystron,

10-MW, 1.5-ms modulatorCC2 RF system

Page 19: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 19

f NML Schedule (Phase-2 & 3)NML Schedule (Phase-2 & 3)

Phase - 2 (FY08) Testing of 1st and 2nd Cryomodule without Beam,

Prepare Facility for Beam• Receive, Install, Power, Cool-down 1st Cryomodule• Install New Gun and Relocate Injector to NML• Extend Cave• Install Beam Lines and Dumps• Install Additional RF Systems needed for CCI and Gun• Receive, Install, Power, Cool-down 2nd Cryomodule• Begin Building Extension needed for Phase-3

Phase - 3 (FY09) Testing of Full RF Unit with Beam

• Complete Building Extension• Begin Testing with Beam• Install 3rd Cryomodule• Upgrade Cryomodule RF system to 10 MW

Page 20: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 20

f Two CMs with beamTwo CMs with beam

The existing building is perfect for testing two cryomodules with ILC-like beam. The building can be extended to fit 3 cryomodules.

Page 21: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 21

f ILC-like beam?ILC-like beam?

3.2 nC/bunch @3 MHz, up to 3000 bunches @ 5Hz

Bunch length: 300-μm rms Transverse emittance: not important (~5 μm) Energy: 30-40 MeV (to avoid overfocusing in

the CM operating at 31 MV/m) Need “known and frozen” beam parameters at

the cryomodule entrance

Page 22: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 22

f

(CC-1)

13m

A0 PhotoinjectorA0 Photoinjector

Page 23: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 23

f

P. Piot

(CC-1, CC-2)

(intended initially for ILC crab cavity tests)

22m

Proposed NML Injector LayoutProposed NML Injector Layout

Page 24: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 24

f Building extensionBuilding extension

Construct a new building ~50m away from NML. Connect by a tunnel when schedule allows. Move loading dock.

ILC-like tunnel, space for 3 more cryomodules Room for a new cryo-plant

2X 276. 0000" 8X 288. 0000"

Loading dock

RF injector (25 m) 1st Cryomodule 2nd Cryomodule 3rd Cryomodule

ILC- like tunnel

New hi-bay building

Page 25: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 25

f A list of some ILC tests at NMLA list of some ILC tests at NML

1. Demonstrate stable long-term high-gradient beam operation at ILC-like bunch parameters.

2. Demonstrate HOM power absorption3. While operating at high gradient and ILC-like beam

currents, demonstrate a LLRF controls system such that the beam energy and beam phase stability meet the ILC specs.

4. Evaluate effects of cavity gradient spreads, dark current, cryogenic load, radiation levels with beam operation.

5. Measure beam kicks due to couplers, cavity tilt, quad rotations + tilt errors characterize focusing properties of SCRF cavities.

6. Measure vibrations of cavities and quads.7. Test beam diagnostics.8. Test ILC crab cavities.9. Test the ILC installation procedure and tunnel layout.10. May evolve into a near-final system integration test.

Page 26: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 26

f A facility to test ILC baseline and A facility to test ILC baseline and alternative designsalternative designs

Many groups in the US and world-wide are looking for a place to test their ILC-related designs. Need beam at 200-800 MeV, need space to set up

tests

Baseline design: “Keep alive” positron source (ANL) SC undulator (Cornell) Crab-cavity (SLAC, Cockcroft Inst)

Alternative designs: New HOM coupler design (MIT)

Page 27: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 27

f AARD plansAARD plans

The existence of the NML facility provides the opportunity to conduct an AARD program Had a workshop in Nov 2006

Fermilab wants to establish an AARD program at NML.

Flexible beam injector needed to support various beam parameters (emittance, bunch charge, bunch length)

Unique beam parameters anticipated: Record high peak current of 14kA possible~30 um beam spot size (FWHM)Beam energy up to 800 MeVStructure: 3000 bunches or a witness bunch

300 um behind

Page 28: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 28

f AARD plansAARD plans

Number of AARD experiments possible in NML itself: one at low energy (50MeV), one-two at full energy (space!)

Building extension needed to provide area for 4-7 more

Low energytest area

Page 29: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 29

f CollaborationsCollaborations

INFN DESY

SLAC

NIUANL Rochester Cockcroft KEK

Page 30: ILC Accelerator R&D and AAR&D at NML

2007 FRA Visiting Committee – S. Nagaitsev 30

f SummarySummary

Fermilab plans to create the NML facility to test the ILC RF unit (3 CMs) with beam at ILC-like parameters by FY10. Planning and engineering designs underway Building extension and new cryo plant are needed to

meet demands of users (ILC, AARD).

Plans to use the NML for accelerator research and training; develop partnerships with NIU and other local universities. Collaborations with SLAC, KEK, DESY and ANL. Building extension required to make it a users facility

with competitive and flexible beam parameters.