IBC_PIM Locating Guide

Embed Size (px)

DESCRIPTION

PIM

Citation preview

  • Page 1,total 4

    IBC site PIM locating guide

    Permission:

    1. IBC site access permission

    2. Site DEA permission

    Engineers:

    1. Operator engineer (clearly with the diagram of the IBC system, and record the detailed

    operation steps)

    2. LMT operator (do the PIM test)

    After preparatory works are being completed, you can enter the actual investigation phase. Actual

    investigation follows the "segmented investigation, from near to far" principle. Points out every

    piece of RF path should contain multiple nodes, shown as below,

    Once operating can exclude multiple nodes determine the issue; IBC sites antenna systems are

    usually many nodes, one by one node investigation is very inefficient.

    BTS from near and far are based on the top, by the first part near BTS positioned away after

    positioning. Because RF path passive inter-modulation interference is characterized by higher

    transmit power, passive inter-modulation interference generated by the stronger and closer from

    the BTS, the passive inter-modulation interference will be lower with the smaller power as the

    attenuation of the RF path insertion loss, so the priority of the jumpers near the BTS will be

    higher.

  • Page 2,total 4

    The method of alternative contrast can be used to confirm the RF path properly or not,

    Replace the certain segment RF path with the low PIM load and do the PIM testing (MML:

    STRRFTEST).

    There will be PIM interference with part 2 when PIM test result is no PIM as the example diagram

    below:

    Or there will be PIM interference with part1 as the example diagram below:

    Low PIM load

    1 2