Upload
lamanh
View
221
Download
4
Embed Size (px)
Citation preview
Enhancing nuclear safety
Safety analysis methodology for the EPR
Institute for Radiation protection and Nuclear Safety
December 13th, 2011
IAEA Workshop on CONSTRUCTION TECHNOLOGIES FOR NUCLEAR POWER
PLANTS: A COMPREHENSIVE APPROACH
K. HERVIOU, C. PIEDAGNEL, F. TARALLO
2/31
1. Context
2. General approach for assessing the Flamanville 3 NPP design
3. Examples of application
Content
EPR safety assessment methodology – IRSN – AIEA workshop
3/31
1. Context
2. General approach for assessing the Flamanville 3 NPP design
3. Examples of application
Content
EPR safety assessment methodology – IRSN – AIEA workshop
4/31
1. Context: generalities
Flamanville 3 is the first EPR built in France
There was no construction of NPP in France for more than 10 years –partial loss of the experience gained in the 70’s and 80’s
New construction technologies for nuclear power plant are now available and the EPR should take benefit of this possibility to enhance the robustness of the plant – but these technologies should be qualified
New design, innovative solutions are proposed by vendors and operators codes and standards of construction should be adapted
Existing reactors experience feedback shows the importance of the compliance of the plant with safety requirements from the commissioning phase
It is essential to carefully follow up the construction of the EPR, the manufacturing of its components to assess its safety
EPR safety assessment methodology – IRSN – AIEA workshop
5/31
1. Context: EPR general safety approach
The EPR general safety approach was defined in 1993 by the French and German standing groups of experts (GPR in France and RSK in Germany) on the basis of proposals provided by the French (IRSN) and German (GRS) TSOs.
Need for a significant improvement of the safety level of future plants at the design stage, compared to the safety level of existing plants
Choice of an evolutionary approach, taking into account:
the large operating experience on PWR plants, notably on the French and German ones,
the results of in-depth studies performed on these plants, in particular the probabilistic safety assessments,
the results of research and development activities, notably on severe accidents
Innovative features to be considered
The assessment of the safety approach by the standing groups of experts led to the definition of the Technical Guidelines for GEN III reactors to be build in France and Germany in 2000 (available in English on www.asn.fr)
EPR safety assessment methodology – IRSN – AIEA workshop
6/31
Technical assessment of safety options and of the preliminary safety analysis report
Authorization creation Decree delivered by the government in April 2007
Technical assessment for the commissioning license (“anticipated assessment”)
Assessment of the detailed design
Operating rules
Control of the realization
Participation to the inspection program set up by ASN
Assessment of constructive non-compliance and of corrective actions
1. Context : IRSN involvement in EPR assessment
EPR safety assessment methodology – IRSN – AIEA workshop
7/31
An assessment program has been defined in 2007 with two main objectives:
Give more time for technical assessment by IRSN experts (ASN has one year after the operating license application to give its advice)
Limit the industrial risk for EDF
Priorities based on:
Feedback of operating plants
Innovative features
Checking that safety provisions are compliant with safety objectives and technical guidelines
The objective of IRSN is to gain a good level of confidence in EPR safety provisions before the commissioning phase.
1. Context : on-going assessment
EPR safety assessment methodology – IRSN – AIEA workshop
8/31
1. Context
2. General approach for assessing the Flamanville 3 NPP design
3. Examples of application
Content
EPR safety assessment methodology – IRSN – AIEA workshop
9/31
2. General approach for assessing the FA 3 NPP design
Before the commissioning of the reactor, IRSN will have to assess the safety level of the reactor as built and give an advice to the nuclear safety authority. He must ensure the achievement of a level of safety performance and compliance with the requirements set design.
For this, the IRSN will continue the analysis of the detailed design, while ensuring the quality of implementation.
IRSN defined a global strategy for assessing the EPR, not only based on the safety documentation provided to support the license application.
EPR safety assessment methodology – IRSN – AIEA workshop
10/31
Flamanville 3
Detailed design
+ operating principles
EDF files assessment
Control of the construction
Inspections
Checking compliance to SAR
hypotheses
Follow-up of the
commissioning tests
Balance/effective improvement in
terms of safety and radiation
protection
Particular follow-up of
first operating years
Safety requirements (2000)
2. General approach for assessing the FA 3 NPP design
Design assumptions and features are confirmed only if they are correctly implemented and maintained in the plant.
EPR safety assessment methodology – IRSN – AIEA workshop
11/31
Detailed design
+ operating principles
EDF files assessment
Control of the construction
Inspections
Checking of the conformity of the
plant to the SAR hypotheses
Follow-up of the
commissioning tests
Balance/effective improvement in
terms of safety and radiation
protection
Particular follow-up of
first operating years
Safety requirements (2000)
30 IRSN engineers
1 resident expert
on-site during testing
24 inspections on site
per year + 8 in
engineering services
or providers –
participation of IRSN
experts is a priority
2. Organization
Engineers in charge of the technical assessment of a topic are defining inspection program and support ASN during inspection related to this topic. They assess non-compliance and corrective actions
EPR safety assessment methodology – IRSN – AIEA workshop
12/31
Accident studies
I&C
Protection system
Internal, external hazards
Detailed design of EPR systems playing a safety role including supporting systems (including risk of sump clogging, electrical supply, ventilation…)
Equipment qualification to accidental conditions
Radiological consequences
Severe accident management (including practical elimination)
Probabilistic studies (levels 1, 2, for the reactor, the fuel pool, regarding internal events, internal and external hazards…)
Radiation protection
Commissioning tests
General Operating rules…
2. Main issues to tackle before the operating license delivery
Attempt to have a global view, by safety function
EPR safety assessment methodology – IRSN – AIEA workshop
13/31
2. Background for assessing operators files
Periodic Safety Reviews
Experience feedback and incident analysis
R&D (severe accident, fuel, human factors, civil works…)
International projects and cooperation (Belene, MDEP, WENRA, IAEA, ITER…)
PSA studies
EPR simulator
Independent calculation chain for neutronics and thermal hydraulic calculations
EPR safety assessment methodology – IRSN – AIEA workshop
14/31
Example: use of the HEMERA chain for independent verification analysis
Neutronics (CHRONOS) and
thermal-hydraulics (FLICA) Affected loop
Control rod stuck
CATHARE: System
description
EPR safety assessment methodology – IRSN – AIEA workshop
15/31
Comparison MTC 3D – HEMERA (IRSN model)
0
0,5
1
1,5
2
2,5
0 50 100 150 200 250 300 350 400
Temps (s)
Puis
sance (%
Pn)
Puissance MTC3D
Puissance HEMERA
0
2
4
6
8
10
12
14
16
0 50 100 150 200 250 300
Temps (s)
RF
TC
RF T C M T C3D
RF T C HE M E RA
Nuclear power DNBR min (at assembly scale - without
penalties)
HEMERA
HEMERA
MTC 3DMTC 3D
2A – SLB with primary pumps shutdown
EPR safety assessment methodology – IRSN – AIEA workshop
16/31
2. IRSN working methodology
Files submitted by operator
Preliminary analysis
• Definition of the objectives of the assessment and main issues• Identification of necessary competence skills needed• Definition of the contribution of the different divisions• Deadlines• Identification of needed complementary documents
Discussion with the ASNon the advice to be provided
by the IRSN and deadlines
Technical exchanges withthe operator (questionnaires,
meetings)
Transmission of the detailed assessment report to the
operator to check there is no IRSN misunderstanding
Transmission of the advice to the ASN.
Depending on the subject, possible input for the inspection program
EPR safety assessment methodology – IRSN – AIEA workshop
17/31
1. Context
2. General approach for assessing the Flamanville 3 NPP design
3. Example of application : civil engineering works
Content
EPR safety assessment methodology – IRSN – AIEA workshop
18/31
Definition of safety functions and requirements associated to SSC: principle
Confinement function
Civil engineering works(safety functions, requirements…)
Protection against external hazards
Protection against internal hazards
Systems (safety functions, requirements…)
Other functions (residual heat removal…)
EPR safety assessment methodology – IRSN – AIEA workshop
19/31
The confinement function aims to:
Avoid the release of radioactive products into the environment (external confinement)
Avoid the release of radioactive products within the installation (internal confinement), in particular to maintain acceptable radiological conditions for workers in normal and accidental situations
In case of release, filter and monitor the release
The assessment of the confinement function includes:
Civil engineering works (structures, static confinement)
Systems participating to the function (HVAC, containment isolation, internal containment release rate monitoring system, penetration leaks collecting system, systems constituting some extension of the 3rd barrier, Containment Heat Removal System…)
3. The confinement function
EPR safety assessment methodology – IRSN – AIEA workshop
20/31
Safety functions
Identification of safety requirements
applied to civil engineeringList of main components of civil
engineering
Behavioral requirements in relation
to each civil engineering component
List of civil engineering components
regarded as sensible or typical
INSPECTIONS
Civil design safety assessment
3. Civil engineering works
EPR safety assessment methodology – IRSN – AIEA workshop
21/31
Civil engineering safety functions:
• ensure containment (in particular a 3rd barrier), in all circumstances, including for serious accidents;
• withstand internal hazards (operational accidents, flooding, fire, explosion...);
• withstand external hazards (floods, earthquakes, plane crash, explosion, extreme weather conditions...).
Civil engineering safety requirements:
• leak-tightness and retention
• resistance, stability, supporting capacity for safety equipments and systems
• choice of materials and determination of their biologic thickness
• controllability and durability of the construction during the time designated for operation of the unit
3. Civil engineering works
Civil design safety assessment
EPR safety assessment methodology – IRSN – AIEA workshop
22/31
Behaviour requirements are defined for each structure or part of structure.
IRSN assessment consists in evaluating:
• ETC-C: Technical Code for Civil works in which are defined design criteria and construction rules
• global models, calculations and results in terms of consistency with assumptions and existence of margins, according to ETC-C
• robustness of design and demonstrations by carrying out a more detailed assessment
Results of IRSN civil design safety assessment:
• Design studies were globally satisfactory
• Demands to EDF to provide additional justifications, sometimes involving significant modifications
• Definition of items whose construction should be inspected: Importance for safety,
Execution difficulties.
Civil design safety assessment
3.1 Civil engineering works
Impact ?
EPR safety assessment methodology – IRSN – AIEA workshop
23/31
Detailed assessment of a selection of safety-related structures
Nuclear island basemat,
Reactor building: steel liner, inner prestressed containment, outer containment (airplane shell), internal structures, pool,
Fuel building: internal structures, pool,
Safeguard auxiliary building,
Pumping station.
EPR safety assessment methodology – IRSN – AIEA workshop
24/31
1. Objective: check, by sample survey, the practical implementation of the provisions that enable the structures to guarantee the safety functions assigned to them.
2. Take into account:
IRSN’s experience from earlier EDF plant series and other construction work, feedback from non-nuclear industry
STUK feedback on the monitoring of the construction of the Finnish EPR reactor
Lessons learned form previous inspections
The irreversible nature of the construction work or the impossibility of inspections on the construction site
3. Inspection program on civil engineering works
Help determining the quality of the construction of the facility
EPR safety assessment methodology – IRSN – AIEA workshop
25/31
Combining the main safety functions with the cross-functional aspects (support of equipment, durability and ageing) of which feedback is an essential element, aspects for inspection are identified as follows:
The main behavioral requirements are related to safety functions that the structures make possible to fulfill,
For each major building, construction elements requiring special attention as regards behavioral requirements assigned to them are identified,
Cross-checking of these indications with the phasing of the construction.
3. Inspection program on civil engineering works
Provisional list of inspections of elements of the construction of civil engineering deemed sensitive or representative of the construction process.
EPR safety assessment methodology – IRSN – AIEA workshop
26/31
Examples of technical problems highlighted during inspections:• Water excess in structural concrete,• Lack of reinforcement in the nuclear island basemat,• Cracks in the concrete of the reactor basemat,• Welding process of the containment steel liner,• Difficulties in anchor plates placing,• Unsatisfactory location of prestressing ducts.
3.1 On-site inspections on civil works: examples of findings
Significant deviations from their specified locations for several horizontal prestressing ducts, in the first concrete layer
Final control partially carried out
Location deviations higher than stated tolerances
Reduce the inner containment resistance
Reduce its capacity to ensure the safety function required
EDF actions: - demonstration of acceptability of those deviations- corrective actions for next concrete layers, to obtain
deviations lower than stated tolerances
EPR safety assessment methodology – IRSN – AIEA workshop
27/31
Basemat/IS link
Internal structures (IS)
Access for materials
External containment
Inner containment
Turning crane support bracket
Airlock
Section
over
buttress
Gusset
APC shell dome
Transfer tube
FB
SAB
-BL
2&3
Reactor
pits
Ash panIRWST
FB roof APC shell
FB basemat
Top of SG
bunker
Pool
Pre-stressing tunnel under basemat
IS basemat RB basemat
Dome
belt
Welding process of the containment steel liner
Steel liner ensures leaktightness
of the containment
EPR safety assessment methodology – IRSN – AIEA workshop
28/31
3. Welding process of the containment steel liner
Inspection in September 2008
Detailed attention to the first welding activity carried out on site on an element endorsing a safety function: the liner manufacturing
IRSN Technical assessment
• Deviations to technical requirements detected on the welding procedure perform complementary examination tests and a 100% non destructive vacuum tests over all those welds;
• Perfectible conditions of welding (climatic conditions protection…);
• Non-compliance in documentations;
• Abnormally high rates of repairs for easily weldable steel welding activity not completely controlled
100% volumetric non-destructive tests until return to a normal situation.
Manufacturer actions
• Action plan to significantly improve the quality of works:
Optimization of welding procedures
Improvement of their conditions of implementation
Complementary training sessions and selections of welders
EPR safety assessment methodology – IRSN – AIEA workshop
29/31
3. Cracks in the concrete of the reactor building basemat
December 2007: concreting for the
first time of common basemat on
nuclear island under the reactor
building
(4225 m3, thickness 1.8 m)
Several days later: open cracks of 1
mm to 3 mm
After cooling: open cracks of 0.4 mm
to 1 mm
Repair: injection of cracks
Configuration of cracks in the
circular basemat
EPR safety assessment methodology – IRSN – AIEA workshop
30/31
3. Cracks in the concrete of the reactor building basemat
Cause of the non-compliance:
• thermical effect due to the heat of hydratation of the cement
during concrete setting (expansion and contraction due to exothermic
reaction)
Aggravating circumstance:
• lack of reinforcement mesh in the upper part of the lift
Risk:
• reduced durability of the structure;
• possible corrosion of the bottom reinforcement even if cracks are
grouted;
• presence of water below the basemat should be detected during
the lifetime of the plant.
EPR safety assessment methodology – IRSN – AIEA workshop
Thank you for your attention
www.irsn.fr