IL & FS casting yardDate: 05/04/2016
1. Batching plant Erection for the plants M1 and CP30 completed. Calibration also completed. Producing concrete only for temporary works. Stacking of raw materials under progress
2. Clients office-
Outer structure is under progress with roof completed. Sand filling for flooring under progress.
3. Quality lab-
Outer structure completed. Interior works are under progress. Equipments for the lab are at site.
4. Gantry track-
Gantry track bottom PCC under progress with rebaring simultaneously. One gantry beam is brought to casting yard.
5. Boundary wall for casting yard-
Work for the boundary wall is under progress with 500m completed.
6. Store-
Outer structure work under progress with roof completed.
7. Contractors office-
Outer structure work under progress.
8. Casting bed-
GEC has commented on the last drawings but still IL & FS have not complied it and no physical work yet started for casting bed.