IDBE-HF-QPZZZ-EF0107 Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure Rev.0

Embed Size (px)

DESCRIPTION

wi

Citation preview

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 1 of 21

    _________________________

    BANYU URIP PROJECT _________________________

    Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure

    IDBE-HF-QPZZZ-EF0107

    0 2-Apr-2014 Issued for Construction MA AW/FS BY F 1-Apr-2014 Re-Issued for Company Review MA AW/FS BY E 9-Mar-2014 Re-Issued for Company Review DA MA/FS BY D 27-Jan-2014 Re-Issued for Company Review DA MA/FS BY C 9-Jan-2014 Re-Issued for Company Review DA MA/FS BY B 29-Nov-2013 Issued for Company Review DA HB/FR BY A 8-Aug-2013 Issued for Internal Review DA HB/FR BY

    REV. REV. DATE DESCRIPTION PREPARED BY CHECKED BY APPROVED BY

    Contract No.: C-3207106

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 2 of 21

    REVISION MODIFICATION LOG

    Revision Section Description

    A All Issued for Internal Review

    B All Issued for Company Review

    C All Re- Issued for Company Review

    D Title Changed the title become : Flooding, Cleaning, Gauging & Hydrostatic Test

    Section 4 Added document SNI 3473-2011

    Section 8.3 Revised text

    Section 9 Revised the number of pax required

    Section 11 Revised Equipment list

    Section 14.2 Complied with Company specification & Revised Acceptance Criteria

    Section 14.2.1 Added detail of the pig sequence

    Section 14.3

    Revised the specification & Stabilization period prior to pressure testing

    Section 14.5.2 a Revised text

    Section 14.7 Revised based on the latest agreed methodology

    Attach. 1 Revised contingency plan

    Attach. 2,3,4,5 Revised Drawing

    Attach. 9 Revised Reporting format

    E All Re- Issued for Company Review

    F All Re- Issued for Company Review

    0 Attach 9 Issued for Construction

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 3 of 21

    TABLE OF CONTENTS

    1. INTRODUCTION .. 4

    2. SCOPE . 4

    3. OBJECTIVE . 5

    4. REFERENCES DOCUMENT . 5

    5. ABBREVIATIONS . 7

    6. DEFINITION . 7

    7. PERMITS . 8

    8. SAFETY AND HEALTH 8

    9. MANPOWER .... 10

    10. ROLES AND RESPONSIBILITIES .. 11

    11. EQUIPMENT 12

    12. WORKING TIME . 13

    13. COMMUNICATION SYSTEM 13

    14. HYDROSTATIC TESTING .... 13

    15. TEST DOCUMENTATION . 19

    16. ATTACHMENT

    Attachment 1 - Contingency Plan Attachment 2 - Flooding, Cleaning & Gauging Arrangement Attachment 3 - Equipment Layout Attachment 4 - Hydrotest Arrangement Attachment 5 - Water Pond Attachment 6 - Hydrostatic Pressure Chart Attachment 7 - Organization Chart Attachment 8 - Pig Data Sheet ( Bi-Di Pig) Attachment 9 - Form Reporting Attachment 10 - Velocity Pigs, Chemical & Dyes Calculation Attachment 11 - MSDS Corrosion Inhibitor Attachment 12 - MSDS Fluorescence Dyes Attachment 13 - Waste Water Standards Attachment 14 - Tracker and Pingers Attachment 15 - Equipment Specs / Calibration Certificate Attachment 16 - Test Blind Attachment 17 - Removal of pulling head/ Installation Of Weld Neck Flange and Test

    Blind Attachment 18 - Risk Assessment Action Items

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 4 of 21 1. INTRODUCTION

    The Export offshore segment consists of a new 20 pipeline and start from onshore the Java Sea coast at Palang, East of Tuban to offshore floating storage and offloading vessel (FSO). The subsea pipeline length is approximately 23 + 295 km.

    2. SCOPE

    The scope of this procedure describes the minimum requirements and methodology for the Hydrostatic Testing .

    The sequence of hydrostatic testing that is covered by this procedure is follows :

    Water Filling

    Pressurization

    Holding Time of Pressure Test

    Test Acceptance

    Depressurization

    Off shore Export Pipeline System Characteristic :

    Pipe Material : API 5L X60 Outside Diameter : 20 + (0.61mm FBE +44mm PUF+10mm HDPE) & CWC Wall thickness : 12.7 mm Length : 23,000. meters Design Pressure Fitting : ASME Pressure Temperature Rating Class 600 Max Operating Pressure : 78C 6.21Mpag (900.68 Psig) Max Operating Pressure : 28C 9.31Mpag (1350 Psig) For restart after cool down Design Pressure : 9.31 Mpag (1350.30 Psig) Design Factor : 0.72 (ASME B3.14) Corrosion Allowance : 1.6mm Max Design Temperature : 95C Minimum Elastic Bend : 800m 9.53thk and 550m 12.7thk Test Pressure : 11.64 Mpag (1688 Psig) Duration : 24 Hours

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 5 of 21 3. OBJECTIVE

    The purpose of this procedure is to provide a methodology for hydrostatic testing. This procedure will help to ensure that the work is performed safely and in full compliance with project requirements.

    4. REFERENCES

    The latest revision of the following reference documents shall be used in conjunction with this procedure document.

    Codes and Standards API RP 1110 Pressure Testing of Liquid Petroleum Pipelines

    ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids

    SNI 3473-2011 Sistem Transportasi Pipa Penyalur Untuk Cairan Hidrokarbon dan Cairan Lain

    Company Specification Document No. Document Title

    IDBE-WO-YSPDS-E00011 System Gauging, Hydrostatic Testing & Disposal

    IDBE-WO-YSPDS-EF0005 Shallow Water Pipeline Construction and Installation

    Project Engineering Reports Document No. Document Title

    IDBE-RL-YBDES-EF0001 Offshore Pipeline Design Basis Document

    IDBE-RL-YBDES-EF0002 Residual Engineering Design Basis

    IDBE-RL-YRPPL-EF0008 Pull Head Design

    IDBE-RL-YRPPL-EF0007 Abandonment & Recovery and Pipeline End Lay down Head Design

    Project Drawings Document No. Document Title

    IDBE-RL-YDMAP-EF0002 Offshore Pipeline Field Layout

    IDBE-RL-YDPAL-EF0001 Offshore Pipeline Alignment Drawings from Landfall to Mooring Tower

    IDBE-RL-YDZZZ-EF0011 Shore Approach: Site Layout Plan

    IDBE-RL-YDZZZ-EF0016 Pull Head Details

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 6 of 21

    IDBE-RL-YDZZZ-EF0019 Abandonment & Recovery and Lay Down Head Details

    IDBE-RL-YRRSK-EF0001 Risk Assessment Reports

    Project Plan Document No. Document Title

    IDBS-RL-SPREG-OF0002 Waste Management Plan

    IDBE-RL-QPITP-EF0008 Inspection and Test Plan for Pigging, Gauging, Flooding & Hydro-Testing of Pipelines

    Indonesian Regulatory

    Document No. Document Title

    Nomor 21.K/38/DJM/1999 Keputusan Direktur Jenderal Minyak dan Gas Bumi

    Nomor 84.K/38/DJM/1998

    Pedoman danTata cara Pemeriksaan Keselamatan Kerja atas Instalasi, Peralatan danTeknik yang Dipergunakan dalam Usaha Pertambangan Minyak dan Gas Bumi dan Penguasaan Sumber daya Panas Bumi (Inspection Guidelines for Safety on Facilities, Equipment and Technology used in Oil and Gas and Geothermal Activity)

    Nomor 300.K/38/M.PE/1997 Keselamatan Kerja Pipa Penyalur Minyak dan Gas Bumi

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 7 of 21 5. ABBREVIATIONS

    - DV/DP : Actual volume change for an associated change in pressure for the specified volume under test

    - ERP : Emergency Response Plan

    - JSA : Job Safety Analysis

    - MCL : Mobil Cepu Limited

    - NDE : Non Destructive Examination

    - PPE : Personal Protection Equipments

    - PTW : Permit to Work

    - QC : Quality Control

    - RA : Risk Assessment

    - WPS : Welding Procedure Specification

    6. DEFINITION

    - Company : Mobil Cepu Ltd. - Contract : Banyu Urip Project Offshore Export Pipeline EPC3. - Contractor : Consortium of PT. REKAYASA and PT. LIPKIN - Subcontractor : PT. Farrel Internusa Pratama. - MIGAS : Indonesian Government Board responsible issuing approvals

    and licenses of oil and gas facilities. - Days : A project calendar day which refers to calendar applied in

    project planning. - Goods : Contractors Equipment, Materials, Plant and Temporary

    Works, or any of them as appropriate. - Construction Drawings : The drawings produced and issued by the Contractor for the

    purpose of construction. - Temporary Works : All temporary works on Site for the execution and completion

    of the Permanent Works and remedying of any defects - Approval or Consent : When given by the COMPANY, that the relevant person(s)

    has/have no objection to a proposal or submittal of the Contractor.

    - Specification : An explicit set of requirements to be satisfied by material, product or services.

    - Procedure : A series of written steps to be carried out in a logical order for a defined operation or a given situation.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 8 of 21 7. PERMITS

    A permit to work (PTW) shall be prepared by the Supervisor and approved by the COMPANY representative and in line to Permit to Work Procedure and Regulatory permit requirement from Ministry of Environment

    8. SAFETY AND HEALTH

    CONTRACTOR personnel shall be pre-briefed on the operating procedures and the potential hazards in a pre-mobilization Job Safety Analysis (JSA). The JSA shall be reviewed prior to commencing any operation activities, refer to Appendix Job Safety Analysis. Prior to commencing the operation CONTRACTOR personnel shall discuss the operations with Client Site Representatives to ensure a complete understanding of the operation will be taken place. CONTRACTOR personnel shall inspect the arrangement of the equipment on site prior to commencing of operations. Whilst on site, CONTRACTOR personnel shall conduct all activities in accordance with the site and project procedures (including the permit to work system). The CONTRACTOR Hydrostatic Engineer shall be responsible for ensuring all permit requirements are fully adhered to the immediate vicinity around the work area shall be cordoned off with barrier tape and suitable signs erected.

    Any individual onboard the vessel has the authority, and obligation, to stop any operation without recrimination should they observe an unsafe act or an occurrence that has a potential hazard to personnel, asset or equipment. Once an "all stop" has been called, only the Barge Superintendent or his on-shift Deck Supervisor has the authority to recommence operations once it has been established that it is safe to do so.

    All works associated within this procedure shall be subject to a risk assessment in accordance with the IDBS-RL-FPRSK-OF0002 Risk Assessment and Management Plan.

    8.1. Tool Box / Safety Talk A Tool Box / Safety Talk shall be conducted on-site before each new phase of operations. The talk shall outline the work to be carried out and shall include but not limited to the following: Sequence, co-ordination and details of work to carried out Hazards/control measures/emergency response contingency plans Safe areas/escape routes/muster points Barriers and signs The toolbox talk shall be given to each shift (day/night) and the permit re-issued each shift.

    8.2. Personnel Risk All personnel shall wear personal protective equipment (PPE) provided for their use. Protective hard hat, steel toe safety boots, safety glasses shall be the minimum safety clothing worn at all times when on-site. All personnel shall carry ear protection and gloves with them at all times and use them in the appropriate situations. Waterproof jacket and trousers shall be worn in adverse weather conditions. Hearing protection is mandatory where equipment with a sound power level in excess of 85 dB (A) is in operation.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 9 of 21

    Portable eyewash station shall be set up in the vicinity of chemical storage and handling. All personnel handling chemicals will wear appropriate chemical protection suits, gloves and face shields, to supplement above PPE requirements.

    8.3. Equipment Set Up All equipment shall be located in a manner which leaves suitable and safe escape routes. Equipment shall be positioned so as to leave 0.6 m access in between, such that it will :

    Prevent trip hazards Prevent damage to hoses Protect all personnel and site equipment in the event of hose failure

    8.4. Pressure Testing Safety Hydro testing involves the application of pressure to pipelines and equipment; a release of pressure energy from the system or equipment could pose a risk to personnel. The following safety rules shall be adhered to at all times:

    All items of equipment containing pressure are to be clearly marked and the areas barrier to prevent unauthorized access.

    Piping and connections must never be opened without checking the system valve positions and ensuring no pressure is present by checking the pressure gauge and opening vents.

    All piping systems are to be supported and restrained to prevent any movement during testing. All flexible hoses are to be restrained to prevent movement, with whiplash protection installed on

    each joint. All hoses and equipment are to be inspected and be in good condition prior to applying pressure. Never attempt any remedial work on any equipment under pressure Always checked that no low pressure or unauthorized fittings/instruments have been used in the

    rig up or system. Pressure Safety Valve (PSV) will be installed in the system.

    8.5. Environmental Control All equipment with the potential for spill causing environmental damage will have drip pans or tarpaulin sheets incorporated. Drip tray or tarpaulin sheets shall be utilized for retrieval of pigs if the presence of hydrocarbon liquids may be present. During filling water (Flooding/Pigging), all hydrotest discharges shall be collected to the water pond for treatment. The treatment consist of Treatment Oxygen ( O2) From Air Compressor Treatment Chemical

    - Limestone (CaCo3) 100 Kg - Alum / Tawas 100 Kg

    Sampling shall be made of the hydrotest discharges in the water pond and an analysis conducted on the Laboratory ( PT Envilab Indonesia) to ensure that quality of the water meets the waste water standard and then returned to the sea. 8.6. Actions In The Event of Emergency In the event of an emergency during operations, all equipment shall be shut down immediately and put in a safe condition.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 10 of 21

    If a system is under pressure at the time of an emergency, the injection point must be closed as soon as pumping has stopped. Non return valves shall be fitted to injection points of systems to ensure that pressure is contained in the event of hose failure Work permits (if any) are to be returned to the permit office/control room. Personnel shall proceed to their allocated emergency muster point in accordance with the platform ongoing response plan. No work can recommence until the permit to work is re-issued. Prior to re-introducing pressure to the system, all equipment must be checked to ensure no damage or alteration has occurred during the emergency stand down. 8.7. Security

    Security will be provided by a professional security provider, supplemented by trained local villagers.

    Security will be provided at all times (night and day) when equipment, tools and material are left on site without any working activity.

    Security shall patrol the job site regularly to keep the working area free from non-authorized persons and local community, and to prevent property loss.

    Badge/verification card shall be used by all personnel during working time on site. Site security shall report to security coordinator if any incident.

    9. MANPOWER

    CONTRACTOR will mobilize the following manpower to perform the Hydrostatic Testing activities :

    NO Description Pax Provider

    1 Hydrostatic Testing Supervisor 2 persons Farrel

    2 Safety Officer As Required Hafar

    3 Hydrostatic Testing Engineer 1 person Farrel

    4 QC Inspector As Required Hafar

    5 Mechanic 6 persons Farrel

    6 Diver As Required Hafar

    7 Medic As Required Hafar

    8 Helper As Required Hafar

    9 Environmental Advisor As Required Hafar

    Safety induction shall be given by safety officer to all workforce. Safety officer is responsible for briefing-out about the working hazards and risk prior to mobilization / assigning to site. Safety induction will be conducted at recruitment officer or at muster point at site.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 11 of 21

    10. ROLES AND RESPONSIBILITIES

    10.1 Hydrostatic Testing Supervisor The Hydrostatic Testing Supervisor is responsible for the overall coordination and supervision of the activities. The Hydrostatic Testing Supervisor will provide the necessary information and liaise with CONTRACTOR PTW Man responsible for applying the correct work permits prior to commencement of works. The Supervisor shall also be responsible for the overall implementation of the Project HSE Plan and safety regulations that govern.

    10.2 Safety Officer The Safety officer will be responsible for the implementation of the HSE Plan and compliance with all statutory regulations that govern on all the activity commenced at his assigned spread. The Safety officer shall supervise the HSE aspects of the work and conduct safety briefings. 10.3 Hydrostatic Testing Engineer The Hydrostatic Testing Engineer is responsible for planning, preparing the working procedure, execution, control and coordination with the Hydrostatic Testing Supervisor to supervise of all Hydrostatic Testing activities is performed in accordance with SHES regulation and working procedure. He also responsible to check the equipment and instrument check list report that prepared by the mechanic.

    10.4 QC Inspector The QC Inspector is responsible for the quality of the documentation produced by the Hydrostatic Testing team. The QC Inspector shall report to QA/QC Department Manager. QC Inspector also responsible to inspect all the connection of the test package and record the required data such as pressure, test temperature, ambient temperature, etc. during hydrostatic testing. 10.5 Mechanic The Mechanic is responsible for checking and maintains all the required equipment in good condition and ready for use.

    10.6 Diver The Diving shall report to the Hydrostatic Testing Engineer. He also The Divers are responsible for installation and operation launching head and removal of pigs with diving safely. Diver shall have valid diving license.

    10.7 Medic The Medic will be standby at the working area during the hydrostatic testing activities. The Medic is responsible to conduct first aid team in case of medical emergencies. The Medic shall be part of the Emergency Response Team. 10.8 Helpers The Helpers are responsible for performing all work ordered by supervisor correctly and safely. Work will consist of unskilled activities such as: preparing the hand tool, perform manual handling, connecting hoses, setting up barricades, etc. 10.9 Environmental Advisor Environmental Advisor is responsible to assist the hydrostatic testing team with environmental issues. Study of hydrostatic testing water including permit, develop water study and treatment plant, water sample analysis and other will be carried out together with Hydrostatic Testing Team.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 12 of 21

    11 EQUIPMENTS CONTRACTOR will mobilize the following equipment to perform the Hydrostatic Testing activities as follow :

    No Description Specification Quantity Provider 1 Supply Pump min 1000 ltr/min 5 Unit Farrel

    2 Filling Pump 5000 ltr/min 2 Unit Farrel 3 Chemical Flow meter 2 Unit Farrel 4 Mesh Screen filter 100 (microns) 1 Unit Farrel 5 Water Filter (Certified) 50 micron 2 Unit Farrel 6 Portable Water Tank Cap. 5000 ltr 2 Unit Farrel 7 Flow Meter Pump (calibrated) resolution 0.01 m3 2 Unit Farrel

    8 Water Filling Flexible Hose 4 c/w hose connection 60 100

    metre Farrel

    9 Whip line 8 mm 1 Lot Farrel 10 Ball valve 1/5 - 2 As Required Farrel 11 Plug 1 - 4 As Required Farrel

    12 Bourdon Pressure Gauge for Water Filling (calibrated) Range 0 Psi 600 Psi 2 Set + Spare Farrel

    13 Bourdon Pressure Gauge for Hydrotest (calibrated) Range 0 Psi 3000 Psi 2 Set + Spare Farrel

    14 High Pressure Injection Pump min 3000 psi Capacity 1 Unit + Spare Farrel

    15 Dead Weight Tester (Certified) Accuracy 0.2 Psi, Increment 1 Psi 2 Unit Farrel

    16a Pressure recorder (calibrated)

    Accuracy 1 % the full range, Range 0 3000 Psi, Chart Diameter min 300 mm, 24 Hours recording period, Increment 0.2 MPa

    2 Set Farrel

    16.b

    Temperature recorder (calibrated)

    Range 0 F 200 F, Accuracy 0.2% over the full range, Chart Diameter min 300 mm, Valid 24 Hours Period

    2 Set Farrel

    17 Barograph 1 Unit Farrel

    18 Invertible thermometers to measure sea bottom temperature 1 Unit Farrel

    19 Laboratory Thermometer for Thermowells Range 0 C to 50 C, Accuracy 0.1 C 1 Unit Farrel

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 13 of 21

    All equipment shall All equipment shall have valid third party certificates which will be attached to Permit to Work (PTW). Refer to Appendix 15

    12 WORKING TIME Working times will start at 7.00 am, after the Pre-Job meeting and after having checked that all equipment and tools are in good condition prior to use. Lunch time is 12.00 to 1.00 pm, but during pressure holding (hydrostatic testing) personnel shall have their lunch at the test area and lunch alternately. Work continues at 1.00 pm until 5.00pm.Priorto leaving the working area, all equipment and tools shall be tidied up and the working area shall be cleaned. Prior to the 24 hours operation, personnel shall be divided into 2 shifts .Working times will then change to 07.00 to 19.00 and 19.00 to 07.00. The Supervisor shall inform the safety officer and COMPANY site representative when overtime is required, in a timely manner.

    13 COMMUNICATION SYSTEM Communications shall be maintained between all parties involved during the entire duration of the pipeline pre-commissioning operations. For communication between launching and receiving locations, intrinsically safe VHF or SSB radio shall be the sole communicating means. If required, VHF radio sets shall be established under CONTRACTOR provision. VHF & SSB radio shall be provided to COMPANY Personnel.

    20 Ambient Air Temperature recorder (Certificated)

    Range 0 C 80 C, Accuracy 1 % over the full range

    1 Unit Farrel

    21 Pressure Relief Valve Set 3% above test pressure 1 Unit Farrel

    22 Handy Talk As Required Hafar

    23 High Pressure Flexible Hose 1 c/w hose connection 1 Lot Farrel

    24 Non-Return Valves (Check Valve) 4 1 Unit Farrel

    25 Ball Valve 2 1 Unit Hafar 26 Bi-Directional Pig for Water Filling 20 4 Set + Spare Farrel

    27 Additional Fitting or connecting (reducer bushing, needle valve, plug, etc.

    As Required Farrel

    28 Hand tools (wrench, hammer, etc.) As Required Farrel

    29 Air Compressor 180 Psi 1 Unit Farrel

    30 Lay down Head (Launcher & Receiver) 2 Set Hafar

    31 Discharge hoses for pigging 2 Dia x 25m 4 Lengths Farrel

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 14 of 21

    14 FLOODING, CLEANING, GAUGING & HYDROSTATIC TESTING 14.1. Test Medium All seawater entering the pipelines shall be free from any debris, sand, silt or air. To achieve this the water shall be fed through a break or settlement tank, and then filtered before being pumped into the pipeline. The filters shall be placed in parallel so they can be cleaned or changed without interrupting operations and shall be capable of removing all particles over 50 microns. The average content of suspended matter shall not exceed 20g/m3. All cleaned test seawater introduced into pipeline shall be chemically treated with corrosion inhibitor, biocide and oxygen scavenger.

    Periodic sampling shall be made of the water pumped into the pipeline and an analysis conducted on the sample taken. At least two independent tests of chemically treated fill water shall be taken for each pipeline test section. Chemically treated water is sufficient for one year preservation in the pipeline.

    Representative samples shall be taken at commencement and at convenient intervals during line filling and flushing. Frequency and timing of samples shall be at the direction of COMPANY. The analyses shall quantify the following:

    1. Oxygen (

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 15 of 21

    The concentration level of each of the chemical additives shall be maintained within 5% of the approved levels. All chemicals shall conform to the written consent for pipelines discharge issued by the relevant Statutory Authorities.

    Selection of the type of corrosion inhibitor, oxygen scavenger, biocide and dye shall be considered for possible harmful interactions and their impact on the environment during and after disposal of the water. Where flanges shall be installed in the pipeline test section a dye shall be added to the treated water during the pressure test. Dyes shall be selected from materials that are easily visible underwater. The dosage should be as recommended by the supplier.

    14.2. Flooding, Cleaning & Gauging Before filling the pipeline (after pig 4, Gauging Pig), the sea water will be treated to ensure that the quality of the water meets COMPANY requirements. A 50 micron filter will be installed to catch solid particles over 50 microns. Multitreat 5549R will be used as corrosion inhibitor, oxygen scavenger and biocide. Chemical inhibitor, oxygen scavenger, dye will be mixed in tank. Preference of dosage is 700 ppm for the chemical treatment and 15 ppm for the fluorescent dye ( green color ).

    Filling water will be injected into the pipeline shall be achieved by using 4 pigs driven by pumped water. The pigs run at 0.5 1.5 m/s. Pressure will be measured by pressure gauge. The volume of the water will be measured by flow meter. The volume of sea water (untreated) in between two pigs is 30 m. Because of the elevation difference along the mainline, a back pressure of 1 bar must be maintained to stabilize the velocity of the pig while water filling. During the filling operation, the volume of seawater pumped into a pipeline shall be enough to achieve a flow velocity in the range 0.5 1.5 m/s . See attachment 10 for Flooding, Cleaning & Gauging calculation.

    The pig sequence is pig 1. Flooding pig (Bi-Di normal), pig 2. Bi-Di Brush, pig 3. Bi-Di Magnet, pig 4. Gauging pig (Bi-Di Gauging). Pingers will be installed on pig 1 and 4, as leading and trailing pigs and tracked on the receiver ( Palang Land Fall ).

    This Step shall be conducted by the following sequence: see attachment-2 (Flooding, Cleaning & Gauging).

    1. The Laydown head shall be pre-loaded with four bi-directional pig for Flooding, Cleaning & Gauging at location. The laydown head will be attached to the Expansion Spool Flange ( KP 23.3).

    The pulling head located at land fall Palang will receive the four pigs. The pulling head was designed to receive the pig train and preparations (include discharge hoses connection to settlement tank and ensuring correct discharge valves status) will be made to vent the line. Preparation will be confirmed prior to pigging operation.

    2. Connect the Laydown Head on the seabed to the flexible hose 4 to filling pump onboard the Hafar Neptune (KP 23.3). Diver to secure hose camlock connections by securing a hose tether to pig launcher guard.

    3. Connect hose 2 to valve 2, 3, 4 & 5 at pulling head at land fall Palang to vent any air trapped in the mainline and by releasing the water to water tank and water pond. Valve No. 1 installed pressure gauge with 0 600 Psi and open position. Valve no. 6 closed position uses for emergency (pig stall).

    4. Open valve no F & E, then turn on the filling pump, insert 10 m of untreated seawater in front of the first pig (Flooding) through valve no. E.

    5. Close valve no. E then open valve no. D to start filling water and thus launch the first pig by pumping of untreated seawater 30 m ( distance between pig is 164 m). Leave valve no. F, 2, 3, 4 & 5 in open position to flush out air and water from the mainline to the water tank, valve no. 6, A, B, C & E are in closed position.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 16 of 21

    6. Then continue to pumping of 30 m untreated seawater for the second pig (Bi-Di Brush) by opening valve no C (distance between pig is 164 m). Leave valve no F, 2, 3, 4 & 5 in open position to flush out air and water from the mainline to water tank, valve no 6, A, B, D & E are in closed position.

    7. Then continue to pumping of 30 m3 untreated sea water for the third pig (Bi Di Magnetic) by opening valve no B (distance between pig is 164 m). Leave valve no F, 2, 3, 4 & 5 in open position to flush out air and water from the mainline to water tank, valve no 6, A, C, D & E are in closed position

    8. Open valve no. A (valves 6, B, C, D & E closed position) Continue with chemically treated sea water filling and send the fourth pig (Bi-Di Gauging) until the mainline is completely filled.

    9. Once the Four pigs have arrived at the pulling head / receiver ( land fall Palang), track the gauging pig to ensure the pig have arrived, then close valve no. 4 & 5 slowly and continue water filling.

    10. Vent out any air from the pulling head / receiver (land fall Palang) by opening valve no. 2 & 3 . Continue until all air is expelled.

    11. All of untreated sea water (10 m of water in front of the first pig, 30 m of water between of first pig and second pig, 30 m of water between of second pig and third pig, 30 m3 of water between of third pig and fourth pig) was released while venting will be collected in water pond through water tank for treatment. Air Compressor supply Oxygen to the water pond. The water returned to the sea after an analysis conducted on the Laboratory ( PT Envilab Indonesia) and meets the waste water standard

    12. Once the pigging operation has been completed, remove the pulling head / receiver ( land fall Palang) and analyze the result of the gauging pig. Then weld on a WN Flange to pipeline.. Refer to attachment 17 for pull head/ receiver removal, weld neck flange aand test blind installation sequence.

    During filling operation, the following data shall be recorded every 15 minutes: Time of departure and arrival bi-di pigs. Flow and water in m3. Inlet and outlet pressure. Acceptance Criteria Cleaning is considered to be completed when the quantity of debris does not exceed 1% of the total pipeline volume during a single pipe cleaning run. In case higher solid contents are found additional pig should be run until pipeline is cleaned from the debris. Sample water will be taken between 3rd & 4th pig arrival, and put into 3 x 1 ltr clear graduated measuring cup. The water then will be sieved through 50 micron filter. The collected debris will be weighed, and then divided by specific weight of steel (7.82 kg/ltr), to get the volume of the debris. The pipeline will be deemed clean if:

    (Volume of debris / Volume of water) x 100% 1%

    Note: If sample completed does not satisfy above requirement, 3 more water samples will be collected after the 4th pig. Average results of the collected water samples will be used.

    The gauge plate is to be made of 6 mm aluminium plate with a gauge plate diameter of 95% of the lines internal diameter. The damage OD gauge plate should not be less than 95% of minimum pipeline ID or 25mm less than minimum pipeline ID whichever is larger.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 17 of 21

    14.3. Hydrostatic Testing

    14.3.1 Pressurization

    After Flooding, Cleaning & Gauging is completed, the filling connection shall be isolated and the pressurizing connections shall be established. AWB Labuan 2310 will support hydrotesting activities. See attachment- 4 Hydrostatic Testing. All the hoses shall be fitted with a whip line. All pressure gauges and recorders shall be calibrated at site using a valid DWT before start of hydrostatic testing. Follow the requirements of IDBE-WO-YSPDS-EF0005 Section 17.6.2 Calibration : a. All recorders and dead weight testers shall be calibrated immediately prior to use. b. Calibration certification shall be provided for each recorder and dead weight tester used. c. Recorders shall have calibration verified following the hydro test. d. Post-test calibration failure for any recorder shall be grounds for the hydrotest to be rejected by

    the Company.

    Before start of pressurization, the pipeline profile shall be studied to confirm the test pressure at the highest point, lowest point and testing point. The test pressure of the pipeline section shall be minimum Tested Pressure = 1.25 x Design Pressure. To accurately monitor the pressurization operation the testing engineer will install, at the test header near the pressure pump a calibrated pressure recorder, pressure gauge, dead weight tester. All test instrumentation will be located in the Hydrostatic Testing cabin or close to the test point area. A positive displacement high pressure pump will be located adjacent to the filling point. The pressurizing pump will deliver the volume of water required to pressurize the test section (0 - 1688 psi). Pressure gauges and pressure recorder shall be installed in the line before starting pressurization. The pressure and temperature recorder chart shall be signed by COMPANY and started to record on real time basis.

    See attachment- 4 (Hydrostatic Testing) & attachment- 6 (hydrostatic pressure chart)

    1. Remove laydown head (on seabed) and install blind flange with vent valve assembly, refer to attachment 16 (Test Blind)

    2. Pressure and Temperature Recorder, Dead Weight Tester (DWT), Bourdon Pressure gauge ( 0 3000 Psi) will be installed at Palang Land Fall, See attachment- 4 (Hydrotest Arrangement)

    3. Weld neck flange shall be welded on the pipeline at Palang Land Fall. Test blind shall be installed onto the weld neck flange. High Pressure Pump (at land fall Palang) connect fittings onto the test manifold (Palang Land Fall) See attachment- 4 (Hydrotest Arrangement) and attachment 17 for weld neck flange and test blind installation. Ensure that all connections are connected and correctly tightened. All the pressure hoses will be secured using whip line before start up of pressurization.

    4. Close valve no. 5 and open valve no 1, 2, 3, & 4 then turn on High Pressure Pump for starting pressurization. (Refer to attachment 4)

    5. The pressurization will be conducted by the following pressurization step, as follow:

    a) Pressurize 5.7% (96.3 psi) to 50% of the test pressure.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 18 of 21

    The pressure increase rate shall not exceed 14.5 psi/min. When the pressure reaches 50% of the test pressure (844 psi), stop the pump 30 minutes for stabilization, ensure no leaks exist and perform air entrapment calculations if necessary. During this period, monitor the pressure and check the test section for leakage. If a leak is found, depressurize and dewater the pipeline if necessary and repair leaks.

    b) Pressurize 50% to 75% of the test pressure

    If no leak is found continue pressurization to 75% of the test pressure (1266 psi). The pressure increase rate shall not exceed 11.6 psi/min. Stop the pump 30 minutes for stabilization and ensure that no leaks exist.

    c) Pressurize 75% to 95% of the test pressure

    Continue pressurization to 95% of the test pressure (1604 psi). Slow the pressurization rate down to 7.3 psi/min. Stop the pump 30 minutes for stabilization and ensure that no leaks exist.

    d) Pressurize 95% to 100% of the test pressure

    After 30 minutes stabilization at 95% of test pressure, resume the pressurization. During this final phase of pressurizing, the pressure increment shall not exceed 1.5 psi/min until reaching 100% of test pressure (1688 psi). Stabilize the pressure for 24 hours prior to start the holding time. When the test pressure is reached, the filling valve shall be closed and the pressurizing line shall be disconnected from the valve on the test header. CONTRACTOR shall perform the trapped air calculation before start of holding time.

    14.3.2 Holding Time of Pressure Test

    After attaining the test pressure, the line shall be left for 24 hours to stabilize. Final pressure in the line shall be noted from the dead weight tester and held for 24 hours

    minimum. Check and report pressure and temperature from Barton chart, pressure gauge, temperature

    gauge and DWT every 15 minute. Sub Sea temperature gauge will be installed at the land fall Palang Atmospheric temperature shall be recorded at regular intervals.

    14.3.3 Entrapped Air Calculation Prior to start-up of test activities, the Hydrostatic Engineer should perform a pre-test calculation of obtain a theoretical value of DV/DP for the verified volume of pipe under test and the appropriate test medium . This information to be used to determine whether entrained gas exist in the line under test. DV/DP is defined as the change in volume for an associated change in pressure of a known volume under pressure.

    14.3.3.1 Theoretical Value A theoretical V/P will give the expected volume change for an associated change in pressure for the specified volume under test assuming that the volume under pressure is free

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 19 of 21

    of entrained gas. The theoretical V/P for buried (restrained) pipe is calculated through the following equitation :

    1

    1

    Where,

    v = Incremental Volume (m3) p = Incremental pressure (bar) V = Pipeline volume (m3)

    D = Pipeline outside diameter (m)

    t = Nominal wall thickness (m)

    E = Youngs elastic modulus of steel = 2.07 x 106 bar

    = Poissons Ratio = 0.3

    B = Bulk modulus of seawater (bar)

    14.3.3.2 The Field Value A field of DV/DP is the actual volume change for an associated change in pressure for the specified volume under test. If air exists within the line under pressure, this value will be different that the theoretical value. This procedure provides guidelines for calculating both DV/DPs and acceptable differences between the theoretical and field values of DV/DP.

    a) Obtaining Field DV/DP During initial pressurization, the test section shall be pressurized to 1688 psi and allowed to stabilize. Take an accurate pressure reading. Then bleed approximately 10 psi and allow the test section to stabilize. Take another accurate pressure reading. Carefully, measure the volume of the fluid that was bled and convert this to gallons if necessary. Take the volume bled and divide this number by the difference in the pressure readings. This is the field value of DV/DP. b) Acceptable DV/DP Result of value DV/DP shall be compared with the theoretical value of DV/DP calculated. A field value of DV/DP that is greater than the theoretical DV/DP indicates the presence of entrapped air or other gas in the pipe section. So, air or other gas should be vented at the test header end, before starting the test. Acceptance Criteria (field DV/DP) (theoretical DV/DP)

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 20 of 21

    14.3.4 Acceptance Criteria

    A successful test shall consist of a twenty four (24) hours hold period in which the test pressure was held, with no unaccountable pressure decrease. Should a leak occurs, the pipeline shall be repaired and the hydrostatic test repeated. The CONTACTOR shall keep complete records of failures occurring during the test, including

    the exact locations, type and cause of failure, and method of repair. Pipe fittings and valves that fail and are replaced shall be marked with their pipeline locations and the pressure at which they failed.

    Pressure drops because of improper stabilization prior the holding time period shall lead to extensions of the holding period by multiples of four-hour periods. No pressure drops shall be acceptable during the test period, except if those clearly attribute to temperature changes or other environmental effects.

    For buried pipeline, pressure test is acceptable if the pipeline is free from leaks and pressure variation is within 0.2% of test pressure is over the agreed 24 hours hold period.

    Test duration shall be increased in case of any abrupt change in atmospheric conditions.

    14.3.5 Depressurization

    When the testing is completed and accepted by COMPANY, depressurization shall be started by the following:

    a) Depressurization will be performed at the launcher (land fall Palang) by draining the water

    Depressurize 100% to 75% of the test pressure, rate 14.5 psi/min, and hold 15 minutes. b) Depressurize 75% to 50% of the test pressure, rate 29.0 psi/min, and hold 15 minutes. c) Depressurize 50% to 30% (50.8 psi) of the test pressure; rate 43.5 psi/min Pressure 50.8

    psi will be kept in the line for back pressure the dewatering activities.

    Depressurization will be performed at the end test header by draining the water through opening valve no. 5 which will installed the hose to water tank. All water released while depressurizing will be collected into a water tank and then to water pond for treatment.

    15 TEST DOCUMENT The CONTRACTOR QC Inspector shall prepare and submit the document and report related to hydrostatic testing operation such as; pressure report and record chart etc.

  • BANYU URIP PROJECT TITLE: Flooding, Cleaning, Gauging & Hydrostatic Testing Procedure DOCUMENT NO.: REV: REVISION DATE: PAGE:

    IDBE-HF-QPZZZ-EF0107 0 2-Apr-2014 21 of 21 16 ATTACHMENT

    Attachment 1 - Contingency Plan Attachment 2 - Flooding, Cleaning & Gauging Arrangement Attachment 3 - Equipment Layout Attachment 4 - Hydrotest Arrangement Attachment 5 - Water Pond Attachment 6 - Hydrostatic Pressure Chart Attachment 7 - Organization Chart Attachment 8 - Pig Data Sheet ( Bi-Di Pig) Attachment 9 - Form Reporting Attachment 10 - Velocity Pigs, Chemical & Dyes Calculation Attachment 11 - MSDS Corrosion Inhibitor MULTITREAT 5549R Attachment 12 - MSDS Fluorescence Dyes Attachment 13 - Waste Water Standards Attachment 14 - Tracker and Pingers Attachment 15 - Equipment Spec / Calibration Certificate Attachment 16 - Test Blind Attachment 17 - Removal of pulling head/ Installation Of Weld Neck Flange and Test Blind Attachment 18 - Risk Assessment Action Items

  • Attachment 1Contingency Plan

  • CONTINGENCY PLAN1. INTRODUCTION

    Sometime due to many reason the pig might not arrive at the receiver during pig operation. If thishappens this work instruction could be applied to recover the pig. Include snapped hose and sea waterentering/flooding pipeline.

    2. HAZARDSVenting causing hearing damage and offensive noise in the local area, damage to valve seats and trims,respiratory damage due to airborne particles.

    3. JOB STEPS3.1. Non Arrival Pig

    This procedure is applicable to recover a pig that has not arrived yet.

    1. Operation notifies that pig has not arrived yet. Pig arrival time is overdue 25% from calculation.

    2. Check launch site. If the pig is still in the launcher, re-launch the pig. If the pig is not in launcher,check flow rate and pressures

    3. If flow rate are normal, the pig is bypassing. Go to section 3.2 (A) of Stall Pig. If flow rate is zero,check differential pressure. If flow rate has changed, re-calculate travel time. If pig travel time is notoverdue then continue pigging process. If pig travel time is overdue, check differential pressure.

    4. Checking differential pressure

    If differential pressure is high, please check receiver. There is possibility that there is debris inreceiver. If differential pressure is low please check possibility of process problem. If there is processproblem continue pigging activity. If there is no problem in process, please check the receiver side fordebris accumulation.

    Confirmed Stall/Pig StuckThis procedure is applicable to recover the pig that is confirmed stalled.

    A. If product bypass occurred1. When the pig is confirmed stall, identify if there is product bypass (indicated by almost normal

    pressure and flow rate). In this case, try to increase pressure and flow rate to push the pig.

    2. If pig still stall, try to re-pumping from receiver

    3. If the pig starts to move, continue pigging operation.

    4. If you can identify that the pig is moving, continue pigging operation. If the pig doesnt move at all,you may see pressure built up. Go to step B of this section 3.2.

    B. If no product bypass occurred1. If the product is not bypassing, you will see indication of pressure built up. It is expected that the pig

    moves. If the pig moves, continue pigging process. If the pig does not move try to do rocking.

    2. Do rocking or increase pressure at launch site and reduce pressure at receiver instantly a coupletimes and pressure not more than 200 psi . Check pig movement. If pig moves, continue piggingoperation. If pig does not move try to push the pig backward a bit then push again to receiver.

    3. If the pig can move, continue pigging operation.

    4. The equipment used for increasing pumping pressure in the event of a stuck pig willbe the same, just that both filling pumps will be operated simultaneously instead ofone filling pump. If there is a need to push the pig backward, the filling pumps will bedeployed in the same setup on Palang land fall. Refer to attachment 2 & 3.

  • Attachment 2Flooding, Cleaning & Gauging Arrangement

  • SEA

    FLEXIBLE HOSE4''

    WATER

    WATER

    SEABED

    PALANG LAND FALLKP 0 = KP 71.550

    5PI

    4321

    WATERTANK

    5000 Ltr

    6WELDEADWATER POND

    AIR COMPRESSOR

    MESWL 2T 2M - 8M

    BI-DI PIG

    TO FILLING PUMP

  • FLOWMETER

    CHECKVALVE

    SCREENER,100

    FILLINGPUMP

    FLOWMETER

    5000 LPM

    SUPPLY PUMPS

    2000 LPM

    2000 LPM

    2000 LPM

    1

    FILLINGPUMP 2

    SAMPLINGPOINT

    FILTER50 micron

    TOLAYDOWN

    HEAD

    ( FOR BACK UP )

    5000 LPM

    PI

    MIXING TANK5000 L

    CHEMICAL TANK

    FLOWMETER

  • WATER

    LAND FALL PALANG

    5

    PI

    4321

    WATERTANK

    5000 Ltr

    6

    WELDEAD

    WATER POND

    AIR COMPRESSOR

    GAUGINGPIG

    MAGNETICPIG

    CLEANINGPIG

    FLOODINGPIG

  • 4A3REVISION

    REV DWG. NO.NO.REV REVISION DESCRIPTIONDATE REFERENCE DRAWINGNO.

    DRAWN CHK'DBY BY

    LEADENG'R

    ENGMGR

    PAPER SIZEDRAWING NUMBERJOB NO.

    7106

    GENERAL NOTES

    PERTAMINAEP CEPU BADAN KERJASAMA PI BLOK CEPU

    C-320

  • A3REVISION

    REV DWG. NO.NO.REV REVISION DESCRIPTIONDATE REFERENCE DRAWINGNO.

    DRAWN CHK'DBY BY

    LEADENG'R

    ENGMGR

    PAPER SIZEDRAWING NUMBERJOB NO.

    7106

    GENERAL NOTES

    C-320 3

    PERTAMINAEP CEPU BADAN KERJASAMA PI BLOK CEPU

  • Attachment 3Equipment Layout

  • HAFAR NEPTUNE DECK LAYOUT PLANSCALE = 1 : 75

    BLASTINGPOT

    BLASTINGPOT

    AFTERCOOLER

    AFTERCOOLER

    WATER

    INDUCTIONFRAME

    SEPARATOR

    INDUCTIONCONTROLLER

    SWITCHBOX

    CROV CONTROL ROOM

    DDC Container w 3P Dive Control

    DIV

    ING

    AN

    D R

    OV

    Mac

    hine

    ry &

    Sto

    res

    Con

    tain

    er (S

    TAC

    KIN

    G)

  • Attachment 4Hydrotest Arrangement

  • CHECKVALVE

    FLOWMETERHigh Pressure

    Injection Pump

    MIXING TANK5000 LFILTER

    50 micron

    VALVE

    CHEMICAL TANK

    SEA

    WATER

    DWTDEAD WEIGHT TEST

    PRESSURE &TEMPERATURE

    RECORDER

    PI

    PRESSURE HOSE

    2 4

    TI

    BALL VALVE

    WELDEAD

    PALANG LAND FALL

    1

    5

    WATERTRUCK

    FLOWMETER

    BALL VALVE

    alastairRectangle

    alastairText BoxVent Point with plug

    alastairText BoxBall valve

    alastairRectangle

    alastairLine

    alastairLine

  • CHECKVALVE

    FLOWMETERHigh Pressure

    Injection Pump

    MIXING TANK5000 LFILTER

    50 micron

    VALVE

    WATER

    DWTDEAD WEIGHT TEST

    PRESSURE &TEMPERATURE

    RECORDER

    PI

    PRESSURE HOSE

    2 4

    TI

    WELDEAD

    PALANG LAND FALL

    1

    5

    WATERTRUCK

    CHEMICAL TANK

    FLOWMETER

    BALL VALVE

    BALL VALVE

    alastairRectangle

    alastairRectangle

    alastairText BoxVent Point with plug

    alastairText BoxBall valve

  • Attachment 5Water Pond

  • SIDE VIEW

    TARPAULIN / WATER PROOF

    TOP VIEW

    HOSE TO AIR COMPRESSOR

    DETAIL A

    AIR HOLE

    DETAIL A

    Waste Water Treatment :1. Treatment Oxygen ( O2 ) From Air Compressor2. Treatment Chemical - Limestone (CaCO3) 100 Kg - Alum / Tawas 100 Kg

    HOSE TO AIR COMPRESSOR

    HOSE TO AIR COMPRESSOR

  • Attachment 6Hydrostatic Pressure Chart

  • 100 %1688 psi

    30 M

    in

    24 H

    rs

    PRESSURE

    TIME

    Keep for Back Pressure (50.8 psi)

    P = Pressure (psi)T = Time (hours)

    95 %1604 psi

    75 %1266 psi

    50 %844 psi

    30 M

    in

    30 M

    in

    30 M

    in

    30 M

    in

    5.7 %96.3 psi24

    Hrs

  • Attachment 7Organization Chart

  • ORGANIZATION CHART

    Office

    Site

    REKIN HAFAR

    FARREL

    Project Manager

    Construction Manager System Completion ManagerQC Manager Environmental Eng.

    Lead QC Construction Lead System Completion lead

    QA/QC (On site) Supervisor (On site)

    Site CoordinatorJuju Juhaerudin

    Launching Team

    SupervisorDarmawan

    1. Krisnadi2. Puji3. A. Sarono

    Receiving Team

    SupervisorHaris Rensyah

    1. Rudi2. A. Yusuf3. Mulya Sitorus

  • Attachment 8Pig Data Sheet ( Bi-Di Pig)

  • 715715715

  • 715715715

  • Front

    BIDI PIG GAUGE PLATE715 mm

  • Attachment 9Form Reporting

  • MCCR

    BANYU URIP PROJECT EPC 3

    System No. Sub System No. Discipline PIPING (PIPELINE)

    Test Pack No. P&B Ref. No.

    Test Pressure (BarG) Chem. Clean Yes/ No

    Test Medium Hot Oil Flush. Yes/ No

    Test Duration (Hours) Location

    Sub System Description Print Date

    Check Record No. L22CR PIPING (PIPELINE) FLOODING INSPECTION Sheet 1 of 1

    S/N Description Yes No Remarks

    1 Pipeline Section: Nominal pipe size: 2 Section Length: m from KP to KP 3 Section geometrical volume (1): m3 Reference dwg.: 4 Reference drawings / specifications: 5 Degree of water filtration: m (< %) 6 Dispatching pressure calculated kPa actual kPa 7 Receiving pressure calculated kPa actual kPa 8 Pig Train transit time calculated hours actual hours 9 Amount of debris (2):

    10 Pipeline trapped air < % 11 For flooding detailed result see: 12 Flooding results: accepted not accepted

    Remarks: (1) Based on field metered filling volume (2) State quantity and relevant unit of measurement Outstanding Punch List attached? ( Yes / No) Enclosure (list property)

    Description Completed By Approved By Accepted By Witnessed By INPUT

    Company / Dept RL Construction RL Quality MCL Quality Third Party / Regulatory WINPCS

    Name

    Signature

    Date

  • MCCR

    BANYU URIP PROJECT EPC 3

    System No. Sub System No. Discipline PIPING (PIPELINE)

    Test Pack No. P&B Ref. No.

    Test Pressure (BarG) Chem. Clean Yes/ No

    Test Medium Hot Oil Flush. Yes/ No

    Test Duration (Hours) Location

    Sub System Description Print Date

    Check Record No. L23CR PIPING (PIPELINE) CLEANING INSPECTION Sheet 1 of 1

    S/N Description Yes No Remarks

    1 Pipeline Section Nominal pipe size: 2 Section Length: m from KP to KP 3 Section geometrical volume (V) (1): m3 Reference dwg.: 4 Reference drawing /specifications: 5 Debris to be removed during cleaning mg/l 6 Actual debris removed during cleaning: mg/l 7 Un-dissolved solid with average size > m Required: < % Actual: %

    8 Present of debris in front of last cleaning pig train : no yes 9 Flow test required not required flow test completed

    10 Actual volumetric capacity: m3 11 For Cleaning detailed result see: 12 Cleaning results: accepted not accepted

    Remarks: (1) Based on drawing data Outstanding Punch List attached? ( Yes / No) Enclosure (list property)

    Description Completed By Approved By Accepted By Witnessed By INPUT

    Company / Dept RL Construction RL Quality MCL Quality Third Party / Regulatory WINPCS

    Name

    Signature

    Date

  • MCCR

    BANYU URIP PROJECT EPC 3

    System No. Sub System No. Discipline PIPING (PIPELINE)

    Test Pack No. P&B Ref. No.

    Test Pressure (BarG) Chem. Clean Yes/ No

    Test Medium Hot Oil Flush. Yes/ No

    Test Duration (Hours) Location

    Sub System Description Print Date

    Check Record No. L25CR POST TEST CRITICAL COMPONENT REINSTATEMENT Sheet 1 of 1

    S/N Description Yes No Remarks

    1 Pipeline Section: Nominal pipe size: 2 Site locations KP- (1) 3 Test spade and blinds 4 Check valve discs 5 Strainers 6 Test drain & vent plugs 7 Valves reinstated properly 8 Instrument reinstated properly 9 Spring/variable support

    10 Temporary support removed 11 Gasket type checked correctly 12 Bolting checked 13 Check flange faces are undamaged 14 All items removed for test reinstated

    Remarks: (1) For items checked and accepted mark with thick (2) For not applicable items mark N/A Outstanding Punch List attached? ( Yes / No) Enclosure (list property)

    Description Completed By Approved By Accepted By Witnessed By INPUT

    Company / Dept RL Construction RL Quality MCL Quality Third Party / Regulatory WINPCS

    Name

    Signature

    Date

  • MCCR

    BANYU URIP PROJECT EPC 3

    System No. Sub System No. Discipline PIPING (PIPELINE)

    Test Pack No. P&B Ref. No.

    Test Pressure (BarG) Chem. Clean Yes/ No

    Test Medium Hot Oil Flush. Yes/ No

    Test Duration (Hours) Location

    Sub System Description Print Date

    Check Record No. L26CR PIPING (PIPELINE) HYDROSTATIC TEST Sheet 1 of 1

    S/N Description Yes No Remarks

    1 Pipeline Section: Nominal pipe size: 2 Section Length: m from KP to KP 3 Section geometrical volume (V1) (1): m3 Reference dwg.: 4 Metered volume of water used for hydrotesting (V2): m3 5 Reference drawing /specifications: 6 Reference flooding report: 7 Test pressure at initial KP: kPa 8 Test pressure at final KP: kPa 9 Leakage during test: no yes

    10 Pressure variation during test period: < % 11 Pressure variation due to temperature change: % 12 For Hydrostatic test results see: 13 Hydrostatic test results: accepted not accepted

    Remarks: (1) Based on field metered filling volume Outstanding Punch List attached? ( Yes / No) Enclosure (list property)

    Description Completed By Approved By Accepted By Witnessed By INPUT

    Company / Dept RL Construction RL Quality MCL Quality Third Party / Regulatory WINPCS

    Name

    Signature

    Date

  • MCCR

    BANYU URIP PROJECT EPC 3

    System No. Sub System No. Discipline PIPING (PIPELINE)

    Test Pack No. P&B Ref. No.

    Test Pressure (BarG) Chem. Clean Yes/ No

    Test Medium Hot Oil Flush. Yes/ No

    Test Duration (Hours) Location

    Sub System Description Print Date

    Check Record No. L27CR CRITICAL COMPONENT REMOVAL & TEST PREPARATION Sheet 1 of 1

    S/N Description Yes No Remarks

    1 Pipeline Section: Nominal pipe size: 2 Site locations KP- (1) Valves set as indicated on pressure test specification 3 Spades and blinds fitted 4 Instruments removed or blocked 5 Check valve disc removed/jacked open 6 Valve opened for filling 7 Bolting checked 8 Special piping items removed 9 Temporary spools positioned

    10 Expansion/flexible joints removed 11 Cement mortar lining checked 12 Temporary supports positioned 13 Spring/variable support blocked 14 Pressure test specifications/drawings checked

    Remarks: (1) For items checked and accepted mark with thick (2) For not applicable items mark N/A Outstanding Punch List attached? ( Yes / No) Enclosure (list property)

    Description Completed By Approved By Accepted By Witnessed By INPUT

    Company / Dept RL Construction RL Quality MCL Quality Third Party / Regulatory WINPCS

    Name

    Signature

    Date

  • MCCR

    BANYU URIP PROJECT EPC 3

    System No. Sub System No. Discipline PIPING (PIPELINE)

    Test Pack No. P&B Ref. No.

    Test Pressure (BarG) Chem. Clean Yes/ No

    Test Medium Hot Oil Flush. Yes/ No

    Test Duration (Hours) Location

    Sub System Description Print Date

    Check Record No. L28CR PIPELINE GAUGING INSPECTION Sheet 1 of 1

    S/N Description Yes No Remarks

    1 Pipeline Section: Nominal pipe size: 2 Section Length: m from KP to KP 3 Section geometric volume (1): m3 Reference dwg.: 4 Reference Drawings / specifications: 5 Pipeline inside diameters: mm 6 Gauging plates: diameter mm thickness mm 7 Electronic gauging devices: required not required 8 Pressure trend during gauging devices run: :required not required 9 Visual inspection of gauging plates after run: :accepted not accepted

    10 Dents: < mm 11 Ovality: < % 12 Penetration steps: < mm 13 For gauging detailed results see: 14 Gauging results: accepted not accepted

    Remarks: (1) Based on drawing data Outstanding Punch List attached? ( Yes / No) Enclosure (list property)

    Description Completed By Approved By Accepted By Witnessed By INPUT

    Company / Dept RL Construction RL Quality MCL Quality Third Party / Regulatory WINPCS

    Name

    Signature

    Date

  • BANYU URIP PROJECTEPC3 Onshore Export Pipeline System

    PRESSURE TEST ACCEPTANCE REPORT

    THIS IS TO CERTIFY THAT THE PIPELINE SECTION BELOWWAS HYDROSTATICALLY TESTED,IN ACCORDANCEWITH CLEANING, HYDROSTATIC TEST PROCEDUREDoc No :

    SUMMARY

    Project :Company :Main Contractor :Test Contractor :Pipeline Length :Pipe Diameter :Pipe Wall Thickness :Pipe Material :Pipeline Section :From : Location :To : Location :Gauging Run :Line Volume Water :Cathodic Protection :Design Pressure :Test Pressure (min) :Test Pressure (max) :Actual Test Pressure :Type & Source of the TestMethode

    :

    Test Started : Time & Pressure: Date:Test Ended : Time & Pressure: Date:Holding Time :Section Leaking :Loc. & Type of Failure :

    Section Accepted :

    REMARKS

    NAME SIGN DATE

    Farrel Internusa Pratama

    Hafar Daya Konstruksi

    RLC Completions Group

  • Section : Report No : Location : Page :

    Date :

    1 2DWT-2 Gauge

    EPC3 : Offshore Export Pipeline System Banyu Urip Project

    Ref. No. C3207106

    Pressure Test Report - Tightness Test

    RecorderNo. TIME

    Pressures (Psi) Temperatures (F)

    RemarksGaugeRecorder DWT-1

    Prepared by,Farrel Internusa Pratama

    Name :Date :

    Witnessedby,Hafar Daya Konstruksi

    Name :Date :

    Reviewed & Confirmed by,RLC Completions Group

    Name :Date :

  • Section : Report No : Location : Page :

    Date :

    Counter Total Flow rate Temp.m3 m3 m3/h Water

    C

    EPC3 : Offshore Export Pipeline System Banyu Urip Project

    Ref. No. C3207106

    Chemical Inhibitor Addition Report

    Time Remarks

    Prepared by,Farrel Internusa Pratama

    Name :Date :

    Witnessedby,Hafar Daya Konstruksi

    Name :Date :

    Reviewed & Confirmed by,RLC Completions Group

    Name :Date :

  • Section : Report No : Location : Page :

    Date :

    1 2Gauge Recorder

    Record Sheet

    No. TIME

    Pressures (Psi) Temperatures (F)

    RemarksGaugeRecorder DWT-1 DWT-2

    Pressure & Temperature Variation

    EPC3 : Onshore Export Pipeline System Banyu Urip Project

    Ref. No. C3207106

    Prepared by,Farrel Internusa Pratama

    Name :Date :

    Witnessedby,Hafar Daya Konstruksi

    Name :Date :

    Reviewed & Confirmed by,RLC Completions Group

    Name :Date :

  • Section : Report No : Location : Page :

    Date :

    Counter Total Flow rate Temp.m3 m3 m3/h Water

    C

    EPC3 : Offshore Export Pipeline System Banyu Urip Project

    Ref. No. C3207106

    Water Filling Report

    Time Remarks

    Prepared by,Farrel Internusa Pratama

    Name :Date :

    Witnessedby,Hafar Daya Konstruksi

    Name :Date :

    Reviewed & Confirmed by,RLC Completions Group

    Name :Date :

  • Report No.: :Date :Line Dia :

    - From KP : To KP :- From Joint No : To Joint No :- NDT Cleared : YES or NO- Back Filling Completed : YES or NO- FJC Completed : YES or NO- Any Hot Work Pending : YES or NO

    CLEARANCE FOR HYDROTESTING

    THIS IS TO CERTIFY THAT ALL WELDS OF THE ABOVE TEST SECTION HAVE BEEN ACCEPTED AND THEPIPELINE SECTION HAS BEEN LAID & BACKFILLED ACCORDING TO THE SPECIFICATIONS, AS PER THE

    ATTACHED DOCUMENTS:

    THE ABOVE LINE IS RELEASE FOR HYDROSTESTING

    BANYU URIP PROJECTEPC3 OFFSHORE EXPORT PIPELINE SYSTEM

    Sign Sign Sign

    Name Name Name

    Date Date Date

    THE ABOVE LINE IS RELEASE FOR HYDROSTESTING

    PREPARED BYFarrel Internusa Pratama

    REVIEWED & CONFIRMED BYRLC Completions Group

    WITNESSED BYHafar Daya Konstruksi

  • Attachment 10Velocity Pigs, Chemical, Dyes & Drop Pressure-Temperature Calculation

  • 1 VOLUME OF WATER REQUIRED TO FILL PIPELINE

    OD = Outside Diameter= 508 mm= 0.508 m

    WT = Wall Thickness= 12.7 mm= 0.0127 m

    ID = Inside Diameter= 482.6 mm= 0.4826 m

    Lpipeline = Pipeline Length Section II= 23295 m

    Llaunching head = Pipeline Length Section III= 8.5 m

    Lrecieving head = Total Length Test Header= 8.5 m

    L = Total Length= 23312.00

    V = Area X Length= A * L

    A = r2

    = 0.182921828 m2

    V = 4264.273647 m3= 4264273.647 ltr

    2 TEST PRESSURE & HOOP STRESSHoop Stress (Sh) Calculation :Maximum Allowable Test Pressure = 90 % SMYS (54.000 psi)SMYS of APL 5L X60 = 60.000 PSI

    Sh = P*D/2*t Sh 90 SMYS= 33,758 ( Ratio Hoop Stress 62.51%)

    Where :P = Test Pressure

    = Pd * 1.25= 1688 Psi

    Pd = Design Pressure= 1350.3 Psi

    D = Outside Diameter= 0.508 m

    t = Wall thickness= 0.0127 m

  • 3 THEORITICAL VALUE DV/DP

    V = Volume of the pipeline diameter, D (gallons)= 4264274 liter= 938009 gallons

    D = Outside diameter of pipe (in)= 20 in

    E = Elastic modulus of steel pipe= 3.00E+07 psi

    t = Wall thickness of pipe= 12.7 mm= 0.500 in

    v = Poissons ratio of steel pipe= 0.3

    B = Bulk Modulus of test media= 3.39E+05 psi

    DVDP

    = V

    = 938009*[(20/30000000*0.5)(1-0.32)+ (1/3.39E+ 05)]= 3.91 gallons/psi

    The Field Value (DV/DP) , will be perform asper section 14.5.2 item (a) and acceptance criteriaasper section 14.5.2 item (b).

  • 4 PRESSURE CHANGE DUE TO TEMPERATURE CHANGE

    = kPa/C= psi/oC

    Where : = Coeffisien of Liniear expansion of steel, /oC1.17E-05

    = Volumetric Expansion Coeffisien of Water,/oC= 0.000296

    B = Bulk Modulus of Water, bar= 23373 bar= 2337310 kpa

    v = Poisson Ratio0.3

    D = Pipeline Outside Diameter, m0.508

    E = Young's Elastic Modulus of Steel, kpa

    63.73439.41

    E = Young's Elastic Modulus of Steel, kpa2.07E+08

    t = Wall Thickness, m0.0127 m

    T = Incremental Temperature, oCP = Incremental Pressure, kpaP = Pressure, kpa

    = 1688 psi= 11638 kpa

    T = Temperature, K28 oC (assum)301.2 oK

  • Water Filling

    OD Pipeline (D) 20 = 0.508 meterWall Thickness (WT) 12.7 = 0.0127 meterID Pipeline (D) 0.48 = 0.2413 meterLength (L) include test header end = 23312 meterArea (A) = 0.182921828 meterVolume (V) = 4264.27 meterFlow Rate (Q) = 5000 ltr/minVelocity (v) = 27.33 m/min

    = 0.46 m/s= 1640.04 m/h

    Duration (t) = 14.21 hour= 0.59 day

    1 ppm = 1/1 million = 0.000001700 ppm = 0.0007

    Volume of pipeline = 4264.27365 m3

    4264273.647 liter

    Corrosion Inhibitor need = 4264273 x 0.0007= 2984.99 liter= 2.98 m3

    Filling Pump Capacity = 5000 ltr/minInjection Rated for Corrosion Inhibitor = 2984.99

    4264273= 3.5 ltr/min

    1 ppm = 1/1 million = 0.00000115 ppm = 0.000015

    Volume of pipeline = 4264.27365 m3

    4264273.647 liter

    Fluorescein dye needed = 4264273 x 0.000015= 63.96 liter= 0.06 m3

    Filling Pump Capacity = 5000 ltr/minInjection Rate for Fluorescein dye = 63.96

    4264274= 0.075 ltr/min

    7 FLUORESCEIN DYES CALCULATIONFOR OFFSHORE PIPELINE

    x 5000 ltr/min

    5FOR OFFSHORE PIPELINEVOLUME, VELOCITY & DURATION CALCULATION

    x 5000

    6CORROSION INHIBITOR CALCULATION

    ltr/min

    FOR OFFSHORE PIPELINE

  • 8 PRESSURE CHANGE DUE TO TEMPERATURE CHANGE

    = bar/oC= psi/oC

    Where : = Coeffisien of Liniear expansion of steel, /oC1.17E-05

    = Volumetric Expansion Coeffisien of Sea Water,/oC= 0.000286

    B = Bulk Modulus of Seawater, bar= 22509 bar

    v = Poisson Ratio0.3

    D = Pipeline Outside Diameter, m0.508

    E = Young's Elastic Modulus of Steel, kpa

    78.235.40

    3

    E = Young's Elastic Modulus of Steel, kpa2.07E+08

    t = Wall Thickness, m0.0127 m

    T = Incremental Temperature, oCP = Incremental Pressure, barP = Pressure, bar

    = 1688 psi Drop 0.2% = 1350 psi= 116 bar = 93.2 bar

    T = Temperature, K28 oC (assum)

  • Attachment 11MSDS Corrosion Inhibitor

  • REVISION DATE / TANGGAL REVISI: May 2009

    Page 1 of 5

    MATERIAL SAFETY DATA SHEET (MSDS) LEMBAR DATA KESELAMATAN

    MULTITREAT 5549 R A COMBINATION OF CORROSION INHIBITOR, BIOCIDE & OXYGEN SCAVENGER

    1. IDENTIFICATION OF THE SUBSTANCE / PREPARATION AND THE COMPANY NAMA PRODUK DAN PERUSAHAAN

    PRODUCT NAME: MULTITREAT 5549 R Nama Produk PART No. : MT 5549 R No. SUKU CADANG SUPPLIER : PT Clariant Indonesia PEMASOK Gatot Subroto Km 4, Jl Kalisabi No. 1 Tangerang 15138, Bandung 15138 INDONESIA TEL : 021 553 8589 / 553 8590 FAX : 021 557 93079

    2. COMPOSITION / INFORMATION ON INGREDIENTS KOMPOSISI / INFORMASI TENTANG BAHAN

    INGREDIENT NAME EC No. CAS No CONTENTS CLASSIFICATION NAMA UNSUR No. EC No. CAS KANDUNGAN KLASIFIKASI

    AMMONIUM BISULPHITE 10-30% 233-469-7 10192-30-0 10-30 % Xi; R36/37/38. R31.

    COCOALKYLMETHYLBENZYL 10-30 % Xn;R22. C;R34. AMMONIUM CHLORIDE

    The Full Text for all R-Phrases are Displayed in Section 16/ Uraian lengkap tentang R-Phrases tertera pada bagian 16

    3. HAZARDS IDENTIFICATION / IDENTIFIKASI BAHAYA

    Contact with acids liberates toxic gas/ Kontak dengan asam dapat menghasilkan gas yang toksik Causes burns/ Berakibat luka bakar

    CLASSIFICATION / Klasifikasi C;R34. R31

    4. FIRST AID MEASURES /TINDAKAN PERTOLONGAN PERTAMA

    INHALATION/ PERNAFASAN Fresh air and rest/ Berikan udara segar dan istirahatlah. Get medical attention if any discomfort continues/ Berikan bantuan medis jika sakit berlanjut. In contact with acids this product may liberate toxic gas/ Jika kontak dengan asam dapat menghasilkan gas toksik. If inhaled seek medical attention/ Jika terhirup segera dapatkan bantuan medis

    INGESTION/ PENCERNAAN Rinse nose, mouth and throat with water/ Cuci hidung, mulut dan tenggorokan dengan air. DO NOT INDUCE VOMITING! NEVER MAKE AN UNCONSCIOUS PERSON VOMIT OR DRINK FLUIDS!/ Jangan induksi untuk dimuntahkan! Jangan pernah membuat orang yang pingsan untuk muntah atau minum air Get medical attention immediately!/ Segera dapatkan bantuan medis

    SKIN CONTACT/ KULIT Immediately remove contaminated clothing/ Segera tanggalkan pakaian yang terkontaminasi. Rinse immediately with plenty of water/ Cuci segera dengan sejumlah air Get medical attention immediately/ Dapatkan segera bantuan medis

  • REVISION DATE / TANGGAL REVISI: May 2009

    Page 2 of 5

    MULTITREAT 5549 R

    EYE CONTACT/ MATA Make sure to remove any contact lenses from the eyes before rinsing/ Pastikan untuk melepaskan lensa kontak sebelum mata dicuci. Promptly wash eyes with plenty of water while lifting the eye lids/ Segera cuci mata dengan sejumlah air ketika kelopak mata dibuka. Get medical attention immediately/ Segera dapatkan bantuan medis. Continue to rinse/ Lanjutkan mencuci

    5. FIRE-FIGHTING MEASURES / TINDAKAN PEMADAMAN KEBAKARAN

    EXTINGUISHING MEDIA Use : Foam, Carbon dioxide (CO2). Dry Powder. Water spray MEDIA PEMADAM Gunakan Busa, Karbon Dioksida (CO2), tepung, semprotan air.

    SPECIFIC HAZARDS Fire creates: Hydrogen chloride (HCl). Nitrous gases (NOx). ZAT BERBAHAYA YANG MUNGKIN TIMBUL Sulphurous gases (SOx)/ Adanya api dapat menimbulkan: Hidrogen Klorida, Gas-gas Nitrat, Gas-gas Sulfur

    PROTECTIVE MEASURES IN FIRE Full protective equipment including suitable respiratory protection ALAT PELINDUNG KETIKA DARI API Alat pelindungan lengkap termasuk alat pelindung pernafasan

    6. ACCIDENTAL RELEASE MEASURES / MENANGANI TUMPAHAN

    PERSONAL PRECAUTIONS: Wear suitable protective clothing to prevent skin contact. Use TINDAKAN PERLINDUNGAN DIR respiratory protection in confined areas/ Gunakan perlengkapan

    pelindung untuk menhindari kontak dengan kulit. Gunakan pelindung pernapasan.

    ENVIRONMENTAL PRECAUTIONS: Take appropriate steps to prevent discharges to drains and TINDAKAN PERLINDUNGAN TERHADAP LINGKUNGAN watercourses. Causes depletion of oxygen in watercourses/ Ambil

    langkah tepat untuk mencegah pembuangan ke saluran air bersih. Menyebabkan kurangnya oksigen dalam aliran air

    SPILL CLEANUP METHODS : Wear necessary protective equipment. Stop leak if possible without CARA MEMBERSIHKAN TUMPAHAN risk. Ventilate well. Do not contaminate water sources or sewer.

    Inform Authorities if large amounts are involved. Absorb in vermiculite, dry sand or earth and place into containers. Flush with plenty of water to clean spillage area. Do not let washing down water contaminate ponds or waterways.

    Gunakan alat pelindung yang diperlukan. Tutup kebocoran jika memungkinkan tanpa menimbulkan resiko. Jangan sampai tumpahan masuk ke sumber air bersih Beritahu pihak berwenang jika bahan yang tumpah cukup banyak Serap dengan vermiculite, pasir kering atau tanah, dan masukkan kedalam kontainer. Guyur dengan air yang banyak untuk membersihkan permukaan yang kena tumpahan. Jangan biarkan biarkan air bekas pencucian mengalir ke selokan.

    7. HANDLING AND STORAGE / PENANGANAN DAN PENYIMPANAN

    USAGE PRECAUTIONS Avoid spilling, skin and eye contact. PENGAMANAN PENGGUNAAN Jaga jangan sampai tumpah mengenai kulit atau mata.

    STORAGE PRECAUTIONS Store in tightly closed original container in a cool, dry well-ventilated PENGAMANAN PENYIMPANAN place. Do NOT use container made of: polyethylene Mild Steel. Simpan dalam kontainer yang tertutup erat,di tempat yang sejuk dan

    berventilasi. Jangan gunakan kcontainer terbuat dari polyethylene Mild Steel.

    8. EXPOSURE CONTROLS / PERSONAL PROTECTION PENGENDALIAN PAPARAN DAN PERLINDUNGAN DIRI

    PROTECTIVE EQUIPMENT HAND GLOVES = SARUNG TANGAN, ALAT PELINDUNG Impermeable material/ Bahan Kedap Air

    FACE SHIELD = ALAT PELINDUNG WAJAH Use approved safety goggles or face shield/ Gunakan alat pengaman

    mata yang disetujui atau pelindungan wajah ENGINEERING MEASURES Provide adequate general and local exhaust ventilation. UKURAN TEKNIK Sediakan alat ventilasi yang memadai

  • REVISION DATE / TANGGAL REVISI: May 2009

    Page 3 of 5

    MULTITREAT 5549 R

    OTHER PROTECTION Wear appropriate clothing to prevent any possibility of skin contact. ALAT PELINDUNG LAINNYA Kenakan pakaian pelindung yang sesuai untuk melindungi

    Kemungkinan kotak dengan kulit

    HYGIENE MEASURES When using do not eat, drink or smoke. DO NOT SMOKE IN UKURAN KEBERSIHAN WORK AREA! Wash at the end of each work shift and before eating,

    smoking and using the toilet. Promptly remove any clothing that becomes contaminated. Wash promptly if skin becomes contaminated. Use appropriate skin cream to prevent drying of skin./ Ketika menggunakan, jangan sambil makan, minum atau merokok. JANGAN MEROKOK DI DAERAH KERJA! Cuci setiap selesai kerja dan sebelum makan, merokok dan gunakan toilet. Segera tanggalkan semua pakaian yang terkontaminasi. Cuci segera jika kulit terkontaminasi. Gunakan krim kulit yangtepat untuk menghindari kulit menjadi kering.

    9. PHYSICAL AND CHEMICAL PROPERTIES / SIFAT SIFAT FISIKA DAN KIMIA

    APPEARANCE: Liquid/Cair. PENAMPAKAN

    COLOUR/WARNA : Clear Colourless to Yellow Greenish./ Bening tidak berwarna sampai Kuning kehijauan ODOUR / TASTE, BAU/RASA Mild (or faint). Sulphur dioxide. / Tajam. Sulfur dioksida

    SOLUBILITY DESCRIPTION Soluble in Water / Larut dalam Air KELARUTAN

    SPECIFIC GRAVITY (WATER=1): 1.00 1.10 @ 25 deg C BERAT JENIS ( AIR = 1 )

    PH VALUE, 10% SOLUTION IN WATER 4 - 7 TINGKAT KEASAMAN, 10% LARUTAN DALAM AIR

    VISCOSITY (@ 25oC): < 50 cps @ 25 C VISKOSITAS

    FLASH POINT (C) / TITIK NYALA > 61 CC (Closed cup).

    10. STABILITY AND REACTIVITY/ KESTABILAN DAN KEREAKTIFAN

    STABILITY / KESTABILAN: No particular stability concerns/ Tidak ada masalah stabilitas yang perlu diperhatikan.

    MATERIALS TO AVOID Oxidising agents and acids BAHAN BAHAN YANG HARUS DIHINDARKAN Zat Pengoksidasi dan asam

    HAZARDOUS DECOMPOSITION PRODUCTS Contact with acids liberates toxic gas. Sulphurous gases HASIL DEKOMPOSISI PRODUK YANG BERBAHAYA (SOx)/ Kontak dengan asam dapat menghasilkan gas toksik. Sufur

    Gas

    11. TOXICOLOGICAL INFORMATION / INFORMASI TOKSIKOLOGI

    INHALATION : Contact with acids liberates toxic gas. PERNAFASAN Kontak dengan asam menghasilkan gas toksik

    INGESTION Causes burns. PENCERNAAN Berakibat luka bakar.

    SKIN Causes burns. KULIT Berakibat luka bakar.

    EYES : Causes burns. MATA Berakibat luka bakar

  • REVISION DATE / TANGGAL REVISI: May 2009

    Page 4 of 5

    12. ECOLOGICAL INFORMATION / INFORMASI EKOLOGI

    MULTITREAT 5549 R

    ECOTOXICITY/ EKOTOKSISITAS Causes depletion of oxygen in watercourses/ Menyebabkan berkurangnya oksigen dalam sumber air bersih Degrades to form sulphates in the natural environment/ Degradasi dari zat-zat sulfat yang ada di lingkungan Harmful to aquatic organisms, may cause long term adverse effects in the aquatic environment/ Berbahaya bagi organisme air, dapat menyebabkan efek timbale balik jangka panjang dalam lingkungan air.

    LC50, 96 hr, Prawn (Panaeus monodon) 1202.898 ppm (Bogor Labs, 2007)

    BIOACCUMULATION / BIOAKUMULASI Log Pow < 3

    DEGRADABILITY/ PENGURAIAN Readily Biodegradable/ Segera terbiodegradasi; >60%

    13. DISPOSAL CONSIDERATIONS / PERTIMBANGAN PEMBUANGAN

    DISPOSAL METHODS : Dispose of in accordance with Local Authority requirements METODE PEMBUANGAN Membuang limbah harus mengikuti peraturan setempat.

    14. TRANSPORT INFORMATION / INFORMASI TENTANG TRANSPORT

    LABEL FOR CONVEYANCE LABEL UNTUK PENGANGKUTAN .

    CORROSIVE

    UK ROAD CLASS/ KELAS DARAT UK: 8

    PROPER SHIPPING NAME/ NAMA PENGAPALAN: Corrosive liquid N.O.S (alkyl dimethyl benzyl ammonium chloride/ Larutan Korosif

    UN No ROAD/ No. UN DARAT : 1760

    UK ROAD PACK. GR./ GRUP PENGEPAKAN DARAT UK: III

    ADR CLASS No : Class 8: Corrosive Substances/ Kelas 8: Zat Korosif

    HAZARD No. (ADR) 80 Corrosive or slightly / 80 Bahan korosif atau sedikit korosif KELAS BAHAYA

    HAZCHEM CODE/ KODE HAZCHEM : 2X UN No. SEA/ No. UN LAUT: 1760

    IMDG CLASS/ KELAS IMDG: 8

    IMDG PACK. GR/ KELAS PENGEPAKAN IMDG: III EMS: F-A, S-B

    UN No. AIR/ No. UN UDARA: 1760 ICAO CLASS/ KELAS ICAO: 8

    AIR PACK. GR/ GRUP PENGEPAKAN UDARA: III

    15. REGULATORY INFORMATION / INFORMASI TENTANG PERATURAN

    LABEL FOR SUPPLY LAMBANG UNTUK PASOKAN

    CORROSIVE

    CONTAINS/ KANDUNGAN QUATERNARY AMMONIUM CHLORIDE

    RISK PHRASES: R31 Contact with acids liberates toxic gas/ Kontak dengam asam dapat

  • REVISION DATE / TANGGAL REVISI: May 2009

    Page 5 of 5

    URAIAN RESIKO

    menghasilkan gas yang toksik

    R34 Causes burns/ Berakibat luka bakar

    MULTITREAT 5549 R

    SAFETY PHRASES: S26 In case of contact with eyes, rinse immediately with plenty of water and URAIAN KESELAMATAN seek medical advice/ Jika terkena mata, segera cuci dengan air yang banyak dan dapatkan bantuan medis.

    S45 In case of accident or if you feel unwell, seek medical advice immediately (show label where possible)/Jika terjadi kecelakaan atau anda merasa tidak enak, segera konsultasikan dengan tenaga medis (tunjukkan lambang jika memungkinkan)

    S24/25 Avoid contact with skin and eyes. Hindari kemungkinan kena kulit dan mata

    S36/37/39 Wear suitable protective clothing, gloves and eye/face protection. Gunakan pakaian pelindung, sarung tangan dan pelindung mata/muka.

    S60 This material and its container must be disposed of as hazardous waste. Bahan ini dan kontainernya harus dibuang sebagai limbah berbahaya

    16. OTHER INFORMATION / INFORMASI LAIN

    ISSUED BY : SPS DIKELUARKAN OLEH

    REVISION DATE : May 2009 TANGGAL REVISI

    REVISION No./REPLACES SDS ISSUED : Rev 0 NO REVISI / MENGGANTIKAN YANG SEBELUMNYA

    SDS No. O 960

    ISSUED IN BILANGUAGE BY SPS DIKELUARKAN DALAM DUA BAHASA OLEH

    DATE / TANGGAL May 2009

    RISK PHRASES IN FULL Harmful if swallowed. R22 Berbahaya jika tertelan Contact with acids liberates toxic gas. R31 Kontak dengan asam dapat menghasilkan gas yang toksik Causes burns. R34 Berakibat Luka Bakar Irritating to eyes, respiratory system and skin. R36/37/38 Iritasi bagi mata, system pernafasan dan kulita Very Toxic to aquatic organisms R50. Sangat beracun bagi organisme air

    DISCLAIMER / PERNYATAAN PELEPASAN TANGGUNG JAWAB THIS INFORMATION RELATES ONLY TO THE SPECIFIC MATERIAL DESIGNATED AND MAY NOT BE VALID FOR SUCH MATERIAL USED IN COMBINATION WITH ANY OTHER MATERIALS OR IN ANY PROCESS. SUCH INFORMATION IS, TO THE BEST OF THE COMPANYS KNOWLEDGE AND BELIEF, ACCURATE AND RELIABLE AS OF THE DATE INDICATED. HOWEVER, NO WARRANTY, GUARANTEE OR REPRESENTATION IS MADE AS TO ITS ACCURACY, RELIABILITY OR COMPLETENESS. IT IS THE USERS RESPONSIBILITY TO SATISFY HIMSELF AS TO THE SUITABILITY OF SUCH INFORMATION FOR HIS OWN PATICULAR USE.

    INFORMASI INI HANYA BERKAITAN DENGAN BAHAN TERTENTU YANG DISEBUTKAN DAN TIDAK BERLAKU PADA BAHAN YANG DIGUNAKAN DENGAN PERPADUAN DENGAN BAHAN-BAHAN LAINNYA ATAU DI DALAM PROSES APAPUN JUGA. INFORMASI INI SEPENGETAHUAN DAN MENURUT KEYAKINAN PERUSAHAAN, AKURAT DAN BISA DIPERCAYA PADA TANGGAL YANG DISEBUTKAN. AKAN TETAPI, TIDAK ADA JAMINAN, GARANSI ATAU PERNYATAAN-PERNYATAAN YANG DIBERIKAN SEHUBUNGAN DENGAN AKURASINYA, KEHANDALANNYA ATAU KELENGKAPANNYA. TANGGUNG JAWAB PEMAKAI UNTUK MENGUSAHAKAN SENDIRI SEHUBUNGAN DENGAN KECOCOKAN INFORMASI UNTUK PENGGUNAANNYA SENDIRI YANG KHUSUS.

  • This information corresponds to the present state of our knowledge and is intended as a general description of our products and their possible applications. Clariant makes no warranties, express or implied, as to the informations accuracy, adequacy, sufficiency or freedom from defect and assumes no liability in connection with any use of this information or of any product, method or apparatus mentioned. Any user of this product is responsible for determining the suitability of Clariant's products for its particular application. NO WARRANTY IS MADE OF THE MERCHANTABILITY OR FITNESS FOR USE OF ANY PRODUCT, AND NOTHING INCLUDED IN THIS INFORMATION WAIVES ANY OF CLARIANTS GENERAL TERMS AND CONDITIONS OF SALE, WHICH CONTROL UNLESS IT AGREES OTHERWISE IN WRITING. Any existing intellectual/industrial property rights must be observed. Due to possible changes in our products and applicable national and international regulations and laws, the status of our products could change. Material Safety Data Sheets providing safety precautions, that should be observed when handling or storing Clariant products, are available by request. You should obtain and review the applicable Material Safety Data Sheet information before handling any of these products. For additional information, please contact Clariant. Copyright Clariant International Ltd, 2009

    MULTITREAT 5549R is a product

    mark protected by Clariant in many

    countries.

    Clariant Oil Services

    www.oil.clariant.com

    PB-MULTITREAT 5549R-A4-February 13

    Product Bulletin

    MULTITREAT 5549R from Clariant Oil Services

    COMBINED BIOCIDE, CORROSION INHIBITOR and OXYGEN SCAVENGER

    Description:

    MULTITREAT 5549R is an aqueous solution of oxygen scavenger, biocide and corrosion inhibitor. It is based on a combination of ammonium bisulphite and quaternary amine chemistry, and is classified as readily biodegradable (>60% in 28 days). MULTITREAT 5549R has already been certified by Ditjen MIGAS Indonesia for hydro test application

    Application:

    MULTITREAT 5549R is used to prevent corrosion in oilfield pipelines and process facilities that are filled with water during hydrostatic testing operations or temporary mothballing of facilities. The product controls the propagation of corrosion-causing sulfate reducing bacteria (SRB). The treatment rate depends on the source of water used and the length of testing / mothballing. Typical doses for seawater: Product is injected at about 300 ppm dosages or diluted 3000 3500 times with water prior to injection. The treatment rate depends on the source of water used and the length of testing / mothballing. Typical doses for seawater are shown below: Duration of test Dose rate (ppm) < 3 months 300 500 3 12 months 500 700 1 5 years 700 1000

    Typical Properties*:

    A. Appearance (QPI 1) Clear Colourless to Yellow Greenish Liquid

    B. Specific Gravity @ 25C (QPI 2) 1.00 - 1.10

    C. pH Neat (QPI 3) 3.5 6.5

    D. Viscosity (QPI 4) < 50 cp