ID Task Name Duration InfoX % Complete Start Finish
1 Pre-Project 9 days 100% Mon 10/5/09 Thu 10/15/09
18 Project 53.25 days 14% Mon 10/5/09 Thu 12/17/09
19 Project Management 40 days 2% Mon 10/19/09 Fri 12/11/09
20 Project Timeline 40 days 0% Mon 10/19/09 Fri 12/11/09
21 Project Start 0 days 0% Mon 10/19/09 Mon 10/19/0922 Project Preparation 5 days 0% Mon 10/19/09 Fri 10/23/09
23 Plan 5 days 0% Mon 10/19/09 Fri 10/23/09
24 Blueprint 0 days 0% Fri 10/23/09 Fri 10/23/09
25 Analyze 0 days 0% Fri 10/23/09 Fri 10/23/09
26 Design 0 days 0% Fri 10/23/09 Fri 10/23/09
27 Realization 25 days 0% Mon 10/26/09 Fri 11/27/09
28 Build 15 days 0% Mon 10/26/09 Fri 11/13/09
29 Test 10 days 0% Mon 11/16/09 Fri 11/27/09
30 Final Preparation 5 days 0% Mon 11/30/09 Fri 12/4/09
31 Deploy 5 days 0% Mon 11/30/09 Fri 12/4/09
32 Release & Support 5 days 0% Fri 12/4/09 Fri 12/11/09
33 Go-Live 0 hrs 0% Fri 12/4/09 Fri 12/4/09
34 Support 5 days 0% Mon 12/7/09 Fri 12/11/09
35 Project Kickoff Meeting 1 day 100% Tue 10/20/09 Tue 10/20/09
36 Kickoff Meeting 1 day 100% Tue 10/20/09 Tue 10/20/09
37 Milestone: Kickoff Meeting Complete 0 days 100% Tue 10/20/09 Tue 10/20/09
38 Application 50.25 days 12% Mon 10/5/09 Mon 12/14/09
39 Project Preparation 14 days 99% Mon 10/5/09 Fri 10/23/09
40 Plan 4 days 100% Mon 10/19/09 Fri 10/23/09
41 Phase Startup 1 min 100% Mon 10/19/09 Mon 10/19/09
42 Customer Data Review 3 days 100% Mon 10/19/09 Thu 10/22/09
43 Base Setup Review 1 day 100% Thu 10/22/09 Fri 10/23/09
44 Milestone: End of Project Preparation 0 days 0% Mon 10/5/09 Mon 10/5/09
45 Realization 32.25 days 8% Mon 10/26/09 Wed 12/9/09
46 Build 27.25 days 9% Mon 10/26/09 Wed 12/2/09
47 Phase Startup 1 min 100% Mon 10/26/09 Mon 10/26/09
48 Base Setup Configuration 3.75 days 0% Wed 11/4/09 Mon 11/9/09
49 Marketing 2.25 days 0% Wed 11/4/09 Fri 11/6/0950 Campaign Management 0.75 days 0% Wed 11/4/09 Wed 11/4/09
51 Base Setup Configuration 4 hrs 0% Wed 11/4/09 Wed 11/4/09
52 Unit Test 2 hrs 0% Wed 11/4/09 Wed 11/4/09
53 Lead Management 0.75 days 0% Wed 11/4/09 Thu 11/5/09
54 Base Setup Configuration 4 hrs 0% Wed 11/4/09 Thu 11/5/09
55 Unit Test 2 hrs 0% Thu 11/5/09 Thu 11/5/09
Task
SplitProgress
Milestone
SummaryProject Summary
External Tasks
External MilestoneDeadline
Page 1
Project: 3.2.020_Project Plan
Date: Thu 11/5/09
8/14/2019 ICON - Project Plan 05-Nov-09a
2/4
8/14/2019 ICON - Project Plan 05-Nov-09a
3/4
8/14/2019 ICON - Project Plan 05-Nov-09a
4/4