IL & FS casting yard Date: 05/04/2016 1. Batching plant Erection for the plants M1 and CP30 completed. Calibration also completed. Producing concrete only for temporary works. Stacking of raw materials under progress 2. Clients office- Outer structure is under progress with roof completed. Sand filling for flooring under progress. 3. Quality lab- Outer structure completed. Interior works are under progress. Equipments for the lab are at site. 4. Gantry track- Gantry track bottom PCC under progress with rebaring simultaneously. One gantry beam is brought to casting yard. 5. Boundary wall for casting yard- Work for the boundary wall is under progress with 500m completed. 6. Store- Outer structure work under progress with roof completed. 7. Contractors office- Outer structure work under progress.

IL &fs

Embed Size (px)

DESCRIPTION

casting yard

Citation preview

Page 1: IL &fs

IL & FS casting yardDate: 05/04/2016

1. Batching plant Erection for the plants M1 and CP30 completed. Calibration also completed. Producing concrete only for temporary works. Stacking of raw materials under progress

2. Clients office-

Outer structure is under progress with roof completed. Sand filling for flooring under progress.

3. Quality lab-

Outer structure completed. Interior works are under progress. Equipments for the lab are at site.

4. Gantry track-

Gantry track bottom PCC under progress with rebaring simultaneously. One gantry beam is brought to casting yard.

5. Boundary wall for casting yard-

Work for the boundary wall is under progress with 500m completed.

6. Store-

Outer structure work under progress with roof completed.

7. Contractors office-

Outer structure work under progress.

8. Casting bed-

GEC has commented on the last drawings but still IL & FS have not complied it and no physical work yet started for casting bed.