30
IEEE Transformer Committee Atlanta 2016 Arturo Núñez MISTRAS Group, Inc. (dba Physical Acoustics Corporation)

IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

  • Upload
    vanngoc

  • View
    224

  • Download
    1

Embed Size (px)

Citation preview

Page 1: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

IEEE Transformer Committee Atlanta 2016

Arturo Núñez

MISTRAS Group, Inc. (dba Physical Acoustics Corporation)

Page 2: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

A

A

A

A

A

A

A

A

AAE Sensor

Page 3: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

ACOUSTIC EMISSIONS

Page 4: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

HFCT

LTC motor

current

Pump current

Load current

Main tank and LTC

compartment temperature

INSTALLATION

AE SENSORS Other info:

DGA

Winding Temp.

Page 5: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

CASE STUDY 1

Three phase Transformer

Core form

144/13.8 Kv

ONAN/ONAF/OFAF

90/120/160 MVA

Built in 1996

A slight increase in combustible

gases was observed on this unit

since February 2010.

An acoustic emission test was

performed on June 2010 to try

detect and locate the gassing

source.

Page 6: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Dissolved Gas Analysis

DATE H2 CO CO2 CH4 C2H6 C2H4 C2H2 TDCG

02-Feb-10 19 166 2861 211 155 94 0 645

09-Ene-09 13 151 1472 174 129 53 0 520

10-Dic-08 326 82 811 209 135 47 0 799

Data prior to AE test

Page 7: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Dissolved Gas Analysis

A sudden increase in the gas concentration was observed on December 2010 (few months after the acoustic test).

Acoustic Test performed on

June 3-4, 2010

Page 8: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

FAULT LOCATION

Several acoustic emission sensors were placed on the main tank. At the end

of the monitoring period in June 2010, an area of acoustic activity was

detected on the upper part of Phase U (Cluster 1).

Page 9: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Internal inspection

• The unit remained in operation for 6 more months until the unit was inspected in January 2011.

• On the area where the acoustic activity was located, severe damaged was found on the conductor of Phase U, on the upper part of the coil.

• After the internal inspection the oil for this transformer tested positive for Corrosive Sulfur

Page 10: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Internal Inspection

TOP COIL

TAP 3

BOTTOM COIL

Page 11: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Case 3 – Nuclear plant GSU DGA trend 2009-2012

0

50

100

150

200

250

300

350

400

450

500

10/14/09 1/22/10 5/2/10 8/10/10 11/18/10 2/26/11 6/6/11 9/14/11 12/23/11 4/1/12

TDC

G

Date

Page 12: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Location of AE signals and correspondingcorrelation with DGA

AE

Cluster

Page 13: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Location of AE signals and corresponding overheating inside the transformer

Page 14: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Remedial action: Added insulation to flux shields

shield spanner

Page 15: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

•GSU Transformer

2002 – OVERHEATED BUS BAREPRI Substation Equipment Diagnostics Conference Paper, 2004

Page 16: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

CASE STUDY 2CASE 6 ON IEEE STD. C57.127, 2007

DATE H2 CO CO2 CH4 C2H6 C2H4 C2H2 TDCG

05/31/05 192 187 728 17 5 3 0 404

Page 17: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

ON-LINE MONITORING – CASE STUDY

Ethylene gasser transformer

No spare available

Next to a River (risk of mineral oil

contamination if failed)

Monitored acoustically to provide warning if

fault increased in severity

Two areas of activity found at different times

EPRI Substation Equipment ,Maintenance Optimization and Diagnostic Conference Paper, 2009

Page 18: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer
Page 19: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

DGA

Sample Date

Top Oil

Temp °C

Hydrogen

(H2)

Methane

(CH4)

Carbon

Monox.

(CO)

Ethane

(C2H6)

Carbon

Dioxide

(CO2)

Ethylene

(C2H4)

Acetylene

(C2H2) COMB GAS

Comb Gas

Rate

ppm/day

01/12/2009 28 48 187 125 0 1620 1020 16 1396 34.67

01/06/2009 28 44 164 133 0 1660 834 13 1188 24.25

12/29/2008 37 129 145 0 1720 673 10 994 11.90

12/08/2008 26 18 79 139 0 1680 502 5.5 744 3.24

11/17/2008 35 19 79 138 0 1780 435 5.2 676 1.53

10/10/2008 35 18 77 128 0 1560 389 5.8 618 0.18

09/23/2008 30 20 72 129 0 1620 388 6.4 615 -0.64

09/12/2008 38 19 74 133 0 1700 390 6.4 622 1.13

08/27/2008 35 17 69 131 0 1850 380 7.2 604 1.14

08/05/2008 42 18 69 121 2.6 1800 361 7.8 579

Page 20: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

– Highest acoustic activity when unit was loaded for extended periods of time

– Utility reduced the load on the unit (when possible) and the gassing and acoustic activity decreased

– Sudden increase in acoustic activity and gassing in December 2008 prompted to remove unit from service

ON-LINE MONITORING

Page 21: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Fault gas interpretation results

• C57.104

– “Thermal-oil” fault profile, Condition 2

• IEC standard 60599: Thermal fault >700 C (T3)

Page 22: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Evidence prior to teardown

• Removed from operation after 8 months of continuous monitoring

• Electrical tests applied at manufacturer’s facility. All tests passed.

• Tank was opened and an unintentional core ground was found

Page 23: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Transformer tear-down in progress

Page 24: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

2D – HIGH VOLTAGE VIEWFault location indicated on the pre-teardown unit

On dismantling of the frame, the fault

was found in the predicted area

Page 25: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

2D – RIGHT SIDE VIEWThe predicted location aligned well with the findings

Good correlation of the fault

with the predicted area

Page 26: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

2D – TOP VIEWThe predicted location aligned well with the findings

Good correlation of the fault

with the predicted area

Page 27: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Close-up of the burnt core-steel and tank

Direct correlation between the damaged

core-steel and the burnt tank – where

sharp burrs from the core-steel cause

an unintentional core-ground and

hence overheating

Page 28: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Location of the problemBurn marks on deformed core-steel

Page 29: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

OLM - Summary

• The application of Acoustic Emission was successful in locating the problem in the unit after tear-down

• The added information provided by the Acoustic Emission results was an aid in the decision-making on whether to take the unit out of service or not

• The timely information provided to the customer allowed them to maintain this unit in service for 8 months (while waiting for a new unit)

Page 30: IEEE Transformer Committee Atlanta 2016grouper.ieee.org/groups/transformers/subcommittees/dielectric_test/... · IEEE Transformer Committee Atlanta 2016 ... Three phase Transformer

Questions?

Arturo NúñezSubstation Reliability COE Manager

MISTRAS Group, [email protected]

(609) 716-4162

www.transformer.clinic