IJAET OCT-DEC,2010 ARTICLE 1.pdf

Embed Size (px)

Citation preview

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    1/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    Research Article

    THERMODYNAMIC ANALYSIS OF GANDHINAGAR

    THERMAL POWER STATIONaProf. Alpesh V. Mehta*,bMr.Manish Maisuria, cMr.Mahashi Patel

    Address for Correspondence

    aAsst.Prefessor, G.H.Patel College Of Engineering And Technology, V.V.Nagarb,c

    Students, G.H.Patel College Of Engineering And Technology,

    [email protected],[email protected]

    ABSTRACT

    Energy and environment both are core for human comfort and peripheral for global survival now-a-days.

    Modern economic pressure demands re-examination of the existing power generating plants for various options

    for their techno-economical and efficient operations. This paper presents a detailed energy study based on the

    first law analysis of the coal fired thermal power station namely Gandhinagar Thermal Power Station (GTPS).In this paper, a detailed energy study is shown for 210MW, Unit-4 of coal fired thermal power plant atGandhinagar Thermal Power Station (GTPS) to evaluate the plant and subsystem{feed water heaters(high

    pressure and low pressure),etc} efficiencies. The boiler efficiency is calculated using indirect method after

    estimating the various heat losses in the boilers. It highlights the positive features of this power plant as well as

    brings out areas where further detailing and corrective measures are required for efficient utilization of the

    sources available in the plant. Energy analysis is used to evaluate the overall thermal efficiency of the plant bycomputing the individual efficiency of the boiler (86.84%), steam turbine (43.5%), and generator (98%). The

    overall efficiency of the plant (Unit-4) appears to be 37.01%.

    KEY WORDS: Power generating plant, boiler, steam turbine, first law analysis.

    1. INTRODUCTION

    Power consumption per capital indicates the

    industrial and economical growth of the

    country and thereby represents the living

    standard of the people of the same. The whole

    world is in grip of electrical energy crisis and

    pollution due to the power plants. The overall

    power scene in India shows heavy shortages in

    almost all the states. The government of India

    has advocated Energy for all by the year

    2012. Even though the Indian power sector is

    at the forth place of the power production in

    the world. The significant role of thermal

    power station in Indias power generation

    scenario can be gauged from the truth that they

    supply about 66% of the total installed

    capacity. Some of the available options are to

    evaluate overall and individual component

    efficiencies and to identify and assess

    thermodynamic losses, thereby improving the

    energy efficiencies of the system. Energy like

    many other commodities should be evaluated

    and the conventional energy analysis, based on

    the first law of thermodynamics, evaluates

    energy mainly on the quality.

    Very careful analysis of the problem and

    proper planning and execution is necessary to

    solve the power crisis in India. So in this

    paper, a detailed energy study is shown for

    210MW, Unit-4 of coal fired thermal power

    plant at Gandhinagar Thermal Power Station

    (GTPS) to evaluate the plant and

    subsystem{feed water heaters(high pressure

    and low pressure),etc} efficiencies. The first

    law analysis is used to assess the overall plant

    performance. In operation and maintenance of

    a power plant, the feed water heaters are

    practically neglected compared with other

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    2/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    components. Efficient and reliable service

    from feed water heaters requires more care in

    both operations and maintenance than care that

    has been taken for nay other components of

    power plant.

    1.1Literature Review

    Power plant is an assembly of a system, where

    electricity is being generated by using

    different mechanical and electrical equipment

    and different processes. The basic components

    of the plants are steam generator {Steam

    generator is a complex integration of boiler

    along-with accessories (furnace, super heater,

    re-heater, boiler, economizer & air pre-heater

    etc.) and various auxiliaries such as pulverizer,

    burners, fans, stokers, dust collector and

    precipitators, ash-handling equipment &

    chimney.}, steam turbine, steam condenser

    and feed water pump.

    1.2The Principle types of Power Plants

    The Principle types of Power Plants are as

    below:

    1. Steam Plants using coal, oil or nuclear

    fission.

    2. Internal combustion engine Plant.

    3. Gas turbine Plant.

    4.

    Hydroelectric Plant.In steam power plant coal or oil is used as a

    fuel for generation of high pressure and high

    temperature steam. In the boilers / the steam

    generators steam is produced and then utilised

    to drive the steam turbines which are coupled

    to generator to get electricity. The furnace may

    employee grate burning of solid fuel,

    pulverised fuel in burner or furnace oil in oil

    burners. The Plant may content server with

    saving devices such as super-heaters,

    economiser, air preheater, reheaters, steam

    traps etc. which effect on overall efficiency of

    coal or oil fired thermal power plants. The

    equipment for firing of fuel into furnace and

    handling of fuel and ash are other important

    aspects of plant study. One should also focus

    on auxiliary equipments and need of

    condensing exhausting steam, water treatment,

    water cooling, dust removal, Draft control, etc.

    In Nuclear stations heat is produce in a reactor

    which replaces the convectional boiler.

    1.3 Classification of steam generator or

    boiler

    Classification of steam generator or boilers

    can be made in different ways. From the point

    of view of application, they can be;

    a) Utility steam generator ,b) Industrial steam

    generator, c)Marine steam generator.

    1.3.1 Utility steam generator

    Utility steam generator is those used by

    utilities for electric-power generating plants.

    Depending on whether the pressure of steam is

    below or above the critical pressure (221.2

    bar), that can be either subcritical or

    supercritical units. The subcritical steam

    generators are water tube drum type and theyusually operate at between 130-180bar steam

    pressure. The supercritical steam generators

    are drum less once-through tube and operate at

    240 bar pressure. Majority of the utility steam

    generators are of the 170-180 bar water tube-

    drum variety, which produce superheated at

    about 540-5800C with one or two stages of

    reheating.

    1.3.2 Industrial steam generators

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    3/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    Industrial steam generators are those used in

    process industries like sugar, paper, and jute

    and so on, and institution like hospital,

    commercial and residential building

    complexes. They are smaller in size. They

    operate pressures ranging 5 to 105 bar with

    steam capacities up to 125 kg/s.

    1.3.3 Marine steam generators

    Marine steam generators are used in many

    marine ships and ocean liners driven by steam

    turbines. They are usually oil-fire. They

    produce superheated steam at about 60-65 bar

    and 5400C.

    1.3About power plant

    The Rankine cycle is the basic cycle for

    operation of steam power plant. Thermal

    power station means a factory for conversion

    of chemical energy of fuel into electrical

    energy. Coal fired units produce electricity by

    the burning coal in a boiler to heat water to

    produce steam. The steam, at tremendous

    pressure, flow into a turbine, which rotates

    armature of generator to produce the

    electricity. The steam is condensate and

    converted back into water, and the returned to

    the boiler to complete the closed cycle.

    The basic requirements of thermal power plantare:

    Raw material should be available

    continuously, generated energy should be

    utilized properly and qualified staff should be

    available as per requirement and proper

    provision of removal of ash and other by-

    products during power generation.

    Basic points to be considered during site

    selection are as follows:

    Type and cost of the land, availability of fuel,

    transportation facility, service water facility,

    availability of staff, near to the load centre, ash

    disposal facility, away from residential area.

    2. About Gandhinagar Power Plant

    Gujarat State Electricity Corporation Limited

    (GSECL) was incorporated in August 1993

    and is registered under the Companies Act,

    1956 with the objectives to initiate a process

    of restructuring of Power Sector and to

    mobilize resources from the market for adding

    to the generating capacity of the State and

    improving the quality and cost of existing

    generation. The Company was promoted by

    erstwhile Gujarat Electricity Board (GEB) as it

    is wholly owned subsidiary in the context of

    liberalization and as a part of efforts towards

    restructuring of the Power Sector. The

    operations of GSECL were limited to Power

    Stations units Gandhinagar Thermal Power

    Station, Wanakbori Thermal Power Station,

    Utran GBPS & Dhuvaran Combined Cycle

    Power Plant (CCPP) till the complete

    unbundling of erstwhile GEB was undertaken

    upto 31st March 2005. The Gandhinagar

    Thermal Power Station is located at

    Gandhinagar, the capital of Gujarat nearAhmedabad. It is a Coal Based Power

    Station. It is on the bank of Sabarmati River.

    There are two units of 120 MW each (Unit no.

    1 & 2), three units of 210 MW each (Unit no.

    3, 4 & 5) with a total installed capacity of 870

    MW. All the above units are of BHEL make.

    Commissioning dates of unit no. 1 to 5 are

    13.03.1977, 10.04.1977, 20.03.1990,

    20.07.1991 and 17.03.1998 respectively.

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    4/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    Based on the data available in table 1, table 2

    and table 3 for Gandhinagar Thermal Power

    Station, we have done a) Energy analysis, b)

    Boiler losses calculations, c) Turbine

    efficiency, and d) Effectiveness of heaters.

    Table 1: Boiler Specifications

    Unit-3 &4 Unit-5

    Actual value

    Particular

    Design

    valueUnit-3 Unit-4

    Design value Actual

    value

    Load(MW) 210 150 180 210 210

    Type Radiant Reheat, Natural

    Circulation,

    Radiant Reheat, Natural

    Circulation,

    Capacity(T/hr) 690 480 520 690 662

    Feed water temp(0C) 247 165 232 245.6 241

    Steam at boiler outlet(Kg/cm2)

    SH 155 135 153 155 147.3

    RH 38.1 26 33 36.11 34.14

    Steam temp at Boiler outlet(0C)

    SH 540 540 540 540 541

    RH 540 530 540 540 542

    Fuel used coal coal

    Efficiency (%) 85.77 82.91 81.79 85.77 81.83

    Table 2: Turbine specification

    Unit-3 &4 Unit-5

    Actual value

    Particular

    Design

    value Unit-3 Unit-4

    Design

    value

    Actual value

    Capacity(MW) 2x 210MW 1x 210MW

    No. of stages of cylinder 690 480 520 690 662

    HP turbine 25 25

    IP turbine 20+20 20+20

    LP turbine 8+8 8+8

    Critical Speed 600 to 300

    Exhaust temp(0C) 45-55 54 52 44-57 40.2

    Efficiency 43.24 37.22 47.71 43.24 41.37

    Table 3: Coal specification

    Particular Unit-3 &4 Unit-5

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    5/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    Actual valueDesign

    value Unit-3 Unit-4

    Design

    value

    Actual value

    Type Bituminous Bituminous

    Caloric value(Kcal/Kg) 3800 3000Ash content (%) 35 42

    Volatile matter (%) 23 23

    Sulphur content (%) 1 0.5

    Quality required (MT/hr) 139.5 94.63 109.5 177 125.77

    Storage capacity (MT) 300000 222003

    3. Result analysis and discussion

    Energy is conserved in every device or process

    i.e. in balance; it can be neither produced nor

    consumed. Energy entering with fuel,

    electricity, flowing streams of matter, and so

    on can be accounted for in the products and by

    products. Energy cannot be destroyed. Energy

    analysis is based on the first law of

    thermodynamics and it is the measured of

    quality only.

    The data for boiler operation and turbine

    operation of unit-4 of GTPS at full load were

    observed and relevant parameters have been

    estimated.

    Using these data and compiled value, First law

    analysis (energy analysis) is carried out for the

    given thermal power plant.

    The performance of a plant is evaluated by

    calculating the overall efficiency of unit by

    using the individual efficiencies of boiler,

    turbine and generator.

    The 210 MW units taken for analysis is to

    consider being having the following system:

    SYSTEM 1 : Boiler system.

    SYSTEM 2 : Steam cycle.

    SYSTEM 3 : Cooling water system.

    SYSTEM 1 (Boiler system) consists of the

    following components and is shown in

    figure1; Combustor, Heat exchangers.

    Figure 1 Folw of fluids on boiler

    SYSTEM 2 (Steam cycle) consists of the

    following components and is shown in

    figure2; Turbine, Condenser(C), Feed Water

    Heater (FWH), Pump (P)

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    6/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    SYSTEM 3 (Cooling Water System) consists

    of the following components; Circulating

    water pumps, Fans.

    The performance of a plant is evaluated bycalculating the individual efficiencies of the

    boiler, turbine and generator. The efficiency of

    the boiler is evaluated by indirect method. In

    the indirect method the input is assumed to be

    100% and the various losses encountered in

    the boiler are calculated and subtracted from

    100. The various losses in the boiler are;

    Energy losses due to the exhaust gases ,

    Energy losses due to unburn carbon ,Energy

    losses due to incomplete combustion Energy

    losses due to moisture in fuel ,Energy losses

    due to hydrogen in fuel , Energy losses due to

    moisture coming with air supplied ,Energylosses due to ash and slag, Energy losses due

    to radiation loss.

    The boiler efficiency is calculated, using the

    indirect method after estimating the various

    heat losses in the boiler. Table 4 represent the

    reading taken for the boiler and coal mill.

    Based on the data available in table 4 , the

    calculations are made for boiler losses and the

    results are shown in table 5.

    Figure 2: Steam cycle

    Figure 3: Energy Balance of Steam Generator

    Table 4: Data for boiler and coal mills

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    7/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    Content Unit Value

    Load MW 210.36

    Coal flow rate T/hr 140.35

    Steam flow rate T/hr 593.37FW inlet temp.

    0C 232

    Mills

    Mill power KW 900

    Total air flow T/hr 690.2

    Relative humidity % 60.42

    Absolute humidity (Kg water/kg dry air) Kg 0.0195

    Dry bulb temp.0C 30

    Wet bulb temp. 0C 27

    FD fan discharge temp0C 37.9

    APH inlet gas temp0C 299

    APH outlet gas temp0C 157.9

    Oxygen in APH inlet % 4

    Oxygen in APH outlet % 4.3

    CO2in APH inlet % 14.8

    CO2in APH outlet % 14.5

    Nitrogen in APH inlet % 14.5

    Combustibles in bottom ash % 6.6

    Combustibles in fly ash % 0.7

    Table 5: Result obtained for boiler and coal mills

    Types of losses KJ/kg %

    Energy losses due to the exhaust gas(Q2) 2501.1 5.29

    Energy losses due to unburn carbon(Q3) 250.98 0.52

    Energy losses due to incomplete combustion. (Q4) 2209.2 4.64

    Energy losses due to moisture in fuel. (Q5) 237.80 0.40

    Energy losses due to hydrogen in fuel. (Q6) 143.0 0.29

    Energy losses due to moisture coming with air supplied. (Q7) 601.48 1.21

    Energy losses due to ash and slag. (Q8) 384.65 0.81

    Total losses 6328.21 13.16

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    8/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    Chart 1 Energy Balance of Steam Generator

    From the chart1, it is clear that losses Energy

    losses due to the exhaust gas are more

    compared to all boiler losses. Which is

    5.2%.the next highest is losses due to

    incomplete combustion, which is 3.4%. The

    lowest losses occur in boiler due to moisture in

    air, which is 0.14%. Due to these energy losses

    boiler efficiency is decrease 13.16%.

    Table no 6 represent the data available for the turbine.

    Content Parameter Unit Reading

    Load L MW 210.36

    Turbine inlet steam flow MS T/hr 593.37

    Super heater steam pressure PSH Kg /cm2

    149.36

    Super heater steam temp. TSH0C 532.92

    Hot Re-heater steam pressure PHRH Kg /cm2 35.09

    Hot Re-heater steam temp THRH0C 534.81

    Cold Re-heater steam pressure PCRH Kg /cm2 34.81

    Cold Re-heater steam temp TCRH0C 335.45

    Feed Water pressure before Economiser PFW Kg /cm2 174.66

    Feed Water temp. before Economiser TFW0C 241.09

    Enthalpy of super heater steam HS KJ/Kg 3549.97

    Enthalpy of Hot Re-heater steam HHRH KJ/Kg 3561.4

    Enthalpy of Cold Re-heater steam HCRH KJ/Kg 3104.1

    Enthalpy of feed water HFW KJ/Kg 1009.4

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    9/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    From the available data for the turbine,

    following calculations are made to calculate

    the turbine efficiency.

    Turbine inlet steam flow = 593.37 T/hr =164.825 kg/s.

    Heat input to turbine

    = {turbine inlet steam flow X (SH enthalpy-

    FW enthalpy)} +{HRH steam flow X (HRH

    enthalpy CRH enthalpy)

    = {164.825 X (3549.97 1009.4)} + {140.1 X

    (3561.4 3104.1)}

    = 482817.18 KJ/Kg

    Turbine efficiency = power generation/ heat

    input to turbine= {210.36 X 103/ 482817.18}

    = 43.5%

    Superheater temperature 532.920C and

    pressure 149.36 Kg/cm2. That means that

    quality of steam is rich. Reheater temperature

    534.810C it is nearly superheater temperature

    532.920C so, we can say that reheater is good

    condition. Feed water temperature is 241.090C

    it is nearby 2500C that is desirable. Due to

    turbine losses, we get turbine efficiency is

    very low which is 43.5%.

    Generator efficiency is taken as 98%

    So the overall efficiency

    = (boiler efficiency X turbine efficiency X

    generator efficiency)= (0.8684 X 0.435 X 0.98)

    = 37.01%

    Due to the turbine efficiency and boiler

    efficiency, we get overall efficiency is

    37.01%. It is very low.

    Overall heat rate = (1 / overall efficiency)

    = 2.701 KJ/S

    The efficiency of the turbine is determined

    estimating the net heat input to turbine and

    electrical power plant from the generator in

    terms of heat values. Thus turbine efficiency

    obtained is 43.5%.

    The generator efficiency is taken as 98%.

    Then the overall efficiency is estimated as

    37.01%.

    The above results are shown in the table no 7

    shown below:

    Table .7 Different efficiencies of power plant Chart 2 Compression of Energy Efficiencies

    Component Efficiency (%)

    Boiler 86.84%

    Turbine 43.5%

    Generator 98.0%

    Overall efficiency 37.01%

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    10/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    Table 8: Represents the observation taken for the high pressure feed water heater (HPH)

    cascaded backward and effectiveness of heaters to be found.

    Contents Unit

    Load MW 210.36FW flow t/hr 593.87

    HPH 5 shell pressure Kg/cm2

    36

    HPH 6 shell pressure Kg/cm2 16

    FW temperature HPH 5 IN0C 163.7

    FW temperature HPH 5 OUT0C 200.7

    FW temperature HPH 6 OUT 0C 244

    Enthalpy of drain water from HPH 5 KJ/Kg 2757

    Enthalpy of drain water from HPH 5 KJ/Kg 2598.62

    Figure 4 Flow diagram of HP Heater

    Effectiveness of heater

    = (FW Temp rise)/ (Tsat tempTFW temp)

    Effectiveness of HPH6 = (243-200.7)/(244.2-

    200.7) =0.97

    Effectiveness of HPH5= (200.7 163.7) /

    (201.1 163.7) =0.98

    Net heat grain to feed water and actual heat

    gained by feed water is respectively 3600

    KJ/Kg and 4131.17 KJ/Kg. That shows that

    system is perfect. Effectiveness of the heater

    HPH6 and HPH5 is 0.97 and 0.98 that is

    nearly 100%. In general, the total losses =

    13.16% , Boiler efficiency = 100 13.26 =

    86.84%, Turbine efficiency = 43.5% ,HP

    heater effectiveness HPH5 and HPH6 are 0.98

    and 0.97.

  • 7/23/2019 IJAET OCT-DEC,2010 ARTICLE 1.pdf

    11/11

    International Journal of Advanced Engineering Technology E-ISSN 0976-3945

    IJAET/Vol.I/ Issue III/Oct.-Dec.,2010/1-12

    CONCLUSION

    From the energy analysis made for the unit-4,

    210MW of the GTPS the following

    conclusion are drawn:. It is seen that boiler efficiency is

    highest, which is 86.84% and the heat

    losses are only 13.16%.

    Out of all the boiler losses, the highest

    heat losses 5.29% occurs due to the

    exhaust gas.

    The turbine efficiency is very less and

    is estimated as 43.5% Because of the

    several turbine losses like ; Losses in

    regulating valve, Nozzle friction

    losses , Blade friction losses , Disc

    friction losses , Partial admission

    losses , Gland leakage losses, Cary

    over losses.

    From the thermodynamic analysis

    using first law of thermodynamics, we

    can conclude that, energy analysis

    evaluates the plant quantitatively. The

    power plant overall efficiency is

    37.01%.

    The effectiveness of HP heater

    working in good condition should

    have an effectiveness of 0.85. The

    performance of HPH6 and HPH5 are

    in good conditions as their

    effectiveness 0.97 and 0.98.

    6. ACKNOWLEDGMENTS

    We are very much thankful to peoples of

    Gandhinagar thermal power plant for

    providing sufficient data for plant. We are also

    thankful to those who help directly or

    indirectly to complete the projectREFERENCES

    1. A.K.Tiwari,Mohd Islam, M.N.Khan ,

    Thermodynamkic Analysis Of Combined

    Cycle Power Plant, International JournalOf Engineering Science And Technology,

    Volume2(4), 2010,480-491.

    2. T.Ganapathy, N.Alagumurthi, R.P.

    Gakkhar, Exergy Analysis Of Operating

    Lignite Fired Thermal Power Plant

    ,Journal Of Engineering Science AndTechnology Review 2(1) 2009,123-130.

    3.

    Szargut, J., 2005, Influence OfRegenerative Feed Water Heaters On The

    Operational Costs Of Steam Power Plants

    And Hp Plants, Int. J. OfThermodynamics, Vol. 8 (3), Pp. 137-141.

    4. R.K.Kapooria, S.Kumar, K.S. Kasana, An

    Analysis Of A Thermal Power Plant

    Working On A Rankine Cycle; A

    Theoretical Investigation, Journal Of

    Energy In Sourthen Africa, Volume 19(1),February 2008, 77-82.

    5. C. Suryanarayan, M. Venkataramanana

    And Dr. N. Algamurthy ,Analysis Energy

    Study Of The Coal Fired Thermal PowerPlant, International Conference On

    Advances In Mechanical Engineering,SVNIT ,2008 ,page no. 78-81.

    6. T. Ganapathy, N. Alagumurthi, R. P.

    Gakkhar and K. Murugesan, Exergy

    Analysis of Operating Lignite Fired

    Thermal Power Plant, International

    Conference On Advances In MechanicalEngineering, SVNIT ,2009 ,page no. 144-

    146.

    7. Nag, P. K., 2001, Power Plant

    Engineering, Tata McGraw Hill, New

    Delhi, 2nd Edition.8. Arora, C.P. (1998), Tata Mc Graw-Hill,

    Thermodynamics New Delhi.

    9. Ballaney, P.L. (1999), Khanna, Thermal

    Engineering Delhi.

    10. El-Wakil, M. M. (1984), New Power Plant

    Technology York: McGraw-Hill

    11. Rajput, R.K. (2001), Laxmi, New Thermal

    Engineering Delhi.