Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
11
New PMP Temporal Distributions New PMP Temporal Distributions and a Simplified Breach Method and a Simplified Breach Method
for Dams in Texasfor Dams in Texas
US Society of DamsUS Society of DamsApril 29, 2008April 29, 2008
John Rutledge – Freese and Nichols Warren Samuelson – TCEQ
22
New GuidelinesNew Guidelines in Texasin TexasDeveloping Design Floods Developing Design Floods and Performing Breach and Performing Breach AnalysesAnalysesHydrologic and Hydraulic Hydrologic and Hydraulic Guidelines for Dams in Guidelines for Dams in TexasTexasWebsite for downloading Website for downloading Guidelines listed in paperGuidelines listed in paper
33
Design Flood Design Flood GuidelinesGuidelinesThings that are Different:Things that are Different:–– PMP Temporal DistributionPMP Temporal Distribution–– PMP Critical DurationPMP Critical Duration–– Simplified Breach MethodSimplified Breach Method
Each will be different under Each will be different under Federal guidelinesFederal guidelines
44
Design Flood GuidelinesDesign Flood Guidelines
Things that are Things that are NotNotDifferent:Different:–– PMP Totals (HMRPMP Totals (HMR––51)51)–– PMP Spatial Distribution PMP Spatial Distribution
(HMR(HMR--52)52)–– Runoff MethodologiesRunoff Methodologies–– Routing MethodologiesRouting Methodologies
55
Background on Temporal Background on Temporal DistributionDistribution
““Critically stackedCritically stacked”” distribution assumes distribution assumes that the PMP 1 hr, 2hr, that the PMP 1 hr, 2hr, …… all occur in the all occur in the same event as the 72 hr.same event as the 72 hr.Extreme rainfall events follow one of two Extreme rainfall events follow one of two patterns:patterns:–– Short highly intense eventShort highly intense event–– Long, steady, heavy rainfall eventLong, steady, heavy rainfall event
Research shows that these two distinct Research shows that these two distinct hydrologic patterns do not happen in the hydrologic patterns do not happen in the same event same event Records show most near PMP events are Records show most near PMP events are front end loadedfront end loaded–– The closer to the PMP, the more likely to be front The closer to the PMP, the more likely to be front
end loadedend loaded
66
Design Flood PrecipitationDesign Flood Precipitation
Design Flood based on PMP Design Flood based on PMP –– PMFPMF–– Percentages based on full PMFPercentages based on full PMF
Avoid critically stacked PMP amountsAvoid critically stacked PMP amounts–– Still use HMR 51 & 52 for totals and Still use HMR 51 & 52 for totals and
spatial distributionspatial distribution–– Different temporal distribution, based on Different temporal distribution, based on
durationduration
Critical Duration for PMPCritical Duration for PMP–– 1, 2, 3, 6, 12, 24, 48, 72 hr1, 2, 3, 6, 12, 24, 48, 72 hr
77
Temporal Distributions
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
% of Total Time
% o
f Tot
al R
ainf
all
1 hr2 hr3 hr6 hr12 hr24 hr48 to 72 hr
88
Temporal DistributionTemporal Distribution
Curves do not Curves do not represent an represent an ““envelopeenvelope”” approach, but are approach, but are reasonably reasonably conservative conservative estimates of the estimates of the temporal temporal distribution that distribution that would be expected would be expected for each specific for each specific durationduration
99
Synthetic Rainfall Distributions Used for PMF Development
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
% of Total Time
% o
f Tot
al R
ainf
all
HMR52NRCS 5-PointNRCS Type IINRCS Fig 2-4, TR60Texas PMP
1010
3-hour Actual
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
% of Total Time
% o
f Tot
al R
ainf
all
Proposed
D'Hannis (103)
North Palm Beach (99)
1111
6-hour Actual
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
% of Total Time
% o
f Tot
al R
ainf
all
Proposed
Elbert Actual (102)
North Palm Beach (97)
Simpson, KY - (71)
Smethport Actual (81)
1212
24-hour Actual
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
% of Total Time
% o
f Tot
al R
ainf
all
Proposed
Alvin Actual (91)
Thrall - (86)
Vic Pierce - (73)
Yankeetown, FL - (82)
1313
48 to 72-Hour Actual
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
% of Total Time
% o
f Tot
al R
ainf
al
Proposed
Alvin Actual (87)
Yankeetown, FL - 48 Hr (83)
Yankeetown, FL - 72 Hr (81)
1414
Temporal DistributionTemporal DistributionCAUTIONCAUTION–– Do NotDo Not Compare old 24 hr or old 72 hr Compare old 24 hr or old 72 hr
with new 24 hr or 72 hr.with new 24 hr or 72 hr.Particularly for small drainage areasParticularly for small drainage areas
–– DoDo compare old PMF level with new compare old PMF level with new PMF level using the critical durationPMF level using the critical duration
New distributions must use critical New distributions must use critical durationdurationSingle duration for all sizes must use Single duration for all sizes must use critically stacked distributioncritically stacked distribution
–– Inflow rates may be significantly less, Inflow rates may be significantly less, while runoff volumes should be similar.while runoff volumes should be similar.
DamDam Drainage Drainage AreaArea((smsm))
Old Peak Old Peak InflowInflow
(1,000 cfs)(1,000 cfs)
New Peak New Peak InflowInflow
(1,000 cfs)(1,000 cfs)
Change Change in Peak in Peak Elev.Elev.(ft)(ft)
Change Change in in
DurationDuration(Hr)(Hr)
LowerLowerBois Bois dd’’ArcArc
328328 464464 242242 (2.2)(2.2) 72/7272/72
Lake Lake HoustonHouston
2,8602,860 615615 582582 (0.5)(0.5) 72/7272/72
Lake Lake CleburneCleburne
100100 220220 196196 (3.0)(3.0) 72/2472/24
DamDam Drainage Drainage AreaArea((smsm))
Old Peak Old Peak InflowInflow
(1,000 cfs)(1,000 cfs)
New Peak New Peak InflowInflow
(1,000 cfs)(1,000 cfs)
Change Change in Peak in Peak Elev.Elev.(ft)(ft)
Change Change in in
DurationDuration(Hr)(Hr)
Brushy Brushy CreekCreekSite 6Site 6
5.95.9 4141 2424 (2.2)(2.2) 24/1224/12
Brushy Brushy CreekCreekSite 12Site 12
3.43.4 3232 1414 (1.5)(1.5) 24/1224/12
Brushy Brushy CreekCreekSite 1Site 1
5.05.0 4343 2121 (1.9)(1.9) 24/1224/12
Lake Lake TawakoniTawakoni
756756 374374 365365 (0.5)(0.5) 72/7272/72
1717
Construction Cost SavingsConstruction Cost Savings
DamDam Cost SavingsCost Savings
Brushy creek Brushy creek Dams (3)Dams (3)
$1,200,000$1,200,000
Lower Bois dLower Bois d’’ArcArc $2,000,000$2,000,000
Lake CleburneLake Cleburne $1,000,000$1,000,000
1818
Applicability to Other AreasApplicability to Other Areas
Rainfall examples primarily from area Rainfall examples primarily from area covered by HMR51 and HMR52covered by HMR51 and HMR52–– Mostly gulf statesMostly gulf states
Temporal distribution concept should Temporal distribution concept should apply over same areaapply over same area
1919
Breach AnalysesBreach Analyses
Breach Analyses performed Breach Analyses performed for:for:–– Hazard ClassificationsHazard Classifications–– Inundation maps for EAPsInundation maps for EAPs
Two types:Two types:–– Full Breach analysisFull Breach analysis–– Simplified breach analysisSimplified breach analysis
2020
Simplified Breach MethodSimplified Breach Method
Small and intermediate size dams onlySmall and intermediate size dams onlyQbQb = 3.1 * B * H^3/2, where= 3.1 * B * H^3/2, where–– QbQb = peak total discharge from the breach, = peak total discharge from the breach,
in cfs.in cfs.–– B = bottom width of breach (ft) [3*H]B = bottom width of breach (ft) [3*H]–– H = maximum height of the dam (ft) [H/3]H = maximum height of the dam (ft) [H/3]
Qt = Qt = QbQb + Qs, where + Qs, where –– Qs = peak discharge capacity from the Qs = peak discharge capacity from the
spillway(sspillway(s) with the reservoir at the top of ) with the reservoir at the top of the dam, in cfs the dam, in cfs
2121
Simplified Breach MethodSimplified Breach Method
Length (Lu) = 0.012 * Ks*SQRT(2*C * H)Length (Lu) = 0.012 * Ks*SQRT(2*C * H)–– Lu = Inundation length (miles)Lu = Inundation length (miles)–– C = capacity at top of dam (acC = capacity at top of dam (ac--ft)ft)–– H = Maximum Height of damH = Maximum Height of dam
Ks= Ks= QbQb / Qs/ Qs [0.5 < Ks < 2.0][0.5 < Ks < 2.0]Interpolate flows from Qt at the dam to Interpolate flows from Qt at the dam to Qs at Lu.Qs at Lu.Determine Stage by normal flow or Determine Stage by normal flow or steady state backwatersteady state backwater–– Increase n values by 25%Increase n values by 25%
2222
Simplified Breach MethodSimplified Breach Method
Empirical Equation based on best fitEmpirical Equation based on best fitBased only on dams in TexasBased only on dams in TexasExamples: Examples: –– Lake Weatherford (Intermediate Size)Lake Weatherford (Intermediate Size)
H= 54 ft; C = 49,000 H= 54 ft; C = 49,000 afafDrainage Area = 108 Drainage Area = 108 smsm
–– Daniel Lake Dam (Small Size)Daniel Lake Dam (Small Size)H= 16 ft; C = 465 H= 16 ft; C = 465 afafDrainage Area = 5.0 Drainage Area = 5.0 smsm
23230 20000 40000 60000 80000 100000 120000
650
700
750
800
850
900
950
Lake Weatherford Simplified Breach Plan: 1) PMFBR2 1/22/2007 2) SimPMFmaxW 1/22/2007
Main Channel Distance (ft)
Elev
atio
n (ft
)
Legend
WS Max WS - PMFBR2
WS PF 1 - SimPMFmaxW
Ground
Pilot Channel
ClearFork Lower ClearFork Upper
2424
2525
Inundation Mapping for EAPsInundation Mapping for EAPs
Simplified Breach AnalysisSimplified Breach Analysis–– Pick sufficient points to map, orPick sufficient points to map, or–– Show limits at all downstream structures Show limits at all downstream structures
within inundation lengthwithin inundation length–– Can do steady state backwater, if desiredCan do steady state backwater, if desired–– Procedure does not allow for time to flood Procedure does not allow for time to flood
estimatesestimates
2626
Applicability to Other AreasApplicability to Other Areas
Simplified Procedure should apply Simplified Procedure should apply almost anywherealmost anywhereExamples all from Texas, so equation Examples all from Texas, so equation for Inundation length would have to for Inundation length would have to be derived for new areas. Should be be derived for new areas. Should be similar for similar topography.similar for similar topography.
2727
Questions?Questions?