Upload
duongminh
View
342
Download
19
Embed Size (px)
Citation preview
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO ‘ANNEX 14 UPDATE’
(ICAO Annex 14 Volume II –Heliports)
WORKSHOP
Dr John W. Leverton
IFHA Representative to ICAO Aerodrome Panel
HAI Heliport Design Focal Point
Vice President Infrastructure Development, AHS
HELIPORT/HELIDECK DESIGN
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
IFHA
International Federation of Helicopter Associations
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ANNEX 14 Vol II WORKSHOP
Comments based on my involvement as the IFHA Representative to the ICAO Aerodrome Panel (AP), the Heliport Design Working Group (HDWG), the Visual Aids Working Group (VAWG) and associated Sub-groups …. …. and Rapporteur of the HDWG Visual Aids Sub-group (VASG).
COMMENTS SHOULD NOT BE TAKEN AS STATEMENT OF ACTUAL ICAO POLICY OR WHAT WILL APPEAR IN THE
NEW ‘TRANCHE 2’ ICAO ANNEX 14 VOLUME II - HELIPORT DESIGN TO BE ISSUED IN 2011 (or 2012!!)
THE VIEWS EXPRESSED ARE MY OWN AND MUST NOT BE TAKEN AS BEING REPRESNTATIVE OF THOSE OF THE
ICAO HDWG, IFHA, HAI OR AHS.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO ‘ANNEX 14 UPDATE’
(ICAO Annex 14 Volume II –Heliports)
WORKSHOP # 1
Dr John W. Leverton
IFHA Representative to ICAO Aerodrome Panel
HAI Heliport Design Focal Point
Vice President Infrastructure Development, AHS
HELIPORT/HELIDECK DESIGN
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO ANNEX 14 Vol IIHELIPORTS
(Heliport/Helideck/Shipboard Heliport Design)
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO ANNEX 14: VOLUME II – HELIPORTS
New ‘Tranche 1’ Annex 14 = THIRD EDITION – JULY 2009
2004 Annex 14 = SECOND EDITION – Amendment 3 – July 2004
***********************
FAA Advisory Circular (AC) 150-5390-2B (2004)
= AC-2B
PRESENTATION TERMINLOGY
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Annex 14 UPDATE PROGRESS
HDSG formed late 2003
HDSG/1 Meeting May 2004 [AP formed Dec 2004]
HDWG/1 Meeting June 2005
[Agreed changes should be addressed in 2 parts – tranche 1 and 2]
HDWG/2 – June 2006
First set of changes (Tranche 1) agreed at HDWG/2 (June 2006) –
Changes endorsed by the „WG of the Whole‟ at WGoTH/3 meeting
(August 2006)
Approved by Aerodrome Panel at AP/1 December 2006.
Tranche 1 Changes approved by ICAO ANC May 2007
ICAO „State Letter‟ ** issued with „Tranche 1 changes‟ August 2007.
** State Letter included also changes to Annex 14 Volume 1 related to Aerodromes
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
CURRENT STATUS
Updated Annex 14 Volume II – Heliports (Tranche 1)
.......... Issue July 2009:
................applicability date 19 November 2009!
Note: Some ‘helideck requirements’ have later applicability date of 2012
HDWG now finalizing ‘Tranche 2’ Changes
ICAO AP/2 to address ‘tranche 2’ changes, originally planned for 2009, now October 2010.
HDWG planning to ‘start work’ on updating the ICAO Heliport Design Manual (Doc 9261) in 3rd Quarter of 2010 ? – this is of major importance since Manual will detail how to apply ‘Annex 14 Volume II’
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
CURRENT STATUS
Updated Annex 14 Volume II – Heliports (Tranche 1)
.......... Issue July 2009:
................applicability date 19 November 2009!
Note: Some ‘helideck requirements’ have later applicability date of 2012
HDWG now finalizing ‘Tranche 2’ Changes
ICAO AP/2 to address ‘tranche 2’ changes, originally planned for 2009, now October 2010.
HDWG planning to ‘start work’ on updating the ICAO Heliport Design Manual (Doc 9261) in 3rd Quarter of 2010 ? – this is of major importance since Manual will detail how to apply ‘Annex 14 Volume II’
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Annex 14 STATUS
•Chapter 1: General (Definition) - main changes completed in ‘tranche 1’ - addition changes to be made in tranche 2 to cover ‘floating (pontoon) heliports’ etc., and to ensure requirements for VFM (VFR) heliports cover also heliports where an instrument
(Point in Space/PinS) approach is used.
•Chapter 2: Heliport Data – tranche 2 minor changes.
•Chapter 3: Physical Characteristics – main changes completed in ‘tranche 1’: someadditional changes and new term ‘FATO/TLOF’ for elevated heliports and helidecks to be made in tranche 2.
•Chapter 4: Obstacle Restriction and Removal (Airspace) : Study completed for VFM (VFR) heliports - to be issued as part of tranche 2.
•Chapter 5: Visual Aids (Markings & Lighting) - minor changes issued in tranche 1 –changes to ‘markings’ to be issued as part of tranche 2, lighting 40 % complete – still being ‘worked’ – changes to ‘lights’ to be made post-tranche 2.
•Chapter 6: Heliport Services (Fire Fighting) – being addressed by separate RFFWG
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Annex 14 Future Work
ICAO agreed –at AP1 (Dec 2006)- for Annex 14 to be reformatted to
make it easier to use – the existing and „new‟ text will be grouped in
the following Chapters:-
Chapter 1. General
Chapter 2. Surface-level Heliports
Chapter 3. Elevated Heliports
Chapter 4. Instrument Heliports
Chapter 5. Helidecks
Chapter 6. Shipboard Heliports and Winching Areas
... and each Chapter will consist of the following sections:-1. General
2. Heliport Data
3. Physical Characteristics
4. Obstacle Restriction and Removal
5. Visual Aids
5.1Marking
5.2Lights
6. Heliport Services
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Annex 14 Future Work
Annex 14 to be reformatted to make it easier to use – the existing and
„new‟ text will be grouped in the following Chapters:-
Chapter 1. General
Chapter 2. Surface-level Heliports
Chapter 3. Elevated Heliports
Chapter 4. Instrument Heliports
Chapter 5. Helidecks
Chapter 6. Shipboard Heliports and Winching Areas
... and each Chapter will consist of the following sections:-1. General
2. Heliport Data
3. Physical Characteristics
4. Obstacle Restriction and Removal
5. Visual Aids
5.1Marking
5.2Lights
6. Heliport Services
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO DOCUMENTS
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO DOCUMENTS
ICAO ANNEX 14: VOLUME II – HELIPORTS
THIRD EDITION – JULY 2009
HELIPORT MANUAL; THIRD EDITION – 1995
(DOC 9261 – AN/903)
RELATED DOCUMENTS
ICAO ANNEX 6, PART III INTERNATIONAL OPERATIONS –
HELICOPTERS: SIXTH EDITION – JULY 2004
ICAO ANNEX 14, VOLUME I – AERODROME DESIGN AND OPERATIONS –
JULY 1990
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO DOCUMENTS
ICAO ANNEX 14: VOLUME II – HELIPORTS
SECOND EDITION -- JULY 1995
[ AMENDMENT 2 (Minor change re Aeronautical Data): NOVEMBER 1997
ADMENTMENT 3 (Major Lighting Changes): NOVEMBER 2004
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO DOCUMENTS
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO DOCUMENTS
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO DOCUMENTS
ICAO Heliport Manual, which is out of date and incorrect in some sections folowing the issue of the Tranche 1 changes, needs to be updated: HDWG is starting work on the sections on helidecks … no specific plans for addressing heliports: aim to decide by 3rd
quarter of 2010…. even so a replacement will not be available for a number of years!!
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Silverstone Paris
‘Free Field‟ Performance Class 1*
„Elongated FATO‟ Performance Class 2 & 3*
* NOT ICAO terms
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Silverstone Paris
‘Free Field‟ Performance Class 1*
„Elongated FATO‟ Performance Class 2 & 3*
* NOT ICAO terms
Tranche 2 Proposal – to be called “Runway-type FATOs.”
Runway-type FATO. A FATO having characteristics similar in shape to a fixed wing
runway with a length-to-width ratio of at least 3:1.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ELEVATED HELIPORTS
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
JW
SURFACE LEVEL HELIORTS
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
HELIDECKS
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
SHIPBOARD HELIPORT
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Floating (Pontoon) Heliport Heliport on „structure‟ over water
Surface-level heliport. A heliport located on the ground or on
the water.
Tranche 2 Proposal:
Surface-level heliport. A heliport located on the ground or on
a structure on the surface of the water.
Elevated heliport. A heliport located on a raised structure on land
Tranche 2 Proposal:
Elevated heliport. A heliport located on a raised structure on land.
Proposed „Tranche 2‟ Definition Changes
Melbourne, Australia
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Safety
Area
FATO
TLOF
HELIPORT TERMINLOGY
FATO: Final Approach and Takeoff Area
TLOF: Touchdown and Liftoff Area
Can be any shape – usually square or round
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Safety
Area
FATO
TLOF/Central Zone
HELIPORT TERMINLOGY
FATO: Final Approach and Takeoff Area
TLOF: Touchdown and Liftoff Area
TLOF can be outside of FATO located in a helicopter stand
Protection Area
Helicopter Stand
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
PRESENTATION TERMINOLOGY
RD = ROTOR DIAMETER
D = „D-value‟ = OVERALL LENGTH (OL)
UCw = UNDERCARRIAGE WIDTH/LENGTH
PC1, PC2 & PC 3 is used to refer to heliports designed on
the assumption that they are “intended to be used by
helicopters operated in performance class 1” or
“performance class 2 and 3” respectively.
The „diagrams‟, although illustrating the approximate relative sizes are
NOT to scale - this is not stated on all diagrams.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
TDP
AEO
OEI200 ft
Reject T/O DistanceFATO
Safe forced landing – outside heliport
AEO OE
I200 ft
Safe forced landing – outside heliportFATO
FATO
AEO
PERFORMANCE CLASSIFICATIONS
PERFORMANCE CLASS 1
PERFORMANCE CLASS 2
PERFORMANCE CLASS 3
[Chart Based on Figures supplied by Jim Lyons]
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
US (FAA) AC150/5390-2B
FAA AC 150/5390-2B-2B (AC-2B) Heliport Design was issued on 9/30/04 (30 September 2004) and is available on a number of FAA and other web sites - the following is one useful web site to obtain the document:-
http://www.faa.gov/arp/publications/acs/5390-2/5390-2b.pdf
Hardcopies are NOT available from the FAA – they are available from a number of commercial suppliers at a fee.
NOTE: AC-2B is an “Advisory Circular” i.e. Guidelines … but is a Requirement for heliports which use Federal Funds and is a Requirements in a number of the US States.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
Annex 14/FAA
MAJOR DIFFERENCES
ICAO ANNEX 14 ~ FAA AC 150-5390-2B*
• ANNEX 14 BASED ON “OPERATIONAL
PERFORMANCE” REQUIREMENTS (HELICOPTER PERFORMANCE CLASS) DEFINED IN ANNEX 6
• FAA AC-2B BASED ON HELIPORT TYPE (USE).
• Main Technical Differences • Load Bearing Area Size Requirements**• Airspace Requirements
*Issued by FAA in September 2004.
** Differences between „Annex 14 Vol II‟ and FAA AC-2B are considerably less
as a result of the „tranche 1‟ changes.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
AIM•EXPLANATION OF TERMINOLOGY AND CONCEPTS USED IN
ICAO ANNEX 14 Vol II
•DISCUSSION AND OUTLINE OF :-
(i) Changes in Annex 14 „tranche 1‟ issued July 2009
(ii) Additional changes being considered by the ICAO HELIPORT
DESIGN WORKING GROUP (HDWG) for „tranche 2‟ .... and some
„Post-Tranche 2‟ changes.
(iii) Review of main differences between US/FAA Heliport Design AC
150/5390-2B (AC-2B) and „tranche 1‟ ICAO Annex 14 „standards and
recommended practices‟ (SARPS) for heliports
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
AIM•EXPLANATION OF TERMINOLOGY AND CONCEPTS USED IN
ICAO ANNEX 14
•DISCUSSION AND OUTLINE OF :-
(i) Changes in Annex 14 „tranche 1‟ to be issued April/May 2009
(ii) Additional changes being considered by the ICAO HELIPORT
DESIGN WORKING GROUP (HDWG) for „tranche 2‟.
(iii) Review of main differences between US/FAA Heliport Design AC
150/5390-2B (AC-2B) and „tranche 1‟ ICAO Annex 14 „standards and
recommended practices‟ (SARPS) for heliports
*** Tranche 2 Proposal – also cover heliports with PinS approaches
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
AIM•EXPLANATION OF TERMINOLOGY AND CONCEPTS USED IN
ICAO ANNEX 14
•DISCUSSION AND OUTLINE OF :-
(i) Changes in Annex 14 „tranche 1‟ to be issued April/May 2009
(ii) Additional changes being considered by the ICAO HELIPORT
DESIGN WORKING GROUP (HDWG) for „tranche 2‟.
(iii) Review of main differences between US/FAA Heliport Design AC
150/5390-2B (AC-2B) and „tranche 1‟ ICAO Annex 14 „standards and
recommended practices‟ (SARPS) for heliports
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ELEVATED HELIPORTS
FATO AND TLOF ARE “COINCIDENTAL” *
(i.e. SAME SIZE – 1D or 0.83 D)… and FATO IS DLB.
DLB = Dynamic Load Bearing **
* Also applies to Helidecks
** Currently difference in DLB requirements:
FAA 1.5 x MTOW Annex 14 2.5 x MTOM
[Both applied through 2 points of contact.]
Covered in Heliport Manual – NOT addressed in Annex 14 – not reviwed to date by HDWG or any Sub-group.
ICAO/International MTOM (Max Takeoff Mass) = US MTOW (Max Takeoff Weight)
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ELEVATED HELIPORTS
FATO AND TLOF ARE “COINCIDENTAL” *
(i.e. SAME SIZE – 1D or 0.83 D)… and FATO IS DLB.
DLB = Dynamic Load Bearing **
* Also applies to Helidecks
** Currently difference in DLB requirements:
FAA 1.5 x MTOW Annex 14 2.5 x MTOM
[Both applied through 2 points of contact.]
Covered in Heliport Manual – NOT addressed in Annex 14 – not reviwed to date by HDWG or any Sub-group.
ICAO/International MTOM (Max Takeoff Mass) = US MTOW (Max Takeoff Weight)
Tranche 2 Proposal – new term FATO/TLOF
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
DIFFERENCES
AC-2B ANNEX 14
PARKING AREA = HELICOPTER STAND
HOVER-TAXI = AIR-TAXI
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO FRAMEWORK
• PPR (Private Use) Heliports Not Directly Considered In Annex 14 [Only Brief Reference To PPR Heliports Made In This Presentation]
• Annex 14 covers Hospital Heliports ** - Most European Nations consider Annex 14 Applies To All „Public Interest‟ Facilities including Hospital Heliports.
• “Europe” considers Hospital Heliports should be designed for Performance Class 1 operations –requirement of JAR OPS 3 …
... or with a DLB Area (FATO + Safety area) of 2D
** US/FAA considers HOSPITAL HELIPORTS are „PRIVATE USE‟
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
GENERAL
• PC2 and PC3 Heliports in ICAO Annex 14
corresponds to General Aviation Heliport in FAA
AC.
• PC1 Heliport in ICAO Annex 14 is approximately
the same as Transport Heliport in FAA AC … but is
Annex 14 based on PC1/Cat A performance rather
that dimensions related to size of helicopter as in
FAA AC-2B: in this case Annex 14 generally less
demanding and more logical than FAA AC-2B!
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
GENERAL
• PC2 and PC3 Heliports in ICAO Annex 14
corresponds to General Aviation Heliport in FAA
AC.
• PC1 Heliport in ICAO Annex 14 is approximately
the same as Transport Heliport in FAA AC … but
is Annex 14 based on PC1/Cat A performance
rather that dimensions related to size of helicopter
as in FAA AC-2B: Annex 14 generally less
demanding and more logical than FAA AC-2B!
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
PC2/PC3 Heliports
2004 Annex 14
- FATO is equivalent to TLOF in FAA AC
- TLOF of 1.5UC is similar to PPR ‘2UC paved portion
of the TLOF’.
‘New’ 2009 Tranche 1 ‘ Annex 14
– FATO and TLOF in general terms same as in FAA AC
HELIPORT TERMINOLOGY CHANGES
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO ANNEX 14 - HELIPORTS
• PERFORMANCE CLASS 1 (PC1)
• PERFORMANCE CLASS 2 & 3 (PC2/PC3)
NOTE: ICAO ANNEX 14 APPLIES TO SURFACE
(GROUND) LEVEL AND ELEVATED HELIPORTS
…….AND HELIDECKS
US/FAA USES AIRWORTHINESS CATORGIES – CAT A and CAT B. NO
FAA PERFORMANCE CLASS / CAT REQUIREMENTS RELATED TO
OPERATIONS AT HELIPORTS – SOME „TRANSPORT/CAT A
REQUIREMENTS‟ APPLIED IN CASE OF SCHEDULE OPERATIONS.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
PERFORMANCE
REQUIREMENTS
ICAO ANNEX 6*(JAR-OPS 3) US/FAA**
PERFORMANCE CLASS 1 CAT A
PERFORMANCE CLASS 2 CAT B***
PERFORMANCE CLASS 3 CAT B
*ANNEX 6: UPDATED/REVISED BY THE ICAO HELICOPTER TILTROTOR STUDY GROUP
(HTSG) – New version issued in 2007.
** CAT A (CATEGORY A) AND CAT B (CATEGORY B) ARE AIRWORTHINESS
CERTIFICATION DESIGNATIONS. –
*** PC 2 – AKIN TO “CAT B TAKEOFF AND LANDING + CAT A EN-ROUTE/CRUISE”: SOME
US/FAA CAT A/OEI EN-ROUTE REQUIREMENTS.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
TDP
AEO
OEI200 ft
Reject T/O DistanceFATO
Safe forced landing – outside heliport
AEO OE
I200 ft
Safe forced landing – outside heliportFATO
FATO
AEO
PERFORMANCE CLASSIFICATIONS
PERFORMANCE CLASS 1
PERFORMANCE CLASS 2
PERFORMANCE CLASS 3
[Chart Based on Figures supplied by Jim Lyons]
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
TDP
AEO
OEI200 ft
Reject T/O DistanceFATO
Safe forced landing – outside heliport
AEO OE
I200 ft
Safe forced landing – outside heliportFATO
FATO
AEO
PERFORMANCE CLASSIFICATIONS
PERFORMANCE CLASS 1
PERFORMANCE CLASS 2
PERFORMANCE CLASS 3
[Chart Based on Figures supplied by Jim Lyons]
„Cat A‟
„Cat A‟ Enroute - Cat B T/O + Land
„Cat B‟
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
PERFORMANCE CLASS 1
(FREE-FIELD) CAT. A.
ICAO Annex 14 FATO
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
„RESTRICTED FIELD LENGTH‟ CAT. A.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
PC1 GROUND SPACE
„Clearway‟: area to be protected – not required to be
load bearing
Free-field/Clear-area Cat A
FATO
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
„Clearway‟: area to be
protected – not required to
be load bearing
Area defined in the H/RFM
PC1 GROUND SPACE
Restricted Area/Short-field Cat A
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
IMPACT OF HELIDECK HEIGHT
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
IMPACT OF HELIPORT HEIGHT
„NO-Drop Down‟ for Scheduled!!
Ground Level
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
ICAO/FAA RELATIONSHIP?
ICAO FAA
PC 1 TRANSPORT
PC 2 GENERAL AVIATION*
PC 3 HOSPITAL
-----------------------------------------------------------------------------GROUND GROUND
ELEVATED ELEVATED
HELIDECKS [Not addressed by FAA]
* ALSO INCLUDES PRIVATE USE/PPR
NO DIRECT
ICAO ANNEX 14 – FAA AC
RELATIONSHIP
BUT ……
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
MAJOR DIFFERENCES
ICAO ANNEX 14 ~ FAA AC 150-5390-2B*
• ANNEX 14 BASED ON “OPERATIONAL
PERFORMANCE” REQUIREMENTS (HELICOPTER
PERFORMANCE CLASSES)
• FAA AC-2B BASED ON HELIPORT USE.
• MAIN TECHNICAL DIFFERENCES
• LOAD BEARING AREA REQUIREMENTS
• AIRPSACE REQUIREMENTS
* ISSUED BY FAA IN SEPTEMBER 2004.
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
GROUND SPACE FATO
• ICAO ANNEX 14* „LINKED‟ TO ICAO ANNEX 6
i.e. DESIGN REQUIREMENTS LINKED TO HELICOPTER PERFORMANCE CLASS (PERFORMANCE CLASS 1, 2 AND 3)
• FAA AC 150/5390-2B „RELATED‟ TO HELIPORT USE
GENERAL AVIATION [PRIVATE USE/PPR]
HOSPITAL
TRANSPORT **
i.e. NO DIRECT „LINK‟ BETWEEN DESIGN AND OPERATIONAL / PERFORMANCE REQUIREMENTS
** EXCEPTION IN THAT CONSIDERATION IS GIVEN TO OPERATIONAL PERFORMANCE NEEDS IN DESIGN OF „TRANSPORT HELIPORTS‟.
*AND ASSOCIATED HELIPORT MANUAL
Leverton Associates, Inc
ICAO ‘Annex 14 Update’ Workshop – HAI HeliExpo 2010
End of this section ….
…… MORE TO COME